Channel deposit quantity calculation method and hydraulic debris flow mechanism forecasting method

By calculating the amount of accumulation and hydrological simulation at the channel unit scale, combined with the two-phase fluid density formula, the problem of basin-scale application and boundary control in hydraulic debris flow forecasting is solved, achieving high-precision hydraulic debris flow forecasting and improving the accuracy of the forecast. Accuracy and reliability.

CN118747484APending Publication Date: 2024-10-08INST OF MOUNTAIN HAZARDS & ENVIRONMENT CHINESE ACADEMY OF SCI +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410752305.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-12
Publication Date
2024-10-08

Smart Images

  • Figure CN118747484A_ABST
    Figure CN118747484A_ABST
Patent Text Reader

Abstract

The invention discloses a hydraulic debris flow forecasting method, which comprises the following steps: S1, taking a channel unit as an environment carrier of a debris flow channel, calculating simulation calculation in all channels in a channel unit environment, constructing a deposit quantity model of a channel unit scale to clarify the deposit quantity in the channel unit at a specific position, and calculating the deposit quantity in the channel unit; a reasonable boundary control condition is provided for a calculation model of the deposit, the development of debris flow mechanism forecast to accurate forecast is facilitated, and the blank of a deposit quantity calculation model capable of quantitatively calculating in a channel section (channel unit) scale is filled; and S2, forecasting debris flow according to the density of the water-soil-rock mixture after water-soil coupling. The waterpower debris flow mechanism forecasting method based on the watershed scale is established, the application problem of a'point scale 'mechanism model on the watershed scale is solved, the blank of the waterpower debris flow mechanism forecasting method based on the watershed scale is filled up, and the precision of the waterpower debris flow mechanism forecasting method based on the watershed scale is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of debris flow prediction, which belongs to the technical field of debris flow disaster prevention and control, and in particular to a basin-scale hydraulic debris flow prediction method under channel unit material intake and discharge conditions. Background Art

[0002] The three necessary conditions for the development of debris flow include excitation conditions (precipitation, runoff), energy conditions (topography) and material conditions (material sources). The material supply channels involved in the formation of debris flow originate from slopes or ditches, so the debris flow ditches in nature are divided into two types: geodynamic and hydraulic. The present invention focuses on the prediction model of hydraulic debris flow.

[0003] There are many models for determining the mechanism of hydraulic debris flow initiation. According to the medium assumptions, they can be divided into continuous medium model, discrete medium model and mixed medium model (solid phase is discrete and liquid phase is continuous). However, they all involve: the instability mechanism and initiation mode of mud, sand or soil and rock bodies (layered instability initiation or gradual initiation of particles) and their relationship with water flow intensity; the influence of water flow intensity and source material composition (particle grading, fine particle content, mud viscosity, etc.) on the transformation of sand-containing water flow into debris flow. For example, Takahashi established a critical formula for hydraulic debris flow initiation based on mechanical equilibrium analysis by using the externally applied shear stress and the internal friction stress of the deposit to calculate the depth of the deposit required for initiation. (Only the channel deposit with thickness a is activated) (The deposits in the channel at this location are all activated); the critical Shields stress formula for the initiation of hydraulic debris flow established by Shields based on the critical initiation stress Wang Zhaoyin and Zhang Xinyu considered the water flow energy and established the hydraulic debris flow starting mechanism judgment formula rqJ≥K based on the flume test results. c ; Sгепанов determined the formula for determining the first critical angle α1 of two critical starting modes of hydraulic debris flow Based on the momentum conservation theorem and the Sгепанов formula, Wei Fangqiang et al. obtained the critical flow expression for the critical flow condition of hydraulic debris flow initiation. Lamb established the critical stress expression of the ditch bed mud and sand based on Shields stress formula and force analysis. Le Maohua and Han Qiwei improved the previous initiation model based on mechanical balance and established a mechanical-stochastic model for the initiation mode of gully erosion from three aspects: single particle initiation (based on the theory of bed layer mud-sand exchange), particle mixing movement (calculating the probability of particle movement transfer and the probability of particle state based on random statistical probability), and debris flow formation (sediment transport rate under corresponding hydraulic conditions, and then judging whether debris flow is formed based on sediment concentration).

[0004] For the channel breach initiation mode, a dominant channel initiation model based on the dominant flow theory and the safety factor method in slope stability analysis was established. Berti considered the surface water flow, groundwater flow, and infiltration water flow, and based on the motion wave equation Calculate the flow rate in the channel to determine whether a debris flow has occurred; Gregoretti, Fontana, Tognacca et al. established a dimensionless flow hydraulic debris flow initiation discrimination model based on single-width flow, median particle size, channel slope and density. Shu Anping et al. established a dimensionless shear stress model for determining the initiation of hydraulic debris flow by considering the particle Reynolds number and shear stress. * ), τ=γRJ; Prancevic et al. established an image of discriminating debris flow initiation between dimensionless shear stress and channel slope based on Lamb's 2008 research, and constructed a dimensionless shear stress τ * ~θ relationship; the Chinese Academy of Sciences and the Chengdu Mountain Hazards and Environment Research Institute of the Ministry of Water Resources proposed a critical flow formula for the start-up judgment of hydraulic debris flows based on single-width flow in the book "China Debris Flows" These initiation models all focus on analyzing the stability of a certain point (hereinafter referred to as point scale) on the basin surface scale (hereinafter referred to as the surface scale) under the action of runoff. However, the initiation and formation process of debris flow is a scientific problem on the surface scale. The prediction model constructed for the point scale cannot evaluate the initiation of debris flow in the entire basin. Therefore, for the prediction of hydraulic debris flow in the entire basin, it is necessary to construct a physical prediction model of hydraulic debris flow in the basin. At present, no method for predicting the mechanism of hydraulic debris flow in the entire basin has been reported.

[0005] The present invention aims to construct a physical prediction model for hydraulic debris flows at the basin scale, and has made breakthroughs in the following key issues: (1) Establishing a prediction unit with relatively uniform terrain and hydraulic conditions to provide a reasonable simulation scenario for many point-scale mechanism judgment models. This content has been solved in the invention patent "A method for extracting debris flow prediction units (application number: 202311750646.7)"; (2) The channel unit's capacity to accommodate material sources solves the material source replenishment required for the formation of hydraulic debris flows and provides a reasonable boundary constraint condition for the calculation model of the starting amount of deposits; (3) Developing a rainfall-induced channel flood evolution model to solve the hydrodynamic conditions required for the formation of hydraulic debris flows; (4) The water-soil integration and judgment indicators of hydraulic debris flows at the "line scale" of the channel complete the application of the "point scale" mechanism model at the basin scale, and realize the basin-scale hydraulic debris flow mechanism prediction.

[0006] The present invention fills the industry gap in the model for calculating the amount of deposits at the scale of a specific channel section (channel unit) and provides a reasonable boundary constraint condition for the starting mechanism model when calculating the starting amount of deposits. At the same time, it solves the application problem of the "point scale" mechanism model at the watershed scale, and overcomes the key scientific problem of hydraulic debris flow mechanism prediction at the watershed scale. These are the two problems currently faced by the hydraulic debris flow mechanism prediction method. Summary of the invention

[0007] To solve the above problems, the present invention aims to provide a hydraulic debris flow prediction method, which takes the channel unit as the environmental carrier of the debris flow channel, and all simulation calculations in the channel are calculated under the channel unit environment. The sediment model at the channel unit scale is constructed as the calculation model of the starting sediment to provide scientific boundary control conditions, and the runoff hydrological model is selected for hydrological simulation. Secondly, based on the channel sediment starting amount at the channel unit scale and the total volume of surface runoff of the channel unit simulated by the hydrological model, the density formula of the two-phase fluid water-soil-rock mixture after water-soil coupling is constructed, and the density of the two-phase fluid at the sediment fan position reaching the debris flow channel basin from the upstream branches and the main ditch is calculated. The forecast is made according to the density grade of the hydraulic debris flow, and a basin-scale hydraulic debris flow prediction method is established to improve the debris flow prediction accuracy. A channel sediment volume calculation method at the channel unit scale is also provided.

