Hole mouth device for secant pile row pile all-sleeve protective wall hole forming and construction method of hole mouth device for secant pile row pile all-sleeve protective wall hole forming
By designing a full-casing wall-protecting hole former for snap-in pile rowing, and using components such as the unloading panel, intubation and anti-falling keys, the problems of offset and wear during the construction of the existing hole holes were solved, and the problem was achieved. The stable fixation of the steel casing and the protection of the guide wall reduce the risk of construction disturbance and deviation.
Patent Information
- Application Number
- CN202410995232.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-10-15
AI Technical Summary
Existing orifices are prone to deviation during construction and cannot be effectively fixed, resulting in guide wall positioning failure and mechanical wear, making it impossible to protect surrounding holes.
A full casing wall hole forming device including a load-removing panel, an intubation tube, an anti-falling key and a load-bearing rib is designed. The unloading panel is aligned with the guide wall positioning hole, the intubation is fixed, and the anti-falling key prevents steel The sheath slides down and the load-bearing ribs provide additional support to ensure accurate positioning and protection.
Effectively fix the steel casing to prevent deviation and mechanical wear, protect the guide wall, reduce construction disturbance, and ensure the safety and accuracy of the working area.
Smart Images

Figure CN118774880A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to an orifice device for forming holes for bite piles, rows of piles and full-casing pipe wall protection, and a construction method thereof. Background Art
[0002] In the construction of underground subway stations, the open-cut method is often used to excavate the station foundation pit. When constructing the open-cut method, factors such as foundation pit drainage are considered, and interlocking piles can be used as foundation pit support and water-stopping structures. Before the construction of interlocking piles, reinforced concrete guide walls should be constructed first, and the positions of the interlocking piles should be determined using the concrete guide walls.
[0003] The existing orifice is a single device that cannot be fixed. The existing orifice is not effectively fixed in actual construction and may be offset. When the offset occurs, the guide wall positioning hole cannot resist the friction of the steel casing or the drill bit during the drilling process. When the guide wall concrete is severely worn, the guide wall no longer has an effective positioning function. The existing orifice cannot protect other holes near the working area. Summary of the invention
[0004] In order to overcome the defects of the prior art, a hole-opening device for interlocking pile row and full-casing pipe wall protection and a construction method thereof are provided to solve the problem that the existing hole-opening devices for interlocking pile row and pile guide wall are prone to deviation in actual construction.
[0005] In order to achieve the above object, a hole-opening device for forming holes in a full-casing pipe wall of a bite pile row is provided, comprising:
[0006] The unloading panel is placed on two guide walls arranged opposite to each other of the interlocking pile row, and a plurality of mutually interlocking positioning holes are formed between the opposite sides of the two guide walls. A through hole for the steel casing to pass through is opened in the middle of the unloading panel, and the through hole is aligned with a positioning hole on the pile position to be constructed;
[0007] Two inserting pipes are connected to the bottom of the unloading panel, and the two inserting pipes are inserted into two positioning holes on two opposite sides of the one positioning hole in a one-to-one correspondence;
[0008] A plurality of anti-falling keys are arranged at intervals along the circumferential direction of the perforation, one end of the anti-falling key is flipably mounted on the force unloading panel, and the other end of the anti-falling key is pressed against the outer wall of the steel casing to prevent the steel casing from sliding down.
[0009] Furthermore, a lifting lug is installed on the force unloading panel.
[0010] Furthermore, there are multiple lifting ears, and the multiple lifting ears are arranged along the circumferential direction of the force unloading panel.
[0011] Furthermore, a load-bearing convex rib is formed on the force unloading panel, and the load-bearing convex rib is arranged in a circle along the circumferential direction of the through hole, and one end of the anti-falling key can be flipped and installed on the load-bearing convex rib.
[0012] Furthermore, an ear plate is vertically arranged on the load-bearing convex rib, the ear plate is connected to a hinge shaft, an axis hole is opened at one end of the anti-falling key, and the hinge shaft is rotatably inserted into the axis hole.
[0013] Furthermore, an anti-slip groove is formed on the outer wall of the steel casing, and the other end of the anti-fall key extends to the anti-slip groove and is supported by the groove wall at the upper portion of the anti-slip groove.
