Multi-workshop production equipment optimization method based on cloud computing and related equipment

Through the multi-workshop production equipment optimization method based on cloud computing, the production plan is dynamically adjusted, which solves the problem of insufficient components caused by reduced workshop production efficiency or shutdown, and realizes the improvement of multi-workshop collaborative and efficient production and assembly efficiency.

CN118822162AInactive Publication Date: 2024-10-22JIANGSU SEATON TECH CO LTD

Patent Information

Application Number
CN202410830108.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2024-10-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the multi-workshop production model, if the production efficiency of a certain workshop decreases or is shut down for maintenance, it will lead to an insufficient number of components, thereby reducing the assembly efficiency of the product. It is difficult to effectively coordinate equipment maintenance and production efficiency with existing technology.

Method used

A multi-workshop production equipment optimization method based on cloud computing is used to determine the optimal production plan by obtaining the component production data, assembly ratio and production efficiency of each equipment of the target product, and dynamically adjust the production plan from equipment status monitoring to maintenance to ensure Component allocation and coordination of production tasks.

Benefits of technology

It realizes multi-workshop collaborative and efficient production, monitors equipment status in real time, adjusts production plans, improves product assembly efficiency, and makes up for production losses during equipment maintenance to the maximum extent.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118822162A_ABST
    Figure CN118822162A_ABST
Patent Text Reader

Abstract

The invention provides a multi-workshop production equipment optimization method and device based on cloud computing, a medium and equipment, and relates to the technical field of production scheduling. According to the technical scheme provided by the invention, the assembly production data of the target product is acquired, and the optimal production plan is determined by considering the assembly proportion and the efficiency of each device, so that multi-workshop cooperative efficient production is realized. When the production equipment needs to be shut down due to maintenance, the scheme can monitor the equipment state in real time, determine the corresponding assembly information, calculate the extra production capacity and adjust the production plan accordingly. Through means of equipment state monitoring and production plan dynamic optimization, coordination between equipment maintenance and production efficiency is realized, and when the production equipment efficiency is reduced or shutdown maintenance is carried out, the product assembly efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of production scheduling, and in particular to a multi-workshop production equipment optimization and related equipment based on cloud computing. Background Art

[0002] In the modern product manufacturing process, many products need to be assembled from multiple parts. This assembly production model is widely used in many industries such as electronic products, mechanical equipment, and automobiles. And because the complexity of products continues to increase, the assembly process usually includes many steps and the assembly requirements are more stringent.

[0003] In order to improve production efficiency in related technologies, the assembly line often adopts a zoning production method. That is, the various parts required for the product are dispersed in the production equipment of different workshops for parallel production, and the produced parts are then concentrated in the assembly area for assembly. Although this production model can fully utilize the production capacity of each area, since the production equipment of each workshop is relatively independent and unrelated to each other, once the production efficiency of a workshop decreases or it is shut down for maintenance, the number of components produced by the production equipment in the workshop will decrease, resulting in insufficient number of components in the downstream assembly area, which in turn leads to reduced assembly efficiency of the product. Summary of the invention

[0004] The present application provides a multi-workshop production equipment optimization method and related equipment based on cloud computing, which can improve the assembly efficiency of products when target equipment to be maintained appears.

[0005] In a first aspect, the present application provides a multi-workshop production equipment optimization method based on cloud computing, which is applied to a cloud computing server, and the method includes: Obtain the production quantity of multiple components to be produced of the target product and the assembly ratio between the components; Determine a production plan for allocating each component to a corresponding production equipment according to the assembly ratio of each component, the production quantity of each component, and the production efficiency of each component produced by production equipment in multiple available workshops, and send the production plan to each production equipment so that each production equipment produces the corresponding component according to the production plan; When at least one target device to be maintained appears in each of the production devices, target component information of each of the target devices whose production is delayed due to maintenance is determined; The production plan is adjusted according to the target component information, and the adjusted production plan is sent to each production equipment.

[0006] By adopting the above technical solutions, the component production data of the target product is obtained, and the optimal production plan is determined by considering the assembly ratio and the efficiency of each equipment, so as to achieve efficient production in multiple workshops. When the production equipment needs maintenance, the solution can monitor the equipment status in real time, determine the corresponding component information, calculate the additional production volume, and adjust the production plan accordingly. Through the means of equipment status monitoring and dynamic optimization of production plans, the coordination between equipment maintenance and production efficiency is achieved, and the assembly efficiency of the product is improved when the efficiency of production equipment decreases or it is shut down for maintenance.

[0007] Optionally, when at least one target device to be maintained appears in each of the production devices, determining target component information of each of the target devices whose production is delayed due to maintenance includes: When at least one target device to be maintained appears in each of the production devices, a target production efficiency and maintenance duration of each of the target devices are obtained; According to the target production efficiency and the maintenance duration, the production reduction quantity of the target component corresponding to each target device is calculated; according to the workshop type of the available workshop where each target device is located, the additional production quantity of the target component that can be produced by the available workshop where the target device is located within the maintenance duration is determined; Based on the extra production volume of the available workshops where each of the target devices is located and the reduced production quantity of the target components corresponding to each of the target devices, the target component information of each of the target devices whose production is delayed due to maintenance is determined, and the target component information includes the load transfer equipment and load transfer quantity of each of the target components.

[0008] By adopting the above technical solution, when it is monitored that the target equipment needs maintenance, the equipment production efficiency and maintenance time are obtained, the amount of production reduction is calculated, and the additional production volume is determined according to the workshop type. Finally, the target equipment and quantity for load transfer are determined, which enables accurate judgment of the impact of maintenance on output, and reasonable arrangement of production task transfer to maximize the compensation for the amount of production reduction, thereby ensuring production efficiency during maintenance.

[0009] Optionally, determining, according to the workshop type of the available workshop where each of the target devices is located, an additional production volume of the target component that can be produced by the available workshop where the target device is located within the maintenance duration includes: Determine whether all available workshops where the target equipment is located are production equipment for producing the target component; If all the available workshops where the target equipment is located are production equipment that produces the target component, the available workshops where the target equipment is located are determined to be workshops of the same type, and the quantity of the target component that can be produced by the workshops of the same type within the maintenance duration is the first additional production quantity; If not all available workshops where the target equipment is located are production equipment for producing the target component, the available workshop where the target equipment is located is determined to be a mixed workshop, and the mixed workshop can produce the target component within the maintenance period in a quantity that is the second additional production quantity, and the first additional production quantity is greater than the second additional production quantity.

[0010] By adopting the above technical solution, the production capacity of workshops is distinguished by judging their types, and the first additional production volume of workshops of the same type and the second additional production volume of mixed workshops are determined, so that the additional production volume that can be provided by different workshops can be reasonably calculated according to their actual conditions. This provides accurate workshop production increase information for subsequent production scheduling, and can scientifically and reasonably allocate production tasks.

