Coke oven hot repair combustion chamber protection structure and assembly method thereof
By using a rectangular protective structure and mechanized installation method in the coke oven combustion chamber, the problem of unstable temperature in the combustion chamber during maintenance is solved, the insulation effect and safety are improved, and the stability of the wall is ensured.
Patent Information
- Application Number
- CN202410828267.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-25
- Publication Date
- 2024-10-11
AI Technical Summary
It is difficult to effectively maintain temperature stability in the coke oven combustion chamber during the maintenance process, causing the refractory material to cool down and deform, affecting the maintenance effect and safety.
A rectangular protective structure welded by channel steel is used, including a white steel plate structure, high-temperature-resistant insulation materials and fixtures. The thermal insulation effect of the combustion chamber is ensured through mechanized installation methods. Universal guide wheels and hook structures are used to achieve mechanized thermal insulation.
It improves the thermal insulation effect of the combustion chamber, improves the efficiency and safety of thermal repair, avoids damage to the wall caused by temperature changes, and ensures the stability of the wall above the damage point.
Smart Images

Figure CN118755488A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coke oven maintenance, and in particular to a coke oven thermal repair combustion chamber protection structure and an assembly method thereof. Background Art
[0002] Coke oven is the core equipment in the coke production process. It is a thermal equipment with complex structure and huge investment for long-term continuous production to make coke from coal distillation. Its designed production service life is generally 25 years. With the increase of the service life of coking production, the coke oven body will inevitably be damaged by aging. The main problems are as follows: the furnace wall bricks of the combustion chamber fall off, the front bricks of the furnace head bulge outward, the wall of the carbonization chamber peels off, the front of the furnace head and the ramp collapse, and the top bricks of the carbonization chamber break. These problems lead to leakage in the furnace, affecting normal production and even losing efficiency.
[0003] However, these problems are usually solved by hot repair methods such as spraying, welding, digging, ceiling, roof removal, etc., or a combination of several methods. Among them, roof removal is the most thorough way of repair. The process of roof removal repair of coke ovens requires coke oven shutdown, insulation and other supporting measures. Among them, maintaining the temperature of the wall of the coke oven combustion chamber is the core key issue and the key link to the success of the repair.
[0004] Therefore, it is of great significance to effectively maintain the temperature of the refractory material of the furnace wall of the combustion chamber adjacent to the maintenance area to maintain its stable performance. Summary of the invention
[0005] According to the above-mentioned technical problem of maintaining the wall temperature of the coke oven combustion chamber, a coke oven thermal repair combustion chamber protection structure and its assembly method are provided. The present invention mainly proposes a coke oven combustion chamber insulation mechanical structure and assembly method through innovation, effectively solves the shortcomings of artificial insulation of adjacent coke oven combustion chambers during the coke oven thermal repair process, avoids the cooling phase change and deformation of the refractory materials in adjacent combustion chambers, improves the thermal insulation effect of the combustion chamber furnace wall, improves the operating efficiency and safety, and improves the thermal repair effect.
[0006] The technical means adopted by the present invention are as follows:
[0007] A coke oven thermal repair combustion chamber protection structure is composed of a plurality of single protection structures, wherein the single protection structure comprises a rectangular protection structure outer frame welded by channel steel, the protection structure is welded on the protection structure frame, and the protection structure comprises a first layer of white steel plate structure close to the combustion chamber, a second layer of high temperature resistant structure and a third layer of fixing device in order outward.
[0008] Furthermore, the white steel plate structure is welded and fixed on the outer frame of the protection structure, and the white steel plate structure has the same size as the outer frame of the protection structure.
[0009] Furthermore, a plurality of hook structures are arranged on one side of the white steel plate structure, and a plurality of hanging ring structures are arranged on the opposite side of the white steel plate structure.
[0010] Furthermore, the high temperature resistant structure distributes the high temperature resistant materials on the white steel plate structure in a nine-square grid through the hook structure on the white steel plate structure.
