Rapid excavation method for deep falling pit in foundation pit under high confined water head

By narrowing the floor of the shallow pit area and increasing the length of the support, the backhoe excavator is allowed to enter the deep pit area, which solves the problems of low earth excavation efficiency and long exposure time of the foundation pit in the deep pit area under high pressure water head. problems, achieving a safer and more efficient construction process.

CN118774136APending Publication Date: 2024-10-15SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411027607.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In the existing technology, the steel support structure of the deep pit in the foundation pit under high pressure water head leads to low earth excavation and transportation efficiency, long exposure time of the foundation pit, affecting the safety of the foundation pit, and high pressure reduction control cost of high pressure water. There is great danger and unpredictability.

Method used

By narrowing the width of the floor in the shallow pit area, increasing the length of the bracing in the deep pit area, reducing the number of bracing in the middle area, widening the spacing and connecting it through steel purlins, the backhoe excavator is allowed to be hoisted vertically into the pit for excavation operations. Adjust the angle brace layout relationship and use the finite element method to calculate the internal force and deformation of the support structure.

Benefits of technology

It improves the efficiency of excavation and transportation in deep pit areas, shortens the construction period, reduces the cost of high pressure water pressure reduction control, enhances the stability and safety of foundation pits, and avoids potential environmental risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774136A_ABST
    Figure CN118774136A_ABST
Patent Text Reader

Abstract

The invention discloses a rapid excavation method for a falling deep pit in a foundation pit under a high confined water head, which comprises the following steps of: narrowing the width of a bottom plate of a shallow pit area so as to increase the distance between a boundary line of the falling deep pit area and the shallow pit area and the bottom plate of the shallow pit area close to the side where the falling deep pit area is located; the length of each diagonal brace between the foundation pit enclosure wall of the deep pit area and the corrected bottom plate of the shallow pit area is increased, the number of the diagonal braces in the middle area between the foundation pit enclosure wall of the deep pit area and the corrected bottom plate of the shallow pit area after the length is increased is reduced, and the distance is widened; arranging the diagonal bracings of which the spacing is widened on the foundation pit enclosure wall through steel enclosing purlins; and the backhoe type excavator is vertically hoisted to the deep pit area through the gap of the opposite supports with the width adjusting interval to carry out earth cutting in the pit, and the deep pit is formed. The construction efficiency of earth cutting and transportation in the deep pit area can be improved, and the construction period is shortened; the exposure time of the foundation pit is shortened, and the safety of the foundation pit is guaranteed; and the pressure reduction control time of the high-pressure-bearing water is shortened, and the control cost of the high-pressure-bearing water is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a method for quickly excavating a deep pit in a foundation pit under a high pressure head. Background Art

[0002] A rainwater storage tank is a rainwater collection facility that temporarily retains the peak flow of rainwater runoff in the tank, and then slowly discharges the rainwater from the storage tank after the maximum flow drops. This can not only avoid rainwater peaks and improve rainwater utilization, but also play a positive role in drainage scheduling between drainage areas. When a rainwater storage tank is integrated under an underground building structure, it forms a high and low pit with the foundation pit of the underground building structure. The foundation pit of the underground building structure with a shallow depth is a shallow pit, and the foundation pit of the rainwater storage tank with a deeper depth is a deep pit. The deep pit has a narrow space and a small area. The height difference between the deep pit and the shallow pit is not large, generally within 2.5m; please refer to Figure 1 The deep pit belongs to an ultra-deep foundation pit, with an underground continuous wall as the foundation pit retaining wall. The position of the foundation pit bottom plate does not meet the conditions for simultaneous construction of high and low pits, and an additional steel support 9 is required. The angle brace combined with the brace is mostly adopted, including two angle braces 13 arranged between the corners of the foundation pit retaining wall 8 in the deep pit area, one angle brace 13 arranged between the thickness center of the foundation pit retaining wall 8 in the deep pit area and the bottom plate 6 in the shallow pit area, and multiple braces 9 arranged horizontally between the foundation pit retaining wall 8 in the deep pit area and the thickness center of the bottom plate 6 in the shallow pit area to ensure the safety of the deep pit; due to the deep depth of the deep pit, considering the stability of the foundation pit against sudden surge, it is generally necessary to reduce the pressure of the high-pressure water, which makes the last layer of earthwork of the deep pit must be constructed before the bottom plate of the shallow pit area is constructed The excavation can only be started after the strength requirements are met. When the last layer of earthwork in the deep pit is excavated, the dense arrangement of the supports makes the excavation space cramped and narrow. The deep pit area can only be excavated and transported vertically by the vertical excavation grab placed on the top of the pit. The areas blocked by the supports and angle supports and the corner areas are excavated by manual excavation and manual transportation. A backhoe excavator cannot be used to enter the deep pit area for excavation, resulting in low excavation efficiency and low earthwork transportation efficiency in the deep pit area. The longer the foundation pit is exposed, the lower the safety of the foundation pit. The extended pressurized precipitation period not only prolongs the construction period of the rainwater storage tank deep pit, but also increases the cost of high-pressure water depressurization control, and also has a greater risk and unpredictability on the stability of the foundation pit itself and the surrounding environment. Summary of the invention

