Built-in drainage system of basement bottom plate and construction method
By building a drainage system in the basement floor, including a slope layer, a pressure groove and a drainage pipe, the problem of water accumulation and blockage on the garage floor is solved, independent drainage and smoothness are achieved, rework and waste of manpower and material resources are reduced, and the efficiency is improved Quality of use.
Patent Information
- Application Number
- CN202411089936.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-10-11
Smart Images

Figure CN118756735A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of basement drainage, and in particular to a basement floor built-in drainage system and a construction method thereof. Background Art
[0002] In traditional construction, the garage floor is grooved against the wall with an open ditch and no slope on the surface, which leads to three problems:
[0003] (1) Water accumulated on the garage floor surface (such as clean water, dehumidifier leakage, and visible water caused by leakage) cannot be discharged and can only be cleaned manually;
[0004] (2) Open ditch drainage causes a lot of garbage to enter the ditch, blocking the buried drainage pipes in the pressure trough or door aisle, resulting in ditch blockage and the inability to drain the accumulated water;
[0005] (3) The slope of trench construction is affected by the length. If the distance from the collection well is too far, the accumulated water will not be able to be discharged.
[0006] Therefore, the present invention designs a basement floor built-in drainage system and a construction method thereof. Summary of the invention
[0007] The purpose of the present invention is to solve the problems in the prior art and to propose a basement floor built-in drainage system.
[0008] A basement floor built-in drainage system, comprising:
[0009] The base plate drainage part includes:
[0010] A slope leveling layer, wherein the slope leveling layer is provided with a slope and slopes toward one side of the wall surface;
[0011] A pressing groove, wherein the pressing groove is arranged on a side close to the wall surface;
[0012] A plurality of drainage pipes, one end of each drainage pipe is connected to the bottom of the pressure groove through a floor drain, and the plurality of drainage pipes are fixed to the concrete layer through steel bars and brackets;
[0013] The garage floor drainage part is located on the upper side of the drainage part of the foundation bottom plate, and the garage floor drainage includes:
[0014] Floor layer;
[0015] Drainage trough, wherein the second drainage trough is provided at the bottom of the floor layer and extends upward along the direction of the groove pressing;
[0016] A hydrophobic layer is laid on top of the slope layer and the floor layer is laid on the hydrophobic layer.
[0017] A plurality of floor drains 2, each of which is arranged at equal distances and has a connecting pipe connected to the bottom;
[0018] A water collection well, to which the drainage pipe is connected.
[0019] In the above-mentioned built-in drainage system in the basement floor, the slope of the slope layer 1 is 0.5%, and the drainage trough is located around the floor drain 2 to perform slope adjustment in the range of 500*500mm with a slope of 5%, sloping toward the floor drain 2.
[0020] In the above-mentioned built-in drainage system in the basement floor, a filter stone layer is laid in the drainage trough, the filter stone layer is connected to the hydrophobic layer, and the bottom of the connecting pipe is connected to the filter stone layer.
[0021] In the built-in drainage system of the basement floor, a floor drain is placed every 30m along the drainage ditch.
[0022] In the above-mentioned built-in drainage system in the basement floor, the filter stone layer is filter stone with a particle size of 20-30 mm.
[0023] In the above-mentioned built-in drainage system in the basement floor, the depth of the drainage pipe extending into the water collection well is not less than 30 mm.
[0024] A construction method for a built-in drainage system in a basement floor, including a construction method for a drainage part of a basement floor and a construction method for a drainage part of a garage floor, wherein the construction method for the drainage part of the basement floor comprises the following steps:
[0025] Step 1: Welding the steel bar support, the specific operations include:
[0026] S1: Tie the steel bars on the lower side of the bottom plate, and make the steel bar bracket of the bottom plate slope layer in advance;
[0027] S2: According to the slope and direction of the bottom plate, weld the steel support in sequence, with the spacing between the support bars being 1500mm; the welding of the support bars should ensure the stability of the upper steel bars;
[0028] S3: With the center line of the vehicle passage as the highest point, slope is set on both sides. The lowest point of the slope is the original design height of the bottom plate. The lowest point is set at the side of the parking space away from the lane or 100mm away from the root of the structural wall column. The slope is 0.5%;
[0029] Step 2: Bury and fix the drainage pipe. The specific operations include:
[0030] S1: The drainage pipe is buried in the middle of the steel bars connected to the bottom plate, one end of which is connected to the floor drain 1 on the bottom plate surface layer, and the other end is connected to the water collection well;
[0031] S2: Floor drains and drainage pipes are installed every 60m, with at least one on each wall;
[0032] S3: The drainage pipe is fixed with a steel bar welded bracket, and the drainage pipe is slightly tilted from the floor drain to the water collection well during fixing;
[0033] S4: After the burial is completed, the end openings of the drainage pipes need to be sealed with tape to prevent subsequent concrete pouring from causing blockage in the pipes.
