Construction method and system of pipelines and decorative ceilings based on BIM technology
Through BIM technology, the space model is constructed and the installation position of the bearing keel is automatically adjusted, which solves the safety and efficiency of the leveling steps in decorative ceiling construction, and achieves an efficient and safe construction process.
Patent Information
- Application Number
- CN202411260458.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-10
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-09-10
AI Technical Summary
During the construction and decoration process, the load keel needs to be leveled before installation during the construction of the decorative ceiling, resulting in low safety and reduced construction efficiency of workers, which cannot meet the working hours saving requirements of prefabricated decoration.
Based on BIM technology, a real spatial model and standard spatial model are constructed by obtaining image data in the area to be worked, the three-dimensional spatial coordinate deviation of each center point is calculated, and the height adjustment device and driving device are used to automatically adjust the installation position of the bearing keel to avoid manual leveling. Steps to realize automated installation.
It improves construction efficiency, enhances workers' safety, and simplifies the installation process of the load-bearing keel, reduces construction time, and meets the labor-saving requirements of prefabricated decoration.
Smart Images

Figure CN118779974B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building decoration, and in particular to a construction method and system for pipelines and decorative ceilings based on BIM technology. Background Art
[0002] The existing BIM-based pipelines and decorative ceilings are pre-programmed before construction, and the entire ceiling is divided into several groups of plate structures of set sizes and produced in advance. The structured assembly method is used for construction, which effectively improves the construction efficiency. However, during the construction process, in the construction of the decorative ceiling, the load-bearing keel needs to be leveled before installation, and the leveling needs to be done at the top. The workers have to climb up and down, which is less safe and the construction efficiency is also reduced, which does not meet the requirements of saving man-hours for prefabricated decoration. Summary of the invention
[0003] In view of this, this application provides a construction method and system for pipelines and decorative ceilings based on BIM technology. The specific solution is:
[0004] The construction method of pipelines and decorative ceilings based on BIM technology includes the following steps:
[0005] Acquire image data of the area to be operated;
[0006] Construct a real space model of the area to be operated based on the acquired image data;
[0007] Taking any inflection point of the ground and the wall in the real space model as the origin, a standard space model of the real space model is constructed;
[0008] The top surface of the standard space model is divided into regions based on the length of the unit pipeline;
[0009] Obtain the three-dimensional spatial coordinates of the center point of each unit area, encode the center point of each area in turn, and calculate the coordinate deviation of each center point of the standard space model and the real space model respectively;
[0010] The load-bearing keels are installed with each center point as the installation point of the load-bearing keel, and then the main keels, secondary keels and pipelines are installed on the load-bearing keels in sequence;
[0011] First assemble the ceiling panels in the unit area, and then connect the ceiling panels between adjacent areas.
[0012] Preferably, the installation steps of the load-bearing keel, the main keel, the secondary keel and the pipeline are:
[0013] First, the positions of the center points are marked on the top surface of the work area by a first positioning device;
[0014] Then, one end of the height adjustment device is fixed at the center point, and the driving device is installed at the other end of the height adjustment device, and the driving device adjusts the height of the height adjustment device according to the corresponding coordinate deviation at the center point obtained;
[0015] Then, after the height of the height adjustment device meets the requirement, the driving device is removed and the load-bearing keel is fixed to the other end of the height adjustment device;
[0016] Finally, install the main keel in a direction perpendicular to the load-bearing keel, install the secondary keel in a direction parallel to the load-bearing keel, arrange the pipelines on the side of the load-bearing keel facing the top surface and along the extension direction of the load-bearing keel, and install the junction box on the ceiling panel corresponding to the center point of each area.
[0017] Preferably, the height adjustment process of the height adjustment device by the driving device is as follows:
[0018] First, the driving device obtains the code of each center point;
[0019] Then, the coordinate deviation corresponding to the center point is retrieved through coding;
[0020] Finally, the driving device starts to drive the height adjustment device to move synchronously according to the coordinate deviation until the feedback coordinates of the second positioning device in the driving device are the same as the coordinates of the center point corresponding to the standard space model, and the height adjustment is completed.
