Workshop foundation high fill construction method
Through geotechnical standard compaction testing and multi-layer step processing combined with large-area leveling and rolling, the problems of long construction period and high cost in high-fill construction of factory foundations were solved, and efficient and safe construction results were achieved, meeting the requirements of high-density degree requirements, reducing settlement and deformation.
Patent Information
- Application Number
- CN202410845381.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-27
- Publication Date
- 2024-10-18
AI Technical Summary
In high-fill projects for factory building foundations with a filling height of less than 25 meters, existing construction methods result in long construction periods and high costs, and are difficult to meet high density and safety requirements, affecting construction efficiency and economy.
The maximum dry density and optimal moisture content of the filler were determined through geotechnical standard compaction tests. Multi-layer step processing and large-area flattening and rolling methods were adopted to reduce the number of layered rolling layers and the number of inspections. Vibratory rollers of more than 20t were used. And conduct density testing during construction to ensure that the foundation density meets the design requirements.
It significantly improves construction efficiency, reduces construction costs, ensures construction safety and foundation quality, meets high density requirements, reduces settlement and deformation, and improves construction management levels.
Smart Images

Figure CN118793071A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of civil engineering, and in particular to a high filling construction method for a factory foundation. Background Art
[0002] In the field of civil engineering and ground treatment, high embankment fill usually refers to embankment projects with a large filling height. According to the Code for Design of Building Foundations (GB 50007-2011), high embankment fill usually refers to embankment projects with a filling height of more than 10 meters. High embankment fill projects usually require special design and construction methods to ensure the stability and safety of the embankment.
[0003] The existing high fill construction method generally adopts the strong tamping method first, which uses a heavy hammer to repeatedly tamp the foundation soil layer, and then uses the layered rolling method. The thickness of each layer of fill is usually controlled at 20-30 cm, and the layers are rolled and compacted layer by layer and the density is tested, resulting in a long construction period and high cost. When the high fill of the factory foundation with a filling height of less than 25m is used, a shorter construction period and a smaller budget are often required, and the high fill construction of the factory has higher requirements for stability and safety. For example, the density of the factory foundation fill is usually required to reach above 0.90, while ordinary buildings usually only need to reach above 0.85. When the existing technology is used for high fill of the factory foundation, the construction plan will be less economical and the construction speed will be slower. Unscientific reduction of construction links will affect the safety of factory construction.
[0004] Therefore, how to not reduce the construction safety requirements while improving the construction efficiency and reducing the construction cost when constructing a high fill of a factory foundation with a filling height of less than 25m is a technical problem that needs to be solved urgently in this field. Summary of the invention
[0005] In view of the above problems, the purpose of the present invention is to provide a method for high filling construction of factory foundation. When the high filling of factory foundation with a filling height of less than 25m is constructed, not only the construction efficiency is high, but also the construction cost can be effectively reduced.
[0006] The factory building foundation high filling construction method of the present invention is applicable to the factory building foundation filling project with a height greater than 10 meters and less than 25 meters, and comprises the following steps:
[0007] Filler treatment: Take the filler selected for the filling project and conduct a geotechnical standard compaction test to determine the maximum dry density and optimal moisture content requirements of the filler during construction; before construction, treat the filler so that it reaches the maximum dry density and optimal moisture content requirements during construction.
[0008] Treatment of the cut-and-fill transition zone: Starting from the backfill elevation value of the cut-and-fill transition zone, multiple layers of steps with a height of 1 meter and a width of 2 meters are excavated from top to bottom to the slope corner.
[0009] Data collection of test section: A 1-meter-high factory foundation is selected in other areas as the test section. The test section is directly flattened and rolled, and the construction parameter data, including the number of rolling times and rolling equipment parameters, are recorded until the density test results of the test section meet the design requirements.
[0010] Foundation filling: From bottom to top, the corresponding factory building foundation position and excavation and filling transition area of each layer are leveled and compacted on a large scale according to the parameters determined in the test section. The density of each layer is not tested. The foundation surface is compacted at least 6 times with rolling equipment until the density of the factory building foundation surface meets the design requirements.
