Basement wall water seepage crack blocking construction method
Through the use of double pouring technology and auxiliary machines, combined with waterproof and weather-resistant glue and concrete, a double-layer protective barrier is formed, which solves the stability and durability problems in sealing seepage cracks in basement walls and achieves efficient and economical sealing. Effect.
Patent Information
- Application Number
- CN202411067725.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-08-06
AI Technical Summary
Existing methods for sealing seepage cracks in basement walls have problems such as unstable repair results, difficult construction, limited applicability and poor durability. Traditional methods are difficult to effectively solve complex cracks and aging cracking problems in long-term use.
Using double pouring technology, combined with high-performance waterproof and weather-resistant glue and concrete materials, pouring grooves are opened at the seepage cracks in the wall. Through the first injection of waterproof and weather-resistant glue and the second injection of cement mortar, a double-layer protective barrier is formed. And use auxiliary machines to simplify construction steps and ensure accuracy and stability.
It significantly enhances the waterproof function of the wall and the durability of the sealing layer, reduces the difficulty and cost of construction, ensures the stability and reliability of the sealing effect, and improves the economy and practicality of construction.
Smart Images

Figure CN118756993A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building crack blocking construction, and in particular to a basement wall water seepage crack blocking construction method. Background Art
[0002] In basement construction projects, water seepage cracks in the walls are common and difficult to deal with. Due to the special geographical location of the basement, it is affected by groundwater pressure and humidity all year round, and coupled with construction quality problems, water seepage cracks are prone to appear in the walls. These cracks pose a threat to the use function, durability and even structural safety of the building.
[0003] At present, there are mainly the following blocking methods to solve this problem:
[0004] Traditional cement mortar repair method: This method is simple to operate, but the effect is not ideal. Cement mortar tends to shrink after drying, which may cause gaps between the wall and the wall, leading to secondary water seepage. It is difficult to completely fill wide cracks or cracks with cavities inside with cement mortar.
[0005] Chemical grouting method: The grouting material is injected into the cracks through high-pressure equipment, and the material expands and solidifies to form a waterproof layer. This method has a good filling effect, but it has strict requirements on the selection and proportion of grouting materials, and the construction is difficult.
[0006] Waterproof paint brushing method: suitable for fine cracks and flat surfaces, but not very effective for wide cracks or internal voids.
[0007] Pre-embedded waterstop method: Pre-embed waterstop during wall construction to prevent water seepage from cracks. However, once the waterstop is damaged or displaced, it will lose its effectiveness.
[0008] Although the above methods can solve the problem of water seepage cracks to a certain extent, there are still many shortcomings:
[0009] Unstable repair effect: Affected by construction quality and environmental conditions, the effects of traditional cement mortar repair method and waterproof paint brushing method are not stable and secondary water seepage is prone to occur.
[0010] The construction is difficult: the chemical grouting method and the embedded waterstop method have high requirements on construction equipment and operators, and the selection and proportion of grouting materials is also a difficult point.
[0011] Limited applicability: Different repair methods are suitable for different types of cracks, but when dealing with complex cracks, the effects of existing methods are often unsatisfactory.
[0012] Poor durability: Some repair materials are prone to aging and cracking during long-term use, resulting in reduced repair effects.
[0013] Although there are a variety of traditional methods for sealing water seepage cracks in basement walls, they generally face problems such as great construction difficulty, high cost, and unsatisfactory results. Summary of the invention
[0014] In view of this, the present invention aims to propose a construction method for sealing water seepage cracks in basement walls, accurately opening casting grooves at the water seepage cracks in the wall, and using two-time casting technology, combined with high-performance waterproof and weather-resistant glue and concrete materials, to achieve effective sealing of the water seepage cracks. The construction is simple and efficient, and the sealing effect is stable and reliable, which significantly improves the economy and practicality of the construction.
[0015] To achieve the above object, the technical solution of the present invention is achieved as follows:
[0016] A construction method for sealing water seepage cracks in a basement wall, comprising the following steps:
[0017] S1: Survey the site, determine the location of water seepage cracks, and mark them;
[0018] S2: Open a casting groove at the marked position of the water seepage crack on the wall;
[0019] S3: Treat the pouring groove area, including removing dust, dirt and loose tissue on the concrete surface, and rinse with clean water after treatment;
[0020] S4: Apply cement-based penetrating crystalline waterproof coating in the casting groove;
[0021] S5: Sleeve the first cavity of the prefabricated waterproof sleeve onto the first supporting flange of the first blocking plate, and cover the casting groove on the wall with the first blocking plate through an auxiliary machine;
[0022] S6: pouring the waterproof and weather-resistant glue into the space between the pouring groove and the prefabricated waterproof sleeve for the first time through the first pouring hole on the first sealing plate;
[0023] S7: After the first pouring is completed, the first blocking plate is separated from the first cavity of the prefabricated waterproof sleeve by an auxiliary machine;
[0024] S8: Apply epoxy resin waterproof coating in the first cavity, and after the coating is completed, cover the first cavity of the prefabricated waterproof sleeve with a second blocking plate;
[0025] S9: pouring the cement mortar mixture into the first cavity for a second time through the second pouring hole;
[0026] S10: After the second pouring is completed, the second blocking plate is disassembled by an auxiliary machine, and the blocking structure is leveled with the wall.
[0027] Furthermore, the auxiliary machine includes:
[0028] A frame assembly, the frame assembly comprising a vertical rail assembly and a bottom plate support, the vertical rail assembly being mounted and fixed on the bottom plate support;
[0029] The sliding rod assembly is used to connect and fix the plugging assembly and can drive the plugging assembly to slide in the horizontal direction;
[0030] A driving assembly, used for driving the slide bar assembly to slide vertically on the vertical rail assembly;
[0031] The blocking assembly includes a first blocking plate or a second blocking plate.
