Closed-loop control method for port multi-energy fusion system containing flexible direct current
By using closed-loop control methods and mathematical models to optimize energy management in the port's multi-energy integration system, the problem of energy flow management is solved, cost and reliability are improved, and carbon emissions are reduced.
Patent Information
- Application Number
- CN202410731837.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-06
- Publication Date
- 2024-10-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In a port multi-energy integration system, how to effectively manage the energy flow between multiple nodes, including external power grids, renewable energy systems, power facilities, electrochemical energy storage and hydrogen energy systems, to meet the needs of the port, especially in Renewable energy output is highly volatile.
A closed-loop control method for the port multi-energy integration system with flexible DC is used to connect these nodes by setting up two bus sections, and construct an objective function and mathematical model for the minimum operating cost, including system equipment constraints and port power flow constraints, to optimize energy Management solutions include minimizing electricity purchase and sale costs, hydrogen purchase costs, and operation and maintenance costs.
It achieves an energy management solution that minimizes the cost of electricity purchase and sale, hydrogen purchase and operation and maintenance costs while meeting the needs of the port, improves the flexibility and reliability of the power grid, and reduces operating costs and carbon emissions.
Smart Images

Figure CN118748435A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of energy control technology, and in particular to a closed-loop control method for a port multi-energy fusion system containing flexible direct current. Background Art
[0002] The port multi-energy fusion system connects a wide variety of loads with different operating characteristics. Its disordered and random production and operation mode is superimposed on the high proportion of renewable energy such as wind and light with extremely volatile output. It is necessary to establish a multi-energy fusion system of "source-grid-load-storage" and its control strategy for the port to achieve global optimized operation. Since the power equipment in the port is discretely distributed, the port power equipment can be effectively connected by setting up two sections of busbars to increase the flexibility and scalability of the power system. Adding flexible DC equipment between the two sections of busbars can improve the flexibility and reliability of the power grid in the face of faults and load changes through rapid response and precise control.
[0003] Nowadays, in order to further improve the environmental protection of ports, hydrogen energy, as a clean energy, has also begun to be gradually used in ports.
[0004] This process involves the flow of energy at multiple nodes, including external power grids, renewable energy systems, power facilities, electrochemical energy storage, flexible DC equipment, and hydrogen energy systems. How to control the energy management between these nodes to meet the needs of the port is one of the problems that needs to be solved urgently. Summary of the invention
[0005] In order to solve at least one of the technical problems mentioned in the background technology, the purpose of the present invention is to provide a closed-loop control method for a port multi-energy fusion system containing flexible direct current, which manages the hydrogen energy and electric energy in the port multi-energy fusion system when the hydrogen energy system is introduced into the port, thereby improving the utilization rate of renewable energy.
[0006] The present invention provides a closed-loop control method for a port multi-energy fusion system including flexible direct current, wherein the port multi-energy fusion system comprises two bus sections arranged in different areas and connected via flexible direct current equipment, wherein the two bus sections are connected with an external power grid, renewable energy, electrical equipment, electrochemical energy storage, and a hydrogen energy system; the hydrogen energy system comprises an electrolyzer for decomposing water into hydrogen and oxygen using electrical energy, a hydrogen storage tank, and a hydrogen fuel cell for generating electricity using hydrogen; the closed-loop control method comprises the following steps:
[0007] S1, determine the energy management cycle;
[0008] S2, obtaining the renewable energy output data and equipment power demand data of the port within a management cycle, wherein the renewable energy output data includes photovoltaic output data and wind turbine output data;
[0009] S3, based on the two bus sections, construct an objective function of minimum operating cost and a mathematical model including system equipment constraints and port power grid flow constraints; the operating cost includes the sum of electricity purchase and sales cost, hydrogen purchase cost and operation and maintenance cost; the electricity purchase and sales cost includes the difference between electricity purchase cost and electricity sales cost; the operation and maintenance cost includes the sum of photovoltaic operation and maintenance cost, wind turbine operation and maintenance cost, electrochemical energy storage operation and maintenance cost, flexible DC equipment operation and maintenance cost and hydrogen energy system operation and maintenance cost;
[0010] S4, substituting the renewable energy output data and the equipment power demand data, solving the mathematical model, and obtaining an energy management plan for the next cycle.
[0011] In certain embodiments of the first aspect of the present invention, the objective function is as follows:
[0012] min C=C BS +C BH +C OM
[0013]
[0014]
[0015]
[0016] Where: C is the total cost of port operation; C BS is the electricity purchase and sales cost, C BH is the cost of purchasing hydrogen, C OM is the operation and maintenance cost; C H is the unit hydrogen purchase cost;
[0017] C B is the electricity purchase price; P t B is the power purchased from the market at time t; C S is the electricity selling price; P t S is the power sold to the market at time t;
[0018] is the hydrogen purchase rate at time t;
[0019] C PV is the operation and maintenance cost per unit power of photovoltaic power, P t PV is the photovoltaic power generation power at time t; C WT is the operation and maintenance price per unit power of the wind turbine, P t WT is the power generation of the wind turbine at time t; C ES is the operation and maintenance price per unit power of electrochemical energy storage, is the electrochemical energy storage charging operating power at time t; is the discharge power of electrochemical energy storage at time t; C FLEX is the operation and maintenance price per unit power of the flexible DC equipment, P t FLEX is the operating power of the flexible DC equipment at time t; C EH is the operation and maintenance cost per unit power of the electrolyzer, is the operating power of the electrolytic cell at time t; C fue is the fuel cell unit power operation and maintenance cost, P t fue is the fuel cell operating power at time t.