[0011] Furthermore, in some embodiments, if the cross-sectional slope of the cut-fill transition zone is less than 1:5, the cut-fill transition zone can be directly flattened, filled and compacted on a large scale together with each layer of foundation without the need to dig multiple layers of steps.
[0012] Furthermore, in some embodiments, the filler is treated, including: spraying water to humidify the filler with low water content or airing the filler with high water content.
[0013] Furthermore, in some embodiments, the rolling equipment is a vibratory roller with a weight of more than 20t.
[0014] Furthermore, in some embodiments, when performing the density test, the test should be performed at least at 3 points / 1000m2.
[0015] It should be understood that within the scope of the present invention, the above-mentioned technical features of the present invention and the technical features specifically described below (such as embodiments) can be combined with each other to form a new or preferred technical solution. Due to space limitations, they will not be described one by one here.
[0016] Compared with the prior art, the present invention has the following technical effects:
[0017] The present invention reduces the number of layered rolling layers and the number of inspections, saves the strong tamping process, reduces the construction machinery usage fee and the inspection fee, reduces the construction cost, improves the construction efficiency, saves the construction period, and ensures the safety of the construction at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The above and other features and advantages of the present invention will become more apparent by describing in detail exemplary embodiments thereof with reference to the attached drawings.
[0019] Figure 1 The flowchart of the high fill construction method for factory foundation of the present invention is shown. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solution, beneficial effects and significant progress of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in combination with the embodiments of the present invention. Obviously, all the embodiments described are only partial embodiments of the present invention, not all embodiments; based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0021] The present invention will be further described below in conjunction with specific implementations. It should be understood that these embodiments are only used to illustrate the present invention and are not intended to limit the scope of the present invention.
[0022] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The phrase appearing in various locations in the specification does not necessarily refer to the same embodiment, nor is it limited to mutually exclusive independent or alternative embodiments. Those skilled in the art should be able to understand that the embodiments herein may be combined with other embodiments without causing structural conflicts.
[0023] In the description of this article, unless otherwise clearly specified and limited, the technical terms "installed", "connected", "connected" and the like should be understood in a broad sense, and can be a movable connection, a fixed connection or an integral connection, or a connection through a certain connector. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of this application can be understood according to specific circumstances.
[0024] In the description of this document, terms indicating orientation or positional relationships, such as "up", "down", "left", "right", "horizontal", "vertical", "height", "length", and "width", are intended to accurately describe the embodiments and simplify the description, but are not intended to limit the parts or structures involved to have a specific orientation, be installed or operate in a specific orientation, and should not be construed as a limitation on the embodiments in this document.
[0025] In the description of this article, the terms "first", "second" and the like are only used to distinguish different objects, and cannot be understood as indicating relative importance or limiting the quantity, specific order or primary and secondary relationship of the described technical features. In the description of this article, the meaning of "plurality" is at least two.
[0026] Embodiments of the present invention will now be described in detail with reference to the accompanying drawings. Reference will now be made in detail to preferred embodiments of the present invention, examples of which are shown in the accompanying drawings. Whenever possible, the same reference numerals will be used throughout the drawings to represent the same or similar parts.
[0027] Figure 1The flowchart of the high filling construction method of the factory foundation of the embodiment of the present invention is shown. The high filling construction method of the factory foundation of the present invention is suitable for the factory foundation filling project with a height greater than 10 meters and less than 25 meters, and includes the following steps:
[0028] S10: Filler treatment: Take the filler selected for the filling project and conduct a geotechnical standard compaction test to determine the maximum dry density and optimal moisture content requirements during filler construction; before construction, treat the filler so that it reaches the maximum dry density and optimal moisture content requirements during construction.
[0029] As those skilled in the art can understand, the main purpose of the geotechnical standard compaction test before foundation filling is to determine the optimal moisture content and maximum dry density of the filler, so as to ensure that the fill can achieve the density and stability required by the design during the construction process. The compaction test can guide the moisture content control and rolling process of the fill during the construction process, thereby improving the bearing capacity and stability of the foundation.
