Control method and device for emergency dispatching on-line of standby train and electronic equipment
Through real-time monitoring and analysis of the train interval time period, the online time period and insertion point of the backup train are calculated, which solves the problem of inconsistent insertion timing of the backup train in fully automatic operating lines, and achieves the effective shortening of large train intervals and the improvement of operating efficiency. promote.
Patent Information
- Application Number
- CN202411020871.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-10-25
AI Technical Summary
In fully automatic lines, due to the different experiences of dispatchers and train drivers, the insertion timing of backup trains is inconsistent, making it impossible to effectively shorten long train intervals.
Through real-time monitoring of the train interval time period, analysis of delay time and planned operation chart, combined with the status and preparation of the backup train, the online time period and insertion point of the backup train are calculated to ensure that it is inserted when the preset conditions are met to improve insertion Accuracy of timing.
It effectively shortens the long train interval, improves the efficiency of the backup train on-line and the control accuracy of the insertion timing, and ensures the orderly and efficient train operation.
Smart Images

Figure CN118833282A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of train operation management technology, and in particular to a control method, device and electronic equipment for emergency dispatching of backup trains. Background Technology
[0002] When train malfunctions or accidents disrupt train operations, large intervals between trains occur. When these large intervals occur, adjustments to train operations on the line are necessary. Methods for adjusting train operations in the subway system include: detaining trains, multiple stops, skipping stops, speed-limited pre-station turnarounds, single-track bidirectional operation, short-route turnarounds, track removal, and deploying standby trains. The principle is to ensure relatively uniform train intervals on the line, avoiding localized congestion or excessively large intervals.
[0003] Currently, the operation of standby trains is mainly controlled manually by dispatchers and train drivers, who then dispatch and insert standby trains at appropriate times to address the issue of large headways between trains. However, in fully automated lines, this method alone has limitations. The differing experience of dispatchers and train drivers leads to inconsistencies in their judgment of when to dispatch standby trains, resulting in inconsistent timing of their insertion. If the timing of the standby train insertion is poor, the large headways cannot be effectively shortened.
[0004] Therefore, there is an urgent need for a control method, device, and electronic equipment for the emergency dispatching of backup trains. Summary of the Invention
[0005] This application aims to solve at least one of the technical problems existing in the prior art, and proposes a control method, device and electronic equipment for emergency dispatching of backup trains.
[0006] The first aspect of this application provides a control method for the emergency dispatching of a backup train, wherein the method includes: obtaining a time interval between a first train and a second train, wherein the second train is ahead of the first train; obtaining a time interval between the first train and the second train, wherein the second train is ahead of the first train, and the first train is a delayed train; obtaining a backup train and its corresponding time interval, wherein the time interval is the period between a first time point and a third time point, the first time point being the time point at which the delay of the first train begins, and the third time point being the time point at which the backup train is ready to start; determining whether the time interval meets a preset time condition; if the time interval corresponding to the backup train meets the preset time condition, obtaining a preset insertion point corresponding to the backup train; determining whether the preset insertion point meets a preset insertion condition; if the preset insertion point meets the preset insertion condition, inserting the backup train at the preset insertion point.
[0007] Optionally, the time interval between the first train and the second train can be obtained, specifically including: obtaining the delay time corresponding to the first train, and obtaining the time interval of the planned timetable; the sum of the delay time and the time interval of the planned timetable is used as the time interval.
[0008] Optionally, the online time period corresponding to the standby train is obtained, specifically including: obtaining the notification time period and the standby train status corresponding to the standby train. The standby train status includes cold standby status and hot standby status. The notification time period is the time period between the first time point and the second time point, and the second time point is the time point corresponding to when the standby train starts self-inspection. If the standby train status is confirmed to be cold standby status, the vehicle inspection time period is obtained. The vehicle inspection time period is the time period required for the standby train to change from cold standby status to hot standby status. The sum of the notification time period and the vehicle inspection time period is taken as the online time period.
[0009] Optionally, after obtaining the notification time period and the status of the standby train, the method further includes: if the status of the standby train is confirmed to be hot standby, the notification time period is used as the online time period.
