Underground diaphragm wall construction auxiliary system and method
By integrating a joint removal device with sensing elements and an adjustable expansion bladder on the joint box, real-time monitoring of concrete stress and adjustment of the anti-bypass components solve the problem of difficulty in dismantling the joint box and anti-bypass effect, and realize the construction of underground diaphragm walls. efficiency and safety.
Patent Information
- Application Number
- CN202411024888.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-10-25
AI Technical Summary
It is difficult to effectively dismantle the joint box when using the existing technology to prevent concrete flow around the construction of underground diaphragm walls. Moreover, the anti-blow-around component is bonded to the concrete after solidification, making it more difficult to dismantle, and cannot dynamically adapt to changes in concrete stress.
A joint removal device including a sensing element and an adjustable expansion bladder is used to monitor concrete stress changes in real time, automatically adjust the shape and pressure of the anti-blow-around component, and combine the stripping unit and lifting unit to ensure that the joint box is successfully removed at the right time. .
It effectively prevents concrete from flowing around, simplifies the joint box dismantling process, reduces construction difficulty, improves construction efficiency and safety, and ensures the stability and overall performance of the underground diaphragm wall.
Smart Images

Figure CN118835591A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of underground continuous wall construction, and in particular to an underground continuous wall construction auxiliary system and method. Background Art
[0002] Diaphragm Wall technology plays a vital role in urban underground projects, especially in the construction of key projects such as rail transit hubs, multi-story building foundations and hydraulic structures. This technology covers a series of processes such as trench excavation, steel cage hoisting and concrete pouring, aiming to build a protective barrier composed of continuous reinforced concrete wall panels. When pouring concrete in the underground continuous wall, a joint box is set on one side of the trench to be poured as a template device, and the rear of the joint box is the trench that has not yet been excavated.
[0003] The use of joint boxes for joint casting is a key step in ensuring a firm connection between adjacent wall panels, which is essential for the stability and continuity of underground continuous wall structures. However, the problem of concrete bypass is often faced during construction. If the concrete injection is not properly controlled, the concrete may bypass along the edge of the joint box instead of evenly filling the entire space, resulting in uneven concrete distribution at the wall joints, affecting the density and overall strength of the wall. Unevenly distributed concrete may form weak points in the wall, increasing the risk of structural failure, especially when subjected to high pressure or groundwater flow. In addition, after the bypassed concrete slurry solidifies and hardens, it will increase the difficulty of removing the joint box from the structure, which may cause defects in the underground continuous wall in severe cases.
[0004] In order to solve the problem of concrete bypass, the existing technology sets an anti-bypass structure at the contact point between the joint box and the slot wall to reduce the risk of bypass. The anti-bypass structure blocks the gap between the joint box body and the side wall of the slot section to prevent concrete from bypassing to the back of the joint box. However, this technical solution does not fully consider that the anti-bypass structure itself may be fixed by the solidified concrete. Although the anti-bypass structure effectively prevents bypass and fixes the joint box body in the slot section by the unhardened concrete, the anti-bypass structure is still more difficult to remove the joint box from the slot section because it is fixed by the concrete.
[0005] CN110284493A discloses a lateral stripping joint device and a construction method thereof, wherein the device comprises: a joint box, comprising a bottom plate and a cover plate which are arranged opposite to each other and connected to each other through a pair of side plates, the cover plate is provided with a pair of through holes, the bottom plate and the cover plate are arranged vertically, and a retaining structure is vertically fixed to the outer side surface of the side plate; a pair of jacks which are built into the joint box and whose bottoms are vertically fixed to the bottom plate, the pair of jacks are symmetrically arranged relative to the center of the joint box, the tops of the jacks can correspond to the through holes penetrated in the cover plate, and a sealing layer is provided between the jacks and the through holes of the cover plate; a pair of oil circuits which are connected between the corresponding jacks and the hydraulic station to control the corresponding jacks to push out of the cover plate.
[0006] This patent vertically fixes a retaining structure on the outer side of the side plate to retain concrete and prevent concrete from pouring around when pouring the trough section. By setting multiple pairs of jacks on the cover plate surface of the joint box, the upper jack is used to first separate the upper part of the joint box from the upper end surface of the trough section, and the lower jack is used to separate the lower part of the joint box from the lower end surface of the trough section, so that the joint box can be peeled off from the solidified concrete in the trough section, and then the joint box can be finally lifted out through the lifting device.
[0007] However, although the retaining structure of the patent can effectively prevent the bypass of concrete, it is designed to form a bent surface on the side panel and form a mortise and tenon structure with the side wall of the groove section. This causes the concrete to gradually adhere to the edge and corner areas of the retaining structure during the solidification process, and finally fix it after solidification, thereby increasing the difficulty of removing the joint box.
[0008] Therefore, in order to improve this design, a new type of joint box removal equipment needs to be developed. This equipment can not only effectively prevent bypass flow when the concrete has not yet solidified and hardened, but also has movable characteristics on both sides when removing the joint box, so that it can be more easily removed from the solidified concrete.
[0009] In addition, on the one hand, there are differences in understanding among those skilled in the art; on the other hand, the applicant studied a large number of documents and patents when making the present invention, but due to space limitations, not all details and contents are listed in detail. However, this does not mean that the present invention does not have the characteristics of these prior arts. On the contrary, the present invention already has all the characteristics of the prior art, and the applicant reserves the right to add relevant prior art to the background technology. Summary of the invention
[0010] The prior art has already presented a technical solution to solve the difficulty of stripping the joint box caused by the bypass phenomenon during the pouring process. For example, the patent document CN118292495A discloses an improved method for preventing bypass flow of the joint box of the rubber water stop strip of the underground continuous wall, including: making underground continuous wall section marks on the guide wall according to the design drawings, configuring the mud, and sinking the groove machine; processing the joint box in combination with the ultrasonic detection data; pouring concrete; after the concrete pouring is completed, the joint box is stripped, and the stripping is performed by gently pushing the joint box with a groove machine until a gap appears between the joint box and the concrete surface, and then pulling it out after 24 hours; wherein the joint box includes a joint box body and brushes arranged on both sides of the joint box body. On the one hand, the brush structure in the technical solution is designed to isolate the bypass flow of concrete, but its shape is fixed and cannot be adjusted accordingly according to the stress changes shown by the concrete at different solidification stages, which is different from the anti-bypass component of the present invention that can adjust the shape and pressure in response to the changes in stress data. This limitation means that although the brush structure can play an isolation role to a certain extent, it cannot dynamically adapt to the complex mechanical behavior of concrete during the solidification process. In contrast, the anti-bypass assembly proposed in the present invention has significant advantages. It can be intelligently adjusted according to the real-time monitored stress data to adapt to the stress changes of concrete in different solidification stages. Specifically, the anti-bypass assembly in the present invention adopts a sensor element that obtains the internal stress change data of concrete, which can capture the stress state of concrete in real time. The system automatically adjusts the shape and applied pressure of the anti-bypass assembly according to the received data. This intelligent adjustment mechanism enables the anti-bypass assembly to adapt to the physical properties of concrete more accurately, thereby providing the best isolation effect at different stages. On the other hand, the stripping unit in this technical solution only performs the stripping process of the joint box under specific time conditions. The stripping unit does not have a connection relationship with other external components (such as the anti-bypass assembly), resulting in its specific stripping action being unable to adapt to the changes in the internal stress data of the concrete, and thus unable to ensure that the joint box is stripped at the right time, and unable to avoid construction quality problems caused by stripping too early or too late.
[0011] In view of the deficiencies of the prior art, the present invention provides an underground continuous wall construction auxiliary system and method to solve at least part of the above-mentioned technical problems.
[0012] The present invention relates to an underground continuous wall construction auxiliary system, which includes a joint box, which is temporarily placed at the end of an underground continuous wall groove section; a joint removal device, including a stripping unit and a lifting unit for removing the joint box from the groove section. The side of the joint box is equipped with an anti-circumference component for preventing concrete from flowing around, and the anti-circumference component is equipped with a sensor element for obtaining stress change data inside the concrete. In response to the change of stress data, the stripping unit connected to the sensor element can generate and execute corresponding work plans at different coagulation stages of the concrete to control the joint box to complete the work links before formal stripping. The lifting unit can be connected to the joint box to pull the joint box out of the groove section after the formal stripping is completed.