[0011] Optionally, determining the target component information of each target device whose output is delayed due to maintenance according to the additional production volume of the available workshop where the target device is located and the reduced production quantity of the target component corresponding to each target device includes: Substitute the additional production volume of the available workshop where each target device is located and the reduced production quantity of the target component corresponding to each target device into the preset allocation formula to obtain the target component information of the delayed production of each target device due to maintenance; wherein the preset allocation formula is: In the formula, A j represents the load transfer quantity of other equipment in the Jth workshop of the same type, J represents the serial number of other equipment in the same workshop, M represents the quantity of other equipment in the same workshop, q j represents the additional production capacity of other equipment in the Jth workshop of the same type, e j represents the efficiency coefficient of other equipment in the Jth workshop of the same type, α represents the additional production capacity of the available workshop where the target equipment is located, K represents the serial number of the production equipment corresponding to the target component in the mixed workshop, L represents the number of production equipment corresponding to the target component in the mixed workshop, s k represents the additional production capacity of the production equipment corresponding to the target component in the Kth hybrid workshop, f k represents the efficiency coefficient of the production equipment corresponding to the target component in the Kth hybrid workshop, β represents the reduced production quantity of the target component corresponding to each target equipment, I represents the sequence number of the target equipment corresponding to the target component, N represents the number of target equipment corresponding to the target component, r i represents the reduction rate of the target equipment corresponding to the first target component, p i Represents the original productivity of the target equipment corresponding to the Ith target component.

[0012] By adopting the above technical solution, the additional production volume of the available workshops and the reduced production quantity of the target equipment are substituted into the preset production task allocation formula for calculation to determine the load transfer quantity of each target equipment. The formula comprehensively considers parameters such as the equipment conditions, efficiency coefficients, additional production capacity of the same type of workshops and mixed workshops, as well as factors such as the reduced production quantity and original productivity of each target equipment. It provides a detailed numerical basis for subsequent production planning and scheduling, and can achieve accurate allocation of production tasks.

[0013] Optionally, the method further includes: determining whether the first additional production amount is greater than the production reduction amount; If the first additional production quantity is greater than the production reduction quantity, determining other equipment in the same type of workshop as load transfer equipment for the target component; If the first additional production volume is not greater than the production reduction quantity, other equipment in the same type of workshop and the production equipment corresponding to the target component in the mixed workshop are jointly determined as the load transfer equipment of the target component.

[0014] By adopting the above technical solution, by judging the relationship between the first additional production volume and the production reduction quantity of the same type of workshop, it can be dynamically determined whether to use only the equipment of the same type of workshop as the load transfer equipment, or to use the equipment of the mixed workshop as the load transfer equipment at the same time. This realizes that according to the actual production increase capacity of the same type of workshop, the equipment of the same type of workshop is preferentially used for load transfer. When the equipment of the same type of workshop is insufficient, the equipment of the mixed workshop is introduced, so that the production capacity of each workshop can be reasonably used.

[0015] Optionally, obtaining the maintenance duration of each target device includes: Obtain maintenance items for the target device to produce the target component, and standard project durations corresponding to each maintenance item; determine the maintenance duration of each target device according to each maintenance item and the corresponding standard project duration.

[0016] By adopting the above technical solution, the overall maintenance time of the equipment is accurately calculated by obtaining the specific maintenance items of the equipment and the standard duration of each item, rather than relying solely on the estimated or empirical value of the maintenance time. This makes it more accurate to calculate the reduction in production based on the maintenance time, thereby making production plans targeted, improving the rationality of the plan, and reducing production risks caused by inaccurate maintenance time estimates.

[0017] Optionally, after obtaining the production quantity of multiple components to be produced of the target product and the assembly ratio between the components, the method further includes: Obtain the historical production efficiency of each production equipment in producing each of the components; The average value of the historical production efficiency is determined as the production efficiency of the production equipment of each available workshop in producing each of the components.

[0018] By adopting the above technical solution, by obtaining the historical production efficiency of the equipment and taking the average value as the current efficiency, the overall production level of the equipment can be more comprehensively reflected, avoiding the occasional influence of the efficiency in certain time periods. Compared with directly using the instantaneous efficiency of a certain time period, this method based on the historical average efficiency can make the subsequent production plan generated based on the production efficiency more accurate and reasonable, accurately reflecting the actual production level of each equipment, thereby formulating a more scientific production allocation plan. This will improve the feasibility of the production plan and reduce the risk of production losses caused by inaccurate equipment efficiency estimates.

[0019] In a second aspect, the present application provides a multi-workshop production equipment optimization device based on cloud computing, the device comprising: A data acquisition module is used to obtain the production quantity of multiple components to be produced of the target product and the assembly ratio between the components; A production plan generating module is used to determine the production plan for allocating each component to the corresponding production equipment according to the assembly ratio of each component, the production quantity of each component, and the production efficiency of each component produced by the production equipment of multiple available workshops, and send the production plan to each production equipment so that each production equipment produces the corresponding component according to the production plan; A maintenance information determination module, used for determining target component information of each target device whose production is delayed due to maintenance when at least one target device to be maintained appears in each of the production devices; The production plan adjustment module is used to adjust the production plan according to the information of each target component and send the adjusted production plan to each production equipment.

[0020] In a third aspect, the present application provides a computer storage medium, wherein the computer storage medium stores a plurality of instructions, wherein the instructions are suitable for being loaded by a processor and executing any one of the above methods.

[0021] In a fourth aspect, the present application provides an electronic device, comprising a processor, a memory and a transceiver, wherein the memory is used to store instructions, the transceiver is used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device performs any one of the methods described above.

[0022] In summary, the beneficial effects brought about by the technical solution of this application include: By adopting the above technical solutions, the component production data of the target product is obtained, and the optimal production plan is determined by considering the assembly ratio and the efficiency of each equipment, so as to achieve efficient production in multiple workshops. When the production equipment needs maintenance, the solution can monitor the equipment status in real time, determine the corresponding component information, calculate the additional production volume, and adjust the production plan accordingly. Through the means of equipment status monitoring and dynamic optimization of production plans, the coordination between equipment maintenance and production efficiency is achieved, and the assembly efficiency of the product is improved when the efficiency of production equipment decreases or it is shut down for maintenance. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a flow chart of a multi-workshop production equipment optimization method based on cloud computing according to an embodiment of the present application; Figure 2 This is a schematic diagram of the structure of a multi-workshop production equipment optimization device based on cloud computing in an embodiment of the present application; Figure 3 It is a structural schematic diagram of an electronic device provided in an embodiment of the present application.

[0024] Description of reference numerals: 300, electronic device; 301, processor; 302, communication bus; 303, user interface; 304, network interface; 305, memory. DETAILED DESCRIPTION

[0025] In order to enable those skilled in the art to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below in conjunction with the drawings in the embodiments of this specification. Obviously, the described embodiments are only part of the embodiments of this application, not all of the embodiments.

[0026] In the description of the embodiments of the present application, words such as "illustrative", "for example" or "for example" are used to indicate examples, illustrations or descriptions. Any embodiment or design described as "illustrative", "for example" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "illustrative", "for example" or "for example" is intended to present related concepts in a specific way.

[0027] In the description of the embodiments of the present application, the meaning of the term "multiple" refers to two or more. For example, multiple systems refer to two or more systems, and multiple screen terminals refer to two or more screen terminals. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. The terms "include", "comprise", "have" and their variations all mean "including but not limited to", unless otherwise specifically emphasized.

