Construction method for adding compensation load in water bag preloading
By calculating and setting the compensation load and increasing the filling load, the problem of insufficient additional stress in the gap area in the water bag preloading was solved, and the foundation reinforcement effect and construction efficiency were improved.
Patent Information
- Application Number
- CN202410760252.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-13
- Publication Date
- 2024-10-11
AI Technical Summary
In large-scale water bag stacking preloading, since the piled soil needs to be equipped with supporting facilities such as water collection wells, drainage ditches, and foundation monitoring instruments, there is a lack of preloading load in the gaps between the water bags, resulting in additional stress spreading in the gap area. Damage affects the effect of foundation reinforcement. Existing treatment measures are time-consuming, laborious and inefficient.
By calculating the transfer distribution of additional stress in the soil, setting the uniform load and compensation load, integrating along the rectangular range, determining the compensation load width, and determining the filling thickness according to the chart at the project site, increasing the filling load, and ensuring the water bag gap The additional stress in the area is not less than the preloading load of the large-scale water bag. Monitoring point monitoring data analysis and processing instructions are generated to adjust the construction.
The foundation reinforcement treatment effect in the water bag gap area is equivalent to that of the large-area paving water bag area, which avoids uneven settlement, improves construction efficiency, reduces dependence on professionals and equipment, and is economical and environmentally friendly.
Smart Images

Figure CN118761127A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of foundation treatment, and relates to a construction method for adding compensating loads in gaps during large-scale water bag paving preloading, and specifically to a construction method for adding compensating loads during water bag preloading. Background Art
[0002] In recent years, the preloading method using water bags as preloading carriers has been gradually applied to reinforce soft soil roadbeds. This type of roadbed is long and narrow, and the water bags are laid in strips. However, the foundation treatment range of the nearshore land formation project is large, the area is wide, and the shape is irregular. There is little research on the application of water-soil combined loading construction technology for this type of site, and there is currently no systematic construction method.
[0003] In the process of large-scale water-soil combined preloading, since supporting facilities such as water collection wells, drainage ditches, and foundation monitoring instruments need to be laid out for the loaded soil, a certain width of gaps (channels) must be planned and reserved between each fully paved water bag module. Since the preloading load of the water bag is missing in the gap range of the water bag, if no corresponding load compensation measures are taken, the additional stress of the water-soil combined preloading around the gap will diffuse and be damaged in the gap area, resulting in under-load preloading in the gap area of the water bag preloading, which affects the effect of the foundation reinforcement treatment and the site will have obvious uneven settlement after construction.
[0004] The existing treatment measures are generally: after the water and soil combined loading is completed, small sand bags are filled in the gaps of the channel to supplement the loading. However, this method is time-consuming and labor-intensive, and requires additional sand bags to be purchased and transported manually, which is inefficient and easily affects the construction period. Summary of the invention
[0005] The present invention provides a construction method for adding a compensating load in water bag preloading, which is used to solve the above-mentioned technical problems.
[0006] The first aspect of the present invention provides a construction method for adding a compensating load in a water bag preloading, comprising:
[0007] Step 1: Calculate the transmission and distribution of additional stress in the soil, specifically: simplify the large-scale water bag load into a large-scale uniformly distributed load, set the uniformly distributed load value and the long and short sides of the load range, take the coordinate origin at the vertex, take any differential area within the load area, and replace the load on it with a concentrated force, and calculate the vertical additional stress caused by the concentrated force at a depth z below the vertex of the load range; integrate along the entire rectangular range to obtain the additional stress at the vertex of the large-scale uniformly distributed load of the rectangle; add fill on both sides of the gap, set its width, and provide compensation load; when the compensation load is added on both sides of the gap, the additional stress brought by the water bag load at a depth of z at point M is, the additional stress brought by the compensation load is, and the additional stress after superposition at the depth z of the midpoint M of the water bag preload gap is;
[0008] Step 2: Analyze the compensation load using the control variable method: Calculate the additional stress value of the water bag load at the midpoint of the gap at different water bag gaps and different preloaded soil depths according to the water bag filling heights, and the compensation load value required when the additional stress is required to be no less than the large-scale water bag load, and compile the calculation results into a corresponding result diagram;
[0009] Step 3: According to the water bag loading height, reserved gap width and preloaded soil thickness at the project site, determine the compensation load according to the corresponding diagram of the results and convert it into fill thickness; first add the fill thickness, then lay the loaded water bags on top, and at the same time set up several monitoring points at the project site.