[0034] Step 3: Tie the upper layer of steel bars on the bottom plate, and tie the upper layer of steel bars in the same way as the lower layer. Use welded brackets to control the elevation of the upper layer of steel mesh to follow the slope change.
[0035] Step 4: Support the groove formwork at the root of the structural wall column. After the reinforcement is tied, use wooden planks to support the groove formwork along the root 100mm away from the root of the structural wall column. The groove is 100mm wide and 20mm high.
[0036] In the present invention, four preventive measures are made in the drainage part of the foundation bottom plate, which are formed in one piece:
[0037] (1) A lane and the two sides of the lane immediately adjacent to it are considered a drainage unit;
[0038] (2) A blind pipe is pre-buried in the foundation slab and connected to the ground on the slab surface, with one end connected to the water collection well through a drainage pipe;
[0039] (3) The steel bar structure of the foundation bottom plate is sloped and fixed by welding steel bar brackets;
[0040] (4) A wooden groove is set at the lowest point.
[0041] In the above-mentioned construction method of the built-in drainage system of the basement floor, the construction method of the garage floor drainage part includes the following steps:
[0042] Step 1: Clean the base layer, clean the dust, mortar skin, and concrete residue on the base layer, and then rinse it with clean water;
[0043] Step 2: Apply the drainage trough and use cement mortar to extend the side wall of the original bottom plate from the original 20mm height to about 70mm height;
[0044] Step 3: Place filter stones in the drainage trough. When the mortar strength of the drainage trough side wall is such that there is no mark left after extrusion, place filter stones with a particle size of 20-30mm in the trough to form a filter stone layer, and stack them uniformly until they are flush with the side wall of the drainage trough.
[0045] Step 4: Lay a hydrophobic layer on top of the base plate;
[0046] Step 5: Lay non-woven fabric. To ensure that the concrete does not flow into the hydrophobic layer during the subsequent floor pouring process, a layer of non-woven fabric needs to be laid on the top of the hydrophobic layer.
[0047] Step 6: Install the second floor drain. Place one second floor drain every 30m along the drainage trough. Connect a 50mm diameter connecting pipe at the bottom of the second floor drain directly to the filter stone layer, so as to ensure that the accumulated water in the basement can flow to the water collection well through the second floor drain on the floor, the connecting pipe, the filter stone layer, the drainage trough, the first floor drain and its pre-buried drainage pipe;
[0048] Step 7: Basement floor construction;
[0049] Step 8: When pouring the floor concrete, find the slope with floor drain 2 as the center.
[0050] The advantages are: this system can drain the seepage of the foundation slab from the source, and use the drainage measures in the foundation slab structure layer and the garage slab floor pouring to form a drainage system for the garage slab. Through the combination of drainage and drainage, the cracking of the garage slab is reduced by 80%. It can almost avoid the rework caused by the cracking of the slab in the later stage and the phenomenon of chiseling out the upper part of the structural slab and reburying the drainage pipe for drainage, reduce the waste of manpower and material resources, ensure the quality of residential use, prevent the occurrence of garage slab seepage, achieve beauty, unobstructed drainage and prevention of seepage and many other problems, and solve the garage drainage problem from the root. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] Figure 1 The present invention is a schematic structural diagram of a basement floor built-in drainage system.
[0052] Figure 2 for Figure 1 Enlarged schematic diagram of part A.
