Optimal configuration method and device for multi-energy coupling system

By obtaining user energy demand data and multi-energy coupling system parameters, and constructing system constraints and objective functions, the total cost optimization problem of the entire process operation in the multi-energy coupling system is solved, and energy utilization and system operation efficiency are improved.

CN118780407APending Publication Date: 2024-10-15ELECTRIC POWER PLANNING & ENG INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310364692.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-04-07
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The existing technology is difficult to optimize configurations for systemic issues such as the total cost of the entire process operation in a multi-energy coupling system, and lacks the ability to solve systemic problems in multi-energy coupling systems.

Method used

By obtaining user energy demand data and parameters of the multi-energy coupling system during the preparation, conversion, transportation, and storage processes, system constraints and objective functions are constructed, and optimal configuration strategies are determined to improve energy utilization and system operation efficiency.

Benefits of technology

It realizes the optimal configuration of the total cost of the whole process operation of the multi-energy coupling system, improves energy utilization, reduces resource waste, and enhances the systematicness and coordination of system operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780407A_ABST
    Figure CN118780407A_ABST
Patent Text Reader

Abstract

The invention provides an optimal configuration method and device for a multi-energy coupling system, the multi-energy coupling system is used for preparing, converting, conveying, storing and supplying four terminal energy sources of electricity, heat, cold and hydrogen, and the method comprises the following steps: obtaining energy consumption demand data of users in a target area, obtaining a first parameter of the multi-energy coupling system in the process of preparing the first energy, a second parameter in the process of converting the first energy into the second energy, a third parameter in the process of conveying the second energy from the sending end to the receiving end, and a fourth parameter in the process of storing the second energy in the storage equipment; based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy consumption demand data, obtaining a system constraint condition; based on the system cost of the multi-energy coupling system in the operation process, and based on the system cost and the energy demand data, constructing an objective function; and determining an optimal configuration strategy of the multi-energy coupling system based on the system constraint condition and the target function.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of integrated energy technology, and in particular to an optimization configuration method and device for a multi-energy coupling system. Background Art

[0002] As the proportion of new energy continues to expand, the energy options available to users are becoming more and more diversified, and the basic characteristics of traditional energy systems are changing. As one of the important energy carriers, electric energy has obvious storage limitations, that is, it cannot be stored on a large scale and for a long period of time, while the use of comprehensive energy can effectively make up for the defects of electric energy storage. Therefore, in the face of the randomness and intermittent characteristics of new energy output, electricity / cold / heat / hydrogen coupling can support the development of new energy with higher penetration. However, due to the multi-link and deep-level coupling between multi-energy coupling systems, the existing technology only optimizes the economic calculation and operation and regulation of multi-energy coupling systems. The optimization targets mainly include electricity sales revenue, energy storage investment cost or output volatility. The constraints mainly consider the abandonment rate indicator, which is mainly the research on independent links and independent problems. It lacks the ability to optimize the configuration of systemic problems such as the total cost of the full process operation in the multi-energy coupling system. Summary of the invention

[0003] The embodiments of the present application provide a method and device for optimizing the configuration of a multi-energy coupling system, which can solve the problem in the prior art of lacking the ability to optimize the configuration for systemic issues such as the total cost of the full-process operation in the multi-energy coupling system.

[0004] In order to solve the above technical problems, this application is implemented as follows:

[0005] In a first aspect, an embodiment of the present application provides an optimization configuration method for a multi-energy coupling system, wherein the multi-energy coupling system is used to prepare, convert, transport, store and supply four terminal energies: electricity, heat, cold and hydrogen. The method includes:

[0006] Obtaining energy demand data of users in the target area, and obtaining a first parameter of the multi-energy coupling system in the process of preparing a first energy, a second parameter in the process of converting the first energy into a second energy, a third parameter in the process of transmitting the second energy from a sending end to a receiving end, and a fourth parameter in the process of storing the second energy in a storage device;

[0007] Acquire system constraints based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy demand data;

[0008] Based on the system cost of the multi-energy coupling system during operation, and based on the system cost and the energy demand data, construct an objective function;

[0009] Based on the system constraints and the objective function, an optimal configuration strategy for the multi-energy coupling system is determined.

[0010] In a second aspect, an embodiment of the present application provides an optimization configuration device for a multi-energy coupling system, wherein the multi-energy coupling system is used to prepare, convert, transport, store and supply four terminal energies: electricity, heat, cold and hydrogen. The device includes:

[0011] A first acquisition module is used to acquire energy demand data of users in a target area, and acquire a first parameter of the multi-energy coupling system in a process of preparing a first energy, a second parameter in a process of converting the first energy into a second energy, a third parameter in a process of transmitting the second energy from a sending end to a receiving end, and a fourth parameter in a process of storing the second energy in a storage device;

[0012] A second acquisition module, configured to acquire a system constraint condition based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy demand data;

[0013] An objective function module, which is used for calculating the system cost of the multi-energy coupling system during operation and constructing an objective function based on the system cost and the energy demand data;

[0014] The optimization configuration module is used to determine the optimization configuration strategy of the multi-energy coupling system based on the system constraints and the objective function.

[0015] In an embodiment of the present application, the system constraints for the optimal configuration are determined by determining the first parameter of the multi-energy coupling system in the process of preparing the first energy, the second parameter in the process of converting the first energy into the second energy, the third parameter in the process of transporting the second energy from the sending end to the receiving end, and the fourth parameter in the process of storing the second energy in the storage device. Subsequently, the objective function of the optimal configuration is determined through the system cost of the operation of the multi-energy coupling system and the user's energy demand data. The optimal configuration can be carried out for systemic issues such as the total cost of the full process operation in the multi-energy coupling system, thereby improving energy utilization, reducing resource waste, and improving system operation efficiency. In this way, various factors in the operation of the multi-energy coupling system can be taken into account, and the systematicity and coordination of the operation of the multi-energy coupling system can be enhanced. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the description of the embodiments of the present application will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0017] Figure 1 It is a flow chart of an optimization configuration method of a multi-energy coupling system provided in an embodiment of the present application;

[0018] Figure 2 It is a structural schematic diagram of an optimization configuration device for a multi-energy coupling system provided in an embodiment of the present application;

[0019] Figure 3 It is a structural schematic diagram of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the present application to clearly describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments in the present application belong to the scope of protection of this application.

[0021] The terms "first", "second", etc. in the specification and claims of the present application are used to distinguish similar objects, and are not used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable under appropriate circumstances, so that the embodiments of the present application can be implemented in an order other than those illustrated or described here, and the objects distinguished by "first", "second", etc. are generally of one type, and the number of objects is not limited. For example, the first object can be one or more. In addition, "and / or" in the specification and claims represents at least one of the connected objects, and the character " / " generally indicates that the objects associated with each other are in an "or" relationship.

[0022] In conjunction with the accompanying drawings, the following describes in detail a method and device for optimizing configuration of a multi-energy coupling system provided by the embodiment of the present application through specific embodiments and application scenarios.

