Method, device and equipment for determining inter-provincial power transmission project planning scheme
By optimizing the target voltage level and resource input, the problem of low computational efficiency in inter-provincial transmission project planning is solved, and the minimum value of the total resource input is efficiently determined when the scale of the power system is large, improving planning efficiency and accuracy.
Patent Information
- Application Number
- CN202410943452.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-10-08
- Estimated Expiration
- 2044-07-15
AI Technical Summary
The existing inter-provincial power transmission project planning method is not very efficient when the power grid is large in scale, and it is difficult to effectively determine the minimum total resource input, the optimal operation and maintenance resource input, and the optimal carbon emission resource input.
By obtaining the operation and maintenance resource input and carbon emission resource input of the power system, the target voltage level is determined, and based on the pre-built total resource input objective function, the operation and maintenance resource input and carbon emission resource input are optimized to determine the optimal Excellent inter-provincial power transmission project planning scheme.
It improves the efficiency of inter-provincial power transmission project planning and can efficiently determine the minimum total resource investment when the scale of the power system is too large. The optimal operation and maintenance resource input and the optimal carbon emission resource input reduce Planning difficulty.
Smart Images

Figure CN118747693A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of power electronics technology, and in particular to a method, device, computer equipment, computer-readable storage medium and computer program product for determining a planning scheme for an inter-provincial power transmission project. Background Art
[0002] Inter-provincial power transmission projects can transmit electricity from one province to another, thus providing power to provinces that lack electricity. By making reasonable plans for inter-provincial power transmission projects, the power transmission efficiency of inter-provincial power transmission projects can be high and the resource input can be low. Therefore, it is particularly important to make reasonable plans for inter-provincial power transmission projects.
[0003] In traditional technology, the main methods for planning inter-provincial transmission projects are: 1) Transmission network planning based on mixed integer nonlinear programming algorithm, which is mainly applicable to AC transmission projects of 500kV (kilovolts) and below; 2) Transmission network planning based on mixed integer linear programming algorithm, which is mainly aimed at AC and DC ultra-high voltage or UHV transmission projects above 500kV.
[0004] However, current inter-provincial transmission project planning methods are not computationally efficient enough when the grid is large. Summary of the invention
[0005] Based on this, it is necessary to provide an efficient method, device, computer equipment, computer-readable storage medium and computer program product for determining inter-provincial power transmission project planning schemes in response to the above-mentioned technical problems.
[0006] In a first aspect, the present application provides a method for determining a planning scheme for an inter-provincial power transmission project, the method comprising:
[0007] Obtain the operation and maintenance resource input and carbon emission resource input of the power system;
[0008] For each inter-provincial transmission project in the power system, determine the target voltage level of the inter-provincial transmission project and the resource input amount under the target voltage level; the target voltage level is the simulated voltage level when the unit resource input amount of the inter-provincial transmission project is the lowest;
[0009] Based on the operation and maintenance resource input, carbon emission resource input, resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function, determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level when the total resource input is minimized;
[0010] Based on the target voltage levels of multiple inter-provincial transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial transmission project at the target voltage level, the inter-provincial transmission project planning scheme is determined.
[0011] In a second aspect, the present application also provides a device for determining a planning scheme for an inter-provincial power transmission project, the device comprising:
[0012] An acquisition module, used to acquire the operation and maintenance resource input and carbon emission resource input of the power system;
[0013] A determination module is used to determine the target voltage level of the inter-provincial power transmission project and the resource input amount under the target voltage level for each inter-provincial power transmission project in the power system; the target voltage level is a simulated voltage level when the unit resource input amount of the inter-provincial power transmission project is the lowest;
[0014] A processing module, for determining the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level under the condition that the total resource input achieves the minimum value based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function;
[0015] The planning module is used to determine the planning scheme for inter-provincial power transmission projects based on the target voltage levels of multiple inter-provincial power transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial power transmission project under the target voltage level.
[0016] In a third aspect, the present application further provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, the following steps are implemented:
[0017] Obtain the operation and maintenance resource input and carbon emission resource input of the power system;
[0018] For each inter-provincial transmission project in the power system, determine the target voltage level of the inter-provincial transmission project and the resource input amount under the target voltage level; the target voltage level is the simulated voltage level when the unit resource input amount of the inter-provincial transmission project is the lowest;
[0019] Based on the operation and maintenance resource input, carbon emission resource input, resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function, determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level when the total resource input is minimized;
[0020] Based on the target voltage levels of multiple inter-provincial transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial transmission project at the target voltage level, the inter-provincial transmission project planning scheme is determined.
[0021] In a fourth aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the following steps are implemented:
[0022] Obtain the operation and maintenance resource input and carbon emission resource input of the power system;
[0023] For each inter-provincial transmission project in the power system, determine the target voltage level of the inter-provincial transmission project and the resource input amount under the target voltage level; the target voltage level is the simulated voltage level when the unit resource input amount of the inter-provincial transmission project is the lowest;
[0024] Based on the operation and maintenance resource input, carbon emission resource input, resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function, determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level when the total resource input is minimized;
[0025] Based on the target voltage levels of multiple inter-provincial transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial transmission project at the target voltage level, the inter-provincial transmission project planning scheme is determined.
[0026] In a fifth aspect, the present application further provides a computer program product, including a computer program, which implements the following steps when executed by a processor:
[0027] Obtain the operation and maintenance resource input and carbon emission resource input of the power system;
[0028] For each inter-provincial transmission project in the power system, determine the target voltage level of the inter-provincial transmission project and the resource input amount under the target voltage level; the target voltage level is the simulated voltage level when the unit resource input amount of the inter-provincial transmission project is the lowest;
[0029] Based on the operation and maintenance resource input, carbon emission resource input, resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function, determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level when the total resource input is minimized;
[0030] Based on the target voltage levels of multiple inter-provincial transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial transmission project at the target voltage level, the inter-provincial transmission project planning scheme is determined.
[0031] The above-mentioned method, device, computer equipment, computer-readable storage medium and computer program product for determining the planning scheme of inter-provincial power transmission projects, during the entire process, when the operation and maintenance resource input and carbon emission resource input of the power system and the target voltage level with the lowest unit resource input are obtained, the problem of determining the planning scheme of the inter-provincial power transmission project is converted into a problem of solving an objective function related to the operation and maintenance resource input, carbon emission resource input and resource input of each inter-provincial power transmission project at the target voltage level through a pre-constructed total resource input objective function, thereby reducing the planning difficulty of the inter-provincial power transmission project. Even when the scale of the power system is too large, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system can be efficiently determined when the total resource input is minimized, as well as the optimal resource input of each inter-provincial power transmission project at the target voltage level, thereby improving the efficiency of determining the planning scheme of the inter-provincial power transmission project. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] In order to more clearly illustrate the technical solutions in the embodiments of the present application or related technologies, the drawings required for use in the embodiments of the present application or related technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0033] FIG1 is an application environment diagram of a method for determining a planning scheme for an inter-provincial power transmission project in one embodiment;
[0034] Figure 2 A schematic diagram of a flow chart of a method for determining a planning scheme for an inter-provincial power transmission project in one embodiment;
[0035] Figure 3 A schematic flow chart of a method for determining a planning scheme for an inter-provincial power transmission project in another embodiment;
[0036] Figure 4 A structural block diagram of a device for determining a planning scheme for an inter-provincial power transmission project in one embodiment;
[0037] Figure 5 FIG. 4 is a diagram showing the internal structure of a computer device in one embodiment. DETAILED DESCRIPTION
[0038] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0039] The method for determining the inter-provincial power transmission project planning scheme provided in the embodiment of the present application can be applied to the application environment shown in Figure 1. Among them, the terminal 102 communicates with the server 104 through the network. The data storage system can store the data that the server 104 needs to process. The data storage system can be integrated on the server 104, or it can be placed on the cloud or other network servers. The power system is actually a power system composed of regional power grids of several provinces.