[0032] Further, the vertical rail assembly includes a first vertical rail and a second vertical rail, the first vertical rail and the second vertical rail are vertically arranged, and the bottom plate support includes a first support plate, a second support plate, and a third support plate, wherein the second support plate is connected to a side of the lower end of the first vertical rail away from the second vertical rail, the third support plate is connected to a side of the lower end of the second vertical rail away from the first vertical rail, and the first support plate is connected at a position between the first vertical rail and the second vertical rail.
[0033] Further, the sliding rod assembly includes a first fixed sliding rod, which includes a first sliding rod, a first transverse rail, a second transverse rail and a first horizontal sliding motor, the first transverse rail is arranged on the first vertical rail, the second transverse rail is arranged on the second vertical rail, the first sliding rod is arranged between the first transverse rail and the second transverse rail and slides horizontally along the first transverse rail and the second transverse rail under the action of the first horizontal sliding motor, and the first sliding rod is fixedly connected to the blocking assembly.
[0034] Furthermore, the sliding rod assembly also includes a second fixed sliding rod, the second fixed sliding rod includes a second sliding rod, a third cross rail, a fourth cross rail and a second horizontal sliding motor, the third cross rail is arranged on the first vertical rail, the fourth cross rail is arranged on the second vertical rail, the second sliding rod is arranged between the third cross rail and the fourth cross rail and slides horizontally along the third cross rail and the fourth cross rail under the action of the second horizontal sliding motor, the second sliding rod is arranged in parallel with the first sliding rod, and the second sliding rod and the first sliding rod are screwed to the upper and lower ends of the first blocking plate or the second blocking plate.
[0035] Furthermore, the first sealing plate includes a first sealing plate body, on which a first connecting hole is arranged, the first connecting hole being a threaded blind hole, for being connected to the first sliding rod or the second sliding rod of the sliding rod assembly by screws, a first supporting flange being arranged on the first sealing plate body, the first supporting flange and the first connecting hole being formed on two side surfaces of the first sealing plate body, a first pouring hole being arranged on the first sealing plate body outside the first supporting flange, the first pouring hole being used for performing the first pouring of the space between the pouring groove and the prefabricated watertight sleeve.
[0036] Furthermore, the first supporting flange is arranged in a circular ring shape, and a plurality of the first pouring holes are arranged, and the plurality of the first pouring holes are evenly distributed in a circular shape and arranged at the outer circumferential position of the projection contour of the first supporting flange on the first sealing plate body.
[0037] Furthermore, a first through hole is arranged on the inner side of the first supporting flange, and the first through hole penetrates the first sealing plate body. Correspondingly, the prefabricated waterproof sleeve includes a first bottom wall and a first side wall, and the first side wall is arranged on one side of the first bottom wall to form a first cavity. The first side wall can be sleeved on the outer wall of the first supporting flange, and at this time, the first bottom wall blocks the first through hole.
[0038] Furthermore, the second sealing plate includes a second sealing plate body, and a second connecting hole and a second pouring hole are arranged on the second sealing plate body. The second connecting hole is used for threaded connection between the second sealing plate and the first sliding rod or the second sliding rod. The second connecting hole is a blind hole. The second pouring hole is used for introducing cement mortar mixture into the first cavity for a second pouring when the second sealing plate covers the outside of the first cavity.
[0039] Furthermore, in step S5, the following specific steps are included:
[0040] S51: removing the electric drill in the first through hole;
[0041] S52: applying a mold release agent on the outer surface of the first supporting flange, and sleeve the first cavity of the prefabricated waterproof sleeve on the outer surface of the first supporting flange;
[0042] S53: attaching first sealing strips to upper and lower ends of the first blocking plate near the end portions;
[0043] S54: Apply epoxy resin waterproof coating on the outer surface of the first side wall of the prefabricated waterproof sleeve;
[0044] S55: controlling the first sliding rod and the second sliding rod to move up and down in unison through a driving assembly, so that the first blocking plate connected to the first sliding rod and the second sliding rod is aligned with the casting groove;
[0045] S56: The first sliding rod and the second sliding rod are driven by the first horizontal sliding motor and the second horizontal sliding motor to slide horizontally along the side close to the wall until the first sealing strip is tightly sealed against the wall.
[0046] Compared with the prior art, the basement wall water seepage crack blocking construction method of the present invention has the following advantages:
[0047] (1) The construction method for sealing water seepage cracks in basement walls described in the present invention constructs a solid double-layer protective barrier by pouring twice, combining waterproof and weather-resistant glue with concrete, effectively curbing water seepage in the wall, significantly enhancing the waterproof function of the wall, and improving the durability of the sealing layer; at the same time, the method simplifies the construction steps with the help of auxiliary machines, reduces the difficulty of manual operation, saves time and labor costs, and ensures the accuracy of construction, significantly optimizing the sealing effect of water seepage cracks in basement walls.