[0014] Furthermore, the other end of the anti-falling key is coated with an anti-slip layer.
[0015] The present invention provides a construction method of a hole opening device for forming holes with full casing of bite piles and pile rows, comprising the following steps:
[0016] The force unloading panel is hoisted and placed on two guide walls of the interlocking pile row that are arranged opposite to each other, so that the perforation on the force unloading panel is aligned with a positioning hole on the pile position to be constructed, and two insert pipes are inserted into two positioning holes on opposite sides of the positioning hole in a one-to-one correspondence;
[0017] Turning the plurality of anti-falling keys toward the outside of the through hole;
[0018] hoisting the steel casing and lowering it into the perforation;
[0019] After the steel casing is lowered to a preset height, the plurality of anti-falling keys are flipped toward the inner side of the through hole, so that the other ends of the plurality of anti-falling keys are pressed against the outer wall of the steel casing to prevent the steel casing from sliding down;
[0020] The drill is put into position and a hole is drilled through the steel casing.
[0021] The beneficial effect of the present invention is that the orifice device for forming holes for interlocking pile rows and full-casing pipe protection walls of the present invention mainly consists of a force-releasing panel, a load-bearing convex ridge, an anti-falling key, and an insert pipe at an adjacent pile position. The orifice device for forming holes for interlocking pile rows and full-casing pipe protection walls of the present invention is a new type of orifice device, which is used to protect the orifice of the positioning hole of the guide wall and to position the auxiliary orifice. The orifice device for forming holes for interlocking pile rows and full-casing pipe protection walls of the present invention protects the guide wall from being damaged by mechanical wear. The orifice device for forming holes for interlocking pile rows and full-casing pipe protection walls of the present invention effectively fixes the steel casing and effectively prevents the steel casing from falling when it is lifted in sections multiple times during concrete pouring. The orifice device for forming holes for interlocking pile rows and full-casing pipe protection walls of the present invention reduces the disturbance of the machinery to the surroundings during the construction process and avoids the displacement of the pile position. The orifice device for forming holes for interlocking pile rows and full-casing pipe protection walls of the present invention effectively protects the hole positions on both sides of the working surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:
[0023] Figure 1 It is a schematic structural diagram of the guide wall of the interlocking pile row according to an embodiment of the present invention.
[0024] Figure 2 It is a schematic structural diagram of a hole-opening device for forming holes in a full-casing pipe wall for engaging pile rows according to an embodiment of the present invention.
[0025] Figure 3 It is a front view of a hole-opening device for forming holes in a full casing of bite pile rows according to an embodiment of the present invention.
[0026] Figure 4 It is a side view of a hole-opening device for forming holes in a full casing of bite pile rows according to an embodiment of the present invention. DETAILED DESCRIPTION
[0027] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It is also necessary to explain that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.
[0028] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0029] Reference Figures 1 to 4 As shown, the present invention provides a hole-opening device for forming holes in a full-casing wall of a bite pile row, comprising: a force-releasing panel 1, a plug pipe 2, and an anti-falling key 3.
[0030] In this embodiment, the unloading panel 1 is rectangular and is placed on two oppositely disposed guide walls 4 of the interlocking pile row. The unloading panel 1 is disposed along the length direction of the guide wall.
[0031] See also Figure 1 As shown, a plurality of mutually engaging positioning holes 40 are formed between the opposite sides of the two guide walls 4 .
[0032] A through hole is provided in the middle of the unloading panel 1. The through hole is used for the steel casing 5 to pass through. The through hole is aligned with a positioning hole 40 on the pile position to be constructed.
[0033] As a preferred implementation, a lifting lug 11 is installed on the force unloading panel 1 .
[0034] In this embodiment, there are multiple lifting ears 11 , which are arranged along the circumferential direction of the load-releasing panel 1 .
[0035] Two inserting tubes 2 are connected to the bottom of the unloading panel 1. In this embodiment, the two inserting tubes are respectively arranged at opposite ends of the unloading panel. The two inserting tubes are respectively arranged at opposite sides of the through hole. The two inserting tubes 2 are inserted into two positioning holes 40 on opposite sides of a positioning hole 40 in a one-to-one correspondence.