[0010] Optionally, the vertical additional stress is:
[0011] Where l is the long side of the load range, b is the short side of the load range, dP is the concentrated stress, and dP=pdA=pdxdy, dA=dxdy, dA is any differential area within the load area.
[0012] Optionally, the additional stress at the vertex is:
[0013] Where p0 is the set uniformly distributed load value.
[0014] Optionally, the additional stress caused by the water bag loading at the depth z of point M is:
[0015]
[0016] The additional stress caused by the compensation load is:
[0017]
[0018] The compensation load is:
[0019]
[0020] in, s is the gap between water bags or the spacing of reserved channels, and d is the width of the compensating load.
[0021] Optional, including:
[0022] Collect monitoring data of the monitoring point, the monitoring data includes the settlement value at the monitoring point and the receiving time corresponding to the stress value;
[0023] Analyze the monitoring data: Analyze the receiving time corresponding to the monitoring data to obtain the time delay value. When the time delay value is less than or equal to the set time delay threshold, generate a transmission processing instruction; otherwise, determine the settlement value and stress value at the monitoring point, compare the settlement value with the set settlement range, and compare the stress value with the corresponding set stress range; if the settlement value is within the settlement range and the stress value is within the stress range, perform a pre-change operation to generate a pre-change signal group, otherwise, generate an abnormal signal; the pre-change signal group includes pre-change signal one, pre-change signal two, pre-change signal three and a normal signal;
[0024] Process transmission processing instructions, abnormal signals and pre-change signal groups.
[0025] Optionally, the specific process of analyzing the receiving time corresponding to the monitoring data is:
[0026] Get the receiving time corresponding to the monitoring data, sort all the receiving times in order, calculate the time difference between two adjacent receiving times to get the receiving interval time, compare all the receiving interval time with the preset interval time, if the receiving interval time is greater than the preset interval time, mark the receiving interval time as the delay time, count the number of delay times, if the number is greater than the set number threshold, substitute the values of all the delay times into the line graph, get the delay point corresponding to the delay time, connect the two adjacent delay points in sequence to get the delay line, then connect the lines with one delay point in sequence to get the interval delay line, finally connect the first delay point and the last delay point to get a line and mark it as the start and end line, calculate the slope of all delay lines, sum all slopes greater than zero and take their values to get the positive delay value; sum all slopes less than zero Sum up all slopes less than zero and take their absolute values to obtain the negative value of delay, and divide the positive value of delay by the negative value of delay to obtain the delay ratio; calculate the area of the triangle enclosed by the separation line and the corresponding connection line and the slope of the separation line, and when the slope is a negative value, mark the numerical value of the area of the triangle corresponding to the connection line as the first numerical value; when the slope is a positive value, mark the numerical value of the area of the triangle corresponding to the connection line as the second numerical value; subtract the sum of all second numerical values from the sum of all first numerical values to obtain the separation value; identify the numerical values of the slopes of the start and end lines, set several numerical ranges, and each numerical range corresponds to a numerical coefficient; match the numerical value of the slope with several numerical ranges to obtain the corresponding numerical coefficient; multiply the numerical value of the slope by the corresponding numerical coefficient to obtain the start and end values; extract the numerical values of the delay ratio, the separation value, and the start and end values, perform weighted calculations, and then sum them up to obtain the duration delay value.