[0040] The planner clicks the planning button in the terminal 102 interface, and the terminal 102 responds to the planner's click operation, obtains the operation and maintenance resource input and carbon emission resource input of the power system from the local, generates a planning scheme determination request based on the operation and maintenance resource input and carbon emission resource input of the power system, and sends the planning scheme determination request to the server 104. The server 104 extracts the operation and maintenance resource input and carbon emission resource input of the power system in the planning scheme determination request; for each inter-provincial transmission project in the power system, determines the target voltage level of the inter-provincial transmission project and the resource input under the target voltage level; the target voltage level is the unit resource input of the inter-provincial transmission project. The simulated voltage level is determined when the input is the lowest; based on the operation and maintenance resource input, carbon emission resource input, resource input of each inter-provincial transmission project at the target voltage level, and the pre-constructed total resource input objective function, the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial transmission project at the target voltage level when the total resource input is minimized are determined; based on the target voltage levels of multiple inter-provincial transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial transmission project at the target voltage level, the inter-provincial transmission project planning scheme is determined.
[0041] The terminal 102 may be, but is not limited to, various personal computers, laptops, smart phones, tablet computers, IoT devices, and portable wearable devices. The IoT devices may be smart speakers, smart TVs, smart air conditioners, smart car devices, projection devices, etc. Portable wearable devices may be smart watches, smart bracelets, head-mounted devices, etc. Head-mounted devices may be virtual reality (VR) devices, augmented reality (AR) devices, smart glasses, etc. The server 104 may be an independent physical server, a server cluster or distributed system consisting of multiple physical servers, or a cloud server that provides cloud computing services.
[0042] In an exemplary embodiment, Figure 2 As shown, a method for determining a planning scheme for an inter-provincial power transmission project is provided, and the method is applied to the server 104 in FIG. 1 as an example for explanation. Among them:
[0043] S200, obtaining the operation and maintenance resource input and carbon emission resource input of the power system.
[0044] Among them, the power system is a power system composed of regional power grids in several provinces. The operation and maintenance resource input includes the operation resource input and maintenance resource input of each province in the power system. The operation resource input refers to the operation resource input of the generator set, and the maintenance resource input refers to the maintenance resource input of the generator set. The operation and maintenance resource input of the power system is equal to the sum of the operation resource input and maintenance resource input of all provinces in the power system. Carbon emission resource input refers to the resource input of carbon emissions under the low-carbon policy. Both the operation and maintenance resource input and the carbon emission resource input are variable parameters.
[0045] Specifically, inter-provincial power transmission projects are power transmission projects established between provinces in the power system. The method for determining the planning scheme for inter-provincial power transmission projects is essentially to find an economically optimal planning scheme for establishing power transmission projects between all provinces in the power system. Therefore, when obtaining the inter-provincial power transmission project plan, it is necessary to consider the resource input in several dimensions to optimize the economic effect of the planning scheme. The multi-dimensional resource inputs that need to be considered include, but are not limited to: resource inputs such as the power system's operation and maintenance resource inputs and carbon emission resource inputs.
[0046] In an exemplary embodiment, obtaining the operation and maintenance resource investment of the power system is essentially obtaining the sum of the operation and maintenance resource investment of each province in the power system, and obtaining the operation and maintenance resource investment of each province in the power system can be achieved through the operation and maintenance plans of each province.
[0047] In an exemplary embodiment, obtaining the carbon emission resource input of the power system is essentially obtaining the sum of the carbon emission resource inputs of each province in the power system. Since the carbon emission resource input is equal to the product of the carbon emissions and the unit carbon emission resource input, the sum of the carbon emission resource inputs of each province in the power system is equal to the product of the sum of the carbon emissions of each province in the power system and the unit carbon emission resource input. In other words, by obtaining the sum of the carbon emissions of each province in the power system and the unit carbon emission resource input, the carbon emission resource input of the power system can be further determined.
[0048] S400, for each inter-provincial power transmission project in the power system, determining a target voltage level of the inter-provincial power transmission project and a resource input amount under the target voltage level.
[0049] Among them, the target voltage level is the simulated voltage level under the condition of the lowest unit resource input of the inter-provincial power transmission project. In practical applications, the simulated voltage level is divided into AC simulated voltage level and DC simulated voltage level. For example, the AC simulated voltage level includes 330kV, 500kV, 750kV, and 1000kV, and the DC simulated voltage level includes ±500kV, ±800kV, and ±1100kV. The resource input is actually the investment input.
[0050] Specifically, the simulated voltage level is more than one voltage level, and for each inter-provincial transmission project in the power system, the corresponding unit resource input amount of the inter-provincial transmission project when simulating different simulated voltage levels can be determined. Based on multiple unit resource input amounts of each inter-provincial transmission project under different simulated voltage levels, the simulated voltage level with the lowest unit resource input amount is determined, and it is used as the target voltage level of the corresponding inter-provincial transmission project until the target voltage level of all inter-provincial transmission projects is determined.
[0051] Furthermore, the target voltage level of each inter-provincial power transmission project is used as the type of the corresponding inter-provincial power transmission project, and then the resource input amount of each inter-provincial power transmission project under the type is determined.
[0052] S600, based on the operation and maintenance resource input, carbon emission resource input, resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function, determines the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level when the total resource input is minimized.
[0053] Among them, the pre-constructed total resource input objective function refers to the corresponding relationship between the total resource input and its multiple influencing factors. In this application, the factors affecting the determination of the inter-provincial power transmission project planning scheme include the operation and maintenance resource input, carbon emission resource input, and the resource input of each inter-provincial power transmission project at the target voltage level.
[0054] Specifically, inter-provincial power transmission projects include direct current power transmission projects and alternating current power transmission projects. The resource input amount of each inter-provincial power transmission project at the target voltage level is determined, that is, the resource input amount of each direct current power transmission project at the target voltage level and the resource input amount of each alternating current power transmission project at the target voltage level are determined. Based on the sum of the resource input amount of each direct current power transmission project at the target voltage level and the resource input amount of each alternating current power transmission project at the target voltage level, the resource input amount of all inter-provincial power transmission projects in the power system at the target voltage level is obtained. In practical applications, the resource input amount of all inter-provincial power transmission projects in the power system at the target voltage level can also be obtained directly based on the sum of the resource input amount of each inter-provincial power transmission project at the target voltage level.