[0028] It should be understood that the execution subject of the embodiment of the present application is a cloud computing server, which has the advantages of powerful computing processing capabilities, massive storage space and high-speed network communication capabilities. It can quickly collect production data from multiple workshops, and calculate and generate optimized production plans in real time, and quickly push the plans to each workshop to achieve real-time collaboration and optimized scheduling between multiple workshops. Applying cloud computing servers to the embodiments of the present application can eliminate the limitations of information islands between multiple workshops, realize centralized processing of production data, and enable each workshop to obtain information such as the equipment status and production capacity level of other workshops. The cloud server can efficiently generate a globally optimized production plan based on this, and quickly send it to each workshop, so as to give full play to the production capacity of each workshop and improve the overall efficiency of collaborative production of multiple workshops.

[0029] See also Figure 1 , is a flow chart of a multi-workshop production equipment optimization method based on cloud computing provided in an embodiment of the present application. The method can be implemented by a computer program, can be implemented by a single-chip microcomputer, or can be run on a multi-workshop production equipment optimization device based on cloud computing based on the von Neumann system. The computer program can be integrated into an application or run as an independent tool application. The specific steps of the multi-workshop production equipment optimization method based on cloud computing are described in detail below.

[0030] S101: Obtain the production quantity of multiple components to be produced of a target product and the assembly ratio between the components.

[0031] The target product refers to the assembled product that the cloud computing server needs to produce in collaboration with multiple workshops according to the production plan requirements. The target product consists of multiple components, which are produced in different workshops and assembled into the final product according to the planned sequence and proportion. The status of the production equipment in each workshop directly affects the output of the target product.

[0032] The production quantity refers to the quantity of each component of the target product that needs to be produced in the production plan. The production quantity is for each component of the target product. The production quantity specifically refers to the required quantity of each component in the production list of the target product. The production quantity will be used as a key input to generate the production plan. The production plan must calculate the specific production volume of each component allocated to each workshop so that the total output of each component meets the production quantity requirements to meet the needs of final assembly.

[0033] The assembly ratio refers to the quantitative ratio of the components of the target product during final assembly. Based on the product design drawings and assembly lists, the assembly order and quantitative relationship of different components in the same product are clarified. The assembly ratio ensures that each component is assembled in the proportion required by the design to avoid the inability to assemble the final product due to insufficient quantity of a certain component.

[0034] Specifically, the cloud computing server can quickly call the database of the product data management system and, through big data technology, intelligently match the relevant information of the target product in the massive product data, efficiently extract its bill of materials and design structure relationship diagram, and use the distributed storage advantages of the cloud server to store the production quantity and assembly ratio data of these components in the cloud.

[0035] S102: Determine the production plan for allocating each component to the corresponding production equipment based on the assembly ratio of each component, the production quantity of each component, and the production efficiency of each component produced by the production equipment in multiple available workshops, and send the production plan to each production equipment so that each production equipment produces the corresponding component according to the production plan.

[0036] Among them, the available workshops refer to the workshops that are involved in the production of the target product and have relevant production equipment and capabilities. The cloud computing server selects workshops that can produce the components required for the target product from multiple workshops based on the production plan and actual conditions. These workshops need to have equipment and sufficient production capacity to produce the components.

[0037] Production efficiency refers to the speed at which the production equipment in an available workshop can produce a certain component. Production efficiency reflects the efficiency and capacity of the production equipment in the available workshop to produce each component. It is closely related to the technical level and performance parameters of the equipment. Production efficiency directly affects the number of components that can be produced by the equipment during the planning period. Therefore, when generating a production plan, it is necessary to fully consider the production efficiency characteristics of the equipment in each workshop in order to reasonably calculate the optimal production allocation of each component in each workshop.

[0038] The production plan refers to the arrangement of the production allocation plan for each component in different available workshops, and is formulated based on factors such as the production quantity of each component of the target product and the efficiency of the workshop equipment. The production plan can be understood as an optimized production allocation plan for components in different workshops generated by the cloud computing server based on the production quantity of components, assembly ratio and the efficiency of each workshop equipment. It is used to guide each workshop to produce the corresponding components according to the plan requirements, realize multi-workshop collaborative production, and achieve the purpose of quickly completing production goals.

[0039] Specifically, in order to achieve collaborative production among multiple workshops and maximize overall efficiency, the cloud computing server needs to reasonably formulate the best production allocation plan for each component on different workshop equipment, that is, the production plan. The purpose of formulating a production plan is to enable each component to be allocated to each workshop for production in the best way, so as to avoid waste of workshop equipment capacity or production bottlenecks due to improper allocation of some components. The cloud computing server determines the production plan based on factors such as the assembly ratio of the components, the production quantity of the components, and the efficiency of the equipment in each workshop in producing the components. The assembly ratio determines the quantity matching relationship between the components, the production quantity is the output target of the components, and the production efficiency reflects the ability of the workshop equipment to produce each component. Taking these factors into full consideration allows the cloud server to accurately calculate the best production allocation of each component in each workshop, which not only meets the requirements of the assembly ratio, but also takes into account the actual production situation of the workshop equipment, avoiding the situation where some components are overproduced while other components cannot meet the production target. After determining the production plan, the cloud computing server sends the optimized production plan to the production equipment in each workshop as a guide for its production. Each device produces the corresponding components according to the received production plan requirements.

[0040] In an optional implementation, the production efficiency of each component produced by production equipment in multiple available workshops can be obtained by using the following steps.

[0041] Obtain the historical production efficiency of each component produced by each production equipment; The average value of historical production efficiency is determined as the production efficiency of each component produced by the production equipment of each available workshop.

[0042] The historical production efficiency refers to the actual efficiency of each workshop's production equipment in producing each component over the past period of time. The cloud computing server obtains the historical production efficiency data of each equipment in producing each component, and determines the average value of these historical efficiencies as the production efficiency of each component produced by the production equipment in each available workshop.

[0043] Specifically, in order for the cloud computing server to develop a more accurate and reasonable multi-workshop production plan, the actual production level of each workshop equipment needs to be fully considered. Directly using the instantaneous production efficiency of a certain period of time is easily affected by accidental factors and cannot fully reflect the overall production capacity of the equipment. To this end, the cloud computing server needs to obtain all the historical production efficiency data of each component produced by the equipment in each workshop over a period of time. Relying on its own powerful computing and processing capabilities, the cloud computing server can quickly extract a large amount of historical efficiency data from the database of each workshop. Then, the cloud computing server will calculate the average historical efficiency of each component produced by each device as the production efficiency of the device producing the component.

[0044] S103: When at least one target device to be maintained appears in each production device, target component information of each target device whose production is delayed due to maintenance is determined.

[0045] Among them, the target equipment refers to the workshop production equipment that needs maintenance, resulting in reduced production efficiency or shutdown. Since the maintenance of the target equipment will reduce or stop the corresponding components of its production, it will affect the implementation progress of the production plan. The cloud computing server needs to monitor the equipment status of each workshop in real time to determine whether there is equipment whose production capacity has decreased or cannot be produced due to maintenance and other reasons. Once such a situation is found in a device, the cloud computing server will identify it as a target device. Then, according to the maintenance status of these target devices, the production plans of multiple workshops are adjusted accordingly to achieve coordination between equipment maintenance and production plan optimization, and ensure the maximization of the overall production efficiency of multiple workshops.

[0046] Target component information refers to the relevant information of components whose production progress is delayed due to target equipment maintenance. When the cloud computing server confirms that target equipment needs maintenance, these equipment will cause the output of the components produced by them to be reduced or delayed due to shutdown or reduced efficiency. The cloud computing server will identify the components whose progress is delayed due to target equipment maintenance, and summarize the key information of these components to form the target component information.