[0020] In some embodiments of the first aspect of the present invention, the system device constraints include:
[0021] The grid energy balance constraint ensures that the energy supply and equipment power demand on the two bus sections at any time maintain power balance;
[0022] Hydrogen energy balance constraint, hydrogen energy can be kept balanced at any time;
[0023] Electrolyzer constraints: The electrolyzer has ramp constraints and start-stop constraints, and the hydrogen production power of the electrolyzer needs to be kept within a certain range;
[0024] Hydrogen storage tank constraints, which constrain the equivalent state of charge and hydrogen injection speed of the hydrogen storage tank;
[0025] Hydrogen fuel cell constraints, constraining the output power of hydrogen fuel cells and the relationship between output power and hydrogen energy;
[0026] Gateway energy exchange limit, setting the gateway exchange power limit between the two bus sections and the external power grid;
[0027] Electrochemical energy storage constraints constrain the power transfer relationship during the power transfer process between the external power grid and the electrochemical energy storage;
[0028] Flexible DC equipment constraints constrain the power transfer relationship of the flexible DC equipment during energy transfer between two bus sections.
[0029] In certain embodiments of the first aspect of the present invention, the grid energy balance constraint is as follows:
[0030]
[0031] ΔP bus2 =P t B2 -P t S2 +P t WT2 -P tL2 +P t FLEX2 +P t fue =0
[0032] Where: ΔP bus1 and ΔP bus2 P is the net power flowing through section I and section II of the electric bus at time t; t B1 is the purchased power of bus section I at time t, P t B2 is the purchased power of bus section II at time t, P t S1 is the power sold by bus section I at time t, P t S2 P is the power sold by bus section II at time t; t PV is the photovoltaic output of bus section I at time t; P t WT1 and P t WT2 P is the fan output of busbar section I and busbar section II; t EH represents the power consumption of the electrolytic cell at time t; P is the charging power and discharging power of the electrochemical energy storage at the moment t of bus section I; t L1 and P t L2 P is the electric load power of bus section I and bus section II at time t; t FLEX1 is the transfer power of the flexible DC of bus section I at time t, P t FLEX2 is the transfer power of flexible DC of bus section II at time t; t fue Represents the discharge power of the hydrogen fuel cell at time t.
[0033] In certain embodiments of the first aspect of the present invention, the hydrogen energy balance constraint is as follows:
[0034]
[0035] Where: is the hydrogen filling rate of the hydrogen storage tank; is the hydrogen consumption rate at time t; Indicates the hydrogen consumption rate of the hydrogen fuel cell, is the hydrogen production rate of the electrolyzer at time t, represents the hydrogen purchase rate at time t.
[0036] In certain embodiments of the first aspect of the present invention, the electrolytic cell is constrained as follows:
[0037] The electrolyzer has ramp constraints and start-stop constraints, and the hydrogen production power of the electrolyzer needs to be kept within a certain range. The hydrogen production power constraints of the electrolyzer are as follows:
[0038]
[0039] Where: is the hydrogen production power of the electrolyzer at time t; is the lower limit of hydrogen production power of electrolyzer, The upper limit of hydrogen production power of electrolyzer;
[0040] Electrolyzer hydrogen production power The hydrogen production rate G EH The relationship is as follows:
[0041]
[0042]
[0043] Where: K EH is the hydrogen production coefficient of the electrolyzer; η F is the Faraday efficiency; N EH is the number of electrolyzers in the electrolyzer array, z H is the number of moles of electrons transferred in the hydrogen reaction; F is the Faraday constant; U EH A constant terminal voltage maintained for the AC / DC converter;
[0044] The start and stop constraints of the electrolyzer are as follows:
[0045]
[0046]
[0047] Where: α EH Delay the start of the electrolyzer; They are respectively the start-up action and the start-up and shutdown action of the electrolytic cell; It is a 0-1 variable, indicating the switch state of the electrolytic cell; and They are the upper limits of the number of times the electrolyzer can be started and shut down in a day;
[0048] The ramp power constraint of the electrolyzer is:
[0049]
[0050] Where: It is the maximum climbing power per unit time period when the electrolyzer is in the on state.
[0051] In certain embodiments of the first aspect of the present invention, the hydrogen storage tank is constrained as follows:
[0052] The equivalent state of charge of the hydrogen storage tank is:
[0053]
[0054] Where: W H is the maximum capacity of the hydrogen storage tank, SOH t is the hydrogen energy state of the hydrogen storage tank at time t; represents the hydrogen production rate of the electrolyzer at time t, is the hydrogen consumption rate at time t, represents the hydrogen purchase rate at time t, Indicates the hydrogen consumption rate of the hydrogen fuel cell;
[0055] Constraints on equivalent state of charge of hydrogen storage tanks:
[0056] SOH min ≤SOH t ≤SOH min
[0057] Where: SOH min and SOH max They are the lower limit and upper limit of the equivalent state of charge of the hydrogen storage tank respectively;
[0058] Hydrogen filling rate of hydrogen storage tank There are also restrictions:
[0059]
[0060] In the formula, G MAX Indicates the upper limit of the hydrogen filling rate of the hydrogen storage tank.
[0061] In certain embodiments of the first aspect of the present invention, the SOC min The value range is 0.1-0.3, the SOH max The value range is 0.8-0.9.
[0062] In certain embodiments of the first aspect of the present invention, the hydrogen fuel cell constraints are as follows:
[0063] The relationship between hydrogen energy and output power is as follows:
[0064]
[0065] Where: is the output power of the hydrogen fuel cell at time t; z H is the number of moles of electrons transferred in the hydrogen reaction; N A is Avogadro's constant; mH is the molar mass of hydrogen; C0 is the number of electrons per coulomb; U N,t is the rated output voltage at time t; η fue is the fuel cell conversion efficiency.
[0066] Fuel cells also need to meet power constraints:
[0067]
[0068] Where: and They are respectively the lower and upper limits of the output power of hydrogen fuel cells.