[0010] Optionally, determine whether the online time period meets the preset time conditions, specifically including: obtaining the resumption time period corresponding to the first train, where the resumption time period is the time between the departure time and the arrival time, the departure time is the time corresponding to the resumption of the first train's operation, and the arrival time is the running time of the first train when the standby train is inserted; determine whether the online time period meets the preset time conditions according to the following inequality:
[0011]
[0012] Among them, T 发 For the departure time, T 进 If T is the arrival time, then 进 -T 发 To restore the running time period, t 总间隔 The time interval between train runs, t 检 For vehicle inspection time periods, t 通知 If t is the notification period, then 检 +t 通知 The online time period is defined as the time period during which the online time period is launched. If the online time period satisfies the above inequality, then the online time period is confirmed to meet the preset time conditions.
[0013] Optionally, determining whether the preset insertion point meets the preset insertion conditions specifically includes: obtaining the first position information corresponding to the preset insertion point, obtaining the second position information corresponding to the first train, wherein the second position information is the position information corresponding to the first train when the standby train completes inspection preparation; determining whether the first position information is located in front of the first position information; if the first position information is located in front of the second position information, then confirming that the preset insertion point meets the preset insertion conditions.
[0014] Optionally, the first train, the second train, and the spare train may be trains traveling in the same direction.
[0015] A second aspect of this application provides a control device for the emergency dispatching and deployment of backup trains. The device includes a train interval acquisition module, a train interval acquisition module, and a backup train deployment module, wherein...
[0016] The train interval acquisition module is used to obtain the time interval between the first train and the second train. The second train is located in front of the first train, and the first train is a delayed train.
[0017] The standby train deployment module is used to obtain standby trains and their corresponding deployment time periods. The deployment time period is the time between a first time point and a third time point. The first time point is the time when the first train begins to experience delays, and the third time point is the time when the standby train is ready to start. It then determines whether the deployment time period meets preset time conditions. If the deployment time period for the standby train meets the preset time conditions, it obtains the preset insertion point for the standby train. Finally, it determines whether the preset insertion point meets the preset insertion conditions. If the preset insertion point meets the preset insertion conditions, it inserts the standby train at the preset insertion point.
[0018] A third aspect of this application provides an electronic device including one or more processors, a memory, an I / O interface, and a communication bus, wherein the memory is used to store one or more programs; when the one or more programs are executed by one or more processors, the one or more processors implement any of the methods described above.
[0019] A fourth aspect of this application provides a computer-readable medium on which a computer program is stored, which, when executed by a processor, implements any of the methods described above. Attached Figure Description
[0020] Figure 1 A flowchart illustrating a control method for emergency dispatching of backup trains provided in this application embodiment;
[0021] Figure 2a This is a schematic diagram illustrating the timing of a backup train insertion, provided in an embodiment of this application.
[0022] Figure 2b This is a schematic diagram illustrating another possible timing for inserting a backup train, as provided in an embodiment of this application.
[0023] Figure 3 A schematic diagram illustrating the timing of the insertion of a spare train, provided in an embodiment of this application;
[0024] Figure 4 A schematic diagram of a control device for emergency dispatching of backup trains provided in an embodiment of this application;
[0025] Figure 5 This is a schematic diagram of the structure of an electronic device provided in an embodiment of this application.
[0026] Explanation of reference numerals in the attached diagram: 21. Delayed train; 22. Train ahead; 23. Spare train; 24. Upward route; 25. Downward route; 26. Insertion point; 201. Platform A; 202. Platform B; 203. Platform C; 204. Platform D; 41. Train interval acquisition module; 42. Spare train insertion module; 501. Processor; 502. Memory; 503. I / O interface; 504. Communication bus. Detailed Implementation
[0027] To enable those skilled in the art to better understand the technical solution of this application, the application will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0028] Unless otherwise defined, the technical or scientific terms used in this application shall have the ordinary meaning understood by one of ordinary skill in the art to which this application pertains. The terms "first," "second," and similar terms used in this application do not indicate any order, quantity, or importance, but are merely used to distinguish different components. Similarly, the terms "an," "a," or "the," etc., do not indicate a quantity limitation, but rather indicate the presence of at least one. The terms "comprising," "including," etc., mean that the element or object preceding the word encompasses the elements or objects listed following the word and their equivalents, without excluding other elements or objects. The terms "connected," "linked," etc., are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. "Above," "below," "left," "right," etc., are used only to indicate relative positional relationships; when the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0029] In the various figures, the same elements are represented by similar reference numerals. For clarity, not all parts in the figures are drawn to scale. Furthermore, some well-known parts may not be shown in the figures.
[0030] Many specific details of this application, such as the structure, materials, dimensions, processing techniques, and methods of the components, are described below to provide a clearer understanding of the application. However, as those skilled in the art will understand, this application may be implemented without adhering to these specific details.