[0008] The present invention is achieved through the following technical solutions:

[0009] A method for calculating the amount of channel deposits at a channel unit scale comprises the following steps: 1) obtaining relevant parameters required for modeling multiple channel sections: average width b, longitudinal slope gradient J, average depth d, and surface area A0 of channel deposits in the channel section; extracting the catchment area A of different channel sections based on DEM data of debris flow basin; extracting lithology data within the catchment area based on the catchment area A, and obtaining the denudation index w of rock and soil based on the lithology data; 2) obtaining the amount Q of deposits in multiple channel sections S , Q s =d*A0, based on Q S Obtain the amount of channel deposits per unit channel length V Q : 3) Constructing multiple channels can characterize the inflow and outflow of sediments into and out of the channel unit and reflect the comprehensive index of the channel unit's ability to accommodate sediments: the channel unit source throughput and accommodation index 4) Based on the obtained data of multiple channels, the channel unit source throughput and accommodation index and b derived from the analysis based on the principles of analytic geometry 2 As the independent variable, V QAs the dependent variable, the multiple linear regression method is used to establish the model relationship between the three:

[0010] The total amount of channel deposits is a potential proof of the large-scale debris flow in a channel, and is also an important basis for evaluating the risk and hazard of debris flow in a channel in advance. At present, the research on calculating the amount of channel deposits is still at the level of vague and rough estimation of the total amount of channel deposits. There is no more accurate method recognized in the field to calculate the total amount of channel deposits. At the same time, there is no report on the calculation model of the amount of deposits above the bedrock of the channel section (channel unit) at a specific location. The determination of the amount of deposits at the channel unit scale above the bedrock at a specific location is crucial for the prediction of hydraulic debris flow mechanism. It is related to the upper limit of the maximum initiation amount of deposits at a specific location, that is, to clarify the storage amount of deposits in the channel unit before initiation and the maximum upper limit of deposits that are activated when calculating in the channel unit using the initiation mechanism model. This is one of the important conditions for the accurate prediction of debris flow prediction methods based on the initiation mechanism. At the same time, the amount of deposits contained in each channel unit can also clarify the impact characteristics of debris flow. Therefore, it is necessary to reconstruct the existing channel deposit calculation model to obtain the channel unit scale deposit calculation model, so as to calculate the deposit volume in the channel unit, so that it can be applied to the calculation and analysis of the debris flow initiation mechanism model, and serve the hydraulic debris flow mechanism prediction method, so as to improve the prediction accuracy and reduce the false alarm rate and missed alarm rate. The deposit volume in all channel units obtained by superposition can more accurately obtain the total amount of deposits in the channel, and the total amount of channel deposits obtained in this way is more accurate.

[0011] Specifically, S1-1, conduct field surveys, use handheld GPS to locate the channel section (select the channel section with relatively uniform channel topography and channel cross-section morphology), use infrared rangefinder to measure the average width b and longitudinal slope gradient J of the sediment in the channel section (measure the distance of more than 10 points along the flow direction of the channel section, and calculate the value of the channel section gradient J through data processing), use geological radar to measure the average depth d of the channel sediment in the channel section and multiply it by the measured surface area A0 of the sediment in the channel section to obtain the volume of the sediment in the channel section, that is, the amount of sediment in the channel section Q s , use Q s Divide by the channel length L to get the channel deposit volume per unit channel length, that is, the channel deposit volume per unit channel length V Q :

[0012] Q s =d*A0

[0013]

[0014] S1-2, based on the 12.5 m DEM data of the debris flow gully basin, ArcGIS software was used to extract the catchment area A of different channel sections (channel units);

[0015] S1-3, using 1:500,000 lithology data, extract the lithology data within the catchment area according to the catchment area A extracted in S1-2, interpret the rock type and the corresponding rock hardness and rock weathering resistance from the attribute table of the obtained lithology data (you can query the reference table of rock hardness and rock weathering resistance, and assign values ​​from small to large according to the rock hardness and weathering resistance corresponding to the rock type, 1, 2, 3... At the same time, give area weight coefficients to different types of rock combinations), and obtain the erosion index w of the rock and soil body from the final rock hardness and rock weathering resistance values;

[0016] S1-4. Through the above steps (S1-1) to (S1-3), a total of 35 sections of 17 debris flow channels (channel units) corresponding to the channel sections where the modeling is located are obtained;

[0017] S1-5, through the rock and soil erosion index w, channel width b, catchment area square root The channel unit source throughput and accommodation index can be constructed by combining the channel section gradient J to characterize the inflow and outflow of sediments into and out of the channel unit and reflect the channel unit's ability to accommodate sediments.

[0018] S1-6, get 35 groups With b 2 Data as independent variables and 35 groups of V Q The data is used as the dependent variable (to prevent the denominator from being 0, J is added with 0.005. This operation is found in many literatures, and 0.005 is also added to prevent the slope J value from being 0). First, the independence and correlation analysis between the independent variables is tested, and then the correlation analysis between the independent variables and the dependent variables is performed. The Durbin-Watson DW value is 1.564, which is close to 2. In this field, it is generally required that 1.5<DW<2.5 indicates that the independent variables are independent of each other; VIF value (variance inflation factor ) is 1.610, which is much smaller than 5. In this field, it is believed that if VIF < 10, there is no serious multicollinearity between the independent variables, and if VIF < 5, there is no multicollinearity between the independent variables, indicating that there is no correlation caused by multicollinearity between the independent variables; at the same time, the constant term and the two independent variables have no significant effect on the dependent variable V Q The significant sig value (or p value) between them is "sig<0.001" less than 0.05. Generally, when the sig value or p value is less than 0.05, it is considered that the corresponding independent variable has a significant impact on the dependent variable, indicating that the independent variable and the constant term meet the significance level for describing the dependent variable. The above results all meet the requirements for building the model;

[0019] S1-7. Use the multivariate linear regression method to establish the channel accumulation amount per unit channel length calculation formula V Q :

[0020]

[0021] Model overall R 2 =0.9122, indicating that the model can explain the amount of channel deposits per unit channel length V Q 91.22%, the effect is better and meets the requirements; V Q is the amount of deposit per unit channel length in the flow direction of a channel unit, in m 3 / m; b is the average width of the channel deposit surface in a channel unit, in m; A is the catchment area corresponding to a channel unit, in km 2 ; J is the longitudinal slope gradient of the channel unit, w is the rock and soil erosion index in the catchment area above a channel unit location;

[0022] S1-8. Obtain the channel deposit amount Q of the channel unit scale s Computational model:

[0023] Q s =V Q *L

[0024] Q s is the amount of deposits in a channel unit, in m 3 , L is the length of a channel unit in the flow direction, in meters; S1-9, first calculate the V obtained in S1-7 Q The computational model was self-validated within 35 sets of data, and the average error rate was 17.559%. The leave-one-out cross-validation method was used to validate V Q The model was verified for universality (each time using 34 different sets of data to establish V according to the previous method). Q The model was validated with a different set of data, and the validation was performed 35 times. The average error rate was 19.3%, indicating that The model is reliable and meets the requirements for universal promotion and application.

[0025] S1-10: Directly use the results obtained in S1-7 in actual promotion and application Model and S1-8 get Q s =V Q *L models are combined to calculate the channel accumulation amount Q at the channel unit scale s , it is only necessary to determine the channel unit source throughput capacity index w, A, b and J (all achievable through ArcGIS software), as well as the channel unit length L (all achievable through ArcGIS software), without having to repeat the field survey work;

[0026] S1-11. Supplement to S1-10: Method for determining b using DEM data: Extract the river network data of the debris flow ditch using ArcGIS software, convert each grid of the debris flow ditch river network data into point data, and then connect the point data into river network central axis data, that is, obtain the channel central axis data. Using the DEM data of the central axis data as a reference, search for points on both sides of the channel that are greater than 2m from the DEM value on the central axis along the direction perpendicular to the channel central axis, connect the two points on the left and right sides of the central axis, and obtain the straight line distance, which is the channel deposit width b. i , and then solve the average width b of the deposits in the channel unit; the method of determining J using DEM data: using ArcGIS software, obtain slope data, superimpose river network data, determine the slope at the river network location in ArcGIS and convert it into a gradient J i , and then solve the average value J of the gradient of the inner river network of the channel unit; the method for obtaining w is the same as S1-3; the method for obtaining A is the same as S1-2. Here, the methods for determining w, A, b, J and L in S1-10 and S1-11 can be automatically obtained and realized by MATLAB and Python programming.

