Pumped storage power station water turbine working condition guide vane closing control method and device

By establishing a simulation model and deep learning algorithm for the load shedding transition process of a pumped storage power station, the guide vane closing control scheme is optimized, which solves the difficulty in parameter setting and computational complexity of the guide vane closing rule optimization in the existing technology, and achieves a more efficient optimization effect.

CN118818979APending Publication Date: 2024-10-22GUODIAN LONGYUAN POWER TECH ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410810658.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2024-10-22

AI Technical Summary

Technical Problem

The existing guide vane closing rule optimization algorithm for pumped storage power stations has problems such as difficulty in parameter setting, uncertainty in effects, and high computational complexity, resulting in poor optimization results and excessive resource consumption.

Method used

By establishing a simulation model of the load shedding transition process of a pumped storage power station, we determine the feasible range of guide vane closing control parameters, construct multiple guide vane closing control schemes, and use deep learning algorithms to train prediction models to optimize the maximum pressure at the volute inlet and the tail end. The minimum pressure at the water pipe inlet and the maximum speed of the unit are used to determine the guide vane closing control plan that meets the optimization goal.

Benefits of technology

It improves the optimization speed and effect, reduces the consumption of computing resources, and is significantly better than traditional methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118818979A_ABST
    Figure CN118818979A_ABST
Patent Text Reader

Abstract

The invention provides a pumped storage power station water turbine working condition guide vane closing control method and device, and relates to the technical field of pumped storage power station control. The load shedding transition process simulation model of the pumped storage power station takes performance indexes of the pumped storage power station as output; determining a feasible region of each guide vane closing control parameter, and constructing a plurality of guide vane closing control schemes including each guide vane closing control parameter as sample schemes; building training data of a preset deep learning algorithm based on the obtained sample scheme and the load shedding transition process simulation model of the pumped storage power station, training the deep learning algorithm by using the obtained training data, and obtaining a closed control parameter of a guide vane of the pumped storage power station as an input, the target prediction model takes a performance index of the pumped storage power station as output; all guide vane closing control schemes meeting the feasible regions of the guide vane closing control parameters are determined, the guide vane closing control schemes serve as input, and performance indexes corresponding to the guide vane closing control schemes are output through the target prediction model. And determining a guide vane closing control scheme corresponding to the performance index meeting the preset optimization target as a target guide vane closing control scheme. According to the invention, the optimization rate and the optimization effect can be effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of pumped-storage power station control technology, and specifically to a pumped-storage power station turbine operating guide vane closing control method, a pumped-storage power station turbine operating guide vane closing control device, a computer-readable storage medium and a terminal device. Background Art

[0002] In the context of the new power system, pumped storage power stations play a key role. They balance the supply and demand of the power grid by storing energy during low-peak power demand and then releasing energy during peak power demand to solve the problem of new energy consumption and improve the stability and reliability of the power system. However, the operational safety of pumped storage power stations depends on the closing rules of their guide vanes. In particular, when an accident occurs in a pumped storage power station and the load is shed, it is necessary to rely on the guide vanes to cut off the water flow to ensure reliable water flow cutoff in the power station. However, unreasonable guide vane closing rules will lead to safety risks for the unit and the water diversion system.

[0003] At present, the optimization of the guide vane closing law of the traditional pumped storage power station is to establish a one-dimensional simulation model to simulate whether the key parameters such as the maximum pressure of the volute inlet, the minimum pressure of the tailwater pipe inlet, and the maximum speed of the unit during the unit load rejection process meet the control value requirements under the guide vane closing law. However, this method can only simulate one set of guide vane closing laws. If multiple closing laws are simulated and calculated, they need to be simulated and calculated separately. When there are many combinations of closing laws, a lot of resources are consumed. Although the existing optimization algorithms such as the gravitational search algorithm and the fish school algorithm can realize a relatively small number of closing law simulation calculations and seek the optimal results, the existing optimization algorithms have the following problems when applied to the optimization of the guide vane closing law. For example, the parameters of the optimization algorithm are difficult to set, and the effect of the optimization algorithm depends to a large extent on the parameter setting, which will lead to uncertainty in the optimization effect. In addition, the algorithm converges slowly, its computational complexity is high, and multiple iterations will consume a lot of computing resources. Summary of the invention

[0004] The purpose of the embodiments of the present application is to provide a pumped-storage power station turbine operating condition guide vane closing control method, a pumped-storage power station turbine operating condition guide vane closing control device, a computer-readable storage medium and a terminal device to solve the above problems.