[0069] In certain embodiments of the first aspect of the present invention, the port power grid flow constraint is as follows:
[0070]
[0071] U j,t =U i,t +2(r ij P ij +x ij Q ij )-(r ij +jx ij )L ij,t
[0072]
[0073] Where P ij,t , Q ij,t is the active power and reactive power of the branch from node i to node j at time t; P jk,t Q jk,t is the active power and reactive power of the branch from node j to node k at time t; r ij x ij is the branch resistance and reactance from node i to j; I ij,t is the branch current from node i to node j at time t; V i,t is the voltage amplitude of node i at time t; r ij and x ij is the branch resistance and reactance from node i to j; U j,t is the square of the voltage at node j at time t; U i,t is the square of the voltage at node i at time t; L ij,t is the square of the current flowing from node i to node j at time t; · , Represents the lower and upper limits of a variable.
[0074] In certain embodiments of the first aspect of the present invention, the gateway energy exchange restriction is as follows:
[0075] 0≤P t S1 ≤P S_max
[0076] 0≤P t S2 ≤P S_max
[0077] Where: and The reverse power of bus section I and bus section II to the grid is P S_max It is the maximum value of the power that a single bus section can send back to the grid.
[0078] In certain embodiments of the first aspect of the present invention, the electrochemical energy storage constraints are as follows:
[0079]
[0080] Where: E ES,t Represents the amount of electrochemical energy stored at time t; and are the charging power and discharging power of the corresponding electrochemical energy storage at time t respectively; η ch and η dis is the charging efficiency and discharging efficiency of electrochemical energy storage; Δt is the interval of scheduling time;
[0081]
[0082] Where: The upper limit of the charging power and the upper limit of the discharging power of the electrochemical energy storage. Considering that the electrochemical energy storage device cannot be charged and discharged at the same time at any time, a 0 / 1 variable is introduced and Join at the same time The conditional constraint means that at any time, the electrochemical energy storage device can only be in one of the three states of charging, discharging, or neither charging nor discharging;
[0083] Electrochemical energy storage state of charge constraints:
[0084] E ES_rated ×SOC ES_min ≤E ES,t ≤E ES_rated ×SOC ES_max
[0085] In the formula, E ES_rated E is the capacity limit of electrochemical energy storage; ES,t Represents the amount of electricity stored in electrochemical energy storage at time t; SOC ES_min SOC is the lowest state of charge for electrochemical energy storage; ES_maxIt is the highest state of charge for electrochemical energy storage.
[0086] In certain embodiments of the first aspect of the present invention, the SOC ES_min The value range is 0.1-0.3, the SOC ES_max The value range is 0.8-0.9.
[0087] In certain embodiments of the first aspect of the present invention, the flexible DC device is constrained as follows:
[0088] P t FLEX ≤|P FLEX_max |
[0089] Where: P t FLEX P is the transfer power of bus section I or II flexible DC equipment at time t; FLEX_max The upper limit of the transfer power of the flexible DC equipment;
[0090] Energy transfer at both ends of the busbars through the flexible DC equipment results in energy loss. The power transfer relationship is as follows according to the direction of energy flow in the power grid:
[0091]
[0092] Where: η FLEX is the transfer efficiency of the flexible DC device; P t FLEX1 is the power between bus section I and flexible DC equipment at time t; P t FLEX2 is the power at the junction between bus section II and flexible DC equipment at time t;
[0093] In certain embodiments of the first aspect of the present invention, the transfer efficiency of the flexible DC device is between 95% and 98%.
[0094] In a second aspect, the present invention provides a closed-loop control system for a port multi-energy fusion system including flexible direct current, comprising:
[0095] A data collection unit, for acquiring the renewable energy output data and equipment power demand data of the port within a management cycle, wherein the renewable energy output data includes photovoltaic output data and wind turbine output data;
[0096] The model building unit constructs the objective function of minimum operation cost and the mathematical model including the system equipment constraint and the port power grid flow constraint based on the two bus sections; the operation cost includes the sum of the electricity purchase and sale cost, the hydrogen purchase cost and the operation and maintenance cost; the electricity purchase and sale cost includes the difference between the electricity purchase cost and the electricity sale cost; the operation and maintenance cost includes the sum of the photovoltaic operation and maintenance cost, the wind turbine operation and maintenance cost, the electrochemical energy storage operation and maintenance cost, the flexible DC equipment operation and maintenance cost and the hydrogen energy system operation and maintenance cost;
[0097] The solving unit substitutes the renewable energy output data and the equipment power demand data, solves the mathematical model, and obtains the energy management plan for the next cycle.
[0098] The solution output unit outputs the energy management solution.
[0099] In certain embodiments of the second aspect of the present invention, the specific contents of the objective function of minimum operating cost and the mathematical model including system equipment constraints and port power grid flow constraints are as described in the first aspect.
[0100] In certain embodiments of the second aspect of the present invention, the energy management scheme comprises:
[0101] 1) Transfer of flexible DC equipment between bus section I and bus section II;
[0102] 2) The charging and discharging conditions and state of charge of electrochemical energy storage at each time point;
[0103] 3) The electricity purchase and sales situation in the external power grid market and the external hydrogen purchase situation.
[0104] Compared with the prior art, the present invention has the following beneficial effects:
[0105] 1. The present invention optimizes energy management based on flexible DC equipment, which can effectively realize energy filling between two bus sections and solve the energy management problem caused by energy charge uncertainty to a certain extent.