[0021] Preferably, the construction process of the standard space model is:
[0022] First, obtain the overall length, width and height information of the real space model;
[0023] Then, taking the origin as the starting point, the standard space model is drawn accordingly in a horizontal and vertical manner according to the length, width and height of the real space model.
[0024] Preferably, the coordinate deviation is calculated as follows:
[0025] Obtain the three-dimensional coordinates of the corresponding center points in the real space model and the standard space model in the coordinate system where the origin is located;
[0026] The coordinate difference between the center point of the real space model and the center point of the standard space model is calculated respectively, and the obtained coordinate difference is the coordinate deviation.
[0027] Preferably, the encoding rule is:
[0028] The first digit is the serial number of the area where it is located, and the spatial coordinates corresponding to the center point are the suffix serial numbers.
[0029] The construction system of pipelines and decorative ceilings based on BIM technology includes:
[0030] An acquisition module, used for acquiring image data of the area to be operated;
[0031] A storage module is connected to the acquisition module, and stores the image data fed back by the acquisition module and the construction process drawings of the work area to be operated;
[0032] The processing module is connected to the storage module, and constructs a real space model according to the image data, and takes any turning point of the ground and the wall in the real space model as the origin to construct a standard space model of the real space model, and divides the top surface of the standard space model into regions based on the pipeline length in the construction process drawing, obtains the three-dimensional space coordinates of the center point of each unit area, and calculates the coordinate deviation between the real space model and the standard space model at the center point;
[0033] The encoding module is connected to the processing module, and encodes the center point of each area in turn, and links each code with the corresponding coordinate deviation of each center point;
[0034] The adjustment module comprises a height adjustment device and a driving device, one end of the height adjustment device is respectively installed at each of the central points, and the other end of the height adjustment device is detachably connected to the driving device;
[0035] The driving device is communicatively connected with the processing module;
[0036] The positioning module includes a first positioning device and a second positioning device. The first positioning device is installed at the corner corresponding to the origin of the working area, and the second positioning device is installed on the driving device. The first positioning device and the second positioning device are respectively connected to the processing module.
[0037] Preferably, the first positioning device includes a controller, an infrared light emitter and a positioner;
[0038] The infrared light emitter and the locator are respectively connected to the controller;
[0039] The controller is connected to the processing module.
[0040] Preferably, the height adjustment device comprises a mounting seat;
[0041] The mounting seat is installed at each center point corresponding to the top surface of the work area, and an adjusting screw is provided on the mounting seat;
[0042] One end of the adjusting screw is threadedly connected to the mounting seat, the other end of the adjusting screw is provided with a connecting seat, and telescopic guide rods are respectively provided on both sides of the adjusting screw;
[0043] One end of the connecting seat is threadedly connected to the adjusting screw, and the other end of the connecting seat is detachably connected to the driving device;
[0044] Two ends of the telescopic guide rod are respectively connected to the mounting seat and the connecting seat.
[0045] Preferably, a mounting cavity is provided on the connecting seat along the vertical direction, and horizontal limiting cavities are provided on both sides of the connecting seat near the bottom end;
[0046] One end of the limiting cavity is connected to the installation cavity, and the other end of the limiting cavity extends out of the connecting seat and is connected to the outside. The inner side of the end of the limiting cavity facing away from the installation cavity is provided with an installation groove;
[0047] A spring and a horizontal limiting rod are arranged in the installation slot, one end of the horizontal limiting rod is located outside the installation slot, and the other end of the horizontal limiting rod passes through the installation slot and the limiting cavity in sequence and extends into the installation cavity;
[0048] The spring is sleeved on the horizontal limiting rod, the spring is located in the mounting groove, and two ends of the spring are respectively connected to the horizontal limiting rod and the mounting groove;
[0049] One end of the adjusting screw rod facing away from the mounting seat extends into the mounting cavity and is threadedly connected to the mounting cavity. The end of the adjusting screw rod extending into the mounting cavity is provided with an internal thread.
[0050] The driving device comprises a connecting shell, a driving motor arranged in the connecting shell, and a connecting piece located outside the connecting shell;
[0051] The top of the connecting shell is in contact with the bottom of the connecting seat;
[0052] The output end of the driving motor faces the adjusting screw;
[0053] One end of the connecting member passes through the connecting housing and is connected to the output end of the driving motor, and the other end of the connecting member extends with a trapezoidal overlapping portion, which extends into the bottom of the connecting seat and overlaps the two horizontal limit rods;
[0054] The second positioning device is installed on the inner side of the top of the connecting shell.