[0005] In order to achieve the above-mentioned object, the first aspect of the present application provides a method for controlling the closing of guide vanes of a hydraulic turbine in a pumped storage power station under working conditions, comprising:

[0006] Establish a simulation model of the load rejection transient process of a pumped storage power station with the guide vane closing control parameters of the pumped storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit as output;

[0007] Determine the feasible domain of each guide vane closing control parameter, and construct multiple guide vane closing control schemes including each guide vane closing control parameter as sample schemes based on the feasible domain of each guide vane closing control parameter, wherein at least one guide vane closing control parameter has a different value in any two groups of sample schemes;

[0008] Based on the obtained sample scheme and the simulation model of the load rejection transient process of the pumped-storage power station, training data of a preset deep learning algorithm is constructed, and the deep learning algorithm is trained with the obtained training data to obtain a target prediction model with the guide vane closing control parameter of the pumped-storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped-storage power station as output;

[0009] All guide vane closing control schemes that satisfy the feasible domain of each guide vane closing control parameter are determined, and each guide vane closing control scheme is used as input. The target prediction model outputs the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit corresponding to each guide vane closing control scheme, and the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit that meet the preset optimization objectives is determined as the target guide vane closing control scheme.

[0010] Optionally, the guide vane closing control parameters include at least:

[0011] The guide vane motionless time and the closing time of each section of the guide vane;

[0012] If the guide vane of the pumped storage power station is a one-stage guide vane, the closing time of each section of the guide vane includes the closing time of the first section of the guide vane;

[0013] If the guide vane of the pumped storage power station is a two-stage guide vane, the closing time of each stage of the guide vane includes the closing time of the first stage of the guide vane and the closing time of the second stage of the guide vane, and the guide vane closing control parameter also includes the inflection point amplitude of the opening change of the first stage of the guide vane;

[0014] If the guide vane of the pumped storage power station is a three-stage guide vane, the closing time of each guide vane section includes the closing time of the first guide vane section, the closing time of the second guide vane section and the closing time of the third guide vane section, and the guide vane closing control parameter also includes the inflection point amplitude of the first guide vane opening change and the inflection point amplitude of the second guide vane opening change.

[0015] Optionally, a plurality of guide vane closing control schemes including each guide vane closing control parameter are constructed as sample schemes based on the feasible domain of each guide vane closing control parameter, including:

[0016] Determine the number of each guide vane closing control parameter, and determine the target number of sample solutions based on the number of each guide vane closing control parameter;

[0017] Randomly assign a value that satisfies the corresponding feasible domain to each guide vane closing control parameter, and obtain a set of guide vane closing control schemes including each guide vane closing control parameter, with the current guide vane closing control scheme as a sample scheme;

[0018] If the number of current sample solutions does not reach the target number, each guide vane closing control parameter is randomly assigned a value that satisfies the corresponding feasible domain to obtain a new set of sample solutions until the number of obtained sample solutions reaches the target number.

[0019] Optionally, determining a target number of sample solutions based on the number of each guide vane closing control parameter includes:

[0020] The minimum target number for a sample scenario is determined by the following formula:

[0021] Minimum target number=(m+2)(m+1) / 2, where m represents the number of guide vane closing control parameters.

[0022] Optionally, constructing training data of a preset deep learning algorithm based on the obtained sample scheme and the simulation model of the load rejection transition process of the pumped storage power station includes:

[0023] Taking each sample scheme as input, the pumped storage power station load rejection transient process simulation model outputs the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit corresponding to each group of sample schemes;

[0024] The preset deep learning algorithm is trained with each sample scheme and the corresponding maximum volute inlet pressure, minimum tailwater inlet pressure and maximum speed of the unit as training data, and a target prediction model is obtained with the guide vane closing control parameters of the pumped-storage power station as input and the maximum volute inlet pressure, minimum tailwater inlet pressure and maximum speed of the unit as output.

[0025] Optionally, the optimization objectives include:

[0026] The maximum pressure at the volute inlet is the smallest, the maximum speed of the unit is the smallest, and the minimum pressure at the tailwater pipe inlet is the largest.

[0027] Optionally, before determining that the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit that meet the preset optimization target is the target guide vane closing control scheme, the method further includes:

[0028] Determine the constraint conditions, and filter out the solutions that do not meet the constraint conditions from all the obtained maximum volute inlet pressures, minimum draft tube inlet pressures, and maximum unit speeds;

[0029] The constraints include:

[0030] The maximum pressure at the volute inlet is not greater than the maximum pressure threshold at the volute inlet, the minimum pressure at the tailwater pipe inlet is not less than the minimum pressure threshold at the tailwater pipe inlet, and the maximum speed of the unit is not greater than the maximum speed threshold of the unit.