[0003] The purpose of the present invention is to provide a method for quickly excavating a deep pit in a foundation pit under a high pressure head, so as to solve the problems that the existing steel support structure in the deep pit area causes low efficiency in earth excavation and transportation when excavating earth through a vertical digging grab bucket on the top of the pit and manual supplementary excavation; the long exposure time of the foundation pit affects the safety of the foundation pit; the pressure reduction control time of the pressurized water is long, which not only prolongs the construction period of the deep pit, but also increases the cost of high pressure water control, and also has great danger and unpredictability on the stability of the foundation pit itself and the surrounding environment.

[0004] In order to solve the above technical problems, the present invention provides a method for rapidly excavating a deep pit in a foundation pit under high pressure head, comprising:

[0005] Narrow the width of the bottom plate of the shallow pit area to increase the distance between the boundary line of the deep pit area and the shallow pit area and the bottom plate of the shallow pit area close to the side where the deep pit area is located;

[0006] The length of each brace between the foundation pit retaining wall of the deep pit area and the revised bottom plate of the shallow pit area is increased. Under the condition of satisfying the internal force and deformation of the foundation pit retaining wall, the number of braces with increased length in the middle area between the foundation pit retaining wall of the deep pit area and the revised bottom plate of the shallow pit area is reduced and the spacing is widened. Each brace with the widened spacing is set on the foundation pit retaining wall through steel purlins;

[0007] The backhoe excavator is vertically hoisted and transported into the deep pit area through the gap between two widened supports to perform excavation operations in the pit to form the deep pit.

[0008] Furthermore, the present invention provides a method for rapid excavation of a deep pit in a foundation pit under high pressure head, and the correction of the support in the deep pit area also includes: adjusting the arrangement relationship between the support and the bottom plate of the shallow pit area from thickness center alignment to upper surface alignment.

[0009] Furthermore, the method for rapidly excavating a deep pit in a foundation pit under a high pressure head provided by the present invention further includes:

[0010] Correct the corner braces in the deep pit area, and adjust the arrangement relationship between the corner braces between the foundation pit retaining walls at the corners of the deep pit area and the bottom plate of the shallow pit area from thickness center alignment to upper surface alignment.

[0011] Furthermore, the rapid excavation method for a deep pit in a foundation pit under high pressure head provided by the present invention, wherein the correction angle brace of the deep pit area further comprises:

[0012] Cancel the angle braces between the pit retaining wall in the deep pit area and the revised bottom plate in the shallow pit area, change the two outermost braces into angle braces as new angle braces and set them on the outside of the original angle braces between the pit retaining walls at the corners of the deep pit area.

[0013] Furthermore, the present invention provides a method for rapid excavation of a deep pit in a foundation pit under high pressure head. In the modified deep pit area support, a plane elastic foundation beam method or a continuous medium finite element method is used to calculate the internal force and deformation of the foundation pit retaining wall.

[0014] Furthermore, the method for rapid excavation of a deep pit in a foundation pit under high pressure head provided by the present invention is calculated based on the linear elastic beam-slab finite element method. On the premise that both stability and strength meet the requirements, the length of the brace is adjusted, and the width of the bottom plate of the shallow pit area after narrowing is determined according to the length of the brace after the increased length.

