Risk assessment method and device, equipment, storage medium and program product
By obtaining and calculating the initial and target time data of risk scenario events and risk elements of the target facility, the problem of time-varying factors not being considered in the existing technology is solved, and the accuracy and timing of risk assessment are improved.
Patent Information
- Application Number
- CN202410741416.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2024-10-08
AI Technical Summary
Existing risk assessment technology fails to effectively consider changes in risk probability caused by time changes, resulting in poor temporal comparability of risk assessment values and a lack of continuity.
By obtaining the initial and target time data information of possible risk scenario events and related risk elements of the target facility, combined with data processing rules, the risk value of each risk scenario event is calculated, and comprehensively evaluated to improve the accuracy and timing of risk assessment. .
By considering the time factor, the accuracy and continuity of the risk assessment results are improved, the risk assessment values are comparable in time series, and the effectiveness of the assessment is enhanced.
Smart Images

Figure CN118747598A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the field of computer technology, and in particular, relates to a risk assessment method, device, equipment, storage medium and program product. Background Art
[0002] Existing risk assessment technology is a qualitative or semi-quantitative analysis conducted according to the processes of risk identification, risk analysis, and risk assessment, and only assesses the current situation of the assessment object.
[0003] Therefore, the existing assessment methods do not pay attention to the regularity of changes in risk probability caused by time changes, so the existing risk assessment values have poor time series comparability. Summary of the invention
[0004] The embodiments of the present application provide a risk assessment method, apparatus, device, storage medium and program product, which can improve the accuracy of risk assessment.
[0005] In a first aspect, an embodiment of the present application provides a risk assessment method, comprising:
[0006] Obtain N risk scenario events of the target facility, wherein the risk scenario event includes multiple risk factors, and N is a positive integer;
[0007] Acquire first data information and data processing rules for each of the risk factors in each of the risk scenario events, wherein the first data information is data information collected by the risk factor at a target time, and the data information is used to indicate the risk of the target facility under the risk factor;
[0008] Determine a first risk value of the risk scenario event based on first data information of multiple risk elements in each of the risk scenario events and a data processing rule, and obtain N first risk values;
[0009] A risk assessment result of the target facility is determined according to the N first risk values.
[0010] In some embodiments, the obtaining of N risk scenario events of the target facility includes:
[0011] Acquire Q risk scenario types of the target facility, wherein each risk scenario type corresponds to an event chain, the event chain includes at least one event chain node, and each event chain node includes at least one risk element;
[0012] Based on the event chain corresponding to each of the risk scenario types and at least one event chain node of the event chain, risk scenario events of each of the risk scenario types are determined to obtain N risk scenario events of the Q risk scenario types, wherein the risk scenario event is composed of a risk element in each event chain node in the event chain corresponding to the risk scenario type to which it belongs.
[0013] In some embodiments, determining the first risk value of the risk scenario event based on the first data information of the plurality of risk elements in each of the risk scenario events and the data processing rules to obtain N first risk values includes:
[0014] Assigning values to the risk elements according to the first data information and data rules of each risk element in each risk scenario event to obtain first data values of multiple risk elements in each risk scenario event;
[0015] Determining preset data information of each of the event chain nodes based on the first data value of the risk factor corresponding to each of the event chain nodes in each of the risk scenario events;
[0016] A first risk value of the risk scenario event is calculated based on preset data information of each event chain node in the risk scenario event.
[0017] In some embodiments, the data processing rule includes a preset time variation function corresponding to the risk factor;
[0018] The step of assigning a value to each risk factor according to the first data information and data processing rules of each risk factor in each risk scenario event to obtain first data values of multiple risk factors in each risk scenario event includes:
[0019] Obtaining a preset time variation function of the risk factor;
[0020] The first data information of the risk factor is assigned a value using the preset time variation function to obtain the first data values of the plurality of risk elements at the target time. In some embodiments, the preset data information includes: the probability, consequence and weight of the event chain node.
[0021] In a second aspect, an embodiment of the present application provides a risk assessment device, comprising:
[0022] A first acquisition module is used to acquire N risk scenario events of a target facility, wherein the risk scenario event includes multiple risk factors, and N is a positive integer;
[0023] A second acquisition module is used to acquire first data information and data processing rules of each risk factor in each risk scenario event, wherein the first data information is data information collected by the risk factor at a target time, and the data information is used to indicate the risk of the target facility under the risk factor;
[0024] A determination module, configured to determine a first risk value of the risk scenario event based on first data information of a plurality of risk elements in each of the risk scenario events and a data processing rule, and obtain N first risk values;
[0025] An assessment module is used to determine a risk assessment result of the target facility according to the N first risk values.