[0055] Obtain the pre-built total resource input objective function. Substitute the operation and maintenance resource input, carbon emission resource input, and resource input of all inter-provincial power transmission projects at the target voltage level into the constructed total resource input objective function to obtain the total resource input.
[0056] For example, inter-provincial power transmission projects include DC power transmission projects and AC power transmission projects. Let the pre-constructed total resource input objective function be:
[0057]
[0058] in, is the amount of operation and maintenance resources invested in the power system, is the amount of operating resources input in the power system, is the amount of maintenance resources invested in the power system; is the resource input of all inter-provincial transmission projects in the power system at the target voltage level. It is the sum of the resource input of each AC transmission project in the power system at the target voltage level. It is the sum of resource inputs of each DC transmission project in the power system at the target voltage level; It is the amount of carbon emission resource input in the power system.
[0059] Furthermore, since the input of operation and maintenance resources, the input of carbon emission resources, and the input of resources for each inter-provincial power transmission project at the target voltage level are all variable, the total amount of resource input obtained is also variable. Since the total amount of resource input is the lowest, the economic benefits of inter-provincial power transmission projects can be maximized. Therefore, when the total amount of resource input is minimized, the optimal input of operation and maintenance resources, the optimal input of carbon emission resources, and the optimal input of resources for all inter-provincial power transmission projects at the target voltage level can be obtained. Based on the optimal input of resources for all inter-provincial power transmission projects at the target voltage level, the optimal input of resources for each inter-provincial power transmission project at the target voltage level can be further determined.
[0060] S800, determining the inter-provincial power transmission project planning scheme based on the target voltage levels of multiple inter-provincial power transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial power transmission project under the target voltage level.
[0061] Specifically, the inter-provincial power transmission project planning scheme needs to consider multi-dimensional factors, including but not limited to the type of inter-provincial power transmission projects between two provinces in the power system, that is, the target voltage level, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial power transmission project at the target voltage level. Therefore, multiple planning dimensions such as the target voltage level of multiple inter-provincial power transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial power transmission project at the target voltage level can be considered to obtain a more accurate inter-provincial power transmission project planning scheme.
[0062] For example, there are three provinces, A, B, and C, in the power system. The inter-provincial transmission project plan can be: establish a DC transmission project with a target voltage level of Level 1 between Province A and Province B, establish an AC transmission project with a target voltage level of Level 2 between Province A and Province C, and establish a DC transmission project with a target voltage level of Level 3 between Province B and Province C; the operation and maintenance resource input of the power system is the optimal operation and maintenance resource input, that is, the sum of the optimal operation and maintenance resource input of Province A, Province B, and Province C is the optimal operation and maintenance resource input; the carbon emission resource input of the power system is the optimal carbon emission resource input; in the power system, the resource input of the Level 2 AC transmission project between Province A and Province C is the optimal resource input of the AC transmission project, the resource input of the Level 1 DC transmission project between Province A and Province B is the optimal resource input of the DC transmission project, and the sum of the resource input of the Level 3 DC transmission project between Province B and Province C is the optimal resource input of the DC transmission project.
[0063] In the above-mentioned method for determining the planning scheme of the inter-provincial power transmission project, when the operation and maintenance resource input and carbon emission resource input of the power system and the target voltage level with the lowest unit resource input are obtained, the problem of determining the planning scheme of the inter-provincial power transmission project is converted into a problem of solving an objective function related to the operation and maintenance resource input, carbon emission resource input, and resource input of each inter-provincial power transmission project at the target voltage level through a pre-constructed total resource input objective function, thereby reducing the planning difficulty of the inter-provincial power transmission project. Even when the scale of the power system is too large, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system can be efficiently determined when the total resource input is minimized, as well as the optimal resource input of each inter-provincial power transmission project at the target voltage level, thereby improving the efficiency of determining the planning scheme of the inter-provincial power transmission project.
[0064] In an exemplary embodiment, Figure 3 As shown, S400 includes:
[0065] S420, for each inter-provincial power transmission project in the power system, obtaining the unit resource input of the inter-provincial power transmission project under different simulated voltage levels.
[0066] S440: Determine the simulated voltage level with the lowest unit resource input as the target voltage level.
[0067] S460, obtaining the unit resource input amount and resource capacity under the target voltage level.
[0068] S480, determining the resource input amount at the target voltage level based on the unit resource input amount and resource capacity at the target voltage level.
[0069] Among them, the simulated voltage level refers to the voltage level of the simulated inter-provincial power transmission project, not the actual voltage level of the inter-provincial power transmission project. Unit resource input refers to the ratio of resource input to transmission capacity, that is, the resource input corresponding to each unit transmission capacity. Resource capacity is the transmission capacity of the inter-provincial power transmission project at the target voltage level.
[0070] Specifically, the unit resource input of the inter-provincial power transmission project under different simulated voltage levels is obtained. Since this application is to determine the planning scheme with the highest economic benefits, the lower the unit resource input, the higher the economic benefits of the obtained planning scheme. Therefore, based on the unit resource input of the inter-provincial power transmission project under different simulated voltage levels, the simulated voltage level corresponding to the lowest unit resource input is screened from multiple simulated voltage levels, and it is determined as the target voltage level. Furthermore, the unit resource input is essentially the ratio of the resource input of the inter-provincial power transmission project under the target voltage level to the transmission capacity. Therefore, in order to determine the resource input, the unit resource input and resource capacity of the inter-provincial power transmission project under the target voltage level can be obtained, and based on the product of the unit resource input and resource capacity under the target voltage level, the resource input under the target voltage level can be obtained.
[0071] In the above embodiment, by determining the simulated voltage level with the lowest unit resource input as the target voltage level, the voltage level with the highest economic benefit can be screened out and used as the actual voltage level of the inter-provincial power transmission project in the planning scheme, thereby improving the accuracy of determining the planning scheme for the inter-provincial power transmission project.
[0072] In an exemplary embodiment, obtaining the unit resource input of the inter-provincial power transmission project under different simulated voltage levels includes:
[0073] For each simulated voltage level, the distance between two provinces of the inter-provincial power transmission project is obtained; the transmission capacity corresponding to the simulated voltage level is determined; based on the product of the distance between the two provinces and the preset unit distance resource input, and the product of the transmission capacity and the preset unit capacity resource input, the resource input amount of the inter-provincial power transmission project under the simulated voltage level is obtained; based on the ratio of the resource input amount to the transmission capacity, the unit resource input amount of the inter-provincial power transmission project under the simulated voltage level is determined.
[0074] Among them, the distance between two provinces refers to the distance between the centers of the two provinces; the transmission capacity refers to the capacity of the inter-provincial transmission project to transmit electricity under the simulated voltage level; the preset unit distance resource input refers to the preset resource input for each unit distance taking into account the differences in land prices among different provinces; the preset unit preset capacity resource input refers to the preset resource input for each unit transmission capacity taking into account the differences in land prices among different provinces.