[0055] The beneficial effects of this application are:
[0056] This application constructs a real space model and a standard space model respectively based on BIM technology, and obtains the three-dimensional spatial coordinates of each center point in the standard space model, as well as the coordinate deviation of the real space model and the standard space model at the center point. In the waiting operation area equivalent to the real space model, the position of each center point is marked by a first positioning device, and a height adjustment device is installed at the marked center point, and a driving device is installed at the bottom of the height adjustment device. Then, based on the coordinate deviation of the real space model and the standard space model at the center point, the driving device is driven to adjust the height of the height adjustment device. Finally, according to the position of the second positioning device built into the driving device Feedback, judge whether to end the height adjustment. Since each center point is used as the installation point of the load-bearing keel, during installation, two center points with the same spacing distance as the length of the load-bearing keel are used as the starting point and end point of the load-bearing keel installation. Therefore, during installation, it is only necessary to use the driving device to adjust the height of the two center points with the same spacing distance as the length of the load-bearing keel. First, the starting point and the end point of the load-bearing keel are connected to the height adjustment device at the corresponding center points, and then the load-bearing keel at the corresponding center point between the starting point and the end point is installed with the corresponding height adjustment device. This process avoids the step of manual leveling required in the prior art.
[0057] At the same time, in the present application, the connection between the driving device and the load-bearing keel and the height adjustment device are all detachable connections, which provides convenience for disassembling and assembling the load-bearing keel during later maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0058] Figure 1 This is a schematic diagram of the construction of the standard space model;
[0059] Figure 2 is a structural schematic diagram of a height adjustment device;
[0060] Figure 3 It is a schematic diagram of the connection between the driving device and the height adjustment device;
[0061] Figure 4 It is a schematic diagram of the connection between the load-bearing keel and the height adjustment device;
[0062] Figure 5 This is the principle framework diagram of the pipeline and decorative ceiling construction system based on BIM technology.
[0063] Some reference numerals:
[0064] 1. Standard space model; 2. Ceiling board; 3. Load-bearing keel; 4. Center point; 5. Top surface; 6. Fixing plate; 7. Adjusting screw; 8. Mounting seat; 9. Telescopic guide rod; 10. Connecting seat; 11. Horizontal limit rod; 12. Insert block; 13. Mounting groove; 14. Limiting plate; 15. Mounting cavity; 16. Connecting shell; 17. Second positioning device; 18. Overlapping part; 19. Connecting part. DETAILED DESCRIPTION
[0065] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0066] Embodiment 1
[0067] According to the attached Figure 1 The construction method of pipelines and decorative ceilings based on BIM technology shown includes the following steps:
[0068] (1) Obtaining image data of the area to be operated through a collection device;
[0069] (2) The processing module constructs a real space model of the work area based on the acquired image data;
[0070] (3) Taking any inflection point of the ground and the wall in the real space model as the origin, construct a standard space model 1 of the real space model;
[0071] (4) dividing the top surface 5 of the standard space model 1 into regions based on the length of the unit pipeline;
[0072] (5) Obtaining the three-dimensional spatial coordinates of the center point 4 of each unit area, encoding the center point 4 of each area in turn, and calculating the coordinate deviations of each center point 4 of the standard space model 1 and the real space model respectively;
[0073] (6) Install the load-bearing keel using each center point as the installation point of the load-bearing keel, and then install the main keel, secondary keel and pipelines on the load-bearing keel in sequence;
[0074] (7) The ceiling panels 2 in a unit area are assembled first, and then the ceiling panels 2 between adjacent areas are connected.