[0031] In a second aspect of the present application, a pumped storage power station turbine operating guide vane closing control device is provided, comprising:

[0032] The simulation model building module is configured to establish a simulation model of the load rejection transient process of the pumped storage power station with the guide vane closing control parameters of the pumped storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped storage power station as output;

[0033] a sample solution generation module, configured to determine a feasible domain of each guide vane closing control parameter, and construct a plurality of guide vane closing control solutions including each guide vane closing control parameter as sample solutions based on the feasible domain of each guide vane closing control parameter, wherein at least one guide vane closing control parameter has a different value in any two groups of sample solutions;

[0034] A prediction model building module is configured to build training data of a preset deep learning algorithm based on the obtained sample scheme and the simulation model of the load rejection transient process of the pumped-storage power station, train the deep learning algorithm with the obtained training data, and obtain a target prediction model with the guide vane closing control parameter of the pumped-storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped-storage power station as output;

[0035] The target guide vane closing control scheme determination module is configured to determine all guide vane closing control schemes that meet the feasible domain of each guide vane closing control parameter, take each guide vane closing control scheme as input, output the maximum volute inlet pressure, the minimum tailwater pipe inlet pressure and the maximum speed of the unit corresponding to each guide vane closing control scheme through the target prediction model, and determine the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum tailwater pipe inlet pressure and the maximum speed of the unit that meet the preset optimization objectives as the target guide vane closing control scheme.

[0036] In a third aspect of the present application, a computer-readable storage medium is provided, which stores a computer program which, when executed by a processor, causes the processor to execute the above-mentioned guide vane closing control method for a turbine in a pumped-storage power station.

[0037] In a fourth aspect of the present application, a terminal device is provided, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the above-mentioned pumped-storage power station turbine operating condition guide vane closing control method when executing the computer program.

[0038] The embodiments provided in this application have the following beneficial effects:

[0039] The present application constructs a simulation model of the load shedding transition process of a pumped-storage power station, constructs a sample scheme of guide vane closing control based on the feasible domain of the determined guide vane closing control parameters, calculates the obtained sample schemes using the simulation model of the load shedding transition process of the pumped-storage power station, and obtains the maximum pressure at the volute inlet, the minimum pressure at the tailwater pipe inlet and the maximum speed of the unit corresponding to each sample scheme, and then constructs training data of a preset deep learning algorithm, and obtains a prediction model after training the deep learning algorithm based on the constructed training data. The obtained prediction model is used to predict the maximum pressure at the volute inlet, the minimum pressure at the tailwater pipe inlet and the maximum speed of the unit corresponding to all control schemes that meet the corresponding feasible domain, and determines that the solution that meets the optimization goal is the optimal solution, thereby effectively improving the optimization rate and optimization effect.

[0040] Other features and advantages of the embodiments or implementations of the present application will be described in detail in the subsequent specific implementation section. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] The accompanying drawings are used to provide a further understanding of the embodiments of the present application and constitute a part of the specification. Together with the following specific implementations, they are used to explain the embodiments of the present application, but do not constitute a limitation on the embodiments of the present application. In the accompanying drawings:

[0042] Figure 1 A method flow chart schematically shows a method for controlling the closing of guide vanes in a pumped storage power station turbine operating condition according to an embodiment of the present application;

[0043] Figure 2 A schematic diagram of the inflection point amplitude of the guide vane opening change in an embodiment of the present application is schematically shown;

[0044] Figure 3 A schematic block diagram of a pumped storage power station turbine operating condition guide vane closing control device according to an embodiment of the present application is schematically shown;

[0045] Figure 4 A schematic diagram of the structure of a terminal device according to an embodiment of the present application is shown schematically.

[0046] Description of Reference Numerals

[0047] 10-terminal device, 100-processor, 101-memory, 102-computer program. DETAILED DESCRIPTION

[0048] The specific implementation of the embodiment of the present application is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the embodiment of the present application, and is not used to limit the embodiment of the present application.

[0049] In order to solve the above problems, Figure 1 As shown, the first aspect of the present application provides a method for controlling the closing of guide vanes of a turbine in a pumped storage power station under operating conditions, comprising:

[0050] S100, establishing a simulation model for the load rejection transient process of a pumped-storage power station with the guide vane closing control parameters of the pumped-storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped-storage power station as output;

[0051] S200, determining a feasible domain of each guide vane closing control parameter, and constructing a plurality of guide vane closing control schemes including each guide vane closing control parameter as sample schemes based on the feasible domain of each guide vane closing control parameter, wherein at least one guide vane closing control parameter has a different value in any two groups of sample schemes;

[0052] S300, constructing training data of a preset deep learning algorithm based on the obtained sample scheme and the simulation model of the load rejection transient process of the pumped-storage power station, training the deep learning algorithm with the obtained training data, and obtaining a target prediction model with the guide vane closing control parameter of the pumped-storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped-storage power station as output;

[0053] S400, determine all guide vane closing control schemes that meet the feasible domain of each guide vane closing control parameter, take each guide vane closing control scheme as input, output the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit corresponding to each guide vane closing control scheme through the target prediction model, and determine the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit that meet the preset optimization target as the target guide vane closing control scheme.

