Winter construction heat preservation method for superimposed reinforced high-rise fabricated building

By using electric roller shutter insulation blankets and heating humidifiers during winter construction of high-rise buildings, combined with integrated attached lifting scaffolding and aluminum mold models, fast and safe construction insulation is achieved, solving the problem of installing insulation materials in winter construction of high-rise buildings Issues of low efficiency and fire safety hazards improve concrete strength and insulation quality.

CN118756980APending Publication Date: 2024-10-11CHINA MCC17 GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411029675.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

The winter construction insulation method of high-rise buildings involves a large amount of labor requirements, slow concrete strength growth caused by dry air, fire safety hazards and quality problems of cold bridge insulation. It is difficult to carry out construction insulation quickly, safely and effectively with existing technology.

Method used

Use vertical and flat electric roller shutter insulation blanket devices and heating and humidifiers for standard curing rooms. Temperature and humidity are controlled through synchronous roller shutter electric motors and heating and humidifiers to ensure the insulation and maintenance of concrete. Combined with integrated attached lifting scaffolding and aluminum formwork models for segmented construction.

Benefits of technology

It significantly improves the installation efficiency of construction insulation devices, ensures construction safety, solves the slow growth of concrete strength and fire safety hazards, reduces construction costs and time, and improves the quality of insulation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118756980A_ABST
    Figure CN118756980A_ABST
Patent Text Reader

Abstract

The invention discloses a method for overlapping and enhancing winter construction heat preservation of a high-rise fabricated building, and belongs to the technical field of winter heat preservation construction of high-rise buildings. Comprising the steps of building a high-rise building, an aluminum mold, a tower crane, a construction hoist and an integrated attached type lifting scaffold model, manufacturing a vertical face electric roller shutter heat preservation blanket device and a plane electric roller shutter heat preservation blanket device, installing a synchronous roller shutter electric motor, installing a heat preservation blanket winding drum, conducting power-on debugging and adjusting, and installing a heating and humidifying device for a standard curing room. And after concrete is poured in sections, the vertical face electric roller shutter heat preservation blanket device and a heat preservation blanket of the plane electric roller shutter heat preservation blanket device are opened, heat preservation maintenance and material transportation are conducted, and the heat preservation blanket of the plane electric roller shutter heat preservation blanket device is rolled up before the integrated attachment type lifting scaffold is lifted. The invention solves the technical problems of high-rise building fire prevention, long construction progress, long mounting and dismounting time, high cost, difficulty in heat preservation and potential fire safety hazards.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of winter construction insulation of high-rise buildings, and in particular relates to a winter construction insulation method for superimposed reinforced high-rise assembled buildings. Background Art

[0002] At present, the insulation method for high-rise building construction in winter is to use insulation materials to block door and window openings, cover the floor with insulation materials to form a greenhouse, and use heaters and coke ovens to heat the greenhouse. The disadvantages of this installation method are: the installation of insulation materials requires a lot of manpower, the air is dry in winter in the north, and the low humidity in the greenhouse affects the maintenance of concrete, the strength increases slowly, and the concrete strength cannot meet the requirements of aluminum mold removal, construction elevators, tower crane wall supports and wall rods, and integrated attached lifting scaffolding wall supports. The fire prevention and construction progress of high-rise buildings must be comprehensively considered. The installation takes a long time and the cost is high. In addition, the facade structure of high-rise buildings is prone to cold bridges and insulation quality problems. The heating of heaters and coke ovens poses a fire safety hazard. Summary of the invention

[0003] The purpose of the present invention is to provide a winter construction insulation method for laminated reinforced high-rise assembled buildings, which is safe and reliable to use, and can quickly, safely and effectively carry out winter construction insulation of high-rise buildings, and the concrete insulation maintenance and mold removal insulation materials can be carried out smoothly, ensuring construction safety.

