A temporary construction platform for stage engineering and construction method

By adopting multi-level support and limit mechanisms and motor-driven screw system in the temporary construction platform of stage engineering, the problems of inconvenience in disassembly and insufficient bearing capacity in the middle are solved, the stability and adaptability of the construction platform are improved, and construction safety is ensured. .

CN118815124BActive Publication Date: 2024-11-26SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411313100.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-26
Estimated Expiration
2044-09-20

AI Technical Summary

Technical Problem

The existing temporary construction platform for stage projects is inconvenient to disassemble and assemble during installation, and the middle load capacity is weak, which is easy to deform, affecting construction safety.

Method used

A construction platform including cow legs, corner frames, trusses, edge strips, fixing mechanisms and clamping mechanisms was designed to ensure structural stability through multi-layered support and limiting mechanisms, and to achieve rapid fixation through a motor-driven screw system. and disassembly to reduce dependence on bolts and enhance structural adaptability and safety.

Benefits of technology

The stability and load-bearing capacity of the platform have been improved, the construction period has been simplified, the adaptability and safety of the construction platform have been improved, and the problems of inconvenience in disassembly and assembly and insufficient bearing capacity in the middle have been solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118815124B_ABST
    Figure CN118815124B_ABST
Patent Text Reader

Abstract

This invention relates to a temporary construction platform and construction method for stage engineering, belonging to the field of building construction technology. Each set of brackets has multiple trusses sequentially spliced ​​between two corner frames, forming multiple hoisting holes for lifting. A first support strip is installed below the adjacent two trusses between two side strips to support the trusses. Fixing strips are fixed to the bottom of one side of both the corner frames and side strips to support the side trusses. Multiple baffles are respectively installed in corresponding hoisting holes to block the internal partitions of the trusses and guide objects. Multiple floorboards are sequentially spliced ​​to form a platform, which is then placed on two side strips to fix the floorboards to the trusses. A snap-fit ​​mechanism is installed on the trusses and works in conjunction with the fixing mechanism to automatically fix two adjacent trusses. This invention solves the problems of inconvenient assembly and disassembly, weak central load-bearing capacity, easy deformation, and impact on construction safety that exist in the installation of existing temporary construction platforms for stage engineering.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and relates to a temporary construction platform for stage engineering and a construction method. Background Art

[0002] With the continuous improvement of spiritual and cultural pursuits, theater construction has been booming. In order to install stage equipment in the venue within the shortest construction period, a construction platform can be set up on the ground between the above-ground and underground stage spaces. The construction platform can serve as a transportation channel for the above-ground stage space and can also achieve the purpose of separating the above-ground and underground stage spaces, making the construction space relatively independent and safe, and gaining space and time for the simultaneous construction of each stage.

[0003] However, the existing temporary construction platform for stage projects still has the following shortcomings during installation: 1. When assembling the construction platform, the large horizontal span trusses are connected by multiple bolts, which is difficult to connect and makes disassembly and assembly inconvenient; 2. When the large span trusses are spliced, the bearing capacity of the middle part is weak, and after long-term use, the middle part will deform. Summary of the invention

[0004] In view of this, the present invention provides a temporary construction platform for stage engineering and a construction method to solve the problems of inconvenient assembly and disassembly, weak bearing capacity in the middle part, easy deformation and affecting construction safety during the installation process of the above-mentioned existing temporary construction platform for stage engineering.

[0005] In order to achieve the above object, the present invention provides the following technical solutions:

[0006] A temporary construction platform for stage engineering, comprising two groups of brackets arranged on the ground, each group of brackets being provided with a corner frame, a plurality of trusses spliced ​​in sequence being provided between the two corner frames, and a plurality of hoisting holes for hoisting being formed between the plurality of trusses;

[0007] Two side bars, a plurality of first support bars are arranged between the two side bars, the first support bars are arranged below between two adjacent trusses, and are used to support the trusses, and the bottom of one side of the angle frame and the side bar are fixed with a fixing bar for supporting the side trusses;

[0008] A plurality of baffles, each of which is disposed in a corresponding hoisting hole and is used for blocking the inside of the truss and guiding an object;

[0009] Multiple floors, multiple floors are spliced ​​in sequence and located on multiple trusses to form a platform;

[0010] A fixing mechanism, arranged on the two side strips, for fixing the floor to the truss;

[0011] The clamping mechanism is arranged on the truss and is used in conjunction with the fixing mechanism to automatically fix two adjacent trusses.