[0013] The underground continuous wall construction auxiliary system of the present invention can greatly simplify and accelerate the joint box removal process during the construction of the underground continuous wall by introducing a joint removal device, especially a combination of a stripping unit and a lifting unit. The stripping unit can intelligently adjust the work plan based on the internal stress change data of the concrete to ensure that the joint box is stripped at the right time, avoiding construction problems caused by premature or late stripping. The design of the anti-circumference component effectively prevents the concrete circumference phenomenon and ensures the integrity and stability of the underground continuous wall. At the same time, the sensor element can obtain the internal stress change data of the concrete in real time, provide accurate work guidance for the stripping unit, and ensure the stability and safety of the joint box during the stripping process. The system of the present invention uses the data obtained by the sensor element, combined with the intelligent control of the stripping unit, to realize the intelligent management of the stripping process of the joint box. Before the formal stripping, the stripping unit can automatically adjust the work plan according to the changes in the internal stress data of the concrete, avoiding the safety risks caused by blind operation. At the same time, the design of the lifting unit also ensures the stability and safety of the joint box during the extraction process, further enhancing the safety of the construction.
[0014] According to a preferred embodiment, the bypass prevention component is configured as a double-layer detachable hollow expansion bladder matching the length of the joint box, the expansion bladder includes an inner bladder body and an elastic outer bladder body covered on the surface of the inner bladder body, the stripping unit includes a first control component for injecting or extracting a fluid medium into the inner bladder body, and the first control component for executing the working scheme changes the distance between the outer wall of the outer bladder body and the groove wall of the underground continuous wall groove section in a manner that increases or decreases the internal pressure of the inner bladder body. The prior art has already seen bypass prevention components that can change their shape. For example, the patent document CN219930972U discloses an end form device for ground-connected wall casting construction, which is composed of two side end formworks with connecting mechanisms, and these connecting mechanisms are equipped with water-filled or air-filled bladders. In addition, a bypass prevention structure for ground-connected wall concrete is also disclosed, which includes a slot well and a steel cage, and is used in combination with the above-mentioned end form device. The steel cage is located in the slot well, the end formwork is installed at the end of the steel cage, and the bladder is located between the end formwork and the side wall of the slot well. This technical solution can effectively fill the gap between the end formwork and the side wall of the slot, prevent the concrete of the ground-connected wall from bypassing along the gap of the slot wall, reduce the risk of handling the bypass concrete during the construction of the adjacent sections of the ground-connected wall, and facilitate the placement of the adjacent sections of the steel cage. However, the bladder in this technical solution is sealed only by one-time inflation or water filling, and does not provide the function of multiple inflation pressure adjustment to adapt to the anti-bypass of the continuous wall and the removal of the joint box. When meeting the need for effective sealing of the slot wall gap, the solution requires the application of sufficient inflation pressure, which will lead to a closer contact between the airbag and the concrete, thereby increasing the difficulty of unpacking after the concrete solidifies. This is contrary to the goal of the present invention to create favorable conditions for the removal of the joint box, and even provides an opposite technical direction. In addition, although these anti-bypass components can prevent concrete from bypassing to the back of the joint box to a certain extent, since the length of the joint box may reach tens of meters, there are significant differences in the concrete pressure it is subjected to at different depths. The existing anti-bypass components do not take into account the pressure changes caused by the depth, and therefore cannot provide corresponding counterpressure or support. This design limitation may lead to uneven structural strength of the continuous wall in certain areas, affecting its overall structural performance. In addition, the current anti-circumvention components lack a mechanism for adaptively adjusting their shape according to the degree of concrete solidification, which may cause these components to be fixed in place during the concrete hardening process, increasing the difficulty of removing the joint box in the future. To this end, the present invention can make the outer bladder body fit tightly against the groove wall by adjusting the internal pressure of the inner bladder body, effectively preventing concrete circumvention and ensuring the construction quality of the underground continuous wall. Since the expansion bladder is detachable, its length can be adjusted according to actual needs to adapt to joint boxes and groove sections of different lengths. At the same time, the size and tightness of the expansion bladder can be flexibly adjusted through the first control component. The elastic outer bladder body can fit tightly against the groove wall when the internal pressure is increased, effectively avoiding the circumvention of concrete. At the same time, it can gradually return to its original state when the internal pressure is reduced, avoiding scratches caused by rubbing against the groove wall when the joint box is taken out.In addition, the design of the outer bladder needs to take into account the difference in internal pressure required by the inner bladder at different heights in different soil layers. The outer bladder can use materials with different elastic deformation amounts in the part corresponding to the upper inner bladder and the part corresponding to the lower inner bladder, so that the deformation capacity of the entire outer bladder on the height scale is different. In addition, when the joint box is used in the anti-bypass flow of water-rich sand layers, the outer bladder is preferably made of a material with a larger elastic deformation amount than in soft soil layers.
[0015] According to a preferred embodiment, the working scheme generated by the stripping unit includes: when the sensing element obtains that the internal stress of the concrete reaches the first threshold value at which the bypass characteristic disappears, the first control component adjusts the internal pressure of the inner bladder to the first pressure; when the sensing element obtains that the internal stress of the concrete reaches the second threshold value that satisfies the removal condition of the joint box, the first control component adjusts the internal pressure of the inner bladder to the second pressure. Unlike the prior art, the expansion component of the present invention can adjust its corresponding internal pressure according to the concrete stress monitored by the sensor. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to effectively prevent the concrete from bypassing while reducing the difficulty of removing the joint box. In order to prevent the concrete from bypassing in the joint area, it is usually necessary to apply sufficient pressure to the airbag or hydraulic hose in the gap between the side of the joint box and the groove wall of the underground construction section to ensure that they can fit the groove wall tightly. However, as the concrete solidifies, these anti-circulation components will bond more tightly to the concrete, which will greatly increase the difficulty of removing the joint box. In other words, the pressure required for concrete anti-circulation and the pressure required for removing the joint box are contradictory. The prior art has not solved how to adjust the internal pressure of the expansion assembly according to the changes in the concrete solidification process to simultaneously meet the dual requirements of preventing bypass flow and facilitating removal. The present invention proposes a solution to this problem. Through automated monitoring and intelligent response mechanisms, the stripping unit can accurately judge the different stages of concrete solidification, so as to strip the joint box at the most appropriate time. This avoids construction problems caused by stripping too early or too late, and improves overall construction efficiency.
[0016] According to a preferred embodiment, a plurality of jacks are arranged along the height direction of the front of the joint box, and the top surface of the jacks is in direct contact with the concrete. When the joint box is formally stripped, a plurality of jacks located near the bottom of the joint box are started after a plurality of jacks located near the top of the joint box, so that the joint box first separates its top from the concrete and then separates its bottom. The plurality of jacks arranged along the height direction of the front of the joint box ensure that the contact force is more evenly distributed during the separation operation from the concrete, avoiding direct impact or pressure concentration on the concrete, effectively reducing the damage of the concrete such as cracking and breaking caused by external forces, and maintaining the integrity and strength of the structure. In addition, when formally stripped, the jack located near the top of the joint box is started first, so that the relatively easy-to-strip top of the joint box is separated from the concrete first, and then the jack located at the bottom is started to separate the relatively difficult-to-strip bottom. This sequential operation makes the stripping process more orderly and efficient.
[0017] According to a preferred embodiment, the working steps of the junction box include, in chronological order, an anti-bypass step, a stripping preparation step, a formal stripping step and a lifting step, wherein, when entering the anti-bypass step, the first control component adjusts the internal pressure of the inner capsule to the initial pressure; when entering the stripping preparation step, the first control component adjusts the internal pressure of the inner capsule to the first pressure; when entering the formal stripping step, the first control component adjusts the internal pressure of the inner capsule to the second pressure, and successively starts the jacks arranged at different heights of the junction box; when entering the lifting step, the lifting unit connected to the junction box is started.