[0015] Furthermore, in the method for rapidly excavating a deep pit in a foundation pit under a high pressure head provided by the present invention, the support is a steel support.

[0016] Furthermore, the present invention provides a method for rapidly excavating a deep pit in a foundation pit under a high pressure head, wherein the steel perimeter purlin is composed of two H-shaped steels spliced ​​together.

[0017] Furthermore, in the method for rapid excavation of a deep pit in a foundation pit under a high pressure head provided by the present invention, the length of the braces extending from both ends of the steel purlin to both sides is more than 1.0 m.

[0018] Furthermore, the present invention provides a method for rapidly excavating a deep pit in a foundation pit under a high pressure head, constructing a bottom plate of the deep pit area, constructing a retaining wall at the vertical boundary of the deep pit area and the shallow pit area, and constructing a shallow pit area filling bottom plate between the retaining wall and the shallow pit area bottom plate to complete the width of the shallow pit area bottom plate.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] The invention provides a rapid excavation method for a deep pit in a foundation pit under a high pressure head. The method increases the distance between the bottom plate of the shallow pit area and the boundary line between the deep pit area and the shallow pit area by narrowing the width of the bottom plate of the shallow pit area, increases the length of each brace between the foundation pit retaining wall of the deep pit area and the corrected bottom plate of the shallow pit area, reduces the number of braces in the middle area, widens the spacing between multiple braces in the middle area, and connects the braces with the widened spacing to the foundation pit retaining wall through steel purlins, thereby ensuring that the braces with the widened spacing are located at the foundation pit. The structure on the pit retaining wall is stressed, and an effective support system is formed in the foundation pit of the deep pit area to control the deformation of the foundation pit in the deep pit area and ensure the safety of the foundation pit construction; then the backhoe excavator is vertically hoisted and transported into the deep pit area through the widened spacing of the support gaps to carry out excavation operations in the pit to form a deep pit. Narrowing the width of the bottom plate in the shallow pit area and increasing the length of the support can provide a wider operating radius for the backhoe excavator, expand the excavation operation space of the backhoe excavator, and facilitate excavation operations. Compared with the method of excavating deep pits by combining vertical excavation grabs on the pit top and manual excavation, excavating at the bottom of the deep pit area with a backhoe excavator improves the construction efficiency of excavation and transportation in the deep pit area and shortens the construction period of forming the deep pit; reduces the exposure time of the foundation pit, ensures the safety of the foundation pit, and avoids the risk of leakage and collapse of the foundation pit; reduces the time for high-pressure water pressure reduction control and reduces the control cost of high-pressure water; avoids the long excavation construction period in the deep pit area, which leads to greater danger and unpredictability in the stability of the foundation pit itself and the surrounding environment. Safety risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a schematic diagram of the plane structure of the deep pit area before the steel support is modified;

[0022] Figure 2 It is a schematic diagram of the revised plan structure of the steel support in the deep pit area;

[0023] Figure 3 It is a schematic diagram of the facade structure after the steel support in the deep pit area is revised;

[0024] Figure 4 It is a schematic diagram of the elevation structure of the bottom plate and the retaining wall of the deep pit area and the bottom plate for filling the gap in the shallow pit area;

[0025] As shown in the figure:

[0026] 1. Crown beam, 2. Steel support, 3. Reinforced concrete purlin, 4. Reinforced concrete support, 5. One column and one pile, 6. Bottom plate of shallow pit area, 7. Reinforced soil, 8. Foundation pit retaining wall, 9. Bracing, 10. Backhoe excavator, 11. Deep pit area, 12. Shallow pit area, 13. Corner brace, 14. New corner brace, 15. Boundary line, 16. Steel purlin, 17. Bottom plate of deep pit area, 18. Retaining wall, 19. Filling the bottom plate of shallow pit area. DETAILED DESCRIPTION

[0027] The present invention is described in detail below in conjunction with the accompanying drawings: The advantages and features of the present invention will become more apparent from the following description. It should be noted that the accompanying drawings are in very simplified form and in non-precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.