[0030] Specifically, taking the planting bodies with moderate wetness in the forest as fillers as an example, the filler processing includes the following steps S101-S105:
[0031] S101. Sampling: Select representative samples from the filler. The preferred filler sample quantity is at least 12 kg, which can meet the needs of multiple tests and retain a certain amount of spare samples to ensure the smooth progress of the test and the reliability of the results.
[0032] S102. Sample preparation: Set 5 different moisture contents for testing, namely 8%, 10%, 12%, 14% and 16%, and measure the initial moisture content of the filler sample. Select 2-3 kg from the filler sample as a spare sample, and divide the remaining samples into groups and process them to the set moisture content. As can be understood by those skilled in the art, if the selected filler has a low moisture content, the sample should be humidified to the set moisture content.
[0033] S103. Sample crushing: crush the sample into particles that can pass through a 4.75mm sieve. The purpose is to make the sample particle size more uniform, thereby improving the uniformity and consistency of the test results, while reducing the interference of large particles on the test results, making the test results more representative and reliable.
[0034] S104. Compaction test: Load the samples with adjusted moisture content into the compaction cylinder in three layers, with each layer about 1 / 3 of the height. Use a standard compaction hammer (mass 2.5kg, drop height 30.5cm) to compact each layer 25 times, ensuring that each compaction is evenly distributed over the entire surface. After the compaction is completed, use a scraper to scrape off the excess soil sample so that it is flush with the top of the compaction cylinder. Weigh the total mass of the compaction cylinder and the compacted soil sample and record the data. Take out a weight of sample from the compacted soil sample and dry it at 105℃~110℃ to constant weight. After drying, weigh the mass of the sample, calculate the moisture content, and record each experimental data according to the requirements of the standard compaction test.
[0035] S105. Data processing: Calculate the wet density based on the total mass of the compaction cylinder and the compacted soil sample. Calculate the dry density based on the wet density and moisture content. Draw a dry density-moisture content curve to determine the maximum dry density and optimal moisture content.
[0036] Further preferably, the filler is treated, including: spraying water to humidify the filler with low water content or airing the filler with high water content.
[0037] S20: Treatment of the cut-and-fill transition zone: starting from the backfill elevation value of the cut-and-fill transition zone, multiple layers of steps with a height of 1 meter and a width of 2 meters are excavated from top to bottom to the slope angle position.
[0038] Specifically, taking the filling project of the factory building with a foundation of 50m long * 20m wide * 20m high as an example, starting from the backfill elevation value of the cut-fill transition zone, steps of 1m high and 2m wide are dug step by step, and a total of 20 steps of 1m can be dug to the slope angle position. As those skilled in the art can understand, the quality and stability of the foundation directly affect the safety and durability of the entire project. The step treatment method for the cut-fill transition zone can increase the contact area between the foundation and the cut-fill transition zone, ensure smooth transition, and reduce stress concentration and uneven settlement.
[0039] S30: Test section data collection: Select a 1-meter-high factory foundation in other areas as the test section, directly flatten and compact the test section, and record the construction parameter data, including the number of rolling times and rolling equipment parameters; until the density test results of the test section meet the design requirements.
[0040] Specifically, taking the filling project of the factory foundation of 50m long * 20m wide * 20m high as an example, a section of the factory foundation in other nearby areas is selected as the test section, and the estimated filling volume is calculated according to the density requirements, filling volume, soil sample density and other data in the design stage. The filling is filled into the test section, and after leveling at a thickness of 1m, a 20t vibratory roller is used to directly flatten and roll the test section at least twice, and the construction parameter data is recorded, of which the 20t vibratory roller is rolled twice; if the design requirements are not met, the rolling operation is continued until the density meets the design requirements. The applicant and the inventor have found through experiments that after the plane of 50m long * 20m wide is leveled at a thickness of 1m, a 20t vibratory roller is used to roll it once, and the density measured at 3 points can reach 0.86, and the density can reach 0.94 or more after two rollings, which can meet the density requirement of 0.90 for most factory foundations.
