A dynamic test device and method for a process electric regulator for uranium enrichment cascade

By designing a test device including evacuation, gas evaporation, boosting, process and monitoring systems, the problem of dynamic test performance verification of process electric regulators is solved, and the accurate simulation of process electric regulators in high pressure and high flow environments is achieved. and assessment.

CN118817362BActive Publication Date: 2024-11-19CNNC LANZHOU URANIUM ENRICHMENT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411295519.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-18
Publication Date
2024-11-19
Estimated Expiration
2044-09-18

AI Technical Summary

Technical Problem

There is a lack of testing devices for verifying the dynamic test performance of process electric regulators in the prior art, and it cannot meet the stability verification needs of process electric regulators in uranium enrichment plants.

Method used

A dynamic testing device for an uranium enrichment cascade process electric regulator is designed, including a evacuation device, a gas evaporation device, a boosting system, a process system, an orifice system and a monitoring system, through which process gas under load conditions is simulated In operation conditions, adjust the inlet pressure of the booster system, and ensure that the test is carried out within the safe pressure range through multiple monitoring points.

Benefits of technology

The device can effectively simulate the performance of the process electric regulator in high pressure and high flow environments, improve test accuracy and reliability, and ensure the evaluation of the dynamic characteristics of the process electric regulator.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118817362B_ABST
    Figure CN118817362B_ABST
Patent Text Reader

Abstract

The present application provides a dynamic test device and method for a process electric regulator for uranium enrichment cascade, wherein the dynamic test device for the process electric regulator for uranium enrichment cascade includes an evacuation device, a gas evaporation device, a pressurization system, a process system, an orifice plate system, and a monitoring system. The evacuation device, the pressurization system, the process system, and the orifice plate system are sequentially connected in series on the main pipeline, and the gas evaporation device is arranged on a branch pipeline connecting the pipeline between the evacuation device and the pressurization system. The present application verifies whether the dynamic test performance of the process electric regulator can meet the use requirements by setting up a dynamic test device dedicated to the process electric regulator for uranium enrichment cascade, and verifies the ability of the process electric regulator to stabilize the system pressure in actual operation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of uranium enrichment, and in particular relates to a dynamic test device and method for a process electric regulator for a uranium enrichment cascade. Background Art

[0002] In a uranium enrichment plant, the process electric regulator (hereinafter referred to as the regulator) is one of the key equipment. With the increase in project capacity, the nominal diameter of the process electric regulator currently used in uranium enrichment projects has increased to DN300mm, and the valve plate diameter of the process electric regulator has increased to φ100mm to φ210mm. In order to verify the stability of the process electric regulator in the project, it is necessary to design a test device that simulates the operating conditions to verify whether the performance of the process electric regulator can meet the use requirements. Summary of the invention

[0003] In view of this, the embodiments of the present application are committed to providing a dynamic test device and method for a process electric regulator for a uranium enrichment cascade. By setting up a dynamic test device dedicated to a process electric regulator for a uranium enrichment cascade, the problem that there is no test device in the prior art for verifying whether the dynamic test performance of the process electric regulator can meet the use requirements is solved.

[0004] In the first aspect of the present application, a dynamic test device for a process electric regulator for a uranium enrichment cascade is provided, and the dynamic test device for the process electric regulator for a uranium enrichment cascade includes an evacuation device, a gas evaporation device, a pressurization system, a process system, an orifice plate system and a monitoring system. The evacuation device is used to pre-evacuate the dynamic test device for the process electric regulator for a uranium enrichment cascade; the gas evaporation device includes a heating device, a first condenser and a flange vacuum valve corresponding to the first condenser, the heating device is used to evaporate the liquid Freon stored in the first condenser, and the flange vacuum valve corresponding to the first condenser is used to control the opening and closing of the channel where the first condenser is located. The evacuation device, the pressurization system, the process system and the orifice plate system are connected in series on the main pipeline in sequence, and the gas evaporation device is arranged on the branch pipeline connecting the pipeline between the evacuation device and the pressurization system. The pressurization system includes three groups of booster devices arranged in parallel, and each group of booster devices includes a first booster, a second booster and a first rotary drum vacuum valve connected in series in sequence through a pipeline. The process system has a first channel, and the first channel is provided with a second drum vacuum valve and a process electric regulator connected in series in sequence. The orifice system has three parallel second channels, a third channel and a fourth channel, the second channel is provided with a fourth drum vacuum valve, the third channel is provided with a fifth drum vacuum valve and a first flow orifice connected in series, and the fourth channel is provided with a sixth drum vacuum valve and a second flow orifice connected in series. The monitoring system includes a first pressure monitoring instrument, a second pressure monitoring instrument, a third pressure monitoring instrument, a fourth pressure monitoring instrument and a fifth pressure monitoring instrument, the first pressure monitoring instrument is provided at the inlet of the boosting system, the second pressure monitoring instrument is provided at the outlet of the boosting system, the third pressure monitoring instrument is provided at the outlet of the process system, the fourth pressure monitoring instrument is provided at the rear end of the orifice system, the rear end of the orifice system is connected with the front end of the boosting system, and the fifth pressure monitoring instrument is provided on a branch pipeline connecting the exhaust port of the first condenser and the inlet of the boosting system and is used to connect the pressure signal with the regulator feed signal.

[0005] In a specific embodiment of the present application, the dynamic test device of the process electric regulator for uranium enrichment cascade also includes a gas condensing device. The gas condensing device includes a low-temperature thermostat, a torpedo vacuum valve, a second condenser and a flange vacuum valve corresponding to the second condenser. The second condenser is placed inside the low-temperature thermostat. The channel formed by connecting the second condenser and the flange vacuum valve corresponding to the second condenser is a parallel structure with the torpedo vacuum valve. The flange vacuum valve corresponding to the second condenser is used to control the opening and closing of the pipeline where the second condenser is located. The evacuation device, the torpedo vacuum valve, the boosting system, the process system and the orifice plate system are connected in series on the main pipeline in sequence. The channel formed by the first condenser and the flange vacuum valve corresponding to the first condenser is located on the branch pipeline connecting the pipeline between the torpedo vacuum valve and the boosting system.

[0006] In a specific embodiment of the present application, the flange vacuum valve corresponding to the second condenser includes a first flange vacuum valve, a second flange vacuum valve, a third flange vacuum valve and a fourth flange vacuum valve, and the gas condensing device also includes a first vacuum bellows and a second vacuum bellows. The exhaust port of the second condenser is connected in series with the first flange vacuum valve, the first vacuum bellows and the third flange vacuum valve in sequence, and then connected to the inlet of the torpedo vacuum valve. The air inlet of the second condenser is connected in series with the second flange vacuum valve, the second vacuum bellows and the fourth flange vacuum valve in sequence, and then connected to the outlet of the torpedo vacuum valve.

[0007] In a specific embodiment of the present application, the flange vacuum valve corresponding to the first condenser includes a fifth flange vacuum valve, a sixth flange vacuum valve and a seventh flange vacuum valve, the gas evaporation device also includes a third vacuum bellows, and the exhaust port of the first condenser is connected to the fifth flange vacuum valve. The air inlet of the first condenser is connected in series with the sixth flange vacuum valve, the third vacuum bellows and the seventh flange vacuum valve in sequence, and then connected to the connecting pipe between the torpedo vacuum valve and the boosting system.

[0008] In a specific embodiment of the present application, the gas evaporation device further includes a manual fine-tuning valve, which is connected in parallel with the seventh flange vacuum valve, and the adjustment accuracy of the seventh flange vacuum valve is greater than the adjustment accuracy of the manual fine-tuning valve.

[0009] In a specific embodiment of the present application, the process system is further provided with a fifth channel connected in parallel with the first channel. The fifth channel is provided with a third rotary drum vacuum valve and an electric regulating valve connected in series in sequence.