[0026] In a third aspect, an embodiment of the present application provides a risk assessment device, the device comprising: a processor and a memory storing computer program instructions;
[0027] When the processor executes the computer program instructions, the risk assessment method as shown in the first aspect is implemented.
[0028] In a fourth aspect, an embodiment of the present application provides a readable storage medium, on which a program or instruction is stored, and when the program or instruction is executed by a processor, the risk assessment method shown in the first aspect is implemented.
[0029] In a fifth aspect, an embodiment of the present application provides a computer program product. When instructions in the computer program product are executed by a processor of an electronic device, the electronic device executes the risk assessment method shown in the first aspect.
[0030] The risk assessment method, device, equipment, storage medium and program product provided by the embodiments of the present application first obtain the risk scenario events that may occur in the target facility, calculate the first risk value of each risk scenario event based on the data information at the target time of each risk element included in each risk scenario event and the corresponding data processing rules, and then conduct a comprehensive assessment based on the first risk value of each risk scenario event to obtain the risk assessment result of the target facility at the target time. By combining the data at the initial time of the relevant risk elements of the target facility and the data at the target time to assess the risk of the facility, the impact of the time factor on the risk of the facility is taken into account, so that the risk assessment value is comparable in terms of time series, and the accuracy and continuity of the risk assessment results are improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to more clearly illustrate the technical solution of the embodiments of the present application, the following is a brief introduction to the drawings required for use in the embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.
[0032] Figure 1 It is a schematic diagram of the process of the risk assessment method provided in the embodiment of the present application;
[0033] Figure 2 is a schematic diagram of the structure of a risk assessment device provided in an embodiment of the present application;
[0034] Figure 3 It is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0035] The features and exemplary embodiments of various aspects of the present application will be described in detail below. In order to make the purpose, technical solutions and advantages of the present application clearer, the present application will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are only intended to explain the present application, rather than to limit the present application. For those skilled in the art, the present application can be implemented without the need for some of these specific details. The following description of the embodiments is only to provide a better understanding of the present application by illustrating the examples of the present application.
[0036] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the statement "include..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0037] Existing risk assessment technologies are qualitative or semi-quantitative analyses conducted in accordance with the processes of risk identification, risk analysis, and risk assessment, and only assess the current situation of the assessment object. Various assessment models have been formed according to different application fields. However, the models have limitations and can only be used for specific objects.
[0038] Insufficient application of historical assessment results and historical situations has reduced the continuity and efficiency of risk assessment work.
[0039] Therefore, in order to improve the accuracy of risk assessment and the accuracy of risk assessment results, this application proposes an assessment method for a single facility (power plant, chemical plant, etc.) based on the inherent risks of the facility and changes in the facility environment, so as to facilitate risk assessment of the facility in different scenarios.
[0040] In order to solve the problems of the prior art, the embodiments of the present application provide a risk assessment method, device, equipment, storage medium and program product. The risk assessment method provided by the embodiments of the present application is first introduced below.
[0041] Figure 1 FIG. 1 is a flow chart of a risk assessment method provided by an embodiment of the present application. Figure 1 As shown, the method includes the following steps 101 to 104.
[0042] Step 101, obtaining N risk scenario events of the target facility.
[0043] Among them, the risk scenario event includes multiple risk factors, and N is a positive integer. The risk scenario event is a risk event that may occur in the target facility. The risk factors included in the risk scenario event
[0044] Taking nuclear facilities as an example, the risk scenario events that may occur in nuclear facilities may be radioactive dispersion events, attack events, nuclear explosion events, etc.
[0045] The determination of risk scenario events can be based on expert experience, historical data, etc. to manually confirm some events that are more likely to occur in some target facilities, or it can be generated by machine model prediction to obtain events that may occur in various facilities. As for how to obtain risk scenario events for target facilities, it is possible, and I will not go into details here.
[0046] Step 102, obtaining first data information and data processing rules for each risk factor in each risk scenario event.
[0047] Among them, the first data information is the data information collected by the risk factor at the target time, that is, it can be the data information related to the risk factor obtained at the target time, it can be the historical data information at any time or the data information collected in real time at the target time (assuming that the risk factor is an earthquake, the first data information can include at least one of the following: earthquake data at the initial time of the construction of the target facility, earthquake data at any time between the initial time and the target time); the data processing rule is the data processing rule of the first data information, which can be a preset assignment rule for the first data information, or a preset related algorithm for the first data information. The data information is used to indicate the risk of the target facility under the risk factor. For example, for an attack event, the risk factor may include specific attack methods, weapon types, attack routes, personnel arrangements, protective measures, etc. Taking the weapon type as an example, assuming that a risk factor of the attack event is the use of bombs to attack, the model and quantity of the bombs are the data information of the risk factor.