[0047] When production equipment is in working condition, its parts or mechanical devices involved in production will gradually wear out. As the wear increases, the production components may not meet production requirements, and may even cause production equipment failure. Therefore, regular maintenance and servicing of production equipment is required.

[0048] When the cloud computing server detects that target equipment in each workshop needs maintenance, it is necessary to determine which components will be affected by the maintenance of these target equipment, that is, to find out the target components that will be delayed. The maintenance of the target equipment is likely to reduce the output of the components it produces or fail to complete production on schedule. If these target components are not determined in advance, it will be found that some key components are insufficient when the production period comes, which will directly affect the implementation of the production plan.

[0049] Specifically, when the cloud computing server detects that there are target devices in each workshop that need maintenance, it determines in advance which components the maintenance of these target devices will affect. Because the target devices will reduce or stop production during the maintenance period, the output of their corresponding components will be reduced or delayed. By determining these target components in advance, the cloud computing server can adjust the production plan in time and reasonably allocate the production tasks of these components to other equipment, minimizing the impact of equipment maintenance on production progress.

[0050] The above embodiment roughly describes the situation when a target device to be maintained appears. Based on the above embodiment, the method for determining the target component information in S103 will be described in detail below.

[0051] As an optional implementation manner, the target component information includes the load transfer device and the load transfer quantity of each target component. S103 may further include the following steps: S201: When each production device has at least one target device to be maintained, a target production efficiency and maintenance duration of each target device are obtained.

[0052] Among them, the target production efficiency refers to the production efficiency of the target equipment under normal production conditions, which is only expressed as the production efficiency corresponding to the target equipment and is used to calculate the number of target components that the target equipment cannot produce during maintenance.

[0053] Maintenance duration refers to the length of time required for maintenance of the target device. Maintenance duration can be understood as the period of time during which the target device cannot perform normal production. Maintenance duration takes into account the specific maintenance content of the target device and can more accurately reflect the time the target device is actually in maintenance. Combined with the target production efficiency, the number of target components that will be reduced during the maintenance period of the target device can be accurately calculated.

[0054] In the process of multi-workshop collaborative production, when the cloud computing server detects that a target device needs maintenance due to maintenance or other reasons, it is necessary to obtain the target production efficiency and specific maintenance time of the target device in advance. This is because the target device will reduce or stop production during the maintenance period, which will directly affect the output progress of its corresponding target component. In order to arrange the production plan reasonably, it is necessary to clearly know the number of target components that can be produced during the maintenance period of the target device and the time taken for maintenance.

[0055] Specifically, the cloud computing server will connect to the production management system database of each workshop and extract the production efficiency parameters of the target equipment under normal working conditions as its target production efficiency. This can reflect the upper limit of the target equipment's production capacity. At the same time, the cloud computing server will count all the maintenance items that the target equipment needs to perform during this maintenance and the duration required for each item, and calculate the total maintenance duration. After obtaining the target production efficiency and maintenance duration, the cloud computing server can accurately calculate how much the number of target components that the target equipment can produce during the maintenance period will be reduced.

[0056] Optionally, when determining the maintenance duration of the target device in step S01, it is necessary to consider the maintenance items that the target device needs to perform when producing the target component, so steps S2011-2012 can be used to calculate the maintenance duration.

[0057] S2011: Obtain maintenance items for producing target components of target equipment and standard project duration corresponding to each maintenance item; Specifically, maintenance items refer to specific maintenance operations that need to be performed during the maintenance of the target equipment. Each maintenance item corresponds to different maintenance operation steps. The category of maintenance items is determined by the type of production equipment and the type of components it produces. Different equipment uses different processes and mechanical structures to produce the same component, and the required maintenance items are also different. At the same time, the production of different components will also have different effects on the loss of equipment, resulting in adjustments to maintenance items.

[0058] For example, two production equipment produce the same component that needs to be polished. One of the production equipment uses sandpaper to polish, so its maintenance project is to replace the sandpaper, while the other production equipment uses a polishing machine to polish, so its maintenance project is to maintain the polishing machine. At the same time, the maintenance projects of different components are also different, because different types of components are produced in different ways, which leads to different maintenance projects.

[0059] The standard project duration corresponding to a maintenance project refers to the standard length of time required to complete the corresponding maintenance project. This duration is determined based on the specific content and process of the maintenance project. The standard project duration corresponding to a maintenance project can be understood as the time required to perform each specific maintenance project. It is used in conjunction with the maintenance project to calculate the total maintenance time required to perform all maintenance on the target device. The standard project duration corresponding to the maintenance project takes into account the specific steps of each project and its estimated time, and can reasonably reflect the standard time cost of each project. Combined with the maintenance project list, the duration of the overall maintenance of the target device can be calculated in detail.

[0060] In order to calculate the total maintenance time of the target device, the cloud computing server needs to obtain all the maintenance items involved in the production of the corresponding target component of the target device, as well as the standard project duration corresponding to each item. This is because the maintenance time of the target device is composed of the accumulated time of each maintenance item. It is necessary to clearly know which specific maintenance items the target device needs to perform and the estimated time required for each item in order to determine the total maintenance time of the device.

[0061] Specifically, the cloud computing server will connect to the equipment maintenance database of the production management system, query and extract the names of all necessary maintenance items involved in the entire process of producing the target component of the target equipment. At the same time, the standard project duration of each item in the equipment manual and maintenance plan is obtained.

[0062] S2012: Determine the maintenance duration of each target device according to each maintenance item and the corresponding standard item duration.

[0063] In order to reasonably determine the maintenance duration of each target device, the cloud computing server needs to calculate based on all the maintenance items of each target device that have been obtained and the standard project duration corresponding to each item. This is because the maintenance duration of the target device is the sum of the durations of all maintenance items. Only by correctly calculating the standard duration of each maintenance item and adding them up can the accurate length of time required for the entire maintenance of the device from the beginning to the end be obtained.

[0064] Specifically, the cloud computing server will summarize all maintenance items for each target device and take out the standard project duration specified in the device manual and maintenance plan. Then, the summation algorithm is used to calculate the total duration of each maintenance item for each device. Finally, the maintenance duration required for each target device to be fully completed from start to finish can be obtained.

[0065] S202: Calculate the production reduction quantity of the target components corresponding to each target device according to the target production efficiency and maintenance duration.

[0066] The production reduction quantity refers to the amount of target component production that is reduced due to maintenance of the target device. It is a reduction relative to normal production. In the embodiment of the present application, the production reduction quantity can be understood as the number of target components that cannot be produced during the maintenance of the target device. It is combined with the target production efficiency and maintenance duration to calculate the impact of the maintenance of the target device on the target component production. The production reduction quantity takes into account the production efficiency level of the target device and the time actually occupied by maintenance, and can accurately reflect that the target device will reduce the number of target components produced during the maintenance period.

[0067] In order to accurately assess the impact of maintenance on the target number of components produced by each target device, the cloud computing server needs to calculate the reduction in production of each target component based on the target production efficiency and maintenance duration that have been obtained. This is because only by clearly understanding the reduction in production caused by maintenance can a new production plan be formulated to make up for the lost output.