[0010] In a specific embodiment of the present application, the evacuation device includes an interlock-activated sliding valve vacuum pump and an electromagnetic belt inflation valve.

[0011] In a specific embodiment of the present application, a tilt sensor is also provided on the process electric regulator. The tilt sensor is installed at the end of a large lever of the process electric regulator. The tilt sensor is used to measure the difference between the time of pressure change and the time of adjustment of the large lever of the process electric regulator when the dynamic test device of the process electric regulator for uranium enrichment cascade flows through the process electric regulator.

[0012] In a specific embodiment of the present application, the dynamic test device of the process electric regulator for uranium enrichment cascade also includes a control panel cabinet. The control panel cabinet is connected to the monitoring system and the boosting system, and is used to control the start and stop of the boosting system and display the data of the monitoring system. The control panel cabinet includes a control cabinet and an industrial computer. The control cabinet is used to power the industrial computer. The control cabinet includes one or more of a plurality of booster compressor inverters and a plurality of booster compressor control buttons, an evacuation device control module, a temperature control module, and a regulator control module. The evacuation device control module is used to control the start and stop of the evacuation device, the temperature control module is used to control the temperature of the heating equipment, the regulator control module is used to power the servo mechanism of the process electric regulator and control the forward and reverse rotation and display angle of the motor of the process electric regulator, the plurality of booster compressor inverters are used to respectively control the plurality of first booster compressors and the plurality of second booster compressors to operate at variable frequencies between 50 Hz and 100 Hz, and the plurality of booster compressor control buttons are used to control the start and stop of the plurality of first booster compressors and the plurality of second booster compressors. The industrial computer includes one or more secondary meters corresponding to multiple pressure monitoring instruments and digital displays corresponding to inclination sensors. The secondary meters corresponding to the multiple pressure monitoring instruments are used to display, output and record the readings of the multiple pressure monitoring instruments respectively, and store, read and output the historical records monitored by the multiple pressure monitoring instruments. The digital display corresponding to the inclination sensor is used to display the signal of the inclination sensor as a real-time curve, and store, read and output the historical records of the inclination sensor measurements.

[0013] The second aspect of the present application provides a dynamic test method for a uranium enrichment cascade process electric regulator, the dynamic test method for a uranium enrichment cascade process electric regulator comprising: before the dynamic test, adding liquid Freon into the first condenser of the gas evaporation device in any dynamic test device of the uranium enrichment cascade process electric regulator provided in the first aspect of the present application; when the dynamic test is performed, opening the evacuation device in the dynamic test device of the uranium enrichment cascade process electric regulator to perform a pre-evacuation operation until the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator is lower than 1Pa, and then closing the evacuation device; using the gas evaporation device to perform a Freon introduction operation, when the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator reaches 800Pa, closing the first condenser to Flange vacuum valve should be installed; start the boosting system and gradually adjust it to variable frequency operation between 50Hz and 100Hz; open the valve of one of the flow orifice plates in the third channel and the fourth channel until the gas circulates in the dynamic test device of the process electric regulator for uranium enrichment cascade and reaches a stable state; close the valve of one of the flow orifice plates in the third channel and the fourth channel, open the valve of the other flow orifice plate in the third channel and the fourth channel, observe and record the pressure changes of the second pressure monitoring instrument and the third pressure monitoring instrument; open the valves of the two flow orifice plates in the third channel and the fourth channel, observe and record the pressure changes of the second pressure monitoring instrument and the third pressure monitoring instrument; if the stable pressure changes of the process electric regulator are not greater than 0.05torr, the dynamic characteristics of the process electric regulator are judged to be qualified.

[0014] The beneficial effects of the technical solution of the present application are: by setting a vacuum device to pre-evacuate the dynamic test device of the process electric regulator for uranium enrichment cascade, a heating device in the gas evaporation device is set to evaporate the liquid Freon stored in the first condenser, so that the evaporated Freon can be passed into the dynamic test device of the process electric regulator for uranium enrichment cascade, simulating the process gas operation condition under load conditions, this gas evaporation process directly affects the inlet pressure of the boosting system, and the evaporation amount of Freon can be controlled by adjusting the heating temperature of the heating device, so as to accurately adjust the inlet pressure of the boosting system and transmit the changed pressure to the process electric regulator. By setting a monitoring system including multiple pressure monitoring instruments, the pressure of each key pressure measuring point in the dynamic test device of the process electric regulator for uranium enrichment cascade is monitored, so that multiple monitoring points are set in the whole gas evaporation and pressure regulation process, ensuring that the dynamic test is carried out within a safe pressure range. By using the opening and closing of the second rotary drum vacuum valve on the first channel of the process system, the switching operation of the process electric regulator in the cascade unit is simulated, and the airflow control under different operating conditions is realized by controlling the opening of the second rotary drum vacuum valve. By setting three parallel second channels, third channels and fourth channels in the orifice plate system, the opening of the fourth drum vacuum valve is used to control the pressure or flow rate in the second channel, and the corresponding relationship between the flow rate and pressure of the process electric regulator is measured and calculated through different flow orifices in the third channel and the fourth channel. In addition, by setting the booster system including three sets of booster devices set in parallel, the dynamic test requirements of the process electric regulator are met by controlling the variable frequency motion of the three sets of booster devices, so that the dynamic test device of the process electric regulator for uranium enrichment cascade can effectively simulate the high pressure environment of the process electric regulator. By adding an orifice plate system and using the three parallel channels in the orifice plate system, the dynamic test device of the process electric regulator for the enrichment cascade greatly improves the test accuracy and reliability when simulating high flow and high pressure environments. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 Shown is a schematic structural diagram of a dynamic test device for a process electric regulator for a uranium enrichment cascade provided in one embodiment of the present application.

[0016] Figure 2 Shown Figure 1 A plan view of a dynamic test apparatus for a process electric regulator for a uranium enrichment cascade according to the embodiment shown.

[0017] Figure 3 Shown Figure 1 The elevational layout along the AA direction of the dynamic test device for the process electric regulator for the uranium enrichment cascade of the illustrated embodiment.

[0018] Figure 4 Shown Figure 3 The elevational layout along the BB direction of the dynamic test device for the process electric regulator for uranium enrichment cascade of the illustrated embodiment.

[0019] Figure 5 Shown Figure 3 The elevational layout along the CC direction of the dynamic test device for the process electric regulator for the uranium enrichment cascade of the illustrated embodiment.

[0020] Figure 6 Shown Figure 3 The elevational layout along the DD direction of the dynamic test device for the process electric regulator for the uranium enrichment cascade of the illustrated embodiment.

[0021] Figure 7 Shown is a schematic flow chart of a dynamic test method for a process electric regulator for a uranium enrichment cascade provided in one embodiment of the present application. DETAILED DESCRIPTION

[0022] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0023] At least one embodiment of the present application provides a dynamic test device for a uranium enrichment cascade process electric regulator, referring to Figure 1 The dynamic test device of the process electric regulator for uranium enrichment cascade includes an evacuation device, a gas evaporation device, a pressurization system, a process system, an orifice system and a monitoring system. The evacuation device is used to pre-evacuate the dynamic test device of the process electric regulator for uranium enrichment cascade. The gas evaporation device includes a heating device 12, a first condenser 3-1 and a flange vacuum valve corresponding to the first condenser 3-1. The heating device 12 is used to evaporate the liquid Freon stored in the first condenser 3-1. The flange vacuum valve corresponding to the first condenser 3-1 is used to control the opening and closing of the channel where the first condenser 3-1 is located. The evacuation device, the pressurization system, the process system and the orifice system are connected in series on the main pipeline in sequence, and the gas evaporation device is arranged on the branch pipeline connecting the pipeline between the evacuation device and the pressurization system. The rear end of the orifice system is connected to the front end of the pressurization system.