[0106] 2. The present invention takes into account the introduction of hydrogen energy systems, constructs an objective function of minimum operating cost and a mathematical model that includes system equipment constraints and port power grid flow constraints. When the output of renewable energy meets the power demand of the equipment, priority is given to electrochemical energy storage charging, and then the excess electricity is sold; when the output of renewable energy does not meet the power demand of the equipment, priority is given to electrochemical energy storage discharge to supplement the grid energy, and then the missing electricity is purchased; during this period, energy is transferred through the two busbars, so as to solve an energy management plan with the lowest electricity purchase and sales cost, hydrogen purchase cost and operation and maintenance cost while meeting the port needs. BRIEF DESCRIPTION OF THE DRAWINGS
[0107] Figure 1FIG. 4 is a schematic diagram of a port multi-energy fusion system according to an embodiment of the present invention.
[0108] Figure 2 The figure is a flow chart of the method of the present invention.
[0109] Figure 3 It is a schematic diagram of the system structure of the present invention.
[0110] Figure 4 Schematic diagram of simulation optimization results of bus section I according to an embodiment of the present invention.
[0111] Figure 5 It is a schematic diagram of the simulation optimization results of the II-section bus according to an embodiment of the present invention.
[0112] Figure 6 Schematic diagram of electrochemical energy storage simulation optimization results according to an embodiment of the present invention.
[0113] Figure 7 Schematic diagram of hydrogen energy simulation optimization results according to an embodiment of the present invention. DETAILED DESCRIPTION
[0114] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0115] Embodiment 1:
[0116] This embodiment provides a closed-loop control method for a port multi-energy fusion system including flexible direct current.
[0117] The port multi-energy fusion system includes two bus sections arranged in different areas and connected via flexible DC equipment, and the two bus sections are connected to an external power grid, renewable energy, electrical equipment, electrochemical energy storage, and a hydrogen energy system.
[0118] The hydrogen energy system includes an electrolyzer that uses electrical energy to decompose water into hydrogen and oxygen, a hydrogen storage tank, and a hydrogen fuel cell that uses hydrogen to generate electricity.
[0119] like Figure 1 As shown, the two bus sections are bus section I and bus section II. Bus section I is connected to the external power grid, renewable energy, electrical equipment, and electrochemical energy storage, while bus section II is connected to the external power grid, renewable energy, electrical equipment, and hydrogen energy system. In other embodiments, only one of the bus bars may be connected to the external power grid or renewable energy, or hydrogen energy systems may be set on both bus bars.
[0120] It is worth mentioning that the renewable energy sources mainly include photovoltaics, wind turbines, etc.
[0121] Electrical equipment includes bridge cranes, gantry cranes, on-site lighting, ship shore power, etc. in the port.
[0122] like Figure 2 As shown, the closed-loop control method comprises the following steps:
[0123] S1, determine the energy management cycle W T ;
[0124] S2, obtaining the renewable energy output data and equipment power demand data of the port within a management cycle, wherein the renewable energy output data includes photovoltaic output data and wind turbine output data.
[0125] The renewable energy output data and equipment power demand data may be actually measured or obtained based on predictions.
[0126] S3, based on the two bus sections, constructs the objective function of minimum operating cost and a mathematical model including system equipment constraints and port power grid flow constraints. The details are as follows:
[0127] 1. Objective Function
[0128] minC=C BS +C BH +C OM
[0129]
[0130] Where: C is the total cost of port operation; C BS is the cost of electricity purchase and sale, C BH is the cost of purchasing hydrogen, C OM is the operation and maintenance cost; that is, the total port operation cost C consists of three parts, including the electricity purchase and sales cost C BS 、Hydrogen purchase cost C BH and operation and maintenance costs C OM .
[0131] C B is the electricity purchase price; P t B is the power purchased from the market at time t; C S is the electricity selling price; P t S is the power sold to the market at time t; that is, the power purchase and sale cost includes the difference between the power purchase cost and the power sale cost.
[0132] is the hydrogen purchase rate at time t; C H is the unit hydrogen purchase cost;
[0133] C PV is the operation and maintenance cost per unit power of photovoltaic power, P t PV is the photovoltaic power generation power at time t; C WT is the operation and maintenance price per unit power of the wind turbine, P t WT is the power generation of the wind turbine at time t; C ES is the operation and maintenance price per unit power of electrochemical energy storage, is the electrochemical energy storage charging operating power at time t; is the discharge power of electrochemical energy storage at time t; C FLEX is the operation and maintenance price per unit power of the flexible DC equipment, P t FLEX is the operating power of the flexible DC equipment at time t; C EH is the operation and maintenance cost per unit power of the electrolyzer, is the operating power of the electrolytic cell at time t; C fue is the unit power operation and maintenance cost of hydrogen fuel cells, P t fue is the operating power of the hydrogen fuel cell at time t.
[0134] That is, the operation and maintenance costs include the sum of photovoltaic operation and maintenance costs, wind turbine operation and maintenance costs, electrochemical energy storage operation and maintenance costs, flexible DC equipment operation and maintenance costs and hydrogen energy system operation and maintenance costs. It is worth mentioning that the operation and maintenance costs of the hydrogen energy system mainly include the electrolyzers and hydrogen fuel cells mentioned above, while the hydrogen storage tanks in the hydrogen energy system do not require special maintenance and are therefore negligible.