[0023] See also Figure 1 , Figure 1 This is a flow chart of an optimization configuration method for a multi-energy coupling system provided in an embodiment of the present application. The multi-energy coupling system is used to prepare, convert, transport, store and supply four terminal energies: electricity, heat, cold and hydrogen. The method includes the following steps:

[0024] S101. Obtain energy demand data of users in the target area, and obtain a first parameter of the multi-energy coupling system in the process of preparing a first energy, a second parameter in the process of converting the first energy into a second energy, a third parameter in the process of transporting the second energy from a sending end to a receiving end, and a fourth parameter in the process of storing the second energy in a storage device.

[0025] It should be noted that the above-mentioned target area can be a residential energy consumption area, and the required energy can be terminal energy such as electricity, heat, cooling, hydrogen, etc., including all energy consumption and living needs in the residential area. The target area can also be an industrial area, specifically an industrial area with a high degree of dependence on electricity and hydrogen. Therefore, in response to the energy demand in the above-mentioned target area, a multi-energy coupling system is established from the whole process of terminal energy preparation, conversion, transportation, storage and supply. The multi-energy coupling system includes the preparation, conversion, transportation, storage and supply process of multiple energy sources. For example, electricity is prepared by the photovoltaic power generation unit in the multi-energy coupling system, and then the conversion equipment in the multi-energy coupling system is used to convert the electricity into heat energy, and then the heat energy is transported to the user through the heating pipeline. When the transported heat energy is in excess, the heat energy can be stored in the storage device for easy access. In this way, the construction of the multi-energy coupling system provides convenience for users with energy needs, and also facilitates the comprehensive utilization of multiple energy sources, so that the preparation, conversion, transportation and other processes of multiple energy sources can be deeply coupled, and the connection between the preparation, conversion, transportation and storage processes of different energy sources can be strengthened.

[0026] It is worth noting that the energy demand data in the above-mentioned target area can be the demand data of residents in the residential area for various energy sources, including electricity load, heat load, cooling load, and hydrogen load. The specific formula is as follows:

[0027] The electric load expression formula is as follows:

[0028]

[0029] Among them, P e,load is the actual value of the electric load;

[0030] J is the number of users, which can include users from various industries and urban and rural residents;

[0031] P e,j,typ is the electric load demand value of the user

[0032] P e,j,gap is the power shortage value of the th user.

[0033] The heat load expression formula is as follows:

[0034]

[0035] Among them, P h,load is the actual value of heat load;

[0036] J is the number of users, which can include users from various industries and urban and rural residents;

[0037] P h,j,typ is the heat load demand value of the jth user

[0038] P h,j,gap is the power shortage value of the jth user;

[0039] P h,j,wave is the comfort margin value of the jth user.

[0040] The cooling load expression formula is as follows:

[0041]

[0042] Among them, P c,load is the actual value of cooling load;

[0043] J is the number of users, which can include users from various industries and urban and rural residents;

[0044] P c,j,typ is the cooling load demand value of the jth user

[0045] P c,j,gap is the power shortage value of the jth user;

[0046] P c,j,wave is the comfort margin value of the jth user.

[0047] The hydrogen load expression formula is as follows:

[0048]

[0049] Among them, P g,load is the actual value of cooling load;

[0050] J is the number of users, which can include users from various industries and urban and rural residents;

[0051] P g,j,typ is the cooling load demand value of the jth user

[0052] P g,j,gap is the power shortage value of the jth user;

[0053] P g,j,wave is the comfort margin value of the jth user.

[0054] By obtaining the implementation demand load, it is possible to optimize the configuration of the specific operation process arrangement of the multi-energy coupling system and other aspects.

[0055] In the above steps, the first parameter of the multi-energy coupling system in the process of preparing the first energy is obtained, that is, the parameter information related to the energy supply unit for preparing the first energy is obtained, which can be the output power, energy consumption power, maximum power, and minimum power output by the energy supply unit. The relevant parameters are obtained specifically according to the needs of model construction. Subsequently, the second parameter in the process of converting the first energy into the second energy is obtained, and the first energy is converted into the second energy, for example, the electrical energy is converted into thermal energy for heating of residents. At the same time, the above second parameter can be the output power of the second energy after conversion, that is, the second output power. It can also be parameters such as the energy efficiency ratio or conversion coefficient related to the conversion equipment. For example, in the process of converting electrical energy into thermal energy, a heat pump can be used for energy conversion, and the above first output power is used as the driving power input of the heat pump. Then, the heating coefficient of the heat pump is determined, and the thermal power output by the heat pump can be determined.

[0056] In addition, the third parameter in the process of transporting the second energy from the sending end to the receiving end is obtained. If the preparation and conversion site of the second energy is inconsistent with the actual use site, the second energy needs to be transported from the location of the conversion device to the user's demand site or the storage device. For the subsequent optimization configuration of the specific transportation method for the second energy, the relevant parameter information in the transportation process needs to be obtained in this step. Therefore, the third parameter can include the second output power corresponding to the second energy at the sending end before a certain transportation method is adopted for transportation, and can also include the loss rate of the aforementioned transportation method. Through the aforementioned second output power and loss rate, the third output power corresponding to the second energy at the receiving end after the transportation by this transportation method can be determined. For example, in the process of transporting thermal energy using a thermal pipeline, the output power corresponding to the thermal energy at the sending end of the thermal pipeline is the second output power. After determining the loss rate of the thermal pipeline, the third output power corresponding to the output of the second energy at the receiving end of the thermal pipeline can be determined.

[0057] Finally, when there is a situation of excess energy supply, or when it is necessary to provide energy in a fixed manner, the energy can be stored first for subsequent use. In the process of energy storage, a variety of storage devices can generally be used. The second energy can be stored in related devices, such as hydrogen storage tanks, etc., or the energy can be fixed in a certain form for storage, such as batteries in electrochemical energy storage. It is worth noting that the stored energy may be lost due to reasons such as poor sealing performance of the storage equipment. Therefore, by calculating the remaining energy capacity before and after storage, the storage effect of such storage devices and equipment can be determined, so as to facilitate the subsequent selection of storage devices with better storage effects and reduce resource waste.

[0058] S102: Acquire system constraints based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy demand data.

[0059] In the above steps, based on the first parameter obtained during the preparation process of the multi-energy coupling system, the second parameter obtained during the conversion process, the third parameter obtained during the transportation process, and the fourth parameter obtained during the storage process, the system constraints for optimizing the configuration of the system can be determined, and the optimal configuration strategy of the system can be determined while satisfying the system constraints. This enables the operation of the multi-energy coupling system to take into account multiple factors, develop and operate in a balanced manner, and enhance the systematicity and coordination of the operation of the multi-energy coupling system.

[0060] S103: constructing an objective function based on the system cost of the multi-energy coupling system during operation and based on the system cost and the energy demand data.

[0061] In this application, the objective function of the optimal configuration is determined by the system cost of the system operation and the energy demand of the user, so that the multi-energy coupling system can determine the optimal configuration strategy when the system cost is the lowest. It not only considers the independent links and independent problems of the system operation, but also can optimize the configuration for systemic issues such as the total cost of the whole process operation in the multi-energy coupling system, improve energy utilization, reduce resource waste, and improve system operation efficiency.