[0011] Furthermore, the fixing device is pressed onto the second layer of high temperature resistant heat insulation material in a cross manner and welded to the outer frame of the protection structure, and the fixing device is a channel steel structure.
[0012] Furthermore, two pairs of universal guide wheels are arranged at the bottom of the protection structure.
[0013] Furthermore, the total height of the protective structure is less than or equal to the height of the carbonization chamber of the maintenance coke oven (h-0.15) meters.
[0014] The present invention also provides a method for assembling a coke oven thermal repair combustion chamber, comprising the following steps:
[0015] S1. Before the coke oven is removed for thermal repair and cooling, the area is calculated according to the number of combustion chambers corresponding to the repaired carbonization chamber, the size of the single protection structure of the combustion chamber of the coke oven is determined, and the corresponding number of protection structures for the combustion chambers of the coke oven are made;
[0016] S2. Install a hook structure on the coke push rod on the machine side, and a fixed pulley and a retracting and releasing control device of a steel rope with multiple rings on the top walkway position of the coke side of the hot repair carbonization chamber of the coke oven;
[0017] S3, after the coke pushing rod is moved to the coke side by the coke pushing car, the steel rope with multiple rings is passed through the fixed pulley on the furnace top, and the first ring on the steel rope is hung on the coke pushing rod hook device, and the other side is connected to the steel rope retracting and releasing control device on the coke side walkway;
[0018] S4. As the coke pusher moves and the steel rope moves toward the machine side, the coke oven thermal repair combustion chamber protection structures are installed in rows from top to bottom. The first protection structure is hooked on the steel rope, the second protection structure is hooked on the first protection structure hanging ring structure, and the third protection structure is hooked on the second protection structure hanging ring structure, and the installation is completed in sequence.
[0019] S5. After the installation of the combustion chamber protection structure of the coke oven thermal repair is completed, the head of the steel rope on the machine side is fixed to the carbonization chamber furnace frame on the machine side, and the protection structure is pressed against the furnace wall by the subsequent thermal repair matching fixing device until the thermal repair is completed and the oven is removed when it is restored to use.
[0020] Furthermore, the length of the steel rope in S2 is determined according to the length of the carbonization chamber.
[0021] Compared with the prior art, the present invention has the following advantages:
[0022] According to the existing technology and equipment conditions, the present invention realizes the transformation of combustion chamber insulation from manual to mechanized during the thermal repair of coke ovens, solves the practical problems of low efficiency of manual laying of thermal insulation materials, poor working environment, high safety risks, etc., is beneficial to improving the thermal insulation effect of thermal repair of coke ovens, improving the thermal repair efficiency, controlling the temperature of exposed wall surface to be above the crystal transformation point temperature at which the brick body is damaged, ensuring that the wall body is protected from damage by temperature changes, avoiding damage to adjacent walls by mechanical external forces, adding some equipment and instruments, and applying sufficient external force protection to the two adjacent walls, which has practical application value. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0024] Figure 1 It is an overall schematic diagram of the protection structure of the present invention.
[0025] Figure 2 It is a side view of the protection structure of the present invention.
[0026] In the figure: 1. Hook structure; 2. High temperature resistant insulation material; 3. Hanging ring structure; 4. Fixing device; 5. Protective structure frame; 6. Universal guide wheel; 7. White steel plate structure. DETAILED DESCRIPTION
[0027] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0028] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means intended to limit the present invention and its application or use. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit exemplary embodiments according to the present invention. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0030] Unless otherwise specifically stated, the relative arrangement of the parts and steps described in these embodiments, the numerical expressions and numerical values do not limit the scope of the present invention. At the same time, it should be clear that, for ease of description, the sizes of the various parts shown in the drawings are not drawn according to the actual proportional relationship. The technology, methods and equipment known to ordinary technicians in the relevant field may not be discussed in detail, but in appropriate cases, the technology, methods and equipment should be regarded as part of the authorization specification. In all examples shown and discussed here, any specific value should be interpreted as merely exemplary, rather than as a limitation. Therefore, other examples of exemplary embodiments may have different values. It should be noted that similar numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further discussed in subsequent drawings.
