Switching starting method and system of unified power quality controller

Through real-time data acquisition and transfer function calculation control signals, the unified power quality controller realizes fast shutdown and pre-charge soft start, solves the problem of large startup delay in the existing technology, and improves the reliability and timeliness of the controller. Enhanced power system stability.

CN118842003APending Publication Date: 2024-10-25湖南经研电力设计有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410959531.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

The existing unified power quality controller has the problem of large startup process delay and large switching process delay during switching startup, which affects the stability of the power system and the reliability of power supply.

Method used

By acquiring data information in real time, the transfer function of the series-side inverter and parallel-side rectifier is used to calculate the control signal to achieve fast shutdown and pre-charge soft start of the unified power quality controller, including the use of PI controller and limiter processing. Current and voltage signals to optimize the switching start-up process.

Benefits of technology

It improves the reliability, accuracy and timeliness of the unified power quality controller, reduces startup delays, and enhances the stability of the power system and the reliability of power supply.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118842003A_ABST
    Figure CN118842003A_ABST
Patent Text Reader

Abstract

The invention discloses a switching starting method of a unified power quality controller. The method comprises the following steps: acquiring data information of the unified power quality controller and data information of a target power system in real time; when a low-voltage problem occurs, the unified power quality controller is quickly turned off; when the unified power quality controller is rapidly turned off, pre-charging soft start is carried out on the unified power quality controller; and completing switching starting of the unified power quality controller. The invention also discloses a system for realizing the switching starting method of the unified power quality controller. According to the invention, the unified power quality controller can be quickly turned off, and pre-charging soft start can be carried out on the unified power quality controller in the quick turn-off process; therefore, the switching and starting of the unified power quality controller can be realized, the reliability is higher, the accuracy is better, and the timeliness is better.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of electrical automation, and in particular relates to a switching start method and system of a unified power quality controller. Background Art

[0002] With the development of economy and technology and the improvement of people's living standards, electricity has become an indispensable secondary energy source in people's production and life, bringing endless convenience to people's production and life. Therefore, ensuring the stable and reliable supply of electricity has become one of the most important tasks of the power system.

[0003] Supply voltage is an important power supply indicator of the power system. Low voltage power supply will lead to increased line loss, equipment failure, power outages and other problems, and affect the production and life of users. In some power supply areas, the outlet voltage of the power system transformer is in a low voltage state due to seasonal and intermittent fluctuations in load, and the simultaneous impact load will also aggravate the voltage fluctuation; in addition, when there is a large load at the end of the line, it will also lead to the problem of low power supply voltage at the end of the power line. Especially in mountainous and remote areas, some substations have a long power supply radius, poor power quality at the end of the power supply, and low power supply reliability, so that the power supply voltage is often lower than the standard voltage (220V). Too low voltage will cause the user's electrical equipment to fail to work normally, which has a great impact on the regional economy and social stability.

[0004] Therefore, the power system adopts a unified power quality controller solution to achieve the management of low voltage problems. Figure 1 The figure shows a schematic diagram of an existing unified power quality controller connected to a power system. However, after the unified power quality controller is connected to a power system, its complex working state and working process cause the existing unified power quality controller to have problems such as long startup delay and long switching delay when switching and starting; these problems greatly reduce the effect of the unified power quality controller, thus causing certain dangers and impacts on the power system. Summary of the invention

[0005] One of the purposes of the present invention is to provide a switching start method of a unified power quality controller with high reliability, good accuracy and good timeliness.

[0006] A second objective of the present invention is to provide a system for implementing the switching start method of the unified power quality controller.

[0007] The switching start method of the unified power quality controller provided by the present invention comprises the following steps:

[0008] S1. Real-time acquisition of unified power quality controller data information and target power system data information;

[0009] S2. When a low voltage problem occurs in the target power system, the unified power quality controller is quickly shut down according to the output current of the series-side inverter and the grid current of the target power system;

[0010] S3. While the unified power quality controller is quickly shut down in step S2, the unified power quality controller is pre-charged and soft-started according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller;

[0011] S4. Finally, the switching start of the unified power quality controller is completed.

[0012] The step S2 of quickly shutting down the unified power quality controller according to the output current of the series-side inverter and the grid current of the target power system specifically includes the following steps:

[0013] The following formula is used as the transfer function G of the series side inverter i :

[0014]

[0015] Where k pi k is the proportional coefficient of the PI controller of the series side inverter; ii I is the integral coefficient of the PI controller of the series-side inverter; g is the grid current of the target power system; I o is the output current of the series side inverter; I rct is the input current of the parallel side rectifier;

[0016] According to the grid current I of the target power system g , the output current I of the series side inverter o and the input current I of the parallel side rectifier rct The value of the series side inverter is adopted i The control signal of the series-side inverter is calculated, and after being limited by the limiter, it is input to the series-side inverter to achieve rapid shutdown of the unified power quality controller.