[0062] S104: Determine an optimal configuration strategy for the multi-energy coupling system based on the system constraints and the objective function.

[0063] In the above steps, after setting the system constraints and objective functions for optimizing the configuration of the multi-energy coupling system, when the system constraints are met, the relevant operation strategy is obtained under the minimum value of the objective function. For example, in different application scenarios, the distance of transmitting the second energy is different, and the energy demand of different target areas is also inconsistent. In view of the above problems, an optimization configuration method for a multi-energy coupling system provided in an embodiment of the present application is adopted, which can determine the energy transmission method, preparation method and other issues in the scenario of multiple energy applications, and can optimize the configuration of the entire process of the multi-energy coupling system, improve the system operation efficiency, and enhance the practicality, coordination and systematicness of the system operation.

[0064] Optionally, the first parameter includes a first output power, and the obtaining of the first parameter in the process of preparing the first energy by the multi-energy coupling system includes:

[0065] The first energy is prepared based on the energy supply unit in the multi-energy coupling system, wherein the energy supply unit includes at least one of a photovoltaic power generation unit, a gas power generation unit, a wind power generation unit, a coal power generation unit, a nuclear power generation unit, a cogeneration unit, a gas boiler, a coal-fired boiler, and a trigeneration energy supply unit;

[0066] A first output power corresponding to the first energy source is obtained.

[0067] In a specific embodiment of the present application, the multi-energy coupling system prepares the first energy through the energy supply unit. Specifically, the primary energy can be input into the energy supply unit to produce four terminal energies: electricity, heat, cold, and hydrogen. The energy supply unit in the present application can be one or more of a photovoltaic power generation unit, a gas-fired power unit, a wind power unit, a coal-fired power unit, a nuclear power unit, a cogeneration unit, a gas boiler, a coal-fired boiler, and a trigeneration power supply unit. The first parameter in the present application can be the actual output, abandoned power, upper limit power of climbing, lower limit power of climbing, preparation time and other data of the energy supply unit in the process of preparing the first energy by the multi-energy coupling system. The first output power corresponding to the first energy prepared by the energy supply unit can be determined by determining the actual output, abandoned power and output in the typical output curve of the energy supply unit. For example, in a photovoltaic power generation unit, the first output power can be:

[0068] P pv =P pv,typ -P pv,cur

[0069] Among them, P pv is the first output power of the photovoltaic generator set; P pv,typ is the output of the typical output curve of the photovoltaic generator set;

[0070] P pv,cur is the abandoned power of the photovoltaic generator set.

[0071] In a gas-electric unit the first output power can be:

[0072] P MT =P MT,gas ×η MT

[0073] Among them, P MT is the first output power of the gas-generator set;

[0074] P MT,gas Consume natural gas power for gas-fired power units;

[0075] η MT is the power generation efficiency of the gas-fired unit.

[0076] In a wind turbine the first output power may be:

[0077] P wind =P wind,typ -P wind,cur

[0078] Among them, P wind is the first output power of the wind turbine generator set;

[0079] P wind,typ is the output of the typical output curve of the wind turbine;

[0080] P wind,cur is the abandoned power of the wind turbine.

[0081] In a coal-fired power unit, the first output power can be:

[0082] P CT =P CT,coal ×η CT

[0083] Among them, P CT is the first output power of the coal-fired power unit;

[0084] P CT,coal Consume coal power for coal-fired power units;

[0085] η CT is the power generation efficiency of coal-fired power units.

[0086] In a nuclear power plant the first output power can be:

[0087] P NT =P NT,gas ×η NT

[0088] Among them, P NT is the first output power of the nuclear power unit;

[0089] P NT,gas Consume nuclear power for nuclear power plants;

[0090] η NT is the power generation efficiency of the nuclear power unit.

[0091] In a combined heat and power plant the first output power can be:

[0092]

[0093] Among them, P bp,h It is the thermal power output of the cogeneration unit;

[0094] P bp,e The electrical power output of the cogeneration unit;

[0095] P bp,gas Consume natural gas power for combined heat and power units;

[0096] η bp is the heating efficiency of the cogeneration unit;

[0097] P bp,h The electrical power output of the cogeneration unit;

[0098] k bp is the power-to-heat ratio of the cogeneration unit.

[0099] In a gas boiler the first output power can be:

[0100] P GB =η GB ×P GB,gas

[0101] Among them, P GB is the first output power of the gas boiler;

[0102] P GB,gas The power consumed by natural gas for gas boilers;

[0103] η GB It is the heating efficiency of gas boiler.

[0104] In a coal-fired boiler the first output power can be:

[0105] P CB =η CB ×P CB,coal

[0106] Among them, P CB is the first output power of the coal-fired boiler;

[0107] P CB,coal The power consumed by natural gas for gas boilers;

[0108] η GB It is the heating efficiency of gas boiler.

[0109] It should be noted that the above-mentioned first output power can be the energy provided by the first energy to the outside world per unit time, or it can be the energy provided by the multi-energy coupling system in this application to the outside world per unit time during the process of preparing the first energy.

[0110] Optionally, the second parameter includes a second output power, and the obtaining of the second parameter in the process of converting the first energy into the second energy includes:

[0111] Inputting the first energy into the conversion device of the multi-energy coupling system for energy conversion to obtain the second energy output by the conversion device, wherein the conversion device includes at least one of a heat pump, an electric refrigerator, an electric hydrogen production device, a waste heat recovery device, and a hydrogen fuel cell;

[0112] A second output power corresponding to the second energy source is obtained.

[0113] In a specific implementation, the first energy prepared above is input into a conversion device for energy conversion processing, which can produce a second energy and change the form of energy. For example, when the first energy is electrical energy, the electrical energy is converted into thermal energy through the conversion device. In the present application, the four terminal energy sources of electricity, heat, cold, and hydrogen mentioned above can be used as inputs, and energy conversion is performed through the conversion device to change the form of energy. In addition, the above-mentioned second parameter may include the second output power corresponding to the second energy after the conversion device converts the first energy into the second energy, and may also include the duration of running the conversion device, etc. For example, the first energy is electrical energy, and the first energy is converted into thermal energy through a heat pump. The specific formula is as follows:

[0114] P HP =P HP,in ×η HP

[0115] Among them, P HP is the second output power of the heat pump;

[0116] P HP,in A first output power is input into the heat pump for a first energy source;

[0117] η HP is the heating coefficient of the heat pump.

[0118] When the conversion device is an electric refrigerator, the specific formula is as follows:

[0119] P EC =P EC,in ×η EC

[0120] Among them, P EC is the second output power of the electric refrigerator;

[0121] P EC,in A first output power input into the electric refrigerator for a first energy source;

[0122] η EC is the energy efficiency ratio of the electric refrigerator.

[0123] When the conversion equipment is electric hydrogen production equipment, the specific formula is as follows:

[0124] P PG,out =P PG,in ×η PG

[0125] Among them, P PG,out is the second output power of the electric hydrogen production equipment;

[0126] P PG,in A first output power in the electric hydrogen production device is inputted by a first energy source;

[0127] ηPG is the conversion coefficient of the electric hydrogen production equipment.