[0031] In related technologies, the problem of large train intervals is solved by manual control by dispatchers and train drivers, who then dispatch and insert standby trains at appropriate times. However, in fully automated lines, this method alone has limitations. The different experiences of dispatchers and train drivers lead to inconsistencies in their judgment of when to dispatch standby trains, resulting in inconsistent timing of standby train insertions. If the timing of a standby train insertion is poor, the problem of not effectively shortening large train intervals persists.
[0032] The purpose of this application is to fully consider the timing control of the temporary deployment of standby trains. By analyzing the delay time of trains on the line, the preparation before the deployment of standby trains, and the line location of the standby trains, this application proposes a control method, device, and electronic equipment for the emergency dispatching of standby trains, so as to improve the deployment efficiency of standby trains and the accuracy of the timing control of standby train insertion.
[0033] Please refer to Figure 1 The diagram illustrates a flowchart of a control method for emergency dispatching of backup trains provided in an embodiment of this application. The flowchart mainly includes the following steps: S101 to S107.
[0034] Step S101: Obtain the time interval between the first train and the second train, where the second train is ahead of the first train and the first train is a delayed train.
[0035] Specifically, the system monitors the train's running status in real time and obtains the time interval between each adjacent train traveling in the same direction. This allows the system to determine whether there are large intervals between different adjacent trains. The first train and the second train are any two different adjacent trains traveling in the same direction on the subway line, with the second train located in front of the first train. By obtaining the time interval between the first train and the second train, the system can promptly identify and judge any abnormal intervals that occur during train operation and take corresponding scheduling measures to adjust the schedule, ensuring the orderly and efficient operation of trains. The first train is one that has already experienced a delay. In this embodiment, the method for confirming a train delay is not limited. The method can be as follows: record the time point when the first train experienced a delay and the time point when the first train resumed operation, thereby obtaining the aforementioned delay time period. Determine whether the delay time period is greater than or equal to a preset time period. If the delay time period is greater than or equal to the preset time period, then the first train is a delayed train. The preset time period can be pre-set by the train operator based on factors such as the operating route, passenger flow, and train timetable. Depending on the actual situation, the delay time period can be 3 minutes, 5 minutes, or 10 minutes, and this embodiment does not limit the setting of the preset time period. If the delay time period is less than the preset time period, then the first train is not a delayed train. It should be noted that some trains arriving late is normal. In this embodiment, a delayed train refers to a train that has already experienced a large interval with the preceding train. Therefore, simply because a train experiences a delay does not automatically mean that the train is a delayed train.
[0036] In one possible implementation, step S101 further includes: obtaining the delay time period corresponding to the first train, and obtaining the scheduled train interval; and using the sum of the delay time period and the scheduled train interval as the train interval time period.
[0037] Specifically, the delay time period corresponding to the first train is obtained. The delay time period is the time from the confirmation of the delay of the first train to the resumption of the first train's operation. The planned train schedule interval is obtained. The planned train schedule interval refers to the time interval between the first train and the second train under the premise that there is no delay, according to the predetermined train operation schedule. The planned train schedule is used to ensure the orderly operation of different trains. The planned train schedule can be preset by the train operator based on factors such as the line, traffic volume, and timetable. This embodiment does not limit the setting of the planned train schedule. Then, the sum of the delay time period and the planned train schedule interval is used as the train interval time period, so as to determine whether the first train is a delayed train based on the train interval time period.
[0038] Step S102: Obtain the standby train and the corresponding online time period of the standby train. The online time period is the time period between the first time point and the third time point. The first time point is the time point corresponding to when the first train is confirmed to be a delayed train, and the third time point is the time point corresponding to when the standby train completes the inspection preparation.
[0039] Specifically, when the first train is delayed and a large interval exists between the first and second trains, the availability of a backup train and its corresponding operational timeframe is obtained. This operational timeframe is the period between a first time point and a third time point. The first time point is the time when the delay of the first train is confirmed, and the third time point is the time when the backup train completes its inspection preparations. By obtaining the availability of the backup train and its corresponding operational timeframe, it is possible to ensure that the backup train can be put into operation in a timely manner, thereby shortening the large interval and improving the overall efficiency and order of train operations.