[0027] For hydraulic debris flow mechanism prediction methods, improving forecast accuracy and universality while reducing missed reporting rate and false alarm rate have always been the goals pursued in the field. The main link to achieve this goal is to provide a reasonable calculation simulation scenario for the starting mechanism model in the mechanism prediction method, that is, the channel unit proposed in the invention patent "A method for extracting debris flow prediction units (application number: 202311750646.7)". Therefore, clarifying the amount of deposits in the channel unit is more essential for hydraulic debris flow mechanism prediction than roughly estimating the total amount of deposits in the entire channel. Physical significance and application significance, which is the direction for the development of hydraulic debris flow mechanism prediction towards accurate prediction. The object affected by the hydrodynamic force of the water flow in the macro channel is the deposits in the macro channel section (channel unit) at a specific location. However, the current channel deposit volume calculation model cannot calculate the deposit volume at the channel unit scale. This is a problem faced by the channel deposit volume calculation model. At the same time, there is a lack of boundary control conditions in the calculation process of the starting deposit volume. When the deposits at a certain channel unit position have been started and there is no margin, the start-up calculation is still carried out blindly, resulting in a problem of too large calculated starting amount of deposits. This is also one of the main reasons that affect the forecast accuracy and result in a large underreporting and false alarm rate.

[0028] The channel unit provenance throughput and accommodation index, which is first proposed in this section, solves the problem of determining the amount of sediment at the channel unit scale based on the principle of mass conservation. It starts from the inflow conditions that affect the sediment flow to a certain channel unit and the outflow conditions of the channel unit, while considering the channel unit's own ability to accommodate sediment. Finally, we determine the actual sediment storage capacity that is actually retained at the channel unit location, and use this as one of the important indexes for constructing a sediment volume calculation model at the channel unit scale above bedrock, named the channel unit provenance throughput and accommodation index. This index comprehensively reflects the objective storage capacity of sediments in a channel unit from the perspective of mass conservation based on the inflow, outflow and accommodation of material sources in a specific channel unit. It is a comprehensive index with strict physical meaning that can reflect the storage capacity of sediments in a channel unit. During a loose sediment transport process or during the transport and accumulation of loose sediments over many years, it satisfies the mass conservation of sediments in the channel unit above the bedrock: Q in =Q out +Q s ,but Then there is Show Q in ∝Q s ;at the same time but Q in A certain time Comprehensive Q in ∝Q s and Knowable in accordance with The relationship shows that the inflow of material source Q in and the outflow of material source Q out The ratio is proportional to the amount of deposits Q retained in the channel unit. s , and the amount of deposits Q retained in the channel unit s The size of Q is also related to the capacity of the channel unit itself. According to the reservoir capacity principle, Q s The size of is related to the three-dimensional geometric size of the channel unit. Therefore, when constructing the accumulation model, the present invention comprehensively considers the factors that affect the inflow and outflow of the basin source and the capacity of the channel unit. in =f1(wA) is a function related to the catchment area A and the corresponding rock and soil erosion index w (the larger wA is, the greater the ability to provide material sources flowing into the channel unit). Because the formation of mud, sand and rocks in the channel unit is inseparable from the geological conditions, the geological conditions w must be considered. Secondly, the ability of material sources to flow into the channel unit and the ability to provide material sources are also related to the size of the catchment area A above the channel unit location; and the outflowing material source amount Q outIt is related to the runoff shear stress τ. Since the runoff shear stress τ=ρgh(sinθ)=ρghJ, the outflow source Q can be considered out =f2(J) is a function related to the gradient J (the larger the J, the easier it is for the source to be washed out, resulting in less ability for the channel unit to retain sediment); and the channel unit's own ability to accommodate sediment per unit channel length is related to the average width b of the channel unit (the width b of the channel unit is like the storage capacity of a reservoir, the larger the b, the greater the ability to accommodate sediment). The amount of existing sediment in the channel unit is the final result of the inflow, outflow and accommodation of the basin where the channel unit is located for many years, so the channel unit source throughput and accommodation index is constructed as represents the ability to provide material sources and flow material sources into the channel unit and transform into channel deposits, J represents the ability of material sources to flow out of the channel unit and consume channel deposits, and b represents the ability of the channel unit to eventually accommodate deposits. The conditions that meet the initial mass conservation principle At the same time On this basis, the channel unit's own capacity is taken into account (based on the mechanism of reservoir capacity principle), so The larger the value, the more deposits there are in the channel unit at that position, which is the theoretical basis for proposing this index. At the same time, the present invention discovers for the first time that the deposits per unit channel length V in the channel unit Q The square of the average width of the channel unit b 2 Positive correlation V Q ∝b 2 :The geometric relationship between the cross-sectional direction and the vertical direction of the channel unit accumulation volume is obtained through geometric modeling: (α≠90°, α≠0°, bedrock not exposed section, assume that the cross section of the channel unit is a trapezoidal section, where b is the average width of the surface of the channel unit deposit, is the upper base of the trapezoid, c is the width of the bedrock below the deposit, is the lower base of the trapezoid, α is the slope of the two side slopes, that is, the supplementary angle between the lower base of the trapezoid and the waist angle, and the slope of the bedrock surface and the horizontal plane is β). Since the bedrock width c and bedrock slope β below the deposit are difficult to determine, they can be determined by V can be clearly determined Q ∝b 2 ; At the same time, the geometric relationship between the longitudinal section direction and the vertical direction of the channel unit accumulation volume is constructed as follows: However, β, c, and l are difficult to determine, but it is also possible to determine (where l is a certain special length of the deposit surface, this l and the actual vertical depth d of the deposit form a right triangle, the longitudinal slope of the channel deposit is θ, and the meanings of the other parameters are the same as before). Since the horizontal and vertical geometric modeling is carried out for the vertical direction of the same position, we have: Then there exists (b 2-c 2 ).2(cosβ) 2 =(bl*sinθ+cl*sinθ).4cotα, from this formula we can know that bl=f(b 2 ) where bl is a function of the width squared b. If the relationship holds, then we have The relationship is established. Combining the horizontal and vertical relationships of the channel deposits, it can be known that V Q ∝b 2 Since the above content is constructed strictly according to the principles of analytic geometry, V Q Calculation formula, so b 2 For V Q It is very important to do b 2 and V Q The correlation analysis shows that the two are highly correlated, so b 2 is another important index that should be considered.

[0029] From the above analysis, we can know that the channel unit source throughput capacity index can be combined and the square of the average width of the channel unit b 2 Build The model is used to obtain a semi-theoretical statistical model for calculating the amount of accumulation at the channel unit scale, which has physical significance. and Q s =V Q *L. This new and effective channel unit scale sediment volume calculation model can not only accurately calculate the sediment volume above the bedrock at a channel section (channel unit) but also calculate the total sediment volume of the debris flow channel by superimposing the sediment volume of all channel units in the channel, overcoming the problem that the previous calculation model roughly estimated the total amount of channel sediment but could not calculate the sediment volume in a specific channel section. At the same time, it provides a scientific boundary restriction condition V for starting the sediment volume calculation model. s i ≤Q s i This avoids the problem of blindly performing start-up calculations when the deposits at a certain channel unit position have been started and there is no margin, resulting in a larger calculated start-up amount of the deposits.