[0128] When the conversion device is a waste heat recovery device, the specific formula is as follows:

[0129] P re,heat =P was,heat ×η re,heat

[0130] Among them, P re,heat The second output power of the waste heat recovery device;

[0131] P was,heat A first output power in the waste heat recovery device is inputted by the first energy source;

[0132] η re,heat It is the recovery efficiency of the waste heat recovery equipment.

[0133] When the conversion equipment is a hydrogen fuel cell equipment, the specific formula is as follows:

[0134] P GE,out =P GE,in ×η GE

[0135] Among them, P GE,out The second output power of the waste heat recovery device;

[0136] P GE,in A first output power in the waste heat recovery device is inputted by the first energy source;

[0137] η GE It is the recovery efficiency of the waste heat recovery equipment.

[0138] Optionally, the third parameter includes a third output power and a fourth power, the fourth power is the power loss of the second energy during transmission, and the obtaining of the third parameter in the process of transmitting the second energy from the sending end to the receiving end includes:

[0139] Input the second energy into the sending end of the transport equipment in the multi-energy coupling system, and transport the second energy to the receiving end of the transport equipment using a preset transport method, wherein the preset transport method includes at least one of cooling pipeline transport, heat pipeline transport, hydrogen pipeline transport, road transport, and power grid transport;

[0140] Obtain a third output power corresponding to the second energy at the receiving end and the fourth power of the second energy during transmission.

[0141] In a specific implementation, the second energy can be used as an energy source that can be directly used by the user, such as electricity, heating, cooling, etc. Before the second energy is actually used by the user, it needs to be transported from the preparation site or conversion site to the user's site. Different transportation methods can be selected during this transportation process, and the loss of the second energy during transportation is different for different transportation methods. When the second energy starts to be transported, the second energy is transported from the sending end of the transmission pipeline or equipment to the receiving end. The second energy output by the receiving end can be directly supplied to the user. In this process, the output power corresponding to the second energy at the receiving end is the third output power, and the power lost during transportation is the fourth power. It can be specifically obtained through the following formula:

[0142] When the preset delivery mode is set to cooling pipe delivery, there are:

[0143] P out,c =P in,c ×(1-η c )

[0144] Among them, P out,c The third output power of the receiving end of the cooling pipe;

[0145] P in,c The second output power at the sending end of the cooling pipe;

[0146] η c is the loss rate of power pipeline transmission.

[0147] When the preset transport mode is set to heat pipeline transport, there are:

[0148] P out,h =P in,h ×(1-η h )

[0149] Among them, P out,h is the third output power at the receiving end of the thermal pipeline;

[0150] P in,h is the second output power at the sending end of the thermal pipeline;

[0151] η h is the loss rate of heat pipeline transportation.

[0152] When the preset transport mode is set to hydrogen pipeline transport, there are:

[0153] P out,g =P in,g ×(1-η g )

[0154] Among them, P out,g The third output power of the receiving end of the hydrogen pipeline;

[0155] P in,g is the second output power at the sending end of the hydrogen pipeline;

[0156] η g is the loss rate of hydrogen pipeline transportation.

[0157] When the default transport mode is set to road transport, there are:

[0158] P out,w =P in,w ×(1-η w )

[0159] Among them, P out,w The third output power for the highway transmission receiving end;

[0160] P in,w The second output power for the highway transmission end;

[0161] η w is the loss rate of road transportation.

[0162] When the preset transmission mode is set to grid transmission, there are:

[0163] P out,e =P in,e ×(1-η e )

[0164] Among them, P out,e Transmitting the third output power of the receiving end to the power grid;

[0165] P in,e Transmitting a second output power of the sending end to the power grid;

[0166] η e is the loss rate of power transmission to the power grid.

[0167] Optionally, the fourth parameter includes a first remaining capacity and a second remaining capacity, and the step of acquiring the fourth parameter in the process of storing the second energy in the storage device includes:

[0168] Inputting the second energy derived from the receiving end into the storage device of the multi-energy coupling system, wherein the storage device includes at least one of an electrochemical energy storage device, a hydrogen storage device, a pumped storage device, a coal storage field energy storage device, and a valley electricity phase change thermal storage device;

[0169] The first remaining capacity at a first moment and the second remaining capacity at a second moment are obtained, wherein the first moment is earlier than the second moment.

[0170] In a specific embodiment of the present application, the above-mentioned second energy can be stored after conversion, and delayed supply can be provided to users who need energy, or, after the second energy is delivered, if the user has no energy application demand for the time being, the energy can also be stored for subsequent energy application. For example, the second energy is electrical energy, and the valley electricity phase change heat storage device can be used to convert electrical energy into thermal energy and store it. In the above embodiment, the second energy derived from the receiving end is input into a storage device, and the storage device can effectively store the second energy for a certain period of time, which can be convenient for users to use at any time. At the same time, it should be noted that when the second energy is stored in the storage device, the second energy will also be lost, and the initial storage capacity will be lost relative to the storage capacity when it is used. Therefore, the remaining capacity after loss is the second remaining capacity, and the remaining capacity measured at the first moment earlier than the second remaining capacity is the first remaining capacity.

[0171] It should also be noted that the above-mentioned fourth parameter includes the first remaining capacity and the second remaining capacity, and the fourth parameter may also include parameters related to the storage device, such as the charging power and discharging power, charging efficiency and energy discharge efficiency of the electrochemical energy storage in the electrochemical storage device.

[0172] Specifically, in electrochemical energy storage, the remaining capacity at the second moment can be expressed by the following formula:

[0173]

[0174] Among them, S e,t is a second remaining capacity of the electrochemical energy storage at a second moment;

[0175] S e,t-1 is a first remaining capacity of the electrochemical energy storage at a first moment;

[0176] P e,cha,t is the charging power of the electrochemical energy storage at the second moment;

[0177] η e,cha The charging efficiency of electrochemical energy storage;

[0178] P e,dis,t is the energy release power of the electrochemical energy storage at the second moment;

[0179] η e,dis is the energy release efficiency of electrochemical energy storage;

[0180] Δt is the duration between the first moment and the second moment, that is, the time of electrochemical energy storage.

[0181] In the hydrogen storage device, the remaining capacity at the second moment can be expressed by the following formula:

[0182]

[0183] Among them, S g,t is a second remaining capacity of the hydrogen storage device at the second moment;

[0184] S g,t-1 is the first remaining capacity of the hydrogen storage device at the first moment;

[0185] P g,cha,t is the charging power of the hydrogen storage device at the second moment;

[0186] η g,cha The charging efficiency of the hydrogen storage device;

[0187] P g,dis,t is the energy release power of the hydrogen storage device at the second moment;

[0188] η g,dis The energy release efficiency of the hydrogen storage device;

[0189] Δt is the duration between the first moment and the second moment, that is, the time the hydrogen storage device stores hydrogen.