[0028] Please refer to Figures 1 to 3 The embodiment of the present invention provides a method for rapidly excavating a deep pit in a foundation pit under a high pressure head, which may include the following steps:

[0029] Step S101, correct the width of the shallow pit area bottom plate 6. Specifically, narrow the width of the shallow pit area bottom plate 6 to increase the distance between the boundary line 15 between the deep pit area 11 and the shallow pit area 12 and the shallow pit area bottom plate 6 near the side where the deep pit area 11 is located. Figure 1 The width of the shallow pit area bottom plate 6 is narrowed to Figure 2 That is to say, Figure 1 The distance C1 between the boundary line 15 in the shallow pit area and the bottom plate 6 is adjusted to Figure 2 The distance C2 between the boundary line 15 and the bottom plate 6 of the shallow pit area, where Figure 1 , Figure 2 The boundary line 15 is the same, Figure 1 C1 in is 1.0m, Figure 2 The C in is 4.0m-5.0m.

[0030] Step S102, correct the length of the braces 9 in the deep pit area. Specifically, increase the length of each brace 9 between the foundation pit retaining wall 8 of the deep pit area 11 and the corrected shallow pit area bottom plate 6. Under the condition of satisfying the internal force and deformation of the foundation pit retaining wall 8, reduce the number of braces 9 with increased length in the middle area between the foundation pit retaining wall 8 of the deep pit area 11 and the corrected shallow pit area bottom plate 6 and widen the spacing. Set each brace 9 with the widened spacing on the foundation pit retaining wall 8 through the steel purlin 16. The internal force of the foundation pit retaining wall 8 includes the bending moment, axial force, shear force, etc. generated by the soil pressure, water pressure and additional loads, which are the structural forces of the foundation pit retaining wall 8. Step S102 is to Figure 1 The four braces 9 with a spacing of A1 in the middle area are adjusted to Figure 2 The middle area of ​​the three braces 9 is spaced A2 apart, where A1 is 2.0m-3.0m and A2 is 3.5m-4.0m. Figure 1 The number of the braces 9 in the middle region is not limited to four, Figure 2 The number of supports in the middle area is not limited to being reduced by only one. Figure 1 to Figure 2In the process of reducing the number of the four pairs of supports 9 in the middle area to three pairs of supports 9, the width between the pairs of supports 9 in the middle area is adjusted by reducing the number of the pairs of supports 9 to a minimum, so as to ensure the steel support stress of the deep pit area 11 and form an effective support. Figure 1 and Figure 2 By comparison, the spacing of the remaining braces 9 outside the middle area is kept Figure 1 Of course, the number of the braces 9 in the middle area may not be reduced, and only the width between any two braces 9 in the middle area may be adjusted to ensure the support stress of the foundation pit in the deep pit area 11 and the safety of the foundation pit construction in the deep pit area 11.

[0031] Step S103, the backhoe excavator 10 is vertically hoisted and transported into the deep pit area 11 through the gap between the two widened supports 9 to perform digging operations in the pit to form a deep pit. That is, the purpose of the widened supports 9 is to enable the backhoe excavator 10 to enter the deep pit area 11 within the gap between the widened supports 9, that is, to enter the pit bottom of the deep pit area 11 to perform digging operations.

[0032] Please refer to Figures 1 to 3The method for rapidly excavating a deep pit in a foundation pit under a high pressure head provided by an embodiment of the present invention increases the distance between the bottom plate 6 of the shallow pit area and the boundary line 15 between the bottom plate 6 of the shallow pit area and the deep pit area 11 and the shallow pit area 12 by narrowing the width of the bottom plate 6 of the shallow pit area, increases the length of each brace 9 between the foundation pit retaining wall 8 of the deep pit area 11 and the corrected bottom plate 6 of the shallow pit area, reduces the number of braces 9 in the middle area, widens the spacing between multiple braces 9 in the middle area, and connects the connecting nodes of the braces 9 with the widened spacing and the foundation pit retaining wall 8 through a steel purlin 16, thereby ensuring that the widened spacing of the braces The support 9 is subjected to structural stress on the foundation pit retaining wall 8, and an effective support system is formed in the foundation pit of the deep pit area 11 to control the deformation of the foundation pit in the deep pit area 11, thereby ensuring the safety of the foundation pit construction; then the backhoe excavator 10 is vertically hoisted and transported into the deep pit area 11 through the gap between the widened supports 9 to carry out excavation operations in the pit to form a deep pit, wherein narrowing the width of the bottom plate 6 in the shallow pit area and increasing the length of the support 9 can provide a wider operating radius for the backhoe excavator 10, expand the excavation operation space of the backhoe excavator 10, and facilitate excavation operations. Compared with the method of excavating the deep pit by combining a vertical excavation grab at the pit top and manual excavation, excavating at the bottom of the deep pit area 11 by a backhoe excavator 10 improves the construction efficiency of excavation and transportation in the deep pit area 11 and shortens the construction period for forming the deep pit; reduces the exposure time of the foundation pit, ensures the safety of the foundation pit, and avoids the risk of leakage and collapse of the foundation pit; reduces the pressure reduction control time of high-pressure water and reduces the control cost of high-pressure water; avoids the safety risk of greater danger and unpredictability of the foundation pit's own stability and the surrounding environment due to the long excavation construction period in the deep pit area 11.