[0075] Specifically, each simulated voltage level of the inter-provincial power transmission project is simulated to obtain the unit resource input of the inter-provincial power transmission project under different simulated voltage levels.
[0076] For each inter-provincial power transmission project under each simulated voltage level, determine the two provinces associated with the inter-provincial power transmission project, and obtain the distance between the two provinces associated with the inter-provincial power transmission project. For example, if the inter-provincial power transmission project is a power transmission project between province n and province m, then obtain the distance x between the centers of province n and province m. n,m , as the distance between the two provinces.
[0077] The transmission capacity corresponding to the simulated voltage level is different in the cases of AC and DC. Therefore, it is necessary to first determine whether the inter-provincial transmission project is an AC transmission project or a DC transmission project, and then determine the transmission capacity of the AC transmission project under the simulated voltage level, or the transmission capacity of the DC transmission project under the simulated voltage level.
[0078] Determining the transmission capacity of the AC transmission project under the simulated voltage level includes: obtaining the correlation between the transmission capacity of the AC transmission project under the simulated voltage level and the distance between two provinces, and obtaining the transmission capacity of the AC transmission project under the simulated voltage level based on the distance between the two provinces corresponding to the AC transmission project and the correlation between the transmission capacity and the distance between the two provinces.
[0079] For example, for the kth simulated voltage level, the correlation relationship between the transmission capacity of the AC transmission project between province n and province m is:
[0080]
[0081] Where i is a settable positive integer. is the transmission capacity of the AC transmission project between provinces n and m under the kth simulated voltage level, , , , The parameters of the polynomial fitting curve of the correlation relationship can be determined by the historical transmission capacity data and the distance between the two provinces corresponding to the historical transmission capacity data.
[0082] And the AC transmission project under the kth simulated voltage level has the corresponding maximum transmission capacity and maximum conveying distance , the transmission distance x of the AC transmission project does not exceed the maximum transmission distance , the transmission capacity of AC transmission projects Not exceeding the maximum conveying capacity That is to say, , .
[0083] Determining the transmission capacity of the DC transmission project under the simulated voltage level includes: the DC transmission project has a fixed transmission capacity corresponding to each simulated voltage level, and determining the simulated voltage level can determine the fixed transmission capacity corresponding to the simulated voltage level. That is, for the kth simulated voltage level, the transmission capacity of the DC transmission project between provinces n and m is The association relationship is: ,in, is the fixed transmission capacity of the kth simulated voltage level.
[0084] After obtaining the inter-provincial distance of the inter-provincial power transmission project and determining the transmission capacity corresponding to the simulated voltage level, the resource input of the inter-provincial power transmission project under the simulated voltage level can be determined according to the transmission capacity corresponding to the inter-provincial distance and the simulated voltage level. The resource input of the inter-provincial power transmission project under the simulated voltage level includes the distance resource input and the capacity resource input.
[0085] When the inter-provincial power transmission project is an AC power transmission project, obtain the preset unit distance resource input under the kth simulated voltage level , based on the distance x between the two provinces n,m The amount of resource input from the preset unit distance The product of distance resources is determined Furthermore, since the substations in each province are an important part of the AC transmission project, the preset unit capacity resource input is obtained based on the sum of the unit capacity resource input of the substations in each province associated with the inter-provincial transmission project. Based on the delivery capacity Compared with the preset unit capacity resource input The product of the capacity resources is used to determine the input amount of capacity resources ( ) . Based on the distance resource input and capacity resource investment The sum of the resources input of the AC power transmission project under the kth simulated voltage level is obtained. .
[0086] When the inter-provincial power transmission project is a DC power transmission project, obtain the preset unit distance resource input under the kth simulated voltage level , based on the distance x between the two provinces n,m The amount of resource input from the preset unit distance The product of distance resources is determined Furthermore, since the converter stations in each province are an important part of the DC transmission project, the preset unit capacity resource input is obtained based on the sum of the unit capacity resource input of the converter stations in each province associated with the inter-provincial transmission project. Based on the delivery capacity Compared with the preset unit capacity resource input The product of the capacity resources is used to determine the input amount of capacity resources. . Based on the distance resource input and capacity resource investment The sum of the resources invested in the DC transmission project under the kth simulated voltage level is obtained. .
[0087] Furthermore, different analog voltage levels are screened by resource input.
[0088] First, based on the maximum transmission distance under the simulated voltage level, the simulated voltage level is preliminarily screened. Specifically, for the AC transmission project under the kth simulated voltage level: the distance between the two provinces x n,m ≤Maximum conveying distance ; For the DC transmission project under the kth simulated voltage level: the distance between the two provinces x n,m ≤Maximum conveying distance , that is, based on the maximum transmission distance, the analog voltage level is preliminarily screened.
[0089] Secondly, based on the amount of resource input With transport capacity The ratio of the unit resource input of the AC transmission project under the simulated voltage level is determined. ; Based on resource input With transport capacity The ratio of the unit resource input of the AC transmission project under the simulated voltage level is determined. .
[0090] The simulated voltage levels are screened by unit resource input, and the simulated voltage level with the lowest unit resource input is determined as the target voltage level for the inter-provincial power transmission project.
[0091] In the above embodiment, when the inter-provincial power transmission project is an AC power transmission project and a DC power transmission project respectively, the resource input amount of the inter-provincial power transmission project under the simulated voltage level is accurately obtained based on the product of the distance between the two provinces and the preset unit distance resource input amount, and the product of the transmission capacity and the preset unit capacity resource input amount. Then, the target voltage level can be accurately screened from different simulated voltage levels through the unit resource input amount determined by the resource input amount.
[0092] In an exemplary embodiment, based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function, the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level are determined when the total resource input is minimized, including:
[0093] Based on the target voltage levels of multiple inter-provincial transmission projects, the power consumption constraints of each province and the inter-provincial transmission capacity constraints are determined; when the power system satisfies the power consumption constraints of each province, the inter-provincial transmission capacity constraints and the preset low-carbon constraints, based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each inter-provincial transmission project at the target voltage level, and the pre-constructed total resource input objective function, the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial transmission project at the target voltage level are determined when the total resource input achieves the minimum value.
[0094] Specifically, when determining the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input for each inter-provincial power transmission project at the target voltage level based on the total resource input objective function, it is necessary to meet multi-dimensional constraints, including the power consumption constraints of each province, the inter-provincial power transmission capacity constraints, and the preset low-carbon constraints. In other words, it is necessary to determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input for each inter-provincial power transmission project at the target voltage level based on the total resource input objective function when the total resource input is minimized, when the power consumption of each province in the power system satisfies its own power consumption constraints, the inter-provincial power transmission project between provinces satisfies the inter-provincial power transmission capacity constraints, and the power system satisfies the preset low-carbon constraints.
[0095] Furthermore, the power consumption constraints of each province and the inter-provincial transmission capacity constraints are determined based on the target voltage levels of multiple inter-provincial transmission projects in the power system. Therefore, when determining the power consumption constraints of a province, the power consumption constraints of the province can be determined based on the target voltage levels of multiple inter-provincial transmission projects associated with the province, and the inter-provincial transmission capacity constraints between any two provinces can be determined based on the target voltage levels of inter-provincial transmission projects between the two provinces.