[0027] Optionally, the specific process of the pre-change operation is: obtain a number of settlement values and stress values within a preset time range and sort them in chronological order, calculate the difference between two adjacent settlement values to obtain the settlement interval difference, extract all settlement interval differences and take their average to obtain the settlement interval mean, and mark the value of the largest settlement interval difference as the maximum settlement value; then calculate the difference between the first and last settlement values and stress values in the sorting to obtain the settlement difference and stress difference, then calculate the collection interval duration of the first and last settlement values and stress values in the sorting to obtain the settlement duration and stress duration, divide the values of the settlement difference and stress difference by the corresponding values of the settlement duration and stress duration to obtain the settlement degree and stress degree; convert the values of the settlement interval mean and the maximum settlement value into length according to a certain ratio degree straight line, intersect the midpoints of the two length straight lines perpendicularly and construct a rhombus, select any corner point of the rhombus as the starting point, make a height perpendicular to the rhombus and equal to the settlement value, connect the remaining corner points of the rhombus to the end point of the height to obtain the vertebral body, extract the volume of the vertebral body and mark its value as the settlement pre-change value; when the settlement pre-change value is greater than the pre-change threshold value 1 and the stress intensity is greater than the stress threshold value 1, a pre-change signal 1 is generated; when the settlement pre-change value is less than or equal to the pre-change threshold value 1 and the stress intensity is greater than the stress threshold value 1, a pre-change signal 2 is generated; when the settlement pre-change value is greater than the pre-change threshold value 1 and the stress intensity is less than or equal to the stress threshold value 1, a pre-change signal 3 is generated; when the settlement pre-change value is less than or equal to the pre-change threshold value 1 and the stress intensity is less than or equal to the stress threshold value 1, a normal signal is generated.
[0028] Optionally, the process of processing the transmission processing instruction, the abnormal signal and the pre-change signal group is as follows:
[0029] When a transmission processing instruction is received, the transmission processing values of all technicians are obtained, and the transmission processing instruction and the location of the monitoring point are sent to the terminal with the largest transmission processing value, and the technician performs maintenance and replacement processing on the monitoring unit of the monitoring point;
[0030] When an abnormal signal is received, the prompt tag corresponding to the abnormal signal is matched and sent to the construction personnel's smart terminal together with the location of the corresponding monitoring point. The construction personnel then arrive at the location of the corresponding monitoring point to handle the abnormality and receive feedback from the construction personnel. If no feedback is received within a preset time range, the prompt tag and location are continuously sent until feedback is received.
[0031] When the pre-change signal 1, the pre-change signal 2, or the pre-change signal 3 is received, the corresponding preset viewing period is matched, and the matched viewing period and the location of the monitoring point are sent to the smart terminal of the construction personnel;
[0032] When a normal signal is received, the monitoring point and the normal signal are sent to the corresponding display terminal for display.
[0033] A second aspect of the present invention provides a computer device, comprising: a memory and at least one processor,
[0034] Instructions are stored in the memory; the at least one processor calls the instructions in the memory to enable the computer device to execute the above-mentioned construction method for adding a compensating load in water bag preloading.
[0035] A third aspect of the present invention provides a computer-readable storage medium, wherein instructions are stored in the computer-readable storage medium, which, when executed on a computer, enables the computer to execute the above-mentioned construction method for adding a compensating load to water bag preloading.
[0036] The technical solution provided by the present invention has the following beneficial effects compared with the prior art: after adding fill compensation load to the surrounding area of the gap, the foundation reinforcement treatment effect of the gap area is equivalent to or even better than that of the adjacent large-area paved water bag area, which can meet the requirement that the additional stress on the bottom of the pre-pressed soil in the gap range of the water bag is not less than the large-scale water bag pre-pressing load. This method only requires advance planning and conversion before large-scale pre-pressing, and adds part of the fill load when pre-pressing the soil on site. It does not require other additional equipment or materials, nor does it require professional personnel to operate the construction. It is constructed simultaneously with the pre-pressed soil loading, does not affect the construction period, is economical and environmentally friendly, and has high efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the following briefly introduces the drawings required for use in the description of the embodiments. The following drawings are not intentionally scaled to the actual size, and the focus is on illustrating the main purpose of the present application.