[0048] (2) The construction method for sealing water seepage cracks in basement walls described in the present invention forms a sealing structure having a first sealing layer - a prefabricated waterproof sleeve - a second sealing layer by pouring twice in a pouring groove, which cleverly combines the advantages of each layer to make the sealing effect more excellent. The first sealing layer and the second sealing layer are respectively located on the inner and outer sides of the prefabricated waterproof sleeve, forming double protection, which greatly improves the reliability and durability of the sealing. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the accompanying drawings:
[0050] Figure 1 It is a front view structural schematic diagram of a plugging assembly assembled on a water seepage crack plugging auxiliary machine according to an embodiment of the present invention;
[0051] Figure 2 It is a side structural schematic diagram of the water seepage crack plugging auxiliary machine according to an embodiment of the present invention;
[0052] Figure 3 It is a schematic diagram of the explosion structure of the assembly structure of the first blocking plate and the prefabricated watertight sleeve in the blocking assembly according to the embodiment of the present invention;
[0053] Figure 4 This is a front view structural schematic diagram of the first blocking plate according to an embodiment of the present invention;
[0054] Figure 5 This is a schematic side view of the structure of the first blocking plate according to an embodiment of the present invention;
[0055] Figure 6This is a schematic diagram of the first pouring structure of grooving at a water seepage crack on a wall according to an embodiment of the present invention;
[0056] Figure 7 This is a front view structural schematic diagram of the second blocking plate according to an embodiment of the present invention;
[0057] Figure 8 This is a schematic diagram of the second pouring structure at the water seepage crack on the wall according to an embodiment of the present invention;
[0058] Fig. 9 This is a schematic diagram of the structure after the basement wall water seepage cracks are blocked by the construction method for blocking the basement wall water seepage cracks according to the embodiment of the present invention;
[0059] Description of reference numerals:
[0060] 100-frame assembly; 200-sliding rod assembly; 300-driving assembly; 400-blocking assembly; 500-wall; 600-first blocking layer; 700-second blocking layer; 1-vertical rail assembly; 2-bottom plate support; 201-first support plate; 202-second support plate; 203-third support plate; 3-first connecting rod; 4-first vertical rail; 5-second vertical rail; 6-first fixed sliding rod; 7-second fixed sliding rod; 8-first sliding rod; 9-first horizontal rail; 10-second horizontal rail; 11-first horizontal sliding motor; 12-second sliding rod; 13-third horizontal rail; 14-fourth horizontal rail; 15- The second horizontal sliding motor; 16-the first driving device; 17-the second driving device; 18-the first sealing plate; 1801-the first sealing plate body; 1802-the first connecting hole; 1803-the first pouring hole; 1804-the first supporting flange; 1805-the first through hole; 19-the prefabricated waterproof sleeve; 1901-the first bottom wall; 1902-the first side wall; 1903-the first cavity; 20-the pouring groove; 21-the flaring part; 22-the first sealing strip; 23-the second sealing plate; 2301-the second sealing plate body; 2302-the second connecting hole; 2303-the second pouring hole; 24-the second sealing strip. DETAILED DESCRIPTION
[0061] In order to make the technical means, objectives and effects of the present invention easy to understand, the embodiments of the present invention are described in detail below with reference to specific drawings.
[0062] It should be noted that all the terms used in the present invention for directional and positional indications, such as "up", "down", "left", "right", "front", "back", "vertical", "horizontal", "inside", "outside", "top", "low", "lateral", "longitudinal", "center", etc., are only used to explain the relative positional relationship and connection status between the components in a certain state (as shown in the accompanying drawings), and are only for the convenience of describing the present invention, rather than requiring the present invention to be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the descriptions of "first", "second", etc. in the present invention are only used for descriptive purposes, and cannot be understood as indicating or suggesting their relative importance or implicitly indicating the number of the indicated technical features.
[0063] In the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0064] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0065] like Figures 1 to 9 As shown, the present application discloses a construction method for sealing water seepage cracks in a basement wall, comprising the following steps:
[0066] S1: Survey the site, determine the location of water seepage cracks, and mark them;
[0067] S2: Opening a casting groove 20 at the marked position of the water seepage crack on the wall 500;
[0068] S3: Treat the casting groove 20 area, including removing dust, dirt and loose parts of the concrete surface, and rinse with clean water after treatment;
[0069] S4: Apply cement-based penetrating crystalline waterproof coating in the casting groove 20;
[0070] S5: Sleeve the first cavity 1903 of the prefabricated waterproof jacket 19 onto the first supporting flange 1804 of the first blocking plate 18, and cover the casting groove 20 on the wall 500 with the first blocking plate 18 through an auxiliary machine;
[0071] S6: pouring the waterproof and weather-resistant glue into the space between the pouring groove 20 and the prefabricated waterproof sleeve 19 through the first pouring hole 1803 on the first blocking plate 18 for the first time;
[0072] S7: After the first pouring is completed, the first blocking plate 18 is separated from the first cavity 1903 of the prefabricated waterproof jacket 19 by an auxiliary machine;
[0073] S8: Apply epoxy resin waterproof paint in the first cavity 1903, and after the application, cover the first cavity 1903 of the prefabricated waterproof jacket 19 with the second blocking plate 23;
[0074] S9: pouring the cement mortar mixture into the first cavity 1903 for the second time through the second pouring hole 2303;
[0075] S10: After the second pouring is completed, the second blocking plate 23 is removed by an auxiliary machine, and the blocking structure is leveled with the wall 500.
[0076] The construction method for sealing water seepage cracks in basement walls disclosed in the present application, at the beginning of construction, firstly accurately survey and mark the water seepage cracks, then open a casting groove 20 at the crack position, and the sealing operation is mainly divided into two steps: first, use the first sealing plate 18 and the prefabricated waterproof sleeve 19, inject waterproof and weather-resistant glue into the casting groove 20, perform preliminary sealing of the main body of the casting groove 20 at the water seepage location, and form a first protective layer; then, remove the first sealing plate 18, replace it with the second sealing plate 23, pour concrete into the first cavity 1903 of the prefabricated waterproof sleeve 19, complete the second sealing of the remaining space, thereby forming double protection, and the waterproof material is used during sealing. In terms of the choice of painting and pouring, cement-based penetrating crystalline waterproof coating can block the internal pores of the wall through crystallization to enhance the waterproof effect; the waterproof and weather-resistant glue is made of polyurethane, acrylic or silicone materials, so that it is liquid before pouring and solidifies after pouring to form a waterproof sealing layer. The poured waterproof sealing layer is the first protective layer. The material of the prefabricated waterproof sleeve 19 is the same as the pouring material of the waterproof and weather-resistant glue. Epoxy resin waterproof coating is applied in the first cavity 1903 of the prefabricated waterproof sleeve 19 to enhance its adhesion with the internal poured cement mortar to form a concrete protective layer, thereby greatly improving the stability of the seal and comprehensively improving the waterproof performance. During the entire sealing process, when grooving and fixing the first sealing plate 18 and the second sealing plate 23, an auxiliary machine is used to limit and fix the electric drill equipment and the first sealing plate 18 and the second sealing plate 23 of the sealing assembly 400, so as to accurately open the casting groove 20 and reduce the number of other connection holes or fixing holes opened near the casting groove 20, thereby better protecting the structural integrity of the wall, reducing the subsequent maintenance frequency, and ensuring the construction quality and speed.