[0075] Furthermore, the installation steps of the load-bearing keel 3, the main keel, the secondary keel and the pipeline are as follows:
[0076] First, the positions of the center points 4 are marked on the top surface of the work area by a first positioning device;
[0077] Then, one end of the height adjustment device is fixed at the center point 4, and the driving device is installed at the other end of the height adjustment device. The driving device adjusts the height of the height adjustment device according to the corresponding coordinate deviation of the center point obtained;
[0078] Then, after the height of the height adjustment device meets the requirement, the driving device is removed and the load-bearing keel 3 is fixed to the other end of the height adjustment device;
[0079] Finally, install the main keel in a direction perpendicular to the load-bearing keel 3, install the secondary keel in a direction parallel to the load-bearing keel 3, arrange pipelines on the side of the load-bearing keel 3 facing the top surface 5 and along the extension direction of the load-bearing keel 3, and install the junction box on the ceiling panel corresponding to the center point of each area.
[0080] Furthermore, the height adjustment process of the height adjustment device performed by the driving device is as follows:
[0081] First, the driving device obtains the code of each center point 4;
[0082] Then, the coordinate deviation corresponding to the center point is retrieved through coding;
[0083] Finally, the driving device starts to drive the height adjustment device to move synchronously according to the coordinate deviation until the second positioning device 17 in the driving device feeds back that its coordinates are the same as the coordinates of the center point corresponding to the standard space model 1, and the height adjustment is completed.
[0084] Furthermore, the construction process of the standard space model 1 is as shown in the attached Figure 1 As shown:
[0085] First, obtain the information (data) of the length a, width b, and height h of the entire real space model;
[0086] Then, taking the origin (point o) as the starting point, according to the length a, width b and height h of the real space model, the standard space model 1 is drawn accordingly along the X, Y and Z directions in a horizontal and vertical manner.
[0087] Furthermore, the coordinate deviation is calculated as follows:
[0088] Obtain the three-dimensional coordinates of the corresponding center point 4 in the real space model and the standard space model 1 in the coordinate system of the origin (point o) respectively;
[0089] Then, the coordinate difference L between the center point 4 of the real space model and the center point 4 of the standard space model 1 is calculated, and the obtained coordinate difference L is the coordinate deviation.
[0090] Further, the rules encoded therein;
[0091] The serial number of the area where the center point is located is used as the first digit to quickly locate the area, and the spatial coordinate corresponding to the center point 4 is used as the suffix serial number. The three-dimensional coordinates of each center point are located in the same coordinate system, which is convenient for quick search later.
[0092] It should be noted that:
[0093] When installing the suspended ceiling, the load-bearing keel is installed first, and the main keels are connected at intervals on the load-bearing keel in a manner of vertical load-bearing keel, and the secondary keels are vertically connected on the main keels, and the pipelines are installed on the secondary keels along the extension direction of the load-bearing keel, and finally the ceiling panels are installed with the area as a unit; when installing the suspended ceiling panels, the suspended ceiling panels 2 located directly below the center point of each area are installed first, and then the suspended ceiling panels 2 below the center point are installed outwardly in a radial direction, and the junction boxes are arranged on the suspended ceiling panels 2 located directly below the center point of each area. Since pipeline failures often occur at the wiring point, the present application arranges the junction boxes on the suspended ceiling panels 2 located directly below the center point of each unit area, and the junction boxes can be accurately found by the codes of each center point during replacement or maintenance;
[0094] Taking the origin (point o) as the starting point, according to the length a, width b and height h of the real space model, the standard space model 1 is drawn accordingly along the X, Y and Z directions in a horizontal and vertical manner, ensuring the absolute levelness of the top surface of the work area.
[0095] Embodiment 2
[0096] According to the attached Figure 2-5 The pipeline and decorative ceiling construction system based on BIM technology shown includes:
[0097] An acquisition module, used for acquiring image data of the area to be operated;
[0098] A storage module is connected to the acquisition module, and stores the image data fed back by the acquisition module and the construction process drawings of the work area to be operated;
[0099] The processing module is connected to the storage module, and constructs a real space model according to the image data, and takes any turning point of the ground and the wall in the real space model as the origin to construct a standard space model 1 of the real space model, and divides the top surface 5 of the standard space model 1 into regions based on the pipeline length in the construction process drawing, obtains the three-dimensional space coordinates of the center point 4 of each unit area, and calculates the coordinate deviation between the real space model and the standard space model 1 at the center point 4;
[0100] The encoding module is connected to the processing module, and encodes the center point 4 of each unit area in turn, and links each code with the coordinate deviation of each corresponding center point;
[0101] The adjustment module comprises a height adjustment device and a driving device, one end of the height adjustment device is respectively installed at each of the central points 4, and the other end of the height adjustment device is detachably connected to the driving device;
[0102] The driving device is communicatively connected with the processing module;
[0103] The positioning module includes a first positioning device and a second positioning device 17. The first positioning device is installed at the corner corresponding to the operating area and the origin position, and the second positioning device 17 is installed on the driving device. The first positioning device and the second positioning device 17 are respectively connected to the processing module.