[0135] 2. System Equipment Constraints
[0136] The system equipment constraints include grid energy balance constraints, hydrogen energy balance constraints, electrolyzer constraints, hydrogen storage tank constraints, hydrogen fuel cell constraints, gateway energy exchange restrictions, electrochemical energy storage constraints and flexible DC equipment constraints. Specifically:
[0137] 1. Grid energy balance constraints
[0138] Due to the involvement of flexible DC equipment, electrolyzers and hydrogen fuel cells, the grid energy balance constraint requires that the energy supply and equipment power demand on the two bus sections at any time maintain power balance. The details are as follows:
[0139]
[0140] ΔP bus2 =P t B2 -P t S2 +P t WT2-P t L2 +P t FLEX2 +P t fue =0
[0141] Where: ΔP bus1 and ΔP bus2 is the net power flowing through section I and section II of the electric bus at time t (excluding network loss); P t B1 is the purchased power of bus section I at time t, P t B2 is the purchased power of bus section II at time t, P t S1 is the power sold by bus section I at time t, P t S2 P is the power sold by bus section II at time t; t PV is the photovoltaic output of bus section I at time t; P t WT1 and P t WT2 P is the fan output of busbar section I and busbar section II; t EH represents the power consumption of the electrolytic cell at time t; P is the charging power and discharging power of the electrochemical energy storage at the moment t of bus section I; t L1 and P t L2 P is the electric load power of bus section I and bus section II at time t; t FLEX1 is the transfer power of the flexible DC of bus section I at time t, P t FLEX2 is the transfer power of flexible DC of bus section II at time t; t fue Represents the discharge power of the hydrogen fuel cell at time t.
[0142] 2. Hydrogen energy balance constraints
[0143] Due to the presence of hydrogen-powered equipment (such as hydrogen-powered container trucks and hydrogen-powered forklifts) and fuel cells in the port area, hydrogen energy needs to be balanced at any time, as follows:
[0144]
[0145] Where: is the hydrogen filling rate of the hydrogen storage tank; is the hydrogen consumption rate at time t; Indicates the hydrogen consumption rate of the hydrogen fuel cell, is the hydrogen production rate of the electrolyzer at time t, kg / h, Represents the hydrogen purchase rate at time t, kg / h.
[0146] 3. Electrolyzer Constraints
[0147] The electrolyzer is an electrochemical device that uses electricity to decompose water into hydrogen and oxygen. The port area uses an alkaline electrolyzer. Due to its characteristics, the electrolyzer has climbing constraints and start-stop constraints, and the hydrogen production power of the electrolyzer must be kept within a certain range. The hydrogen production power constraints of the electrolyzer are as follows. The electrolyzer constraints are as follows:
[0148]
[0149] Where: is the hydrogen production power of the electrolyzer at time t; is the lower limit of hydrogen production power of electrolyzer, The upper limit of hydrogen production power for electrolyzers;
[0150] Electrolyzer hydrogen production power The hydrogen production rate G EH The relationship between (kg / h) is as follows:
[0151]
[0152]
[0153] Where: K EH is the hydrogen production coefficient of the electrolyzer, kg / kWh; η F is the Faraday efficiency, which reflects the ratio of actual hydrogen production to theoretical hydrogen production and is closely related to the electrolysis temperature; N EH is the number of electrolyzers in the electrolyzer array, z H is the number of moles of electrons transferred in the hydrogen reaction, which is taken as 2; F is the Faraday constant, which is approximately 96485 coulombs per mole (C / mol); U EH A constant terminal voltage maintained for the AC / DC converter;
[0154] The start and stop constraints of the electrolyzer are as follows:
[0155]
[0156] Where: α EH Delay the start of the electrolyzer; They are respectively the start-up action and the start-up and shutdown action of the electrolytic cell; It is a 0-1 variable, indicating the switch state of the electrolytic cell; and They are the upper limits of the number of times the electrolyzer can be started and shut down in a day;
[0157] The ramp power constraint of the electrolyzer is:
[0158]
[0159] Where: It is the maximum climbing power per unit time period when the electrolyzer is in the on state.
[0160] 4. Hydrogen storage tank constraints
[0161] The hydrogen storage tank constraints are as follows:
[0162] The capacity of the hydrogen energy system is determined by the amount of gas stored in the hydrogen storage tank. In order to reflect the hydrogen storage situation of the hydrogen storage tank and facilitate energy management, the equivalent state of charge of the hydrogen storage tank is:
[0163]
[0164] Where: W H is the maximum capacity of the hydrogen storage tank, SOH t is the hydrogen energy state of the hydrogen storage tank at time t; represents the hydrogen production rate of the electrolyzer at time t, is the hydrogen consumption rate at time t, represents the hydrogen purchase rate at time t, G t fue Indicates the hydrogen consumption rate of the hydrogen fuel cell;
[0165] In order to ensure that the hydrogen storage tank is in the best working condition and avoid overcharging and overdischarging, the capacity of the hydrogen storage tank needs to have a certain margin. The equivalent state of charge constraints of the hydrogen storage tank are:
[0166] SOH min ≤SOH t ≤SOH min
[0167] Where: SOH min and SOH max are the lower limit and upper limit of the equivalent state of charge of the hydrogen storage tank respectively; considering the service life of the hydrogen storage device, the SOH min The value range is 0.1-0.3, preferably 0.2; the SOH max The value range is 0.8-0.9, preferably 0.85.
[0168] Hydrogen filling rate of hydrogen storage tank There are also restrictions:
[0169]
[0170] In the formula, G MAXIndicates the upper limit of the hydrogen injection rate of the hydrogen storage tank, which is generally 50kg / h.
[0171] 5. Hydrogen fuel cell constraints
[0172] Hydrogen fuel cells use hydrogen energy to generate electricity and are a green, environmentally friendly, high-quality power source. The reaction of proton exchange membrane fuel cells can be seen as the reverse process of water electrolysis. The output voltage is generated by the accumulation of mobile charges during the reaction, and a large amount of heat is released along with the reaction.
[0173] The relationship between hydrogen energy and output power is as follows:
[0174]
[0175] Where: P t fue is the output power of the hydrogen fuel cell at time t; z H is the number of moles of electrons transferred in the hydrogen reaction; N A is Avogadro's constant; m H is the molar mass of hydrogen, 2.016 g / mol; C0 is the number of electrons per coulomb; U N,t is the rated output voltage at time t; η fue is the fuel cell conversion efficiency.