[0068] Specifically, the cloud computing server expresses the target production efficiency of each target device as the target number of components produced per hour. The maintenance time of each device is then converted into hours. Finally, through a simple multiplication calculation, the number of target components of the target device that will be reduced during the maintenance period can be obtained.

[0069] S203: Determine, according to the workshop type of the available workshop where each target device is located, the additional production volume of the target component that can be produced by the available workshop where the target device is located within the maintenance duration.

[0070] The workshop type refers to the type of production equipment contained in the available workshop. In the embodiment of the present application, it can be understood that the workshop is a combination of the same type of production equipment that specializes in producing a certain component, or a combination of multiple types of production equipment that produces multiple different components.

[0071] The additional production volume refers to the amount of target components that can be produced by the available workshop through other equipment during the maintenance of the target equipment. In the embodiment of the present application, it can be understood that during the maintenance period of the target equipment, other equipment in the available workshop is used to produce additional target components to make up for the loss caused by the reduction in production of the target equipment. In other words, the additional production volume reflects the other equipment in the available workshop other than the target equipment, and the amount of target components that can be produced during the maintenance of the target equipment can be increased to make up for the reduction in production of the target equipment, ensuring that the total output of the target components meets the production plan requirements.

[0072] The cloud computing server needs to determine whether the workshop can increase the additional production of the target component within the maintenance time according to the workshop type of the available workshop where the target device is located. Specifically, the cloud computing server first determines the type of workshop where the target device is located. If it is a workshop of the same type, that is, all equipment is used to produce the target component, it has a higher production capacity. At this time, other equipment in the workshop can be directly used as production equipment to calculate the number of target components that can be produced as the first additional production. If it is a mixed workshop, it is necessary to further determine whether it contains equipment for producing target components. If so, the second additional production is calculated with these equipment as production equipment, which is usually lower than the first additional production. If not, the target component cannot be directly increased. By judging the workshop type and distinguishing different production capacity, the server can clarify the additional production of each workshop to make up for the loss of production reduction of the target equipment, thereby reasonably adjusting the production plan.

[0073] As an optional implementation, for the step of determining the workshop type of the workshop where the target equipment is located and the additional production volume of the target component that the workshop of this type can produce, S203 may further include steps S301-S307.

[0074] S301: Determine whether all available workshops where the target equipment is located are production equipment for producing the target component.

[0075] In order to distinguish the additional production capacity of different workshops and determine the reasonable additional production volume, the cloud computing server needs to determine whether all the available workshops where the target equipment is located are the same type of production equipment that produces the target component.

[0076] The specific operation is that the cloud computing server queries the equipment list of the available workshop and determines whether each device is used to produce the target component. By determining the production purpose of all equipment in the workshop, the type attribute of the workshop can be clarified, thereby distinguishing its ability to increase the production of the target component.

[0077] S302: If all the available workshops where the target equipment is located are production equipment that produces the target component, the available workshops where the target equipment is located are determined to be workshops of the same type, and the quantity of the target component that can be produced by the workshops of the same type within the maintenance duration is the first additional production quantity.

[0078] The same type of workshop refers to a scenario where all the production equipment in the available workshop is used to produce the same component. In the embodiment of the present application, it can be understood that the equipment in the workshop uniformly produces the target component, which is used to judge that the workshop has a strong ability to increase the production of the target component. In other words, when all the equipment in the available workshop is equipment for producing the target component, the workshop is determined to be a workshop of the same type. The ability of the same type of workshop to produce the target component is strong because its highly unified production environment optimizes the entire workshop, and all aspects such as workers, equipment, and management are professionally optimized for the same component, so that the workshop, as a whole system, can produce the component very efficiently. Specifically, the workers are proficient in the production process, the equipment efficiency is maximized, and the management and quality control are specialized, which makes the same type of workshop have a strong production capacity. Combining the synergy of various aspects, the overall production efficiency of the same type of workshop.

[0079] The first additional production volume refers to the number of target components that can be additionally produced by other equipment of the same type in the workshop during the maintenance period of the target equipment. In the embodiment of the present application, it can be understood that other equipment in the same type of workshop is used to produce additional target components during the maintenance period of the target equipment to make up for the reduction in production of the target equipment due to maintenance, and the number of additional target components produced is defined as the first additional production volume. In other words, the first additional production volume represents other equipment of the same type in the same type of workshop, which can produce more additional target components during the maintenance period of the target equipment due to its high production efficiency. This part of the additional output is defined as the first additional production volume, which is used to make up for the loss of production reduction of the target equipment.

[0080] In order to accurately determine the production capacity of different workshops and obtain a reasonable additional production volume, the cloud computing server needs to determine that the workshop is a workshop of the same type when it is determined that all equipment in the available workshop where the target equipment is located is used to produce the target component. The specific operation is that the server queries all equipment in the available workshop and matches their production purposes one by one. If all equipment is used to produce the target component, the workshop is confirmed to be a workshop of the same type. Since all equipment in the same type of workshop is the same type of equipment for producing the target component, the workers are highly skilled and the production efficiency is optimal. Therefore, the server can directly use the production capacity of other equipment of the same type in the workshop as the additional production volume to make up for the loss of reduced production of the target equipment. The number of target components produced in addition by the same type of workshop is defined as the first additional production volume.

[0081] S303: If the available workshop where the target equipment is located is not entirely production equipment for producing the target component, the available workshop where the target equipment is located is determined to be a mixed workshop. The quantity of target components that can be produced by the mixed workshop during the maintenance period is the second additional production quantity, and the first additional production quantity is greater than the second additional production quantity.

[0082] A mixed workshop refers to a scenario where an available workshop contains multiple different types of production equipment at the same time and can produce multiple different components. In the embodiment of the present application, it can be understood that some equipment in the workshop produces target components, and there are also other types of equipment, which is used to judge that the ability of the workshop to directly increase the production of target components is weak. In other words, when the available workshop is not full of equipment for producing target components, the workshop is judged as a mixed workshop.

[0083] The second additional production volume refers to the number of target components that can be produced additionally by the equipment producing the target components in the hybrid workshop during the maintenance time of the target equipment. In the embodiment of the present application, it can be understood that the equipment corresponding to the target components in the hybrid workshop is used to produce additional target components during the maintenance period of the target equipment to partially make up for the loss caused by the reduction in production of the target equipment. The number of target components produced in addition is defined as the second additional production volume. In other words, the second additional production volume represents the number of target components that can be produced additionally by these devices during the maintenance time in the hybrid workshop when only some of the equipment matches the target components. Since only some of the equipment is involved, its additional output is lower than the first additional production volume of the same type of workshop.

[0084] In order to accurately distinguish the production capacity of different workshops and obtain a reasonable additional production volume, the cloud computing server needs to determine that the workshop is a mixed workshop when it is determined that not all equipment in the available workshop where the target equipment is located is used to produce the target component. The specific operation is that the server queries the equipment in the available workshop and determines that if there are other types of equipment that are not used to produce the target component, the workshop is confirmed to be a mixed workshop. Only some of the equipment in the mixed workshop produces the target component, and the direct production capacity is limited. The server needs to determine the equipment that produces these target components and use their production capacity as the additional production volume of the workshop, that is, the second additional production volume. However, since only some of the equipment is involved, the production efficiency of the mixed workshop is lower than that of the same type of workshop.