[0030] In the past, the rock and soil erosion index w was obtained by using an arithmetic mean value w0 of the entire basin or region instead, which is a non-weighted average value w. It also does not consider the differences in rock and soil properties between different positions in the same debris flow ditch, which will lead to certain errors. Therefore, in order to calculate the w value more accurately, the present invention proposes that the rock and soil erosion index w value should be calculated according to the following formula:

[0031]

[0032]

[0033]

[0034]

[0035] is the average hardness of the i-type rock combination in the catchment area A, is the hardness of each rock in the i-type rock combination (the hardness of each rock in each debris flow ditch in the study area is ranked from small to large: 1, 2...n), A i is the area of ​​rock combination type i, is the average weathering resistance of rock combination type i in catchment area A, is the weathering resistance of each rock in the i-type rock combination (the weathering resistance of each rock in each debris flow gully in the study area is ranked from small to large: 1, 2…n), w i is the erosion index of rock combination type i, w is the overall rock erosion index in the area with catchment area A corresponding to the location of the channel unit, is the area A of rock combination type i i The area proportion weight of the catchment area A corresponding to the location of the channel unit (there may be m types of rock combinations in an area with a catchment area of ​​A, because the lithology data presents the rock types and weathering degrees in each different area, and different areas correspond to different types of rock combinations). A hydraulic debris flow mechanism prediction method includes the following steps:

[0036] S'1. Simulate the whole process of channel flood evolution induced by rainfall, and design the corresponding hydrological model of channel flood evolution: slope infiltration runoff process model → slope confluence process model → channel confluence process model. The infiltration runoff process simulation and slope confluence process simulation use grid units as calculation units. All simulation processes in the channel use the divided channel units as calculation units. The surface runoff V in each channel unit is obtained by simulation and calculation based on the hydrological model. 1-2 i , then the V of all channel units is calculated by superposition. 1-2 i The total amount of channel runoff V2 is obtained, that is, the hydrological model that simulates the entire process of channel flood evolution induced by rainfall is designed and selected, and the channel unit runoff and the total amount of channel runoff are calculated:

[0037] In the study of the evolution model of rainfall-induced channel flood, the present invention firstly carries out the water volume design process of rainfall P to obtain the rainfall intensity i; secondly, the slope infiltration runoff hydrological model is determined; then the channel confluence hydrological model is selected; and finally, the hydrological simulation of the channel unit scale during the fluid evolution process is carried out. Before simulating the specific hydrological process, two conditions are assumed:

[0038] Assumption 1. After the loose deposits in the debris flow channel are started, it is assumed that the started deposits can at least flow out to the end of the flow area (the starting end of the accumulation fan) as the channel runoff increases, and the amount of channel deposits will gradually decrease after each start; Assumption 2. It is assumed that the soil layer of the loose deposits in the started channel is a water-saturated soil and rock body (the purpose is to set the boundary of the hydrological simulation to facilitate the simulation of the hydrological process). The calculation principles of the hydrological process simulation are set as follows:

[0039] A. The time step is 1 hour;

[0040] B. The spatial distance step of the channel is calculated based on the size of the channel unit, and the spatial distance step of the slope is calculated based on the size of the higher resolution grid unit;

[0041] C. According to the catchment area threshold, the runoff is determined for each grid whose area is less than or equal to the threshold grid number on the slope. The number of catchment area grids of the simulated slope is required to be 0≤N≤threshold grid number. The runoff generation and runoff confluence of all types of grids with the threshold grid number on the slope are calculated (grids with an ACC value of 0 only calculate runoff generation without considering runoff, and grids with other ACC values ​​must consider both runoff generation and runoff confluence. Grid types are divided according to ACC values, such as all grids with an ACC value of 1 are one type, and those with an ACC value of 2 are another type). Use ArcGIS software to mark all grid positions on the slope as 0, and the channel position as 1 (this value is different from the ACC value, the purpose is to mark the position and distinguish the slope from the channel).

[0042] D. Calculate the runoff based on the ACC data obtained by processing DEM data with ArcGIS software, and its principle is based on the D8 algorithm; E. Calculate the runoff or runoff depth of the channel unit based on the calculation results of the evolution of slope runoff and channel runoff, and introduce it into the debris flow initiation mechanism model as an input parameter;

[0043] F. Simultaneously simulate the total amount of surface runoff generated every hour until it moves to the entire channel of the accumulation fan.

[0044] (1) Design of computing units in hydrological process simulation:

[0045] The present invention adopts a combination of channel units and grid units as calculation units for the entire debris flow ditch basin. The infiltration runoff and slope runoff of the entire basin are both calculated using grid units, while the channel unit is used as the calculation unit when calculating the channel runoff evolution in the channel.

[0046] (2) Calculation of previous rainfall:

[0047] Using the formula Directly superimpose and calculate the effective precipitation of the 15 consecutive days before the forecast day as the effective previous rainfall on the day of debris flow forecast. a In the calculation formula, R t is the rainfall on day t; a t is the rainfall attenuation coefficient, a t =0.84 t / T ; T is the rainfall half-life, generally T = 1 day.

[0048] (3) Selection of hydrological model for runoff generation in debris flow gully basins and calculation of runoff generation

[0049] Richard's differential equation of moisture movement was selected due to its strong universality, clearer physical meaning and higher accuracy of calculation results. This equation is used to describe the vertical movement of soil moisture in the unsaturated layer, that is, the differential equation that describes the change of soil moisture content with time and space after rainfall infiltrates into the soil.

[0050] 1) Obtain the simulated slope infiltration flow rate of the grid unit;

[0051] Infiltration process and its control conditions:

[0052] Infiltration boundary control equation Richards differential equation In the formula, θ is the soil moisture content; is the soil-hydraulic diffusion coefficient; z is the soil depth, with the soil surface as the origin and positive along the soil depth; K(θ) is the hydraulic conductivity; I(t) is the rainfall intensity at time t.

[0053] Use the Van Genuchten model to determine the infiltration boundary governing equation K(θ) in , the model formula is as follows:

[0054]

[0055] but Where S e is the soil saturation degree, k0 is the saturated hydraulic conductivity of the topsoil, θ s is the saturated water content of soil, θ r is the residual moisture content of soil, θ tis the soil moisture content at the current moment t, K(θ) is the hydraulic conductivity, ψ is the matrix suction of the unsaturated soil. The matrix suction in the unsaturated soil is the main external force driving the water movement, which can be expressed by Calculate, α, n, m are the parameters of water and soil characteristic curve,

[0056] 2) Runoff control conditions and calculation of surface runoff:

[0057] Based on the super-seepage flow mechanism in Horton's flow theory When surface runoff is generated, and I(t)≤f pt All precipitation is infiltrated and no surface runoff is generated, where I(t) is the rainfall intensity at time t, f pt is the infiltration capacity at time t, q is the amount of water that has infiltrated into the soil, E is the evaporation (generally negligible in the debris flow field), and D is the water deficit in the soil vadose zone. The surface runoff R of grid i at time t is calculated by the following formula t i:

[0058] At time t, I(t)>f pt Surface runoff R t i, at this time

[0059] I(t)i=q t (θ,z)i+R t i, then R t i=I(t)iq t (θ, z)i, input the calculation parameters of Richards differential equation and VanGenuchten model, and calculate the soil moisture content θ(z,t) of each grid in the basin at that time i , according to the θ(z,t) of each grid i θ(z,t) at adjacent moments i The change determines the infiltration volume q at time t t (θ, z)i, then the surface flow of the corresponding grid is calculated based on R t i=I(t)iq t (θ, z)i is calculated.

[0060] (4) Obtain the slope runoff of the grid unit;

[0061] The confluence process is mainly divided into two aspects: one is to determine the flow rate or runoff depth of the confluence at a certain section of the channel, that is, to determine the confluence flow; the other is to determine the confluence time when the confluence reaches a certain section of the channel. The specific determination method is as follows:

[0062] Under the over-seepage runoff mechanism, surface runoff is generated in each grid in the study area. The runoff in the grid will flow to the nearby grids according to the flow direction and topography, or will not flow out and continue to accumulate and infiltrate into the soil, and finally flow into the ditch along their respective flow routes to become ditch runoff. The migration and replenishment process of how the surface runoff generated by the runoff is gathered into the ditch to form the ditch runoff, the process of momentum energy change during movement, and the movement time are the processes to be described in the simulation of the confluence hydrological model. When the slope converges, the surface runoff R that converges into each grid t (x, t) will change with time and space position, then:

[0063]

[0064]

[0065]

[0066]

[0067] Where Q is the propagation flow of the slope motion wave, i.e., the slope runoff, A is the cross-sectional area of ​​the water flow, t is the time, c is the velocity of the motion wave, x is the distance along the flow direction, H is the water level (equal to the sum of the riverbed elevation z and the propagation flow depth h0), a is the grid side length, and h is the net water depth after deducting the depression water storage (h = R t i-z0), R t i is the runoff depth of a grid under a certain rainfall intensity at time t, z0 is the depth of water intercepted by surface vegetation, The ACC result is obtained based on the D8 algorithm of GIS. There are m surrounding grids, each corresponding to the net water depth R S The superposition sum of (i, t)-z0. From formula (3)

[0068] (4)(5)(6) Calculate the flow rate Q of each grid i (x, t) (i.e., approximate calculation of Q by finite difference) and the confluence water level H i (x, t) corresponds to the confluence depth h0(x, t) (i.e. h0), and the confluence time is also determined.