[0024] The boosting system includes three groups of booster devices arranged in parallel, each group of booster devices including a first booster 4-1, a second booster 4-2 and a first rotary drum vacuum valve 7-1 which are sequentially connected in series through pipelines.

[0025] The process system has a first channel on which a second rotary drum vacuum valve 7-2 and a process electric regulator 5 are arranged in series.

[0026] The orifice plate system has three parallel second channels, a third channel and a fourth channel. The second channel is provided with a fourth drum vacuum valve 7-4, the third channel is provided with a fifth drum vacuum valve 7-5 and a first flow orifice plate 8-1 connected in series, and the fourth channel is provided with a sixth drum vacuum valve 7-6 and a second flow orifice plate 8-2 connected in series.

[0027] The monitoring system includes a first pressure monitoring instrument PI001, a second pressure monitoring instrument PI002, a third pressure monitoring instrument PI003, a fourth pressure monitoring instrument PI004 and a fifth pressure monitoring instrument PI005. The first pressure monitoring instrument PI001 is arranged at the inlet of the boosting system. The second pressure monitoring instrument PI002 is arranged at the outlet of the boosting system. The third pressure monitoring instrument PI003 is arranged at the outlet of the process system. The fourth pressure monitoring instrument PI004 is arranged at the rear end of the orifice system. The fifth pressure monitoring instrument PI005 is arranged on a branch pipeline connecting the exhaust port of the first condenser 3-1 and the inlet of the boosting system, and is used to connect the pressure signal with the regulator feed signal.

[0028] It should be noted that the heating device 12 can be an electric heating belt, which can be arranged outside the first condenser 3-1. The first pressure monitoring instrument PI001 is used to monitor the pressure at the inlet of the boosting system. The second pressure monitoring instrument PI002 is used to monitor the pressure at the outlet of the boosting system. The outlet pressure of the boosting system is also the front end pressure of the process electric regulator 5. The second pressure monitoring instrument PI002 is mainly used to keep the front end pressure of the process electric regulator 5 stable. If the process electric regulator 5 is a pressure regulator, the pressure at the outlet of the boosting system is the main control pressure. The third pressure monitoring instrument PI003 is used to monitor the pressure at the rear end of the process electric regulator 5. The process electric regulator 5 controls the pressure at the front end of the process electric regulator 5 by controlling the opening of the valve plate, thereby generating a pressure difference before and after the process electric regulator 5 (for example, the pressure difference range is 5mmHg~50mmHg). The fourth pressure monitoring instrument PI004 is used to monitor the pressure at the rear end of the flow orifice plate. Its main function is to measure the control of the flow orifice plate on the flow of the dynamic test device of the process electric regulator 5 for uranium enrichment cascade. The fifth pressure monitoring instrument PI005 is the feed pressure control point. Its main function is to connect the pressure signal with the regulator feed signal during the dynamic test, and control the pressure of the fifth pressure monitoring instrument PI005 by opening or closing the valve of the corresponding flange vacuum valve of the first condenser 3-1, so as to feed back to the regulator feed pressure, so as to simulate the unit feed pressure fluctuation in the uranium enrichment cascade and adjust the lean material pressure.

[0029] According to the technical solution provided in the embodiment of the present application, the dynamic test device of the process electric regulator for uranium enrichment cascade is pre-evacuated by setting an evacuation device, and the heating device 12 in the gas evaporation device is set to evaporate the liquid Freon stored in the first condenser 3-1, so that the evaporated Freon can be passed into the dynamic test device of the process electric regulator for uranium enrichment cascade, simulating the process gas operation condition under load conditions. This gas evaporation process directly affects the inlet pressure of the boosting system. By adjusting the heating temperature of the heating device 12, the evaporation amount of Freon can be controlled, thereby accurately adjusting the inlet pressure of the boosting system and transmitting the changed pressure to the process electric regulator 5. By setting a monitoring system including multiple pressure monitoring instruments, the pressure of each key pressure measuring point in the dynamic test device of the process electric regulator for uranium enrichment cascade is monitored, so that multiple monitoring points are set in the entire gas evaporation and pressure regulation process, ensuring that the dynamic test is carried out within a safe pressure range. By using the opening and closing of the second drum vacuum valve 7-2 on the first channel of the process system, the switching operation of the process electric regulator 5 in the cascade unit is simulated, and the airflow control under different operating conditions is achieved by controlling the opening of the second drum vacuum valve 7-2. By setting three parallel second channels, third channels and fourth channels in the orifice system, the pressure or flow is controlled by the opening of the fourth drum vacuum valve 7-4 on the second channel, and the corresponding relationship between the flow and pressure of the process electric regulator 5 is measured and calculated by using different flow orifices on the third channel and the fourth channel. In addition, by setting the boosting system including three sets of booster devices arranged in parallel, the dynamic test requirements of the process electric regulator 5 are met by controlling the variable frequency motion of the three sets of booster devices, so that the dynamic test device of the process electric regulator for uranium enrichment cascade can effectively simulate the high pressure environment (for example, the working pressure range is 5mmHg to 50mmHg) of the process electric regulator 5. By adding an orifice plate system and using three parallel channels in the orifice plate system, the dynamic test device for the process electric regulator for the enrichment cascade greatly improves the test accuracy and reliability when simulating a high flow and high pressure environment. The embodiment of the present application verifies whether the dynamic test performance of the process electric regulator 5 can meet the use requirements by setting up a dynamic test device dedicated to the process electric regulator for uranium enrichment cascade, and verifies the ability of the process electric regulator 5 to stabilize the system pressure in actual operation. In addition, since the test gas used in the dynamic test device for the process electric regulator for uranium enrichment cascade is Freon (C7F 14 ), with a molecular weight of 350g / mol. The gas actually produced is UF6 gas, with a molecular weight of 352g / mol. The molecular weight difference between the two is 2g / mol, which can simulate the produced gas very well. In addition, Freon is non-radioactive, environmentally friendly, non-toxic and easy to recycle. UF6 gas is a nuclear material and is subject to control.

[0030] In at least one embodiment of the present application, the dynamic test device of the process electric regulator for uranium enrichment cascade also includes a gas condensation device. The gas condensation device includes a low temperature thermostat 2, a torpedo vacuum valve 11, a second condenser 3-2 and a flange vacuum valve corresponding to the second condenser 3-2. The second condenser 3-2 is placed inside the low temperature thermostat 2. The channel formed by connecting the second condenser 3-2 and the flange vacuum valve corresponding to the second condenser 3-2 is in parallel with the torpedo vacuum valve 11. The flange vacuum valve corresponding to the second condenser 3-2 is used to control the opening and closing of the pipeline where the second condenser 3-2 is located. The evacuation device, the torpedo vacuum valve 11, the boosting system, the process system and the orifice plate system are connected in series on the main pipeline in sequence. The channel formed by the first condenser 3-1 and the flange vacuum valve corresponding to the first condenser 3-1 is located on the branch pipeline of the connecting pipeline between the torpedo vacuum valve 11 and the boosting system. Thus, by adding a gas condensing device, on the one hand, the gas condensing device can be used to recover Freon, and on the other hand, the pressure in the entire dynamic test device can be reduced by controlling the opening of the corresponding flange vacuum valve of the second condenser 3-2.

[0031] It should be noted that, if sufficient Freon is recovered in the second condenser 3-2, the second condenser 3-2 can be exchanged with the first condenser 3-1, thereby realizing the recycling of Freon and reducing the test cost.