[0176] Fuel cells also need to meet power constraints:
[0177]
[0178] Where: and They are respectively the lower and upper limits of the output power of hydrogen fuel cells.
[0179] 6. Limitation of energy exchange at the gateway
[0180] In order to ensure the safety characteristics of the distribution network, the gateway exchange power limit between the two bus sections and the external power grid is set as follows:
[0181] 0≤P t S1 ≤P S_max
[0182] 0≤P t S2 ≤P S_max
[0183] Where: and The reverse power of bus section I and bus section II to the grid is P S_max It is the maximum value of the power that a single bus section can send back to the grid, and the unit is kW.
[0184] 7. Electrochemical Energy Storage Constraints
[0185] During the power transfer process between the external power grid and the electric energy storage, there is energy loss inside the device, which constrains the power transfer relationship during the power transfer process between the external power grid and the electrochemical energy storage, as follows:
[0186]
[0187] Where: E ES,t Indicates the amount of electrochemical energy storage at time t, in kWh; and are the charging power and discharging power of the corresponding electrochemical energy storage at time t, in kW; η ch and η dis is the charging efficiency and discharging efficiency of electrochemical energy storage; Δt is the interval of scheduling time;
[0188]
[0189] Where: The upper limit of the charging power and the upper limit of the discharging power of the electrochemical energy storage. Considering that the electrochemical energy storage device cannot be charged and discharged at the same time at any time, a 0 / 1 variable is introduced and Join at the same time The conditional constraints mean that at any time, the electrochemical energy storage device can only be in one of the three states of charging, discharging, or neither charging nor discharging. There is no physically impossible phenomenon of both charging and discharging.
[0190] In order to ensure that the energy storage device is in the best working state and avoid overcharging and overdischarging, the energy storage capacity needs to have a certain margin. The state of charge constraints of electrochemical energy storage are:
[0191] E ES_rated ×SOC ES_min ≤E ES,t ≤E ES_rated ×SOC ES_max
[0192] In the formula, E ES_rated E is the capacity limit of electrochemical energy storage; ES,t Represents the amount of electricity stored in electrochemical energy storage at time t; SOC ES_min SOC is the lowest state of charge for electrochemical energy storage, ranging from 0.1 to 0.3, preferably 0.2; ES_max It is the highest state of charge of electrochemical energy storage, with a value range of 0.8-0.9, preferably 0.85.
[0193] 8. Flexible DC equipment constraints
[0194] Constrain the power transfer relationship of the flexible DC equipment during energy transfer between two bus sections.
[0195] Since the flexible DC device itself has power limitations due to its device characteristics, the flexible DC device constraints are as follows:
[0196] P t FLEX ≤|P FLEX_max |
[0197] Where: P t FLEX P is the transfer power of bus section I or II flexible DC equipment at time t; FLEX_max The upper limit of the transfer power of the flexible DC equipment;
[0198] Energy transfer at both ends of the busbars through the flexible DC equipment results in energy loss. The power transfer relationship is as follows according to the direction of energy flow in the power grid:
[0199]
[0200] Where: η FLEX is the transfer efficiency of the flexible DC device; P t FLEX1 is the power between bus section I and flexible DC equipment at time t; P t FLEX2 is the junction power between bus section II and flexible DC equipment at time t.
[0201] Generally speaking, energy transfer between the two-end busbars through flexible DC equipment involves energy loss, and its transfer efficiency is between 95% and 98%.
[0202] 3. Port power grid flow constraints
[0203] Considering that the power load in the port multi-energy fusion system is distributed in multiple substations under the bus and controlled separately, and the wind turbine photovoltaic power generation and port loading and unloading load equipment have energy feedback, in order to ensure the safety of power flow during the operation of the power grid.
[0204] The port power grid flow constraints are as follows:
[0205]
[0206] U j,t =U i,t +2(r ij P ij +x ij Q ij )-(r ij +jx ij )L ij,t
[0207]
[0208] Where P ij,t , Q ij,t is the active power and reactive power of the branch from node i to node j at time t; P jk,t Q jk,t is the active power and reactive power of the branch from node j to node k at time t; r ij x ij is the branch resistance and reactance from node i to j; I ij,t is the branch current from node i to node j at time t; V i,t is the voltage amplitude of node i at time t; r ij and x ij is the branch resistance and reactance from node i to j; U j,t is the square of the voltage at node j at time t; U i,t is the square of the voltage at node i at time t; L ij,t is the square of the current flowing from node i to node j at time t; · , Represents the lower and upper limits of a variable.
[0209] S4, substituting the renewable energy output data and the equipment power demand data, calling the commercial solver CPLEX and YALMIP toolkit to solve the mathematical model, solving the mathematical model, and obtaining the energy management plan for the next cycle.
[0210] The output information includes:
[0211] 1) Transfer of flexible DC equipment between bus section I and bus section II;
[0212] 2) The charging and discharging conditions and state of charge of electrochemical energy storage at each time point;
[0213] 3) The purchase and sale of electricity from the external power grid market and the purchase of external hydrogen;
[0214] Based on the output information, an energy management plan with optimal cost is formed.
[0215] like Figures 4 to 7 As shown, they are schematic diagrams of optimization results of bus section I, bus section II, electrochemical energy storage, and hydrogen energy system under a certain simulation embodiment.
[0216] The comparison of the port's operating costs and carbon emissions after the port uses the closed-loop control method of the present invention for energy management and when the port does not use the closed-loop control method of the present invention is shown in Table 1 below.
[0217] Table 2 Comparison of operating costs under closed-loop control strategy
[0218]
[0219] The total operating cost was reduced by 10,331.3 yuan, accounting for about 8.8%, and the carbon emission was reduced by 8.98 tons, accounting for about 12.1%. The present invention can effectively reduce the operating cost of the port power grid, while reducing carbon emissions and being more environmentally friendly.