[0033] Please refer to Figures 2 to 3 In order to improve the clearance height of the backhoe excavator 10 during the excavation operation in the area of ​​the support 9, the rapid excavation method of the deep pit in the foundation pit under high pressure head provided by the embodiment of the present invention can also include: adjusting the arrangement relationship between the support 9 and the bottom plate 6 of the shallow pit area from thickness center alignment to upper surface alignment in the correction of the support 9 in the deep pit area 11. That is, the upper surface of the support 9 is aligned with the upper surface of the bottom plate 6 in the shallow pit area. At this time, the clear height of about 0.3m can be increased to facilitate the backhoe excavator 10 to perform excavation operations in the deep pit area 11 and improve its working space.

[0034] It should be noted that Figure 3The brace 9 in the example is the ninth support. When the shallow pit area 12 and the deep pit area 11 are constructed synchronously on the upper part, eight supports are set in the complete foundation pit, of which the second and third supports can be steel supports 2, and the first, fourth to eighth supports can be reinforced concrete supports 4. When the reinforced concrete supports 4 are used, it is necessary to set reinforced concrete support purlins 3 between the connection nodes between the reinforced concrete supports and the foundation pit retaining wall 8, and the connection node between the first support and the foundation pit retaining wall 8 is provided with a cap beam 1. When the shallow pit area 12 and the deep pit area 11 are constructed synchronously above the ninth support, it is necessary to first construct a column and a pile 5 within the scope of the foundation pit.

[0035] Please refer to Figure 2 In order to improve the clearance height of the backhoe excavator 10 during the excavation operation in the area of ​​the corner brace 13, the rapid excavation method of the deep pit in the foundation pit under high pressure head provided by the embodiment of the present invention can also include: correcting the corner brace of the deep pit area before and after the correction of the support 9 of the deep pit area 11. Specifically, the arrangement relationship between the corner brace 13 between the foundation pit retaining wall 8 at each corner of the deep pit area 11 and the bottom plate 6 of the shallow pit area is adjusted from thickness center alignment to upper surface alignment. That is, the upper surface of the corner brace 13 is aligned with the upper surface of the bottom plate 6 of the shallow pit area. At this time, the clear height of about 0.3m can be increased. In other words, by changing the arrangement relationship between the support 9, the corner brace 13 and the bottom plate 6 of the shallow pit area from thickness center alignment to upper surface alignment, the working space is increased, and the backhoe excavator 10 can perform earth excavation operations in the deep pit area 11 while meeting the full height requirement of the cab.

[0036] Please refer to Figure 1 to Figure 2 In order to improve the supporting strength of the corner brace of the deep pit area 11, the rapid excavation method of the deep pit in the foundation pit under high pressure head provided by the embodiment of the present invention may further include, in the correction of the corner brace 13 of the deep pit area 11:

[0037] The angle braces 13 between the pit retaining wall 8 of the deep pit area 11 and the revised shallow pit area bottom plate 6 are cancelled, and the two outermost braces 9 are replaced with angle braces 13 as new angle braces 14 and arranged outside the original angle braces 13 between the pit retaining walls 8 at the corners of the deep pit area 11. Figure 2 Cancel Figure 1 Middle right corner brace 13, Figure 2 Lieutenant General Figure 1 In addition to the two original angle braces 13 on the left side, a new angle brace 14 is added, so that the three angle braces 13 are adjusted between the foundation pit retaining walls 8 at each corner. It should be noted that when there are originally three or more angle braces 13 between the foundation pit retaining walls 8 at each corner, the two outermost braces 9 may not be changed to the new angle braces 14.