[0048] Here, the data processing rules may be determined by relevant experts based on the type, attributes, relevant data models and professional experience gaps of the risk factor data. This application does not limit how to determine the data processing rules for the risk factor data information of the target facility.
[0049] Here, the method for obtaining the risk factor data information may be to collect data through on-site measurement, or to consult literature, construct a mathematical model, etc. This application does not limit how to obtain the risk factor data information of the target facility. Step 103, based on the first data information and data processing rules of multiple risk factors in each risk scenario event, determine the first risk value of the risk scenario event, and obtain N first risk values
[0050] Among them, the first risk value is the risk value of a single risk scenario event.
[0051] Specifically, the risk value of each risk scenario event may be evaluated or calculated based on the first data information of each relevant risk factor in each risk scenario event and the corresponding data processing rules.
[0052] Step 104: Determine a risk assessment result of the target facility according to the N first risk values.
[0053] In some embodiments, the risk value of each risk scenario type may be determined based on the risk value of the risk scenario event with the largest risk value in that risk scenario type, and then the risk value of each risk scenario type is added together to obtain the risk value of the target facility, and the risk assessment result of the target facility is determined based on the risk value of the target facility.
[0054] In some embodiments, the risk value with the largest risk value among all risk scenario events can also be directly determined as the risk value of the target facility, that is, the first risk value with the largest risk value among N first risk values can be determined as the risk value of the target facility, and then the risk assessment result of the target facility can be determined based on the risk value of the target facility.
[0055] In some embodiments, the risk assessment result may be a risk level, and the risk level may be determined according to a preset rating rule, and illustratively, the risk level may include five levels. The preset rating rule may include a data distribution state of the risk value.
[0056] For example, if one wants to assess the nuclear security risk situation of a facility, one may obtain risk factor data of risk scenario events related to the facility, and execute S101 to S104 to obtain a nuclear security risk assessment result of the facility.
[0057] In the embodiments of the present application, the risk assessment method, device, equipment, storage medium and program product provided in the embodiments of the present application first obtain the risk scenario events that may occur in the target facility, and calculate the first risk value of each risk scenario event based on the data information at the target time of each risk element included in each risk scenario event and the corresponding data processing rules, and then perform a comprehensive assessment based on the first risk value of each risk scenario event to obtain the risk assessment result of the target facility at the target time. By combining the data at the initial time of the relevant risk elements of the target facility and the data at the target time to assess the risk of the facility, the impact of the time factor on the risk of the facility is taken into account, so that the risk assessment value is comparable in terms of time series, and the accuracy and continuity of the risk assessment results are improved.
[0058] In some embodiments, the N risk scenario events of the target facility obtained in the above step 101 may be manually confirmed based on expert experience, historical data, etc., for some events that are more likely to occur in the target facility; the risk scenario events of the target facility may also be obtained by the following method:
[0059] Acquire Q risk scenario types of the target facility, wherein each risk scenario type corresponds to an event chain, the event chain includes at least one event chain node, and each event chain node includes at least one risk factor;
[0060] Based on the event chain corresponding to each risk scenario type and at least one event chain node of the event chain, the risk scenario event of each risk scenario type is determined to obtain N risk scenario events of Q risk scenario types. The risk scenario event is composed of a risk element in each event chain node in the event chain corresponding to the risk scenario type to which it belongs.
[0061] Among them, the risk scenario type is the classification of scenario events that may occur in the target facility according to different scenario types. For example, for security incidents at nuclear power plants, attacks on nuclear power plants can be divided into land attack scenarios, water attack scenarios, air attack scenarios and network attack scenarios based on the attack path.
[0062] The risk scenario events in each risk scenario type have the same event chain nodes, that is, the risk scenario events with the same event chain nodes are classified into one type of risk scenario events. The event chain node can be a node in the development process of a risk scenario event, or it can be a necessary element of the event. The mechanism of the occurrence of typical risk scenario events under the risk scenario type is analyzed, and the event elements of the scenario are decomposed to obtain the event chain nodes.
[0063] For example: based on the occurrence patterns of typical nuclear security incidents in nuclear facilities, the event chain of attack incidents at nuclear facilities can be decomposed to obtain event chain nodes. The event chain nodes may include attack targets, protection measures, activity implementation methods, etc.