[0054] In this way, the present application constructs a simulation model of the load shedding transition process of a pumped-storage power station, constructs a sample scheme of guide vane closing control based on the feasible domain of the determined guide vane closing control parameters, and calculates the obtained sample schemes using the simulation model of the load shedding transition process of the pumped-storage power station to obtain the maximum pressure at the volute inlet, the minimum pressure at the tailwater pipe inlet and the maximum speed of the unit corresponding to each sample scheme, and then constructs training data for a preset deep learning algorithm, and obtains a prediction model after training the deep learning algorithm based on the constructed training data. The obtained prediction model is used to predict the maximum pressure at the volute inlet, the minimum pressure at the tailwater pipe inlet and the maximum speed of the unit corresponding to all control schemes that meet the corresponding feasible domain, and the solution that meets the optimization objective is determined to be the optimal solution, thereby effectively improving the optimization rate and optimization effect.

[0055] In step S100, when modeling a pumped-storage power station, by collecting the horizontal layout diagram of the power station water level, the vertical layout diagram, the four-quadrant curve of the turbine and other parameters, using the principle of the equivalent circuit method, and using commercial computing software to establish a one-dimensional simplified model of the pumped-storage power station. Specifically, by simplifying the models of the upper reservoir inlet / outlet, the upper reservoir gate well, the upper flat tunnel, the upstream surge chamber, the upper shaft, the middle flat tunnel, the lower shaft, the lower flat tunnel, the water diversion steel bifurcated pipe, the water diversion high-pressure steel branch pipe, the tailwater branch pipe, the tailwater bifurcated pipe, the tailwater surge chamber, the tailwater tunnel, the downstream gate well, the lower reservoir inlet / outlet, etc. into a one-dimensional model, a simulation model of the load rejection transition process of the pumped-storage power station is established, the input of the model is the guide vane closing law, that is, the guide vane closing control parameter, and the output is the maximum pressure of the volute inlet of the pumped-storage power station, the minimum pressure of the tailwater pipe inlet and the maximum speed of the unit, so as to simulate and calculate the load rejection process of the unit. It can be understood that the simulation model of the load shedding transient process of the pumped storage power station can be constructed by using existing simulation software, for example, existing simulation software such as SIMSEN can be used, which is not limited here.

[0056] Among them, the guide vane closing control parameters at least include: the guide vane stationary time t0 and the closing time of each guide vane section; if the guide vane of the pumped storage power station is a one-stage guide vane, the closing time of each guide vane section includes the closing time t1 of the first guide vane section; if the guide vane of the pumped storage power station is a two-stage guide vane, the closing time of each guide vane section includes the closing time t1 of the first guide vane section and the closing time t2 of the second guide vane section, and the guide vane closing control parameters also include the inflection point amplitude y1 of the first guide vane opening change; if the guide vane of the pumped storage power station is a three-stage guide vane, the closing time of each guide vane section includes the closing time t1 of the first guide vane section, the closing time t2 of the second guide vane section and the closing time t3 of the third guide vane section, and the guide vane closing control parameters also include the inflection point amplitude y1 of the first guide vane opening change and the inflection point amplitude y2 of the second guide vane opening change.

[0057] It can be understood that the guide vane immobility time refers to the time from when the control system issues an instruction requiring the guide vane to start changing position, such as closing or opening, when the turbine needs to adjust quickly to cope with load changes, to when the guide vane actually starts to move; Figure 2 As shown, the guide vane opening change inflection point amplitude refers to the amplitude of the relative change of the guide vane opening.

[0058] In this application, taking the two-stage guide vane as an example, after establishing the simulation model of the load shedding transition process of the pumped storage power station, firstly, according to the needs of the power station, a preliminary two-stage guide vane closing law is formulated, and the unit parameters in the process of controlling the unit load shedding are set, and the iteration accuracy is set to 0.01 and the number of iterations is set to 300.