[0004] In order to solve the above technical problems, the inventors have obtained the technical solution of the present invention through practice and summary. The present invention discloses a winter construction insulation method for a laminated reinforced high-rise prefabricated building, comprising the following steps:

[0005] Step 1: Build models of high-rise buildings, aluminum formwork, tower cranes, construction elevators, and integrated attached lifting scaffolding before installation;

[0006] Step 2: According to the outer dimensions of the integrated attached lifting scaffold, the scaffold is at least two floors high; and the facade of the high-rise building is segmented to produce a facade electric roller curtain insulation blanket device and a flat electric roller curtain insulation blanket device;

[0007] Step 3: The facade electric roller shutter insulation blanket device first installs a synchronous roller shutter electric motor on the periphery of the integrated attached lifting scaffolding, installs the insulation blanket reel that is pre-rolled up according to the height of two floors, and connects the synchronous roller shutter electric motor to the power supply;

[0008] Step 4: The flat electric roller blind insulation blanket device is first installed at both ends of the integrated attached lifting scaffolding and the short sides are equipped with synchronous roller blind electric motors;

[0009] Install the insulation blanket drum that is pre-rolled up to half the length of the long side, and connect the synchronous roller blind electric motor to the power supply;

[0010] Step 5: Power on and debug, adjust the facade electric roller blind insulation blanket device and the flat electric roller blind insulation blanket device until they meet the insulation and maintenance requirements;

[0011] Step 6: Install the heating and humidifying device for the standard curing room symmetrically on the walkway boards around the integrated attached lifting scaffolding. Connect the heating and humidifying device for the standard curing room to the water source and power supply, and turn on the water and electricity for debugging and adjustment until the heating and humidifying device for the standard curing room meets the requirements of insulation and maintenance. After the concrete is poured in sections, start the electric motor in sections to open the facade electric roller curtain insulation blanket device and the plane electric roller curtain insulation blanket device to drive the insulation blanket, and start the heating and humidifying device for the standard curing room for insulation and maintenance until the maintenance is completed;

[0012] Before material transportation and integrated attached lifting scaffolding are lifted, the electric motor is started in sections to roll up the flat electric roller curtain insulation blanket device to drive the insulation blanket and stop the operation of the heating and humidifier in the standard curing room.

[0013] In a further technical solution, the temperature of the insulation device during winter construction is 20℃±2℃ and the relative humidity is controlled at 95%-98%.

[0014] In a further technical solution, the aluminum mold is installed in a high-rise building through an installation pin; and the aluminum mold is installed on the top of the synchronous roller shutter electric motor.

[0015] In a further technical solution, the upper part of the insulation blanket drum is connected to the end of the synchronous rolling curtain electric motor; the end of the synchronous rolling curtain electric motor away from the insulation blanket drum is connected to the flat electric rolling curtain insulation blanket device; the flat electric rolling curtain insulation blanket device is suitable for being fixed in a high-rise building.

[0016] In a further technical solution, the facade electric roller shutter insulation blanket device is installed on the side of the insulation blanket drum facing away from the high-rise building, and the height is higher than the laying height of the corresponding high-rise building.

[0017] In a further technical solution, a steel pipe is installed on the walkway board and is connected to the facade electric roller shutter insulation blanket device; and a hook is installed at the bottom of the walkway board, a connecting rope is installed on the hook, and the top of the integrated attached lifting scaffolding is connected at the bottom.

[0018] In a further technical solution, a pulley block is installed at the bottom of the integrated attached lifting scaffold, and is connected to the corresponding walkway board at the bottom by ropes.

[0019] Compared with the prior art, the present invention can achieve the following technical effects:

[0020] The invention provides a winter construction insulation method for reinforced high-rise prefabricated buildings. The method is safe and reliable, and can effectively speed up the installation efficiency of winter construction insulation devices during installation, ensure the construction period, and solve the problem that the installation of insulation materials requires a lot of manpower, the air is dry in northern winter, and the low humidity in the greenhouse affects the concrete maintenance, and the strength increases slowly. The concrete strength cannot meet the requirements of aluminum mold removal, construction elevators, tower crane wall supports and wall rods, and integrated attached lifting scaffolding wall supports. The fire prevention and construction progress of high-rise buildings must be comprehensively considered. The installation takes a long time and is costly. In addition, the facade structure of high-rise buildings is prone to cold bridges and is not easy to be insulated. The heating of heaters and coke ovens poses a fire safety hazard. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0022] Figure 1 This is a schematic diagram of a winter construction insulation method for stacked and reinforced high-rise assembled buildings proposed by the present invention. Figure 1 ;

[0023] Figure 2 This is a schematic diagram of a winter construction insulation method for stacked and reinforced high-rise assembled buildings proposed by the present invention. Figure 2 ;

[0024] Figure 3 It is a elevation view of a winter construction insulation method for superimposed and reinforced high-rise assembled buildings proposed by the present invention;

[0025] Figure 4 It is a plan view of a winter construction insulation method for superimposed and reinforced high-rise assembled buildings proposed by the present invention;

[0026] Figure 5 It is a schematic diagram of a tower crane for the winter construction insulation method of a superimposed and reinforced high-rise prefabricated building proposed by the present invention.