[0040] In one possible implementation, step S102 further includes: obtaining the notification time period corresponding to the standby train and the standby train status corresponding to the standby train, the standby train status including cold standby status and hot standby status, the notification time period being the time period between a first time point and a second time point, the second time point being the time point corresponding to when the standby train begins inspection preparation; if it is confirmed that the standby train status is cold standby status, obtaining the inspection time period, the inspection time period being the time period required for the standby train to change from cold standby status to hot standby status; the sum of the notification time period and the inspection time period being used as the online time period; if it is confirmed that the standby train status is hot standby status, the notification time period being used as the online time period.
[0041] Specifically, the past steps for the backup train's online time period are as follows: First, record the first and second time points. The first time point is the time when the first train began to experience delays, and the second time point is the time when the backup train began its self-inspection. The second time point is located between the first and third time points, and the time period between the first and second time points is used as the notification time period. After receiving information about the delay of the first train, relevant personnel need to perform a series of notification operations, including but not limited to: notifying the dispatcher and notifying the backup train operator, to notify the backup train to prepare for online operation. The time consumed by the above operations is the notification time period. Afterward, it is necessary to obtain the status of the backup train and confirm that the backup train status is in a cold standby state. The status of the standby train is either cold standby or hot standby. If the standby train is confirmed to be in cold standby, it cannot be dispatched for a short period of time. Therefore, a train inspection time period is required. The train inspection time period is the time required for the standby train to switch from cold standby to hot standby. During this time period, a series of train inspection operations will be performed, including but not limited to: standby train system wake-up, standby train self-test, and standby train communication function check, to switch the standby train from cold standby to hot standby. The sum of the notification time period and the train inspection time period is used as the online time period. If the standby train is confirmed to be in hot standby, the standby train does not need to undergo a series of train inspection operations. The standby train is ready at any time and can be directly put into service. In this case, the train inspection time period is zero, so the notification time period can be used directly as the online time period. It should be noted that during the train inspection process, abnormal situations may occur during the backup train inspection. For example, when the communication function of the backup train is abnormal, it is necessary to repair the communication function of the backup train. The time required for the backup train to repair the abnormality is also included in the train inspection time period. Furthermore, if the train fails to successfully repair the abnormality, and there are other backup trains, the same train inspection operation needs to be performed on the other backup trains. In this case, the sum of the time periods of all backup trains that have undergone train inspection operation is taken as the aforementioned train inspection time period.
[0042] Step S103: Determine whether the online time period meets the preset time conditions.
[0043] Specifically, the availability of backup trains can be determined by assessing whether the online time period meets preset time conditions.
[0044] In one possible implementation, step S104 further includes: obtaining the resumption of operation time period corresponding to the first train, wherein the resumption of operation time period is the time period between the departure time and the arrival time, the departure time is the time point corresponding to the resumption of operation of the first train, and the arrival time is the running time of the first train when the arrival time is the time point when the standby train is inserted; and determining whether the online time period meets the preset time condition according to the following inequality:
[0045]
[0046] Among them, T 发 For the departure time, T 进 If T is the arrival time, then 进 -T 发 To restore the running time period, t 总间隔 The time interval between train runs, t 检 For vehicle inspection time periods, t 通知 If t is the notification period, then 检 +t 通知 The online time period is defined as the time period during which the online time period is launched. If the online time period satisfies the above inequality, then the online time period is confirmed to meet the preset time conditions.
[0047] Specifically, determining whether the time period for the standby train to go online meets the preset time conditions requires full consideration of the timing control of the standby train's temporary deployment. The specific steps are as follows: First, obtain the resumption time period corresponding to the first train. The resumption time period is the time period between the departure time and the arrival time. The departure time is the time point corresponding to the resumption of the first train's operation, and the arrival time is the running time of the first train when the standby train inserts after the first train has resumed operation. Since this embodiment is based on the premise that the delayed train can resume operation, under this condition, the optimal time for the standby train to operate is when the average point of the long headway coincides with the preset insertion point of the standby train. Therefore, when the long headway shifts to the preset insertion point of the standby train, if the time period for the standby train to go online satisfies the following inequality, it can be determined that the time period for going online meets the preset time conditions:
[0048]
[0049] Among them, T 发 For the departure time, T 进 If T is the arrival time, then 进 -T 发 To restore the running time period, t 总间隔 The time interval between train runs, t 检 For vehicle inspection time periods, t 通知 If t is the notification period, then 检 +t 通知 This refers to the online time period; since the train interval is the sum of the delay time period and the planned train interval, i.e., t... 总间隔 =t 延 +t 行车间隔 , where t 延 To delay the time period, t 行车间隔 The planned train travel intervals are given; the final inequality is:
[0050] T 进 -T 发 +(t 延 +t 行车间隔 ) / 2≥t 检 +t 通知 ;
[0051] If the online time period satisfies the above inequality, then the online time period is confirmed to meet the preset time condition; if the online time period does not satisfy the above inequality, the online time of the standby train needs to be adjusted until the above preset time condition is met; if the preset time condition is still not met after adjusting the online time of the standby train, then it is confirmed that the standby train cannot be put into service, and the large headway between the first train and the second train can be reduced by other means. Other means include, but are not limited to: detaining the train, multiple stops, skipping stops, speed-limited pre-station turnaround, single-track bidirectional operation, short-route turnaround, and track pulling. The above other means are not within the scope of discussion in this embodiment, so this embodiment does not limit the above other means.