[0096] In the above embodiment, when the power system satisfies the power consumption constraints of each province, the inter-provincial transmission capacity constraints and the preset low-carbon constraints, the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial transmission project at the target voltage level are determined based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each inter-provincial transmission project at the target voltage level, and the pre-constructed total resource input objective function. This improves the accuracy of determining the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial transmission project at the target voltage level, thereby obtaining an accurate and more economical inter-provincial transmission project planning scheme, and the obtained inter-provincial transmission project planning scheme has good green and low-carbon characteristics.
[0097] In an exemplary embodiment, based on the target voltage levels of multiple inter-provincial power transmission projects, the power consumption constraints of each province are determined, including:
[0098] For each target province, based on the target voltage levels of multiple inter-provincial transmission projects associated with the target province, the inter-provincial transmission power associated with the target province is obtained; the power generation power and power load of the target province are obtained; based on the inter-provincial transmission power, power generation power, and power load, the power quantity constraint conditions of the target province in the power system are determined.
[0099] The target province is any province in the power system. The power consumption constraint condition means that the power supply and consumption in a province always maintain a dynamic balance.
[0100] Specifically, for the target province n, the power supply in province n can be defined as the power load at time t. The power consumption in province n includes several consumption factors, including: the power generation power of various types of generator sets in province n at time t, the inter-provincial transmission power of the DC transmission lines of the DC transmission project connected to province n at time t, and the inter-provincial transmission power of the AC transmission lines of the AC transmission project connected to province n at time t. Furthermore, the inter-provincial transmission power of the DC transmission lines of the DC transmission project connected to province n at time t can be determined by the target voltage level of each DC transmission project, and the inter-provincial transmission power of the AC transmission lines of the AC transmission project connected to province n at time t can be determined by the target voltage level of each AC transmission project.
[0101] In order to keep the power supply and consumption in the target province in dynamic balance at all times, the power consumption constraint condition of the target province at time t can be determined as follows: the power generation power of various types of generator sets in n provinces at time t + the inter-provincial transmission power of the DC transmission lines of the DC transmission project connected to n provinces at time t + the inter-provincial transmission power of the AC transmission lines of the AC transmission project connected to n provinces at time t = power load.
[0102] Let the power load be L n,t , the power generation of each type of generator set in province n at time t is , the inter-provincial transmission power of the DC transmission line of the DC transmission project connecting n provinces at time t is , the inter-provincial transmission power of the DC transmission line of the DC transmission project connecting n provinces at time t is , determine the power consumption constraint of the target province at time t as:
[0103]
[0104] in, is the total number of types of generating units, is the total number of AC transmission projects connected to province n, is the total number of DC transmission projects connected to n provinces.
[0105] In the above embodiment, by establishing power consumption constraints based on inter-provincial transmission power, power generation power, and power load, it is possible to impose a certain degree of constraints on the power consumption of the province when planning the inter-provincial power transmission project, so that the power supply and consumption in the target province can always maintain a dynamic balance.
[0106] In an exemplary embodiment, based on target voltage levels of multiple inter-provincial power transmission projects, determining inter-provincial power transmission capacity constraint conditions includes:
[0107] Based on the respective target voltage levels of multiple inter-provincial transmission projects, the rated transmission capacity of the inter-provincial transmission projects is obtained; based on the rated transmission capacity, the inter-provincial transmission capacity constraint conditions are determined.
[0108] Among them, the inter-provincial transmission capacity constraint means that the inter-provincial transmission power should not exceed the power limit of the inter-provincial transmission project.
[0109] Specifically, for each inter-provincial power transmission project, the rated transmission capacity of the inter-provincial power transmission project is obtained, and the rated transmission capacity is determined based on the target voltage level of the inter-provincial power transmission project, and different target voltage levels determine different rated transmission capacities.
[0110] Furthermore, obtaining the rated transmission capacity of the inter-provincial power transmission project includes: obtaining the rated transmission capacity of the AC power transmission project and the rated transmission capacity of the DC power transmission project. Based on the rated transmission capacity of the AC power transmission project, the inter-provincial power transmission capacity constraint of the AC power transmission project is determined; based on the rated transmission capacity of the DC power transmission project, the inter-provincial power transmission capacity constraint of the DC power transmission project is determined.
[0111] In an exemplary embodiment, for an AC power transmission project between provinces n and m, based on the rated transmission capacity of the AC power transmission project , determine the inter-provincial transmission capacity constraints of AC transmission projects .in, It is the transmission capacity at time t in AC transmission projects. That is to say, in AC transmission projects, the absolute value of the transmission capacity at time t cannot exceed the rated transmission capacity.
[0112] In an exemplary embodiment, for a DC transmission project between provinces n and m, based on the rated transmission capacity of the DC transmission project , determine the inter-provincial transmission capacity constraints of DC transmission projects .in, It is the resource capacity of the DC transmission project at the target voltage level at time t. That is to say, in the DC transmission project, the absolute value of the resource capacity at time t cannot exceed the rated transmission capacity.
[0113] In the above embodiment, by determining the inter-provincial transmission capacity constraint conditions, it is possible to ensure that the absolute value of the transmission capacity of the inter-provincial transmission project at time t does not exceed the rated transmission capacity, thereby accurately determining the inter-provincial transmission project planning scheme that meets the inter-provincial transmission capacity constraint conditions.
[0114] In one embodiment, the preset low-carbon constraint condition refers to limiting the total amount of CO2 emitted by the power system. The preset low-carbon constraint condition includes: .in, is the total number of generator set types, is the carbon emission factor of the i-th type of generator set, is the total number of provinces in the power system, T is the total number of calculation periods of the pre-built resource input total objective function, Emission limits for the power system.
[0115] In an exemplary embodiment, the method for determining the inter-provincial power transmission project planning scheme further includes: when the inter-provincial transmission power and the power generation power of the target province meet the power load, determining that the power system meets the power consumption constraints of each province.
[0116] The method for determining the inter-provincial power transmission project planning scheme also includes: obtaining the resource capacity of each inter-provincial power transmission project under the target voltage level; when the resource capacity of each inter-provincial power transmission project meets the rated transmission capacity, determining that the power system meets the inter-provincial power transmission capacity constraint condition;
[0117] The method for determining the planning scheme of the inter-provincial power transmission project also includes: obtaining the total amount of carbon emissions in the power system; and determining that the power system meets the low-carbon constraint conditions when the total amount of carbon emissions in the power system is less than or equal to the preset carbon emission limit.
[0118] Specifically, for any target province in the power system, when the inter-provincial transmission power and power generation power of the target province meet the power load, that is, when all provinces in the power system meet the power consumption constraints of the corresponding provinces, the power system is determined to meet the power consumption constraints of each province; when the inter-provincial transmission power and power generation power of any target province do not meet the power load, the power system is determined to not meet the power consumption constraints of each province.
