Software development progress early warning method and system
By using data acquisition, project rating, exception warning and comprehensive control modules in the software development progress early warning system, the problems of poor prediction accuracy and inability to adjust quickly in the existing technology are solved, and efficient software development progress management and early warning are achieved to ensure Finished on time.
Patent Information
- Application Number
- CN202410898180.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-05
- Publication Date
- 2024-10-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When the existing software development progress warning system handles multiple requirements and different development stages, the prediction accuracy is poor and the inability to quickly adjust leads to defects such as slow software development progress and inability to be successfully completed.
Design a software development progress early warning system. Through the data acquisition module, project rating module, exception early warning module and comprehensive control module, it obtains branch project data, calculates the difficulty level and standard time, provides early warning and adjusts strategies to ensure that software development is completed on time.
It improves the accuracy of software development progress prediction and early warning, enables dynamic adjustment of strategies, avoids problems that lead to slow progress and fails to complete development smoothly, and improves the efficiency and quality of software development.
Smart Images

Figure CN118860465A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of software development, and in particular to a software development progress early warning method and system. Background Art
[0002] Software is generally implemented in a certain programming language. Software development tools are usually used for development. Software is divided into system software and application software. It does not only include programs that can be run on computers, but also files related to these programs are generally considered to be part of the software. With the globalization of the economy and the continuous improvement of software technology, there are more and more types of software on the market. Software has also developed from being simple, monotonous, and single in technology to integrating multiple technologies, with diversified functions and diversified market demands. Software development is the process of building a software system or the software part of a system according to customer requirements. Software development is a systematic project that includes demand capture, demand analysis, design, implementation, and testing.
[0003] The existing application publication number is CN107679683B, and the Chinese invention patent named Software Development Progress Warning Method and Device points out that the total Story points corresponding to the current version and the preset development cycle corresponding to the current version are obtained; the Story points to be delivered within the preset monitoring cycle are obtained according to the preset development cycle and the total Story points; the Story points actually delivered within the preset monitoring cycle are obtained, and the actual delivery rate is obtained according to the actually delivered Story points and the Story points to be delivered; the preset delivery rate threshold is read from the database, the actual delivery rate is compared with the delivery rate threshold, and the warning information corresponding to the version delivery progress is generated according to the comparison result; the warning information corresponding to the version delivery progress is sent to the terminal. The software development efficiency is improved.
[0004] However, according to the above content and in combination with the prior art, the effect of the solution recorded in the above patent is very limited. The solution adopted above is mainly to judge customer needs, directly predict the progress of software development based on customer demand data, and then compare the predicted development progress with the actual development progress, and judge whether the development progress is too slow based on the comparison results. However, in the actual software development process, the difficulty of requirements varies, and when there are multiple requirements, the response will be complicated when multiple requirements are combined, and at different stages of software development, affected by experience, the time taken to develop requirements of the same difficulty is also different. Therefore, the software development process is not a simple division of time directly according to demand. The accuracy of the solution recorded in the above patent is relatively poor, and the prediction results are inaccurate, which does not meet people's usage requirements. For this reason, we have developed a software development progress early warning method and system. Summary of the invention
[0005] 1. Technical issues to be solved
[0006] In view of the deficiencies in the prior art, the present invention provides a software development progress warning method and system, which, when used, obtains data of branch projects based on the classification of existing software development projects, and rates the branch projects, and predicts the time required for the projects based on the results of the project rating. The overall prediction accuracy is relatively high, and the project warning is achieved based on the difference between the actual progress and the predicted progress. The software development completion time can be predicted, and the corresponding strategy can be dynamically adjusted according to the customer's requirements, thereby ensuring that the software development can be completed smoothly on time, effectively avoiding the existing software development progress warning system that only has warnings but cannot generate corresponding strategies based on the warnings, and avoiding the defect that the software development progress is slow and cannot be quickly adjusted, resulting in the failure of the software development to be successfully completed. The method and system have good use effects and good prospects for use.