[0052] Step S104: If the online time period corresponding to the standby train meets the preset time conditions, then obtain the preset insertion point corresponding to the standby train.
[0053] Specifically, if the online time period corresponding to the standby train meets the preset time conditions through the inequality in step S103, it is also necessary to obtain the preset insertion point corresponding to the standby train so as to more fully determine whether the timing of the standby train's temporary online operation is appropriate in combination with the line location of the standby train.
[0054] Step S105: Determine whether the preset insertion point meets the preset insertion conditions.
[0055] Specifically, by determining whether the preset insertion point meets the preset insertion conditions, it is possible to more fully determine whether the standby train can be put into operation.
[0056] In one possible implementation, step S106 further includes: obtaining first position information corresponding to a preset insertion point, obtaining second position information corresponding to a first train, wherein the second position information is the position information corresponding to the first train when the standby train completes inspection preparation; determining whether the first position information is located in front of the first position information; if the first position information is located in front of the second position information, then confirming that the preset insertion point meets the preset insertion conditions.
[0057] Specifically, the system obtains the first position information corresponding to the preset insertion point of the standby train, and obtains the second position information corresponding to the first train. The second position information is the position information corresponding to the position of the first train when the standby train completes its inspection preparation. Then, based on the direction of travel of the first train, it determines whether the first position information is ahead of the first position information. If the first position information is ahead of the second position information, it is confirmed that the preset insertion point meets the preset insertion conditions. At this time, the standby train meets all the conditions for going online, and the accuracy of the timing control of the standby train insertion is relatively high, which can effectively shorten the large train interval between the first train and the second train.
[0058] Step S106: If the preset insertion point meets the preset insertion conditions, then insert the spare train at the preset insertion point.
[0059] Specifically, when the online time period meets the preset time condition and the preset insertion point meets the preset insertion condition, a standby train is inserted at the preset insertion point, such as... Figure 2a As shown, this diagram illustrates a backup train insertion timing according to an embodiment of this application. In this diagram, 21 is the delayed train, 22 is the train preceding the delayed train 21, 23 is the backup train, 24 and 25 are the train routes, with 24 being the up-line route and 25 the down-line route. 26 is the insertion point for the backup train. 201-204 are the platforms passed by the delayed train 21, the preceding train 22, and the backup train 23 along their routes, corresponding to platforms A through D respectively. The delayed train 21, the preceding train 22, and the backup train 23 all travel in the direction of the arrows on the routes. Figure 2a If a large gap is formed between trains 21 and 22, and train 22 arrives at platform A 201 and turns around while the delayed train 21 is traveling on the up-line 24, then train 23 prepares to pass through the insertion point 26 to fill the large gap between the delayed train 21 and the preceding train 22; Figure 2b As shown, it presents another schematic diagram of the timing of the insertion of a standby train provided in the embodiment of this application. In this diagram, the delayed train 21 resumes operation, and the standby train 23 has been put into operation to fill the large train interval. At this time, the delayed train 21 has not yet traveled to the insertion point 26 of the standby train 23.
[0060] like Figure 3 As shown, it presents a schematic diagram of the timing of the backup train insertion provided in the application embodiment. The horizontal axis represents the stations the train passes through, the vertical axis represents time, train A is the first train, and train B is the second train. Furthermore, traveling from G to A is a downhill journey, and traveling from A to G is an uphill journey. Assuming train A arrives at C at time a and train B arrives at C at time b, the time interval ab can be considered as t. 行车间隔This refers to the planned train travel time interval. Assuming that train A experiences a delay at point C and resumes operation at time c, then time point c is T. 发 That is, the time point when it opens, as shown in the figure. To delay the departure time of the train heading south from station C, and the time interval between b and c is t. 延 If the delay period is t, then the time period of ac is t. 总间隔 That is, the time interval between trains. Assuming the preset insertion point is B, and the standby train can depart from the preset insertion point at time d, then the time interval bd is t. 检 +t 通知 That is, the online time period. If the standby train is already in hot standby mode, then t 检 =0; At this time, if car A turns upward after reaching A, and arrives at B at time point e, then time point e is T. 进 That is, the time of entry into the station, as shown in the figure. To delay the arrival time of the train when it travels northbound at station B.