[0077] The construction method for sealing water seepage cracks in basement walls disclosed in the present application constructs a solid double-layer protective barrier through two pourings, combining waterproof and weather-resistant glue with concrete, which effectively curbs water seepage in the wall, significantly enhances the waterproof function of the wall, and improves the durability of the sealing layer; at the same time, the method simplifies the construction steps with the help of auxiliary machines, reduces the difficulty of manual operation, saves time and labor costs, ensures the accuracy of construction, and significantly optimizes the sealing effect of water seepage cracks in basement walls.
[0078] As a preferred example of the present application, the auxiliary machine includes:
[0079] A frame assembly 100, the frame assembly 100 comprises a vertical rail assembly 1 and a bottom plate support 2, the vertical rail assembly 1 is mounted and fixed on the bottom plate support 2;
[0080] The sliding rod assembly 200 is used to connect and fix the blocking assembly 400, and can drive the blocking assembly 400 to slide in the horizontal direction;
[0081] The driving assembly 300 is used to drive the sliding rod assembly 200 to slide vertically on the vertical rail assembly 1;
[0082] The blocking assembly 400 includes a first blocking plate 18 or a second blocking plate 23 .
[0083] This setting discloses a structure of an auxiliary machine. By setting a frame assembly 100 including a vertical rail assembly 1 and a bottom plate support 2, the stability and load-bearing capacity of the auxiliary machine are ensured. The slide bar assembly 200 is responsible for connecting and fixing the plugging assembly 400. It can drive the plugging assembly 400 to slide in the horizontal direction, so that the plugging plate can be easily moved to the specified position, so that when plugging, the first plugging plate 18 or the second plugging plate 23 can quickly and reliably cover the opening of the casting cavity; the driving assembly 300 is the power source of the auxiliary machine, which can drive the slide bar assembly 200 to slide in the vertical direction on the vertical rail assembly 1, so that the plugging plate can be precisely adjusted in the vertical direction to meet different construction requirements. The above setting greatly simplifies the construction process. Construction personnel do not need to perform complex measurement and positioning work. They can complete the precise placement of the plugging plate by operating the auxiliary machine, which saves time and reduces the difficulty of construction. In addition, the auxiliary machine also improves the safety of construction. Since the blocking plates can be accurately moved and positioned by the auxiliary machine, construction workers do not need to perform manual operations in dangerous locations, thereby reducing the occurrence of safety accidents.
[0084] As a preferred example of the present application, the vertical rail assembly 1 includes a first vertical rail 4 and a second vertical rail 5, the first vertical rail 4 and the second vertical rail 5 are arranged vertically, and the bottom plate support 2 includes a first support plate 201, a second support plate 202, and a third support plate 203, wherein the second support plate 202 is connected to the side of the lower end of the first vertical rail 4 away from the second vertical rail 5, the third support plate 203 is connected to the side of the lower end of the second vertical rail 5 away from the first vertical rail 4, and the first support plate 201 is connected to the position between the first vertical rail 4 and the second vertical rail 5. As a specific example of the present application, the first support plate 201 is used to connect and fix the drive assembly 300, the second support plate 202 and the third support plate 203 are symmetrically arranged on opposite sides of the first support plate 201, and the second support plate 202 and the third support plate 203 are used to be fixedly connected to the ground or fixedly connected to other fixing devices to ensure that the frame assembly 100 is fixed relative to the ground when in use. The above-mentioned setting discloses a specific structure of a frame assembly, in which the frame assembly 100 is composed of a vertical rail assembly 1, a base plate support 2 and a slide bar assembly 200, thereby ensuring the stability and flexibility of the construction process; the vertical rail assembly 1 is installed on the base plate support 2 to provide solid support, thereby ensuring the effective sealing of water seepage cracks in the basement wall; the slide bar assembly 200 is arranged between the first vertical rail 4 and the second vertical rail 5, and its position can be precisely adjusted by a motor drive to adapt to different walls and cracks, thereby simplifying the construction process and improving the accuracy and efficiency of the sealing. By adjusting the slide bar assembly 200, the sealing plate can be easily installed and moved without drilling holes in the wall, thereby ensuring safe and reliable sealing.
[0085] As a preferred example of the present application, a first connecting rod 3 is arranged at the upper ends of the first vertical rail 4 and the second vertical rail 5, and the first connecting rod 3, the first vertical rail 4, the second vertical rail 5 and the first support plate 201 of the bottom plate support 2 surround a rectangular frame body. This design arranges the first connecting rod 3 for connecting the first vertical rail 4 and the second vertical rail 5 at the upper ends thereof, so that the first connecting rod 3, the vertical rail assembly 1 and the bottom plate support 2 form a stable frame structure, which provides a solid support for the blocking process, thereby effectively improving the blocking efficiency and blocking quality. In addition, the arrangement of the first connecting rod 3 not only strengthens the integrity of the frame, but also greatly facilitates the hoisting, fixing, transportation and storage of the frame assembly 100, thereby improving the convenience and safety of construction.