[0031] In the description of the present invention, it is necessary to understand that the directions or positional relationships indicated by directional words such as "front, back, up, down, left, right", "lateral, vertical, perpendicular, horizontal" and "top, bottom" are usually based on the directions or positional relationships shown in the drawings. They are only for the convenience of describing the present invention and simplifying the description. Unless otherwise specified, these directional words do not indicate or imply that the device or element referred to must have a specific direction or be constructed and operated in a specific direction. Therefore, they cannot be understood as limiting the scope of protection of the present invention: the directional words "inside and outside" refer to the inside and outside relative to the contours of each component itself.
[0032] For ease of description, spatially relative terms such as "above", "above", "on the upper surface of", "above", etc. may be used here to describe the spatial positional relationship between a device or feature and other devices or features as shown in the figure. It should be understood that spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation described in the figure. For example, if the device in the accompanying drawings is inverted, the device described as "above other devices or structures" or "above other devices or structures" will be positioned as "below other devices or structures" or "below their position devices or structures". Thus, the exemplary term "above" can include both "above" and "below". The device can also be positioned in other different ways (rotated 90 degrees or in other orientations), and the spatially relative descriptions used here are interpreted accordingly.
[0033] In addition, it should be noted that the use of terms such as "first" and "second" to limit components is only for the convenience of distinguishing the corresponding components. If not otherwise stated, the above terms have no special meaning and therefore cannot be understood as limiting the scope of protection of the present invention.
[0034] like Figure 1-2 As shown, the present invention provides a coke oven thermal repair combustion chamber protection structure, which includes a plurality of single-block protection structures, wherein the single-block protection structure includes a rectangular protection structure outer frame 5 welded by channel steel, and the protection structure is welded on the protection structure frame, and the protection structure includes a first layer of white steel plate structure 7 close to the combustion chamber, a second layer of high temperature resistant heat insulation material 2, and a third layer of fixing device 4 in order from outside;
[0035] The protection structure of the combustion chamber of the coke oven thermal repair is a rectangular structure, which is a square or rectangular structure welded by channel steel, and is composed of n single protection structures. The size of the single protection structure is determined by calculating the height and length of the carbonization chamber. The effective structure is 1 to 3 meters long and 0.5 to 2 meters wide. When in use, the total height of the protection structure is less than or equal to the height of the carbonization chamber being repaired (h-0.15) meters. The internal channel steel is evenly divided into a nine-square grid structure and welded on the outer frame 5 of the protection structure;
[0036] The first layer of white steel plate structure 7 can be the same size as the protective structure and fixed to the protective structure outer frame 5 by welding, or welded and fixed separately according to the size of the nine-square grid; the second layer of high temperature resistant heat insulation material 2 is arranged in a nine-square grid. The hook structure 1 evenly installed on the white steel plate structure 7 in advance is snapped on the white steel plate structure 7; the third layer of fixing device 4 uses channel steel and the like to press the high temperature resistant heat insulation material 2 and is welded to the rectangular structure outer frame 5.
[0037] The protective structure is a rectangular structure with a hook structure 1 on one side and a hanging ring structure 3 on the opposite side, which are welded to the corresponding channel steels. The second layer of high temperature resistant heat insulation material 2 can be stacked in multiple layers to improve the heat insulation effect. The third layer of fixing device 4 uses channel steel to press on the second layer of high temperature resistant heat insulation material 2 in a cross-shaped manner and is welded to the protective structure frame 5. At the bottom, there are two pairs of universal guide wheel groups 6 that can move in all directions.
[0038] The present invention also provides a method for assembling a coke oven thermal repair combustion chamber, comprising the following steps:
[0039] S1. Before the coke oven is removed for thermal repair and cooling, the area is calculated according to the number of combustion chambers corresponding to the repaired carbonization chamber, the size of a single piece of the protection structure for the combustion chamber of the coke oven is determined, and the corresponding number of protection structures for the combustion chamber of the coke oven is manufactured.