[0220] Embodiment 2:
[0221] Please refer to Figure 3 , this embodiment 2 provides a closed-loop control system of a port multi-energy fusion system including flexible direct current, including:
[0222] A data collection unit, for acquiring the renewable energy output data and equipment power demand data of the port within a management cycle, wherein the renewable energy output data includes photovoltaic output data and wind turbine output data;
[0223] The model building unit constructs the objective function of minimum operation cost and the mathematical model including the system equipment constraint and the port power grid flow constraint based on the two bus sections; the operation cost includes the sum of the electricity purchase and sale cost, the hydrogen purchase cost and the operation and maintenance cost; the electricity purchase and sale cost includes the difference between the electricity purchase cost and the electricity sale cost; the operation and maintenance cost includes the sum of the photovoltaic operation and maintenance cost, the wind turbine operation and maintenance cost, the electrochemical energy storage operation and maintenance cost, the flexible DC equipment operation and maintenance cost and the hydrogen energy system operation and maintenance cost;
[0224] The solving unit substitutes the renewable energy output data and the equipment power demand data, solves the mathematical model, and obtains the energy management plan for the next cycle.
[0225] The solution output unit outputs the energy management solution.
[0226] The energy management scheme includes:
[0227] 1) Transfer of flexible DC equipment between bus section I and bus section II;
[0228] 2) The charging and discharging conditions and state of charge of electrochemical energy storage at each time point;
[0229] 3) The electricity purchase and sales situation in the external power grid market and the external hydrogen purchase situation.
[0230] In this embodiment, the specific contents of the objective function of the minimum operating cost and the mathematical model including the system equipment constraints and the port power grid flow constraints are as described in the first embodiment and will not be repeated here.
[0231] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention.
Claims
1. A closed-loop control method for a port multi-energy fusion system with flexible DC. It is characterized in that The port multi-energy fusion system includes two busbars connected by flexible DC equipment in different areas, and the two busbars are connected to an external power grid, renewable energy, electrical equipment, electrochemical energy storage, and a hydrogen energy system; the hydrogen energy system includes an electrolyzer that uses electrical energy to decompose water into hydrogen and oxygen, a hydrogen storage tank, and a hydrogen fuel cell that uses hydrogen to generate electricity; the closed-loop control method includes the following steps: S1, determine the energy management cycle; S2, obtaining the renewable energy output data and equipment power demand data of the port within a management cycle, wherein the renewable energy output data includes photovoltaic output data and wind turbine output data; S3, based on the two bus sections, construct an objective function of minimum operating cost and a mathematical model including system equipment constraints and port power grid flow constraints; the operating cost includes the sum of electricity purchase and sales cost, hydrogen purchase cost and operation and maintenance cost; the electricity purchase and sales cost includes the difference between electricity purchase cost and electricity sales cost; the operation and maintenance cost includes the sum of photovoltaic operation and maintenance cost, wind turbine operation and maintenance cost, electrochemical energy storage operation and maintenance cost, flexible DC equipment operation and maintenance cost and hydrogen energy system operation and maintenance cost; S4, substituting the renewable energy output data and the equipment power demand data, solving the mathematical model, and obtaining an energy management plan for the next cycle.
2. According to claim 1, a closed-loop control method for a port multi-energy fusion system with flexible direct current, It is characterized in that The objective function is as follows: my C=C BS +C BH +C OM Where: C is the total cost of port operation; C BS is the cost of electricity purchase and sale, C BH is the cost of purchasing hydrogen, C OM C is the operation and maintenance cost; H is the unit hydrogen purchase cost; C B is the electricity purchase price; P t B is the power purchased from the market at time t; C S is the electricity selling price; P t S is the power sold to the market at time t; is the hydrogen purchase rate at time t; C PV is the operation and maintenance cost per unit power of photovoltaic power, P t PV is the photovoltaic power generation power at time t; C WT is the operation and maintenance price per unit power of the wind turbine, P t WT is the power generation of the wind turbine at time t; C ES is the operation and maintenance price per unit power of electrochemical energy storage, is the electrochemical energy storage charging operating power at time t; is the discharge power of electrochemical energy storage at time t; C FLEX is the operation and maintenance price per unit power of the flexible DC equipment, P t FLEX is the operating power of the flexible DC equipment at time t; C EH is the operation and maintenance cost per unit power of the electrolyzer, is the operating power of the electrolytic cell at time t; C fue is the fuel cell unit power operation and maintenance cost, is the fuel cell operating power at time t.
3. According to claim 1, a closed-loop control method for a port multi-energy fusion system with flexible direct current, It is characterized in that The system device constraints include: The grid energy balance constraint ensures that the energy supply and equipment power demand on the two bus sections at any time maintain power balance; Hydrogen energy balance constraint, hydrogen energy can be kept balanced at any time; Electrolyzer constraints: The electrolyzer has ramp constraints and start-stop constraints, and the hydrogen production power of the electrolyzer needs to be kept within a certain range; Hydrogen storage tank constraints, which constrain the equivalent state of charge and hydrogen injection speed of the hydrogen storage tank; Hydrogen fuel cell constraints, constraining the output power of hydrogen fuel cells and the relationship between output power and hydrogen energy; Gateway energy exchange limit, setting the gateway exchange power limit between the two bus sections and the external power grid; Electrochemical energy storage constraints constrain the power transfer relationship during the power transfer process between the external power grid and the electrochemical energy storage; Flexible DC equipment constraints constrain the power transfer relationship of the flexible DC equipment during energy transfer between two bus sections.