[0069] (5) Obtain the runoff of a channel unit after the channel unit division

[0070] The runoff Q of each grid on the slope is calculated by step S'1 "(4), calculate the slope runoff" i (x, t) results, and based on the D8 algorithm of GIS, determine the specific flow of the slope grid propagation that flows into the channel. The calculation method is as follows:

[0071] The flow rate at the position of channel j is:

[0072] Flow rate at channel j:

[0073]

[0074]

[0075] J is the ditch bottom gradient, n is the Manning roughness coefficient, b is the ditch width, R is the hydraulic radius, n is the Manning roughness coefficient, h is the ditch runoff depth, m is the slope coefficient, V j is the flow rate at channel j, is the groove n at the position of the groove j

[0076] is the surface runoff of a grid, and a is the grid size.

[0077] According to formula (8), the runoff V1 of the upstream starting end section of a channel unit (length L, average width b) can also determine the runoff V2 of the downstream ending end section of the channel unit. Then the runoff of the channel unit is According to formula (7)(8)(9)(10), the channel runoff depth h is calculated by trial and error. Then, the runoff depth h1 of the upstream starting section and the runoff volume h2 of the downstream ending section of a channel unit can be obtained. The runoff depth of the channel unit is:

[0078] (6) Obtain the total surface runoff V in the channel w :

[0079] After the channel unit division, all channels in the debris flow channel basin have been divided into a number of channel units of a certain number. The surface runoff V of each channel unit calculated in step (5) is 1-2 i The total amount of surface runoff V in the channel is obtained by superposition calculation w , the total amount of surface runoff in the channel V w The calculation method is as follows:

[0080]

[0081] S'2. Debris flow prediction is carried out based on the density of the two-phase fluid water-soil-rock mixture after water-soil coupling:

[0082] Determine the boundaries, time steps and spatial distance steps of each calculation model, input the parameters required for the calculation of the accumulation model at the channel unit scale and the parameters required for the hydrological process simulation calculation into the MATLAB and Fortran program algorithms to calculate the accumulation amount and runoff depth in each corresponding channel unit during this period, and input the calculated accumulation amount in the channel unit during this period, runoff depth data and other parameters required by the hydraulic debris flow initiation mechanism model into the program algorithm of the initiation mechanism model to realize the calculation of the initiation amount of accumulation in each corresponding channel unit during this period. The initiation amount of deposits and runoff of each corresponding channel unit in this period are iterated from the upstream channel of the debris flow ditch basin to the downstream accumulation fan for the channel "line scale" to obtain the total initiation amount of deposits and the total runoff of all channels (all channel units) in the basin during this period. At this time, the average density of the two-phase fluid water-soil-rock mixture formed at the accumulation fan of the basin outlet of the entire debris flow ditch is calculated. After the water-soil coupling of the initiated deposits and the runoff, a two-phase fluid water-soil-rock mixture with a certain density will be formed. As the overall density of the mixture increases, the possibility (probability) of the sand-containing water flow gradually transforming into a debris flow increases. Compared with sand-containing water flow and landslide, the characteristic physical quantity of debris flow is density. Therefore, the density level is divided according to the density interval of hydraulic debris flow to judge the density of the two-phase fluid mixture formed in this period at the accumulation fan. The density interval is then used to judge the possibility of forming a hydraulic debris flow, that is, the probability of the occurrence of a hydraulic debris flow is judged by the density level of the hydraulic debris flow to make a red, orange, yellow and blue forecast. All channels in the basin are transformed through channel units, and all slopes are transformed according to grid units. The "point scale" mechanism models are transformed to the basin scale based on the channel units of all channels and the grid units of the slopes, solving the problem of mismatch when the "point scale" mechanism model is applied at the basin scale, and realizing the hydraulic debris flow mechanism prediction at the basin scale. Within a calculation time step, the amount of deposits above the bedrock in the channel unit is reduced each time it is started. If the amount of deposits in a channel unit at the start of the calculation is V s0 , and the amount of deposits above the bedrock in the channel unit was Q s0 If , then the upper boundary condition for calculating the starting amount of the channel unit accumulation next time (next time step) will be Q s0 -V s0 , the overall constraint is V s i ≤Q s i .

[0083] Obtain the total volume V of the channel deposits activated by hydrodynamics s, and then find the density ρ of the two-phase fluid water-soil-rock mixture, and make a debris flow forecast based on the density of the two-phase fluid water-soil-rock mixture and debris flow warning table 1;

[0084] Specifically, the starting mechanism model by Takahashi: Combined with (5) in step S'1, the runoff depth of a channel unit i is provided. That is, h in the Takahashi initiation mechanism model, the thickness a0 of the channel deposit in the channel unit is obtained, and the initiation volume V of the deposit at the position of the channel unit i is obtained. s i , V s i =a0 i *b i *L i , channel unit accumulation starting amount V s i The boundary constraint is the amount of deposit Q above the channel unit bedrock calculated in claim 1 s ,Right now

[0085] V s i ≤Q s i

[0086] The total volume of all channel unit deposits V s The calculation method is as follows:

[0087]

[0088] Where θ is the longitudinal slope of the channel deposits, is the internal friction angle of the deposit, C * is the particle concentration by volume in the static debris bed (particle volume concentration in the static debris layer), σ is the solid particle density, ρ is the density of the fluid, h is the surface runoff depth of the channel unit, a0 is the depth at which the externally applied tangential stress coincides with the internal resistance stress, that is, the depth of the activated deposits, b is the average width of the channel unit, and L is the length of the channel unit;

[0089] In order to complete the calculation, the following calculation parameters need to be provided for the formula, including: θ is obtained by processing DEM data using ArcGIS software (the present invention uses 12.5 m DEM data), According to the relevant literature of Wenchuan, the value is 30°-35°, and the value of this invention is 32.5°. * According to the field survey, the value is 40% (the value in the relevant literature of Wenchuan is 30%-50%), and the value of σ is 2800Kg / m 3 ρ is taken as 1000Kg / m according to the density of clean water3 , where the h channel unit runoff depth parameter is provided by (5) in step S'1, that is, The value of is h here.

[0090] The time step of all calculations in the present invention is 1 hour. The calculation space distance step in the channel is the size of the channel unit, and the calculation space step on the slope is the size of the grid. The density result of a two-phase fluid is calculated every hour.

[0091] Table 1 Hydraulic debris flow warning table

[0092]

[0093] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0094] 1. This new and effective calculation model for the amount of sediment at the channel unit scale can not only accurately calculate the amount of sediment above the bedrock at a certain channel section (channel unit), but also calculate the total amount of sediment in the debris flow channel by superimposing the sediment of all channel units in the channel, overcoming the problem that the previous calculation model roughly estimates the total amount of channel sediment but cannot calculate the sediment in a specific channel section. At the same time, the amount of sediment above the bedrock calculated by this model can provide a scientific boundary restriction condition for the calculation model of the starting sediment amount, avoiding the problem of blindly starting the calculation when the sediment at a certain channel unit position has been started and there is no margin, resulting in the calculated sediment starting amount being too large. This will be beneficial to improving the forecast accuracy of debris flow mechanism forecasting.

[0095] 2. The model for calculating the amount of deposits above the bedrock constructed by the present invention requires fewer parameters, making the model easier to promote and apply. Since the corresponding amount of deposits in the channel unit at a specific location is clarified, the starting mechanism model has a clear starting action object when calculating the starting amount of deposits, and at the same time fills the gap in the channel deposit amount calculation model at the channel section (channel unit) scale, which is conducive to the development of debris flow mechanism prediction methods towards accurate prediction; at the same time, the total amount of deposits in the channel can be obtained more accurately by superimposing the deposit amounts in all channel units, so that the total amount of channel deposits obtained is more accurate; when constructing the channel deposit amount at the channel unit scale, a new channel unit material source throughput and storage index and a deposit width square index are created, which can effectively reflect the deposit inflow and outflow conditions of the actual channel unit (channel section) and the channel unit's own ability to accommodate deposits, so that the deposit amount calculation at the channel unit scale is more accurate.