[0085] After determining the first additional production volume of the same type of workshop and the second additional production volume of the mixed workshop, since the same type of workshop has high production efficiency and can continue to utilize the raw materials and productivity of the workshop, it can be determined whether the difference generated by the target equipment can be fully borne by the equipment of the same type of workshop. The specific steps are as follows.

[0086] S304: Determine whether the first additional production quantity is greater than the production reduction quantity; After calculating the target equipment's production reduction and the first additional production of the same type of workshop, in order to reasonably arrange production tasks and reduce resource waste, the cloud computing server needs to determine whether the first additional production is greater than the production reduction. The specific operation is that the server directly compares the two. The purpose of the judgment is to examine whether the same type of workshop has sufficient production capacity to fully compensate for the loss of production reduction of the target equipment. The reason why the same type of workshop is considered first is that it has high production efficiency, sufficient raw materials and capacity, and can directly undertake the output of the original target equipment without adding new investment.

[0087] S305: If the first additional production quantity is greater than the production reduction quantity, determining other equipment in the same type of workshop as load transfer equipment for the target component; Load transfer equipment refers to other equipment that undertakes the production tasks that the target equipment cannot complete during maintenance and replaces the target equipment to produce the target components. In the embodiment of the present application, the load transfer equipment can be understood as equipment used to produce target components in a mixed workshop. When the first additional production volume of the same type of workshop cannot completely make up for the reduction in production of the target equipment, these load transfer equipment will undertake the remaining production tasks of the target equipment and produce a specific number of target components. In other words, the load transfer equipment directly replaces the target equipment to produce products, rather than just allocating and transferring tasks.

[0088] After determining that the first additional production volume of the same type of workshop is greater than the production reduction of the target equipment, in order to rationally utilize production resources and maximize the compensation for the production reduction loss, the cloud computing server needs to determine other equipment of the same type in the same type of workshop as load transfer equipment. The specific operation is to directly specify the equipment other than the target equipment in the same type of workshop as load transfer equipment. In this way, the production capacity and resources of the same type of workshop can be directly used to complete the output task of the original target equipment without adding other new investments. The reason why other equipment of the same type in the same type of workshop is determined as load transfer equipment is that it does not require secondary transfer tasks, has the ability to directly complete the production of target components, and has the highest production efficiency. Through the same type of load transfer, the production reduction loss can be fully compensated, and the production progress can be seamlessly continued. At the same time, the waste of resources is minimized and the overall efficiency of multi-workshop collaborative production is improved.

[0089] S306: If the first additional production quantity is greater than the production reduction quantity, determining other equipment in the same type of workshop as load transfer equipment for the target component; After determining that the first additional production volume of the same type of workshop is greater than the target equipment's production reduction, in order to maximize the compensation for the production reduction loss, the cloud computing server needs to directly designate other similar equipment in the same type of workshop except the target equipment as load transfer equipment. The reason for this is that the same type of workshop is an integral system, and other equipment inside it uses the same process and production line as the target equipment. The workers are highly skilled and can directly undertake the production tasks of the target equipment without transfer and readaptation, thereby ensuring the highest efficiency in completing the production target. The specific operation is that the server directly assigns the corresponding number of other similar equipment in the same type of workshop to produce the target components according to the original process, directly compensating for the loss of the target equipment's production reduction.

[0090] S204: Determine target component information of delayed production of each target device due to maintenance based on the additional production volume of the available workshop where each target device is located and the reduced production quantity of the target component corresponding to each target device.

[0091] The target component information includes the load transfer device and the load transfer quantity of each target component.

[0092] The load transfer quantity refers to the number of target components that each load transfer device needs to produce during the maintenance of the target device. In the embodiment of the present application, the load transfer device refers to other devices that replace the target device to produce the target components. The load transfer quantity is the number of target components that each load transfer device needs to produce according to the production plan calculated by the server. The load transfer quantity is the specific production task quantity assigned to each load transfer device according to the production capacity.

[0093] In order to reasonably determine the post-maintenance production arrangements for each target device, the cloud server needs to determine the detailed information of the target components that each target device still needs to produce based on the first additional production volume or the second additional production volume of the available workshop where each target device is located, and the corresponding target component production reduction quantity. The specific operation is to calculate the number of target components that the target device still needs to produce after comparing the additional production volume and the production reduction quantity. Then, based on this number, the specific load transfer equipment that can undertake the corresponding output task is determined in combination with the production capacity. Finally, the specific number of target components that each determined load transfer equipment needs to produce, that is, the load transfer quantity, is calculated.

[0094] In this way, detailed information about the target components of each target device can be obtained, including the quantity that still needs to be produced, the corresponding load transfer device, and the specific production volume of each device, so that the server can accurately arrange the production plan and improve the efficiency of production coordination. By determining the complete target component information, the plan for multi-workshop collaborative production can be made more specific and feasible, and each production link can be highly coordinated to ultimately achieve the overall output target.

[0095] In an optional implementation, the target component information may be calculated in the following manner.

[0096] Substitute the additional production volume of the available workshop where each target device is located and the reduced production quantity of the target component corresponding to each target device into the preset allocation formula to obtain the target component information of each target device whose production is delayed due to maintenance; Among them, the preset allocation formula is: In the formula, A j represents the load transfer quantity of other equipment in the jth workshop of the same type, j represents the serial number of other equipment in the same workshop, m represents the number of other equipment in the same workshop, q j represents the additional production capacity of other equipment in the jth workshop of the same type, e j represents the efficiency coefficient of other equipment in the jth workshop of the same type, α represents the additional production capacity of the available workshop where the target equipment is located, k represents the serial number of the production equipment corresponding to the target component in the mixed workshop, l represents the number of production equipment corresponding to the target component in the mixed workshop, and s k represents the additional production capacity of the production equipment corresponding to the target component in the k-th hybrid workshop, f k represents the efficiency coefficient of the production equipment corresponding to the target component in the kth hybrid workshop, β represents the reduction quantity of the target component corresponding to each target equipment, i represents the sequence number of the target equipment corresponding to the target component, n represents the number of target equipment corresponding to the target component, r i represents the reduction rate of the target equipment corresponding to the i-th target component, p i represents the original productivity of the target equipment corresponding to the i-th target component.

[0097] In order to reasonably determine the load transfer quantity of each target device, the cloud server needs to substitute the first additional production volume and the second additional production volume of the available workshop where each target device is located, as well as the respective production reduction quantity into the preset allocation formula for calculation. Specifically, the server substitutes the equipment conditions, efficiency coefficients and other data of the same type and mixed workshops, as well as the production reduction rate and original yield of each target device as known quantities into the corresponding variables in the formula, and calculates the load transfer quantity of each target device.

[0098] The load transfer quantity in the same type of workshop where the target equipment is located is calculated through the preset allocation formula. If this load transfer quantity is less than the production reduction quantity, the load transfer quantity of this target equipment can be absorbed by the same type of workshop itself, and no longer needs to be borne by other equipment in the mixed workshop. When other equipment in the same type of workshop cannot fully absorb the production reduction quantity of the target equipment, other equipment in the mixed workshop that can produce the target components will be considered.

[0099] S104: Adjust the production plan according to the information of each target component, and send the adjusted production plan to each production equipment.