[0012] Furthermore, a rectangular opening adapted to the ground is provided at the bottom of the corbel, and at least two bolts are provided through the rectangular opening and one side of the edge strip, and one end of the bolt is fixed to an inner wall of one side of the ground.

[0013] Furthermore, a limit block is fixedly provided on one side of the corbel, a limit groove corresponding to the limit block is opened on one side of the angle bracket, a positioning column is fixedly provided on the top of the corbel, and a positioning hole corresponding to the positioning column is opened on the top of the angle bracket for positioning the angle bracket.

[0014] Furthermore, the fixing mechanism includes two rotating seats fixed on the side strips, a screw rod is rotatably provided between the two rotating seats, a motor is fixedly provided on one side of one of the rotating seats, the output end of the motor is fixedly connected to the screw rod, a plurality of second support strips are threadedly sleeved on the two screw rods, a fixing rod corresponding to the truss is fixedly provided on the top of the second support rod, a second insertion rod is fixedly provided on one side of the fixing rod, and first insertion holes corresponding to the second insertion rod are opened on both sides of the truss for limiting the two adjacent trusses.

[0015] Furthermore, a sliding bar is provided for sliding inside the truss, a first fixed block corresponding to the floor is fixedly provided on the top of the sliding bar, a first pin is fixedly provided on one side of the first fixed block, a reinforcing rib is fixedly provided on the bottom of the floor, a plug block connected to the reinforcing rib is fixedly provided on one end of the reinforcing rib, a third plug hole corresponding to the first pin is provided on one side of the reinforcing rib, a second pin is fixedly provided on the bottom of one end of the sliding bar, a second fixed block is fixedly provided on one side of the fixed rod, a second plug hole connected to the second pin is provided on the top of the second fixed block, and the first pin is driven to be inserted into the corresponding third plug hole when the fixed rod moves.

[0016] Furthermore, the clamping mechanism includes a first plug rod fixedly arranged at one end of the truss, the first plug rod can be inserted into the other end of the truss, at least two first guide rods are fixedly arranged on one side of the truss, the outer walls of the two first guide rods are slidingly sleeved with the same sliding plate, the sliding plate corresponds to the first insertion hole, guide seats are fixedly arranged on the inner walls on both sides of the truss, the guide seat and one side of the truss slide through the same latch, the latch and the sliding plate are rotatably provided with the same connecting rod, the outer wall of the first plug rod is provided with a positioning groove which is plugged into the latch, and when the fixed rod drives the second plug rod to be inserted into the first insertion hole, it drives the latch to be inserted into the corresponding positioning groove.

[0017] Furthermore, a spring is sleeved on the outer wall of the first guide rod, and two ends of the spring are respectively fixedly connected to the outer wall of the first guide rod and one side of the sliding plate to provide resetting power for the latch.

[0018] Furthermore, a plurality of groups of limiting plates corresponding to the trusses are fixedly provided on the top of the first supporting bar, and a guiding part is provided on the top of the limiting plate. The two guiding parts form an eight-shaped shape for guiding and positioning the placement of the trusses.

[0019] Furthermore, connecting columns are fixedly provided between each set of limiting plates, and waist-shaped holes corresponding to the connecting columns are opened at the bottom of the truss for further limiting the installation of the truss.

[0020] A construction method for a temporary construction platform for a stage project comprises the following steps:

[0021] S1. Install the corbels on both sides of the ground, and install the side strips on the other two inner walls of the ground, and then install the two corner brackets on the two sets of corbels;

[0022] S2, splicing multiple trusses on two sets of corbels and two sets of side strips, and supporting the middle of the trusses through multiple first support strips and second support strips on the side strips, and limiting support for the trusses at both ends by the angle brackets on both sides, and reserving hoisting holes at the same time;

[0023] S3, installing the shield in the hoisting hole, and splicing multiple floors on multiple trusses;

[0024] S4, start the motor to drive the second support bar to move. The movement of the second support bar can drive the pin to be inserted into the corresponding positioning groove to fix the two adjacent trusses, and at the same time drive the first pin column to be inserted into the corresponding third plug hole to fix the floor.