[0190] In a pumped storage system, the remaining capacity at the second moment can be expressed by the following formula:

[0191]

[0192] Among them, S p,t is a second residual capacity of the pumped storage equipment at the second moment;

[0193] S p,t-1 is a first residual capacity of the pumped storage equipment at a first moment;

[0194] P p,cha,t is the charging power of the pumped storage equipment at the second moment;

[0195] η p,cha Charging efficiency of pumped storage equipment;

[0196] P p,dis,t is the discharge power of the pumped storage equipment at the second moment;

[0197] η p,dis The energy discharge efficiency of pumped storage equipment;

[0198] Δt is the duration between the first moment and the second moment, that is, the time for the pumped storage device to store energy.

[0199] In the coal storage yard, the remaining capacity at the second moment can be expressed by the following formula:

[0200]

[0201] Among them, S c,t is the second remaining capacity of the coal storage yard at the second moment;

[0202] S c,t-1 is the first remaining capacity of the coal storage yard at the first moment;

[0203] P c,cha,t is the charging power of the coal storage yard at the second moment;

[0204] η c,di s is the charging efficiency of the coal storage yard;

[0205] P c,dis,t is the energy release power of the coal storage yard at the second moment;

[0206] η c,dis The energy release efficiency of the coal storage yard;

[0207] Δt is the duration between the first moment and the second moment, that is, the time for energy storage in the coal storage yard.

[0208] In the valley electricity phase change thermal storage device, the remaining capacity at the second moment can be expressed by the following formula:

[0209]

[0210] Among them, S h,t is the second remaining capacity of the coal storage yard at the second moment;

[0211] S h,t-1 is the first remaining capacity of the coal storage yard at the first moment;

[0212] P echa,t is the charging power of the coal storage yard at the second moment;

[0213] η eh Charging efficiency of coal storage yard;

[0214] P hdis,t is the energy release power of the coal storage yard at the second moment;

[0215] η hdis The energy release efficiency of the coal storage yard;

[0216] Δt is the duration between the first moment and the second moment, that is, the time for energy storage in the coal storage yard.

[0217] Optionally, the system constraints include energy balance constraints, upper and lower limit constraints of system output power, system operation utilization constraints, system climbing constraints, and energy storage balance constraints; the energy demand data include energy load power and energy consumption equipment loss power; based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy demand data, obtaining the system constraints includes:

[0218] acquiring the energy balance constraint based on the first output power, the second output power, the third output power, the fourth power, the energy load power and the energy consumption equipment loss power;

[0219] Based on the first parameter, the maximum output power and the minimum output power of the energy supply unit in the process of preparing the first energy are obtained, and based on the maximum output power and the minimum output power, the upper and lower limit constraints of the system output power are obtained;

[0220] Based on the first parameter, the second parameter, the third parameter and the fourth parameter, determining the actual operation duration of the multi-energy coupling system, and obtaining the system operation utilization constraint by comparing the actual operation duration with a preset operation duration;

[0221] Determine a climbing upper limit parameter and a climbing lower limit parameter of the multi-energy coupling system based on the first parameter, the second parameter, the third parameter and the fourth parameter, and obtain the system climbing constraint based on the climbing upper limit parameter and the climbing lower limit parameter;

[0222] The energy storage balance constraint is acquired based on the first remaining capacity and the second remaining capacity.

[0223] In a specific embodiment of the present application, the system constraints for optimizing the configuration of the multi-energy coupling system are determined, and the system constraints are used to limit the internal and external conditions that need to be considered in the optimization configuration process of the multi-energy coupling system. Specifically, multiple constraints including energy balance constraints, upper and lower limits of system output power constraints, system operation utilization constraints, system climbing constraints, energy storage balance constraints, etc. can be set. The setting of specific constraints can be adjusted according to different energy supply units, different transmission methods, different conversion equipment, and different storage devices. This application does not make specific limitations. In this way, after setting the system constraints, the relevant optimization strategies of the multi-energy coupling system can be determined under the condition of meeting internal and external needs, effectively improving the overall coordination and feasibility of the operation of the multi-energy coupling system, and effectively improving the operating efficiency of the multi-energy coupling system.

[0224] Specifically, the above system constraints can be determined by using the following formula:

[0225] For example, the energy balance constraint can be determined by the following formula:

[0226]

[0227] P g,n,tThe first output power of the energy supply unit related to the nth required energy at time t, where n represents different types of required energy. It can be set to 1 for cold, 2 for heat, 3 for electricity, and 4 for hydrogen;

[0228] P o,n,t is the second output power of the nth required energy at time t;

[0229] P in,n,t is the third output power of the nth required energy at time t;

[0230] P loss,n,t is the fourth power of the nth energy demand at time t;

[0231] P load,n,t is the actual load power of the nth energy demand at time t;

[0232] P n,t The energy consumption of energy-consuming equipment.

[0233] The determined upper and lower limits of the system output power can also be expressed by the following formula:

[0234] P g,n,min <P g,n,t <P g,n,max

[0235] P g,n,min The minimum output power in the process of preparing the nth type of energy required for the gth type of equipment;

[0236] P g,n,t Output power in the process of preparing the nth type of energy demand for the gth type of equipment;

[0237] P g,n,max The maximum output power in the process of preparing the nth type of energy required for the gth type of equipment;

[0238] The determined system operation utilization constraint can also be expressed by the following formula:

[0239] T fa >T fa,min

[0240] T fa The actual operation time of the multi-energy coupling system;

[0241] T fa,min The preset duration for the multi-energy coupling system to operate.

[0242] The determined system ramp constraint can also be expressed by the following formula:

[0243] -ΔP g,n,l,max <P g,n,t-P g,n,t-1 <ΔP g,n,u,max

[0244] ΔP g,n,l,max For multi-energy coupling system g The upper limit parameter of the ramp rate of the nth type of energy demand of the equipment;

[0245] P g,n,t For the g The output power of the equipment in the process of preparing the nth required energy at time t;

[0246] P g,n,t-1 For the g The output power of the equipment in the process of preparing the nth required energy at time t-1;

[0247] ΔP g,n,u,max For multi-energy coupling system g The lower limit parameter of the ramp rate of the nth type of energy demand of the equipment.

[0248] The determined energy storage balance constraint can also be expressed by the following formula, requiring that the remaining capacity of the energy storage device at the last moment is equal to that at the initial moment, that is:

[0249] S0=S end

[0250] Wherein, S0 is the first remaining capacity of the energy storage device at the first moment;

[0251] S end It is the second remaining capacity of the energy storage device at the second moment.

[0252] Optionally, the system cost of the multi-energy coupling system during operation, and constructing an objective function based on the system cost and the energy demand data, includes:

[0253] Obtaining M operation cycles of the multi-energy coupling system, where M is an integer greater than or equal to 1;

[0254] constructing a first function in each operation cycle based on the system cost and the energy demand data;

[0255] Based on the first function corresponding to each of the operation cycles, a target function is constructed.