[0100] After obtaining the complete target component information corresponding to each target device, including the load transfer device and the respective load transfer quantity, in order to start multi-workshop collaborative production according to the new production arrangement, the cloud server needs to adjust the original production plan based on this information. The specific operation is that the server re-formulates the production plan according to the load transfer quantity of each target device, and accurately arranges the production tasks of each load transfer device during the maintenance of the target device. And considering the output tasks after the target device is restored, the production progress of each device in the entire production cycle is reasonably adjusted. The purpose of this is to make the new production plan highly consistent with the actual situation of each workshop through accurate component information, and to accurately connect each production link to ensure the overall efficiency of multi-workshop collaborative production. The adjusted production plan will be sent to each production equipment by the server as their new production task instructions to guide the equipment to collaborate in production and ultimately achieve the overall production target.

[0101] The following are device embodiments of the present application, which can be used to execute the method embodiments of the present application. For details not disclosed in the device embodiments of the present application, please refer to the method embodiments of the present application.

[0102] See also Figure 2 , which shows a schematic diagram of the structure of a multi-workshop production equipment optimization device based on cloud computing provided by an exemplary embodiment of the present application. The device can be implemented as all or part of the device through software, hardware or a combination of both.

[0103] Optionally, the data acquisition module also includes a historical data acquisition unit.

[0104] The historical data acquisition unit is used to acquire the historical production efficiency of each component produced by each production equipment; and determine the average value of the historical production efficiency as the production efficiency of each component produced by the production equipment of each available workshop.

[0105] Optionally, the maintenance information determination module also includes a target component information determination unit, a workshop type determination unit, a load transfer equipment determination unit, a maintenance duration determination unit, and a load transfer quantity calculation unit.

[0106] The target component information determination unit is used to obtain the target production efficiency and maintenance time of each target device when at least one target device to be maintained appears in each production device; calculate the reduced production quantity of the target component corresponding to each target device according to the target production efficiency and the maintenance time; determine the additional production quantity of the target component that can be produced by the available workshop where the target device is located within the maintenance time according to the workshop type of the available workshop where each target device is located; determine the target component information of each target device whose output is delayed due to maintenance according to the additional production quantity of the available workshop where each target device is located and the reduced production quantity of the target component corresponding to each target device, the target component information including the load transfer device and the load transfer quantity of each target component.

[0107] The workshop type determination unit is used to determine whether all available workshops where the target equipment is located are production equipment that produces the target components; if all available workshops where the target equipment is located are production equipment that produces the target components, the available workshops where the target equipment is located are determined to be workshops of the same type, and the number of target components that can be produced by the same type of workshops within the maintenance period is a first additional production quantity; if not all available workshops where the target equipment is located are production equipment that produces the target components, the available workshops where the target equipment is located are determined to be mixed workshops, and the number of target components that can be produced by the mixed workshops within the maintenance period is a second additional production quantity, and the first additional production quantity is greater than the second additional production quantity.

[0108] The load transfer equipment determination unit is used to determine whether the first additional production volume is greater than the production reduction volume; if the first additional production volume is greater than the production reduction volume, other equipment in the same type of workshop is determined as the load transfer equipment of the target component; if the first additional production volume is not greater than the production reduction volume, other equipment in the same type of workshop and the production equipment corresponding to the target component in the mixed workshop are jointly determined as the load transfer equipment of the target component.

[0109] The maintenance duration determination unit is used to obtain the maintenance items of the target equipment to produce the target components, and the standard project duration corresponding to each maintenance item; and determine the maintenance duration of each target equipment according to each maintenance item and the corresponding standard project duration.

[0110] The load transfer quantity calculation unit is used to substitute the additional production volume of the available workshop where each target device is located and the reduced production quantity of the target component corresponding to each target device into a preset allocation formula to obtain the target component information of the delayed production of each target device due to maintenance; Among them, the preset allocation formula is: In the formula, A j represents the load transfer quantity of other equipment in the jth workshop of the same type, j represents the serial number of other equipment in the same workshop, m represents the number of other equipment in the same workshop, qj represents the additional production capacity of other equipment in the jth workshop of the same type, e j represents the efficiency coefficient of other equipment in the jth workshop of the same type, α represents the additional production capacity of the available workshop where the target equipment is located, k represents the serial number of the production equipment corresponding to the target component in the mixed workshop, l represents the number of production equipment corresponding to the target component in the mixed workshop, and s k represents the additional production capacity of the production equipment corresponding to the target component in the k-th hybrid workshop, f k represents the efficiency coefficient of the production equipment corresponding to the target component in the kth hybrid workshop, β represents the reduction quantity of the target component corresponding to each target equipment, i represents the sequence number of the target equipment corresponding to the target component, n represents the number of target equipment corresponding to the target component, r i represents the reduction rate of the target equipment corresponding to the i-th target component, p i represents the original productivity of the target equipment corresponding to the i-th target component.

[0111] The present application also provides a computer storage medium that can store multiple instructions, which are suitable for being loaded and executed by a processor as described above. Figure 1 The multi-workshop production equipment optimization method based on cloud computing in the embodiment shown in the figure can be specifically implemented by referring to Figure 1 The specific description of the illustrated embodiment will not be repeated here.

[0112] See also Figure 3 , is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application. Figure 3 As shown, the electronic device 300 may include: at least one processor 301 , at least one network interface 304 , a user interface 303 , a memory 305 , and at least one communication bus 302 .

[0113] The communication bus 302 is used to realize the connection and communication between these components.

[0114] The user interface 303 may include a standard wired interface or a wireless interface.

[0115] The network interface 304 may optionally include a standard wired interface or a wireless interface (such as a WI-FI interface).

[0116] Among them, the processor 301 may include one or more processing cores. The processor 301 uses various interfaces and lines to connect various parts in the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory 305, and calling data stored in the memory 305. Optionally, the processor 301 can be implemented in at least one hardware form of digital signal processing (Digital Signal Processing, DSP), field programmable gate array (Field-Programmable Gate Array, FPGA), and programmable logic array (Programmable Logic Array, PLA). The processor 301 can integrate one or a combination of a central processing unit (Central Processing Unit, CPU), a graphics processing unit (Graphics Processing Unit, GPU) and a modem. Among them, the CPU mainly processes the operating system, user interface and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display screen; the modem is used to process wireless communications. It can be understood that the above-mentioned modem may not be integrated into the processor 301, and it can be implemented separately through a chip.

[0117] Among them, the memory 305 may include a random access memory (Random Access Memory, RAM) and may also include a read-only memory (Read-Only Memory). Optionally, the memory 305 includes a non-transitory computer-readable storage medium. The memory 305 can be used to store instructions, programs, codes, code sets or instruction sets. The memory 305 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory 305 may optionally be at least one storage device located away from the aforementioned processor 301. As Figure 3 As shown, the memory 305 as a computer storage medium may include an operating system, a network communication module, a user interface module, and an application program of a multi-workshop production equipment optimization method based on cloud computing.

[0118] exist Figure 3In the electronic device 300 shown, the user interface 303 is mainly used to provide an input interface for the user and obtain data input by the user; and the processor 301 can be used to call an application program stored in the memory 305 for a cloud computing-based multi-workshop production equipment optimization method. When executed by one or more processors, the electronic device executes one or more methods in the above-mentioned embodiments.

[0119] An electronic device readable storage medium stores instructions, which, when executed by one or more processors, enable the electronic device to execute one or more methods in the above embodiments.