[0025] The beneficial effects of the present invention are:

[0026] 1. A temporary construction platform for stage engineering disclosed in the present invention provides comprehensive support for the middle and both ends of the truss through a multi-level support and limiting mechanism, such as corbels, side strips, first support strips and second support strips, thereby ensuring the stability and load-bearing capacity of the platform structure. At the same time, the designs of limiting blocks and limiting grooves, positioning columns and positioning holes effectively limit the movement of the support strips, further enhancing the stability of the structure.

[0027] 2. The temporary construction platform for stage engineering disclosed in the present invention can not only drive the movement of the pin column in the guide seat, but also drive the insertion of the first pin column into the third socket by starting the motor, thereby realizing flexible fixation of the truss and the floor, so that the temporary construction platform can be quickly adjusted and reorganized according to different usage requirements, thereby enhancing the adaptability and flexibility of the temporary construction platform.

[0028] 3. The temporary construction platform for stage engineering disclosed in the present invention can quickly fix the truss through the coordinated use of the pin and the first plug rod, and there is no need to use bolts to connect, so that it is easy to disassemble and assemble, which can greatly shorten the construction period and is convenient for plugging and positioning.

[0029] 4. The temporary construction platform for stage engineering disclosed in the present invention can make the rectangular opening contact with the ground by setting a rectangular opening on one side of the corbel, thereby reducing the pressure on the bolts, effectively preventing the bolts from being subjected to excessive force and bending and breaking, and further improving the safety during use.

[0030] 5. The present invention discloses a temporary construction platform for stage engineering. When the construction platform is assembled, the clamping mechanism and the fixing mechanism arranged on the truss are used in cooperation to automatically fix the adjacent large span trusses laterally. The assembled truss structure is fixed longitudinally by the cooperation of the first support bar and the second support bar, so as to improve the bearing capacity of the middle part and facilitate the disassembly and assembly of the whole structure. The problems of inconvenient disassembly and assembly, weak bearing capacity in the middle part, easy deformation and affecting construction safety in the installation process of the existing temporary construction platform for stage engineering are solved. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be described in detail below in conjunction with the accompanying drawings, wherein:

[0032] Figure 1 It is a schematic diagram of the three-dimensional structure of a temporary construction platform for stage engineering of the present invention;

[0033] Figure 2 This is a schematic diagram of the three-dimensional structure of a temporary construction platform for stage engineering without the floor of the present invention;

[0034] Figure 3 This is a schematic diagram of the connection structure between the bracket and the ground of a temporary construction platform for stage engineering of the present invention;

[0035] Figure 4 This is a schematic diagram of a truss structure of a temporary construction platform for stage engineering of the present invention;

[0036] Figure 5 This is a schematic diagram of a truss docking structure of a temporary construction platform for stage engineering of the present invention;

[0037] Figure 6 for Figure 5 A schematic diagram of the enlarged structure of the middle part A;

[0038] Figure 7 This is a schematic diagram of the connection structure between the support strips and the side strips of a temporary construction platform for stage engineering of the present invention;

[0039] Figure 8The present invention is a schematic diagram of the floor-to-floor connection structure of a temporary construction platform for stage engineering.

[0040] Figure numerals: 1, ground; 2, corbel; 3, angle bracket; 4, truss; 5, lifting hole; 6, shield; 7, floor; 8, side strip; 9, rectangular opening; 10, bolt; 11, fixing strip; 12, limit block; 13, limit groove; 14, positioning hole; 15, positioning column; 16, sliding bar; 17, first fixing block; 18, first pin column; 19, second pin column; 20, first plug hole; 21, first plug rod; 22, positioning groove; 23, waist-shaped hole; 24, first support bar; 25, limit plate; 26, connecting column; 27, guide part; 28, first guide rod; 29, sliding plate; 30, spring; 31, connecting rod; 32, guide seat; 33, latch; 34, second support bar; 35, fixing rod; 36, second plug rod; 37, second fixing block; 38, second plug hole; 39, rotating seat; 40, screw; 41, motor; 42, reinforcing rib; 43, third plug hole; 44, plug block. DETAILED DESCRIPTION

[0041] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the illustrations provided in the following embodiments only illustrate the basic concept of the present invention in a schematic manner, and the following embodiments and features in the embodiments can be combined with each other without conflict.