[0059] In step S200, the feasible region of each guide vane closing control parameter is determined in advance. For example, the feasible region of each control parameter is determined to be t 0i∈[0,10], t 1i ∈[0,20], t 2i ∈[0, 20], y 1i ∈[40, 80], where i represents the i-th group of control parameters, the units of t0, t1, t2, and y1 are seconds, the interval number of t is 1, and the interval number of y is 1.

[0060] In step S200, a plurality of guide vane closing control schemes including the guide vane closing control parameters are constructed as sample schemes based on the feasible domain of the guide vane closing control parameters, including:

[0061] S210, determine the number of each guide vane closing control parameter, and determine the target number of sample solutions based on the number of each guide vane closing control parameter. For example, taking a two-stage guide vane as an example, the guide vane closing control parameters include the guide vane immobility time t0, the first-stage guide vane closing time t1, the second-stage guide vane closing time t2, and the first-stage guide vane opening change inflection point amplitude y1, then the number of guide vane closing control parameters is 4, if it is a three-stage guide vane, then the number of guide vane closing control parameters is 6.

[0062] S220, randomly assign a value that satisfies the corresponding feasible domain to each guide vane closing control parameter, and obtain a set of guide vane closing control schemes including each guide vane closing control parameter, with the current guide vane closing control scheme as a sample scheme. It can be understood that a set of guide vane closing control schemes is a set of values ​​of guide vane closing control parameters, that is, a set of guide vane closing control schemes includes [t0, t1, t2, y1], wherein the values ​​of t0, t1, t2, y1 are randomly selected from the corresponding feasible domain determined in advance.

[0063] S230. If the number of current sample solutions does not reach the target number, return to step S220, randomly assign a value that satisfies the corresponding feasible domain to each guide vane closing control parameter, and obtain a new set of sample solutions until the number of sample solutions obtained reaches the target number. If the number of current sample solutions does not reach the predetermined target number, randomly select values ​​from the predetermined corresponding feasible domain again, assign values ​​to t0, t1, t2, and y1, and obtain a new set of sample solutions until the number of sample solutions obtained reaches the predetermined target number. Among them, if the value of each control parameter in the current sample solution is the same as the value of each control parameter in any set of sample solutions that have been generated, then randomly assign values ​​to each control parameter in the current sample solution again.

[0064] In step S210, the target number of sample solutions is determined based on the number of each guide vane closing control parameter, including: determining the target number of sample solutions by the following formula: target number = (m + 2) (m + 1) / 2, where m represents the number of each guide vane closing control parameter. For example, for a two-stage guide vane, the number of control parameters is 4, that is, m = 4, then the target number is 15, that is, at least 15 groups of sample solutions need to be constructed.

[0065] In step S300, training data of a preset deep learning algorithm is constructed based on the obtained sample scheme and the simulation model of the load shedding transient process of the pumped storage power station, including:

[0066] S310, taking each sample scheme as input, the pumped storage power station load rejection transient process simulation model outputs the maximum volute inlet pressure, the minimum tailwater pipe inlet pressure and the maximum speed of the unit corresponding to each sample scheme. For example, the 15 groups of sample schemes obtained are respectively input into the pre-constructed pumped storage power station load rejection transient process simulation model, and the pumped storage power station load rejection transient process simulation model simulates and calculates each sample scheme, and obtains the maximum volute inlet pressure P of the pumped storage power station load rejection process corresponding to each sample scheme. scmax , minimum tailwater pipe inlet pressure P dtmin And the maximum speed of the unit N max .

[0067] S320, using each sample scheme and the corresponding maximum volute inlet pressure, minimum tailwater inlet pressure and maximum unit speed as training data to train the preset deep learning algorithm, and obtain a target prediction model with the guide vane closing control parameter of the pumped storage power station as input and the maximum volute inlet pressure, minimum tailwater inlet pressure and maximum unit speed of the pumped storage power station as output. Each set of training data can be expressed as {[t0, t1, t2, y1], [P scmax , P dtmin , N max ]}, the deep learning algorithm can adopt an existing neural network model, for example, the GMDH neural network model can be adopted, and the 15 groups of training data obtained are divided into a training set, a validation set and a test set by random sampling. The neural network model is trained with the 15 groups of training data, and the neural network model outputs the predicted values ​​of the maximum pressure of the volute inlet, the minimum pressure of the tailwater pipe inlet and the maximum speed of the unit under each group of control parameters. The network parameters of the neural network model, such as the network structure, activation function, optimizer and other parameters, are optimized according to the predicted values ​​of the neural network model and the actual values ​​corresponding to the training data, so as to establish a mapping relationship between the guide vane closing control parameters and the performance indicators, namely the maximum pressure of the volute inlet, the minimum pressure of the tailwater pipe inlet and the maximum speed of the unit, and then obtain the target prediction model.