[0018] When entering the anti-circumference link, the first control component adjusts the internal pressure of the inner bladder to the initial pressure. This step effectively ensures the initial state of the anti-circumference component, so that the outer wall of the expansion bag is closely attached to the groove wall of the underground continuous wall groove section, thereby preventing concrete from circumferential flow and ensuring the construction quality. When entering the stripping preparation link, the first control component adjusts the internal pressure of the inner bladder to the first pressure. This adjustment helps to prepare for the subsequent stripping operation while maintaining the anti-circumference effect. The setting of the first pressure allows the outer bladder to maintain a certain degree of tightness while also providing sufficient flexibility for subsequent stripping. In the formal stripping link, the first control component adjusts the internal pressure of the inner bladder to the second pressure, and successively starts the jacks configured at different heights of the joint box. Such an operation ensures that after the concrete reaches the appropriate strength, the joint box and the concrete are smoothly and orderly stripped by adjusting the internal pressure of the inner bladder and the order of using the jacks. This operation method not only ensures construction efficiency, but also reduces damage to the concrete structure and the anti-circumference component itself. When entering the lifting link, the lifting unit connected to the joint box is started to pull the stripped joint box out of the groove section. This step marks the completion of the stripping work. The activation of the lifting unit ensures that the joint box can leave the construction area safely and quickly, creating conditions for subsequent construction work.
[0019] According to a preferred embodiment, at least two sections of inner bladders at different heights are arranged inside the outer bladder. In the bypass prevention link and the stripping preparation link, the first control component will determine the independent pressure size and pressure adjustment timing for the upper and lower inner bladders according to the geological parameters associated with the stratum in which the joint box is embedded and the permeability parameters of the concrete relative to the stratum. Different from the prior art, the bladder in the expansion assembly of the present invention is a two-stage structure in height, and each section of the bladder can independently adjust its internal pressure according to the stress generated by the concrete at different depths. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to provide matching counterpressure or supporting force according to the change of concrete pressure at different depths to achieve a relatively consistent bypass prevention effect. Since the pressure and density of the bottom area of the soft soil stratum increase with depth, the possibility of bypass in the bottom area is low. The first control component sets a relatively low second pressure for the lower inner bladder to cope with this characteristic. At the first time, the first pressure of the upper inner bladder is high to ensure the stability of the upper area. However, as time goes by (at the second time), the soil layer will be squeezed and deformed by the bladder of the first pressure, which will cause the first pressure to decrease over time. In soft soil layers, this rate of change is relatively gentle, so at the second time, the first control component will adjust the pressure of the bladder in the upper section according to the actual situation to maintain the required stability. In water-rich sand layers, due to large voids and unevenness, bypass flow is more likely to occur during concrete pouring. The first control component first sets a relatively high first pressure of the bladder in the upper section at the first time to reduce the bypass flow phenomenon in the upper area, and at the same time sets a higher second pressure of the bladder in the lower section at the first time to ensure the stability of the lower area. As time goes by (at the second time), the soil layer will be squeezed and deformed by the bladder of the first pressure, causing the first pressure to decrease. In water-rich sand layers, the rate of change of this pressure reduction is relatively fast, so at the second time, the first control component adjusts the pressure of the bladder in the upper section more frequently to maintain the stability of the upper and lower areas and effectively control the bypass flow phenomenon.
[0020] According to a preferred embodiment, the sensor element is arranged on the side of the joint box adjacent to the anti-bypass assembly, and it can be embedded under the side surface of the joint box while maintaining contact with the concrete. The sensor element with an embedded layout can be placed within the surface of the joint box, avoiding the addition of unnecessary friction during the disassembly process, while ensuring that it is not damaged during the pouring and solidification of the concrete. This design ensures the stability of the position of the sensor element throughout the construction process and provides continuous and accurate data for monitoring the internal stress of the concrete. When the concrete develops to a suitable strength and the joint box needs to be dismantled, the sensor element will not cause any interference to the disassembly operation due to its concealed position, ensuring the smooth removal of the joint box. In addition, the embedded design provides an additional layer of protection for the sensor element, protecting it from potential damage to the concrete during the disassembly process, maintaining the integrity and functionality of the sensor element.
[0021] According to a preferred embodiment, the stripping unit includes a second control component, which is connected to a number of jacks through hydraulic pipes. The jacks located on the lower layer are equipped with hydraulic locks to prevent automatic ejection, and the jacks are equipped with hydraulic sensors for checking the hydraulic conditions. The jacks located on the lower layer are equipped with hydraulic locks as a safety protection measure. When the stripping work has not yet begun, the hydraulic locks can prevent the jacks from automatically ejecting due to unexpected reasons, avoiding accidental damage to the joint box or surrounding structures, and ensuring construction safety. In addition, the hydraulic sensors equipped on the jacks can monitor key parameters such as pressure and flow of the hydraulic system in real time. Through these real-time data, construction personnel can promptly understand the working status of the stripping unit, such as whether there are abnormal conditions such as leakage and blockage. This helps to discover and solve problems in a timely manner and ensure the smooth progress of the stripping operation.
[0022] According to a preferred embodiment, a vertical slot is provided on the front of the joint box, and a water stop is inserted in the slot. The water stop can be kept in the concrete structure when the joint box is removed to provide a seal for the joint of the underground continuous wall groove section. This design effectively prevents moisture penetration, maintains the durability of the underground continuous wall, and improves the integrity and collaborative working ability of the wall.
[0023] The present invention also relates to an auxiliary method for underground continuous wall construction, which comprises the following steps:
[0024] Obtain the internal stress change data of concrete, and generate corresponding working plans by the stripping unit at different setting stages of concrete;
[0025] Execute the work plan to complete the work steps before the formal stripping of the joint box;
[0026] After the formal stripping is completed, the joint box is pulled out from the slot section by the lifting unit. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of an application scenario of the underground continuous wall construction auxiliary system provided by the present invention;
[0028] Figure 2 It is a structural schematic diagram of the junction box and the first control assembly provided by the present invention;
[0029] Figure 3 It is a schematic structural diagram of the anti-bypass flow assembly provided by the present invention under initial pressure;
[0030] Figure 4 is a schematic structural diagram of the anti-bypass flow assembly provided by the present invention under a first pressure;
[0031] Figure 5 is a schematic structural diagram of the anti-bypass flow assembly provided by the present invention under a second pressure;
[0032] Figure 6 It is a structural schematic diagram of the pipe pulling machine provided by the present invention before the joint box is laterally stripped;
[0033] Figure 7 It is a structural schematic diagram of the pipe pulling machine provided by the present invention when completing the lateral stripping of the joint box;
[0034] Figure 8 It is an example block diagram of different working links of the underground continuous wall construction auxiliary system provided by the present invention;
[0035] Fig. 9 It is a hardware connection diagram of the underground continuous wall construction auxiliary system provided by the present invention;
[0036] Fig.10 It is a schematic diagram of the longitudinal section of the soft soil layer under ultrasonic trenching detection;
[0037] Fig.11 It is a schematic diagram of the longitudinal section of the water-rich sand layer under ultrasonic troughing detection;
[0038] Fig.12 It is a data lookup table for the internal pressure and pressure adjustment timing set by the first control component.
[0039] Reference numerals list
[0040] 100: joint box; 110: anti-circumference assembly; 111: outer bladder; 112: inner bladder; 113: sensor element; 120: jack; 130: water stop; 200: joint removal device; 210: stripping unit; 211: first control assembly; 212: second control assembly; 213: pipe pulling machine; 220: lifting unit. DETAILED DESCRIPTION
[0041] The following is a detailed description with reference to the accompanying drawings.
[0042] Example 1
[0043] In underground continuous wall construction, whether it is soft soil or water-rich sand, it is crucial to ensure the quality of trenching and prevent trench wall collapse. However, water-rich sand has high permeability and loose structure, which makes it easier for the flow of groundwater to cause sand flow and collapse during trenching, resulting in poor trench wall stability. In water-rich sand, the disturbance during trenching may not only cause local collapse of the trench wall, but also cause the flow of groundwater to carry away sand, forming larger gaps. Due to its special geological characteristics, water-rich sand poses a more severe challenge to construction.