[0256] Specifically, the system cost of the above-mentioned multi-energy coupling system during operation can be the total system cost of the multi-energy coupling system during the whole process of preparation, conversion, transportation and storage, which can include the total installation cost, the total fuel cost, the total operation and maintenance cost, the total start-stop cost, the total emission cost, the total abandoned energy cost and the total energy shortage cost. The total system cost can be the cost within the total cycle of the overall operation of the multi-energy coupling system. The duration of the multi-energy coupling system from the time it is put into construction and use to the time it is scrapped and stopped can include multiple operation cycles. In each operation cycle, the multi-energy coupling system can complete the whole process of preparation, conversion, transportation and storage. For example, within the target operation cycle of the construction of the multi-energy coupling system, its system cost and the user energy demand data within the cycle can be calculated to determine the first function within each target operation cycle. Subsequently, the M first functions corresponding to the M operation cycles are summed to determine the objective function. In this way, the operation of the multi-energy coupling system is specific to each operation cycle, which can effectively determine the objective function of the overall system, so that the objective function can be combined with the actual application, and the systematic nature of the operation of the multi-energy coupling system is improved.

[0257] Optionally, the system cost includes unit installed capacity cost, unit fuel cost, unit operation and maintenance cost, unit start and stop cost, unit emission cost, unit abandoned energy cost and unit energy shortage cost within unit time, and acquiring the first function within the target operation cycle based on the system cost includes:

[0258] Obtaining the duration of a target operation cycle, wherein the target operation cycle is any one of the M operation cycles;

[0259] Based on the unit installed capacity cost, the unit fuel cost, the unit operation and maintenance cost, the unit start and stop cost, the unit emission cost, the unit abandoned energy cost, the unit energy shortage cost and the energy demand data, constructing a second function within the unit time length, where the unit time length is a preset unit time within the target operation cycle;

[0260] Based on the second function corresponding to each unit time length in the target operation cycle, the first function in the target operation cycle is acquired.

[0261] It is worth noting that to determine the first function within the target operation cycle, the unit cost of the system per unit operation within the target operation cycle can be determined by summing up the second function determined for each unit time. For example, the target operation cycle of the multi-energy coupling system can be set to 5 years, and the unit time can be 1 year. The second function within the unit time, that is, within 1 year, can be determined. Then, by summing up the second function of each year in 5 years, the first function of the operation of the multi-energy coupling system can be determined. In this way, the objective function can be determined by the first function, thereby determining the objective function for the optimal configuration of the multi-energy coupling system. The objective function is constructed using the first function and the second function, and timely adjustments can be made to the changes in the system cost per unit time, so that the optimal configuration strategy of the multi-energy coupling system can be reasonably determined later.

[0262] Specifically, the objective function expression can be expressed by the following formula:

[0263]

[0264] Among them, C sys Total system cost for operation of multi-energy coupled systems;

[0265] C I,m The installed capacity cost of the multi-energy coupling system within the target operation period;

[0266] C F,t,m is the fuel cost of the multi-energy coupling system during the target operation cycle;

[0267] C V,t,m The operation and maintenance cost of the multi-energy coupling system within the target operation cycle;

[0268] C S,t,m is the start-up and shutdown cost of the multi-energy coupling system within the target operation cycle;

[0269] C E,t,m is the emission cost of the multi-energy coupling system during the target operation cycle;

[0270] C D,t,m The energy abandonment cost of the multi-energy coupling system during the target operation cycle;

[0271] C L,t,m The energy shortage cost of the multi-energy coupling system during the target operation cycle;

[0272] C I It is the unit installed cost of the multi-energy coupling system during operation;

[0273] C F The unit fuel cost of the multi-energy coupling system during operation;

[0274] C V It is the unit operation and maintenance cost of the multi-energy coupling system during operation;

[0275] C S It is the unit start-stop cost of the multi-energy coupling system during operation;

[0276] C E is the unit emission cost of the multi-energy coupling system during operation;

[0277] C D The unit energy abandonment cost of the multi-energy coupling system during operation;

[0278] C L It is the unit energy shortage cost of the multi-energy coupling system during operation;

[0279] G is the number of types of energy supply units in the multi-energy coupling system;

[0280] N is the number of load types in the multi-energy coupling system;

[0281] M is the number of operation cycles of the multi-energy coupling system;

[0282] c I,g is the unit installation cost of the g-type energy supply unit;

[0283] S I,g The installed capacity of the g-type energy supply unit;

[0284] P coal,g The power consumed by coal for the g-type energy supply unit;

[0285] P gas,g The power consumed by hydrogen for the g-type energy supply unit;

[0286] c coa l is the unit cost of coal consumption;

[0287] c gas is the unit cost of hydrogen consumption;

[0288] c V,g The unit variable operation and maintenance cost of the multi-energy coupling system;

[0289] P g is the output power of the multi-energy coupling system;

[0290] c S,g The single start-stop cost of the multi-energy coupling system;

[0291] M g is the start and stop times of the multi-energy coupling system;

[0292] cE,g is the unit emission cost of the multi-energy coupling system;

[0293] c D,g The unit energy abandonment cost of the multi-energy coupling system;

[0294] D g It is the abandoned power of the multi-energy coupling system;

[0295] c L,n is the unit energy shortage cost of the nth energy load in the multi-energy coupling system;

[0296] L n is the total amount of energy shortage of the nth type of load.

[0297] Optionally, determining the optimization configuration strategy of the multi-energy coupling system based on the system constraints and the objective function includes:

[0298] Under the condition that the system constraints are met and the objective function reaches the preset conditions, determining the target energy supply unit and / or target transmission mode of the multi-energy coupling system;

[0299] Determine the optimal configuration strategy of the multi-energy coupling system according to the determined target energy supply unit and / or target transmission mode;

[0300] Among them, the target energy supply unit includes at least one of a photovoltaic power generation unit, a gas-fired power unit, a wind power unit, a coal-fired power unit, a nuclear power unit, a cogeneration unit, a gas boiler, a coal-fired boiler, and a trigeneration energy supply unit; the target transportation method includes at least one of cooling pipeline transportation, heat pipeline transportation, hydrogen pipeline transportation, road transportation, and power grid transportation.

[0301] In an embodiment of the present application, when the system constraints are met and the objective function reaches the preset conditions, the optimal configuration strategy of the multi-energy coupling system can be determined. Specifically, the preset conditions can be the minimum value of the objective function under the system constraints, or a pre-set value. In addition, the above-mentioned optimal configuration strategy can specifically be a target energy supply unit and / or a target transportation method, and a target energy supply unit and / or a target transportation method that can effectively improve the operating efficiency of the multi-energy coupling system, improve the overall operating efficiency of the system, and reduce the overall cost of system operation are selected. In this way, the systemic problems such as the total cost of the full process operation in the multi-energy coupling system can be optimized and configured to improve energy utilization, reduce resource waste, and improve system operation efficiency.

[0302] Please refer to Figure 2 , Figure 2 An optimization configuration device for a multi-energy coupling system provided in an embodiment of the present application, the optimization configuration device 200 for the multi-energy coupling system includes:

[0303] The first acquisition module 201 is used to acquire energy demand data of users in the target area, and acquire a first parameter of the multi-energy coupling system in the process of preparing the first energy, a second parameter in the process of converting the first energy into the second energy, a third parameter in the process of transmitting the second energy from the sending end to the receiving end, and a fourth parameter in the process of storing the second energy in the storage device;

[0304] A second acquisition module 202, configured to acquire system constraints based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy demand data;

[0305] An objective function module 203 is used for calculating the system cost of the multi-energy coupling system during operation, and constructing an objective function based on the system cost and the energy demand data;

[0306] The optimization configuration module 204 is used to determine the optimization configuration strategy of the multi-energy coupling system based on the system constraints and the objective function.