[0068] In step S400, according to the predetermined feasible region t 0i ∈[0,10], t 1i ∈[0,20], t 2i ∈[0,20],y 1i ∈[40, 80], we get the set P of all guide vane closing control schemes i =[t 0i , t 1i , t 2i ,y 1i ], that is, all the guide vane closing control schemes total 10×20×20×40=160,000 schemes. Among them, t 01 represents the first group of solutions, t 02 Indicates the second group of solutions, and so on.

[0069] In step S400, before determining the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit that meet the preset optimization target as the target guide vane closing control scheme, the method also includes: determining the constraint conditions, and filtering out the solutions that do not meet the constraint conditions from all the obtained maximum volute inlet pressures, the minimum draft tube inlet pressures and the maximum speed of the unit. Traverse all control schemes, input each control scheme into the pre-built target prediction model, and output the performance index values ​​corresponding to each group of control schemes through the target prediction model to quickly obtain the calculation result F i =[P scmax (P i ), P dtmin (P i ), N max (P i )], and filter out the performance index values ​​that do not meet the constraint conditions from all the obtained performance index values.

[0070] Among them, the constraints include: the maximum pressure of the volute inlet is not greater than the maximum pressure threshold of the volute inlet, the minimum pressure of the tailwater pipe inlet is not less than the minimum pressure threshold of the tailwater pipe inlet, and the maximum speed of the unit is not greater than the maximum speed threshold of the unit. Specifically, the constraints can be set as: P scmax ≤860m / water head, P dtmin ≥-8m / water head, N max ≤145%, that is, the maximum speed of the unit is not greater than 145% of the preset standard speed.

[0071] After screening all the obtained solutions, the optimal solution that meets the optimization goal is further selected from all the obtained results. In this application, the optimization goals include: the minimum maximum pressure at the volute inlet, the minimum maximum speed of the unit, and the maximum minimum pressure at the tailwater pipe inlet. It can be understood that the multi-objective optimization of the obtained calculation results can be achieved using existing technologies, which is not limited here.

[0072] In a specific example, the present application uses the maximum volute inlet pressure P scmax Smaller, minimum tailwater pipe inlet pressure P dtmin Larger, maximum unit speed N max The smaller the target principle, the multi-objective optimization evaluation function is established, and the multi-objective optimization evaluation function is solved based on the improved genetic algorithm NSGA-Ⅲ in the multi-objective optimization algorithm, so as to ensure the global optimization in the design space, reduce the computational complexity, and improve the optimization accuracy. Then, according to the value of the multi-objective function, the Pareto solution set is constructed, the optimal Pareto solution is obtained from the Pareto solution set, and the optimal solution is obtained by manually screening from the Pareto optimal solution.

[0073] Among them, the multi-objective optimization evaluation function is:

[0074]

[0075] Among them, α0 is a constant term, α i is the unknown coefficient of the first-order term, α ij is the unknown coefficient of the quadratic term, m means there are m variables, y means the predicted value, x i and x j Represents a variable.

[0076] In this way, the results obtained by optimization through this application are significantly better than the design results of traditional methods in terms of comprehensive effects. At the same time, among the 160,000 optimization schemes, this application only uses simulation software to calculate some schemes. For example, this application only calculates 15 sample schemes. Compared with the traditional optimization method that needs to calculate each result through simulation software, this application not only greatly improves the optimization rate, but also has a more outstanding optimization effect.

[0077] like Figure 3 As shown, in a second aspect of the present application, a pumped storage power station turbine operating guide vane closing control device is provided, comprising:

[0078] The simulation model building module is configured to establish a simulation model of the load rejection transient process of the pumped storage power station with the guide vane closing control parameters of the pumped storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped storage power station as output;

[0079] a sample solution generation module, configured to determine a feasible domain of each guide vane closing control parameter, and construct a plurality of guide vane closing control solutions including each guide vane closing control parameter as sample solutions based on the feasible domain of each guide vane closing control parameter, wherein at least one guide vane closing control parameter has a different value in any two groups of sample solutions;

[0080] A prediction model building module is configured to build training data of a preset deep learning algorithm based on the obtained sample scheme and the simulation model of the load rejection transient process of the pumped storage power station, train the deep learning algorithm with the obtained training data, and obtain a target prediction model with the guide vane closing control parameter of the pumped storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped storage power station as output;

[0081] The target guide vane closing control scheme determination module is configured to determine all guide vane closing control schemes that meet the feasible domain of each guide vane closing control parameter, take each guide vane closing control scheme as input, output the maximum volute inlet pressure, the minimum tailwater pipe inlet pressure and the maximum speed of the unit corresponding to each guide vane closing control scheme through the target prediction model, and determine the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum tailwater pipe inlet pressure and the maximum speed of the unit that meet the preset optimization objectives as the target guide vane closing control scheme.