[0096] The computational model has clearer physical meaning.

[0097] 3. The hydraulic debris flow prediction method provided by the present invention takes the channel unit as the environmental carrier of the debris flow channel, and all simulation calculations in the channel are calculated under the channel unit environment, which provides a suitable application environment for the mechanism model. The sediment volume model at the channel unit scale is constructed as the starting mechanism calculation model of the starting sediment to provide the upper limit boundary control condition of the calculation interval, and the runoff generation and confluence hydrological model is selected for hydrological simulation. Based on the channel sediment starting volume at the channel unit scale and the channel unit surface runoff simulated by the hydrological model, the density formula of the two-phase fluid water-soil-rock mixture after water-soil coupling is used to calculate the density of the two-phase fluid at the sediment fan position reaching the debris flow channel basin from the upstream branches and the main ditch, and the hydraulic debris flow density grade is predicted. A basin-scale hydraulic debris flow mechanism prediction method is established, which solves the application problem of the "point scale" mechanism model at the basin scale, fills the gap in the research of basin-scale hydraulic debris flow mechanism prediction method, and improves the accuracy of hydraulic debris flow prediction. BRIEF DESCRIPTION OF THE DRAWINGS

[0098] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings:

[0099] Figure 1 This is the distribution map of the river network and DEM superposition results of the Yeniugou debris flow gully;

[0100] Figure 2 V is the amount of sediment per unit channel length of each channel unit above the bedrock of the Yeniugou channel Q Result distribution diagram (L0 is the distance from the end of the accumulation fan);

[0101] Figure 3 Q is the amount of sediment in each channel unit above the bedrock of Yeniugou channel s Result distribution diagram (L0 is the distance from the end of the accumulation fan);

[0102] Figure 4 This is the forecast result of hydraulic debris flow mechanism in Yeniugou Basin; DETAILED DESCRIPTION

[0103] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.

[0104] Example 1

[0105] Channel unit accumulation volume Q s calculate

[0106] A debris flow gully in Wenchuan County, Sichuan Province, China. Here we select the Yeniugou debris flow gully basin as the research object, because through our field investigation we confirmed that Yeniugou is a hydraulic debris flow gully, which is consistent with the results of Zhang Changchun's "Characteristics of debris flow disasters in Yeniugou, Wenchuan County and analysis of river blocking hazards" and Mao Shuo's "Formation mechanism and river blocking analysis of debris flow in Yeniugou, Minjiang River", which believe that Yeniugou is a hydraulic debris flow gully (ditch bed-initiated debris flow gully or runoff-initiated debris flow gully). Therefore, it is reliable to choose Yeniugou as the research basin.

[0107] According to the following steps, the w, A, b, J and L parameters of each channel unit in the basin are extracted. The final result is as follows Figure 1-Figure 3 (1) Determination of the catchment area A corresponding to the channel unit

[0108] According to the invention patent "A method for extracting debris flow prediction units (application number: 202311750646.7)", the Fr threshold is adjusted to obtain the number of channel units to be 409. Through the locations of the 409 channel units, ArcGIS software is used, using DEM data with an accuracy of 12.5m. The depressions are first filled, and then the flow direction analysis is performed, and then the number of confluence grids is calculated. In this way, the catchment area value A of the 409 channel unit locations in Ye Niugou is obtained.

[0109] (2) Determination of rock and soil erosion index w:

[0110] The tif data layers of the 409 catchment areas A obtained in (1) were used to intercept the 1:500,000 lithology shp data in ArcGIS software to obtain 409 lithology data. The rock hardness data and rock weathering resistance data were obtained from the lithology data, and the 409 w values ​​were obtained by combining the calculation formula of the rock and soil erosion index w.

[0111] (3) Determination of the average width b of the channel deposits at the channel unit position

[0112] Using ArcGIS software, the river network data of the Yeniugou debris flow gully (such as Figure 1 ) is first converted into point data, and then the point data is connected and converted into river network central axis data, that is, the channel central axis data is obtained. Based on the DEM data of this central axis data, search for points with a value greater than +2m on the DEM on the central axis along the direction perpendicular to the channel central axis to both sides of the channel (determine a point on the left side of the reference point on the central axis, and a point on the right side. The straight line formed by the points determined on the left and right sides is perpendicular to the central axis, the straight line formed by the reference point and the point on the left is perpendicular to the central axis at this position, and the straight line formed by the point on the right side and the reference point is also perpendicular to the central axis at this position). Connect the two points on the left and right sides of the central axis to obtain the straight line segment distance, and then you can get the channel deposit width b at this position. iThe upper limit of the width of the deposits in the entire channel is set to 165m (based on the actual field survey results). Then the width b of all calculated deposits in each channel unit is i The overall calculation averages the value b, and this technique can be used to determine the value of the average width b of the deposits in each channel unit.

[0113] (4) Longitudinal slope gradient J in the flow direction of the channel unit

[0114] Using the method of step S1-11, using the 12.5-meter DEM data, the slope data is obtained through ArcGIS software, the river network data is superimposed, and the slope at the river network location is determined in ArcGIS and converted into a gradient J i , and then solve the average value J of the gradient of all river network positions in the channel unit.

[0115] (5) Determination of the length L of the channel unit in the flow direction

[0116] This can be achieved through ArcGIS software. Since the 409 channel units have been determined, the distance can be obtained based on the upper and lower positions of the channel unit flow direction, or the distance between two points can be calculated based on the coordinates of the intersection of the upper and lower sides with the central axis of the river network (using the distance formula between two points), which is the L value.

[0117] (6) Deposits per unit channel length V of the channel cell Q Determination

[0118] Substitute the 409 sets of A, w, J, and b parameters obtained from processes (1) to (4) into the following formula:

[0119]

[0120] The accumulation volume V per unit channel length of each of the 409 channel units is obtained. Q ,like Figure 2 The results show that the closer to the debris flow fan, the larger the volume of the deposit per unit channel length V Q The bigger.

[0121] (7) Channel deposit quantity Q at channel unit scale s Determination

[0122] Substituting (5) and (6) we get 409 L and V Q Substituting the parameters into the formula obtained in S1-8, the formula is as follows:

[0123] Q s =V Q *L

[0124] The amount of channel deposits Q currently contained in each of the 409 channel units is obtained.s ,like Figure 3 The results show that the closer to the debris flow fan, the greater the amount of deposits in the channel unit. s The bigger.

[0125] (8) The total amount of sediment in the entire Yeniugou ditch

[0126] 409 Qs in (7) s The numerical superposition is a more accurate total amount of channel deposits, which is 3996350m 3 , which is close to the findings in the literature.

[0127] Example 2

[0128] Calculate the channel unit runoff V 1-2 i and the total channel runoff V w

[0129] On August 20, 2019, a hydraulic debris flow occurred in Yeniugou, Wenchuan County. Therefore, the present invention selects the debris flow ditch basin on that day as the forecast object.

[0130] 1. Calculation of early rainfall in Yeniugou Basin

[0131] The quantitative precipitation estimate (QPE) provided by the China Meteorological Administration is used to calculate the effective rainfall in the basin. The rainfall accuracy is hourly rainfall with a grid accuracy of 5 km*5 km. The formula is used. (Among them, a t =0.84 t / T , T = 1 day, R t That is, the superposition value of QPE data for 24 hours a day) is directly superimposed and calculated to predict that the effective precipitation for 15 consecutive days before the forecast day is 20.9 mm, and this result is used as the previous precipitation of all channel units and grid units in Yeniugou.

[0132] 2. Calculate the flow rate of the Yeniugou debris flow basin

[0133] 1) The previous effective rainfall of 20.9 mm in (1) is taken as the total rainfall of 20.9 mm in one hour, that is, the rainfall from 23:00 to 24:00 on August 19, 2019 is assumed to be 20.9 mm, and the initial soil moisture content (residual moisture content θ r ) is 0, that is, in the formula I(t) is considered to be 20.9 mm / h, and The residual water content θ r 0, used to calculate the current water content θ at 24:00 on August 19, 2019 tThat is, the residual water content θ at 0:00 on August 20, 2019 r , I(t) = 20.49 mm / h and θ r = 0 is substituted into the Richards differential equation and the Van Genuchten model to calculate the current water content θ of each grid in the Yeniugou Basin at 24:00 on August 19, 2019 t (Residual water content θ at 0:00 on August 20, 2019 r ), that is, the initial soil moisture content at the beginning of the forecast day is determined. The calculation is realized by using the finite difference method (forward difference format) through Fortran programming.