[0120] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the order of the actions described, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required for the present application.

[0121] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0122] In the several embodiments provided in this application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are only schematic, such as the division of units, which is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some service interfaces, and the indirect coupling or communication connection of devices or units can be electrical or other forms.

[0123] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0124] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0125] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the various embodiments of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.

[0126] The above are only exemplary embodiments of the present disclosure and cannot be used to limit the scope of the present disclosure. That is, any equivalent changes and modifications made according to the teachings of the present disclosure are still within the scope of the present disclosure. After considering the disclosure of the specification and the truth of practice, it will be easy for those skilled in the art to think of other embodiments of the present disclosure. This application is intended to cover any variation, use or adaptive change of the present disclosure, which follows the general principles of the present disclosure and includes common knowledge or customary technical means in the technical field that are not recorded in the present disclosure.

Claims

1. A multi-workshop production equipment optimization method based on cloud computing, characterized in that: Applied to a cloud computing server, the method comprises: Obtain the production quantity of multiple components to be produced of the target product and the assembly ratio between the components; Determine a production plan for allocating each component to a corresponding production equipment according to the assembly ratio of each component, the production quantity of each component, and the production efficiency of each component produced by production equipment in multiple available workshops, and send the production plan to each production equipment so that each production equipment produces the corresponding component according to the production plan; When at least one target device to be maintained appears in each of the production devices, target component information of each of the target devices whose production is delayed due to maintenance is determined; The production plan is adjusted according to the target component information, and the adjusted production plan is sent to each production equipment.

2. The method according to claim 1, characterized in that: When at least one target device to be maintained appears in each of the production devices, determining target component information of each of the target devices whose production is delayed due to maintenance includes: When at least one target device to be maintained appears in each of the production devices, a target production efficiency and maintenance duration of each of the target devices are obtained; According to the target production efficiency and the maintenance duration, the production reduction quantity of the target component corresponding to each target device is calculated; according to the workshop type of the available workshop where each target device is located, the additional production quantity of the target component that can be produced by the available workshop where the target device is located within the maintenance duration is determined; Based on the extra production volume of the available workshops where each of the target devices is located and the reduced production quantity of the target components corresponding to each of the target devices, the target component information of each of the target devices whose production is delayed due to maintenance is determined, and the target component information includes the load transfer equipment and load transfer quantity of each of the target components.

3. The method according to claim 2, characterized in that The determining, according to the workshop type of the available workshop where each of the target devices is located, the additional production volume of the target component that can be produced by the available workshop where the target device is located within the maintenance duration includes: Determine whether all available workshops where the target equipment is located are production equipment for producing the target component; If all the available workshops where the target equipment is located are production equipment that produces the target component, the available workshops where the target equipment is located are determined to be workshops of the same type, and the quantity of the target component that can be produced by the workshops of the same type within the maintenance duration is the first additional production quantity; If not all available workshops where the target equipment is located are production equipment for producing the target component, the available workshop where the target equipment is located is determined to be a mixed workshop, and the mixed workshop can produce the target component within the maintenance period in a quantity that is the second additional production quantity, and the first additional production quantity is greater than the second additional production quantity.

4. The method according to claim 3, characterized in that: The step of determining target component information of each target device whose output is delayed due to maintenance based on the additional production volume of the available workshop where the target device is located and the reduced production volume of the target component corresponding to each target device includes: Substituting the additional production volume of the available workshop where each target device is located and the reduced production quantity of the target component corresponding to each target device into a preset allocation formula, to obtain the target component information of each target device whose production is delayed due to maintenance; Among them, the preset allocation formula is: In the formula, A j represents the load transfer quantity of other equipment in the jth workshop of the same type, j represents the serial number of other equipment in the same workshop, m represents the number of other equipment in the same workshop, q j represents the additional production capacity of other equipment in the jth workshop of the same type, e j represents the efficiency coefficient of other equipment in the jth workshop of the same type, α represents the additional production capacity of the available workshop where the target equipment is located, k represents the serial number of the production equipment corresponding to the target component in the mixed workshop, l represents the number of production equipment corresponding to the target component in the mixed workshop, s k represents the additional production capacity of the production equipment corresponding to the target component in the kth hybrid workshop, f k represents the efficiency coefficient of the production equipment corresponding to the target component in the kth hybrid workshop, β represents the reduced production quantity of the target component corresponding to each target equipment, i represents the sequence number of the target equipment corresponding to the target component, n represents the number of target equipment corresponding to the target component, r i represents the reduction rate of the target equipment corresponding to the i-th target component, p i represents the original productivity of the target equipment corresponding to the i-th target component.

5. The method according to claim 3, characterized in that: The method further comprises: determining whether the first additional production amount is greater than the production reduction amount; If the first additional production quantity is greater than the production reduction quantity, determining other equipment in the same type of workshop as load transfer equipment for the target component; If the first additional production volume is not greater than the production reduction quantity, other equipment in the same type of workshop and the production equipment corresponding to the target component in the mixed workshop are jointly determined as the load transfer equipment of the target component.

6. The method according to claim 2, characterized in that The obtaining of the maintenance duration of each of the target devices comprises: obtaining the maintenance items for producing the target components of the target devices, and the standard item duration corresponding to each of the maintenance items; and determining the maintenance duration of each of the target devices according to each of the maintenance items and the corresponding standard item duration.

7. The method according to claim 1, characterized in that After obtaining the production quantity of multiple components to be produced of the target product and the assembly ratio between the components, the method further includes: Obtain the historical production efficiency of each production equipment in producing each of the components; The average value of the historical production efficiency is determined as the production efficiency of the production equipment of each available workshop in producing each of the components.

8. A multi-workshop production equipment optimization device based on cloud computing, characterized in that: The device comprises: a data acquisition module for acquiring the production quantity of a plurality of components to be produced of a target product and the assembly ratio between the components; A production plan generating module is used to determine the production plan for allocating each component to the corresponding production equipment according to the assembly ratio of each component, the production quantity of each component, and the production efficiency of each component produced by the production equipment of multiple available workshops, and send the production plan to each production equipment so that each production equipment produces the corresponding component according to the production plan; A maintenance information determination module, used for determining target component information of each target device whose production is delayed due to maintenance when at least one target device to be maintained appears in each of the production devices; The production plan adjustment module is used to adjust the production plan according to the information of each target component and send the adjusted production plan to each production equipment.

9. A computer storage medium, characterized in that The computer storage medium stores a plurality of instructions, and the instructions are suitable for being loaded by a processor and executing the method according to any one of claims 1 to 7.

10. An electronic device, characterized in that: The electronic device comprises a processor, a memory and a transceiver, wherein the memory is used to store instructions, the transceiver is used to communicate with other devices, and the processor is used to execute the instructions stored in the memory so that the electronic device executes the method according to any one of claims 1 to 7.

Citation Information

Patent Citations

  • Shop operation dynamic dispatching method based on disturbance event driving

    CN101794147A

  • Production plan optimization device, system and method, and computer readable medium

    CN114692899A

  • Production management method and device, electronic equipment and storage medium

    CN114742662A

  • Intelligent management method, system and equipment for digital factory and storage medium

    CN116976614A

  • Generation method of cable scheduling scheme and electronic equipment

    CN117608257A

Cited By

  • Factory management method and system based on industrial big data

    CN121581534A