[0086] As a preferred example of the present application, the sliding rod assembly 200 includes a first fixed sliding rod 6, which includes a first sliding rod 8, a first transverse rail 9, a second transverse rail 10 and a first horizontal sliding motor 11, the first transverse rail 9 is arranged on the first vertical rail 4, the second transverse rail 10 is arranged on the second vertical rail 5, the first sliding rod 8 is arranged between the first transverse rail 9 and the second transverse rail 10 and slides horizontally along the first transverse rail 9 and the second transverse rail 10 under the action of the first horizontal sliding motor 11, and the first sliding rod 8 is fixedly connected to the blocking assembly 400. In the example of the present application, when sealing water seepage cracks, when the driving assembly 300 drives the first fixed sliding rod 6 to move to the vertical working position on the vertical rail assembly 1, the first horizontal sliding motor 11 drives the first sliding rod 8 to move along the first transverse rails 9 and the second transverse rails 10 on the left and right sides and toward the side close to the wall 500, and the first sealing plate 18 or the second sealing plate 23 in the sealing assembly 400 moves integrally with the first sliding rod 8 until the pouring chamber is covered, and then the first horizontal sliding motor 11 locks the sealing assembly 400 relative to the wall 500 until the pouring is completed, and the first horizontal sliding motor 11 drives the first sliding rod 8 to move to the side away from the wall 500 to achieve the detachment of the sealing assembly 400.
[0087] The setting discloses a structure of a sliding rod assembly 200. Through the structure of the first fixed sliding rod 6, the precise movement of the sealing assembly in the horizontal and vertical directions is realized, so that the sealing plate can quickly and accurately reach the specified position and cover the casting chamber. The design structure is ingenious and practical, which improves the construction efficiency and further enhances the accuracy and stability of the sealing. At the same time, it also makes the sealing process more automated and intelligent, reducing the complexity and uncertainty of manual operation.
[0088] As a preferred example of the present application, the sliding rod assembly 200 also includes a second fixed sliding rod 7, which includes a second sliding rod 12, a third transverse rail 13, a fourth transverse rail 14 and a second horizontal sliding motor 15. The third transverse rail 13 is arranged on the first vertical rail 4, and the fourth transverse rail 14 is arranged on the second vertical rail 5. The second sliding rod 12 is arranged between the third transverse rail 13 and the fourth transverse rail 14 and slides horizontally along the third transverse rail 13 and the fourth transverse rail 14 under the action of the second horizontal sliding motor 15. The second sliding rod 12 is arranged in parallel with the first sliding rod 8, and the second sliding rod 12 and the first sliding rod 8 are screwed to the upper and lower ends of the first blocking plate 18 or the second blocking plate 23.
[0089] The configuration discloses a sliding rod assembly 200 structure including two sliding rods. This double sliding rod design not only improves the stability of the plugging plate during movement, but also enhances its positioning accuracy. In addition, the second sliding rod is arranged in parallel with the first sliding rod, and the two are respectively connected to the upper and lower ends of the plugging plate. This structure further enhances the stability of the plugging plate, effectively preventing possible shaking or deviation during construction, and improving the reliability of the plugging construction of water seepage cracks in the basement wall.
[0090] As a preferred example of the present application, the first fixed slide bar 6 and the second fixed slide bar 7 are integrally moved upward and slid on the vertical rail assembly 1 through the driving assembly 300, or the first fixed slide bar 6 and the second fixed slide bar 7 are independently driven by the first driving device 16 and the second driving device 17 in the driving assembly 300. As a specific example of the present application, the driving assembly 300 includes a first driving device 16 and a second driving device 17. The first driving device 16 is used to drive the first fixed sliding rod 6 to slide vertically on the vertical rail assembly 1, and the second driving device 17 is used to drive the second fixed sliding rod 7 to slide vertically on the vertical rail assembly 1. When in use, firstly, according to the installation size of the first blocking plate 18 or the second blocking plate 23, the vertical distance between the second sliding rod 12 and the first sliding rod 8 is adjusted to meet the installation requirements of various different specifications of blocking assemblies 400. After the first blocking plate 18 or the second blocking plate 23 is installed and fixed with the second sliding rod 12 and the first sliding rod 8, the first horizontal sliding motor 11 and the second horizontal sliding motor 15 are used to drive the second sliding rod 12 and the first sliding rod 8 to slide horizontally as a whole, so as to realize the driving movement of the blocking assembly 400 approaching or moving away from the wall 500.
[0091] This setting discloses the specific driving scheme of the slide rod assembly 200, and realizes the flexible driving of the first fixed slide rod 6 and the second fixed slide rod 7. It not only meets the installation requirements of various specifications of plugging assemblies, but also greatly improves the flexibility and adaptability of construction, improves the convenience and efficiency of construction, ensures the accuracy and reliability of plugging, and provides strong technical support for the plugging construction of water seepage cracks in basement walls.
[0092] As a preferred example of the present application, the first sealing plate 18 includes a first sealing plate body 1801, on which a first connecting hole 1802 is arranged, and the first connecting hole 1802 is a threaded blind hole, which is used to be connected to the first sliding rod 8 or the second sliding rod 12 of the sliding rod assembly 200 by screws, and a first supporting flange 1804 is arranged on the first sealing plate body 1801, and the first supporting flange 1804 and the first connecting hole 1802 are formed on two side surfaces of the first sealing plate body 1801, and a first pouring hole 1803 is arranged on the first sealing plate body 1801 outside the first supporting flange 1804, and the first pouring hole 1803 is used for the first pouring of the space between the pouring groove 20 and the prefabricated watertight sleeve 19. This arrangement discloses a specific structure of a first sealing plate 18. By adopting a blind hole design for the first connecting hole 1802 opened in the first sealing plate body 1801, it can be firmly connected to the sliding rod assembly, thereby ensuring the stability and safety of the sealing plate. At the same time, the design of the first supporting flange 1804 on the first sealing plate body 1801 is used to support and fix the prefabricated waterproof sleeve 19 during the first pouring and sealing. Combined with the position design of the first pouring hole 1803, it enables the first pouring of the space between the pouring groove 20 and the prefabricated waterproof sleeve 19 to be performed accurately, thereby improving construction efficiency and ensuring pouring quality.