[0134] 2) After determining the initial soil moisture content (soil residual moisture content), the quantitative forecast precipitation (QPF) provided by the China Meteorological Administration was used to characterize the induced rainfall level on August 20, 2019, and to calculate the hydrological process of the Yeniugou. The rainfall accuracy was hourly rainfall with a grid accuracy of 5 km*5 km, that is, the value of I(t) in the hourly calculation was the corresponding hourly QPF data in real time. The Richards differential equation, Van Genuchten model and formula R were used. t i=I(t)iq t (θ, z)i, when time t, satisfies I(t)>f pt Surface runoff R t i, calculate the hourly flow R of each grid in the Yeniugou Basin t i. The calculations were performed using the finite difference method (forward difference scheme) using Fortran programming.

[0135] 3. Calculate the drainage volume of the Yeniugou debris flow ditch and determine the channel runoff V w

[0136] 1) Calculate the slope flow Q i (x,t)

[0137] We decided to use the finite difference approximation to the wave equation of motion to calculate Q i (x, t) (explicit solution in backward linear difference format) was calculated using Fortran programming, using the formula and The flow rate Q of each slope grid is obtained i (x,t), where The ACC result is obtained based on the D8 algorithm of GIS. There are m surrounding grids, each corresponding to the net water depth R S The superposition sum of (i,t)-z0, z0 takes the value of 15mm.

[0138] 2) Calculate the channel unit sink V1-2 i

[0139] according to and Combined with the runoff V1 of the upstream starting end section of a channel unit (length L, average width b), and the runoff V2 of the downstream ending end section, the runoff of the channel unit is The runoff V of all 409 channel units 1-2 i Such calculations are performed, where the flow rate entering the channel The specific flow rates of the slope grids that flow into the channel are determined by the D8 algorithm of GIS, and the calculation is realized by Fortran programming. Enter the calculated corresponding Q i (x,t) and R t i. According to the invention patent "A method for extracting debris flow prediction units (application number: 202311750646.7)", the values ​​of b, m, J, and Manning coefficient n in this part are 0.096, and a is 12.5 (the resolution of the DEM image is 12.5 meters). The channel runoff depth h is calculated by trial and error, and the calculation is realized by MATLAB programming. Then the runoff depth h1 of the upstream starting end section of a channel unit and the runoff volume h2 of the downstream ending end section can be obtained. The runoff depth of the channel unit is The runoff depth h of all 409 channel units 1-2 i Such calculations are performed.

[0140] 3) Calculate the total surface runoff V in the channel w

[0141] The V of all channel cells obtained in 2) 1-2 i Result Input The formula gives V w , the results are as follows Figure 4 The results presented in are also the calculation results in Table 2. Debris flow prediction is carried out according to the density of the two-phase fluid water-soil-rock mixture after water-soil coupling:

[0142] The density calculation formula of two-phase fluid water-soil-rock mixture is: Where ρ is the density of the two-phase fluid water-soil-rock mixture (Kg / m 3 ), ρ w is the density of water (1×10 3 Kg / m 3 ), V w is the total volume of channel surface runoff simulated by the hydrological model (m3 ), ρ s is the density of the soil and rock mass in the channel deposits that have been moved (Kg / m 3 ), here the value is 2.8×10 3 Kg / m 3 , V s is the total volume of channel deposits activated based on calculations (m 3 ); From the density formula of the forecast model, we can know that the current ρ w , s 、V w (available in (3) in this example) have been obtained, and V s It can be predicted by first using Calculate the depth a0 of the deposit to be started, and the corresponding parameter values ​​are: θ is obtained by processing DEM data with ArcGIS software (the present invention uses 12.5m DEM data), According to the relevant literature of Wenchuan, the value is 30°-35°, and the value of this invention is 32.5°. * According to the field survey, the value is 40% (the value in the relevant literature of Wenchuan is 30%-50%), and the value of σ is 2800Kg / m 3 ρ is taken as 1000Kg / m according to the density of clean water 3 , where the h channel unit runoff depth parameter is provided by (3) in this example, that is, The value of is h here; then use V s i =a0 i *b i *L i Calculate the accumulation starting volume V in each channel unit s i , input the calculated a0, b, L data, wherein the method for obtaining b and L data is as shown in Example 1, the channel unit accumulation starting amount V s i The boundary constraint condition is the amount of deposit Q above the channel unit bedrock calculated in step S1. s The result requires that V s i ≤Q s i In a calculation time step (within 1 hour), the amount of deposits above the bedrock in the channel unit is reduced each time it is started. If the amount of deposits in a channel unit at the time of starting the calculation is V s0 , and the amount of deposits above the bedrock in the channel unit was Q s0 If , then the upper boundary condition for calculating the starting amount of the channel unit accumulation next time (within the next time step of 1 hour) will be Qs0 -V s0 .

[0143] The total volume of all channel unit deposits V s Calculation formula All calculations in this section are implemented using Fortran programming. s The results are as follows Figure 4 As shown and Table 2.

[0144] V s 、V w , w , s Data entry formula Calculate the density ρ of the two-phase fluid mixture per hour. The result is as follows: Figure 4 And as shown in Table 2.

[0145] When ρ is calculated, debris flow forecast can be carried out according to the hydraulic debris flow warning table 1.

[0146] Table 1 Hydraulic debris flow warning table

[0147]

[0148] The forecast results of hydraulic debris flow in Yeniugou are as follows: Figure 4 As shown in Table 2, it can be seen from the chart that the peak density of the two-phase fluid water-soil-rock mixture in Yeniugou on August 20, 2019 is 1.778387×10 3 Kg / m 3 , reaching the density range of hydraulic debris flow, indicating that debris flow has occurred. At the same time, the peak value of the density ρ of the two-phase fluid water-soil-rock mixture is 1.65×10 3 Kg / m 3 <1.778387×10 3 Kg / m 3 ≤1.8×10 3 Kg / m 3 , indicating that the probability of hydraulic debris flow is 80%-100%, and a red warning should be issued; and it can also be known that the density ρ of the two-phase fluid water-soil-rock mixture is 1.2×10 3 Kg / m 3 <ρ≤1.8×10 3 Kg / m 3The results in the interval lasted from about 16h to about 18h, a total of about 3 hours, indicating that the duration of the hydraulic debris flow event was about 3 hours. This is consistent with the actual case of the debris flow disaster in Ye Niu Gou on August 20, 2019, proving that the forecast was successful and accurate, and the red warning level issued was also accurate. Because if the result issued is an orange or yellow warning, it is not very successful, because when the Ye Niu Gou debris flow did occur, and the forecast results of the present invention issued red warnings at 16h and 17h, it shows that the forecast was successful and accurate.