[0041] S40: Foundation filling: From bottom to top, the corresponding plant foundation position and the excavation and filling transition area of each layer are leveled and filled and rolled in a large area according to the parameters determined in the test section. The density of each layer is not tested. The foundation surface is rolled at least 6 times with rolling equipment until the density of the plant foundation surface meets the design requirements. The preferred rolling equipment is a 20t vibratory roller.
[0042] Specifically, taking the filling project of the factory building foundation of 50m long * 20m wide * 20m high as an example, each foundation layer and the transition zone between filling and excavation are leveled at a height of 1 meter, and then a 20t vibratory roller is used to roll twice. The density of each layer is not tested. After the filling is completed, the foundation surface is rolled at least 6 times with a rolling equipment until the density of the factory building foundation surface meets the design requirements. As can be understood by those skilled in the art, the purpose of using a 20t vibratory roller to roll the top layer at least 6 times is to further improve the density and stability of the foundation, especially to reduce the porosity between the layers, to ensure that the foundation can withstand the load of the superstructure, and to reduce settlement and deformation.
[0043] Further preferably, when the cross-sectional slope of the cut-fill transition zone is less than 1:5, the cut-fill transition zone can be directly flattened, filled and compacted on a large scale together with each layer of foundation layer by layer at a height of 1 meter, without the need to start from the backfill elevation value of the cut-fill transition zone and dig multiple layers of steps with a height of 1 meter and a width of 2 meters from top to bottom to the slope angle. As those skilled in the art can understand, different slopes will affect the stability, construction difficulty and safety of the slope. When the cross-sectional slope of the cut-fill transition zone is less than 1:5, the slope is relatively gentle, the construction difficulty is relatively low, the stability of the slope is relatively high, and the risk of landslide and collapse is relatively low. Therefore, there is no need to start from the backfill elevation value of the cut-fill transition zone and dig multiple layers of steps with a height of 1 meter and a width of 2 meters from top to bottom to the slope angle; when the cross-sectional slope of the cut-fill transition zone is greater than 1:5, the slope is relatively steep and the construction difficulty is relatively high. The slope has poor stability and a high risk of landslide and collapse. It is necessary to start from the backfill elevation value of the cut-fill transition zone and dig multiple layers of 1-meter-high and 2-meter-wide steps from top to bottom to the slope angle to increase the contact area between the cut-fill transition zone and the foundation, improve the stability of the slope and the safety of construction, and reduce the difficulty of construction. Through layered replacement and rolling slope treatment, the stability and uniform settlement of the foundation and slope can be ensured, the transition between the fill and cut areas can be smoother, stress concentration can be reduced, and overall stability can be enhanced.
[0044] Furthermore, in some embodiments, the rolling equipment selects a vibrating roller of 20 tons or more. A 20t vibrating roller is preferred. The applicant and the inventor comprehensively compared 15t vibrating rollers, 20t vibrating rollers, and 25t vibrating rollers and conducted filling tests on a 50m long*20m wide*1m high filling project. It was found that at least 4 rollings with a 15t vibrating roller can make the surface density of the foundation reach 0.90, at least 2 rollings with a 20t vibrating roller can make the surface density of the foundation reach 0.90, and at least 2 rollings with a 25t vibrating roller can make the surface density of the foundation reach 0.90. The 20t vibrating roller is used at a lower cost and has the highest efficiency.
[0045] Furthermore, in some embodiments, when performing density testing, at least 3 points / 1000m 2 As can be understood by those skilled in the art, 3 points / 1000m 2 The high detection density can ensure that the detection results are highly representative and accurate, and avoid the overall judgment being affected by abnormal conditions at individual points. It can help discover local problems, improve construction quality control, ensure project safety, meet regulatory requirements, and improve data reliability and construction management level.
[0046] In summary, the factory building foundation high filling construction method of the present invention has the following beneficial effects compared with the prior art:
[0047] Compared with the prior art, the factory building foundation high filling construction method of the present invention has the following beneficial effects:
[0048] 1. Improve construction efficiency: The present invention reduces the number of layers and inspections, omits the tamping process, simplifies the construction process, and thus significantly improves construction efficiency. Especially in the high-fill project of the factory foundation with a filling height of less than 25 meters, the construction task can be completed more quickly to meet the urgent construction period requirements.