[0042] like Figure 1-8 A temporary construction platform for stage engineering shown in the figure comprises two sets of corbels 2 installed on the ground 1, and a rectangular opening 9 adapted to the ground 1 is opened at the bottom of each set of corbels 2 to ensure that the corbels 2 are firmly attached to the ground 1. Subsequently, at least two bolts 10 are provided through one side of the rectangular opening 9 and the edge strip 8, and one end of the bolt 10 is firmly fixed to the inner wall of the ground 1, thereby further enhancing the stability of the corbels 2.

[0043] Next, the angle bracket 3 is installed on each group of corbels 2. A limiting groove 13 is designed on one side of the angle bracket 3, corresponding to the limiting block 12 on one side of the corbel 2. The limiting block 12 cooperates with the limiting groove 13 to ensure the accurate position of the angle bracket 3 on the corbel 2. At the same time, a positioning column 15 is fixed on the top of the corbel 2, and a positioning hole 14 corresponding to the positioning column 15 is opened on the top of the angle bracket 3. The positioning column 15 is plugged into the positioning hole 14 to further accurately position and fix the angle bracket 3.

[0044] Between the two corner frames 3, multiple groups of trusses 4 are sequentially spliced ​​and installed. Multiple hoisting holes 5 are formed between these trusses 4 for subsequent hoisting operations. In order to enhance the connection strength between the trusses 4, multiple first support bars 24 are arranged below between two adjacent trusses 4, and the two ends of these first support bars 24 are respectively fixed between the two side bars 8 to provide additional support for the trusses 4.

[0045] A shield 6 is installed in each hoisting hole 5 to block the space in the truss 4 and guide the hoisted objects to prevent them from being damaged by hitting the truss. Subsequently, multiple floors 7 are sequentially spliced ​​and installed on multiple trusses 4 to form the plane part of the construction platform.

[0046] In order to firmly fix the floor 7 on the truss 4, a fixing mechanism is designed. The fixing mechanism includes two rotating seats 39 fixed on the edge strips 8, and a screw rod 40 is rotatably provided between the two rotating seats 39. A motor 41 is installed on one side of one of the rotating seats 39, and the output end of the motor 41 is fixedly connected to the screw rod 40. The screw rod 40 can be driven to rotate by the drive of the motor 41. A plurality of second support bars 34 are threadedly sleeved on the screw rod 40. As the screw rod 40 rotates, the second support bars 34 will move along the axial direction of the screw rod 40. A fixing rod 35 corresponding to the truss 4 is fixedly provided on the top of each second support bar 34, and a second insertion rod 36 is fixedly provided on one side of the fixing rod 35. When the second support bar 34 moves, it will drive the fixing rod 35 and the second insertion rod 36 to move together until the second insertion rod 36 is inserted into the first insertion holes 20 on both sides of the two adjacent trusses 4, thereby realizing the limiting and fixing of the adjacent trusses 4.

[0047] In addition, in order to further enhance the connection strength between the floor 7 and the truss 4, a sliding bar 16 is slidably provided in the truss 4. A first fixing block 17 corresponding to the floor 7 is fixedly provided on the top of the sliding bar 16, and a first pin 18 is fixedly provided on one side of the first fixing block 17. A reinforcing rib 42 is fixedly provided on the bottom of the floor 7, and an insert block 44 is fixedly provided on one end of the reinforcing rib 42 for plugging and connecting with the adjacent reinforcing rib 42. A third insertion hole 43 corresponding to the first pin 18 is also provided on one side of the reinforcing rib 42. When the sliding bar 16 slides in the truss 4, it will drive the first fixing block 17 and the first pin 18 to move together until the first pin 18 is inserted into the corresponding third insertion hole 43, thereby firmly fixing the floor 7 on the truss 4.

[0048] At the same time, a second pin 19 is fixedly provided at the bottom of one end of the sliding bar 16, and a second fixing block 37 is fixedly provided at one side of the fixing rod 35. A second insertion hole 38 is provided at the top of the second fixing block 37 to be plugged with the second pin 19. When the fixing rod 35 moves, the second pin 19 is driven to be inserted into the second insertion hole 38, thereby further enhancing the connection stability between the floor 7 and the truss 4.