[0149] Table 2 Bison Valley August 20, 2019 V s 、V w ,ρ, hourly rainfall results and forecast results are presented

[0150]

[0151]

[0152]

[0153] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A method for calculating the amount of channel deposits at a channel unit scale, characterized in that: The following steps are involved: 1) Obtain the relevant parameters required for modeling multiple channel sections: the average width b, longitudinal slope gradient J, average depth d, and surface area A0 of channel deposits in the channel section; extract the catchment area A of different channel sections based on the DEM data of the debris flow basin; extract the lithology data within the catchment area based on the catchment area A, and obtain the erosion index w of the rock and soil body based on the lithology data; 2) Obtain the amount of deposits Q of deposits in multiple channel sections S , Q s =d*A0, based on Q S Obtain the amount of channel deposits per unit channel length 3) Constructing multiple channels can characterize the inflow and outflow of sediments into and out of the channel unit and reflect the comprehensive index of the channel unit's ability to accommodate sediments: the channel unit source throughput and accommodation index 4) Based on the obtained data of multiple channels, the channel unit source throughput and accommodation index and b derived from the analysis based on the principles of analytic geometry 2 As the independent variable, V Q As the dependent variable, the multiple linear regression method is used to establish the model relationship between the three:

2. A hydraulic debris flow prediction method, characterized in that: The following steps are involved: S'1. Simulate the whole process of rainfall-induced channel flood evolution and design the hydrological model of basin flood evolution: slope infiltration runoff process model → slope confluence process model → channel confluence process model. The infiltration runoff process model and slope confluence process model use grid units as calculation units, and all channel calculation models use divided channel units as calculation units. The surface runoff V in each channel unit is obtained by simulation and calculation based on the hydrological model. 1-2 i , then the V of all channel units is calculated by superposition. 1-2 i Get the total channel runoff V w , specifically: (1) Obtain the simulated slope infiltration flow rate of the grid unit; 1) Slope infiltration process and its control conditions: Infiltration boundary control equation Richards differential equation In the formula, θ is the soil moisture content; is the soil-hydraulic diffusion coefficient; z is the soil depth, with the soil surface as the origin and positive along the soil depth; K(θ) is the hydraulic conductivity; I(t) is the rainfall intensity at time t; Determining the infiltration boundary governing equation using the Van Genuchten model K(θ) in , the model formula is as follows: but Where S e is the soil saturation degree, k0 is the saturated hydraulic conductivity of the topsoil, θ s is the saturated water content of soil, θ r is the residual moisture content of soil, θ t is the soil moisture content at the current moment t, K(θ) is the hydraulic conductivity, ψ is the matrix suction of the unsaturated soil. The matrix suction in the unsaturated soil is the main external force driving the water movement, which can be expressed by Calculate, α, n, m are the parameters of water and soil characteristic curve, 2) Runoff control conditions and calculation of surface runoff: According to the super-seepage mechanism of Horton's flow theory, I(t)>f pt , When surface runoff is generated, and I(t)≤f pt All precipitation is infiltrated and no surface runoff is generated, where I(t) is the rainfall intensity at time t, f pt is the infiltration capacity at time t, q is the amount of water that has infiltrated into the soil, E is the evaporation (generally negligible in the debris flow field), and D is the water deficit in the soil vadose zone. The surface runoff R of grid i at time t is calculated by the following formula t i: At time t, I(t)>f pt Surface runoff R t i, at this time I(t)i=q t (θ,z)i+R t i, Then R t i=I(t)iq t (θ, z)i, input the calculation parameters of Richards differential equation and Van Genuchten model, and calculate the soil moisture content θ(z, t) of each grid in the basin at that time i , according to the θ(z,t) of each grid i θ(z,t) at adjacent moments i The change determines the infiltration amount q at time t t (θ, z)i, then the surface flow of the corresponding grid is calculated based on R t i=I(t)iq t (θ, z)i is calculated; (2) Obtain the slope runoff of the grid unit; When the slope converges, the surface runoff R that flows into each grid t (x, t) will change with time and space position, then: Where Q is the propagation flow of the slope motion wave, i.e., the slope runoff, A is the cross-sectional area of ​​the water flow, t is the time, c is the velocity of the motion wave, x is the distance along the flow direction, H is the water level, which is equal to the sum of the riverbed elevation z and the propagation flow depth h0, a is the grid side length, h is the net water depth after deducting the water storage in the depression, and h = R t i-z0,R t i is the runoff depth of a grid under a certain rainfall intensity at time t, z0 is the depth of water intercepted by surface vegetation, The ACC result is obtained based on the D8 algorithm of GIS. There are m surrounding grids, each corresponding to the net water depth R S The superposition sum of (i,t)-z0; The flow rate Q of each grid is calculated by formula (3)(4)(5)(6): i (x, t) and the confluence water level H i (x, t) corresponding to the confluence depth h0(x, t) is h0, and the confluence time is determined at the same time; (3) Obtain the runoff of a channel unit after the channel unit division The flow rate Q of each grid on the slope calculated by step (2) i (x, t) results, according to the GIS D8 algorithm to determine the specific slope grid flow into the channel, the calculation method is as follows: The flow rate at the position where it enters the channel j is: Flow rate at channel j: J is the ditch bottom gradient, n is the Manning roughness coefficient, b is the ditch width, R is the hydraulic radius, n is the Manning roughness coefficient, h is the ditch runoff depth, m is the slope coefficient, V j is the flow rate at channel j, is the surface flow production of n grids in the ditch at position j in the ditch, and a is the grid size; According to formula (8), for a channel unit with a length of L and an average width of b, the runoff V1 of the upstream starting end section can also determine the runoff V2 of the downstream ending end section of the channel unit. Then the runoff of the channel unit is According to formula (7)(8)(9)(10), the channel runoff depth h is calculated by trial and error. Then, the runoff depth h1 of the upstream starting section and the runoff volume h2 of the downstream ending section of a channel unit can be obtained. The runoff depth of the channel unit is: (4) Obtain the total surface runoff V in the channel w : After the channel unit division, all channels in the debris flow channel basin have been divided into a number of channel units of a certain number. The surface runoff V of each channel unit calculated in step (3) is 1-2 i The total amount of surface runoff V in the channel is obtained by superposition calculation w , which is calculated as follows: S'2, obtain the total volume V of the channel deposits activated by hydrodynamics s , and then find the density ρ of the two-phase fluid water-soil-rock mixture, and make a debris flow forecast based on the density of the two-phase fluid water-soil-rock mixture and debris flow warning table 1; Specifically, the starting mechanism model by Takahashi: Combined with (3) in step S'1, the runoff depth of a channel unit i is provided That is, h in the Takahashi initiation mechanism model, the thickness a0 of the channel deposit in the channel unit is obtained, and the initiation volume V of the deposit at the position of the channel unit i is obtained. s i , V s i =a0 i *b i *L i , channel unit accumulation starting amount V s i The boundary control condition is the amount of deposit Q above the channel unit bedrock calculated in claim 1 s ,Right now In s i ≤Q s i The total volume of all channel unit deposits V s The calculation method is as follows: Where θ is the longitudinal slope of the channel deposits, is the internal friction angle of the deposit, C * is the volumetric particle concentration in the static debris bed, σ is the solid particle density, ρ is the density of the fluid, h is the surface runoff depth of the channel unit, a0 is the depth at which the externally applied tangential stress coincides with the internal resistance stress, that is, the depth of the activated deposit, b is the average width of the channel unit, and L is the length of the channel unit; The density calculation formula of the two-phase fluid water-soil-rock mixture is as follows: Where ρ is the density of the two-phase fluid water-soil-rock mixture, kg / m 3 , ρ w is the density of water (1×10 3 Kg / m 3 ), V w is the total volume of channel surface runoff simulated by the hydrological model, m 3 ρ s is the density of the soil and rock mass in the channel deposits that have been moved, kg / m 3 , here the value is 2.8×10 3 Kg / m 3 ; V s is the total volume of channel deposits activated according to calculation, m 3 ; When ρ is calculated, debris flow forecast can be carried out according to debris flow warning table 1; Table 1 Hydraulic debris flow warning table 3. The method for predicting hydraulic debris flow according to claim 1, characterized in that: After the loose deposits in the debris flow channel are started, it is assumed that the started deposits can at least flow out to the end of the flow area, that is, the starting end of the accumulation fan, as the channel runoff increases. The amount of channel deposits will gradually decrease after each start.

4. The method for predicting hydraulic debris flow according to claim 1, characterized in that: It is assumed that the loose deposit soil layer of the activated channel is a water-saturated soil and rock mass.

5. The method for predicting hydraulic debris flow according to claim 1, characterized in that: The erosion index w value of the rock and soil mass is also calculated by the following formula: is the average hardness of the i-type rock combination in the catchment area A, is the hardness of each rock in the i-type rock combination (the hardness of each rock in each debris flow ditch in the study area is ranked from small to large: 1, 2...n), A i is the area of ​​rock combination type i, is the average weathering resistance of rock combination type i in catchment area A, is the weathering resistance of each rock in the i-type rock combination (the weathering resistance of each rock in each debris flow gully in the study area is ranked from small to large: 1, 2…n), w i is the erosion index of rock combination type i, w is the overall rock erosion index in the area with catchment area A corresponding to the location of the channel unit, is the area A of rock combination type i i The area proportion weight is A, which is the catchment area corresponding to the location of the channel unit.