[0036] In this embodiment, the two insertion tubes are respectively inserted into two adjacent positioning holes on the left and right of a positioning hole.
[0037] The number of the anti-falling keys 3 is multiple. The multiple anti-falling keys 3 are arranged at intervals along the circumferential direction of the perforation. In this embodiment, the anti-falling keys are arranged at equal intervals along the circumferential direction of the perforation. The number of the anti-falling keys is four.
[0038] One end of the anti-falling card key 3 is reversibly mounted on the force unloading panel 1. The other ends of the plurality of anti-falling card keys 3 are pressed against the outer wall of the steel casing 5 to prevent the steel casing 5 from sliding down.
[0039] As a preferred embodiment, a load-bearing convex rib 12 is formed on the force-releasing panel 1. The load-bearing convex rib 12 is arranged in a circle along the circumferential direction of the perforation. One end of the anti-falling key 3 is installed on the load-bearing convex rib 12 in a flippable manner.
[0040] Specifically, an ear plate 13 is vertically arranged on the load-bearing convex rib 12. There are two ear plates. The two ear plates are arranged opposite to each other. The ear plate 13 is connected with a hinge shaft 14. The hinge shaft is connected between the two ear plates. An axis hole is opened at one end of the anti-falling key 3. The hinge shaft 14 is rotatably penetrated in the axis hole.
[0041] As a preferred embodiment, the outer wall of the steel casing 5 is formed with an anti-slip groove 50. The other end of the anti-falling key 3 extends to the anti-slip groove 50 and is supported by the groove wall of the upper part of the anti-slip groove 50.
[0042] As a preferred implementation, the other end of the anti-falling key 3 is coated with an anti-slip layer.
[0043] The present invention provides a construction method of a hole opening device for forming holes with full casing of bite piles and pile rows, comprising the following steps:
[0044] S1. Lift the unloading panel 1 and place it on two guide walls 4 that are oppositely arranged on the interlocking pile row, so that the through hole on the unloading panel 1 is aligned with a positioning hole 40 on the pile position to be constructed, and two insert pipes 2 are inserted into two positioning holes 40 on opposite sides of the positioning hole 40 in a one-to-one manner.
[0045] S2, turning over the plurality of anti-falling keys 3 toward the outside of the perforations.
[0046] S3, hoist the steel casing 5 and lower it into the perforation.
[0047] S4. After the steel casing 5 is lowered to a preset height, the plurality of anti-falling keys 3 are flipped toward the inner side of the perforation, so that the other ends of the plurality of anti-falling keys 3 are pressed against the outer wall of the steel casing 5 to prevent the steel casing 5 from sliding down.
[0048] S5, the drilling rig is put in place and a hole is drilled through the steel casing 5.
[0049] The orifice device for forming holes in full-casing pipe wall for interlocking pile rows of piles of the present invention mainly comprises a force-releasing panel, a load-bearing convex rib, an anti-falling card key, and an inserting pipe at an adjacent pile position. The components of the orifice device are all made of Q235B steel, and the thickness can be determined according to the actual situation on site.
[0050] Before the drilling rig is in place, the orifice mouth device is hoisted by a crane and placed at the hole to be constructed (positioning hole), and the bottom insert is inserted into the positioning hole of the adjacent pile position for fixation. At this time, the curved inner wall of the guide wall effectively fixes the orifice mouth device to avoid displacement during construction.
[0051] Turn the anti-drop key toward the outside of the perforation to prevent it from affecting the lowering of the steel casing. Lower the steel casing from the perforation in the center of the orifice. When the steel casing is lowered to the corresponding height, flip the anti-drop key in the opposite direction so that the other end of the anti-drop key can clamp the steel casing.
[0052] When the steel casing needs to be lifted up in sections during concrete pouring, the method is the same as lowering the steel casing. It is only necessary to ensure that the anti-fall key is stuck in the steel casing.
[0053] During the installation of the reinforcement cage of the interlocking pile row, the lowering of the guide tube and the pouring of concrete, the operators can stand on the opposite sides of the plate surface of the force unloading panel, which is safe and reliable.