[0307] Optionally, the first acquisition module 201 includes a first acquisition submodule, the first parameter includes a second output power, and the first acquisition submodule is used to:

[0308] The first energy is prepared based on the energy supply unit in the multi-energy coupling system, wherein the energy supply unit includes at least one of a photovoltaic power generation unit, a gas power generation unit, a wind power generation unit, a coal power generation unit, a nuclear power generation unit, a cogeneration unit, a gas boiler, a coal-fired boiler, and a trigeneration energy supply unit;

[0309] A first output power corresponding to the first energy source is obtained.

[0310] Optionally, the first acquisition module 201 includes a second acquisition submodule, the second parameter includes a second output power, and the second acquisition submodule is used to:

[0311] Inputting the first energy into the conversion device of the multi-energy coupling system for energy conversion to obtain the second energy output by the conversion device, wherein the conversion device includes at least one of a heat pump, an electric refrigerator, an electric hydrogen production device, a waste heat recovery device, and a hydrogen fuel cell;

[0312] A second output power corresponding to the second energy source is obtained.

[0313] Optionally, the first acquisition module 201 includes a third acquisition submodule, the third parameter includes a third output power and a fourth power, the fourth power is the power loss of the second energy during transmission, and the third acquisition submodule is used to:

[0314] Input the second energy into the sending end of the transport equipment in the multi-energy coupling system, and transport the second energy to the receiving end of the transport equipment using a preset transport method, wherein the preset transport method includes at least one of cooling pipeline transport, heat pipeline transport, hydrogen pipeline transport, road transport, and power grid transport;

[0315] Obtain a third output power corresponding to the second energy at the receiving end and the fourth power of the second energy during transmission.

[0316] Optionally, the first acquisition module 201 includes a fourth acquisition submodule, the fourth parameter includes a first remaining capacity and a second remaining capacity, and the fourth acquisition submodule is used to:

[0317] Inputting the second energy derived from the receiving end into the storage device of the multi-energy coupling system, wherein the storage device includes at least one of an electrochemical energy storage device, a hydrogen storage device, a pumped storage device, a coal storage field energy storage device, and a valley electricity phase change thermal storage device;

[0318] The first remaining capacity at a first moment and the second remaining capacity at a second moment are obtained, wherein the first moment is earlier than the second moment.

[0319] Optionally, the system constraints include energy balance constraints, system output power upper and lower limit constraints, system operation utilization constraints, system climbing constraints, and energy storage balance constraints. The energy demand data includes energy load power and energy consumption equipment loss power. The second acquisition module 202 is used to:

[0320] acquiring the energy balance constraint based on the first output power, the second output power, the third output power, the fourth power, the energy load power and the energy consumption equipment loss power;

[0321] Based on the first parameter, the maximum output power and the minimum output power of the energy supply unit in the process of preparing the first energy are obtained, and based on the maximum output power and the minimum output power, the upper and lower limit constraints of the system output power are obtained;

[0322] Based on the first parameter, the second parameter, the third parameter and the fourth parameter, determining the actual operation duration of the multi-energy coupling system, and obtaining the system operation utilization constraint by comparing the actual operation duration with a preset operation duration;

[0323] Determine a climbing upper limit parameter and a climbing lower limit parameter of the multi-energy coupling system based on the first parameter, the second parameter, the third parameter and the fourth parameter, and obtain the system climbing constraint based on the climbing upper limit parameter and the climbing lower limit parameter;

[0324] The energy storage balance constraint is acquired based on the first remaining capacity and the second remaining capacity.

[0325] Optionally, the objective function module 203 is used to:

[0326] Obtaining M operation cycles of the multi-energy coupling system, where M is an integer greater than or equal to 1;

[0327] constructing a first function in each operation cycle based on the system cost and the energy demand data;

[0328] Based on the first function corresponding to each of the operation cycles, a target function is constructed.

[0329] Optionally, the system cost includes unit installation cost, unit fuel cost, unit operation and maintenance cost, unit start and stop cost, unit emission cost, unit abandoned energy cost and unit energy shortage cost within unit time, and the objective function module 203 is used to:

[0330] Obtaining the duration of a target operation cycle, wherein the target operation cycle is any one of the M operation cycles;

[0331] Based on the unit installed capacity cost, the unit fuel cost, the unit operation and maintenance cost, the unit start and stop cost, the unit emission cost, the unit abandoned energy cost, the unit energy shortage cost and the energy demand data, constructing a second function within the unit time length, where the unit time length is a preset unit time within the target operation cycle;

[0332] Based on the second function corresponding to each unit time length in the target operation cycle, the first function in the target operation cycle is acquired.

[0333] Optionally, the optimization configuration module 204 is used to:

[0334] Under the condition that the system constraints are met and the objective function reaches the preset conditions, determining the target energy supply unit and / or target transmission mode of the multi-energy coupling system;

[0335] Determine the optimal configuration strategy of the multi-energy coupling system according to the determined target energy supply unit and / or target transmission mode;

[0336] Among them, the target energy supply unit includes at least one of a photovoltaic power generation unit, a gas-fired power unit, a wind power unit, a coal-fired power unit, a nuclear power unit, a cogeneration unit, a gas boiler, a coal-fired boiler, and a trigeneration energy supply unit; the target transportation method includes at least one of cooling pipeline transportation, heat pipeline transportation, hydrogen pipeline transportation, road transportation, and power grid transportation.

[0337] The optimization configuration device 200 of a multi-energy coupling system provided in an embodiment of the present invention can implement each process of the optimization configuration method of a multi-energy coupling system provided in an embodiment of the present invention, and can achieve the same beneficial effects. To avoid repetition, it will not be described here.

[0338] See also Figure 3 , Figure 3 3 is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application. The electronic device 300 includes: a memory 301, a processor 302, and a computer program stored in the memory 301 and executable on the processor 302. The present application embodiment can achieve the following Figure 1 The various steps in the embodiment of the optimization configuration method for a multi-energy coupling system shown can achieve the same beneficial effects. To avoid repetition, they will not be described again here.

[0339] The embodiment of the present invention further provides a computer-readable storage medium, wherein a computer program is stored on the computer-readable storage medium, and when the computer program is executed by a processor, the following is implemented: Figure 1 The various processes in the optimization configuration method of a multi-energy coupling system provided in the illustrated embodiment can achieve the same technical effect, and are not described here in detail to avoid repetition. The computer-readable storage medium is, for example, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk.

[0340] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or device including the element.

[0341] The embodiments of the present application are described above in conjunction with the accompanying drawings, but the present application is not limited to the above-mentioned specific implementation methods. The above-mentioned specific implementation methods are merely illustrative and not restrictive. Under the guidance of the present application, ordinary technicians in this field can also make many forms without departing from the purpose of the present application and the scope of protection of the claims, all of which are within the protection of the present application.