[0049] In order to achieve a quick and stable connection between the trusses 4, the following clamping mechanism is designed: a first plug rod 21 is fixedly set at one end of each truss 4, and the size and shape of the first plug rod 21 are designed to be accurately inserted into the hole reserved at the other end of the adjacent truss 4, thereby achieving preliminary docking.

[0050] At least two first guide rods 28 are fixedly mounted on one side of the truss 4. The two first guide rods 28 are arranged in parallel, and the outer wall thereof is slidably sleeved with a same sliding plate 29. The position of the sliding plate 29 corresponds to the first insertion hole 20 on the truss 4, and is used for guiding and positioning the subsequent latch 33.

[0051] Guide seats 32 are fixedly arranged on the inner walls of both sides of the truss 4, and a latch 33 is slidably installed through the guide seat 32 and one side of the truss 4. The latch 33 is rotatably connected to the sliding plate 29 through the connecting rod 31. When the sliding plate 29 slides along the first guide rod 28, the latch 33 will slide in the guide seat 32 accordingly through the transmission action of the connecting rod 31.

[0052] The outer wall of the first plug rod 21 is provided with a positioning groove 22 that matches the size of the latch pin 33. After the two trusses 4 are preliminarily connected through the first plug rod 21, the second plug rod 36 drives the sliding plate 29 to slide, thereby driving the latch pin 33 to be inserted into the positioning groove 22 on the first plug rod 21, thereby achieving a firm fixation between the trusses 4. At the same time, when the fixing rod 35 drives the second plug rod 36 to be inserted into the first insertion hole 20, the linkage mechanism also drives the latch pin 33 to be automatically inserted into the corresponding positioning groove 22, thereby enhancing the stability and reliability of the connection.

[0053] In order to ensure that the latch 33 can automatically reset when not needed, a spring 30 is sleeved on the outer wall of the first guide rod 28. The two ends of the spring 30 are respectively fixedly connected to the outer wall of the first guide rod 28 and one side of the sliding plate 29. When the second plug rod 36 is away from the sliding plate 29, the spring 30 can drive the sliding plate 29 to reset and move, and help the latch 33 to be smoothly pulled out of the positioning groove 22 through the connecting rod 31 and return to the initial position.

[0054] In order to further enhance the stability and installation convenience of the truss 4 on the platform, the following limit and guide mechanisms are designed:

[0055] A plurality of groups of limit plates 25 corresponding to the trusses 4 are fixedly arranged on the top of the first support bar 24. A guide portion 27 is provided at the top of each group of limit plates 25, and the two guide portions 27 form an eight-shaped structure, so that the trusses 4 can be accurately aligned and slide into a preset position when placed.

[0056] A connecting column 26 is fixedly arranged between each set of limiting plates 25, and a waist-shaped hole 23 corresponding to the connecting column 26 is provided at the bottom of the truss 4. When the truss 4 slides into the preset position along the guide portion 27, the connecting column 26 will enter the waist-shaped hole 23, and the cooperation between the two further limits the lateral movement of the truss 4, thereby enhancing the stability and safety of the overall structure.

[0057] A construction method for a temporary construction platform for a stage project, specifically comprising the following steps:

[0058] First, the corbels 2 and the side strips 8 are mounted on the inner wall of the floor 1 by means of bolts 10, and then two angle brackets 3 are mounted on the two sets of corbels 2, and the limiting blocks 12 are clamped in the corresponding limiting grooves 13, and the positioning columns 15 are inserted into the corresponding positioning holes 14 to limit the angle brackets 3;

[0059] Secondly, multiple trusses 4 are spliced ​​on two groups of corbels 2 and two groups of side strips 8, and the first insertion rods 21 are inserted into the corresponding trusses 4, and the splicing is carried out in sequence. The trusses 4 at both ends are in conflict with the corresponding fixing strips 11, and the middle part of the truss 4 is supported by multiple first support strips 24 and second support strips 34 on the side strips 8, and the trusses 4 at both ends are limitedly supported by the angle brackets 3 on both sides, and the lifting holes 5 are reserved at the same time. At the same time, in the process of placing the truss 4 on the fixing strip 11, the second pin column 19 is inserted into the corresponding second insertion hole 38. In the process of placing, the truss 4 can be guided by multiple groups of limiting plates 25, so that two adjacent trusses 4 are located between the two limiting plates 25, and the connecting column 26 is stuck in the waist-shaped hole 23 to limit the interval between adjacent trusses 4;