[0053] In the figure: 101 slope layer, 102 pressure groove, 103 drainage pipe, 104 floor drain 1, 201 floor layer, 202 drainage groove, 203 drainage layer, 204 floor drain 2, 205 connecting pipe, 206 filter stone layer, 3 water collection wells. DETAILED DESCRIPTION
[0054] Reference Figure 1-2 , a basement floor built-in drainage system, comprising:
[0055] The drainage part of the foundation slab includes:
[0056] The slope layer 101 is provided with a slope and slopes toward one side of the wall surface, and the slope of the slope layer 101 is 0.5%;
[0057] A pressing groove 102, wherein the pressing groove 102 is arranged on a side close to the wall surface;
[0058] Multiple drainage pipes 103, one end of each drainage pipe 103 is connected to the bottom of the pressure groove 102 through a floor drain 104, and multiple drainage pipes 103 are fixed to the concrete layer through steel bars and brackets. The depth of the drainage pipe 103 extending into the water collection well 3 is not less than 30mm;
[0059] The garage floor drainage part is located on the upper side of the drainage part of the foundation slab. The garage floor drainage includes:
[0060] Floor level 201;
[0061] Drain trough 202, drainage trough 202 is opened at the bottom of the floor layer 201 and extends upward along the direction of the pressure groove 102. Drain trough 202 is located around floor drain 204 and slopes in the range of 500*500mm. The slope is 5% and slopes toward floor drain 204. A filter stone layer 206 is laid in the drainage trough 202. The filter stone layer 206 is a filter stone with a particle size of 20-30mm. The filter stone layer 206 is connected to the hydrophobic layer 203, and the bottom of the connecting pipe 205 is connected to the filter stone layer 206;
[0062] The hydrophobic layer 203 is laid on the top of the slope layer 101 and the floor layer 201 is laid on the hydrophobic layer 203.
[0063] A plurality of floor drains 204 are arranged at equal distances and connected to a connecting pipe 205 at the bottom, and a floor drain 204 is placed every 30m along the drainage trough 202;
[0064] The water collection well 3 , to which the drainage pipe 103 is connected.
[0065] The construction method of the drainage part of the foundation slab includes the following steps:
[0066] Step 1: Welding the steel bar support, the specific operations include:
[0067] S1: Tie the steel bars on the lower side of the bottom plate, and make the steel bar bracket of the bottom plate slope layer in advance;
[0068] S2: According to the slope and direction of the bottom plate, weld the steel support in sequence, with the spacing between the support bars being 1500mm; the welding of the support bars should ensure the stability of the upper steel bars;
[0069] S3: With the center line of the vehicle passage as the highest point, slope is set on both sides. The lowest point of the slope is the original design height of the bottom plate. The lowest point is set at the side of the parking space away from the lane or 100mm away from the root of the structural wall column. The slope is 0.5%;
[0070] Step 2: burying and fixing the drainage pipe 103, the specific operations include:
[0071] S1: The drainage pipe 103 is buried in the middle of the steel bars connected to the bottom plate, one end of which is connected to the floor drain 104 on the bottom plate surface, and the other end is connected to the water collection well 3. Generally, the drainage pipe 103 buried in the bottom plate of the basement of the civil air defense part is a JDG pipe, and the drainage pipe 103 buried in the bottom plate of the basement of the non-civil air defense part is a PVC pipe;
[0072] S2: Floor drain 104 and drainage pipe 103 are set every 60m, at least one on each wall;
[0073] S3: The drainage pipe 103 is fixed by welding a bracket with waste short steel bars, and the drainage pipe 103 is slightly tilted from the floor drain 104 to the water collection well 3 during the fixing process;
[0074] S4: After the burial is completed, the end of the drainage pipe 103 needs to be sealed with tape to prevent subsequent concrete pouring from causing blockage in the pipe.
[0075] Step 3: Tie the upper layer of steel bars on the bottom plate, and tie the upper layer of steel bars in the same way as the lower layer. Use welded brackets to control the elevation of the upper layer of steel mesh to follow the slope change.
[0076] Step 4: Support the formwork of the groove 102 at the root of the structural wall column. After the reinforcement is tied, use wooden planks to support the formwork of the groove 102 along its root at a position 100mm away from the root of the structural wall column. The groove 102 is 100mm wide and 20mm high.