[0093] As a preferred example of the present application, the first support flange 1804 is arranged in an annular shape, and a plurality of first pouring holes 1803 are arranged, and the plurality of first pouring holes 1803 are arranged in an evenly distributed circumferential shape at the outer circumferential position of the projection contour of the first support flange 1804 on the first sealing plate body 1801. As a specific example of the present application, eight first pouring holes 1803 are arranged, and the line connecting the center of two adjacent first pouring holes 1803 and the center of the first support flange 1804 is arranged at an angle of 45°. This arrangement further optimizes the structure of the first sealing plate 18. The first supporting flange 1804 is designed to be in a circular shape, which not only enhances the overall structural strength of the first sealing plate and provides a stable supporting surface for the sealing operation, but also facilitates the reliable separation of the first sealing plate 18 from the prefabricated waterproof sleeve 19 after the first sealing is completed. At the same time, multiple first pouring holes 1803 are evenly distributed in a circular shape on the first sealing plate body 1801, making the first pouring process more uniform and efficient, improving construction efficiency, and ensuring the uniformity of pouring quality, making the pouring process smoother and without dead ends.
[0094] As a preferred example of the present application, a first through hole 1805 is arranged on the inner side of the first supporting flange 1804, and the first through hole 1805 penetrates the first sealing plate body 1801. Correspondingly, the prefabricated waterproof jacket 19 includes a first bottom wall 1901 and a first side wall 1902, and the first side wall 1902 is arranged on one side of the first bottom wall 1901 and forms a first cavity 1903. The first side wall 1902 can be sleeved on the outer wall of the first supporting flange 1804, and at this time, the first bottom wall 1901 blocks the first through hole 1805. In the example of the present application, the first through hole 1805 is designed as a through hole, which helps to use the first sealing plate 18 as a supporting and fixing structure for fixing the electric drill, so that there is no need to replace the sealing assembly 400 when the drilling is completed. After the electric drill is dismantled, the prefabricated waterproof sleeve 19 can be directly installed for sealing, which simplifies the construction process and improves construction efficiency. At the same time, the structural design of the prefabricated waterproof sleeve 19 perfectly matches the first sealing plate 18, and the first side wall 1902 can be easily mounted on the outer wall of the first supporting flange 1804, and the first bottom wall 1901 can effectively block the first through hole 1805, ensuring the tightness and stability of the sealing, realizing functional diversification and efficient construction, and bringing substantial convenience and improvement to the sealing project of water seepage cracks in basement walls.
[0095] As a preferred example of the present application, the second sealing plate 23 includes a second sealing plate body 2301, on which a second connecting hole 2302 and a second pouring hole 2303 are arranged, the second connecting hole 2302 is used for threaded connection between the second sealing plate 23 and the first sliding rod 8 or the second sliding rod 12, the second connecting hole 2302 is a blind hole, and the second pouring hole 2303 is used for the second sealing plate 23 to cover the outside of the first cavity 1903 while the cement mortar mixture is introduced into the first cavity 1903 for a second pouring.
[0096] The arrangement discloses a specific structure of the second blocking plate 23, which can slide in the vertical and horizontal directions in combination with the slide bar assembly 200 on the auxiliary machine, with reliable connection, accurate positioning, and reasonable structure, ensuring uniformity and compactness of pouring and improving the blocking effect. In addition, the design helps to further simplify the construction process and improve construction quality and efficiency.
[0097] In the example of the present application, the cement mortar mixture poured in the second sealing structure has a weight ratio of cement to mortar of 1:2 to 2.8, and the coating thickness of the cement-based penetrating crystalline waterproof coating is 1.2 mm to 1.7 mm, preferably 1.5 mm.
[0098] As a preferred example of the present application, in step S2, the following specific steps are included:
[0099] S21: Screw the first connection hole 1802 on the first blocking plate 18 to the first sliding rod 8 and the second sliding rod 12 in the auxiliary machine upper sliding rod assembly 200;
[0100] S22: fix the bottom plate support 2 of the frame assembly 100 relative to the ground, and make the first blocking plate 18 cover the marked position of the water seepage crack in S1;
[0101] S23: Fix the electric drill used for opening the casting groove 20 at the first through hole 1805 of the first sealing plate 18, and drive the first sealing plate 18 to adjust the up and down and far and near positions according to the sliding rod assembly 200, change the position of the electric drill relative to the wall 500, and open the casting groove 20 on the wall 500 by adjusting the direction angle of the electric drill.
[0102] This setting utilizes the first blocking plate on the auxiliary machine to connect with the slide bar assembly through screws, fixes the bottom plate support of the frame assembly relative to the ground, thereby achieving stable connection and reliable support of the frame assembly 100, and fixes the electric drill by cleverly utilizing the through hole on the first blocking plate, and changes the position and orientation of the electric drill according to the adjustment of the slide bar assembly, so as to accurately open a casting groove on the wall. This series of operations not only simplifies the construction process, but also greatly improves the construction accuracy and efficiency, and realizes the rapid and accurate treatment of water seepage cracks. In the example of the present application, the electric drill structure and the installation structure of the first through hole 1805 are fixed by any connection method in the prior art to achieve angle change. This connection structure is not an improvement point of the present application and will not be repeated here.
[0103] In the example of the present application, the pouring groove 20 is roughly rectangular, and when the pouring groove 20 is opened, a flared portion 21 is provided on its opening side. As a specific example of the present application, the flared portion 21 is inclined from the inside to the outside, and when the first sealing plate 18 covers the pouring groove 20 for the first pouring, a first sealing strip 22 is provided between the first sealing plate 18 and the wall 500, and when the second sealing plate 23 covers the first cavity 1903 for the second pouring, a second sealing strip 24 is provided between the second sealing plate 23 and the wall 500.