[0038] Figure 1 It is a schematic diagram of the process of the present invention;
[0039] Figure 2 The stress at a certain point under the rectangular area when the uniformly distributed load is applied in the present invention is shown in FIG. Figure 1 ;
[0040] Figure 3 The stress at a certain point under the rectangular area when the uniformly distributed load is applied in the present invention is shown in FIG. Figure 2 ;
[0041] Figure 4 It is a schematic plan view of the layout of the water bag gap compensation load of the present invention;
[0042] Figure 5 It is a schematic diagram of the layout of the water bag gap compensation load of the present invention;
[0043] Figure 6 This is a simplified diagram for calculating the water bag gap compensation load of the present invention;
[0044] Figure 7 This is a schematic diagram of additional stress at point M when the water bag of the present invention is filled with water at a height of 1.0 m;
[0045] Figure 8 This is a schematic diagram of additional stress at point M when the water bag of the present invention is filled with water at a height of 1.5 m;
[0046] Fig. 9 This is a schematic diagram of additional stress at point M when the water bag of the present invention is filled with water at a height of 2.0 m;
[0047] Fig.10 This is a schematic diagram of additional stress at point M when the water bag of the present invention is filled with water at a height of 2.5 m;
[0048] Fig.11 This is a schematic diagram of the compensation load when the water bag of the present invention is filled with water at a height of 1.0m;
[0049] Fig.12 This is a schematic diagram of the compensation load when the water bag of the present invention is filled with water at a height of 1.5m;
[0050] Fig.13 This is a schematic diagram of the compensation load when the water bag of the present invention is filled with water at a height of 2.0m;
[0051] Fig.14 This is a schematic diagram of the compensation load when the water bag of the present invention is filled with water at a height of 2.5m;
[0052] Fig.15 This is a block diagram of the internal principle of the server of the present invention;
[0053] Fig.16 It is a schematic diagram of a line graph of the present invention. DETAILED DESCRIPTION
[0054] Embodiments of the present invention provide an energy scheduling management method, apparatus, device and storage medium. The terms "first", "second", "third", "fourth", etc. (if any) in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments described herein can be implemented in an order other than that illustrated or described herein. In addition, the terms "including" or "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0055] Example 1: Please refer to Figure 1 - Figure 3 As shown, a construction method for adding a compensating load in a water bag preloading comprises:
[0056] First, we study the calculation of the transfer and distribution of additional stress in the soil. Simplify the large-scale water bag load into a large-scale uniformly distributed load. Assume that the uniformly distributed load value is p0, the long side of the load range is l, and the short side is b. Take the origin of the coordinate system at the vertex O. Take any differential area dA=dxdy within the load area, and replace the load on it with the concentrated force dP. Then dP=pdA=pdxdy. The above formula can be used to calculate the vertical additional stress dσ caused by the concentrated force at the depth z below the vertex of the load range. z :
[0057]
[0058] Integrate the above formula along the entire rectangular range to obtain the additional stress σ at the vertex of the large-scale uniformly distributed load p0 in the rectangle. z :
[0059]
[0060] According to the principle of stress diffusion, transmission and mutual superposition in soil, the additional stress σ at the depth z at the midpoint M of the water bag gap is z1 It must be smaller than other loading areas. In order to make the additional stress at point M reach the large-area loading design stress p0, additional fill is required on both sides of the gap, with a width of d, to provide a compensation load Δp. The calculation diagram and plane diagram are shown in the figure. Figure 4 - Figure 6 As shown:
[0061] Figure 6 In the equation, s is the spacing of the water bag gap (reserved channel). When the compensation load Δp is added on both sides of the channel, the additional stress caused by the water bag loading at the depth z of point M is σ z1 , the additional stress caused by the compensating load is σ z2 , the additional stress after superposition at the midpoint M of the water bag preload gap at a depth of z is: σ z =σ z1 +σ z2 , where σ z1 and σ z2 They are:
[0062]
[0063] in
[0064] If the additional stress of the water bag preload in the soil is to be no less than the additional stress of other large-scale water bag loads, then: z ≥p0, the compensation load Δp is:
[0065]
[0066] Based on the above theoretical calculation method, the compensation load is analyzed by the control variable method. According to the four conventional water bag filling heights (H = 1.0m, 1.5m, 2.0m, 2.5m), the additional stress value of the water bag load at the midpoint M of the gap and the compensation load Δp value required when the additional stress is not less than the large range of water bag load are calculated at different water bag gaps s and different preloading soil depths z, and the calculation results are statistically compiled into a graph.