[0044] Ultrasonic testing technology can effectively evaluate the quality of trenching. By analyzing the propagation characteristics of ultrasonic waves in the soil layer, the integrity and uniformity of the trench wall can be identified. Fig.10 and Fig.11 The following is a schematic diagram of ultrasonic troughing detection of two types of formations. Fig.10 As shown in Figure 2, in soft soil layers, ultrasonic testing shows a relatively uniform soil structure, with smaller gaps in the trench wall and a lower possibility of bypass flow. Fig.11 As shown, in the water-rich sand layer, ultrasonic testing reveals the existence of large voids and unevenness in the trench wall, which means that there is a high possibility of bypass flow during concrete pouring.
[0045] Therefore, especially for soils such as water-rich sand strata where trench walls are prone to collapse, the present invention provides an underground continuous wall construction auxiliary system, such as Figure 1 As shown, the system includes a joint box 100 disposed at the end of an underground continuous wall groove section and a joint removal device 200 located on the ground for removing the joint box 100 from the underground continuous wall groove section.
[0046] Preferably, if Figure 2As shown, the side of the joint box 100 is provided with an anti-circumvention component 110 for preventing concrete from flowing around to the back of the joint box 100, and the front of the joint box 100 is provided with a jack 120 for separating it from the solidified concrete. The anti-circumvention component 110 can adaptively change its shape according to different working links of the joint box 100 under the control of the joint removal device 200, and form an effective blockage between the side of the joint box 100 and the side wall of the adjacent underground continuous wall groove section, ensuring that the joint box 100 can be smoothly removed after the concrete poured in the groove section is solidified. In addition, the joint removal device 200 can control the jack 120 to automatically push out according to the preset rules when the joint box 100 is officially removed, so as to peel the joint box 100 from the concrete surface. The working steps of the joint box 100 include the bypass prevention step, the stripping preparation step, the formal stripping step and the lifting step in the order of the working process. In the three key stages of the bypass prevention step, the stripping preparation step and the formal stripping step, the bypass prevention component 110 plays a vital role to ensure the isolation and protection of the joint box 100 from the surrounding concrete structure. In the formal stripping step, the jack 120 automatically pushes out according to the preset rules and control signals to provide the necessary power support for the joint box 100 to be stripped from the concrete.
[0047] Preferably, if Figure 2 As shown, in the construction of underground continuous wall, in order to ensure the quality of concrete pouring and the convenience of subsequent removal of the joint box 100, the bypass prevention component 110 is designed as a double-layer detachable hollow expansion bag that precisely matches the length of the joint box 100. Figure 3 As shown, the expansion bladder includes an inner bladder body 112 and an elastic outer bladder body 111 covering the surface of the inner bladder body 112, aiming to provide excellent sealing and adaptability. Specifically, the inner bladder body 112 is the main structure of the expansion bladder and is responsible for storing the injected gas or liquid medium. The outer bladder body 111 is made of a highly elastic material and can fit tightly into the gap between the side of the joint box 100 and the groove wall, effectively preventing concrete from bypassing.
[0048] Preferably, if Figure 1 As shown, the joint removal device 200 includes a stripping unit 210 and a lifting unit 220, wherein the stripping unit 210 is used to formulate and execute corresponding work plans in different working links of the joint box 100 to ensure that the joint box 100 is smoothly separated from the concrete under the premise of avoiding concrete bypass, and the lifting unit 220 is used to remove the stripped joint box 100 from the underground continuous wall groove section during the lifting link of the joint box 100.
[0049] Preferably, if Figure 1 , Figure 2As shown, the stripping unit 210 is equipped with a first control component 211 that can controllably inject a fluid medium into the anti-bypass assembly 110 according to a formulated work plan. Exemplarily, the first control component 211 is composed of a series of devices, which may include devices for controlling gaseous media such as gas valves, pressure regulators and pneumatic pumps, or devices for controlling liquid media such as liquid-driven pumps, hydraulic valves and pressure sensors. In particular, the first control component 211 also includes a programmable logic controller (PLC) capable of pressure management, which allows construction personnel to accurately control the aforementioned gas or liquid equipment through the operation interface thereon according to construction requirements, adjust the amount of gas or liquid injected into the expansion bag of the anti-bypass assembly 110, and adjust the expansion degree of the expansion bag in a manner that changes the pressure level in the bag. During the concrete pouring process, the stripping unit 210 injects gas or liquid medium into the anti-bypass assembly 110 through the first control component 211, so that the internal pressure of the expansion bag increases and the volume gradually expands. As the expansion bladder expands, its outer bladder body 111 fits tightly against the gap between the side of the joint box 100 and the groove wall, forming an effective blocking structure. This design ensures that the concrete will not flow around to the back of the joint box 100 during the concrete pouring process, thereby ensuring the pouring quality of the concrete in the groove section. When the joint box 100 is removed, the gas or liquid medium in the expansion bladder is released through the first control component 211, so that its internal pressure is reduced and its volume gradually shrinks, thereby releasing the blockage of the gap between the side of the joint box 100 and the groove wall. Subsequently, the stripping unit 210 can start the jack 120 or other tools to smoothly strip the joint box 100 from the concrete.
[0050] Preferably, if Figure 1 As shown, the lifting unit 220 can be configured as a hydraulically or electrically driven lifting equipment, such as a crane, a grab, etc., which has a powerful lifting function. It is accurately connected to the joint box 100 through a special connection method such as a steel cable, a chain or a hook to ensure the safety and stability of the lifting process. Preferably, the lifting unit 220 of the present invention can also achieve data connection with the controller included in the stripping unit 210. The control component included in the stripping unit 210 can send a prompt message to the controller of the lifting unit 220 after completing the formal stripping link of the joint box 100. In response to the prompt message, the controller can control the crane, grab and other lifting equipment to automatically and accurately lift the joint box 100 out of the slot section.
[0051] Preferably, if Figure 2As shown, the bypass prevention assembly 110 is equipped with a sensor element 113 for obtaining the data of stress changes inside the concrete. The sensor element 113 is connected to the stripping unit 210 so that the stripping unit 210 can generate a work plan corresponding to different coagulation stages of the concrete in response to the changes in the stress data. Preferably, the sensor element 113 is specifically arranged on the side of the junction box 100 adjacent to the bypass prevention assembly 110. Therefore, its monitoring data will directly reflect the concrete coagulation state near the bypass prevention assembly 110 in the underground continuous wall groove section, and transmit the concrete stress as a monitoring indicator to the stripping unit 210. The sensor element 113 can monitor the stress exerted on it by the concrete. The coagulation of concrete is a chemical reaction process. As the hydration proceeds, the concrete gradually changes from a plastic state to a solid state, and its strength gradually increases. In this process, the stress value measured by the sensor element 113 gradually increases. Therefore, the sensor element 113 can be a stress-strain sensor. By measuring the concrete stress data, the coagulation state (or strength development state) of the concrete can be known.
[0052] Preferably, if Figure 2 As shown, in order to ensure that the sensor element 113 does not hinder the removal of the joint box 100 and avoid damage to the sensor element 113 during the removal process, the present invention optimizes the structure of the joint box 100. While ensuring that the sensor element 113 can make necessary contact with the concrete, the sensor element 113 is designed to be able to properly penetrate under the surface of the joint box 100. This design not only ensures the smoothness of the surface of the joint box 100 and reduces the resistance during the disassembly process, but also protects the sensor element 113 from being scratched by the solidified concrete during the removal of the joint box 100, thereby ensuring its integrity and functionality.