[0027] In the figure: 1. High-rise building; 2. Tower crane; 3. Construction elevator; 4. Integrated attached lifting scaffolding; 5. Facade electric roller shutter insulation blanket device; 6. Plane electric roller shutter insulation blanket device; 7. Synchronous roller shutter electric motor; 8. Insulation blanket drum; 9. Heating and humidifying device for standard curing room; 10. Insulation blanket; 11. Aluminum mold; 12. Walkway board. DETAILED DESCRIPTION

[0028] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0029] The application principle of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0030] Example 1

[0031] like Figures 1 to 5 As shown, an embodiment of the present invention is a method for winter construction insulation of a laminated reinforced high-rise prefabricated building, comprising the following steps:

[0032] Step 1: before installation, build models of high-rise building 1, aluminum formwork 11, tower crane 2, construction elevator 3, and integrated attached lifting scaffold 4;

[0033] Step 2: According to the outer dimensions of the integrated attached lifting scaffold 4, the scaffold is at least two floors high; and the facade of the high-rise building 1 is segmented to produce a facade electric roller curtain insulation blanket device 5 and a flat electric roller curtain insulation blanket device 6;

[0034] Step 3: The facade electric roller blind insulation blanket device 5 first installs a synchronous roller blind electric motor 7 on the periphery of the integrated attached lifting scaffold 4, installs a insulation blanket reel 8 pre-rolled up according to the height of two floors, and connects the synchronous roller blind electric motor 7 to a power source;

[0035] Step 4: The flat electric rolling curtain insulation blanket device 6 is first installed at both ends and short sides of the integrated attached lifting scaffolding 4 with a synchronous rolling curtain electric motor 7;

[0036] Install the thermal insulation blanket reel 8 which is pre-rolled up to half the length of the long side, and connect the synchronous rolling curtain electric motor 7 to the power supply;

[0037] Step 5: Power on and debug, adjust the facade electric roller blind insulation blanket device 5 and the plane electric roller blind insulation blanket device 6 until they meet the insulation and maintenance requirements;

[0038] Step six, symmetrically install the standard curing room heating and humidifying device 9 on the walkway boards 12 around the integrated attached lifting scaffolding 4, connect the standard curing room heating and humidifying device 9 to the water source and power supply, and adjust the standard curing room heating and humidifying device 9 until it meets the insulation and maintenance requirements. After the concrete is poured in sections, start the electric motor in sections to open the facade electric roller curtain insulation blanket device 5 and the plane electric roller curtain insulation blanket device 6 to drive the insulation blanket 10, and start the standard curing room heating and humidifying device 9 for insulation and maintenance until the maintenance is completed;

[0039] Before the material transportation and integrated attached lifting scaffold 4 are lifted, the electric motor is started in sections to roll up the flat electric roller curtain insulation blanket device 6 to drive the insulation blanket and stop the operation of the heating and humidifying device 9 for the standard curing room.

[0040] In a further technical solution, the temperature of the insulation device during winter construction is 20℃±2℃ and the relative humidity is controlled at 95%-98%.

[0041] In a further technical solution, the aluminum mold 11 is installed in the high-rise building 1 through a mounting pin; and the aluminum mold 11 is installed on the top of the synchronous roller shutter electric motor 7.

[0042] In a further technical solution, the upper part of the thermal insulation blanket drum 8 is connected to the end of the synchronous rolling curtain electric motor 7; the end of the synchronous rolling curtain electric motor 7 away from the thermal insulation blanket drum 8 is connected to the flat electric rolling curtain thermal insulation blanket device 6; the flat electric rolling curtain thermal insulation blanket device 6 is suitable for being fixed in a high-rise building 1.

[0043] In a further technical solution, the facade electric roller blind insulation blanket device 5 is installed on the side of the insulation blanket drum 8 facing away from the high-rise building 1, and the height is higher than the laying height of the corresponding high-rise building 1.

[0044] In a further technical solution, a steel pipe is installed on the walkway board 12 and is connected to the facade electric roller shutter insulation blanket device 5; and a hook is installed at the bottom of the walkway board 12, a connecting rope is installed on the hook, and the top of the integrated attached lifting scaffolding 4 is connected at the bottom.