[0061] This application, by employing the aforementioned method, accurately acquires and analyzes the time intervals between trains by monitoring their operating status in real time. This allows for timely identification and judgment of large intervals between different trains. Furthermore, by analyzing factors such as train delays on the line, the preparation status of standby trains before their deployment, and the line location of the standby trains, the optimal timing for the standby trains to be deployed within large intervals can be determined. This effectively shortens large intervals, thereby improving the efficiency of standby train deployment and the accuracy of standby train deployment timing control.
[0062] Please refer to Figure 4 This document illustrates a schematic diagram of a control device for emergency dispatching of backup trains according to an embodiment of this application. The device includes a train interval acquisition module 41 and a backup train deployment module 42.
[0063] The train interval acquisition module 41 is used to acquire the train interval time period between the first train and the second train, where the second train is located in front of the first train and the first train is a delayed train.
[0064] The standby train deployment module 42 is used to obtain the standby train and its corresponding deployment time period. The deployment time period is the time period between the first time point and the third time point. The first time point is the time point corresponding to when the first train begins to experience delays, and the third time point is the time point corresponding to when the standby train is ready to start. It determines whether the deployment time period meets the preset time conditions. If the deployment time period corresponding to the standby train meets the preset time conditions, it obtains the preset insertion point corresponding to the standby train. It then determines whether the preset insertion point meets the preset insertion conditions. If the preset insertion point meets the preset insertion conditions, it inserts the standby train at the preset insertion point.
[0065] In one possible implementation, the train interval acquisition module 41 is used to acquire the train interval time period between the first train and the second train, specifically including: acquiring the delay time period corresponding to the first train, and acquiring the planned time interval; and using the sum of the delay time period and the planned time interval as the train interval time period.
[0066] In one possible implementation, the standby train deployment module 42 is used to obtain the deployment time period corresponding to the standby train, specifically including: obtaining the notification time period corresponding to the standby train and the standby train status corresponding to the standby train, the standby train status including cold standby status and hot standby status, the notification time period being the time period between a first time point and a second time point, the second time point being the time point corresponding to when the standby train starts self-inspection; if it is confirmed that the standby train status is cold standby status, obtaining the vehicle inspection time period, the vehicle inspection time period being the time period required for the standby train to change from cold standby status to hot standby status; and using the sum of the notification time period and the vehicle inspection time period as the deployment time period.
[0067] In one possible implementation, the standby train online module 42 is used to, after obtaining the notification time period and the standby train status corresponding to the standby train, further include: if it is confirmed that the standby train status is hot standby, using the notification time period as the online time period.
[0068] In one possible implementation, the standby train deployment module 42 is used to determine whether the deployment time period meets a preset time condition. Specifically, this includes: obtaining the resumption time period corresponding to the first train, where the resumption time period is the time between the departure time and the arrival time, the departure time is the time corresponding to the resumption of the first train's operation, and the arrival time is the running time of the first train when the standby train is inserted; and determining whether the deployment time period meets the preset time condition based on the following inequality:
[0069]
[0070] Among them, T 发 For the departure time, T 进If T is the arrival time, then 进 -T 发 To restore the running time period, t 总间隔 The time interval between train runs, t 检 For vehicle inspection time periods, t 通知 If t is the notification period, then 检 +t 通知 The online time period is defined as the time period during which the online time period is launched. If the online time period satisfies the above inequality, then the online time period is confirmed to meet the preset time conditions.
[0071] In one possible implementation, the standby train deployment module 42 is used to determine whether the preset insertion point meets the preset insertion conditions. Specifically, it includes: obtaining first position information corresponding to the preset insertion point, obtaining second position information corresponding to the first train, wherein the second position information is the position information corresponding to the first train when the standby train completes inspection preparation; determining whether the first position information is located in front of the first position information; if the first position information is located in front of the second position information, then confirming that the preset insertion point meets the preset insertion conditions.
[0072] In one possible implementation, the first train, the second train, and the spare train are trains traveling in the same direction.