[0064] Each risk scenario type corresponds to an event chain, each event chain includes at least one event chain node, and each event chain node may include multiple risk factors.
[0065] In some embodiments, the risk factors included in an event chain node may be a variety of situations that may exist in the event chain node. For example, the event chain node may be a weapon of a risk scenario event, and the risk factors of the event chain node may include: armed invasion (land) drone (airspace), etc.
[0066] In one example, the event chain nodes of an attack event against a nuclear facility may include: weapon type, attack route, personnel arrangement, and protective measures; wherein the weapon type may include: armed invasion, drone, network attack, etc. Therefore, according to the event chain under the risk scenario type, a risk factor is selected from the risk factors in each event chain node to generate a risk scenario event. Therefore, all possible risk scenario events of each risk scenario type can be determined based on the event chain corresponding to each risk scenario type and at least one event chain node of the event chain.
[0067] In this embodiment, according to the event chain of the risk scenario event corresponding to the risk scenario type of the target facility, according to the multiple risk factors included in the event chain node, a computer can be used to gradually select from the multiple risk factors in the event chain node according to the event chain to generate a specific risk scenario event. Refining the assessment of the target facility risk to the event level can make the connotation of the risk assessment more comprehensive.
[0068] In some embodiments, in the above step 103, based on the first data information and data processing rules of multiple risk elements in each risk scenario event, the first risk value of the risk scenario event is determined to obtain N first risk values, including:
[0069] Assigning values to the risk factors according to the first data information of each risk factor in each risk scenario event and the data processing rules to obtain the first data values of multiple risk factors in each risk scenario event;
[0070] Determine preset data information of each event chain node based on the first data value of the risk factor corresponding to each event chain node in each risk scenario event;
[0071] According to the preset data information of each event chain node in the risk scenario event, the first risk value of the risk scenario event is calculated.
[0072] Since the data information types of various risk factors are different and their impacts on facility risks are also different, after obtaining the data information of the risk factors, it is usually not possible to directly conduct an assessment based on the original data information. Instead, it is necessary to first process the original data information and quantify the data information to facilitate subsequent risk assessment.
[0073] Optionally, the data processing rules may include preset assignment rules for quantifying risk factors (ie, quantifying the first data information).
[0074] Therefore, specifically, the first step is to assign values to the data information of the risk factors corresponding to each event chain in the risk scenario event, and to quantify or normalize the data information of the risk factors. The second step is to determine the preset data information of the risk factor at the target time based on the first data value of the risk factor obtained after processing, that is, the corresponding preset data information of each event chain node of the risk scenario event; finally, the risk value of the risk scenario event is evaluated based on the preset data information of each event chain node of the risk scenario event, thereby improving the accuracy of risk assessment.
[0075] In an example, assuming that the risk scenario event is an attack event, the event chain nodes included in the event chain corresponding to the risk scenario type to which the attack event belongs include: weapon type. First, the assignment rule (i.e., data processing rule) can be predetermined based on the characteristics of the risk factor (for example, if the weapon type is an armed invasion, the risk factor information of the event chain node is assigned 20; if the weapon type is a drone, the risk factor information of the event chain node is assigned 5), and the first data value of the risk factor is determined using the preset assignment rule.
[0076] In some embodiments, the data processing rules include a preset time variation function corresponding to the risk factor. In order to further improve the accuracy of risk assessment, the risk factor is assigned a value according to the first data information of each risk factor in each risk scenario event and the data processing rules to obtain the first data values of multiple risk factors in each risk scenario event, which may include:
[0077] Obtaining a preset time variation function of a risk factor;
[0078] The first data information of the risk factor is assigned a value using a preset time variation function to obtain the first data values of multiple risk factors at the target time.
[0079] Among them, the preset time variation function can be constructed by analyzing the relevant data of the risk factor (such as historical data, research results, etc.) to obtain the law of change of the risk factor over time.
[0080] Specifically, after obtaining the preset time variation function of the risk factor, the data information of the risk factor can be passed through the preset time variation function to calculate the preset data information, that is, the calculated value for evaluating the risk value at the target moment.
[0081] In this embodiment, the risk of the facility can be assessed in combination with relevant data information of relevant risk factors of the target facility (including data at the initial moment and data at the target moment, etc.), taking into account the impact of time factors on the risk of the facility, making the risk assessment values comparable in time series, and improving the accuracy and comparability of the risk assessment results.
[0082] In some embodiments, the first data value of the risk factor corresponding to each event chain node in each risk scenario event is used to determine the preset data information of each event chain node.