[0032] In at least one embodiment of the present application, the flange vacuum valves corresponding to the second condenser 3-2 include a first flange vacuum valve 9-1, a second flange vacuum valve 9-2, a third flange vacuum valve 9-3, and a fourth flange vacuum valve 9-4. The gas condensing device also includes a first vacuum bellows 15-1 and a second vacuum bellows 15-2. The exhaust port of the second condenser 3-2 is connected in series with the first flange vacuum valve 9-1, the first vacuum bellows 15-1, and the third flange vacuum valve 9-3 in sequence, and then connected to the inlet of the torpedo vacuum valve 11. The air inlet of the second condenser 3-2 is connected in series with the second flange vacuum valve 9-2, the second vacuum bellows 15-2, and the fourth flange vacuum valve 9-4 in sequence, and then connected to the outlet of the torpedo vacuum valve 11.

[0033] It should be noted that the first flange vacuum valve 9-1 and the second flange vacuum valve 9-2 may be flange vacuum valves provided on the second condenser 3-2.

[0034] In at least one embodiment of the present application, the flange vacuum valves corresponding to the first condenser 3-1 include a fifth flange vacuum valve 9-5, a sixth flange vacuum valve 9-6, and a seventh flange vacuum valve 9-7. The gas evaporation device also includes a third vacuum bellows 15-3. The exhaust port of the first condenser 3-1 is connected to the fifth flange vacuum valve 9-5. The air inlet of the first condenser 3-1 is connected in series with the sixth flange vacuum valve 9-6, the third vacuum bellows 15-3, and the seventh flange vacuum valve 9-7 in sequence, and then connected to the connecting pipe between the torpedo vacuum valve 11 and the boosting system.

[0035] It should be noted that the second condenser 3-2 and the first condenser 3-1 may be of the same specification, for example, the capacity of the second condenser 3-2 and the first condenser 3-1 may be 24 L. The fifth flange vacuum valve 9-5 and the sixth flange vacuum valve 9-6 may be vacuum valves provided by the first condenser 3-1.

[0036] In at least one embodiment of the present application, the gas evaporation device further includes a manual fine-tuning valve 14. The manual fine-tuning valve 14 and the seventh flange vacuum valve 9-7 are connected in parallel. The adjustment accuracy of the seventh flange vacuum valve 9-7 is greater than the adjustment accuracy of the manual fine-tuning valve 14. In this way, the seventh flange vacuum valve 9-7 can be used for rough adjustment first, and then the manual fine-tuning valve 14 can be used for fine adjustment, so that the gas flow adjustment is more accurate.

[0037] In at least one embodiment of the present application, the process system is further provided with a fifth channel connected in parallel with the first channel. The fifth channel is provided with a third drum vacuum valve 7-3 and an electric regulating valve 6 connected in series. Thus, by providing the third drum vacuum valve 7-3 and the electric regulating valve 6 connected in series in the fifth channel, the airflow control under different operating conditions can be achieved by controlling the opening of the third drum vacuum valve 7-3, and the performance of the electric regulating valve 6 can be synchronously tested by the dynamic test device of the uranium enrichment cascade process electric regulator.

[0038] In at least one embodiment of the present application, the evacuation device includes an interlocked start-up slide valve vacuum pump 1 and an electromagnetic belt inflation valve 13 .

[0039] In at least one embodiment of the present application, the dynamic test device of the uranium enrichment cascade process electric regulator also includes a control panel cabinet. The control panel cabinet is connected to the monitoring system and the boosting system, and the control panel cabinet is used to control the start and stop of the boosting system and display the data of the monitoring system. In this way, by adding the control panel cabinet, the automatic operation of the entire dynamic test device is realized.

[0040] In at least one embodiment of the present application, the control panel cabinet includes a control cabinet and an industrial computer, and the control cabinet is used to power the industrial computer. The control cabinet includes an evacuation device control module, a temperature control module, a regulator control module, multiple booster frequency converters and multiple booster control buttons. The evacuation device control module is used to control the start and stop of the evacuation device. The temperature control module is used to control the temperature of the heating device 12. The regulator control module is used to power the servo mechanism of the process electric regulator 5 and control the forward and reverse rotation and display angle of the motor of the process electric regulator 5. Multiple booster frequency converters are used to control multiple first booster 4-1 and multiple second booster 4-2 to operate at variable frequencies between 50Hz and 100Hz respectively. Multiple booster control buttons are used to control the start and stop of multiple first booster 4-1 and multiple second booster 4-2. The industrial computer includes secondary meters corresponding to multiple pressure monitoring instruments and digital displays corresponding to the inclination sensor 16. The secondary meters corresponding to the multiple pressure monitoring instruments are used to display, output and record the readings of the multiple pressure monitoring instruments respectively, and store, read and output the historical records monitored by the multiple pressure monitoring instruments. The digital display corresponding to the inclination sensor 16 is used to display the signal of the inclination sensor 16 as a real-time curve, and store, read and output the historical records measured by the inclination sensor 16. In this way, by integrating advanced control and monitoring technologies, the dynamic test device of the process electric regulator for uranium enrichment cascade is suitable for various high-precision gas processing and test requirements.

[0041] It should be noted that the pressure monitoring instrument is a primary meter. The secondary meter is used to display, output and record the readings of the primary meter. The evacuation device control module can be a slide valve vacuum pump control module, which is used to control the start and stop of the slide valve vacuum pump 1, and the start and stop of the related electromagnetic belt inflation valve 13.

[0042] For example, the control cabinet has a manual mode and an automatic mode. When the control cabinet is in manual mode, multiple booster control buttons are used to control the start and stop of multiple first booster 4-1 and multiple second booster 4-2 separately. When the control cabinet is in automatic mode, multiple booster control buttons are used to control the start and stop of multiple first booster 4-1 and multiple second booster 4-2 at the same time. In this way, in manual mode, the start and stop of each first booster 4-1 and second booster 4-2 can be controlled separately, and the frequency of the first booster 4-1 and the second booster 4-2 can be adjusted to meet the needs of different compression ratios. In automatic mode, the program in the control cabinet will control the start and stop of 6 boosters (i.e., 3 first booster 4-1 and 3 second booster 4-2) at the same time according to the pre-set settings.

[0043] In at least one embodiment of the present application, the process electric regulator 5 is further provided with an inclination sensor 16. The inclination sensor 16 is installed at the end of the large lever of the process electric regulator 5. The inclination sensor 16 is used to measure the difference between the time of pressure change and the time of large lever adjustment of the process electric regulator 5 when the dynamic test device of the process electric regulator for uranium enrichment cascade flows through the process electric regulator 5. In this way, by adding the inclination sensor 16, the time constant and pure lag time of the process electric regulator 5 can be monitored by using the dynamic test device of the process electric regulator for uranium enrichment cascade.

[0044] Next, the structure of the dynamic test device for the process electric regulator for uranium enrichment cascade is specifically described in combination with the specific process assembly tube design. It should be noted that in the following description, the installation between two adjacent assembly tubes or between adjacent assembly tubes and equipment can be installed by means of concave-convex flanges, and a sealing gasket can be installed between the concave-convex flanges, and the concave-convex flanges press the sealing gasket to achieve a vacuum sealing effect. The concave-convex flanges can also be evenly provided with bolt holes to be installed, and bolts are passed through the bolt holes and tightened with nuts to achieve sealing. Unless otherwise specified, concave-convex flanges can be used to connect and seal between two adjacent assembly tubes or between adjacent assembly tubes and equipment.

[0045] For evacuation devices, refer to Figure 3 The slide valve vacuum pump 1 is connected to the electromagnetic belt inflation valve 13 through a hose. The electromagnetic belt inflation valve 13 is connected to the thirty-eighth assembly pipe P38. The thirty-eighth assembly pipe P38 is connected to the torpedo vacuum valve 11.