[0077] For the drainage part of the foundation bottom plate, the present invention takes four measures:
[0078] (1) A lane and the two sides of the lane immediately adjacent to it are considered a drainage unit;
[0079] (2) A blind pipe is pre-buried in the foundation slab and connected to the ground on the slab surface, with one end connected to the water collection well through a drainage pipe;
[0080] (3) The steel bar structure of the foundation bottom plate is sloped and fixed by welding steel bar brackets;
[0081] (4) A wooden groove is set at the lowest point.
[0082] This method is mainly to prevent water seepage from the foundation bottom plate surface and the interior. Once there is a possibility of water seepage, the water can be discharged to the collection well 3 through the floor drain 104 through the system.
[0083] The construction method of the garage floor drainage part includes the following steps:
[0084] Step 1: Clean the base layer, clean the dust, mortar skin, and concrete residue on the base layer, and then rinse it with clean water;
[0085] Step 2: Apply the drainage groove 202, and use cement mortar to extend the side wall of the groove 102 of the original bottom plate from the original 20mm height to about 70mm height;
[0086] Step 3: Place filter stones in the drainage trough 202. When the mortar strength of the side wall of the drainage trough 202 is such that there is no mark left after extrusion, place filter stones with a particle size of 20-30 mm in the trough to form a filter stone layer 206, and stack them uniformly to be flush with the side wall of the drainage trough 202.
[0087] Step 4: Laying a hydrophobic layer 203 on the bottom plate;
[0088] Step 5: Lay non-woven fabric. To ensure that the concrete does not flow into the hydrophobic layer during the subsequent floor pouring process, a layer of non-woven fabric needs to be laid on the top of the hydrophobic layer.
[0089] Step 6: Install the second floor drain 204, and place one second floor drain 204 every 30m along the drainage groove 202. The lower part of the second floor drain is connected to a connecting pipe 205 with a diameter of 50mm, which directly passes to the filter stone layer 206, so as to ensure that the accumulated water in the basement can flow to the water collection well 3 through the second floor drain 204 on the floor, the filter stone layer, the drainage groove 202, the first floor drain 104 and the pre-buried drainage pipe 103;
[0090] Step 7: Basement floor construction;
[0091] Step 8: When pouring the floor concrete, find the slope with floor drain 204 as the center.
[0092] The above approach solves the drainage problems of traditional basement floors, and achieves many problems such as aesthetics, smooth drainage, and prevention of water accumulation, thus solving the garage drainage problem from the root.
[0093] It is known from common technical knowledge that the present invention can be implemented by other embodiments that do not deviate from its spirit or essential features. Therefore, the above disclosed embodiments are only illustrative in all respects and are not exclusive. All changes within the scope of the present invention or within the scope equivalent to the present invention are included in the present invention.
Claims
1. A basement floor built-in drainage system, characterized in that: include: The base plate drainage part includes: A slope leveling layer (101), wherein the slope leveling layer (101) is provided with a slope and slopes toward one side of the wall surface; A pressing groove (102), wherein the pressing groove (102) is arranged on a side close to the wall surface; A plurality of drainage pipes (103), one end of each drainage pipe (103) is connected to the bottom of the pressure groove (102) through a floor drain (104), and the plurality of drainage pipes (103) are fixed to the concrete layer through steel bars and brackets; The garage floor drainage part is located on the upper side of the drainage part of the foundation bottom plate, and the garage floor drainage includes: Floor layer (201); A drainage trough (202), wherein the drainage trough (202) is provided at the bottom of the floor layer (201) and extends upward along the direction of the pressed groove (102); A hydrophobic layer (203), wherein the hydrophobic layer (203) is laid on the top of the slope layer (101) and the floor layer (201) is laid on the hydrophobic layer (203). A plurality of second floor drains (204), each of the second floor drains (204) being arranged at equal distances and having a connecting pipe (205) connected to the bottom; A water collection well (3), wherein the drainage pipe (103) is connected to the water collection well (3).
2. The basement floor built-in drainage system according to claim 1, characterized in that: The slope gradient of the first slope layer (101) is 0.5%, and the drainage groove (202) is located around the second floor drain (204) and slopes in a range of 500*500mm with a slope gradient of 5%, sloping toward the second floor drain (204).
3. The basement floor built-in drainage system according to claim 1, characterized in that: A filter stone layer (206) is laid in the drainage trough (202), the filter stone layer (206) is connected to the hydrophobic layer (203), and the bottom of the connecting pipe (205) is connected to the filter stone layer (206).