[0040] S2. Install a hook structure on the coke push rod on the machine side, and install a fixed pulley and a retracting and releasing control device for the steel rope with multiple rings on the top walkway position of the coke side of the hot repair carbonization chamber of the coke oven.
[0041] S3. After the coke pushing rod is moved to the coke side by the coke pushing car, the steel rope with multiple rings is passed through the fixed pulley on the furnace top and the first ring on the steel rope is hung on the coke pushing rod hook device, and the other side is connected to the steel rope retraction and release control device on the coke side walkway; the length of the steel rope is determined in advance according to the length of the carbonization chamber.
[0042] S4. As the coke pushing rod moves and the pulling steel rope moves toward the machine side, the coke oven thermal repair combustion chamber protection structures are installed in rows from top to bottom. The first single-block protection structure is hooked on the steel rope, the second single-block protection structure is hung on the first single-block protection structure hanging ring structure 3 through the hook structure 1, the third single-block protection structure is hung on the second single-block protection structure hanging ring structure 3 through the hook structure 1, and so on. The nth single-block protection structure is hung on the n-1th single-block protection structure hanging ring structure (n≥2) through the hook structure 1.
[0043] S5. After the installation of the protection structure of the combustion chamber of the coke oven thermal repair is completed, the head of the steel rope on the machine side is fixed to the furnace frame of the corresponding carbonization chamber on the machine side, and the structure is pressed against the furnace wall by the subsequent hot repair matching fixing device until the hot repair is completed and the oven is removed when it is restored to use.
[0044] Example 1
[0045] Taking the hot repair of a 7-meter coke oven as an example, the maintenance area is from the coke side oven door to the bottom of the first coal loading port:
[0046] 1. A square protective structure for the thermal repair combustion chamber of a coke oven is manufactured. The effective structure has a side length of 6.7 m. The first layer is a white steel plate structure 7 with a side length of 2.23 m, which is directly welded to the outer frame 5 of the protective structure. The second layer is a high-temperature resistant thermal insulation material 2 distributed in a nine-square grid divided by a side length of 2.23 m. Two pieces of high-temperature resistant thermal insulation material have a side length of 74 cm. Each protective structure is arranged in two layers with 18 pieces. The third-layer fixing device 4 uses channel steel to press the high-temperature resistant thermal insulation material 2 in a cross-shaped manner and is welded to the channel steel of the outer frame 5 of the protective structure.
[0047] 2. Before the coke oven is cooled and dismantled for hot repair, the area is calculated according to the number of combustion chambers corresponding to the repaired carbonization chamber, the size of a single piece of the protection structure of the hot repair combustion chamber of the coke oven is determined, and the corresponding number of protection structure parts for the hot repair combustion chamber of the coke oven are made.
[0048] 3. Install a hook structure on the coke push rod on the machine side, and determine the fixed pulley of the top walkway on the coke side of the hot repair carbonization chamber and the retraction and release control device of the steel rope with multiple rings.
[0049] 4. After the coke pushing rod is moved to the coke side by the coke pushing car, the steel rope with multiple rings is passed through the fixed pulley on the furnace top and the first ring on the steel rope is hung on the coke pushing rod hook device, and the other side is connected to the steel rope retraction and release control device on the coke side walkway; the length of the steel rope is determined in advance according to the length of the carbonization chamber.
[0050] 5. As the coke pusher moves and the traction steel rope moves toward the machine side, the coke oven thermal repair combustion chamber protection structure is installed in rows from top to bottom. The first single protection structure is hooked on the steel rope, the second single protection structure is hung on the first single protection structure hanging ring structure 3 through the hook structure 1, the third single protection structure is hung on the second single protection structure hanging ring structure 3 through the hook structure 1, and so on. The nth single protection structure is hung on the n-1th single protection structure hanging ring structure (n≥2) through the hook structure 1. Determine the number of coke oven thermal repair combustion chamber protection parts to be used according to the thermal repair size.