[0083] The preset data information includes: probability, consequence and weight of event chain nodes.
[0084] According to the probability, consequence and parameters of each event chain node in each risk scenario event, the first risk value of the risk scenario event is calculated.
[0085] Among them, the probability and consequence of the event chain node can be calculated according to the preset algorithm, and the weight of the event chain node is based on the attributes of the event chain node and can be preset by experts.
[0086] In one example, assuming that the risk scenario event is an attack event, if the event chain corresponding to the risk scenario type to which the attack event belongs includes an event chain node: weapon type, then the assignment rule can be pre-determined according to the characteristics of the risk factor and the first data value of the risk factor corresponding to the event chain node can be determined as k by the preset time change function. Then, the k value can be substituted into the algorithm pre-set for the event chain node to calculate the probability, consequence and weight of the event chain node.
[0087] In order to facilitate the understanding of the evaluation method provided in this embodiment, the practical application of the above evaluation method is provided here for illustration, and specifically refer to the following example:
[0088] Step 1: Build a risk indicator database (i.e., risk factor database).
[0089] (1) Build an index database of factors that affect risks in the natural environment.
[0090] E={e1,e2,……,e y}
[0091] Among them, e y Natural environmental factors that affect facility risks, such as earthquakes, fires, and heavy rains.
[0092] (2) Construct a database of risk factors in the social environment.
[0093] S={s1,s2,……,s z}
[0094] Among them, s z Social environmental factors that affect facility risks, such as public security level, population density, domestic and international environment, etc.
[0095] (3) Construct a risk factor indicator library related to facility attributes.
[0096] F={f1,f2,……,f l}
[0097] Among them, f n Facility attribute factors that affect facility risks, such as facility type, level, protection measures, and management system.
[0098] (4) In view of the particularity of the facilities, a library of indicators for other factors not covered by (1), (2), and (3) is constructed.
[0099] P = {p1, p2, ..., p w}
[0100] Among them, p w It includes special requirements in different fields and special considerations beyond the common features of facilities of the same type.
[0101] Step 2: According to the typical scenario classification, obtain each risk scenario event.
[0102] (1) According to the characteristics of the field to which the target facility belongs, the risk A of the target facility can be divided into u risk scenarios: A = {a1, a2, ..., a u};
[0103] Risk scenario a u Including multiple risk scenario events L n :a u ={L1, L2, ..., L n};
[0104] Risk scenario event L n Includes multiple event chain nodes v :L n ={l1,l2,...,l v};
[0105] Event chain node l v It includes multiple risk factors. v ={m1, m2, ..., m x},m x ∈
[0106] {E,S,F,P};
[0107] For the risk factor set corresponding to the event chain node in each risk scenario type, according to the event chain, select from the risk factor set corresponding to the event chain node step by step to generate specific risk scenario events.
[0108] Step 3: Determine the probability, consequence, and weight of the event chain nodes.
[0109] Construct a database of l = {probability, consequence, weight}.
[0110] Among them, l v概率 =G v概率 {E,S,F,S};l v后果 =G v后果 {E,S,F,S};l v权重 =G v权重 {E,S,F,S}.
[0111] Step 4: According to the above steps S101 to S104, the risk of the target facility is assessed to obtain a risk assessment result.
[0112] This application also provides another risk assessment method, the steps are as follows:
[0113] 1. Initial risk of the facility
[0114] Facility risks generally include environmental risks related to geographical location. 自然 , such as natural events such as earthquakes, tsunamis, rainstorms, volcanic eruptions, etc.; social environment related to social security in the area where the facility is located R 社会 , such as the incidence of public security incidents, the density of people around the facility, the acquisition of attack weapons, the acquisition of facility information, etc.; related to the attributes of the facility itself 属性 , such as thermal power plants, hydropower plants, nuclear power plants, etc.; Special considerations for risks R 特殊 , given the special circumstances, risks not covered by the first three risks are given special consideration.
[0115] The risk R of the facility is expressed by formula (1).
[0116] R=ω·r (1)
[0117] Among them, ω is the weight vector and r is the risk vector, which are expressed by formula (2) and formula (3) respectively.
[0118] ω={ω 自然 ,ω 社会 ,ω 属性 ,ω 其它} (2)
[0119] r={r 自然 , r 社会 , r 属性 , r 其它} (3)
[0120] For different types of facilities, ω is different. For the same facility, different values of r are obtained when the evaluation is carried out at different times.