[0038] In order to ensure the effectiveness of the support 9, an embodiment of the present invention provides a method for rapid excavation of a deep pit in a foundation pit under a high pressure head. In the support 9 of the modified deep pit area 11, a plane elastic foundation beam method or a continuous medium finite element method is used to calculate the internal force and deformation of the foundation pit retaining wall 8.

[0039] In order to ensure the effectiveness of the brace 9, the rapid excavation method for a deep pit in a foundation pit under a high pressure head provided by the embodiment of the present invention is based on the calculation of the linear elastic body beam-slab finite element method. Under the premise that both the stability and strength meet the requirements, the length of the brace 9 is adjusted, and the width of the shallow pit area bottom plate 6 after narrowing is determined according to the length of the brace 9 after the length is increased. In order to ensure the support strength of the brace 9, the brace 9 can be a steel support.

[0040] In order to ensure the structural stress of the steel purlin 16, the embodiment of the present invention provides a rapid excavation method for a deep pit in a foundation pit under a high pressure head, wherein the steel purlin 16 can be composed of two H-shaped steels. The steel purlin 16 can enhance the integrity of the underground continuous wall and coordinate the stress and deformation between the support and the underground continuous wall.

[0041] Please refer to Figure 2 In order to ensure the reliable connection between the steel purlin 16 and the brace 9, the embodiment of the present invention provides a rapid excavation method for a deep pit in a foundation pit under a high pressure head, in which the length B of the two ends of the steel purlin 16 extending from the brace 9 on both sides is more than 1.0m.

[0042] Please refer to Figure 4 In order to form a rainwater storage pool in the deep pit area 11, the rapid excavation method of the deep pit in the foundation pit under high pressure head provided by the embodiment of the present invention may also include:

[0043] Step S104, construct the deep pit area bottom plate 17, construct the retaining wall 18 at the vertical intersection of the deep pit area 11 and the shallow pit area 12, and construct the shallow pit area gap filling bottom plate 19 between the retaining wall 18 and the shallow pit area bottom plate 6 to fill the width of the shallow pit area bottom plate 6. In order to ensure the safety during the construction of step S104, the deep pit area bottom plate 17 and the retaining wall 18 can be cast by the formwork system first, and then the shallow pit area gap filling bottom plate 19 can be constructed in two layers. After the shallow pit area gap filling bottom plate 19 of the bottom layer reaches the strength condition, the angle brace 13 and the brace 9 in the deep pit area 11 are removed, and the shallow pit area gap filling bottom plate 19 of the top layer is constructed. In step S104, in order to ensure the width of the deep pit area 11, when digging, the boundary line 15 can be crossed to dig at the bottom plate 6 of the shallow pit area 12 without the shallow pit area, so that after the construction of the retaining wall 18, the width of the deep pit area 11 can still be ensured to remain unchanged.

[0044] It should be noted that the deep pit as a rainwater storage tank collects rainwater flowing through the ground into the pit through pipes, so it does not affect the normal use of the basement structure above the deep pit as a rainwater storage tank. When collecting and calling rainwater, it does not affect the use of the basement structure and will not cause flooding of the basement structure. The calling of rainwater is achieved by a water pump installed in the deep pit.

[0045] Please refer to Figure 3 to Figure 4 The embodiment of the present invention provides a rapid excavation method for a deep pit in a foundation pit under a high pressure head, and uses high-pressure jet grouting piles to fully reinforce the soil below the pit bottom of the pouring pit area 12 and the deep pit area 11 to form reinforced soil 7. The reinforced soil 7 improves the strength of the soil below the pit bottom of the shallow pit area 12 and the deep pit area 11, improves the water stopping effect at the pit bottom, and avoids the problem of pipe burst at the pit bottom.

[0046] Please refer to Figure 3 to Figure 4 The embodiment of the present invention provides a method for rapidly excavating a deep pit in a foundation pit under high pressure head, wherein the depth of the deep pit is 35.2m, that is, the depth from the ground to the bottom of the deep pit is 35.2m.