[0049] 2. Reduce construction costs: Since the number of times construction machinery is used and the number of times it is tested are reduced, the present invention reduces the cost of using construction machinery and the testing fee. In addition, the strong tamping process is omitted, further reducing the construction cost. Overall, the present invention can significantly reduce the construction cost while ensuring the construction quality.
[0050] 3. Ensure construction safety: This invention can ensure construction safety while improving construction efficiency and reducing costs. Through scientific filling treatment and rolling technology, the density and stability of the foundation are ensured to meet the high density requirements of the factory foundation fill (usually need to reach more than 0.90), thereby ensuring the safety and stability of the superstructure. When conducting density testing, at least 3 points / 1000m 2 The inspection density is maintained to ensure that the inspection results are highly representative and accurate, thus ensuring the quality of the project.
[0051] 4. Improve foundation quality: Determine the optimal moisture content and maximum dry density of the filler through geotechnical standard compaction test, and strictly control the moisture content and rolling process of the filler during construction to ensure the density and stability of the foundation. In particular, the treatment of the transition zone between excavation and filling, using multi-step steps and layered replacement and rolling slope treatment, further improves the quality and stability of the foundation.
[0052] 5. Reduce settlement and deformation: Through scientific filling treatment and rolling technology, the porosity of the foundation is reduced and the density of the foundation is improved, thereby reducing the settlement and deformation of the foundation under load and ensuring the stability and safety of the superstructure.
[0053] 6. Improve the level of construction management: Through scientific construction methods and strict quality control measures, the level of construction management has been improved. The construction unit can adjust the construction process and methods in time through the test data to ensure that every link in the construction process meets the quality requirements. At the same time, whether it is the treatment of fillers, the selection of rolling equipment, or the treatment method of the transition zone between excavation and filling, this method has strong flexibility and adaptability, and can meet the needs of different projects.
[0054] The high fill construction method for factory foundation of the present invention not only improves construction efficiency and reduces construction cost by optimizing construction process, scientifically processing filler, strictly controlling rolling process and density detection, but also ensures construction safety and foundation quality, reduces settlement and deformation, meets relevant regulatory requirements, and has significant technical and economic advantages.
[0055] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. The high filling construction method for factory foundation is characterized by: Applicable to the factory foundation filling project with a height greater than 10 meters and less than 25 meters, including the following steps: Filler treatment: Take the filler selected for the filling project and conduct a geotechnical standard compaction test to determine the maximum dry density and optimal moisture content requirements of the filler during construction; before construction, treat the filler so that it reaches the maximum dry density and optimal moisture content requirements during construction; Treatment of the cut-fill transition zone: Starting from the backfill elevation of the cut-fill transition zone, dig multiple layers of steps with a height of 1 meter and a width of 2 meters from top to bottom to the slope angle; Test section data collection: A 1-meter-high factory foundation is selected from other areas as the test section. The test section is directly flattened and rolled, and the construction parameter data, including the number of rolling times and rolling equipment parameters, are recorded until the density test results of the test section meet the design requirements; Foundation filling: From bottom to top, the corresponding factory building foundation position and excavation and filling transition area of each layer are leveled and compacted on a large scale according to the parameters determined in the test section. The density of each layer is not tested. The foundation surface is compacted at least 6 times with rolling equipment until the density of the factory building foundation surface meets the design requirements.
2. The high filling construction method for factory foundation according to claim 1 is characterized in that: If the cross-sectional slope of the cut-and-fill transition zone is less than 1:5, the cut-and-fill transition zone can be directly flattened, filled and compacted on a large scale together with each layer of foundation without the need to dig multiple layers of steps.
3. The high filling construction method for factory foundation according to claim 1 is characterized in that: The filler is processed, including: spraying water to humidify the filler with low water content or airing the filler with high water content.
4. The high filling construction method for factory foundation according to claim 1 is characterized in that: The rolling equipment is a vibratory roller with a 20t capacity or more.
5. The high filling construction method for factory foundation according to claim 1 is characterized in that: When conducting the density test, the test should be carried out at least at 3 points / 1000m2.