[0121] The initial risk value of a single facility is derived from the risk analyzed when the facility is constructed, and is expressed in formula (4):
[0122] R 初始 =ω 自然 × 自然·初始 +ω 社会 × 社会·初始 +ω 属性 × 属性·初始 +
[0123] ω 其它 × 其它·初始 (4)
[0124] The weight vector ω is related to the degree to which the facility is affected by the environment, and the risk vector r takes the expected value during design, or the value of the first risk assessment after construction is completed.
[0125] 2. Risk of the facility at time t
[0126] The risk at time t is relative to the initial risk. After the facility has been in operation for t time, the natural environment, social environment, and facility aging have changed. 初始 Based on this, the risk value changes, which can be expressed by formula (5):
[0127] r (t) = k·r 初始 ±Δ r (5)
[0128] Where k = {k 自然 , k 社会 , k 属性 , k 其它}, Δ r = {r 自然 , r 社会 , r 属性 , r 其它}.
[0129] Carry out risk assessment according to steps (1) to (4) to obtain the risk value of the facility at time t.
[0130] like Figure 2 As shown, the embodiment of the present application further provides a risk assessment device 200, comprising:
[0131] The first acquisition module 201 is used to acquire N risk scenario events of the target facility, where the risk scenario event includes multiple risk factors, and N is a positive integer;
[0132] The second acquisition module 202 is used to acquire first data information and data processing rules of each risk factor in each risk scenario event, wherein the first data information is data information collected by the risk factor at the target time, and the data information is used to indicate the risk existing in the target facility under the risk factor;
[0133] A determination module 203, for determining first data information and data processing rules based on a plurality of risk factors in each risk scenario event;
[0134] The assessment module 204 is used to determine the risk assessment result of the target facility according to the N first risk values.
[0135] In some embodiments, in order to improve the accuracy of the evaluation result, the first acquisition module 201 may include:
[0136] A first acquisition submodule is used to acquire Q risk scenario types of the target facility, wherein each risk scenario type corresponds to an event chain, the event chain includes at least one event chain node, each event chain node includes at least one risk factor, and Q is a positive integer;
[0137] The first determination submodule is used to determine the risk scenario events of each risk scenario type based on the event chain corresponding to each risk scenario type and at least one event chain node of the event chain, and obtain N risk scenario events of Q risk scenario types. The risk scenario event is composed of a risk element in each event chain node in the event chain corresponding to the risk scenario type to which it belongs.
[0138] In some embodiments, the determination module 203 is specifically used to:
[0139] An assignment submodule, used to assign values to risk factors according to the first data information of each risk factor in each risk scenario event and a data processing rule, to obtain first data values of multiple risk factors in each risk scenario event;
[0140] A second determination submodule, for determining preset data information of each event chain node based on the first data value of the risk factor corresponding to each event chain node in each risk scenario event;
[0141] The calculation submodule is used to calculate the first risk value of the risk scenario event based on the preset data information of each event chain node in the risk scenario event.
[0142] In some embodiments, the data processing rule includes a preset time variation function corresponding to the risk factor, and the above-mentioned assignment submodule is specifically used for:
[0143] Obtaining a preset time variation function of a risk factor;
[0144] The first data information of the risk factor is assigned a value using a preset time variation function to obtain the first data values of the plurality of risk elements at the target time.
[0145] In some embodiments, the above-mentioned preset data information includes: probability, consequence and weight of event chain nodes.
[0146] The risk assessment device provided in the embodiment of the present application first obtains the risk scenario events that may occur in the target facility, calculates the first risk value of each risk scenario event based on the data information of the target time of each risk element included in each risk scenario event and the corresponding data processing rules, and then performs a comprehensive assessment based on the first risk value of each risk scenario event to obtain the risk assessment result of the target facility at the target time. By combining the data information of the relevant risk elements of the target facility (including the data at the initial time and the data at the target time) to assess the risk of the facility, the impact of the time factor on the risk of the facility is taken into account, so that the risk assessment value is comparable in terms of time series, and the accuracy and continuity of the risk assessment results are improved.
[0147] Figure 3 A schematic diagram of the hardware structure of an electronic device provided in an embodiment of the present application is shown.
[0148] The electronic device may include a processor 301 and a memory 302 storing computer program instructions.
[0149] Specifically, the processor 301 may include a central processing unit (CPU), or an application specific integrated circuit (ASIC), or may be configured to implement one or more integrated circuits of the embodiments of the present application.