[0104] Furthermore, the first positioning device includes a controller, an infrared light emitter and a positioner;
[0105] The infrared light emitter and the locator are respectively connected to the controller;
[0106] The controller is connected to the processing module.
[0107] Further, the height adjustment device includes a mounting seat 8;
[0108] The mounting seat 8 is installed at each center point corresponding to the top surface 5 of the work area, and an adjusting screw 7 is provided on the mounting seat. A vertical through threaded hole is provided at the center of the mounting seat 8;
[0109] One end of the adjusting screw 7 is threadedly connected to the mounting seat 8, the other end of the adjusting screw 7 is provided with a connecting seat 10, and telescopic guide rods 9 are respectively provided on both sides of the adjusting screw 7;
[0110] One end of the connecting seat 10 is threadedly connected to the adjusting screw 7, and the other end of the connecting seat 10 is detachably connected to the driving device;
[0111] Two ends of the telescopic guide rod 9 are connected to the mounting seat 8 and the connecting seat 10 respectively.
[0112] Furthermore, a mounting cavity 15 is provided on the connecting seat 10 along the vertical direction, and horizontal limiting cavities are provided on both sides of the connecting seat 10 near the bottom end;
[0113] One end of the limiting cavity is connected to the installation cavity 15, and the other end of the limiting cavity extends out of the connecting seat and is connected to the outside. The inner side of the end of the limiting cavity facing away from the installation cavity 15 is provided with an installation groove;
[0114] A spring and a horizontal limiting rod 11 are arranged in the installation groove 13, one end of the horizontal limiting rod 11 is located outside the installation groove, and the other end of the horizontal limiting rod 11 passes through the installation groove 13 and the limiting cavity in sequence and extends into the installation cavity 15;
[0115] The spring is sleeved on the horizontal limit rod 11, and the spring is located in the installation groove 13. The two ends of the spring are respectively connected to the horizontal limit rod 11 and one end of the installation groove 13 facing the installation cavity 15. A limit plate 14 is arranged at the end of the installation groove 13 facing away from the installation cavity. The limit plate 14 is fixed on the connecting seat, and the limit plate 14 prevents the spring from moving out of the installation groove 13.
[0116] One end of the adjusting screw 7 facing away from the mounting seat 8 extends into the mounting cavity 15 and is rotatably connected to the mounting cavity 15. The end of the adjusting screw 7 extending into the mounting cavity 15 is provided with an internal thread.
[0117] The driving device includes a connecting shell 16, a driving motor arranged in the connecting shell 16, and a connecting member located outside the connecting shell 16;
[0118] The top of the connecting shell is in contact with the bottom of the connecting seat;
[0119] The output end of the driving motor faces the adjusting screw 7;
[0120] One end of the connecting member passes through the connecting housing 16 and is connected to the output end of the driving motor, and the other end of the connecting member is extended with a trapezoidal overlapping portion 18, which extends into the bottom of the connecting seat 10 and overlaps the two horizontal limit rods 11, and the end of the overlapping portion 18 in contact with the adjusting screw 7 is provided with an external thread rod matching the internal thread; wherein the controller of the driving motor and the second positioning device are respectively connected to the processing module;
[0121] The second positioning device is installed on the inner side of the top of the connecting shell, wherein the second positioning device is a positioner.