[0119] For any inter-provincial transmission project in the power system, when the resource capacity of the inter-provincial transmission project meets the rated transmission capacity, that is, when the absolute value of the resource capacity of all AC transmission projects is less than or equal to the rated transmission capacity of the AC transmission project, and the absolute value of the resource capacity of all DC transmission projects is less than or equal to the rated transmission capacity of the DC transmission project, the power system is determined to meet the inter-provincial transmission capacity constraint.
[0120] For the total carbon emissions in the power system, first, the total carbon emissions in the power system are obtained, where the total carbon emissions in the power system = .in, is the total number of generator types, is the carbon emission factor of the i-th type of generator set, is the total number of provinces in the power system, and T is the total number of calculation periods of the pre-built resource input total objective function. Less than or equal to the preset carbon emission limit In this case, it is determined that the power system meets the low-carbon constraints.
[0121] Furthermore, the unit carbon emission resource input amount is obtained, and based on the total carbon emissions in the power system and the unit carbon emission resource input amount, the carbon emission resource input amount can be determined.
[0122] In the above embodiment, the accuracy of inter-provincial transmission project planning is improved by achieving the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input for each inter-provincial transmission project at the target voltage level under the condition that the total resource input is minimized, while the inter-provincial transmission power and the generated power in the target province meet the power load, the resource capacity of each inter-provincial transmission project meets the rated transmission capacity, and the total carbon emissions in the power system are less than or equal to the preset carbon emission limit.
[0123] In one embodiment, after determining the inter-provincial transmission project planning scheme based on the target voltage levels of multiple inter-provincial transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial transmission project at the target voltage level, the planning results can also be evaluated through the levelized electricity per kilowatt-hour index and the carbon emission reduction index.
[0124] Specifically, is the optimal amount of operation and maintenance resource input in the power system. is the optimal operating resource input in the power system. is the optimal maintenance resource input in the power system, It is the optimal resource input of all inter-provincial transmission projects in the power system at the target voltage level. It is the sum of the optimal resource inputs of each AC transmission project in the power system at the target voltage level. It is the sum of the optimal resource inputs of each DC transmission project in the power system at the target voltage level. is the optimal carbon emission resource input in the power system, then based on the optimal operation and maintenance resource input , optimal carbon emission resource input , and the optimal resource input for each inter-provincial transmission project at the target voltage level , get the minimum value of the total amount of resource input .
[0125] make is the total number of generator set types, is the total number of provinces in the power system, and T is the total number of calculation periods of the pre-built resource input total objective function. The total power generation of each province in the power system during the whole period is determined as .
[0126] Minimum value based on total resource input Total power generation of each province in the power system at all times , determine the levelized electricity index .
[0127] Further, Consider it as the minimum value of the total resource input when low carbon is considered, and obtain the minimum value of the total resource input when low carbon is not considered , get the carbon emissions considering low carbon , Carbon emissions without considering low carbon , based on the minimum total resource input under low carbon considerations , the minimum value of total resource input without considering low carbon , Carbon emissions considering low carbon , and carbon emissions without considering low carbon , determine carbon reduction targets .
[0128] Based on levelized electricity index Carbon reduction targets , and evaluate the planning schemes for inter-provincial power transmission projects.
[0129] In a specific application example, there are three provinces A, B, and C in the power system. Inter-provincial power transmission projects are established between Province A and Province B, between Province A and Province C, and between Province B and Province C. The inter-provincial power transmission projects can be direct current power transmission projects or alternating current power transmission projects. In the planning process of the inter-provincial power transmission projects, the economic benefits of the power system are maximized. The method for determining the planning scheme of the inter-provincial power transmission project includes:
[0130] S1. From the simulated voltage levels, the voltage levels of the inter-provincial power transmission projects that may be built between any two provinces of A, B, and C are preliminarily screened. Specifically, the inter-provincial power transmission projects built between any two provinces may be of any simulated voltage level. Therefore, the simulated voltage levels of the inter-provincial power transmission projects can be preliminarily screened by the maximum transmission distance of the inter-provincial power transmission projects under each simulated voltage level. For example, assuming that a level 1 AC power transmission project is established between provinces A and B, the maximum transmission distance of the level 1 AC power transmission project is 200km, but the distance between provinces A and B is 300km, so a level 1 AC power transmission project cannot be established between provinces A and B.
[0131] S2. Based on the voltage levels of the inter-provincial transmission projects that may be constructed between any two of the three provinces A, B, and C, determine the unit investment cost of each inter-provincial transmission project at each voltage level; based on the unit investment cost of each inter-provincial transmission project at each voltage level, determine the optimal target voltage level corresponding to each inter-provincial transmission project.
[0132] Specifically, taking the inter-provincial power transmission project established between provinces A and B as an example, the distance between province A and province B is obtained. Based on the correlation between the transmission capacity and the distance under the kth simulated voltage level, the transmission capacity of the inter-provincial power transmission project under the kth simulated voltage level between province n and province m is determined.
[0133] Furthermore, for each inter-provincial power transmission project, based on the product of the distance between provinces A and B and the preset unit distance resource input, as well as the product of the transmission capacity and the preset unit preset capacity resource input, the resource input amount of the inter-provincial power transmission project under the kth simulated voltage level, that is, the investment cost, is obtained.
[0134] Based on the ratio of investment cost to transmission capacity, the unit investment cost of the inter-provincial power transmission project under the kth simulated voltage level is determined. The unit investment costs of the inter-provincial power transmission project under all simulated voltage levels are compared, and the simulated voltage level corresponding to the lowest unit investment cost is determined, and the simulated voltage level is determined as the target voltage level.
[0135] S3. Considering the power consumption constraints of each province, the inter-provincial transmission capacity constraints and the preset low-carbon constraints, when the power system meets the power consumption constraints of each province, the inter-provincial transmission capacity constraints and the preset low-carbon constraints, based on the pre-constructed system-wide power generation cost objective function, determine the optimal operation and maintenance cost, the optimal carbon emission resource cost, and the optimal investment cost of each inter-provincial transmission project at the target voltage level when the system-wide power generation cost is minimized.
[0136] Among them, the power consumption constraints of each province refer to:
[0137] Let the power load be L n,t , the power generation of each type of generator set in province n at time t is , the inter-provincial transmission power of the DC transmission line of the DC transmission project connecting n provinces at time t is , the inter-provincial transmission power of the DC transmission line of the DC transmission project connecting n provinces at time t is , determine the power consumption constraint of the target province at time t as:
[0138]
[0139] in, is the total number of types of generating units, is the total number of AC transmission projects connected to province n, is the total number of DC transmission projects connected to n provinces.
[0140] Inter-provincial transmission capacity constraints refer to: , .in, is the resource capacity of the DC transmission project at the target voltage level at time t, is the transmission capacity at time t in the AC transmission project, is the rated transmission capacity of the AC transmission project, It is the rated transmission capacity of the DC transmission project.