[0073] Based on the same inventive concept, embodiments of this application also provide an electronic device. Figure 5 This is a schematic diagram of the structure of an electronic device provided in an embodiment of this application, such as... Figure 5 As shown, this application embodiment provides an electronic device including: one or more processors 501, a memory 502, and one or more I / O interfaces 503. The memory 502 stores one or more programs, which, when executed by the one or more processors, enable the one or more processors to implement a control method for the emergency dispatching of backup trains as described in any of the above embodiments; the one or more I / O interfaces 503 are connected between the processor and the memory, configured to enable information interaction between the processor and the memory.
[0074] Among them, processor 501 is a device with data processing capabilities, including but not limited to central processing unit (CPU); memory 502 is a device with data storage capabilities, including but not limited to random access memory (RAM, more specifically SDRAM, DDR, etc.), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory (FLASH); I / O interface (read-write interface) 503 is connected between processor 501 and memory 502, and can realize information interaction between processor 501 and memory 502, including but not limited to data bus (Bus).
[0075] In some embodiments, the processor 501, memory 502, and I / O interface 503 are interconnected with the communication bus 504, thereby connecting to other components of the computing device.
[0076] In some embodiments, the one or more processors 501 include a field-programmable gate array.
[0077] According to embodiments of this application, a computer-readable medium is also provided. This computer-readable medium stores a computer program, wherein when executed by a processor, the program implements the steps of the control method for activating emergency dispatch of backup trains as described in any of the above embodiments.
[0078] Specifically, according to embodiments of this application, the processes described above with reference to the flowcharts can be implemented as computer software programs. For example, embodiments of this application include a computer program product comprising a computer program carried on a machine-readable medium, the computer program containing program code for performing the methods shown in the flowcharts. In such embodiments, the computer program can be downloaded and installed from a network via a communication component, and / or installed from a removable medium. When the computer program is executed by a central processing unit (CPU), it performs the functions defined above in the system of this application.
[0079] It should be noted that the computer-readable medium shown in this application can be a computer-readable signal medium or a computer-readable storage medium, or any combination of the two. A computer-readable storage medium can be, for example,—but not limited to—an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination thereof. More specific examples of a computer-readable storage medium may include, but are not limited to: an electrical connection having one or more wires, a portable computer disk, a hard disk, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM or flash memory), optical fiber, portable compact disk read-only memory (CD-ROM), optical storage device, magnetic storage device, or any suitable combination thereof. In this application, a computer-readable storage medium can be any tangible medium containing or storing a program that can be used by or in conjunction with an instruction execution system, apparatus, or device. In this application, a computer-readable signal medium can include a data signal propagated in baseband or as part of a carrier wave, carrying computer-readable program code. Such propagated data signals can take various forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination thereof. Computer-readable signal media can also be any computer-readable medium other than computer-readable storage media, which can send, propagate, or transmit a program for use by or in connection with an instruction execution system, apparatus, or device. The program code contained on the computer-readable medium can be transmitted using any suitable medium, including but not limited to: wireless, wire, optical fiber, RF, etc., or any suitable combination thereof.
[0080] The flowcharts and block diagrams in the accompanying drawings illustrate the architecture, functionality, and operation of possible implementations of systems, methods, and computer program products according to various embodiments of this application. In this regard, each block in a flowchart or block diagram may represent a module, segment, or portion of code containing one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions indicated in the blocks may occur in a different order than those indicated in the drawings. For example, two consecutively indicated blocks may actually be executed substantially in parallel, and they may sometimes be executed in reverse order, depending on the functions involved. It should also be noted that each block in the block diagrams and / or flowcharts, and combinations of blocks in the block diagrams and / or flowcharts, can be implemented using a dedicated hardware-based system that performs the specified function or operation, or using a combination of dedicated hardware and computer instructions.
[0081] The circuits or sub-circuits described in the embodiments of this application can be implemented in software or hardware. The described circuits or sub-circuits can also be housed in a processor; for example, it can be described as: a processor including: a receiving circuit and a processing circuit, the processing module including a writing sub-circuit and a reading sub-circuit. The names of these circuits or sub-circuits do not necessarily limit the circuit or sub-circuit itself; for example, a receiving circuit can also be described as "receiving video signals".
[0082] It is understood that the above embodiments are merely exemplary implementations used to illustrate the principles of this application, and this application is not limited thereto. For those skilled in the art, various modifications and improvements can be made without departing from the spirit and substance of this application, and these modifications and improvements are also considered to be within the scope of protection of this application.