[0104] The design of the pouring groove in this example takes into account the practicality of construction and the sealing effect. The rectangular groove shape facilitates construction and positioning. During pouring, the first sealing strip 22 and the second sealing strip 24 are respectively arranged between the first sealing plate 18 and the second sealing plate 23 and the wall 500, which further enhances the tightness of the sealing and ensures that the pouring material will not leak out, thereby improving the sealing effect.
[0105] As a preferred example of the present application, in step S5, the following specific steps are included:
[0106] S51: removing the electric drill in the first through hole 1805;
[0107] S52: applying a mold release agent on the outer surface of the first supporting flange 1804, and sleeve the first cavity 1903 of the prefabricated waterproof sleeve 19 on the outer surface of the first supporting flange 1804;
[0108] S53: attaching first sealing strips 22 to the upper and lower ends of the first blocking plate 18 near the end portions;
[0109] S54: Apply epoxy resin waterproof coating on the outer surface of the first side wall 1902 of the prefabricated waterproof jacket 19;
[0110] S55: Control the first sliding rod 8 and the second sliding rod 12 to move up and down in unison through the driving assembly 300, so that the first blocking plate 18 connected to the first sliding rod 8 and the second sliding rod 12 is aligned with the casting groove 20;
[0111] S56: The first horizontal sliding motor 11 and the second horizontal sliding motor 15 drive the first sliding rod 8 and the second sliding rod 12 to slide horizontally along the side close to the wall 500 until the first sealing strip 22 is tightly sealed against the wall 500.
[0112] As a preferred example of the present application, in step S6, the glue injection nozzle of the glue injection device is inserted into the first pouring hole 1803 on the first sealing plate 18, and the first pouring is performed on the space between the pouring groove 20 and the prefabricated waterproof sleeve 19 to form a first sealing layer 600 after molding.
[0113] As an example of the present application, in step S6, when the glue injection device performs the first pouring on the pouring groove 20, the pouring space is divided into 3 to 5 pourings, and after each pouring, hot air is pressurized into the space through the first pouring hole 1803.
[0114] This setting discloses a specific step of using an auxiliary machine for the first pouring through scientific step design and delicate operation. First, remove the electric drill and apply the release agent to facilitate subsequent operations; then, set the prefabricated waterproof sleeve 19 and affix the first sealing strip 22 to enhance the sealing performance of the plugging; brush the epoxy resin waterproof coating on the outside of the prefabricated waterproof sleeve 19 to further enhance the waterproof effect; through the precise control of the drive assembly 300 and the horizontal sliding motor, the first plugging plate 18 can be accurately aligned and close to the wall 500, ensuring the accuracy of the plugging; and the method of pouring in batches and introducing hot air for pressurization not only ensures the compactness of the pouring, but also effectively prevents the occurrence of hollows and cracks. This series of operation steps is rigorous and efficient, greatly improving the plugging effect and construction quality.
[0115] In the example of the present application, during the second pouring in step S9, the installation and plugging of the second plugging plate 23 are similar to the installation and plugging of the first plugging plate 18 in step S5, and will not be repeated here. After the second pouring in step S8, the second plugging layer 700 is formed in the first cavity 1903.
[0116] According to the construction method for sealing water seepage cracks in basement walls described in the present invention, a sealing structure comprising a first sealing layer 600 - a prefabricated waterproof sleeve 19 - a second sealing layer 700 is formed by pouring twice in the pouring groove 20, which cleverly combines the advantages of each layer to make the sealing effect more excellent. The first sealing layer 600 and the second sealing layer 700 are respectively located on the inner and outer sides of the prefabricated waterproof sleeve 19, forming double protection, which greatly improves the reliability and durability of the sealing.
[0117] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A construction method for sealing water seepage cracks in basement walls. It is characterized in that The steps include: S1: Survey the site, determine the location of water seepage cracks, and mark them; S2: Opening a casting groove (20) at the marked position of the water seepage crack on the wall (500); S3: Treat the casting groove (20) area, including removing dust, dirt and loose parts of the concrete surface, and rinse with clean water after treatment; S4: applying cement-based penetrating crystalline waterproof coating in the casting groove (20); S5: Sleeve the first cavity (1903) of the prefabricated waterproof sleeve (19) onto the first supporting flange (1804) of the first sealing plate (18), and cover the casting groove (20) on the wall (500) with the first sealing plate (18) through an auxiliary machine; S6: pouring the waterproof and weather-resistant glue into the space between the pouring groove (20) and the prefabricated waterproof sleeve (19) through the first pouring hole (1803) on the first sealing plate (18); S7: After the first pouring is completed, the first sealing plate (18) is separated from the first cavity (1903) of the prefabricated waterproof jacket (19) by an auxiliary machine; S8: applying epoxy resin waterproof coating in the first cavity (1903), and after the coating is completed, covering the first cavity (1903) of the prefabricated waterproof sleeve (19) with a second blocking plate (23); S9: pouring the cement mortar mixture into the first cavity (1903) through the second pouring hole (2303) for the second time; S10: After the second pouring is completed, the second blocking plate (23) is disassembled by an auxiliary machine, and the blocking structure is leveled with the wall (500).
2. The basement wall water seepage crack sealing construction method according to claim 1, It is characterized in that The auxiliary machine comprises: A frame assembly (100), the frame assembly (100) comprising a vertical rail assembly (1) and a bottom plate support (2), the vertical rail assembly (1) being mounted and fixed on the bottom plate support (2); The sliding rod assembly (200) is used to connect and fix the blocking assembly (400) and can drive the blocking assembly (400) to slide in the horizontal direction; A driving assembly (300) for driving the sliding rod assembly (200) to slide vertically on the vertical rail assembly (1); The blocking assembly (400) comprises a first blocking plate (18) or a second blocking plate (23).