[0082] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.

[0083] In a third aspect of the present application, a computer-readable storage medium is provided, which stores a computer program which, when executed by a processor, causes the processor to execute the above-mentioned pumped-storage power station turbine operating condition guide vane closing control method.

[0084] In a fourth aspect of the present application, a terminal device is provided, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the above-mentioned pumped-storage power station turbine operating condition guide vane closing control method when executing the computer program.

[0085] like Figure 4 FIG. 1 is a schematic diagram of a terminal device provided in an embodiment of the present application. Figure 4As shown, the terminal device 10 of this embodiment includes: a processor 100, a memory 101, and a computer program 102 stored in the memory 101 and executable on the processor 100. When the processor 100 executes the computer program 102, the steps in the above method embodiment are implemented. Alternatively, when the processor 100 executes the computer program 102, the functions of each module / unit in the above device embodiments are implemented.

[0086] Exemplarily, the computer program 102 may be divided into one or more modules / units, one or more modules / units are stored in the memory 101, and are executed by the processor 100 to complete the present application. One or more modules / units may be a series of computer program instruction segments capable of completing specific functions, and the instruction segments are used to describe the execution process of the computer program 102 in the terminal device 10.

[0087] The terminal device 10 may be a computing device such as a desktop computer, a notebook, a PDA, or a cloud server. The terminal device 10 may include, but is not limited to, a processor 100 and a memory 101. Those skilled in the art will appreciate that Figure 4 It is only an example of the terminal device 10 and does not constitute a limitation of the terminal device 10. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, the terminal device may also include input and output devices, network access devices, buses, etc.

[0088] The processor 100 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may be any conventional processor, etc.

[0089] The memory 101 may be an internal storage unit of the terminal device 10, such as a hard disk or memory of the terminal device 10. The memory 101 may also be an external storage device of the terminal device 10, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the terminal device 10. Further, the memory 101 may also include both an internal storage unit of the terminal device 10 and an external storage device. The memory 101 is used to store computer programs and other programs and data required by the terminal device 10. The memory 101 may also be used to temporarily store data that has been output or is to be output.

[0090] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0091] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0092] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.

Claims

1. A method for controlling the closing of guide vanes of a hydraulic turbine in a pumped storage power station, characterized in that: include: Establish a simulation model of the load rejection transient process of a pumped storage power station with the guide vane closing control parameters of the pumped storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit as output; Determine the feasible domain of each guide vane closing control parameter, and construct multiple guide vane closing control schemes including each guide vane closing control parameter as sample schemes based on the feasible domain of each guide vane closing control parameter, wherein at least one guide vane closing control parameter has a different value in any two groups of sample schemes; Based on the obtained sample scheme and the simulation model of the load rejection transient process of the pumped-storage power station, training data of a preset deep learning algorithm is constructed, and the deep learning algorithm is trained with the obtained training data to obtain a target prediction model with the guide vane closing control parameter of the pumped-storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped-storage power station as output; All guide vane closing control schemes that satisfy the feasible domain of each guide vane closing control parameter are determined, and each guide vane closing control scheme is used as input. The target prediction model outputs the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit corresponding to each guide vane closing control scheme, and the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit that meet the preset optimization objectives is determined as the target guide vane closing control scheme.

2. The method for controlling the closing of guide vanes of a pumped storage power station turbine in working condition according to claim 1, characterized in that: The guide vane closing control parameters include at least: The guide vane motionless time and the closing time of each section of the guide vane; If the guide vane of the pumped storage power station is a one-stage guide vane, the closing time of each section of the guide vane includes the closing time of the first section of the guide vane; If the guide vane of the pumped storage power station is a two-stage guide vane, the closing time of each stage of the guide vane includes the closing time of the first stage of the guide vane and the closing time of the second stage of the guide vane, and the guide vane closing control parameter also includes the inflection point amplitude of the opening change of the first stage of the guide vane; If the guide vane of the pumped storage power station is a three-stage guide vane, the closing time of each guide vane section includes the closing time of the first guide vane section, the closing time of the second guide vane section and the closing time of the third guide vane section, and the guide vane closing control parameter also includes the inflection point amplitude of the first guide vane opening change and the inflection point amplitude of the second guide vane opening change.