[0053] Although the anti-bypass assembly 110, by virtue of its expandability, effectively closes the tiny gap between the joint box 100 and the slot wall during the concrete pouring process, thereby significantly suppressing the phenomenon of concrete flowing around to the back of the joint box 100 during the solidification process, and greatly reducing the difficulty of smoothly removing the joint box 100 from the slot section during the construction of the underground continuous wall. However, due to the design features of the anti-bypass assembly 110, the portion of the anti-bypass assembly 110 that protrudes from the side wall of the joint box 100 is at risk of being fixed to the side wall of the slot section during the concrete solidification process. Once the anti-bypass assembly 110 is fixed by concrete, not only will the removal process of the joint box 100 become complicated and difficult, but if a forced removal method is adopted, it is very likely to cause the anti-bypass assembly 110 to break or be damaged, thereby affecting the possibility of its reuse, which undoubtedly increases the material cost and labor cost during the construction process.
[0054] In order to meet this technical challenge, the present invention proposes an automated control technology based on the distribution and development of concrete stress to achieve dynamic adjustment of the working form of the anti-bypass assembly 110. The core of this technical solution is to ensure that the anti-bypass assembly 110 can effectively perform its anti-bypass function in the early stage of concrete solidification. At the same time, in the process of gradual solidification of concrete and stabilization of stress development, the form of the anti-bypass assembly 110 is gradually adjusted through the automated control mechanism to reduce its contact area with the side wall of the slot section, thereby avoiding being solidified by concrete and ensuring that no obstacles will be caused during the later removal of the joint box 100. The underground continuous wall construction auxiliary system of the present invention can select appropriate working plans in different working links of the joint box 100, ensure the quality of the construction of the joint box 100, reduce construction costs, and improve construction efficiency.
[0055] Preferably, the working process of the joint box 100 is closely related to the setting process of concrete, and the setting state of concrete can be indirectly reflected by the internal stress data monitored in real time by the sensor element 113. Specifically, when the concrete strength has developed to a preset critical stage, the internal stress of the concrete will also reach a certain specific value. Based on the above principle, when the sensor element 113 captures these special stress data that mark the important nodes of the concrete setting stage, it will send a corresponding signal to the stripping unit 210. After receiving these signals, the stripping unit 210 can accurately judge the current setting state of the concrete, and formulate and execute the corresponding work plan accordingly. This ensures that the anti-circumvention operation and the stripping operation are carried out when the concrete reaches a specific strength, thereby ensuring the safety and efficiency of the construction. In the whole process, the data acquisition, signal transmission and work plan execution of the sensor element 113 and the stripping unit 210 together efficiently and accurately realize the anti-circumvention control when the concrete has not yet solidified and the stripping control when the concrete has completed solidification.
[0056] Preferably, if Figure 2As shown, the front of the joint box 100 is equipped with a number of jacks 120 along its height direction, and the top surface of the jacks 120 is in direct contact with the concrete. In order to enhance the stability and reliability of the system, the jacks 120 are arranged in two groups, namely the main group and the standby group. This dual configuration ensures that when any group of jacks 120 fails, the other group can quickly take over, thereby ensuring the continuity and safety of the stripping operation. The main group jacks 120 present a specific distribution pattern in the height direction of the joint box 100. Starting from the bottom of the joint box 100, they are arranged alternately to form a "jumping" configuration. This layout is intended to ensure that during the stripping process, all parts of the joint box 100 can be evenly stressed to avoid the problem of local stress concentration. At the same time, the standby group jacks 120 are also configured in a similar "jumping" mode, but their positions are staggered from the main group jacks 120, so that when a problem occurs with the main jacks 120 at any position, there is a corresponding standby jack 120 that can be quickly activated. This layout not only improves the redundancy of the system, but also greatly enhances the fault tolerance of the stripping operation. In actual operation, once a jack 120 in the main group fails or requires maintenance, the underground continuous wall construction auxiliary system will immediately switch to the jack 120 at the corresponding position in the standby group to ensure that the stripping process will not be interrupted due to a single point failure.
[0057] Preferably, in the formal stripping process of the joint box 100, the plurality of jacks 120 located near the bottom of the joint box 100 will be started after the plurality of jacks 120 located near the top of the joint box 100. This starting method optimizes the stripping sequence, ensuring that the joint box 100 is first separated from the concrete at the top layer of the jacks 120, and then the bottom layer of the jacks 120 will be operated to further strip the bottom layer of the joint box 100, which is more difficult to strip, from the concrete. Figure 8As shown, each jack 120 can be connected to the second control component 212 configured by the stripping unit 210 through a hydraulic pipe to ensure the controllable transmission of hydraulic power. The second control component 212 may include a driving pump, a hydraulic valve, a pressure sensor and other equipment for controlling hydraulic oil to achieve precise control of the jack 120. In particular, the second control component 212 also includes a programmable logic controller (PLC) capable of pressure management, which can be connected to the controller of the first control component 211 by data. When the controller of the first control component 211 completes its task in the formal stripping link, that is, after the anti-circumvention component 110 blocks the gap between the side of the joint box 100 and the side wall of the underground continuous wall groove section, it can immediately send a clear control signal to the controller of the second control component 212. After receiving this instruction, the controller of the second control component 212 can automatically respond according to the construction requirements, or according to the operation instructions of the construction personnel, accurately adjust the number and sequence of starting the jacks 120 at different positions of the joint box 100 to ensure that the joint box 100 can be stripped from the concrete surface in a predetermined manner.
[0058] Preferably, the bottom jack 120 is equipped with hydraulic locks to prevent automatic ejection when not needed. These hydraulic locks can effectively lock the jack 120 in a stationary state until a clear start signal is received from the stripping unit 210. In addition, in order to improve the safety and accuracy of the operation, the jack 120 is also equipped with hydraulic sensors. These sensors can monitor key parameters such as pressure and flow of the hydraulic pipe in real time and feed back the data to the construction personnel. Through these data, the construction personnel can understand the working status of the jack 120 before construction, so that the abnormal jack 120 can be repaired in place in time to prevent abnormal ejection during the concrete pouring process.
[0059] As a preferred embodiment, when the joint box 100 is not provided with the jack 120, the stripping unit 210 can also realize the lateral stripping of the joint box 100 by adding a pipe pulling machine 213. The pipe pulling machine 213 can be set on the ground of the underground continuous wall groove section, and it can perform the lateral stripping task of the joint box 100 under the precise control of the second control component 212. Figure 6 , Figure 7 As shown, the pipe pulling machine 213 is a ground device, which has a base and a chuck arranged above the base. The base can span the ground slot gap of the underground continuous wall, thereby providing a stable support for the pipe pulling machine 213. The base is also provided with an opening at a position corresponding to the ground slot gap, allowing the joint box 100 to pass through the opening smoothly to expose the ground. The chuck can be clamped on the surface of the joint box 100, and driven by the driving mechanism equipped with the pipe pulling machine 213, the chuck can realize vertical pulling of the joint box 100. In particular, as Figure 6 , Figure 7As shown, the driving mechanism of the pipe pulling machine 213 can also drive the translation of the base on the ground to drive the synchronous movement of the joint box 100 clamped by the chuck, ensuring that the front of the joint box 100 can be separated from the concrete surface. Preferably, the start timing of the pipe pulling machine 213 is precisely controlled by the second control component 212, and this moment is immediately after the first control component 211 completes its task, that is, releases the blockage of the gap by the expansion bag of the anti-circumference component 110. Once receiving the instruction from the first control component 211, the second control component 212 immediately sends a control signal to the pipe pulling machine to drive it to perform a lateral translation operation to ensure that the front of the joint box 100 is completely separated from the concrete surface. After completing the lateral stripping, the pipe pulling machine 213 can also adjust the translation direction to smoothly move the joint box 100 back to its original position, making full preparations for the subsequent lifting operations.
[0060] Preferably, the stripping unit 210 will accurately adjust the working plan according to the concrete stress data provided by the sensor element 113. Specifically, when the sensor element 113 detects that the internal stress of the concrete reaches a specific point, that is, the first threshold value at which the flow characteristics disappear, the first control component 211 will respond to this signal and accurately adjust the internal pressure of the inner capsule 112 to the first pressure to adapt to the change of concrete stress at this stage. Similarly, when the sensor element 113 captures that the internal stress of the concrete has reached the second threshold value that meets the conditions for dismantling the joint box 100, the first control component 211 will make adjustments again and set the internal pressure of the inner capsule 112 to the second pressure to ensure the safety and efficiency of the stripping process.