[0017] The step S3 of precharging and soft-starting the unified power quality controller according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller specifically includes the following steps:

[0018] The following formula is used as the transfer function G of the parallel side rectifier r :

[0019]

[0020] Where k pr k is the proportional coefficient of the rectifier inner loop PI controller; ir k is the integral coefficient of the rectifier inner loop PI controller; pv k is the proportional coefficient of the voltage outer loop PI controller; iv is the integral coefficient of the voltage outer loop PI controller; V ref is the reference DC bus voltage of the unified power quality controller; V dc is the actual DC bus voltage of the unified power quality controller; sinωt is the grid phase of the target power system; I rct is the input current of the parallel side rectifier; [] is the processing function of the limiter;

[0021] According to the reference DC bus voltage V of the unified power quality controller ref , actual DC bus voltage V dc , the grid phase sinωt of the target power system and the input current I of the parallel side rectifier rct , using the transfer function G of the parallel side rectifier r The control signal of the parallel side rectifier is calculated and input to the parallel side rectifier to realize the pre-charging soft start of the unified power quality controller.

[0022] The present invention also provides a system for implementing the switching start method of the unified power quality controller, comprising a data acquisition module, a fast shutdown module, a charging start module and a switching start module; the output of the data acquisition module is simultaneously input into the fast shutdown module and the charging start module, and the output of the fast shutdown module and the charging start module is simultaneously input into the switching start module; the data acquisition module is used to acquire data information of the unified power quality controller and data information of the target power system in real time, and upload the data information to the fast shutdown module; the fast shutdown module is used to, according to the received data information, when a low voltage problem occurs in the target power system, quickly shut down the unified power quality controller according to the output current of the series side inverter and the grid current of the target power system, and upload the data information to the charging start module; the charging start module is used to, according to the received data information, perform pre-charging soft start on the unified power quality controller according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller while the fast shutdown module quickly shuts down the unified power quality controller, and uploads the data information to the switching start module; the switching start module is used to complete the switching start of the unified power quality controller according to the received data information.

[0023] The switching and starting method and system of the unified power quality controller provided by the present invention can quickly shut down the unified power quality controller, and pre-charge and soft-start the unified power quality controller during the rapid shutdown process; therefore, the present invention can not only realize the switching and starting of the unified power quality controller, but also has higher reliability, better accuracy and better timeliness. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 The figure is a schematic diagram of connecting an existing unified power quality controller to a power grid and a load.

[0025] Figure 2 The figure is a schematic diagram of the method flow of the present invention.

[0026] Figure 3 It is a control schematic diagram of quickly shutting down the unified power quality controller in the method of the present invention.

[0027] Figure 4 The present invention is a control schematic diagram of pre-charging and soft-starting a unified power quality controller in the method of the present invention.

[0028] Figure 5 Schematic diagram of the functional modules of the system of the present invention. DETAILED DESCRIPTION

[0029] like Figure 2 The method flow chart of the method of the present invention is shown as follows: the switching start method of the unified power quality controller disclosed in the present invention comprises the following steps:

[0030] S1. Real-time acquisition of unified power quality controller data information and target power system data information;

[0031] S2. When a low voltage problem occurs in the target power system, the unified power quality controller is quickly shut down according to the output current of the series-side inverter and the grid current of the target power system; specifically, the steps include:

[0032] The following formula is used as the transfer function G of the series side inverter i :

[0033]

[0034] Where k pi k is the proportional coefficient of the PI controller of the series side inverter; ii I is the integral coefficient of the PI controller of the series-side inverter; g is the grid current of the target power system; I o is the output current of the series side inverter; I rct is the input current of the parallel side rectifier;

[0035] like Figure 3 As shown, according to the grid current I of the target power system g , the output current I of the series side inverter o and the input current I of the parallel side rectifier rct The value of the series side inverter is adopted i The control signal of the series-side inverter is calculated and input to the series-side inverter after being limited by the limiter, so as to realize the rapid shutdown of the unified power quality controller;

[0036] The purpose of this step is to quickly shut down the thyristors of the series-side inverter of the unified power quality controller;

[0037] S3. While the unified power quality controller is quickly shut down in step S2, the unified power quality controller is pre-charged and soft-started according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller; specifically comprising the following steps:

[0038] The following formula is used as the transfer function G of the parallel side rectifier r :

[0039]

[0040] Where k pr k is the proportional coefficient of the rectifier inner loop PI controller; ir k is the integral coefficient of the rectifier inner loop PI controller; pv k is the proportional coefficient of the voltage outer loop PI controller; iv is the integral coefficient of the voltage outer loop PI controller; V ref is the reference DC bus voltage of the unified power quality controller; V dc is the actual DC bus voltage of the unified power quality controller; sinωt is the grid phase of the target power system; I rct is the input current of the parallel side rectifier; [] is the processing function of the limiter;

[0041] like Figure 4 As shown, according to the reference DC bus voltage V of the unified power quality controller ref , actual DC bus voltage V dc , the grid phase sinωt of the target power system and the input current I of the parallel side rectifier rct , using the transfer function G of the parallel side rectifier r The control signal of the parallel side rectifier is calculated and input to the parallel side rectifier to realize the pre-charging soft start of the unified power quality controller;

[0042] Steps S2 and S3 of the present invention are performed in parallel, and there is no particular order; step S2 performs a rapid shutdown of the thyristor of the series-side inverter of the unified power quality controller; however, rapid shutdown still requires a certain process and time; therefore, within this time, the parallel-side rectifier of the unified power quality controller is pre-charged and soft-started through the technical solution of this step;

[0043] S4. Finally, the switching start of the unified power quality controller is completed.