[0141] The preset low-carbon constraint conditions refer to limiting the total amount of CO2 emitted by the power system. The preset low-carbon constraint conditions include: .in, is the total number of generator types, is the carbon emission factor of the i-th type of generator set, is the total number of provinces in the power system, T is the total number of calculation periods of the pre-built resource input total objective function, Emission limits for the power system.
[0142] The pre-built resource input total objective function is: .
[0143] in, is the operation and maintenance cost in the power system, is the operating cost of the power system, is the maintenance cost in the power system; is the investment cost of all inter-provincial transmission projects in the power system at the target voltage level. It is the sum of the investment costs of each AC transmission project in the power system at the target voltage level. It is the sum of the investment costs of each DC transmission project in the power system at the target voltage level; is the cost of carbon emissions in the power system. Including: Obtaining carbon emission resources , determine the carbon emission cost based on the amount of carbon emission resources and the unit carbon emission cost.
[0144] S4. Determine the planning scheme for inter-provincial power transmission projects based on the target voltage level of the inter-provincial power transmission projects between any two provinces of A, B and C, the optimal operation and maintenance cost of the power system, the optimal carbon emission resource cost, and the optimal investment cost of each inter-provincial power transmission project at the target voltage level when the power generation cost of the entire system is minimized.
[0145] S5. Determine the levelized cost per kilowatt-hour index and carbon emission reduction cost index of the inter-provincial power transmission project planning scheme, and conduct a comprehensive analysis of the inter-provincial power transmission project planning scheme based on the levelized cost per kilowatt-hour index and carbon emission reduction cost index.
[0146] The method for determining the planning scheme of inter-provincial transmission projects in the present application can be used to analyze the economically optimal planning scheme of full-voltage AC and DC transmission projects between any two provinces across regions, and provide guidance and suggestions for the layout of inter-provincial transmission networks in the construction of new power systems; the current typical low-carbon policies are added as mathematical constraints to the total resource input objective function, and the impact of energy policies on the capacity expansion planning of new power system transmission projects can be analyzed; the mixed integer programming problem of traditional transmission network planning can be transformed into a continuous linear programming problem, reducing the difficulty of solving the total resource input objective function, improving the universality of the method for determining the planning scheme of inter-provincial transmission projects, and solving the problem of a significant decrease in computing efficiency and accuracy when the scale of the power grid system is large, and having better economy and green and low-carbon characteristics.
[0147] It should be understood that, although the steps in the flowcharts involved in the above embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps is not strictly limited in order, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above embodiments may include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.
[0148] Based on the same inventive concept, the embodiment of the present application also provides a device for determining a provincial power transmission project planning scheme for implementing the method for determining a provincial power transmission project planning scheme involved above. The implementation scheme for solving the problem provided by the device is similar to the implementation scheme recorded in the above method, so the specific limitations in one or more embodiments of the device for determining a provincial power transmission project planning scheme provided below can refer to the limitations of the method for determining a provincial power transmission project planning scheme above, and will not be repeated here.
[0149] In an exemplary embodiment, Figure 4 As shown, a device 900 for determining a planning scheme for an inter-provincial power transmission project is provided, comprising: an acquisition module 200, a determination module 400, a processing module 600 and a planning module 800, wherein:
[0150] An acquisition module 200 is used to acquire the operation and maintenance resource input and carbon emission resource input of the power system;
[0151] The determination module 400 is used to determine the target voltage level of the inter-provincial power transmission project and the resource input amount under the target voltage level for each inter-provincial power transmission project in the power system; the target voltage level is a simulated voltage level when the unit resource input amount of the inter-provincial power transmission project is the lowest;
[0152] The processing module 600 is used to determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial power transmission project at the target voltage level under the condition that the total resource input achieves the minimum value based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function;
[0153] The planning module 800 is used to determine the planning scheme for the inter-provincial power transmission project based on the target voltage levels of multiple inter-provincial power transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial power transmission project at the target voltage level.
[0154] In one of the embodiments, the determination module 400 is also used to obtain the unit resource input of the inter-provincial power transmission project under different simulated voltage levels; determine the simulated voltage level with the lowest unit resource input as the target voltage level; obtain the unit resource input and resource capacity under the target voltage level; and determine the resource input under the target voltage level based on the unit resource input and resource capacity under the target voltage level.
[0155] In one of the embodiments, the determination module 400 is also used to obtain the distance between two provinces of the inter-provincial power transmission project for each simulated voltage level; determine the transmission capacity corresponding to the simulated voltage level; obtain the resource input amount of the inter-provincial power transmission project under the simulated voltage level based on the product of the distance between the two provinces and the preset unit distance resource input amount, and the product of the transmission capacity and the preset unit capacity resource input amount; determine the unit resource input amount of the inter-provincial power transmission project under the simulated voltage level based on the ratio of the resource input amount to the transmission capacity.
[0156] In one embodiment, the processing module 600 is also used to determine the power consumption constraints of each province and the inter-provincial transmission capacity constraints based on the target voltage levels of multiple inter-provincial transmission projects; when the power system satisfies the power consumption constraints of each province, the inter-provincial transmission capacity constraints and the preset low-carbon constraints, based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each inter-provincial transmission project at the target voltage level, and the pre-constructed total resource input objective function, determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each inter-provincial transmission project at the target voltage level when the total resource input achieves the minimum value.
[0157] In one embodiment, the processing module 600 is also used to obtain, for each target province, the inter-provincial transmission power associated with the target province based on the target voltage levels of multiple inter-provincial transmission projects associated with the target province; obtain the power generation power and power load of the target province; and determine the power quantity constraints of the target province in the power system based on the inter-provincial transmission power, power generation power, and power load.
[0158] In one of the embodiments, the processing module 600 is further used to obtain the rated transmission capacity of the inter-provincial power transmission project based on the target voltage levels of each of the plurality of inter-provincial power transmission projects; and determine the inter-provincial power transmission capacity constraint conditions based on the rated transmission capacity.
[0159] In one of the embodiments, the inter-provincial power transmission project planning scheme determination device 900 also includes a constraint module, which is used to determine whether the power system meets the power quantity constraint conditions of each province when the inter-provincial transmission power and power generation power of the target province meet the power load; the constraint module is also used to obtain the resource capacity of each inter-provincial power transmission project under the target voltage level; when the resource capacity of each inter-provincial power transmission project meets the rated transmission capacity, the power system is determined to meet the inter-provincial transmission capacity constraint conditions; the constraint module is also used to obtain the total amount of carbon emissions in the power system; when the total amount of carbon emissions in the power system is less than or equal to the preset carbon emission limit, the power system is determined to meet the low-carbon constraint conditions.
[0160] Each module in the above-mentioned inter-provincial power transmission project planning scheme determination device can be implemented in whole or in part by software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0161] In an exemplary embodiment, a computer device is provided. The computer device may be a server, and its internal structure diagram may be as shown in FIG. Figure 5As shown. The computer device includes a processor, a memory, an input / output interface (Input / Output, referred to as I / O) and a communication interface. Among them, the processor, the memory and the input / output interface are connected through a system bus, and the communication interface is connected to the system bus through the input / output interface. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store data such as a pre-built total resource input objective function. The input / output interface of the computer device is used to exchange information between the processor and an external device. The communication interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, a method for determining a planning scheme for an inter-provincial power transmission project is implemented.