[0061] Preferably, the workflow of the joint box 100 is designed strictly in accordance with the time sequence and engineering requirements. Figure 8 , Fig. 9As shown, first, when entering the anti-bypass link, that is, when the concrete in the underground continuous wall groove section has just been poured, the first control component 211 will set the internal pressure of the inner sac 112 to the initial pressure. This is to ensure that the concrete will not be adversely affected by bypass during the initial solidification process. Subsequently, when entering the stripping preparation link, that is, when the concrete strength gradually increases and the bypass characteristics just disappear, the first control component 211 will adjust the internal pressure to the first pressure to prepare for the subsequent stripping operation. When entering the formal stripping link, that is, when the concrete strength develops to a level sufficient to meet the removal of the joint box 100, the first control component 211 will further adjust the internal pressure to the second pressure to avoid damage to the anti-bypass component 110 during the stripping process. At the same time, when the joint box 100 is equipped with a jack 120, the second control component 212 will successively start the jacks 120 located at different heights of the joint box 100 to ensure that the front of the joint box 100 is smoothly peeled off from the concrete surface; and when the joint box 100 is not equipped with a jack 120, the second control component 212 can realize the lateral peeling of the joint box 100 by controlling the translation operation of the pipe pulling machine 213. Finally, when entering the lifting link, the first control component 211 and / or the second control component 212 can send a prompt message to the lifting unit 220, and the lifting unit 220 connected to the joint box 100 will start to complete the removal of the joint box 100. In particular, when the stripping unit 210 is equipped with a pipe pulling machine 213, the second control component 212 can also realize the vertical pulling of the joint box 100 by activating the lifting function of the chuck of the pipe pulling machine 213. During the whole process, the precise control of the first control component 211 and the second control component 212 and the real-time monitoring of the sensor element 113 jointly ensure the safety and efficiency of the project.
[0062] Preferably, when the internal stress of the concrete reaches a preset first threshold value, this indicates that the concrete has entered the initial setting stage. At this stage, the plastic flow characteristics of the concrete have disappeared, which means that its plasticity is significantly reduced and it no longer has the ability to undergo plastic deformation without external force. At this point, the self-flowing property of the concrete has been greatly weakened, and it is almost impossible to automatically fill the small gaps in the construction. This change is an important sign that the concrete is gradually hardening, and has important guiding significance for subsequent construction steps. As the concrete continues to solidify, when its internal stress reaches the second threshold value, it indicates that the concrete has begun to enter the final setting stage. At this stage, the degree of coagulation of the concrete has been significantly improved, and its structural strength is sufficient to support the safe removal of the joint box 100 without causing deformation or damage to the concrete. The achievement of this state is an important milestone in the construction process, which means that the next stage of construction operations can be carried out safely. In order to ensure the accuracy and safety of the construction, the determination of the first threshold value and the second threshold value is crucial. Preferably, these threshold values can be determined by a professional concrete mixing station through a designed concrete performance observation experiment. In this experiment, high-precision professional equipment such as rheometers and pressure testing machines can be used to comprehensively evaluate key characteristics of concrete such as fluidity and deformation capacity at different strengths. Through in-depth analysis of experimental data, the strength value corresponding to when the concrete loses its plastic flow characteristics can be accurately set as the first threshold. Similarly, the second threshold when the concrete reaches sufficient strength to support the safe removal of the joint box 100 can also be determined. The setting of these precise thresholds provides a scientific basis for key decisions during the construction process, thereby ensuring the safety and efficiency of the entire construction process.
[0063] Preferably, the designs of the initial pressure, the first pressure and the second pressure follow a decreasing numerical sequence to ensure that the requirements of different stages in the concrete construction process are accurately met.
[0064] First, the value of the initial pressure is set to the maximum, the main purpose of which is to maximize the expansion degree of the bypass prevention assembly 110. This setting allows the outer wall of the bypass prevention assembly 110 to fit closely to the groove wall, thereby effectively closing the gap between the groove wall and the joint box 100 in the initial stage of concrete pouring to prevent the bypass phenomenon from occurring. Exemplarily, the initial pressure setting should be such that the expansion degree of the bypass prevention assembly 110 reaches 80%-100% of its maximum allowable expansion degree (e.g. Figure 3 As shown in the figure), this ensures that the gaps in the trench wall are tightly sealed in the early stages of construction, laying a solid foundation for the subsequent stable solidification of the concrete.
[0065] Subsequently, when the concrete begins to solidify and its internal stress reaches a preset first threshold, the first pressure is set to a value lower than the initial pressure. This adjustment is intended to allow the anti-bypass component 110 to partially shrink while maintaining a certain degree of expansion. This partial shrinkage design can create a tiny gap between the outer wall of the anti-bypass component 110 and the groove wall, effectively preventing the concrete from solidifying the anti-bypass component 110 on the groove wall during the solidification process. Since the timing of the first pressure adjustment happens to be when the concrete's bypass characteristics disappear, even if the anti-bypass component 110 does not completely seal the gap at this time, the concrete will not bypass to the back of the joint box 100 on its own. Exemplarily, the first pressure should be set so that the expansion degree of the anti-bypass component 110 is maintained at 40%-60% of the maximum allowable expansion degree (such as Figure 4 As shown), this ensures that both bypass and over-curing can be prevented during the setting process of concrete.
[0066] Finally, when the concrete stress reaches a preset second threshold value, that is, when the conditions for safe removal of the joint box 100 are met, the second pressure is set to a value lower than the first pressure. This pressure adjustment further promotes the contraction of the anti-bypass assembly 110 relative to the first pressure state. At this time, the volume of the anti-bypass assembly 110 is reduced, which is intended to reduce the risk of abrasions caused by the contact between the anti-bypass assembly 110 and the slot wall during the removal of the joint box 100, and to avoid damage to the anti-bypass assembly 110 due to improper operation. Exemplarily, the setting of the second pressure should further shrink the expansion degree of the anti-bypass assembly 110 to 0%-20% of the maximum allowable expansion degree (such as Figure 5 As shown), to ensure the safety and integrity of the anti-bypass assembly 110 when the joint box 100 is removed.
[0067] In summary, the working steps of the underground continuous wall construction auxiliary system of the present invention can be summarized as follows:
[0068] 1. Acquisition of stress change data:
[0069] The sensor element 113 obtains the data σ(t) of the change of the internal stress of the concrete over time;
[0070] 2. Generation of working plan of stripping unit 210:
[0071] According to the stress data change Δσ(t), the working plan W(t) is generated:
[0072]
[0073] Let σ threshold1 and σ threshold2 are the stress thresholds for initial and final setting of concrete, respectively. The specific work plan is as follows:
[0074] When σ(t)≤σ threshold1When the initial work plan W1 is implemented;
[0075] When σ threshold1 <σ(t)≤σ threshold2 When the intermediate work plan W2 is executed;
[0076] When σ(t)>σ threshold2 When the final work plan W3 is executed;
[0077] 3. Stripping process control:
[0078] When σ(t)≤σ threshold1 When the initial work plan W1 is implemented;
[0079] In σ threshold1 <σ(t)≤σ threshold2 When the intermediate work plan W2 is executed;
[0080] When σ(t)>σ threshold2 When the final work plan W3 is executed, the formal divestiture is completed.
[0081] 4. After the stripping unit 210 completes the formal stripping, the lifting unit 220 pulls the joint box 100 out of the slot section.
[0082] The underground continuous wall construction auxiliary system of the present invention monitors and controls stress changes automatically, accurately controls the stripping process, reduces unnecessary waiting time, and thus shortens the construction period. By accurately controlling the setting stage of concrete, the structural integrity of the joint box 100 during the stripping process is ensured, and construction quality problems caused by incomplete solidification or excessive solidification of concrete are avoided. In addition, the automated system not only reduces the need for manual monitoring and operation, reducing labor costs, but also accurately controls the operation of the expansion assembly and the joint box 100, reducing material waste and improving construction efficiency. Finally, the system's accurate stress monitoring and control reduces risks during the construction process and improves overall safety.