[0150] The memory 302 may include a large capacity memory for data or instructions. By way of example and not limitation, the memory 302 may include a hard disk drive (HDD), a floppy disk drive, a flash memory, an optical disk, a magneto-optical disk, a magnetic tape, or a universal serial bus (USB) drive or a combination of two or more of these. In appropriate cases, the memory 302 may include a removable or non-removable (or fixed) medium. In appropriate cases, the memory 302 may be inside or outside the integrated gateway disaster recovery device. In a specific embodiment, the memory 302 is a non-volatile solid-state memory.
[0151] The memory may include read-only memory (ROM), random access memory (RAM), magnetic disk storage media devices, optical storage media devices, flash memory devices, electrical, optical or other physical / tangible memory storage devices. Thus, typically, the memory includes one or more tangible (non-transitory) computer-readable storage media (e.g., memory devices) encoded with software including computer-executable instructions, and when the software is executed (e.g., by one or more processors), it is operable to perform the operations described with reference to the method according to an aspect of the present disclosure.
[0152] The processor 301 implements any one of the risk assessment methods in the above embodiments by reading and executing computer program instructions stored in the memory 302 .
[0153] In one example, the electronic device may further include a communication interface 303 and a bus 304. Figure 3 As shown, the processor 301, the memory 302, and the communication interface 303 are connected via a bus 304 and communicate with each other.
[0154] The communication interface 303 is mainly used to implement communication between various modules, devices, units and / or equipment in the embodiments of the present application.
[0155] Bus 304 includes hardware, software or both, and the parts of online data flow billing equipment are coupled to each other. For example, but not limitation, bus may include accelerated graphics port (AGP) or other graphics bus, enhanced industrial standard architecture (EISA) bus, front-end bus (FSB), hypertransport (HT) interconnection, industrial standard architecture (ISA) bus, infinite bandwidth interconnection, low pin count (LPC) bus, memory bus, micro channel architecture (MCA) bus, peripheral component interconnection (PCI) bus, PCI-Express (PCI-X) bus, serial advanced technology attachment (SATA) bus, video electronics standard association local (VLB) bus or other suitable bus or two or more of these combinations. In appropriate cases, bus 304 may include one or more buses. Although the present application embodiment describes and shows a specific bus, the present application considers any suitable bus or interconnection.
[0156] In addition, in combination with the risk assessment method in the above embodiment, the embodiment of the present application can provide a computer storage medium to implement. The computer storage medium stores computer program instructions; when the computer program instructions are executed by the processor, any one of the risk assessment methods in the above embodiment is implemented.
[0157] It should be clear that the present application is not limited to the specific configuration and processing described above and shown in the figures. For the sake of simplicity, a detailed description of the known method is omitted here. In the above embodiments, several specific steps are described and shown as examples. However, the method process of the present application is not limited to the specific steps described and shown, and those skilled in the art can make various changes, modifications and additions, or change the order between the steps after understanding the spirit of the present application.
[0158] The functional blocks shown in the above block diagram can be implemented as hardware, software, firmware or a combination thereof. When implemented in hardware, it can be, for example, an electronic circuit, an application specific integrated circuit (ASIC), appropriate firmware, a plug-in, a function card, etc. When implemented in software, the elements of the present application are programs or code segments that are used to perform the required tasks. The program or code segment can be stored in a machine-readable medium, or transmitted on a transmission medium or a communication link by a data signal carried in a carrier wave. "Machine-readable medium" can include any medium capable of storing or transmitting information. Examples of machine-readable media include electronic circuits, semiconductor memory devices, ROM, flash memory, erasable ROM (EROM), floppy disks, CD-ROMs, optical disks, hard disks, optical fiber media, radio frequency (RF) links, etc. The code segment can be downloaded via a computer network such as the Internet, an intranet, etc.
[0159] It should also be noted that the exemplary embodiments mentioned in this application describe some methods or systems based on a series of steps or devices. However, this application is not limited to the order of the above steps, that is, the steps can be performed in the order mentioned in the embodiment, or in a different order from the embodiment, or several steps can be performed simultaneously.
[0160] Aspects of the present disclosure are described above with reference to the flowcharts and / or block diagrams of the methods, devices (systems) and computer program products according to the embodiments of the present disclosure. It should be understood that each box in the flowchart and / or block diagram and the combination of each box in the flowchart and / or block diagram can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable risk assessment device to produce a machine so that these instructions executed by the processor of the computer or other programmable risk assessment device enable the implementation of the function / action specified in one or more boxes of the flowchart and / or block diagram. Such a processor can be, but is not limited to, a general-purpose processor, a special-purpose processor, a special application processor, or a field programmable logic circuit. It can also be understood that each box in the block diagram and / or flowchart and the combination of boxes in the block diagram and / or flowchart can also be implemented by dedicated hardware that performs a specified function or action, or can be implemented by a combination of dedicated hardware and computer instructions.