[0122] It should be noted that:
[0123] In the present application, a fixing plate 6 is provided at one end of the mounting seat 8 connected to the top surface 5 of the work area, and a connecting hole is provided at the center of the fixing plate 6. The height adjustment process of the height adjustment device is as follows;
[0124] First, the first positioning device obtains the three-dimensional spatial coordinates of each center point based on the origin (point O) fed back by the processing module, and then emits infrared rays through the infrared transmitter to mark the actual positions of each center point on the top surface of the work area;
[0125] Then, the operator places the connection holes of the fixing plate 6 at the center points of the marks and fixes the fixing plate 6 to the top surface by bolts / screws;
[0126] Subsequently, the mounting seat 8 is fixed to the bottom of the fixing plate 6, and the driving device is installed at the bottom of the connecting seat 10. At this time, the plug block 12 arranged at the top of the connecting shell 16 is inserted into the slot at the bottom of the connecting seat 10, the top of the connecting shell 16 abuts against the bottom of the connecting seat 10, the overlapping portion 18 overlaps the top of the two horizontal limit rods 11, and the external threaded rod of the overlapping portion 18 extends into the bottom of the adjusting screw 7;
[0127] Finally, the processing module is connected to the controller of the drive motor. The processing module obtains the coordinate deviation corresponding to the center point according to the code corresponding to the center point, and controls the drive motor to make corresponding actions according to the coordinate deviation. The drive motor drives the connecting rod and the adjusting screw 7 to rotate synchronously, and rotate in or out of the connecting hole in the mounting seat 8, thereby adjusting the overall height of the connecting seat 10.
[0128] When the processing module judges that the second positioning device is qualified according to the feedback, the driving motor is stopped. At this time, the operator pulls out the horizontal limit rod 11 horizontally, removes the driving device, and then installs the connecting part 19 installed at the end of the load-bearing keel 3 on the top of the adjusting screw 7 to install the load-bearing keel 3. In the later maintenance, only the connecting part 19 needs to be removed, which is convenient for the later maintenance.
Claims
1. The construction method of pipelines and decorative ceilings based on BIM technology is characterized by: The following steps are involved: (1) Obtaining image data of the area to be operated; (2) Constructing a real space model of the work area based on the acquired image data; (3) Taking any inflection point of the ground and the wall in the real space model as the origin, a standard space model of the real space model is constructed; (4) Divide the top surface of the standard space model into regions based on the length of the unit pipeline; (5) Obtain the three-dimensional spatial coordinates of the center point of each unit area, encode the center point of each area in turn, and calculate the coordinate deviation of each center point relative to the standard space model and the real space model; (6) Install the load-bearing keel using each center point as the installation point of the load-bearing keel, and then install the main keel, secondary keel and pipelines on the load-bearing keel in sequence; (7) First assemble the ceiling panels in the unit area, and then connect the ceiling panels between adjacent areas; The installation steps of the load-bearing keel, main keel, secondary keel and pipelines are as follows: First, the positions of the center points are marked on the top surface of the work area by a first positioning device; Then, one end of the height adjustment device is fixed at the center point, and the driving device is installed at the other end of the height adjustment device, and the driving device adjusts the height of the height adjustment device according to the corresponding coordinate deviation at the center point obtained; Then, after the height of the height adjustment device meets the requirement, the driving device is removed and the load-bearing keel is fixed to the other end of the height adjustment device; Finally, install the main keel in a direction perpendicular to the load-bearing keel, install the secondary keel in a direction parallel to the load-bearing keel, arrange the pipelines on the side of the load-bearing keel facing the top surface and along the extension direction of the load-bearing keel, and install the junction box on the ceiling board corresponding to the center point of each area; The height adjustment process of the height adjustment device by the driving device is as follows: First, the driving device obtains the code of each center point; Then, the coordinate deviation corresponding to the center point is retrieved through coding; Finally, the driving device starts to drive the height adjustment device to move synchronously according to the coordinate deviation until the feedback coordinates of the second positioning device in the driving device are the same as the coordinates of the center point corresponding to the standard space model, and the height adjustment is completed.
2. The construction method of pipelines and decorative ceilings based on BIM technology according to claim 1, characterized in that: The construction process of the standard space model is as follows: First, obtain the overall length, width and height information of the real space model; Then, taking the origin as the starting point, the standard space model is drawn accordingly in a horizontal and vertical manner according to the length, width and height of the real space model.
3. The construction method of pipelines and decorative ceilings based on BIM technology according to claim 1 is characterized in that: The calculation steps of the coordinate deviation are: Obtain the three-dimensional coordinates of the corresponding center points in the real space model and the standard space model in the coordinate system where the origin is located; The coordinate difference between the center point of the real space model and the center point of the standard space model is calculated respectively, and the obtained coordinate difference is the coordinate deviation.