[0083] According to a preferred embodiment, the working scheme generated by the stripping unit 210 includes:
[0084] When the sensor element 113 obtains that the internal stress of the concrete reaches the first threshold value σ where the flow characteristics disappear threshold1 When the first control component 211 adjusts the internal pressure of the inner capsule 112 to the first pressure
[0085] When the sensor element 113 obtains that the internal stress of the concrete reaches the second threshold value σ that satisfies the removal condition of the joint box 100 threshold2 When the pressure of the inner capsule 112 is adjusted to the second pressure P2, the first control component 211 adjusts the internal pressure of the inner capsule 112 to the second pressure P2:
[0086]
[0087] Through automated monitoring and intelligent response mechanisms, the stripping unit 210 can accurately determine the different stages of concrete coagulation, thereby stripping the joint box 100 at the most appropriate time. This avoids construction problems caused by stripping too early or too late, and improves overall construction efficiency.
[0088] Preferably, if Figure 8 As shown, the first control component 211 of the present invention adopts a progressive pressure adjustment strategy, instead of immediately reducing the pressure of the anti-circulation component 110 from the initial state to the second pressure after the concrete loses its circumferential flow characteristics. Specifically, the first control component 211 sets a critical first pressure between the initial pressure and the second pressure as an intermediate transition stage for pressure regulation. This progressive pressure regulation strategy is intended to accurately control the behavior of the anti-circumference component 110 during the concrete setting process to minimize unnecessary interference with the concrete setting process. In the initial solidification stage of concrete, that is, when the concrete can maintain its current shape without external interference, if the first control component 211 directly drops the pressure from the initial value to the second pressure, the anti-circumference component 110 will shrink sharply, which may produce a large impact force, disturbing the adjacent concrete structure, and thus affecting its normal setting process. In order to avoid this potential risk, the first control component 211 sets the first pressure as a buffer stage so that the pressure of the anti-circumference component 110 can be gradually reduced to the first pressure level first, and then further reduced to the second pressure. This gradual pressure release method can significantly reduce the impact on the concrete setting process, thereby ensuring the integrity and stability of the concrete structure. Through this refined pressure control, the first control component 211 of the present invention provides higher reliability and safety for concrete construction.
[0089] Preferably, in the construction of underground continuous wall anti-circulation, since the length of the joint box 100 often reaches tens of meters, the pressure generated by the concrete at different depths on the joint box 100 is significantly different. If the anti-circulation component 110 cannot adapt to these differences, the components in the deep part may not be able to fully expand due to the greater concrete pressure, thereby affecting its anti-circulation performance. Therefore, the anti-circulation component 110 proposed in the present invention is designed to include at least two sections of independent inner bladders 112 located at different heights, and each section of the inner bladder 112 is independently connected to the first control component 211 to adjust the pressure separately. Specifically, the first control component 211 can set different initial pressures, first pressures, and second pressures for the lower section inner bladder 112 and the upper section inner bladder 112. This segmented bladder design ensures that each part of the anti-circulation component 110 can adapt to the specific pressure conditions of its depth, thereby achieving effective anti-circulation effect within the entire length of the joint box 100.
[0090] In soft soil, such as Fig.10 As shown in the figure, the pressure exerted on the joint box 100 in the bottom area is significantly greater than that in the upper area because the pressure and density of the soil layer itself increase with depth. This uneven distribution of pressure causes the flow around the bottom area to be relatively weak, or even completely disappear. Therefore, the stability of the joint box 100 in soft soil is relatively high, but special attention should be paid to the flow control in the upper area. In contrast, in water-rich sand layers, such as Fig.11 As shown, due to the large voids and unevenness of the soil layer, the flow around during concrete pouring is more significant, especially in the upper area where the soil pressure is weakened. This flow around not only affects the uniformity and density of the concrete, but may also have an adverse effect on the structural stability of the joint box 100.
[0091] In order to meet these challenges, the first control component 211 of the joint box 100 of the present invention can dynamically adjust the internal pressure of the lower section inner bladder 112 and the upper section inner bladder 112 according to the specific conditions of the soil layer where the joint box 100 is located. Specifically, the first control component 211 can apply a higher internal pressure to the lower section inner bladder 112 than the upper section inner bladder 112 according to the pressure generated by the concrete at different depths, or conversely, apply a higher internal pressure to the upper section inner bladder 112 than the lower section inner bladder 112. This dynamic adjustment mechanism can optimize the stability and consistency of the concrete pouring process and reduce the bypass phenomenon.
[0092] In a soft soil layer, the first control component 211 can set a relatively low internal pressure for the lower section inner bladder 112 according to the pressure and density of the bottom area of the soil layer to adapt to the low possibility of bypass flow in this area. At the same time, in order to ensure the stability of the upper area, the first control component 211 will set a higher internal pressure for the upper section inner bladder 112. This pressure setting strategy helps to achieve uniformity and density of concrete pouring in soft soil layers. In particular, for soft soil layers, the first control component 211 can set the first pressure of the upper section inner bladder 112 and the second pressure of the lower section inner bladder 112 at the first time. Since the pressure and density of the bottom area of the soft soil layer increase with depth, the possibility of bypass flow phenomenon decreases, so the first control component 211 sets a relatively low second pressure for the lower section inner bladder 112 to adapt to this geological characteristic. At the same time, in order to ensure the stability of the upper area, the upper section inner bladder 112 is set to a higher first pressure. Over time, the soil layer is deformed under the compression of the upper section inner bladder 112, resulting in a gradual decrease in the first pressure. Since the pressure change rate in the soft soil layer is relatively gentle, the first control component 211 can adjust the pressure of the upper inner bladder 112 in a timely manner according to the actual reaction characteristics of the soil layer at the second time to maintain the required stability.
[0093] In the water-rich sand layer, the first control component 211 needs to set a relatively high internal pressure for the upper inner bladder 112 to reduce the bypass phenomenon in the upper area. At the same time, in order to ensure the stability of the lower area, the first control component 211 will set a higher internal pressure for the lower inner bladder 112. This pressure setting strategy helps to control the bypass phenomenon during concrete pouring in the water-rich sand layer and improve the uniformity and density of the concrete. In particular, for the water-rich sand layer, the first control component 211 can set a relatively high first pressure of the upper inner bladder 112 at the first time to reduce the bypass phenomenon in the upper area. At the same time, in order to ensure the stability of the lower area, the lower inner bladder 112 is set to a higher second pressure. Due to the large voids and unevenness of the soil layer in the water-rich sand layer, the rate of change of pressure reduction is fast, and the first control component 211 needs to adjust the pressure of the upper inner bladder 112 earlier and more frequently at the second time. This adjustment strategy helps maintain the stability of the upper and lower areas and effectively controls the bypass phenomenon, ensuring the quality and efficiency of concrete pouring.
[0094] Through the above design, the joint box 100 of the present invention can optimize the concrete pouring process and improve the engineering quality and construction safety under different geological conditions through the dynamic pressure adjustment mechanism of the first control component 211.
[0095] Preferably, the key to the present invention is that the first control component 211 can independently and dynamically set the internal pressure of the inner capsule 112 at different heights and the timing of pressure adjustment according to the external geological parameters of the soil layer where the joint box 100 is located and the permeability parameters of the concrete. These parameters include but are not limited to soil layer type, density, thickness, water content, strength, groundwater level, as well as permeability coefficient, resistance, pressure head, porosity and soil layer permeability. The accurate acquisition and application of these parameters enable the first control component 211 to accurately control the internal pressure of the inner capsule 112 to meet the concrete pouring requirements under different geological conditions.
[0096] During the setting process of the first control component 211, the external geological parameter set is assumed to be G = {G1, G2, ..., G n}, where G i represents the i-th geological parameter. Assume that the permeability parameter set is P = {P1, P2, ..., P m}, where P j represents the jth penetration parameter.