[0046] For the design of process assembly pipes for gas evaporation devices, refer to Figure 3 , the thirty-sixth assembly pipe P36 and the forty-first assembly pipe P41 are connected through the seventh flange vacuum valve 9-7. The forty-first assembly pipe P41 is connected to the sixth flange vacuum valve 9-6 at the inlet of the first condenser 3-1 through the third vacuum bellows 15-3; the manual fine-tuning valve 14 is respectively connected to the thirty-sixth assembly pipe P36 and the forty-first assembly pipe P41 through the forty-second assembly pipe P42. The channel composed of the thirty-sixth assembly pipe P36, the seventh flange vacuum valve 9-7, and the forty-first assembly pipe P41 is in parallel with the channel composed of the thirty-sixth assembly pipe P36, the manual fine-tuning valve 14, and the forty-second assembly pipe P42. Reference Figure 2 An eighth flange vacuum valve 9-8 may also be provided on the pipeline connecting the rear end of the orifice plate system and the front end of the boosting system.

[0047] refer to Figures 2 to 6, the third assembly pipe P03, the fourth assembly pipe P04, the sixth assembly pipe P06, the ninth assembly pipe P09, the eleventh assembly pipe P11, the twelfth assembly pipe P12, the fourteenth assembly pipe P14, the fifteenth assembly pipe P15, the twentieth assembly pipe P20, the twenty-third assembly pipe P23, the twenty-fifth assembly pipe P25, and the thirty-first assembly pipe P31 can be respectively provided with a connection point of the three-way vacuum valve 10. The three-way vacuum valve 10 can be connected to a pressure monitoring instrument as needed, and the pressure monitoring instrument is used to measure the pressure at the corresponding position in the dynamic test device of the process electric regulator for uranium enrichment cascade.

[0048] For the design of process assembly pipes for booster systems, refer to Figure 2 The first assembly pipe P01 is connected to the second assembly pipe P02; the second assembly pipe P02 is connected to the third assembly pipe P03; the third assembly pipe P03 is a four-way assembly pipe, and the remaining three channels of the third assembly pipe P03 are respectively connected to the sixth assembly pipe P06 and the two fourth assembly pipes P04, and these three channels are in parallel.

[0049] Take the channel connecting the third assembly pipe P03 and one of the fourth assembly pipes P04 as an example, Figure 2 and Figure 4 , the fourth assembly pipe P04 is connected to the air inlet of the first booster 4-1 through the fifth assembly pipe P05 and the seventh assembly pipe P07-1 in sequence; the exhaust port of the first booster 4-1 is connected to the air inlet of the second booster 4-2 through the eighth assembly pipe P08, the ninth assembly pipe P09 and the seventh assembly pipe P07-2 in sequence. The exhaust port of the second booster 4-2 is connected to the tenth assembly pipe P10-1, the first rotary drum vacuum valve 7-1 and the twelfth assembly pipe P12 in sequence. The sealing surface of the first rotary drum vacuum valve 7-1 is close to the second booster 4-2.

[0050] The passage connecting the third assembly pipe P03 and another fourth assembly pipe P04 is Figure 4 The difference of the illustrated embodiment is that the exhaust port of the second booster 4-2 is connected in sequence to the tenth assembly pipe three P10-3, the first drum vacuum valve 7-1 and the fourteenth assembly pipe P14.

[0051] The passage connecting the third assembly pipe P03 and the sixth assembly pipe P06 is Figure 4 The difference of the illustrated embodiment is that the sixth assembly pipe P06 is connected to the air inlet of the first booster 4-1, and the exhaust port of the second booster 4-2 is connected to the tenth assembly pipe P10-2, the first drum vacuum valve 7-1 and the eleventh assembly pipe P11 in sequence.

[0052] The eleventh assembly pipe P11, the twelfth assembly pipe P12, and the fourteenth assembly pipe P14 are connected to three channels of the thirteenth assembly pipe P13, and these three channels are integrated into one channel through the thirteenth assembly pipe P13 and connected to the fifteenth assembly pipe P15.

[0053] In some embodiments, the dynamic test device of the process electric regulator for uranium enrichment cascade further includes a plurality of retractable forty-third assembly tubes P43. For example, a forty-third assembly tube P43 is connected between the first assembly tube P01 and the thirty-fifth assembly tube P35. A forty-third assembly tube P43 is connected between the fourteenth assembly tube P14 and the thirteenth assembly tube P13. A forty-third assembly tube P43 is connected between the fifth assembly tube P05 and the seventh assembly tube one P07-1. A forty-third assembly tube P43 is connected between the eighth assembly tube P08 and the ninth assembly tube P09. A forty-third assembly tube P43 is connected between the ninth assembly tube P09 and the seventh assembly tube two P07-2. A forty-third assembly tube P43 is connected between the eighteenth assembly tube P18 and the nineteenth assembly tube P19. A forty-third assembly tube P43 is connected between the twenty-second assembly tube P22 and the twenty-third assembly tube P23. A forty-third assembly tube P43 is connected between the twenty-third assembly tube P23 and the twenty-fourth assembly tube P24. A forty-third assembly tube P43 is connected between the 30th assembly tube P30 and the 31st assembly tube P31. A forty-third assembly tube P43 is connected between the 32nd assembly tube P32 and the 33rd assembly tube P33. A forty-third assembly tube P43 is connected between the 33rd assembly tube P33 and the 34th assembly tube P34. In this way, installation and manufacturing errors are compensated by using a plurality of telescopic forty-third assembly tubes P43.

[0054] With regard to the design of process assembly pipes of the process system, the thirteenth assembly pipe P13 is connected to the fifteenth assembly pipe P15, and the outlet of the fifteenth assembly pipe P15 consists of two channels. For the convenience of description, the connection methods of the fifteenth assembly pipe P15 will be described separately; the fifteenth assembly pipe P15 has three channels, and its two outlet channels and the equipment in the process system connected to its rear end form two parallel loops.

[0055] In one loop, one channel of the fifteenth assembly pipe P15 is connected to the sixteenth assembly pipe P16; the sixteenth assembly pipe P16 is connected to the second drum vacuum valve 7-2, and the sealing surface of the second drum vacuum valve 7-2 is close to the sixteenth assembly pipe P16; the second drum vacuum valve 7-2 is connected to the seventeenth assembly pipe P17, and the seventeenth assembly pipe P17 is characterized by a reducer assembly pipe; the seventeenth assembly pipe P17 with a larger reducer is connected to the end of the process electric regulator 5 where the valve plate is not installed; the end of the process electric regulator 5 where the valve plate is installed is connected to the eighteenth assembly pipe P18; the eighteenth assembly pipe P18 is connected to the nineteenth assembly pipe P19; the nineteenth assembly pipe P19 is connected to the first air inlet of the twenty-fifth assembly pipe P25, and the twenty-fifth assembly pipe P25 is a three-way structure, and the two channels divided at the front end of the fifteenth assembly pipe P15 are merged into one channel through the twenty-fifth assembly pipe P25.

[0056] In another loop, the second channel of the fifteenth assembly tube P15 is connected to the twentieth assembly tube P20; the twentieth assembly tube P20 is connected to the third drum vacuum valve 7-3; the sealing surface of the third drum vacuum valve 7-3 is close to the twentieth assembly tube P20; the third drum vacuum valve 7-3 is connected to the twenty-first assembly tube P21, and the twenty-first assembly tube P21 is connected to the end of the electric regulating valve 6 where the valve plate is not installed; the end of the electric regulating valve 6 where the valve plate is installed is connected to the twenty-second assembly tube P22; the twenty-second assembly tube P22 is connected to the twenty-third assembly tube P23; the twenty-third assembly tube P23 is connected to the twenty-fourth assembly tube P24; the twenty-fourth assembly tube P24 is connected to the second air inlet of the twenty-fifth assembly tube P25, and the two channel structures divided by the fifteenth assembly tube P15 merge into one channel at the twenty-fifth assembly tube P25.