[0045] In a further technical solution, a pulley block is installed at the bottom of the integrated attached lifting scaffold 4, and is connected to the corresponding walkway board 12 at the bottom by a rope.

[0046] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention.

[0047] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A winter construction insulation method for laminated reinforced high-rise assembled buildings, characterized in that: The following steps are involved: Step 1: before installation, a model of a high-rise building (1), an aluminum formwork (11), a tower crane (2), a construction elevator (3), and an integrated attached lifting scaffold (4) is established; Step 2: according to the outer dimensions of the integrated attached lifting scaffold (4), the scaffold is at least at the height of two floors; The exterior facade of the high-rise building (1) is segmented to produce a facade electric rolling curtain thermal insulation blanket device (5) and a flat electric rolling curtain thermal insulation blanket device (6); Step 3: The facade electric rolling curtain insulation blanket device (5) first installs a synchronous rolling curtain electric motor (7) on the periphery of the integrated attached lifting scaffold (4), installs a insulation blanket reel (8) pre-rolled up according to the height of two floors, and connects the synchronous rolling curtain electric motor (7) to a power source; Step 4: The flat electric rolling curtain insulation blanket device (6) is first installed with a synchronous rolling curtain electric motor (7) on the short sides at both ends of the integrated attached lifting scaffold (4); A heat preservation blanket reel (8) pre-rolled up to half the length of the long side is installed, and a synchronous rolling curtain electric motor (7) is connected to a power source; Step 5: respectively power on, debug and adjust the facade electric roller curtain insulation blanket device (5) and the plane electric roller curtain insulation blanket device (6) until they meet the insulation and maintenance requirements; Step 6: symmetrically install the standard curing room heating and humidifying device (9) on the walkway boards (12) around the integrated attached lifting scaffold (4), connect the standard curing room heating and humidifying device (9) to the water source and the power supply, and turn on the water and electricity to debug and adjust the standard curing room heating and humidifying device (9) until it meets the insulation and maintenance requirements. After the concrete is poured in sections, start the electric motor in sections to open the vertical electric roller curtain insulation blanket device (5) and the plane electric roller curtain insulation blanket device (6) to drive the insulation blanket (10), and start the standard curing room heating and humidifying device (9) to perform insulation maintenance until the maintenance is completed; Before the material transportation and integrated attached lifting scaffold (4) is lifted, the electric motor is started in sections to roll up the flat electric roller curtain insulation blanket device (6) to drive the insulation blanket and stop the operation of the heating and humidifying device (9) for the standard curing room.

2. A winter construction insulation method for laminated reinforced high-rise assembled buildings according to claim 1, characterized in that: During winter construction, the temperature of the insulation device is 20℃±2℃ and the relative humidity is controlled at 95%-98%.

3. A winter construction insulation method for laminated reinforced high-rise assembled buildings according to claim 1, characterized in that: The aluminum mold (11) is installed in a high-rise building (1) via an installation pin; and the aluminum mold (11) is installed on the top of a synchronous rolling shutter electric motor (7).

4. A winter construction insulation method for laminated reinforced high-rise assembled buildings according to claim 1, characterized in that: The upper part of the thermal insulation blanket drum (8) is connected to the end of a synchronous rolling curtain electric motor (7); the end of the synchronous rolling curtain electric motor (7) away from the thermal insulation blanket drum (8) is connected to a flat electric rolling curtain thermal insulation blanket device (6); the flat electric rolling curtain thermal insulation blanket device (6) is suitable for being fixed in a high-rise building (1).

5. A winter construction insulation method for laminated reinforced high-rise assembled buildings according to claim 1, characterized in that: The facade electric roller blind thermal insulation blanket device (5) is installed on the side of the thermal insulation blanket drum (8) facing away from the high-rise building (1), and its height is higher than the laying height of the corresponding high-rise building (1).

6. A winter construction insulation method for laminated reinforced high-rise assembled buildings according to claim 1, characterized in that: The walkway board (12) is provided with a steel pipe and is connected to the facade electric roller blind thermal insulation blanket device (5); and a hook is provided at the bottom of the walkway board (12), a connecting rope is provided on the hook, and the top of the integrated attached lifting scaffold (4) is connected at the bottom.

7. A winter construction insulation method for laminated reinforced high-rise assembled buildings according to claim 6, characterized in that: A pulley block is installed at the bottom of the integrated attachment type lifting scaffold (4), and is connected to the corresponding walkway board (12) at the bottom through a rope.