[0067] according to Figure 7 - Fig.10 Analysis shows that under different water filling height conditions of the water bag, the water bag gap M point has different degrees of additional stress loss, and the loss degree is about 12% to 64%. At the same depth, the larger the water bag spacing, the higher the loss degree; at the same gap spacing, the smaller the preloading soil thickness, the more additional stress loss, and the greater the preloading soil thickness, the more additional stress gradually tends to be stable, but its value is always smaller than the large range of water bag preloading load.
[0068] Since the M points of the water bag gap have different degrees of additional stress loss, it is necessary to add corresponding loads around the water bag gap (the width of both sides of the gap is not less than 5m) to compensate for the loss stress. Fig.11 - Fig.14 Analysis shows that when the thickness of the preloaded soil is smaller, the required compensation load is larger, and when the thickness of the preloaded soil is larger, the required compensation load approaches a stable value, which is consistent with the law of stress transfer in foundation soil.
[0069] In actual applications, the compensation load is determined according to the water bag loading height, reserved gap width and preloaded soil thickness at the project site, and converted into fill thickness according to the corresponding chart of the results. In the actual loading process, the fill thickness is supplemented first, and then the loading water bags are laid on top.
[0070] After the present invention increases the fill compensation load in the surrounding area of the gap, the foundation reinforcement treatment effect of the gap area is equivalent to or even better than the treatment effect of the adjacent large-area paved water bag area, and can meet the requirement that the additional stress on the bottom surface of the pre-compressed soil in the gap range of the water bag is not less than the large-area water bag pre-compression load.
[0071] From the perspective of engineering benefits, this method only requires advance planning and conversion before large-scale preloading, and adding part of the fill load when preloading the soil on site. No other additional equipment or materials are required, and no professional personnel are required to operate the construction. It can be constructed simultaneously with the preloading of soil, does not affect the construction period, is economical, environmentally friendly, and highly efficient.
[0072] Embodiment 2: Based on Embodiment 1, several monitoring points are arranged in the project site, and monitoring units are arranged in the monitoring points. The monitoring units are used to collect monitoring data corresponding to the monitoring points and send them to the server. The monitoring data includes the settlement value at the monitoring point and the receiving time corresponding to the stress value; the server is provided with a data analysis unit and a signal processing unit, such as Fig.15 As shown, the data analysis unit is used to analyze the monitoring data, and the specific analysis process is:
[0073] Get the receiving time corresponding to the monitoring data, sort all the receiving times in order, calculate the time difference between two adjacent receiving times to get the receiving interval duration, compare all the receiving interval durations with the preset interval durations, if the receiving interval duration is greater than the preset interval duration, then the receiving interval duration is marked as the delay duration, count the number of delay durations, if the number is greater than the set number threshold, substitute all the values of the delay durations into the line chart, such as Fig.16 As shown, the delay point corresponding to the delay time is obtained, and the adjacent two delay points are connected in sequence to obtain the delay line, and then the delay points are connected in sequence to obtain the separation delay line, and finally the first delay point and the last delay point are connected to obtain a line and marked as the start and end line, and the slopes of all the delay lines are calculated, and all slopes greater than zero are summed and taken to obtain the positive delay value; all slopes less than zero are summed and taken to obtain the negative delay value, and the positive delay value is divided by the negative delay value to obtain the delay ratio; the triangle enclosed by the separation delay line and the corresponding delay line is calculated. The area of the shape and the slope of the separation line. When the slope is a negative value, the numerical value of the triangle area corresponding to the connection line is marked as the first numerical value; when the slope is a positive value, the numerical value of the triangle area corresponding to the connection line is marked as the second numerical value; the sum of all the first numerical values minus the sum of all the second numerical values is obtained to obtain the separation value; the numerical value of the slope of the start and end lines is identified, and several numerical ranges are set, each numerical range corresponds to a numerical coefficient; the numerical coefficient has a value range of (0, 1), and the numerical coefficient is proportional to the slope. The larger the slope, the larger the corresponding numerical coefficient;
[0074] Match the value of the slope with several value ranges to obtain the corresponding numerical coefficient; multiply the value of the slope by the corresponding numerical coefficient to obtain the start and end values; extract the values of the delay ratio, the interval value and the start and end values and perform weighted calculation, and then sum them to obtain the time delay value; when the time delay value is less than or equal to the set delay threshold, generate a transmission processing instruction and send it to the signal processing unit, and send an abnormal signal to the signal processing unit;