[0057] Regarding the process assembly pipe design of the orifice plate system, the twenty-fifth assembly pipe P25 is connected to the twenty-sixth assembly pipe P26. The twenty-sixth assembly pipe P26 is a four-way structure, and its outlet is divided into three channels, which are respectively connected to the fourth drum vacuum valve 7-4, the fifth drum vacuum valve 7-5 and the sixth drum vacuum valve 7-6; the fourth drum vacuum valve 7-4 is connected to the twenty-eighth assembly pipe P28; the fifth drum vacuum valve 7-5 and the sixth drum vacuum valve 7-6 are respectively connected to two twenty-seventh assembly pipes P27; two of the channels are respectively installed with the first flow orifice plate 8-1 (for example, with a diameter of Φ70mm) connected in series with the fifth drum vacuum valve 7-5 and the second flow orifice plate 8-2 (for example, with a diameter of Φ100mm) connected in series with the sixth drum vacuum valve 7-6; the first flow orifice plate 8-1, the second flow orifice plate 8-2 and the twenty-eighth assembly pipe P28 are all connected to the twenty-ninth assembly pipe P29. The twenty-ninth assembly pipe P29 is a four-way structure, and the three channels are respectively merged into the twenty-ninth assembly pipe P29, and the rear end of the twenty-ninth assembly pipe P29 has only one channel; the twenty-ninth assembly pipe P29 is connected to the thirtieth assembly pipe P30; the thirtieth assembly pipe P30 is connected to the thirty-first assembly pipe P31; the thirty-first assembly pipe P31 is connected to the thirty-second assembly pipe P32; the thirty-second assembly pipe P32 is connected to the thirty-third assembly pipe P33; the thirty-third assembly pipe P33 is connected to the thirty-fourth assembly pipe P34; the thirty-fourth assembly pipe P34 is connected to the thirty-fifth assembly pipe P35; the thirty-fifth assembly pipe P35 is connected to the first assembly pipe P01, thereby forming a closed-loop vacuum test circuit.

[0058] For the design of process assembly pipes for gas condensation units, refer to Figure 2 and Figure 3 The exhaust port of the second condenser 3-2 is connected to one end of the thirty-ninth assembly pipe P39 through the first vacuum bellows 15-1, and the other end of the thirty-ninth assembly pipe P39 is connected to one end of the third flange vacuum valve 9-3; the other end of the third flange vacuum valve 9-3 is connected to the three-way branch of the thirty-seventh assembly pipe P37.

[0059] The air inlet of the second condenser 3-2 is connected to one end of the 40th assembly pipe P40 through the second vacuum bellows 15-2; the other end of the 40th assembly pipe P40 is connected to one end of the fourth flange vacuum valve 9-4; the other end of the fourth flange vacuum valve 9-4 is connected to the thirty-sixth assembly pipe P36.

[0060] The thirty-sixth assembly pipe P36 and the thirty-seventh assembly pipe P37 are connected by a torpedo vacuum valve 11. The torpedo vacuum valve 11 is located between the air inlet and the exhaust port of the second condenser 3-2. The channel formed by the thirty-sixth assembly pipe P36, the thirty-seventh assembly pipe P37 and the torpedo vacuum valve 11 is in parallel with the channel formed by the thirty-sixth assembly pipe P36, the thirty-seventh assembly pipe P37 and the second condenser 3-2. The sealing surface of the torpedo vacuum valve 11 is close to the thirty-seventh assembly pipe P37; the thirty-sixth assembly pipe P36 is connected to the first assembly pipe P01.

[0061] It should be noted that the dynamic test device for the uranium enrichment cascade process electric regulator can also be provided with a plurality of brackets to support each assembly tube, for example, Figure 3 The plurality of brackets may include a plurality of first brackets Z1, a plurality of second brackets Z2, a plurality of third brackets Z3 and a plurality of fourth brackets Z4.

[0062] At least one embodiment of the present application further provides a dynamic test method for an electric regulator for a uranium enrichment cascade process, and the dynamic test method for an electric regulator for a uranium enrichment cascade process can be tested using a dynamic test device for an electric regulator for a uranium enrichment cascade process in any of the above embodiments of the present application. Figure 7 The dynamic test method of the process electric regulator for the uranium enrichment cascade includes the following steps.

[0063] S1: Before the dynamic test, liquid Freon is added into the first condenser 3-1 of the gas evaporation device in the dynamic test device of the process electric regulator for uranium enrichment cascade.

[0064] The process gas is generally uranium hexafluoride, and the molecular weight of uranium hexafluoride is 352g / mol. Uranium hexafluoride is a highly volatile, toxic and harmful gas, which will pollute the dynamic test device of the process electric regulator for uranium enrichment cascade. Based on this, Freon is selected to pass through the dynamic test device of the process electric regulator for uranium enrichment cascade. The molecular weight of Freon is 350 g / mol, which is close to the molecular weight of uranium hexafluoride, and is only 2 molecular weights smaller than the molecular weight of uranium hexafluoride. Therefore, Freon can be used to simulate the working conditions of uranium hexafluoride, and the toxicity of Freon is less than that of uranium hexafluoride.

[0065] S2: When conducting a dynamic test, open the vacuum device in the dynamic test device of the uranium enrichment cascade process electric regulator to perform a pre-vacuum operation until the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator is lower than 1Pa, and then close the vacuum device.

[0066] For example, the slide valve vacuum pump 1 in the evacuation device is turned on, and the electromagnetic belt gas charging valve 13 in the evacuation device is interlocked and started, and when the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator is lower than 1Pa, the slide valve vacuum pump 1 is turned off, and the electromagnetic belt gas charging valve 13 is interlocked and closed. In this way, a low-pressure vacuum environment of less than 0.1 mmHg can be provided for the dynamic test of the uranium enrichment cascade process electric regulator 5.

[0067] The pre-evacuation operation of the evacuation device can ensure that the dynamic test device of the uranium enrichment cascade process electric regulator passes the vacuum leak detection. The leakage rate of the dynamic test device of the uranium enrichment cascade process electric regulator can meet 1.3×10 -8 Pa·m 3 / s.

[0068] It should be noted that the pressure inside the dynamic test device of the uranium enrichment cascade process electric regulator being lower than 1Pa can be monitored by any pressure monitoring instrument. For example, in some embodiments, the first pressure monitoring instrument PI001 is used to monitor whether the pressure inside the dynamic test device of the uranium enrichment cascade process electric regulator is lower than 1Pa.

[0069] S3: Use the gas evaporation device to perform the Freon introduction operation. When the pressure in the dynamic test device of the process electric regulator for the uranium enrichment cascade reaches 800Pa, close the corresponding flange vacuum valve of the first condenser 3-1.

[0070] Specifically, the flange vacuum valve corresponding to the first condenser 3-1 in the gas evaporation device is opened, and the liquid Freon stored in the first condenser 3-1 is heated by the heating device 12, so that the evaporated Freon is passed into the dynamic test device of the uranium enrichment cascade process electric regulator, until the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator reaches 800Pa, and then the flange vacuum valve corresponding to the first condenser 3-1 is closed to stop adding Freon.

[0071] It should be noted that the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator reaching 800Pa can be monitored by any pressure monitoring instrument. For example, in some embodiments, the first pressure monitoring instrument PI001 is used to monitor whether the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator reaches 800Pa.

[0072] In some embodiments, the test parameters of the process electric regulator 5 can be: the maximum diameter of the flow nozzle of the process electric regulator 5 is not less than 180mm, and the rated flow is not less than 350g / s. The working pressure range of the process electric regulator 5 is 5~50mmHg. The full action time of the servo motor of the process electric regulator 5 is not more than 3s. The stable pressure change of the process electric regulator 5 (i.e., the fluctuation amplitude of the second pressure monitoring instrument PI002) is not more than 0.05torr. The pure lag time τ0 is less than 0.5s.