3. The basement wall water seepage crack sealing construction method according to claim 2, It is characterized in that The vertical rail assembly (1) comprises a first vertical rail (4) and a second vertical rail (5), wherein the first vertical rail (4) and the second vertical rail (5) are arranged in a vertical shape, and the bottom plate support (2) comprises a first support plate (201), a second support plate (202), and a third support plate (203), wherein the second support plate (202) is connected to a side of the lower end of the first vertical rail (4) away from the second vertical rail (5), the third support plate (203) is connected to a side of the lower end of the second vertical rail (5) away from the first vertical rail (4), and the first support plate (201) is connected to a position between the first vertical rail (4) and the second vertical rail (5).
4. The basement wall water seepage crack sealing construction method according to claim 3, It is characterized in that The slide bar assembly (200) includes a first fixed slide bar (6), the first fixed slide bar (6) includes a first sliding bar (8), a first transverse rail (9), a second transverse rail (10) and a first horizontal sliding motor (11), the first transverse rail (9) is arranged on the first vertical rail (4), the second transverse rail (10) is arranged on the second vertical rail (5), the first sliding bar (8) is arranged between the first transverse rail (9) and the second transverse rail (10) and slides horizontally along the first transverse rail (9) and the second transverse rail (10) under the action of the first horizontal sliding motor (11), and the first sliding bar (8) is fixedly connected to the blocking assembly (400).
5. The basement wall water seepage crack sealing construction method according to claim 4, It is characterized in that The slide bar assembly (200) also includes a second fixed slide bar (7), which includes a second slide bar (12), a third transverse rail (13), a fourth transverse rail (14) and a second horizontal sliding motor (15). The third transverse rail (13) is arranged on the first vertical rail (4), and the fourth transverse rail (14) is arranged on the second vertical rail (5). The second slide bar (12) is arranged between the third transverse rail (13) and the fourth transverse rail (14) and slides horizontally along the third transverse rail (13) and the fourth transverse rail (14) under the action of the second horizontal sliding motor (15). The second slide bar (12) is arranged in parallel with the first slide bar (8). The second slide bar (12) and the first slide bar (8) are screwed to the upper and lower ends of the first blocking plate (18) or the second blocking plate (23).
6. The basement wall water seepage crack sealing construction method according to claim 5, It is characterized in that The first sealing plate (18) includes a first sealing plate body (1801), on which a first connecting hole (1802) is arranged. The first connecting hole (1802) is a threaded blind hole for connecting to the first sliding rod (8) or the second sliding rod (12) of the sliding rod assembly (200) by screws. A first supporting flange (1804) is arranged on the first sealing plate body (1801). The first supporting flange (1804) and the first connecting hole (1802) are formed on two side surfaces of the first sealing plate body (1801). A first pouring hole (1803) is arranged on the first sealing plate body (1801) outside the first supporting flange (1804). The first pouring hole (1803) is used for performing the first pouring of the space between the pouring groove (20) and the prefabricated watertight sleeve (19).
7. The basement wall water seepage crack sealing construction method according to claim 6, It is characterized in that The first supporting flange (1804) is arranged in a circular ring shape, and a plurality of the first pouring holes (1803) are arranged, and the plurality of the first pouring holes (1803) are arranged in a uniformly distributed circular shape at the outer circumferential position of the projection contour of the first supporting flange (1804) on the first sealing plate body (1801).
8. The construction method for sealing water seepage cracks in basement walls according to claim 7, It is characterized in that A first through hole (1805) is arranged on the inner side of the first supporting flange (1804), and the first through hole (1805) passes through the first sealing plate body (1801). Correspondingly, the prefabricated waterproof sleeve (19) includes a first bottom wall (1901) and a first side wall (1902), and the first side wall (1902) is arranged on one side of the first bottom wall (1901) to form a first cavity (1903). The first side wall (1902) can be sleeved on the outer wall of the first supporting flange (1804), and at this time, the first bottom wall (1901) blocks the first through hole (1805).
9. The basement wall water seepage crack sealing construction method according to claim 8, It is characterized in that The second sealing plate (23) includes a second sealing plate body (2301), on which a second connecting hole (2302) and a second pouring hole (2303) are arranged. The second connecting hole (2302) is used for threaded connection between the second sealing plate (23) and the first sliding rod (8) or the second sliding rod (12). The second connecting hole (2302) is a blind hole. The second pouring hole (2303) is used for introducing cement mortar mixture into the first cavity (1903) for a second pouring when the second sealing plate (23) is sealed on the outside of the first cavity (1903).
10. The basement wall water seepage crack sealing construction method according to claim 9, It is characterized in that In step S5, the following specific steps are included: S51: Remove the electric drill in the first through hole (1805); S52: applying a mold release agent to the outer surface of the first supporting flange (1804), and sleeve the first cavity (1903) of the prefabricated waterproof sleeve (19) on the outer surface of the first supporting flange (1804); S53: attaching first sealing strips (22) to the upper and lower ends of the first sealing plate (18) close to the end portions; S54: applying epoxy resin waterproof coating to the outer surface of the first side wall (1902) of the prefabricated waterproof jacket (19); S55: controlling the first sliding rod (8) and the second sliding rod (12) to move up and down in unison through the driving assembly (300), so that the first blocking plate (18) connected to the first sliding rod (8) and the second sliding rod (12) is aligned with the casting groove (20); S56: The first horizontal sliding motor (11) and the second horizontal sliding motor (15) drive the first sliding rod (8) and the second sliding rod (12) to slide horizontally along the side close to the wall (500) until the first sealing strip (22) is tightly sealed against the wall (500).
Citation Information
Patent Citations
Blocking system for water seepage crack of basement wall body and construction method thereof
CN106759842A
Basement enclosure wall water seepage position leaking stoppage reinforcing structure
CN212104216U
Basement downstream face leakage repairing and water stopping structure
CN214462854U
Stable anti-seepage mounting assembly
CN217518262U
The Method For Repairing Joint Part Of Concrete Structure With Multi-Layer
KR1020160080619A