[0097] The internal pressure P of the inner capsule 112 can be expressed as: P = f(G1, G2, ..., G n , P1, P2, …, P m )=α1G1+α2G2+…+α n G n +β1P1+β2P2+…+β m P m +γ, where α i and β j is the weight coefficient of the corresponding parameter, and γ is a constant term.
[0098] The pressure adjustment timing T can be expressed as: T = g(G1, G2, ..., G n , P1, P2, …, P m )=δ1G1+δ2G2+…+δ n G n +∈1P1+∈2P2+…+∈ m P m +ζ, where δ i and ∈ j is the weight coefficient of the corresponding parameter, and ζ is a constant term.
[0099] Preferably, in actual construction, the function of the internal pressure P and the pressure adjustment timing T is a data lookup table summarized based on experience. The data lookup table can be as follows: Fig.12 Shown
[0100] Preferably, if Figure 2As shown, the present invention also provides a vertical slot on the front of the joint box 100, and inserts a waterstop 130. The waterstop 130 is made of highly elastic and chemically resistant materials, such as rubber, plastic or special alloys, to adapt to the slight deformation of the concrete structure when the joint box 100 is removed, and to maintain its sealing performance. Once the joint box 100 is removed, the waterstop 130 will remain in the solidified concrete structure, providing a long-term water-stopping effect for the joints between two adjacent sections of the underground continuous wall groove. This can not only effectively prevent moisture penetration and maintain the durability of the underground continuous wall, but also enhance the integrity and collaborative working ability of the wall. By accurately inserting the waterstop 130 and fixing it in the slot before pouring the concrete, the construction process is simplified, and the waterproof performance and quality of the underground structure are significantly improved.
[0101] Example 2
[0102] This embodiment is a further improvement on Embodiment 1, and the repeated contents will not be repeated here.
[0103] The present invention relates to an auxiliary method for underground continuous wall construction. Preferably, the auxiliary method adopts the auxiliary system as described in Example 1, and the method comprises the following steps:
[0104] S1, obtaining the internal stress variation data of concrete, and generating corresponding working schemes by the stripping unit 210 at different setting stages of concrete;
[0105] S2, executing the work plan to complete the work steps before formal stripping of the joint box 100;
[0106] S3. After the formal stripping is completed, the lifting unit 220 pulls the joint box 100 out of the slot section.
[0107] It should be noted that the above-mentioned specific embodiments are exemplary, and those skilled in the art can come up with various solutions inspired by the disclosure of the present invention, and these solutions also belong to the disclosure scope of the present invention and fall within the protection scope of the present invention. Those skilled in the art should understand that the present invention specification and its drawings are illustrative and do not constitute a limitation of the claims. The scope of protection of the present invention is defined by the claims and their equivalents. The present invention specification contains multiple inventive concepts, such as "preferably" or "according to a preferred embodiment", which means that the corresponding paragraph discloses an independent concept, and the applicant reserves the right to file a divisional application based on each inventive concept. Throughout the text, the features guided by "preferably" are only an optional method and should not be understood as a must-have setting. Therefore, the applicant reserves the right to abandon or delete the relevant preferred features at any time.
Claims
1. An underground continuous wall construction auxiliary system, comprising: The joint box (100) is temporarily placed at the end of the underground continuous wall trench section. A joint removal device (200) comprises a stripping unit (210) and a lifting unit (220) for removing the joint box (100) from a slot section. It is characterized in that The side of the joint box (100) is provided with an anti-circumvention component (110) for preventing concrete from circumventing, and the anti-circumvention component (110) is provided with a sensor element (113) for obtaining stress change data inside the concrete. In response to the change of stress data, the stripping unit (210) data-connected to the sensor element (113) can generate and execute corresponding working plans at different coagulation stages of the concrete, so as to control the joint box (100) to complete the working links before formal stripping. The lifting unit (220) can be connected to the joint box (100) so as to pull the joint box (100) out of the slot section after formal stripping is completed.
2. The system according to claim 1, characterized in that The stripping unit (210) comprises a second control component (212), and the second control component (212) is connected to a plurality of jacks (120) arranged along the front height direction of the joint box (100) through a hydraulic pipe. When the joint box (100) is formally stripped, the second control component (212) controls a plurality of the jacks (120) adjacent to the top of the joint box (100) to start before a plurality of the jacks (120) adjacent to the bottom of the joint box (100), so that the joint box (100) can be stripped laterally in a manner that the top of the joint box (100) is separated from the concrete before the bottom.
3. The system according to claim 1, characterized in that The stripping unit (210) comprises a tube pulling machine (213) for laterally stripping the joint box (100) and a second control component (212) connected to the tube pulling machine (213) by data. The pipe pulling machine (213) can clamp the part of the joint box (100) exposed to the ground when the joint box (100) is formally stripped. The second control component (212) can control the pipe pulling machine (213) to perform translational movement on the ground in the form of data instructions, and separate the front side of the joint box (100) from the concrete surface.
4. The system according to any one of claims 1 to 3, characterized in that: The bypass prevention assembly (110) is configured as a double-layer detachable hollow expansion bladder that matches the length of the joint box (100), and the expansion bladder comprises an inner bladder body (112) and an elastic outer bladder body (111) that covers the surface of the inner bladder body (112). The stripping unit (210) includes a first control component (211) for injecting or extracting a fluid medium into the inner sac (112), and the first control component (211) executing the working scheme changes the distance between the outer wall of the outer sac (111) and the groove wall of the underground continuous wall groove section in such a way as to increase or decrease the internal pressure of the inner sac (112).
5. The system according to any one of claims 1 to 4, characterized in that: The working scheme generated by the stripping unit (210) includes: When the sensing element (113) obtains that the internal stress of the concrete reaches a first threshold value at which the flow characteristics disappear, the first control component (211) adjusts the internal pressure of the inner bladder (112) to a first pressure; When the sensor element (113) obtains that the internal stress of the concrete reaches a second threshold value that satisfies the removal condition of the joint box (100), the first control component (211) adjusts the internal pressure of the inner bladder (112) to a second pressure.
6. The system according to any one of claims 1 to 5, characterized in that: The first control component (211) can adjust the pressure of the inner capsule (112) to different values in different working stages of the joint box (100) according to the chronological order, wherein: The first control component (211) is capable of adjusting the internal pressure of the inner bladder (112) to an initial pressure when entering the bypass prevention phase; adjusting the internal pressure of the inner bladder (112) to a first pressure when entering the stripping preparation phase; and adjusting the internal pressure of the inner bladder (112) to a second pressure when entering the formal stripping phase. The first control component (211) is also data-connected to the lifting unit (220) so as to send a prompt message to the lifting unit (220) in the form of a data instruction after the formal stripping phase is completed, so that the lifting unit (220) can be started when entering the lifting phase to pull out the joint box (100) connected thereto.
7. The system according to any one of claims 1 to 6, characterized in that: At least two sections of the inner bladder (112) located at different heights are arranged inside the outer bladder (111). In the anti-bypass stage and the stripping preparation stage, the first control component (211) will determine the independent pressure size and pressure adjustment timing for the upper section of the inner bladder (112) and the lower section of the inner bladder (112) based on the pre-known geological parameters associated with the stratum in which the joint box (100) is embedded, and the permeability parameters of the concrete relative to the stratum.
8. The system according to any one of claims 1 to 7, characterized in that: The sensor element (113) is arranged on a side surface of the joint box (100) adjacent to the bypass prevention assembly (110), and can be embedded under the side surface layer of the joint box (100) while maintaining contact with concrete.
9. The system according to any one of claims 1 to 8, characterized in that: The front of the joint box (100) is provided with a vertical slot, in which a water stop strip (130) is inserted. When the joint box (100) is removed, the water stop strip (130) can be kept in the concrete structure to provide sealing for the joint of the underground continuous wall groove section.
10. An auxiliary method for underground continuous wall construction, characterized in that: The method comprises the following steps: Acquiring the data of stress variation inside the concrete, and generating corresponding working plans by the stripping unit (210) at different setting stages of the concrete; Executing the work plan to complete the work steps before formal stripping of the joint box (100); After the formal stripping is completed, the joint box (100) is pulled out from the slot section by the lifting unit (220).