[0073] S4: Start the boost system and gradually adjust it to variable frequency operation between 50Hz and 100Hz.

[0074] S5: Open the valve of one of the flow orifice plates in the third channel and the fourth channel until the gas circulates in the dynamic test device of the process electric regulator for uranium enrichment cascade and reaches a stable state.

[0075] In some embodiments, a dynamic test of the process electric regulator 5 is performed respectively when the cam of the process electric regulator 5 is at the lowest and highest positions, and all raw data are recorded to comprehensively analyze the regulator performance. In this way, the full flow range of the process electric regulator 5 can be included, the highest position corresponds to the highest pressure and the highest flow, and the lowest position corresponds to the lowest pressure and the lowest flow.

[0076] It should be noted that, by manually controlling the cam of the servo mechanism of the process electric regulator 5, the change in the cam angle will determine the adjustment characteristics of the process electric regulator 5. If the process electric regulator 5 is a pressure regulator, the given value of the pressure adjusted by the pressure regulator increases according to the increase of the cam. By manually controlling the change of the cam, when the pressure regulator is switched from manual mode to automatic mode, it will automatically adjust and stabilize within the pressure range of the given value according to the given value after adjusting the cam and remain stable.

[0077] One of the dynamic test methods for the process electric regulator for the uranium enrichment cascade is to test the range of the regulation capability of the process electric regulator 5 by increasing the pressure before the boosting system and producing more Freon gas through evaporation. The pressure before the boosting system is continuously increased, and the pressure after the boosting system is doubled according to the compression ratio of the boosting system. When the pressure before the process electric regulator 5 increases, the stroke of the process electric regulator 5 will increase under the condition of the current pressure given value, and the valve plate opening will be automatically increased to allow more mass flow of test gas to pass through the process electric regulator 5, thereby reducing the pressure before the process electric regulator 5 until the process electric regulator 5 can be stabilized within the pressure given value range and stabilized.

[0078] Conversely, when the Freon gas recovered by the gas condensation device is used to test the range of the regulating capacity of the process electric regulator 5. The inlet valve of the gas condensation device is opened, and after the gas is condensed, the pressure of the dynamic test device of the process electric regulator for the uranium enrichment cascade is continuously reduced. When the pressure before the process electric regulator 5 is reduced, the stroke of the process electric regulator 5 will be reduced under the condition of the current pressure set value, and the valve plate opening will be automatically reduced, so that less mass flow of test gas can pass through the process electric regulator 5, thereby increasing the pressure before the process electric regulator 5, until the process electric regulator 5 can be stabilized within the pressure set value range and stabilized.

[0079] S6: Close the valve of one of the flow orifice plates in the third channel and the fourth channel, open the valve of the other flow orifice plate in the third channel and the fourth channel, and observe and record the pressure changes of the second pressure monitoring instrument PI002 and the third pressure monitoring instrument PI003.

[0080] S7: Open the valves of the two flow orifice plates in the third channel and the fourth channel, and observe and record the pressure changes of the second pressure monitoring instrument PI002 and the third pressure monitoring instrument PI003.

[0081] S8: If the stable pressure change of the process electric regulator 5 is not greater than 0.05 torr, it is determined that the dynamic characteristics of the process electric regulator 5 are qualified.

[0082] It should be noted that steps S5 to S7 can be tested in multiple rounds. The stable pressure change of the process electric regulator 5 is observed and recorded, and it is qualified if it is not greater than 0.05 torr.

[0083] According to the technical solution provided in the embodiment of the present application, by selecting Freon (C7F 14 ) as the test gas. Since the molecular weight of Freon is similar to that of uranium hexafluoride (UF6) used in the uranium enrichment process, this choice makes the dynamic test device of the process electric regulator for uranium enrichment cascade as close to the actual working conditions as possible, effectively simulating the molecular weight of Freon (C7F 14) The operating effect of the gas in the test device is used to test the ability of the process electric regulator 5 to stabilize the system pressure in actual operation, so as to better evaluate the actual performance of the process electric regulator 5 in the uranium enrichment environment, more accurately simulate the actual operating conditions in the uranium enrichment plant, and use Freon as a substitute gas to conduct the test under safe conditions. In the uranium enrichment cascade process, the molecular weight of the gas is crucial to the flow characteristics and aerodynamic behavior. The embodiment of the present application uses Freon to ensure that the test conditions are highly consistent with the actual uranium enrichment process in terms of molecular weight and flow dynamics, providing a more accurate and practical way to evaluate the performance of the process electric regulator 5 in a UF6-like environment. This method not only enhances the reliability of the test, but also improves the validity of the data, because it can more accurately reflect the performance of the process electric regulator 5 in the actual working environment. In addition, the use of Freon as a test medium also has advantages in safety and environmental protection. Compared with the direct use of UF6, Freon is safer and easier to handle, reducing the potential dangers and environmental impacts during the test. In addition, by controlling the Freon added into the dynamic test device of the process electric regulator 5 for uranium enrichment cascade and changing the inlet pressure of the boosting system, the changed pressure is transmitted to the process electric regulator 5, so as to ensure that the rated flow of the process electric regulator 5 is not greater than 350g / s, and the working pressure range is 5mmHg to 50mmHg, so that the process electric regulator 5 (divided into: pressure regulator - the nozzle is installed at the outlet of the pressure regulator, or flow regulator - the nozzle is installed at the inlet of the flow regulator) with a nozzle diameter greater than 100mm can simulate the centrifugal cascade operation condition under a high flow (150g / s~350g / s) environment, providing a theoretical and experimental basis for the manufacture of the process electric regulator 5 for uranium enrichment engineering.

[0084] In at least one embodiment of the present application, the dynamic test method of the process electric regulator for the uranium enrichment cascade further includes the following steps.

[0085] S9: Repeat the pre-evacuation operation and the Freon introduction operation.

[0086] S10: Close the second drum vacuum valve 7 - 2 of the process electric regulator 5 .

[0087] S11: Read the change time of the pressure of the second pressure monitoring instrument PI002 and the tilt sensor 16 before and after the process electric regulator 5 is closed, so as to draw a response curve that changes with time.

[0088] According to the technical solution provided in the embodiment of the present application, a response curve of the output changing with time is plotted through steps S8 to S11, and the time constant and pure lag time of the process electric regulator 5 can be determined based on the response curve of the output changing with time.

[0089] It should be noted that the combination of the various technical features in the embodiments of the present application is not limited to the combination described in the embodiments of the present application or the combination described in the specific embodiments, and all technical features described in the present application can be freely combined or combined in any way unless there is a contradiction between them.

[0090] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application.