[0075] The specific process of the pre-change operation is as follows: obtain a number of settlement values and stress values within a preset time range and sort them in chronological order, calculate the difference between two adjacent settlement values to obtain the settlement interval difference, extract all settlement interval differences and take their average to obtain the settlement interval mean, and mark the value of the largest settlement interval difference as the maximum settlement value; then calculate the difference between the settlement value and the stress value at the front and the end of the sort to obtain the settlement difference and stress difference, then calculate the collection interval time of the settlement value and the stress value at the front and the end of the sort to obtain the settlement time and stress time, divide the settlement difference and stress difference values by the corresponding settlement time and stress time values to obtain the settlement degree and stress degree; convert the values of the settlement interval mean and the maximum settlement value into length straight lines according to a certain ratio, and connect the midpoints of the two length straight lines vertically. Construct a rhombus by intersection and union, select any corner point of the rhombus as the starting point, make a height perpendicular to the rhombus and equal to the settlement value, connect the remaining corner points of the rhombus to the end point of the height to obtain a cone, extract the volume of the cone and mark its value as the settlement pre-change value; when the settlement pre-change value is greater than the pre-change threshold value 1 and the stress is greater than the stress threshold value 1, a pre-change signal 1 is generated; when the settlement pre-change value is less than or equal to the pre-change threshold value 1 and the stress is greater than the stress threshold value 1, a pre-change signal 2 is generated; when the settlement pre-change value is greater than the pre-change threshold value 1 and the stress is less than or equal to the stress threshold value 1, a pre-change signal 3 is generated; when the settlement pre-change value is less than or equal to the pre-change threshold value 1 and the stress is less than or equal to the stress threshold value 1, a normal signal is generated, and the pre-change signal 1, the pre-change signal 2, the pre-change signal 3 and the normal signal are sent to the signal processing unit;
[0076] The signal processing unit is used to process the received signal or instruction, specifically:
[0077] When a transmission processing instruction is received, the transmission processing values of all technicians are obtained, and the transmission processing instruction and the location of the monitoring point are sent to the terminal with the largest transmission processing value, and the technician performs maintenance and replacement processing on the monitoring unit of the monitoring point; the transmission processing value is obtained by weighted calculation of the distance between the technician's current location and the location of the corresponding monitoring point, the length of time on the job, and the total number of processing times, wherein the smaller the distance, the larger the transmission processing value, and the larger the length of time on the job and the total number of processing times, the larger the transmission processing value;
[0078] When an abnormal signal is received, the prompt tag corresponding to the abnormal signal is matched and sent to the construction personnel's smart terminal together with the location of the corresponding monitoring point. The construction personnel then arrive at the location of the corresponding monitoring point to handle the abnormality and receive feedback from the construction personnel. If no feedback is received within a preset time range, the prompt tag and location are continuously sent until feedback is received.
[0079] When the pre-change signal 1, the pre-change signal 2, or the pre-change signal 3 is received, the corresponding preset viewing period is matched, and the matched viewing period and the location of the monitoring point are sent to the smart terminal of the construction personnel;
[0080] When a normal signal is received, the monitoring point and the normal signal are sent to the corresponding display terminal for display.
[0081] By monitoring the settlement and stress of the monitoring points, abnormalities can be detected in advance to avoid excessive or insufficient local settlement, which would affect the overall reinforcement effect.
[0082] The present invention provides a computer device, comprising: a memory and at least one processor,
[0083] Instructions are stored in the memory; the at least one processor calls the instructions in the memory to enable the computer device to execute the above-mentioned construction method for adding a compensating load in water bag preloading.
[0084] The present invention provides a computer-readable storage medium, in which instructions are stored. When the computer-readable storage medium is run on a computer, the computer is enabled to execute the above-mentioned construction method for adding a compensating load in water bag stacking preloading.
[0085] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0086] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk and other media that can store program code.