Claims

1. A method for optimizing the configuration of a multi-energy coupling system, wherein the multi-energy coupling system is used to prepare, convert, transport, store and supply four terminal energies: electricity, heat, cold and hydrogen, characterized in that: The method comprises: Obtaining energy demand data of users in the target area, and obtaining a first parameter of the multi-energy coupling system in the process of preparing a first energy, a second parameter in the process of converting the first energy into a second energy, a third parameter in the process of transmitting the second energy from a sending end to a receiving end, and a fourth parameter in the process of storing the second energy in a storage device; Acquire system constraints based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy demand data; Based on the system cost of the multi-energy coupling system during operation, and based on the system cost and the energy demand data, construct an objective function; Based on the system constraints and the objective function, an optimal configuration strategy for the multi-energy coupling system is determined.

2. The method according to claim 1, characterized in that The first parameter includes a first output power, and the obtaining of the first parameter in the process of preparing the first energy by the multi-energy coupling system includes: The first energy is prepared based on the energy supply unit in the multi-energy coupling system, wherein the energy supply unit includes at least one of a photovoltaic power generation unit, a gas power generation unit, a wind power generation unit, a coal power generation unit, a nuclear power generation unit, a cogeneration unit, a gas boiler, a coal-fired boiler, and a trigeneration energy supply unit; A first output power corresponding to the first energy source is obtained.

3. The method according to claim 2, characterized in that The second parameter includes a second output power, and the obtaining of the second parameter in the process of converting the first energy into the second energy includes: Inputting the first energy into the conversion device of the multi-energy coupling system for energy conversion to obtain the second energy output by the conversion device, wherein the conversion device includes at least one of a heat pump, an electric refrigerator, an electric hydrogen production device, a waste heat recovery device, and a hydrogen fuel cell; A second output power corresponding to the second energy source is obtained.

4. The method according to claim 3, characterized in that The third parameter includes a third output power and a fourth power, the fourth power is the power loss of the second energy during transmission, and the obtaining of the third parameter in the process of transmitting the second energy from the transmitting end to the receiving end includes: Input the second energy into the sending end of the transport equipment in the multi-energy coupling system, and transport the second energy to the receiving end of the transport equipment using a preset transport method, wherein the preset transport method includes at least one of cooling pipeline transport, heat pipeline transport, hydrogen pipeline transport, road transport, and power grid transport; Obtain a third output power corresponding to the second energy at the receiving end and the fourth power of the second energy during transmission.

5. The method according to claim 4, characterized in that The fourth parameter includes the first remaining capacity and the second remaining capacity, and the obtaining of the fourth parameter in the process of storing the second energy in the storage device includes: Inputting the second energy derived from the receiving end into the storage device of the multi-energy coupling system, wherein the storage device includes at least one of an electrochemical energy storage device, a hydrogen storage device, a pumped storage device, a coal storage field energy storage device, and a valley electricity phase change thermal storage device; The first remaining capacity at a first moment and the second remaining capacity at a second moment are obtained, wherein the first moment is earlier than the second moment.

6. The method according to claim 5, characterized in that The system constraints include energy balance constraints, upper and lower limit constraints of system output power, system operation utilization constraints, system climbing constraints, and energy storage balance constraints. The energy demand data include energy load power and energy consumption equipment loss power. Based on the first parameter, the second parameter, the third parameter, the fourth parameter, and the energy demand data, the system constraints are obtained, including: acquiring the energy balance constraint based on the first output power, the second output power, the third output power, the fourth power, the energy load power and the energy consumption equipment loss power; Based on the first parameter, the maximum output power and the minimum output power of the energy supply unit in the process of preparing the first energy are obtained, and based on the maximum output power and the minimum output power, the upper and lower limit constraints of the system output power are obtained; Based on the first parameter, the second parameter, the third parameter and the fourth parameter, determining the actual operation duration of the multi-energy coupling system, and obtaining the system operation utilization constraint by comparing the actual operation duration with a preset operation duration; Determine a climbing upper limit parameter and a climbing lower limit parameter of the multi-energy coupling system based on the first parameter, the second parameter, the third parameter and the fourth parameter, and obtain the system climbing constraint based on the climbing upper limit parameter and the climbing lower limit parameter; The energy storage balance constraint is acquired based on the first remaining capacity and the second remaining capacity.

7. The method according to claim 1, characterized in that The system cost of the multi-energy coupling system during operation, and constructing an objective function based on the system cost and the energy demand data, including: Obtaining M operation cycles of the multi-energy coupling system, where M is an integer greater than or equal to 1; constructing a first function in each operation cycle based on the system cost and the energy demand data; Based on the first function corresponding to each of the operation cycles, a target function is constructed.

8. The method according to claim 7, characterized in that The system cost includes unit installed capacity cost, unit fuel cost, unit operation and maintenance cost, unit start and stop cost, unit emission cost, unit abandoned energy cost and unit energy shortage cost within unit time. The first function within the target operation cycle is obtained based on the system cost, including: Obtaining the duration of a target operation cycle, wherein the target operation cycle is any one of the M operation cycles; Based on the unit installed capacity cost, the unit fuel cost, the unit operation and maintenance cost, the unit start and stop cost, the unit emission cost, the unit abandoned energy cost, the unit energy shortage cost and the energy demand data, constructing a second function within the unit time length, where the unit time length is a preset unit time within the target operation cycle; Based on the second function corresponding to each unit time length in the target operation cycle, the first function in the target operation cycle is acquired.

9. The method according to claim 1, characterized in that: Determining the optimization configuration strategy of the multi-energy coupling system based on the system constraints and the objective function includes: Under the condition that the system constraints are met and the objective function reaches the preset conditions, determining the target energy supply unit and / or target transmission mode of the multi-energy coupling system; Determine the optimal configuration strategy of the multi-energy coupling system according to the determined target energy supply unit and / or target transmission mode; Among them, the target energy supply unit includes at least one of a photovoltaic power generation unit, a gas-fired power unit, a wind power unit, a coal-fired power unit, a nuclear power unit, a cogeneration unit, a gas boiler, a coal-fired boiler, and a trigeneration energy supply unit; the target transportation method includes at least one of cooling pipeline transportation, heat pipeline transportation, hydrogen pipeline transportation, road transportation, and power grid transportation.

10. An optimization configuration device for a multi-energy coupling system, the multi-energy coupling system is used to prepare, convert, transport, store and supply four terminal energies: electricity, heat, cold and hydrogen, characterized in that: include: A first acquisition module is used to acquire energy demand data of users in a target area, and acquire a first parameter of the multi-energy coupling system in a process of preparing a first energy, a second parameter in a process of converting the first energy into a second energy, a third parameter in a process of transmitting the second energy from a sending end to a receiving end, and a fourth parameter in a process of storing the second energy in a storage device; A second acquisition module, configured to acquire a system constraint condition based on the first parameter, the second parameter, the third parameter, the fourth parameter and the energy demand data; An objective function module, which is used for calculating the system cost of the multi-energy coupling system during operation and constructing an objective function based on the system cost and the energy demand data; The optimization configuration module is used to determine the optimization configuration strategy of the multi-energy coupling system based on the system constraints and the objective function.