4. According to claim 3, a closed-loop control method for a port multi-energy fusion system with flexible direct current, It is characterized in that The grid energy balance constraints are as follows: ΔP bus2 =P t B2 -P t S2 +P t WT2 -P t L2 +P t FLEX2 +P t fue =0 Where: ΔP bus1 and ΔP bus2 P is the net power flowing through section I and section II of the electric bus at time t; t B1 is the purchased power of bus section I at time t, P t B2 is the purchased power of bus section II at time t, P t S1 is the power sold by bus section I at time t, P t S2 P is the power sold by bus section II at time t; t PV is the photovoltaic output of bus section I at time t; P t WT1 and P t WT2 P is the fan output of busbar section I and busbar section II; t EH represents the power consumption of the electrolytic cell at time t; P is the charging power and discharging power of the electrochemical energy storage at the moment t of bus section I; t L1 and P t L2 P is the electric load power of bus section I and bus section II at time t; t FLEX1 is the transfer power of the flexible DC of bus section I at time t, P t FLEX2 is the transfer power of flexible DC of bus section II at time t; t fue Represents the discharge power of the hydrogen fuel cell at time t.
5. According to claim 3, a closed-loop control method for a port multi-energy fusion system with flexible direct current, It is characterized in that The hydrogen energy balance constraints are as follows: Where: is the hydrogen filling rate of the hydrogen storage tank; is the hydrogen consumption rate at time t; Indicates the hydrogen consumption rate of the hydrogen fuel cell, is the hydrogen production rate of the electrolyzer at time t, represents the hydrogen purchase rate at time t.
6. According to claim 3, a closed-loop control method for a port multi-energy fusion system with flexible direct current, It is characterized in that The electrolyser constraints are as follows: The electrolyzer has ramp constraints and start-stop constraints, and the hydrogen production power of the electrolyzer needs to be kept within a certain range. The hydrogen production power constraints of the electrolyzer are as follows: Where: is the hydrogen production power of the electrolyzer at time t; is the lower limit of hydrogen production power of electrolyzer, The upper limit of hydrogen production power for electrolyzers; Electrolyzer hydrogen production power The hydrogen production rate G EH The relationship is as follows: Where: K EH is the hydrogen production coefficient of the electrolyzer; η F is the Faraday efficiency; N EH is the number of electrolyzers in the electrolyzer array, z H is the number of moles of electrons transferred in the hydrogen reaction; F is the Faraday constant; U EH A constant terminal voltage maintained for the AC / DC converter; The start and stop constraints of the electrolyzer are as follows: Where: α EH Delay the start of the electrolyzer; They are respectively the start-up action and the start-up and shutdown action of the electrolytic cell; It is a 0-1 variable, indicating the switch state of the electrolytic cell; and They are the upper limits of the number of times the electrolyzer can be started and shut down in a day; The ramp power constraint of the electrolyzer is: Where: It is the maximum climbing power per unit time period when the electrolyzer is in the on state.
7. According to claim 3, a closed-loop control method for a port multi-energy fusion system with flexible direct current, It is characterized in that The hydrogen storage tank constraints are as follows: The equivalent state of charge of the hydrogen storage tank is: Where: W H is the maximum capacity of the hydrogen storage tank, SOH t is the hydrogen energy state of the hydrogen storage tank at time t; represents the hydrogen production rate of the electrolyzer at time t, is the hydrogen consumption rate at time t, represents the hydrogen purchase rate at time t, Indicates the hydrogen consumption rate of the hydrogen fuel cell; Constraints on equivalent state of charge of hydrogen storage tanks: SOH min ≤SOH t ≤SOH min Where: SOH min and SOH max They are the lower limit and upper limit of the equivalent state of charge of the hydrogen storage tank respectively; Hydrogen filling rate of hydrogen storage tank There are also restrictions: In the formula, G MAX Indicates the upper limit of the hydrogen filling rate of the hydrogen storage tank.
8. A closed-loop control method for a port multi-energy fusion system with flexible direct current according to claim 7, It is characterized in that The SOH min The value range is 0.1-0.3, the SOH max The value range is 0.8-0.
9.
9. According to claim 3, a closed-loop control method for a port multi-energy fusion system with flexible direct current, It is characterized in that The hydrogen fuel cell constraints are as follows: The relationship between hydrogen energy and output power is as follows: Where: is the output power of the hydrogen fuel cell at time t; z H is the number of moles of electrons transferred in the hydrogen reaction; N A is Avogadro's constant; m H is the molar mass of hydrogen; C 0 is the number of electrons per coulomb; U N,t is the rated output voltage at time t; η fue is the fuel cell conversion efficiency. Fuel cells also need to meet power constraints: Where: and They are respectively the lower and upper limits of the output power of hydrogen fuel cells.
10. The closed-loop control method of a port multi-energy fusion system with flexible direct current according to claim 1, It is characterized in that The port power grid flow constraints are as follows: Where P ij,t , Q ij,t is the active power and reactive power of the branch from node i to node j at time t; P jk,t Q jk,t is the active power and reactive power of the branch from node j to node k at time t; r ij x ij is the branch resistance and reactance from node i to j; I ij,t is the branch current from node i to node j at time t; V i,t is the voltage amplitude of node i at time t; r ij and x ij is the branch resistance and reactance from node i to j; U j,t is the square of the voltage at node j at time t; U i,t is the square of the voltage at node i at time t; L ij,t is the square of the current flowing from node i to node j at time t; · , Represents the lower and upper limits of a variable.
Citation Information
Patent Citations
Harbor-ship multi-energy fusion system
CN115693726A
Harbor-ship multi-energy fusion system and multi-level energy management method thereof
CN115693727A
Harbor district multi-energy fusion system and self-consistent operation method, equipment and medium thereof
CN116073411A
Multi-layer optimization method and system for operation mode of new energy access port power distribution network
CN116826864A
Port multi-energy fusion system capacity configuration optimization method
CN117787518A
Cited By