[0060] Then, the shield 6 is installed in the hanging hole 5, and the shield 6 is also made to contact the truss 4 by using the limit plate 25 and the connecting column 26, and a plurality of floors 7 are spliced ​​on a plurality of trusses 4, so that the plug block 44 is inserted into the corresponding third plug hole 43 and corresponds to the hanging hole 5;

[0061] Finally, the motor 41 is started to drive multiple second support bars 34 to move simultaneously. The movement of the second support bars 34 can drive the fixing rod 35 to move. The movement of the fixing rod 35 can drive the second insertion rod 36 to be inserted into the corresponding first socket 20, and drive the sliding plate 29 to move during the penetration process. The movement of the sliding plate 29 can drive the latch 33 to move in the guide seat 32 through the connecting rod 31, so that the latch 33 is inserted into the corresponding positioning groove 22 to fix the two adjacent trusses 4. In the process of moving the fixing rod 35, the second pin 19 can also be driven to move through the second socket 38 on the second fixing block 37. The movement of the second pin 19 can drive the sliding bar 16 to move. The movement of the sliding bar 16 can simultaneously drive multiple first fixing blocks 17 to move, and drive the first pin 18 to be inserted into the corresponding third socket 43 to fix the floor 7, and the installation is completed.

[0062] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution, which should be included in the scope of the claims of the present invention.

Claims

1. A temporary construction platform for stage engineering, It is characterized in that It comprises two groups of brackets (2) arranged on the ground (1), each group of the brackets (2) is provided with an angle frame (3), a plurality of trusses (4) spliced ​​in sequence are provided between the two angle frames (3), and a plurality of hoisting holes (5) for hoisting are formed between the plurality of trusses (4); Two side bars (8), a plurality of first support bars (24) being provided between the two side bars (8), the first support bars (24) being provided below between two adjacent trusses (4) for supporting the trusses (4), and a fixing bar (11) for supporting the side trusses (4) being fixedly provided at the bottom of one side of the angle frame (3) and the side bar (8); A plurality of blocking covers (6), wherein the plurality of blocking covers (6) are respectively arranged in corresponding lifting holes (5) and are used for blocking inside the truss (4) and guiding objects; A plurality of floors (7), wherein the plurality of floors (7) are sequentially spliced ​​and located on a plurality of trusses (4) to form a platform; A fixing mechanism, arranged on the two side strips (8), for fixing the floor (7) on the truss (4); The clamping mechanism is arranged on the truss (4) and is used in conjunction with the fixing mechanism to automatically fix two adjacent trusses (4).

2. A temporary construction platform for stage engineering as claimed in claim 1, It is characterized in that The bottom of the bracket (2) is provided with a rectangular opening (9) adapted to the ground (1), and at least two bolts (10) are provided through one side of the rectangular opening (9) and the side strip (8), and the bracket (2) and the side strip (8) are fixed to the inner wall of the ground (1) by means of the bolts (10).

3. A temporary construction platform for stage engineering as claimed in claim 2, It is characterized in that A limiting block (12) is fixedly provided on one side of the corbel (2), a limiting groove (13) corresponding to the limiting block (12) is provided on one side of the angle bracket (3), a positioning column (15) is fixedly provided on the top of the corbel (2), and a positioning hole (14) corresponding to the positioning column (15) is provided on the top of the angle bracket (3) for positioning the angle bracket (3).

4. A temporary construction platform for stage engineering as claimed in claim 3, It is characterized in that The fixing mechanism comprises two rotating seats (39) fixedly arranged on the side bars (8), a screw rod (40) rotatably passing through the two rotating seats (39), a motor (41) being fixedly arranged on one side of one of the rotating seats (39), an output end of the motor (41) being fixedly connected to the screw rod (40), a plurality of second support bars (34) being threadedly sleeved on the two screw rods (40), a fixing rod (35) corresponding to the truss (4) being fixedly arranged on the top of the second support bar (34), a second insertion rod (36) being fixedly arranged on one side of the fixing rod (35), and first insertion holes (20) corresponding to the second insertion rod (36) being provided on both sides of the truss (4) for limiting the position of two adjacent trusses (4).