4. The basement floor built-in drainage system according to claim 1, characterized in that: A floor drain (204) is placed (1) every 30 m along the drainage ditch (202).
5. The basement floor built-in drainage system according to claim 4, characterized in that: The filter stone layer (206) is filter stone with a particle size of 20-30 mm.
6. The basement floor built-in drainage system according to claim 4, characterized in that: The drainage pipe (103) extends into the water collection well (3) to a depth of not less than 30 mm.
7. The construction method of the basement floor built-in drainage system according to any one of claims 1 to 6, characterized in that: The construction method includes a construction method of a drainage part of a foundation bottom plate and a construction method of a drainage part of a garage floor, and the construction method of the drainage part of the foundation bottom plate includes the following steps: Step 1: Welding the steel bar support, the specific operations include: S1: Tie the steel bars on the lower side of the bottom plate, and make the steel bar bracket of the bottom plate slope layer in advance; S2: According to the slope and direction of the bottom plate, weld the steel support in sequence, with the spacing between the support bars being 1500mm; the welding of the support bars should ensure the stability of the upper steel bars; S3: With the center line of the vehicle passage as the highest point, slope is set on both sides. The lowest point of the slope is the original design height of the bottom plate. The lowest point is set at the side of the parking space away from the lane or 100mm away from the root of the structural wall column. The slope is 0.5%; Step 2: burying and fixing the drainage pipe (103), the specific operations include: S1: The drainage pipe (103) is buried in the middle of the steel bars connected to the bottom plate, one end of which is connected to the floor drain 1 (104) on the bottom plate surface layer, and the other end is connected to the water collection well (3); S2: Floor drains (104) and drainage pipes (103) are installed every 60m, with at least one on each wall; S3: The drainage pipe (103) is fixed by using a steel bar welding bracket, and during the fixing process, the drainage pipe (103) is ensured to be slightly tilted from the floor drain (104) to the water collection well (3); S4: After the burial is completed, the end of the drainage pipe (103) needs to be sealed with tape to prevent subsequent concrete pouring from causing blockage in the pipe. Step 3: Tie the upper layer of steel bars on the bottom plate, and tie the upper layer of steel bars in the same way as the lower layer. Use welded brackets to control the elevation of the upper layer of steel mesh to follow the slope change. Step 4: Formwork for the groove (102) at the root of the structural wall column. After the reinforcement is tied, use wooden planks to support the groove (102) template along the root of the structural wall column at a position 100 mm away from the root. The groove (102) is 100 mm wide and 20 mm high.
8. The construction method of a basement floor built-in drainage system according to claim 7, characterized in that: The construction method of the garage floor drainage part comprises the following steps: Step 1: Clean the base layer, clean the dust, mortar skin, and concrete residue on the base layer, and then rinse it with clean water; Step 2: Apply the drainage groove (202), and use cement mortar to extend the side wall of the groove (102) of the original bottom plate from the original 20mm height to about 70mm height; Step 3: Filter stones are placed in the drainage trough (202). When the mortar strength of the side wall of the drainage trough (202) is such that there is no mark left after extrusion, filter stones with a particle size of 20-30 mm are placed in the trough to form a filter stone layer (206), and the filter stones are uniformly stacked to be flush with the side wall of the drainage trough (202); Step 4: Laying a hydrophobic layer (203) on the bottom plate; Step 5: Lay non-woven fabric. To ensure that the concrete does not flow into the hydrophobic layer during the subsequent floor pouring process, a layer of non-woven fabric needs to be laid on the top of the hydrophobic layer. Step 6: Install the second floor drain (204), place (1) second floor drain (204) every 30m along the drainage groove (202), and connect the lower part of the second floor drain (204) with a connecting pipe (205) with a diameter of 50mm directly to the filter stone layer (206), so as to ensure that the basement seepage water can flow to the water collection well (3) through the second floor drain (204) on the floor, the connecting pipe (205), the filter stone layer (206), the drainage groove (202), the first floor drain (104) and the pre-buried drainage pipe (103); Step 7: Basement floor construction; Step 8: When pouring the floor concrete, find the slope with the second floor drain (204) as the center.