[0044] like Figure 5 The functional module schematic diagram of the system of the present invention is shown as follows: the system for implementing the switching start method of the unified power quality controller disclosed in the present invention comprises a data acquisition module, a fast shutdown module, a charging start module and a switching start module; the output of the data acquisition module is simultaneously input into the fast shutdown module and the charging start module, and the output of the fast shutdown module and the charging start module is simultaneously input into the switching start module; the data acquisition module is used to acquire the data information of the unified power quality controller and the data information of the target power system in real time, and upload the data information to the fast shutdown module; the fast shutdown module is used to, according to the received data information, when the target power system has a low voltage problem, quickly shut down the unified power quality controller according to the output current of the series side inverter and the grid current of the target power system, and upload the data information to the charging start module; the charging start module is used to, according to the received data information, perform pre-charging soft start on the unified power quality controller according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller while the fast shutdown module quickly shuts down the unified power quality controller, and uploads the data information to the switching start module; the switching start module is used to complete the switching start of the unified power quality controller according to the received data information.

Claims

1. A switching start method of a unified power quality controller, comprising the following steps: S1. Real-time acquisition of unified power quality controller data information and target power system data information; S2. When a low voltage problem occurs in the target power system, the unified power quality controller is quickly shut down according to the output current of the series-side inverter and the grid current of the target power system; S3. While quickly shutting down the unified power quality controller, pre-charging and soft-starting the unified power quality controller according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller; S4. Finally, the switching start of the unified power quality controller is completed.

2. The switching start method of the unified power quality controller according to claim 1, characterized in that The step S2 of quickly shutting down the unified power quality controller according to the output current of the series-side inverter and the grid current of the target power system specifically includes the following steps: The following formula is used as the transfer function G of the series side inverter i : Where k pi k is the proportional coefficient of the PI controller of the series side inverter; ii I is the integral coefficient of the PI controller of the series-side inverter; g is the grid current of the target power system; I o is the output current of the series side inverter; I rct is the input current of the parallel side rectifier; According to the grid current I of the target power system g , the output current I of the series side inverter o and the input current I of the parallel side rectifier rct The value of the series side inverter is adopted i The control signal of the series-side inverter is calculated, and after being limited by the limiter, it is input to the series-side inverter to achieve rapid shutdown of the unified power quality controller.

3. The switching start method of the unified power quality controller according to claim 2, characterized in that The step S3 of precharging and soft-starting the unified power quality controller according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller specifically includes the following steps: The following formula is used as the transfer function G of the parallel side rectifier r : Where k pr k is the proportional coefficient of the rectifier inner loop PI controller; ir k is the integral coefficient of the rectifier inner loop PI controller; pv k is the proportional coefficient of the voltage outer loop PI controller; iv is the integral coefficient of the voltage outer loop PI controller; V ref is the reference DC bus voltage of the unified power quality controller; V dc is the actual DC bus voltage of the unified power quality controller; sinωt is the grid phase of the target power system; I rct is the input current of the parallel side rectifier; [] is the processing function of the limiter; According to the reference DC bus voltage V of the unified power quality controller ref , actual DC bus voltage V dc , the grid phase sinωt of the target power system and the input current I of the parallel side rectifier rct , using the transfer function G of the parallel side rectifier r The control signal of the parallel side rectifier is calculated and input to the parallel side rectifier to realize the pre-charging soft start of the unified power quality controller.

4. A system for implementing the switching start method of the unified power quality controller according to any one of claims 1 to 3, characterized in that It includes a data acquisition module, a fast shutdown module, a charging start module and a switching start module; the output of the data acquisition module is simultaneously input to the fast shutdown module and the charging start module, and the output of the fast shutdown module and the charging start module is simultaneously input to the switching start module; the data acquisition module is used to obtain the data information of the unified power quality controller and the target power system data information in real time, and upload the data information to the fast shutdown module; The fast shutdown module is used to quickly shut down the unified power quality controller according to the received data information when a low voltage problem occurs in the target power system, based on the output current of the series-side inverter and the grid current of the target power system, and upload the data information to the charging start module; the charging start module is used to pre-charge and soft-start the unified power quality controller according to the reference DC bus voltage and the actual DC bus voltage of the unified power quality controller while the fast shutdown module quickly shuts down the unified power quality controller according to the received data information, and upload the data information to the switching start module; the switching start module is used to complete the switching start of the unified power quality controller according to the received data information.