Claims

1. A dynamic test device for a process electric regulator for uranium enrichment cascade, characterized in that: Including vacuum device, gas evaporation device, pressurization system, process system, orifice system and monitoring system, Wherein, the evacuation device is used to pre-evacuate the dynamic test device of the process electric regulator for uranium enrichment cascade; the gas evaporation device includes a heating device, a first condenser and a flange vacuum valve corresponding to the first condenser, the heating device is used to evaporate the liquid Freon stored in the first condenser, and the flange vacuum valve corresponding to the first condenser is used to control the opening and closing of the channel where the first condenser is located; the evacuation device, the booster system, the process system and the orifice system are connected in series on the main pipeline in sequence, the gas evaporation device is arranged on a branch pipeline connecting the pipeline between the evacuation device and the booster system, and the rear end of the orifice system is connected to the front end of the booster system; The boosting system comprises three groups of booster devices connected in parallel, each group of booster devices comprising a first booster, a second booster and a first drum vacuum valve connected in series in sequence through a pipeline; The process system comprises a first channel, on which a second rotary drum vacuum valve and a process electric regulator are arranged in series; The orifice plate system has three parallel second channels, a third channel and a fourth channel, the second channel is provided with a fourth drum vacuum valve, the third channel is provided with a fifth drum vacuum valve and a first flow orifice plate connected in series, and the fourth channel is provided with a sixth drum vacuum valve and a second flow orifice plate connected in series; The monitoring system includes a first pressure monitoring instrument, a second pressure monitoring instrument, a third pressure monitoring instrument, a fourth pressure monitoring instrument and a fifth pressure monitoring instrument. The first pressure monitoring instrument is arranged at the inlet of the boosting system, the second pressure monitoring instrument is arranged at the outlet of the boosting system, the third pressure monitoring instrument is arranged at the outlet of the process system, the fourth pressure monitoring instrument is arranged at the rear end of the orifice system, and the fifth pressure monitoring instrument is arranged on a branch pipe connecting the exhaust port of the first condenser and the inlet of the boosting system and is used to connect the pressure signal with the regulator feed signal.

2. The dynamic test device for a uranium enrichment cascade process electric regulator according to claim 1, characterized in that: Also includes a gas condensing device, Wherein, the gas condensing device includes a low-temperature thermostat, a torpedo vacuum valve, a second condenser and a flange vacuum valve corresponding to the second condenser, the second condenser is placed inside the low-temperature thermostat, the channel formed by the second condenser and the flange vacuum valve corresponding to the second condenser is in parallel with the torpedo vacuum valve, the flange vacuum valve corresponding to the second condenser is used to control the opening and closing of the pipeline where the second condenser is located, the evacuation device, the torpedo vacuum valve, the boosting system, the process system and the orifice plate system are connected in series on the main pipeline in sequence, and the channel formed by the first condenser and the flange vacuum valve corresponding to the first condenser is located on the branch pipeline connecting the pipeline between the torpedo vacuum valve and the boosting system.

3. The dynamic test device for a uranium enrichment cascade process electric regulator according to claim 2, characterized in that: The flange vacuum valves corresponding to the second condenser include a first flange vacuum valve, a second flange vacuum valve, a third flange vacuum valve and a fourth flange vacuum valve. The gas condensing device also includes a first vacuum bellows and a second vacuum bellows. The exhaust port of the second condenser is connected in series with the first flange vacuum valve, the first vacuum bellows and the third flange vacuum valve in sequence and then connected to the inlet of the torpedo vacuum valve. The air inlet of the second condenser is connected in series with the second flange vacuum valve, the second vacuum bellows and the fourth flange vacuum valve in sequence and then connected to the outlet of the torpedo vacuum valve.

4. The dynamic test device for a uranium enrichment cascade process electric regulator according to claim 2, characterized in that: The flange vacuum valves corresponding to the first condenser include a fifth flange vacuum valve, a sixth flange vacuum valve and a seventh flange vacuum valve, the gas evaporation device also includes a third vacuum bellows, the exhaust port of the first condenser is connected to the fifth flange vacuum valve, the air inlet of the first condenser is connected in series with the sixth flange vacuum valve, the third vacuum bellows and the seventh flange vacuum valve in sequence, and then connected to the connecting pipe between the torpedo vacuum valve and the boosting system.

5. The dynamic test device for a uranium enrichment cascade process electric regulator according to claim 4, characterized in that: The gas evaporation device further comprises a manual fine-tuning valve, which is connected in parallel with the seventh flange vacuum valve, and the adjustment accuracy of the seventh flange vacuum valve is greater than the adjustment accuracy of the manual fine-tuning valve.

6. The dynamic test device for a uranium enrichment cascade process electric regulator according to claim 1, characterized in that: The process system is also provided with a fifth channel connected in parallel with the first channel, and the fifth channel is provided with a third rotary drum vacuum valve and an electric regulating valve connected in series in sequence.

7. The dynamic test device for a uranium enrichment cascade process electric regulator according to claim 1, characterized in that: The evacuation device comprises an interlocked start-up slide valve vacuum pump and an electromagnetic belt inflation valve.

8. The dynamic test device for the process electric regulator for uranium enrichment cascade according to claim 1 is characterized in that: The process electric regulator is also provided with an inclination sensor, which is installed at the end of the large lever of the process electric regulator. The inclination sensor is used to measure the difference between the pressure change time and the large lever adjustment time of the process electric regulator when the dynamic test device of the process electric regulator for uranium enrichment cascade flows through the process electric regulator.

9. A dynamic test device for a uranium enrichment cascade process electric regulator according to any one of claims 1 to 8, characterized in that: Also includes control panel cabinet, The control panel is connected to the monitoring system and the boosting system, and is used to control the start and stop of the boosting system and display the data of the monitoring system. The control panel cabinet includes a control cabinet and an industrial computer, wherein the control cabinet is used to supply power to the industrial computer. The control cabinet includes one or more of a plurality of booster compressor frequency converters, a plurality of booster compressor control buttons, an evacuation device control module, a temperature control module, and a regulator control module. The evacuation device control module is used to control the start and stop of the evacuation device. The temperature control module is used to control the temperature of the heating device. The regulator control module is used to supply power to the servo mechanism of the process electric regulator and control the forward and reverse rotation and display angle of the motor of the process electric regulator. The plurality of booster compressor frequency converters are used to respectively control the plurality of first booster compressors and the plurality of second booster compressors to operate at variable frequencies between 50 Hz and 100 Hz. The plurality of booster compressor control buttons are used to control the start and stop of the plurality of first booster compressors and the plurality of second booster compressors. The industrial computer includes one or more secondary meters corresponding to multiple pressure monitoring instruments and digital display meters corresponding to the inclination sensor. The secondary meters corresponding to the multiple pressure monitoring instruments are used to display, output and record the readings of the multiple pressure monitoring instruments respectively, and store, read and output the historical records monitored by the multiple pressure monitoring instruments. The digital display meter corresponding to the inclination sensor is used to display the signal of the inclination sensor as a real-time curve, and store, read and output the historical records measured by the inclination sensor.

10. A dynamic test method for a process electric regulator for uranium enrichment cascade, characterized in that: include: Before the dynamic test, liquid Freon is added into the first condenser of the gas evaporation device in the dynamic test device of the process electric regulator for uranium enrichment cascade as claimed in any one of claims 1 to 9; When conducting a dynamic test, the evacuation device in the dynamic test device of the uranium enrichment cascade process electric regulator is turned on to perform a pre-evacuation operation until the pressure in the dynamic test device of the uranium enrichment cascade process electric regulator is lower than 1Pa, and then the evacuation device is closed; The gas evaporation device is used to perform the Freon introduction operation. When the pressure in the dynamic test device of the electric regulator for the uranium enrichment cascade process reaches 800Pa, the corresponding flange vacuum valve of the first condenser is closed; Start the boost system and gradually adjust it to variable frequency operation between 50Hz and 100Hz; Open the valve of one of the flow orifice plates in the third channel and the fourth channel until the gas circulates in the dynamic test device of the process electric regulator for the uranium enrichment cascade and reaches a stable state; Close the valve of one of the flow orifice plates in the third channel and the fourth channel, open the valve of the other flow orifice plate in the third channel and the fourth channel, and observe and record the pressure changes of the second pressure monitoring instrument and the third pressure monitoring instrument; Open the valves of the two flow orifice plates in the third channel and the fourth channel, and observe and record the pressure changes of the second pressure monitoring instrument and the third pressure monitoring instrument; If the stable pressure change of the process electric regulator is no more than 0.05 torr, the dynamic characteristics of the process electric regulator are judged to be qualified.