[0162] Those skilled in the art will understand that Figure 5 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.
[0163] In one embodiment, a computer device is further provided, including a memory and a processor, wherein a computer program is stored in the memory, and the processor implements the steps in the above method embodiments when executing the computer program.
[0164] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps in the above-mentioned method embodiments are implemented.
[0165] In one embodiment, a computer program product is provided, including a computer program, which implements the steps in the above method embodiments when executed by a processor.
[0166] A person of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment method can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in the present application can include at least one of non-volatile memory and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, an artificial intelligence (AI) processor, etc., but are not limited to this.
[0167] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this application.
[0168] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.
Claims
1. A method for determining a planning scheme for an inter-provincial power transmission project. It is characterized in that The method comprises: Obtain the operation and maintenance resource input and carbon emission resource input of the power system; For each inter-provincial power transmission project in the power system, determine a target voltage level of the inter-provincial power transmission project and a resource input amount under the target voltage level; the target voltage level is a simulated voltage level when the unit resource input amount of the inter-provincial power transmission project is the lowest; Based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each of the inter-provincial power transmission projects at the target voltage level, and a pre-constructed total resource input objective function, determine the optimal operation and maintenance resource input, the optimal carbon emission resource input, and the optimal resource input of each of the inter-provincial power transmission projects at the target voltage level when the total resource input achieves a minimum value; Based on the target voltage levels of the multiple inter-provincial power transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial power transmission project at the target voltage level, a planning scheme for the inter-provincial power transmission project is determined.
2. The method according to claim 1, It is characterized in that The determining of the target voltage level of the inter-provincial power transmission project and the resource input amount under the target voltage level includes: Obtaining the unit resource input of the inter-provincial power transmission project under different simulated voltage levels; Determine the simulated voltage level with the lowest unit resource input as the target voltage level; Obtaining unit resource input and resource capacity under the target voltage level; Based on the unit resource input amount and the resource capacity at the target voltage level, the resource input amount at the target voltage level is determined.
3. The method according to claim 2, It is characterized in that The obtaining of the unit resource input of the inter-provincial power transmission project under different simulated voltage levels includes: For each simulated voltage level, obtaining the inter-provincial distance between two provinces of the inter-provincial power transmission project; Determine the transmission capacity corresponding to the simulated voltage level; Based on the product of the distance between the two provinces and the preset resource input per unit distance, and the product of the transmission capacity and the preset resource input per unit capacity, the resource input amount of the inter-provincial power transmission project under the simulated voltage level is obtained; Based on the ratio of the resource input amount to the transmission capacity, the unit resource input amount of the inter-provincial power transmission project at the simulated voltage level is determined.
4. The method according to claim 1, It is characterized in that The determining of the optimal operation and maintenance resource input amount, the optimal carbon emission resource input amount, and the optimal resource input amount of each inter-provincial power transmission project at the target voltage level when the total resource input is minimized based on the operation and maintenance resource input amount, the carbon emission resource input amount, the resource input amount of each inter-provincial power transmission project at the target voltage level, and the pre-constructed total resource input objective function, includes: Based on the target voltage levels of the plurality of inter-provincial power transmission projects, determining power consumption constraints of each province and inter-provincial power transmission capacity constraints; When the power system satisfies the power consumption constraints of each province, the inter-provincial transmission capacity constraints and the preset low-carbon constraints, based on the operation and maintenance resource input, the carbon emission resource input, the resource input of each inter-provincial transmission project at the target voltage level, and the pre-constructed total resource input objective function, the optimal operation and maintenance resource input, the optimal carbon emission resource input and the optimal resource input of each inter-provincial transmission project at the target voltage level are determined when the total resource input achieves the minimum value.
5. The method according to claim 4, It is characterized in that The determining of the power consumption constraint conditions of each province based on the target voltage levels of the plurality of inter-provincial power transmission projects includes: For each target province, based on the target voltage levels of the plurality of inter-provincial power transmission projects associated with the target province, obtaining the inter-provincial transmission power associated with the target province; Obtaining the power generation capacity and power load of the target province; Based on the inter-provincial transmission power, the generated power, and the power load, the power quantity constraint condition of the target province in the power system is determined.
6. The method according to claim 4, It is characterized in that The determining of the inter-provincial power transmission capacity constraint conditions based on the target voltage levels of the plurality of inter-provincial power transmission projects comprises: Based on the target voltage levels of each of the plurality of inter-provincial power transmission projects, obtaining the rated transmission capacity of the inter-provincial power transmission project; Based on the rated transmission capacity, inter-provincial transmission capacity constraints are determined.
7. The method according to any one of claims 5 to 6, It is characterized in that The method further comprises: When the inter-provincial transmission power and the generated power of the target province satisfy the power load, determining that the power system satisfies the power quantity constraint conditions of each province; The method further comprises: Obtaining the resource capacity of each of the inter-provincial power transmission projects at the target voltage level; In the case where the resource capacity of each of the inter-provincial power transmission projects meets the rated transmission capacity, determining that the power system meets the inter-provincial power transmission capacity constraint condition; Obtaining the total amount of carbon emissions in the power system; When the total carbon emissions in the power system are less than or equal to a preset carbon emission limit, it is determined that the power system meets the low-carbon constraint condition.
8. A device for determining a planning scheme for an inter-provincial power transmission project, It is characterized in that The device comprises: An acquisition module, used to acquire the operation and maintenance resource input and carbon emission resource input of the power system; A determination module, for determining, for each inter-provincial power transmission project in the power system, a target voltage level of the inter-provincial power transmission project and a resource input amount under the target voltage level; the target voltage level is a simulated voltage level when the unit resource input amount of the inter-provincial power transmission project is the lowest; A processing module, for determining the optimal operation and maintenance resource input amount, the optimal carbon emission resource input amount, and the optimal resource input amount of each inter-provincial power transmission project at the target voltage level when the total resource input amount is minimized based on the operation and maintenance resource input amount, the carbon emission resource input amount, the resource input amount of each inter-provincial power transmission project at the target voltage level, and a pre-constructed total resource input objective function; A planning module is used to determine a planning scheme for an inter-provincial power transmission project based on the target voltage levels of the multiple inter-provincial power transmission projects, the optimal operation and maintenance resource input and the optimal carbon emission resource input of the power system, and the optimal resource input of each inter-provincial power transmission project at the target voltage level.
9. A computer device comprising a memory and a processor, wherein the memory stores a computer program. It is characterized in that When the processor executes the computer program, the steps of the method according to any one of claims 1 to 7 are implemented.
10. A computer-readable storage medium having a computer program stored thereon, It is characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 7 are implemented.
Citation Information
Patent Citations
Method and device for determining transmission capacity of power grid new energy base and related equipment
CN111835005A
Planning method and device for power transmission network under new energy access
CN116799870A
Resource allocation method and device based on electricity-carbon market, and storage medium
CN118278702A