[0054] The orifice device for forming holes with full casing of bite piles and pile rows is a novel orifice device, which is used to protect the orifice of the positioning hole of the guide wall, and to assist the positioning of the orifice and prevent the steel casing from falling.
[0055] The orifice device used for forming holes by full-casing pipe wall protection for bite pile rows of piles of the present invention protects the guide wall from being damaged by mechanical wear.
[0056] The orifice device for forming holes in the full-casing pipe wall of the bite pile row pile of the present invention effectively fixes the steel casing and effectively prevents the steel casing from falling when it is lifted up in sections for multiple times during concrete pouring.
[0057] The orifice device for forming holes in the full-casing pipe wall of the interlocking pile row piles of the present invention reduces the disturbance of the machinery to the surroundings during the construction process and avoids the deviation of the pile position.
[0058] The hole mouth device used for forming holes with full casing pipes for engaging pile rows and pile rows according to the present invention effectively protects the hole positions on both sides of the working surface.
[0059] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the present application.
Claims
1. A hole-opening device for forming holes in a full-casing pipe wall for a occlusal pile row, characterized in that: include: The unloading panel is placed on two guide walls arranged opposite to each other of the interlocking pile row, and a plurality of mutually interlocking positioning holes are formed between the opposite sides of the two guide walls. A through hole for the steel casing to pass through is opened in the middle of the unloading panel, and the through hole is aligned with a positioning hole on the pile position to be constructed; Two inserting pipes are connected to the bottom of the unloading panel, and the two inserting pipes are inserted into two positioning holes on two opposite sides of the one positioning hole in a one-to-one correspondence; A plurality of anti-falling keys are arranged at intervals along the circumferential direction of the perforation, one end of the anti-falling key is flipably mounted on the force unloading panel, and the other end of the anti-falling key is pressed against the outer wall of the steel casing to prevent the steel casing from sliding down.
2. The orifice device for forming holes for bite piles and pile rows with full casing pipe protection wall according to claim 1, characterized in that: The force unloading panel is provided with a lifting lug.
3. The orifice device for forming holes for bite piles and pile rows with full casing pipe protection wall according to claim 2, characterized in that: The number of the lifting ears is multiple, and the multiple lifting ears are arranged along the circumferential direction of the force unloading panel.
4. The orifice device for forming holes for bite piles and pile rows with full casing pipe protection wall according to claim 1, characterized in that: The force unloading panel is formed with load-bearing convex ribs, and the load-bearing convex ribs are arranged in a circle along the circumferential direction of the through hole. One end of the anti-falling key can be flipped and installed on the load-bearing convex ribs.
5. The orifice device for forming holes for bite piles and pile rows with full casing pipe protection wall according to claim 4, characterized in that: An ear plate is vertically arranged on the load-bearing convex rib, and the ear plate is connected with a hinge shaft. An axis hole is opened at one end of the anti-falling key, and the hinge shaft is rotatably penetrated through the axis hole.
6. The orifice device for forming holes for bite piles and pile rows with full casing pipe protection wall according to claim 1, characterized in that: An anti-slip groove is formed on the outer wall of the steel casing, and the other end of the anti-falling key extends to the anti-slip groove and is supported by the groove wall at the upper part of the anti-slip groove.
7. The orifice device for forming holes for bite piles and pile rows with full casing pipe protection wall according to claim 6, characterized in that: The other end of the anti-falling key is coated with an anti-slip layer.
8. A construction method of a hole-opening device for full-casing pipe wall drilling of interlocking pile rows as claimed in any one of claims 1 to 7, characterized in that: The following steps are involved: The force unloading panel is hoisted and placed on two guide walls of the interlocking pile row that are arranged opposite to each other, so that the perforation on the force unloading panel is aligned with a positioning hole on the pile position to be constructed, and two insert pipes are inserted into two positioning holes on opposite sides of the positioning hole in a one-to-one correspondence; Turning the plurality of anti-falling keys toward the outside of the through hole; hoisting the steel casing and lowering it into the perforation; After the steel casing is lowered to a preset height, the plurality of anti-falling keys are flipped toward the inner side of the through hole, so that the other ends of the plurality of anti-falling keys are pressed against the outer wall of the steel casing to prevent the steel casing from sliding down; The drill is put into position and a hole is drilled through the steel casing.