Claims
1. A control method for emergency dispatching of a standby train, characterized in that: The method comprises: Obtaining a travel interval time period between a first train and a second train, wherein the second train is located ahead of the first train and the first train is a delayed train; Obtaining a standby train and an online time period corresponding to the standby train, the online time period being a time period between a first time point and a third time point, the first time point being a time point corresponding to when the first train begins to be delayed, and the third time point being a time point corresponding to when the standby train is ready to start; Determine whether the online time period meets the preset time condition; If the online time period corresponding to the standby train meets the preset time condition, obtaining the preset insertion point corresponding to the standby train; Determining whether the preset insertion point meets a preset insertion condition; If the preset insertion point meets the preset insertion condition, the spare train is inserted at the preset insertion point.
2. The method according to claim 1, characterized in that The obtaining of the interval time period between the first train and the second train specifically includes: Obtaining the delay time period corresponding to the first train, and obtaining the driving time interval of the planned operation diagram; The sum of the delay time period and the driving time interval of the planned operation diagram is taken as the driving interval time period.
3. The method according to claim 1, characterized in that The obtaining of the online time period corresponding to the standby train specifically includes: Acquire a notification time period corresponding to the standby train and a standby train state corresponding to the standby train, wherein the standby train state includes a cold standby state and a hot standby state, the notification time period is a time period between the first time point and a second time point, and the second time point is a time point corresponding to when the standby train starts self-inspection; If it is confirmed that the state of the standby train is the cold standby state, obtaining a vehicle inspection time period, where the vehicle inspection time period is a time period required for the standby train to change from the cold standby state to the hot standby state; The sum of the notification time period and the vehicle inspection time period is used as the online time period.
4. The method according to claim 3, characterized in that After acquiring the notification time period corresponding to the standby train and the standby train status corresponding to the standby train, the method further includes: If the state of the standby train is confirmed to be the hot standby state, the notified time period is used as the online time period.
5. The method according to claim 3, characterized in that: The determining whether the online time period meets the preset time condition specifically includes: Obtaining a resumption time period corresponding to the first train, the resumption time period being a time period between a departure time point and an entry time point, the departure time point being a time point corresponding to when the first train resumes operation, and the entry time point being an operation time of the first train when the standby train is inserted; Whether the online time period meets the preset time condition is determined according to the following inequality: Among them, T 发 is the opening time point, T 进 is the entry time point, then T 进 -T 发 is the recovery time period, t 总间隔 is the driving interval time period, t 检 is the vehicle inspection time period, t 通知 is the notification time period, then t 检 +t 通知 is the online time period; If the online time period satisfies the above inequality, it is confirmed that the online time period satisfies the preset time condition.
6. The method according to claim 1, characterized in that The determining whether the preset insertion point satisfies the preset insertion condition specifically includes: Acquire the first position information corresponding to the preset insertion point, and acquire the second position information corresponding to the first train, wherein the second position information is the position information corresponding to the first train when the standby train completes the vehicle inspection preparation; determining whether the first position information is located in front of the first position information; If the first position information is located in front of the second position information, it is confirmed that the preset insertion point meets the preset insertion condition.
7. The method according to claim 1, characterized in that The first train, the second train and the spare train are trains traveling in the same direction.
8. A control device for emergency dispatch of standby trains, characterized in that: The device comprises a train interval acquisition module and a standby train on-line module, wherein: The train interval acquisition module is used to acquire the train interval time period between a first train and a second train, the second train is located in front of the first train, and the first train is a delayed train; The standby train online module is used to obtain a standby train and the online time period corresponding to the standby train, the online time period being the time period between a first time point and a third time point, the first time point being the time point corresponding to when the first train begins to be delayed, and the third time point being the time point corresponding to when the standby train is ready to start; judging whether the online time period meets a preset time condition; if the online time period corresponding to the standby train meets the preset time condition, obtaining a preset insertion point corresponding to the standby train; judging whether the preset insertion point meets the preset insertion condition; if the preset insertion point meets the preset insertion condition, inserting the standby train at the preset insertion point.
9. An electronic device, wherein: It includes one or more processors, a memory, an I / O interface and a communication bus, wherein the memory is used to store one or more programs; When the one or more programs are executed by the one or more processors, the one or more processors implement the method as claimed in any one of claims 1 to 7.
10. A computer readable medium having a computer program stored thereon, wherein: When the computer program is executed by a processor, the steps in the method according to any one of claims 1 to 7 are implemented.