[0161] The above are only specific implementation methods of the present application. Those skilled in the art can clearly understand that for the convenience and simplicity of description, the specific working processes of the systems, modules and units described above can refer to the corresponding processes in the aforementioned method embodiments, and will not be repeated here. It should be understood that the protection scope of the present application is not limited to this. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed in this application, and these modifications or replacements should be included in the protection scope of this application.
Claims
1. A risk assessment method, characterized in that: include: Obtain N risk scenario events of the target facility, wherein the risk scenario event includes multiple risk factors, and N is a positive integer; Acquire first data information and data processing rules for each of the risk factors in each of the risk scenario events, wherein the first data information is data information collected by the risk factor at a target time, and the data information is used to indicate the risk of the target facility under the risk factor; Determine a first risk value of the risk scenario event based on first data information of multiple risk elements in each of the risk scenario events and a data processing rule, and obtain N first risk values; A risk assessment result of the target facility is determined according to the N first risk values.
2. The method according to claim 1, characterized in that: The N risk scenario events of the target facility are obtained, including: Acquire Q risk scenario types of the target facility, wherein each risk scenario type corresponds to an event chain, the event chain includes at least one event chain node, and each event chain node includes at least one risk element; Based on the event chain corresponding to each of the risk scenario types and at least one event chain node of the event chain, risk scenario events of each of the risk scenario types are determined to obtain N risk scenario events of the Q risk scenario types, wherein the risk scenario event is composed of a risk element in each event chain node in the event chain corresponding to the risk scenario type to which it belongs.
3. The method according to claim 2, characterized in that The determining the first risk value of the risk scenario event based on the first data information of the plurality of risk elements in each of the risk scenario events and the data processing rules to obtain N first risk values comprises: Assigning values to the risk factors according to the first data information and data processing rules of each risk factor in each risk scenario event to obtain first data values of multiple risk factors in each risk scenario event; Determining preset data information of each of the event chain nodes based on the first data value of the risk factor corresponding to each of the event chain nodes in each of the risk scenario events; A first risk value of the risk scenario event is calculated based on preset data information of each event chain node in the risk scenario event.
4. The method according to claim 3, characterized in that The data processing rules include a preset time variation function corresponding to the risk factor; The step of assigning a value to each risk factor according to the first data information and data processing rules of each risk factor in each risk scenario event to obtain first data values of multiple risk factors in each risk scenario event includes: Obtaining a preset time variation function of the risk factor; The first data information of the risk factor is assigned a value using the preset time variation function to obtain first data values of multiple risk elements at the target time.
5. The method according to claim 3, characterized in that: The preset data information includes: the probability, consequence and weight of the event chain node.
6. A risk assessment device, characterized in that: include: A first acquisition module is used to acquire N risk scenario events of a target facility, wherein the risk scenario event includes multiple risk factors, and N is a positive integer; A second acquisition module is used to acquire first data information and data processing rules of each risk factor in each risk scenario event, wherein the first data information is data information collected by the risk factor at a target time, and the data information is used to indicate the risk of the target facility under the risk factor; A determination module, configured to determine a first risk value of the risk scenario event based on first data information of a plurality of risk elements in each of the risk scenario events and a data processing rule, and obtain N first risk values; An assessment module is used to determine a risk assessment result of the target facility according to the N first risk values.
7. The device according to claim 6, characterized in that The first acquisition module includes: A first acquisition submodule is used to acquire Q risk scenario types of a target facility, wherein each risk scenario type corresponds to an event chain, the event chain includes at least one event chain node, each event chain node includes at least one risk factor, and Q is a positive integer; The first determination submodule is used to determine the risk scenario events of each risk scenario type based on the event chain corresponding to each risk scenario type and at least one event chain node of the event chain, to obtain N risk scenario events of the Q risk scenario types, wherein the risk scenario event is composed of a risk element in each event chain node in the event chain corresponding to the risk scenario type to which it belongs.
8. A risk assessment device, characterized in that: The device comprises: a processor and a memory storing computer program instructions; When the processor executes the computer program instructions, the risk assessment method according to any one of claims 1 to 5 is implemented.
9. A readable storage medium, characterized in that: The readable storage medium stores a program or instruction, and when the program or instruction is executed by the processor, the steps of the risk assessment method according to any one of claims 1 to 5 are implemented.
10. A computer program product, characterized in that When the instructions in the computer program product are executed by a processor of an electronic device, the electronic device executes the risk assessment method as described in any one of claims 1 to 5.