4. The construction method of pipelines and decorative ceilings based on BIM technology according to claim 1 is characterized in that: The encoding rules are: The first digit is the serial number of the area where the area is located, and the spatial coordinates corresponding to the center point are the suffix serial number.
5. The pipeline and ceiling construction system based on BIM technology is characterized by: The construction system is applied to the construction method of pipelines and decorative ceilings based on BIM technology as described in any of claims 1 to 4, and the construction system comprises: An acquisition module, used for acquiring image data of the area to be operated; A storage module is connected to the acquisition module, and stores the image data fed back by the acquisition module and the construction process drawings of the work area to be operated; The processing module is connected to the storage module, and constructs a real space model according to the image data, and takes any turning point of the ground and the wall in the real space model as the origin to construct a standard space model of the real space model, and divides the top surface of the standard space model into regions based on the pipeline length in the construction process drawing, obtains the three-dimensional space coordinates of the center point of each unit area, and calculates the coordinate deviation between the real space model and the standard space model at the center point; The encoding module is connected to the processing module, and encodes the center point of each unit area in turn, and links each code with the corresponding coordinate deviation of each center point; The adjustment module comprises a height adjustment device and a driving device, one end of the height adjustment device is respectively installed at each of the central points, and the other end of the height adjustment device is detachably connected to the driving device; The driving device is communicatively connected with the processing module; The positioning module includes a first positioning device and a second positioning device. The first positioning device is installed at the corner corresponding to the origin of the working area, and the second positioning device is installed on the driving device. The first positioning device and the second positioning device are respectively connected to the processing module.
6. The pipeline and decorative ceiling construction system based on BIM technology according to claim 5 is characterized in that: The first positioning device includes a controller, an infrared light emitter and a locator; The infrared light emitter and the locator are respectively connected to the controller; The controller is connected to the processing module.
7. The pipeline and decorative ceiling construction system based on BIM technology according to claim 5 is characterized in that: The height adjustment device includes a mounting seat; The mounting seat is installed at each center point corresponding to the top surface of the work area, and an adjusting screw is provided on the mounting seat; One end of the adjusting screw is threadedly connected to the mounting seat, the other end of the adjusting screw is provided with a connecting seat, and telescopic guide rods are respectively provided on both sides of the adjusting screw; One end of the connecting seat is threadedly connected to the adjusting screw, and the other end of the connecting seat is detachably connected to the driving device; Two ends of the telescopic guide rod are respectively connected to the mounting seat and the connecting seat.
8. The pipeline and decorative ceiling construction system based on BIM technology according to claim 7 is characterized in that: The connecting seat is provided with a mounting cavity along the vertical direction, and the connecting seat is provided with horizontal limiting cavities on both sides close to the bottom end; One end of the limiting cavity is connected to the installation cavity, and the other end of the limiting cavity extends out of the connecting seat and is connected to the outside. The inner side of the end of the limiting cavity facing away from the installation cavity is provided with an installation groove; A spring and a horizontal limiting rod are arranged in the installation slot, one end of the horizontal limiting rod is located outside the installation slot, and the other end of the horizontal limiting rod passes through the installation slot and the limiting cavity in sequence and extends into the installation cavity; The spring is sleeved on the horizontal limiting rod, the spring is located in the mounting groove, and two ends of the spring are respectively connected to the horizontal limiting rod and the mounting groove; One end of the adjusting screw rod facing away from the mounting seat extends into the mounting cavity and is threadedly connected to the mounting cavity. The end of the adjusting screw rod extending into the mounting cavity is provided with an internal thread. The driving device comprises a connecting shell, a driving motor arranged in the connecting shell, and a connecting piece located outside the connecting shell; The top of the connecting shell is in contact with the bottom of the connecting seat; The output end of the driving motor faces the adjusting screw; One end of the connecting member passes through the connecting housing and is connected to the output end of the driving motor, and the other end of the connecting member extends with a trapezoidal overlapping portion, which extends into the bottom of the connecting seat and overlaps the two horizontal limit rods; The second positioning device is installed on the inner side of the top of the connecting shell.