[0087] As described above, the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features thereof may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A construction method for adding compensating load in water bag preloading, characterized in that: include: Step 1: Calculate the transmission and distribution of additional stress in the soil, specifically: simplify the large-scale water bag load into a large-scale uniformly distributed load, set the uniformly distributed load value and the long and short sides of the load range, take the origin of the coordinate at the vertex, take any differential area within the load area, and replace the load on it with a concentrated force, and calculate the vertical additional stress caused by the concentrated force at a depth z below the vertex of the load range; Integrate along the entire rectangular range, and the additional stress at the vertex of the large-scale uniformly distributed load of the rectangle is obtained; add fill soil on both sides of the gap, set its width, and provide compensation load; when the compensation load is added on both sides of the gap, the additional stress caused by the water bag load at the depth z of point M is σ z1 , the additional stress caused by the compensating load is σ z2 , the additional stress after superposition at the midpoint M of the water bag preload gap at depth z is σ z =σ z1 +σ z2 ; Step 2: Analyze the compensation load using the control variable method: Calculate the additional stress value of the water bag load at the midpoint of the gap at different water bag gaps and different preloaded soil depths according to the water bag filling heights, and the compensation load value required when the additional stress is required to be no less than the large-scale water bag load, and compile the calculation results into a corresponding result diagram; Step 3: According to the water bag loading height, reserved gap width and preloaded soil thickness at the project site, determine the compensation load according to the corresponding diagram of the results and convert it into fill thickness; first add the fill thickness, then lay the loaded water bags on top, and at the same time set up several monitoring points at the project site.
2. A construction method for adding compensating load in water bag preloading according to claim 1, characterized in that: The vertical additional stress is: Where l is the long side of the load range, b is the short side of the load range, dP is the concentrated stress, and dP=pdA=pdxdy, dA=dxdy, dA is any differential area within the load area.
3. A construction method for adding compensating load in water bag preloading according to claim 2, characterized in that: The additional stress at the vertex is: Where p0 is the set uniformly distributed load value.
4. A construction method for adding compensating load in water bag preloading according to claim 3, characterized in that: The additional stress caused by the water bag loading at the depth z of point M is: The additional stress caused by the compensation load is: The compensation load is: in, s is the gap between water bags or the spacing of reserved channels, and d is the width of the compensating load.
5. A construction method for adding compensating load in water bag preloading according to claim 1, characterized in that: Also includes: Collect monitoring data of the monitoring point, including the settlement value at the monitoring point and the receiving time corresponding to the stress value; Analyze the monitoring data: Analyze the receiving time corresponding to the monitoring data to obtain the delay value. When the delay value is less than or equal to the set delay threshold, generate a transmission processing instruction; No, determine the settlement value and stress value at the monitoring point, compare the settlement value with the set settlement range, and compare the stress value with the corresponding set stress range; If the settlement value is within the settlement range and the stress value is within the stress range, a pre-change operation is performed to generate a pre-change signal group; otherwise, an abnormal signal is generated; the pre-change signal group includes pre-change signal 1, pre-change signal 2, pre-change signal 3 and a normal signal; Process transmission processing instructions, abnormal signals and pre-change signal groups.
6. A construction method for adding compensating load in water bag preloading according to claim 5, characterized in that: The specific process of analyzing the receiving time corresponding to the monitoring data is as follows: Get the receiving time corresponding to the monitoring data, sort all the receiving times in order, calculate the time difference between two adjacent receiving times to get the receiving interval time, compare all the receiving interval time with the preset interval time, if the receiving interval time is greater than the preset interval time, mark the receiving interval time as the delay time, count the number of delay times, if the number is greater than the set number threshold, substitute the values of all the delay times into the line graph, get the delay point corresponding to the delay time, connect the two adjacent delay points in sequence to get the delay line, then connect the lines with one delay point in sequence to get the interval delay line, finally connect the first delay point and the last delay point to get a line and mark it as the start and end line, calculate the slope of all delay lines, sum all slopes greater than zero and take their values to get the positive delay value; sum all slopes less than zero Sum up all slopes less than zero and take their absolute values to obtain the negative value of delay, and divide the positive value of delay by the negative value of delay to obtain the delay ratio; calculate the area of the triangle enclosed by the separation line and the corresponding connection line and the slope of the separation line, and when the slope is a negative value, mark the numerical value of the area of the triangle corresponding to the connection line as the first numerical value; when the slope is a positive value, mark the numerical value of the area of the triangle corresponding to the connection line as the second numerical value; subtract the sum of all second numerical values from the sum of all first numerical values to obtain the separation value; identify the numerical values of the slopes of the start and end lines, set several numerical ranges, and each numerical range corresponds to a numerical coefficient; match the numerical value of the slope with several numerical ranges to obtain the corresponding numerical coefficient; multiply the numerical value of the slope by the corresponding numerical coefficient to obtain the start and end values; extract the numerical values of the delay ratio, the separation value, and the start and end values, perform weighted calculations, and then sum them up to obtain the duration delay value.