[0051] 6. After the installation of the protective structural parts of the combustion chamber of the coke oven thermal repair is completed, the head of the steel rope on the machine side is fixed to the furnace frame of the corresponding carbonization chamber on the machine side, and the structural parts are pressed against the furnace wall by the subsequent hot repair matching fixing device until the hot repair is completed and the oven is removed when it is restored to use.
[0052] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A coke oven thermal repair combustion chamber protection structure, characterized in that: The invention is composed of a plurality of single-block protective structures, wherein the single-block protective structure comprises a rectangular protective structure outer frame (5) welded by channel steel, the protective structure is welded on the protective structure frame, and the protective structure comprises a first layer of white steel plate structure (7) close to the combustion chamber, a second layer of high-temperature resistant heat-insulating material (2), and a third layer of fixing device (4) in order from the outside to the outside.
2. The coke oven thermal repair combustion chamber protection structure according to claim 1 is characterized in that: The white steel plate structure (7) is welded and fixed on the protective structure outer frame (5); the white steel plate structure (7) and the protective structure outer frame (5) have the same size.
3. The coke oven thermal repair combustion chamber protection structure according to claim 1, characterized in that: A plurality of hook structures (1) are arranged on one side of the white steel plate structure (7), and a plurality of hanging ring structures (3) are arranged on the opposite side of the white steel plate structure (7).
4. The coke oven thermal repair combustion chamber protection structure according to claim 3 is characterized in that: The high temperature resistant structure distributes the high temperature resistant heat insulating material (2) on the white steel plate structure (7) in a nine-square grid pattern through the hook structure (1) on the white steel plate structure (7).
5. The coke oven thermal repair combustion chamber protection structure according to claim 1, characterized in that: The fixing device (4) is pressed onto the second layer of high temperature resistant heat insulation material (2) in a cross manner and welded onto the protective structure outer frame (5); the fixing device (4) is a channel steel structure.
6. The coke oven thermal repair combustion chamber protection structure according to claim 1, characterized in that: Two pairs of universal guide wheels (6) are arranged at the bottom of the protection structure.
7. The coke oven thermal repair combustion chamber protection structure according to claim 1, characterized in that: The total height of the protective structure is less than or equal to the height of the carbonization chamber of the maintenance coke oven (h-0.15) meters.
8. A method for assembling a coke oven thermal repair combustion chamber, which is implemented based on the coke oven thermal repair combustion chamber protection structure according to any of claims 1 to 7, comprising the following steps: S1. Before the coke oven thermal repair and cooling dismantling, calculate the area according to the number of carbonization chambers and combustion chambers to be repaired, determine the size of the single-piece protection structure of the coke oven thermal repair combustion chamber, and make the corresponding number of protection structures for the coke oven thermal repair combustion chambers; S2. Install a hook structure on the coke push rod on the machine side, and fix a pulley and a steel rope retracting and releasing control device with multiple rings on the top walkway position of the coke side of the hot repair carbonization chamber of the coke oven; S3, after the coke pushing rod is moved to the coke side by the coke pushing car, the steel rope with multiple rings is passed through the fixed pulley on the furnace top, and the first ring on the steel rope is hung on the coke pushing rod hook device, and the other side is connected to the steel rope retracting and releasing control device on the coke side walkway; S4. As the coke pusher moves and the steel rope moves toward the machine side, the coke oven thermal repair combustion chamber protection structures are installed in order from top to bottom. The hook structure (1) of the first protection structure is hooked on the steel rope, the second protection structure is hooked on the first protection structure hanging ring structure (3) through the hook structure (1), and the third protection structure is hooked on the second protection structure hanging ring structure (3) through the hook structure (1), and the installation is completed in order. S5. After the installation of the combustion chamber protection structure of the coke oven thermal repair is completed, the head of the steel rope on the machine side is fixed to the carbonization chamber furnace frame on the machine side, and the protection structure is pressed against the furnace wall by the subsequent thermal repair matching fixing device until the thermal repair is completed and the oven is removed when it is restored to use.
9. The method for assembling a coke oven thermal repair combustion chamber according to claim 8, characterized in that: The length of the steel rope in S2 is determined according to the length of the carbonization chamber.