3. The method for controlling the closing of guide vanes of a pumped storage power station turbine in working condition according to claim 1, characterized in that: Based on the feasible domain of each guide vane closing control parameter, multiple guide vane closing control schemes including each guide vane closing control parameter are constructed as sample schemes, including: Determine the number of each guide vane closing control parameter, and determine the target number of sample solutions based on the number of each guide vane closing control parameter; Randomly assign a value that satisfies the corresponding feasible domain to each guide vane closing control parameter, and obtain a set of guide vane closing control schemes including each guide vane closing control parameter, with the current guide vane closing control scheme as a sample scheme; If the number of current sample solutions does not reach the target number, each guide vane closing control parameter is randomly assigned a value that satisfies the corresponding feasible domain to obtain a new set of sample solutions until the number of obtained sample solutions reaches the target number.

4. The method for controlling the closing of guide vanes of a pumped storage power station turbine in working condition according to claim 3, characterized in that: The target number of sample solutions is determined based on the number of each guide vane closing control parameter, including: The minimum target number for a sample scenario is determined by the following formula: Minimum target number=(m+2)(m+1) / 2, where m represents the number of guide vane closing control parameters.

5. The method for controlling guide vane closing of a turbine in a pumped storage power station according to claim 1, characterized in that: The training data of the preset deep learning algorithm is constructed based on the obtained sample scheme and the simulation model of the load rejection transition process of the pumped storage power station, including: Taking each sample scheme as input, the pumped storage power station load rejection transient process simulation model outputs the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit corresponding to each group of sample schemes; The preset deep learning algorithm is trained with each sample scheme and the corresponding maximum volute inlet pressure, minimum tailwater inlet pressure and maximum speed of the unit as training data, and a target prediction model is obtained with the guide vane closing control parameters of the pumped-storage power station as input and the maximum volute inlet pressure, minimum tailwater inlet pressure and maximum speed of the unit as output.

6. The method for controlling guide vane closing of a pumped storage power station turbine in operating condition according to claim 1, characterized in that: The optimization objectives include: The maximum pressure at the volute inlet is the smallest, the maximum speed of the unit is the smallest, and the minimum pressure at the tailwater pipe inlet is the largest.

7. The method for controlling the closing of guide vanes of a pumped storage power station turbine in operating condition according to claim 6, characterized in that: Before determining the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum draft tube inlet pressure and the maximum speed of the unit that meet the preset optimization objectives as the target guide vane closing control scheme, the method further includes: Determine the constraint conditions, and filter out the solutions that do not meet the constraint conditions from all the obtained maximum volute inlet pressures, minimum draft tube inlet pressures, and maximum unit speeds; The constraints include: The maximum pressure at the volute inlet is not greater than the maximum pressure threshold at the volute inlet, the minimum pressure at the tailwater pipe inlet is not less than the minimum pressure threshold at the tailwater pipe inlet, and the maximum speed of the unit is not greater than the maximum speed threshold of the unit.

8. A pumped storage power station turbine operating guide vane closing control device, characterized in that: include: The simulation model building module is configured to establish a simulation model of the load rejection transient process of the pumped storage power station with the guide vane closing control parameters of the pumped storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped storage power station as output; a sample solution generation module, configured to determine a feasible domain of each guide vane closing control parameter, and construct a plurality of guide vane closing control solutions including each guide vane closing control parameter as sample solutions based on the feasible domain of each guide vane closing control parameter, wherein at least one guide vane closing control parameter has a different value in any two groups of sample solutions; A prediction model building module is configured to build training data of a preset deep learning algorithm based on the obtained sample scheme and the simulation model of the load rejection transient process of the pumped-storage power station, train the deep learning algorithm with the obtained training data, and obtain a target prediction model with the guide vane closing control parameter of the pumped-storage power station as input and the maximum volute inlet pressure, the minimum tailwater inlet pressure and the maximum speed of the unit of the pumped-storage power station as output; The target guide vane closing control scheme determination module is configured to determine all guide vane closing control schemes that meet the feasible domain of each guide vane closing control parameter, take each guide vane closing control scheme as input, output the maximum volute inlet pressure, the minimum tailwater pipe inlet pressure and the maximum speed of the unit corresponding to each guide vane closing control scheme through the target prediction model, and determine the guide vane closing control scheme corresponding to the maximum volute inlet pressure, the minimum tailwater pipe inlet pressure and the maximum speed of the unit that meet the preset optimization objectives as the target guide vane closing control scheme.

9. A computer-readable storage medium storing a computer program which, when executed by a processor, causes the processor to execute the method for controlling guide vane closing in operating condition of a turbine in a pumped-storage power station as claimed in any one of claims 1 to 7.

10. A terminal device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the guide vane closing control method for the operating condition of a pumped storage power station turbine is implemented as described in any one of claims 1 to 7.