7. A construction method for adding compensating load in water bag preloading according to claim 5, characterized in that: The specific process of the pre-change operation is as follows: obtain a number of settlement values and stress values within a preset time range and sort them in chronological order, calculate the difference between two adjacent settlement values to obtain the settlement interval difference, extract all settlement interval differences and take their average to obtain the mean settlement interval difference, and mark the value of the largest settlement interval difference as the maximum settlement value; then calculate the difference between the settlement value and the stress value at the front and the end of the sort to obtain the settlement difference and stress difference, then calculate the collection interval time of the settlement value and the stress value at the front and the end of the sort to obtain the settlement time and stress time, divide the values of the settlement difference and stress difference by the corresponding values of the settlement time and stress time to obtain the settlement degree and stress degree; convert the values of the mean settlement interval and the maximum settlement value into length straight lines according to a certain ratio line, intersect the midpoints of the two length straight lines vertically and construct a rhombus, select any corner point of the rhombus as the starting point, make a height perpendicular to the rhombus and equal to the settlement value, connect the remaining corner points of the rhombus to the end point of the height to obtain the vertebral body, extract the volume of the vertebral body and mark its value as the settlement pre-change value; when the settlement pre-change value is greater than the pre-change threshold value 1 and the stress force is greater than the stress threshold value 1, a pre-change signal 1 is generated; when the settlement pre-change value is less than or equal to the pre-change threshold value 1 and the stress force is greater than the stress threshold value 1, a pre-change signal 2 is generated; when the settlement pre-change value is greater than the pre-change threshold value 1 and the stress force is less than or equal to the stress threshold value 1, a pre-change signal 3 is generated; when the settlement pre-change value is less than or equal to the pre-change threshold value 1 and the stress force is less than or equal to the stress threshold value 1, a normal signal is generated.
8. A construction method for adding compensating load in water bag preloading according to claim 5, characterized in that: The process of processing the transmission processing instruction, abnormal signal and pre-change signal group is as follows: When a transmission processing instruction is received, the transmission processing values of all technicians are obtained, and the transmission processing instruction and the location of the monitoring point are sent to the terminal with the largest transmission processing value, and the technician performs maintenance and replacement processing on the monitoring unit of the monitoring point; When an abnormal signal is received, the prompt tag corresponding to the abnormal signal is matched and sent to the construction personnel's smart terminal together with the location of the corresponding monitoring point. The construction personnel then arrive at the location of the corresponding monitoring point to handle the abnormality and receive feedback from the construction personnel. If no feedback is received within a preset time range, the prompt tag and location are continuously sent until feedback is received. When the pre-change signal 1, the pre-change signal 2, or the pre-change signal 3 is received, the corresponding preset viewing period is matched, and the matched viewing period and the location of the monitoring point are sent to the smart terminal of the construction personnel; When a normal signal is received, the monitoring point and the normal signal are sent to the corresponding display terminal for display.
9. A computer device, characterized in that: The device includes: a memory and at least one processor, wherein instructions are stored in the memory; the at least one processor calls the instructions in the memory so that the computer device executes a construction method for adding a compensating load in water bag preloading as described in any one of claims 1-8.
10. A computer-readable storage medium having instructions stored thereon, characterized in that: When the instructions are executed by the processor, a construction method for adding a compensating load to water bag preloading is implemented as described in any one of claims 1-8.