5. A temporary construction platform for stage engineering as claimed in claim 4, It is characterized in that A sliding bar (16) is slidably provided in the truss (4), a first fixed block (17) corresponding to the floor (7) is fixedly provided on the top of the sliding bar (16), a first pin (18) is fixedly provided on one side of the first fixed block (17), a reinforcing rib (42) is fixedly provided on the bottom of the floor (7), an insert block (44) plugged into the reinforcing rib (42) is fixedly provided on one end of the reinforcing rib (42), a third plug hole (43) corresponding to the first pin (18) is provided on one side of the reinforcing rib (42), a second pin (19) is fixedly provided on the bottom of one end of the sliding bar (16), a second fixed block (37) is fixedly provided on one side of the fixing rod (35), a second plug hole (38) plugged into the second pin (19) is provided on the top of the second fixed block (37), and when the fixing rod (35) moves, the first pin (18) is driven to be inserted into the corresponding third plug hole (43).

6. A temporary construction platform for stage engineering as claimed in claim 5, It is characterized in that The clamping mechanism comprises a first plug rod (21) fixedly arranged at one end of the truss (4), the first plug rod (21) being capable of being inserted into the other end of the truss (4), at least two first guide rods (28) being fixedly arranged on one side of the truss (4), the outer walls of the two first guide rods (28) being slidably sleeved with a same sliding plate (29), the sliding plate (29) corresponding to the first insertion hole (20), guide seats (32) being fixedly arranged on the inner walls of both sides of the truss (4), a same sliding pin (33) slidingly passing through the guide seat (32) and one side of the truss (4), a same connecting rod (31) being rotatably arranged between the plug pin (33) and the sliding plate (29), a positioning groove (22) being arranged on the outer wall of the first plug rod (21) being plugged into the plug pin (33), and when the fixing rod (35) drives the second plug rod (36) to be inserted into the first insertion hole (20), the plug pin (33) is driven to be inserted into the corresponding positioning groove (22).

7. A temporary construction platform for stage engineering as claimed in claim 6, It is characterized in that The outer wall of the first guide rod (28) is sleeved with a spring (30), and the two ends of the spring (30) are respectively fixedly connected to the outer wall of the first guide rod (28) and one side of the sliding plate (29), so as to provide a reset force for the latch (33).

8. A temporary construction platform for stage engineering as claimed in claim 1, It is characterized in that A plurality of groups of limit plates (25) corresponding to the trusses (4) are fixedly provided on the top of the first support bar (24), and a guide portion (27) is provided on the top of the limit plate (25), and the two guide portions (27) form an eight-shaped shape for guiding and positioning the placement of the trusses (4).

9. A temporary construction platform for stage engineering as claimed in claim 8, It is characterized in that A connecting column (26) is fixedly provided between each set of the limiting plates (25), and a waist-shaped hole (23) corresponding to the connecting column (26) is provided at the bottom of the truss (4) for further limiting the installation of the truss (4).

10. A construction method for a temporary construction platform for stage engineering according to claim 6 or 7, It is characterized in that The following steps are involved: S1, after installing the corbels (2) on both sides of the ground (1), installing the side strips (8) on the other two inner walls of the ground (1), and then installing the two corner brackets (3) on the two sets of corbels (2); S2, splicing a plurality of trusses (4) onto two groups of corbels (2) and two groups of side strips (8), and supporting the middle of the trusses (4) through a plurality of first support strips (24) and second support strips (34) on the side strips (8), and providing position-limiting support to the trusses (4) at both ends through the angle brackets (3) on both sides, and at the same time reserving lifting holes (5); S3, installing the baffle (6) in the lifting hole (5), and splicing the plurality of floors (7) onto the plurality of trusses (4); S4, starting the motor (41) to drive the second support bar (34) to move. The movement of the second support bar (34) can drive the latch (33) to be inserted into the corresponding positioning groove (22) to fix the two adjacent trusses (4), and at the same time drive the first pin (18) to be inserted into the corresponding third insertion hole (43) to fix the floor (7).