[0047] It should be noted that the rapid excavation method for a deep pit in a foundation pit under a high pressure head provided by the embodiment of the present invention is used for excavating the foundation pit in the deep pit area 11 using a backhoe excavator, which can well handle the situation where the local deep pit below the bottom plate 6 of the shallow pit area under the high pressure head has dense supports and the excavator has difficulty entering the deep pit and can only dig at the top of the pit. It can also avoid the high pressure head control being restricted by low digging efficiency, greatly shortening the exposure time of the deep pit under the high pressure head, which is much better than the traditional method in terms of technical feasibility, work efficiency, and implementation effect. The adjacent shallow pit area 12 can use a secondary transfer excavator and a vertical transport excavator on the top of the pit for earth excavation. Since the depths of both the deep pit and the shallow pit belong to deep foundation pits and there is a pressurized water layer, in order to avoid the situation where the pressurized water rises and makes it impossible to excavate the deep foundation pit, it is necessary to control the pressure of the pressurized water and reduce the height of the rising pressurized water, that is, to reduce the head height of the pressurized water, so as to smoothly carry out the foundation pit excavation operation.

[0048] The present invention is not limited to the above-mentioned specific implementation modes. Obviously, the above-mentioned embodiments are only some embodiments of the embodiments of the present invention, but not all embodiments. Based on the described embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention. Those skilled in the art can make other levels of modifications and changes to the present invention. In this way, if these modifications and changes of the present invention fall within the scope of the claims of the present invention, the present invention is also intended to include these changes and changes.

Claims

1. A method for rapidly excavating a deep pit in a foundation pit under high pressure head, characterized in that: include: Narrow the width of the bottom plate of the shallow pit area to increase the distance between the boundary line of the deep pit area and the shallow pit area and the bottom plate of the shallow pit area close to the side where the deep pit area is located; The length of each brace between the foundation pit retaining wall of the deep pit area and the revised bottom plate of the shallow pit area is increased. Under the condition of satisfying the internal force and deformation of the foundation pit retaining wall, the number of braces with increased length in the middle area between the foundation pit retaining wall of the deep pit area and the revised bottom plate of the shallow pit area is reduced and the spacing is widened. Each brace with the widened spacing is set on the foundation pit retaining wall through steel purlins; The backhoe excavator is vertically hoisted and transported into the deep pit area through the gap between two widened supports to perform excavation operations in the pit to form the deep pit.

2. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 1 is characterized in that: The correction of the deep pit area support also includes: adjusting the arrangement relationship between the support and the shallow pit area bottom plate from thickness center alignment to upper surface alignment.

3. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 2 is characterized in that: Also includes: Correct the corner braces in the deep pit area, and adjust the arrangement relationship between the corner braces between the foundation pit retaining walls at the corners of the deep pit area and the bottom plate of the shallow pit area from thickness center alignment to upper surface alignment.

4. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 3 is characterized in that: The modified deep pit area angle brace also includes: Cancel the angle braces between the pit retaining wall in the deep pit area and the revised bottom plate in the shallow pit area, change the two outermost braces into angle braces as new angle braces and set them on the outside of the original angle braces between the pit retaining walls at the corners of the deep pit area.

5. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 1 is characterized in that: In the modified deep pit area support, the plane elastic foundation beam method or the continuous medium finite element method is used to calculate the internal force and deformation of the foundation pit retaining wall.

6. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 1 is characterized in that: Based on the calculation of linear elastic beam-slab finite element method, on the premise that both stability and strength meet the requirements, the length of the brace is adjusted, and the width of the bottom plate of the shallow pit area after narrowing is determined according to the length of the brace after the increase.

7. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 6 is characterized in that: The counter supports are steel supports.

8. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 7, characterized in that: The steel perimeter purlin is composed of two H-shaped steels.

9. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 1, characterized in that: The length of the braces extending from both ends of the steel purlin to both sides is more than 1.0m.

10. The rapid excavation method for a deep pit in a foundation pit under high pressure head according to claim 1, characterized in that: The backhoe excavator is hoisted out of the deep pit from the gap between the two supports with adjusted width, and the bottom plate of the deep pit area is constructed. A retaining wall is constructed at the vertical junction of the deep pit area and the shallow pit area, and a shallow pit area filling bottom plate is constructed between the retaining wall and the shallow pit area bottom plate to complete the width of the shallow pit area bottom plate.