[0007] (II) Technical solution
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0009] A software development progress warning system includes a data acquisition module, a project rating module, an abnormal warning module, a progress analysis module and a comprehensive control module:
[0010] A data acquisition module is used to acquire data of a software development project, where the data of the software development project includes data of various branch projects constituting the project;
[0011] The project rating module is used to process the acquired branch project data, calculate the difficulty level of the branch project, obtain the branch project data of the same difficulty level closest to the current time from the database, and calculate the standard time of the corresponding branch project based on the acquired data;
[0012] The abnormal warning module is used to obtain the actual progress Sjjd of the branch project fed back by the software developers, calculate the standard progress Bzjd according to the standard time of the corresponding branch project, and calculate the difference between the actual progress Sjjd and the standard progress Bzjd, compare the difference with the set threshold range, and execute the corresponding warning strategy according to the comparison result;
[0013] The progress analysis module is used to obtain the time actually spent on completing some branch projects in the software development, calculate the remaining time spent on the entire software development project, and predict the completion time of the software development based on the remaining time;
[0014] The comprehensive control module is used to obtain the time required by customers, compare the time requirements with the software development completion time, and perform corresponding strategy adjustments based on the comparison results.
[0015] Preferably, the calculation formula for the difficulty level of the branch project is as follows:
[0016]
[0017] In the formula, Nddj is the difficulty level of the branch project, A is the constant coefficient, n is the number of customer requirements in the branch project, and Fzxd i is the complexity of the i-th customer demand, Djxs is the level coefficient corresponding to the customer demand;
[0018] The formula for calculating the standard time Bzsj of the corresponding branch project is as follows:
[0019]
[0020] In the formula, ceil() is a round-up function, Rs is the number of staff members of the branch project with the same difficulty level closest to the current time, Sysj is the time taken to complete the branch project with the same difficulty level closest to the current time, Rsdq is the number of staff members of the current branch project, The bonus ratio of the i-th staff member's experience to the speed of his / her personal development branch project;
[0021] α is a constant coefficient, 8<α<10, and β is the number of times the former branch project staff has worked on branch projects.
[0022] Preferably, the calculation formula for calculating the standard progress Bzjd according to the standard time of the corresponding branch project is as follows:
[0023]
[0024] Where Dqsj is the time it takes for software developers to feedback the actual progress Sjjd of the branch project, and Bzsj is the calculated standard time of the branch project.
[0025] Preferably, the threshold interval is set to [0-Fdz, 0+Fdz], and the calculation formula of the floating value Fdz is as follows:
[0026]
[0027] In the formula, int() is the floor rounding function;
[0028] The corresponding early warning strategies are implemented according to the comparison results as follows:
[0029] When Sjjd-Bzjd is within the threshold interval [0-Fdz, 0+Fdz], no adjustment is made;
[0030] When Sjjd-Bzjd is outside the threshold interval [0-Fdz, 0+Fdz] and Sjjd-Bzjd<0-Fdz, an abnormal progress warning is issued;
[0031] During the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(0,3), the first-level warning, is given;
[0032] In the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(3,8), secondary warning, increase the number of software developers;
[0033] During the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(8,100), level 3 warning, replace the software development team, and increase the number of software developers;
[0034] When Sjjd-Bzjd is outside the threshold interval [0-Fdz, 0+Fdz] and Sjjd-Bzjd>0+Fdz, review the data that has been developed during the software development process.
[0035] Preferably, the formula for calculating the remaining time Sysc spent on the entire software development project is as follows:
[0036]
[0037] In the formula, B is the number of branch projects that are actually completed in the software development, C is the number of all branch projects in the software development, D is the number of remaining unfinished branch projects, Sjsc i Nddj is the usage time of the completed i-th branch project. i is the difficulty level of the completed i-th branch project, The total difficulty level of the remaining unfinished branch projects. is the time to start the i-th remaining unfinished project.
[0038] Preferably, the calculation formula for predicting the software development completion time based on the remaining time is as follows:
[0039]
[0040] Among them, Wcsj is the predicted time for software development to be completed, Kfsc is the number of days used for software development so far, and Dqrq is the current date.
[0041] Preferably, when comparing the customer required time with the software development completion time, the order of the customer required time Sjyq and the software development completion time Wcsj is compared;
[0042] If the software development completion time Wcsj is before the customer's required time Sjyq or is on the same day, no adjustment will be made;
[0043] If the software development completion time Wcsj is behind the customer required time Sjyq, an early warning is issued and the strategy is adjusted to increase the number of software developers.
[0044] Preferably, the calculation formula for increasing the number of software developers is as follows:
[0045]
[0046] Where Zjsl is the number of additional software developers, and Syxs is the adaptation coefficient of the newly added software developers.
[0047] Preferably, the calculation formula for the adaptation coefficient of the newly added software developer is as follows:
[0048]
[0049] In the formula, δ and η are constant coefficients, -0.1<δ<0, η>2.
[0050] Preferably, a software development progress early warning method comprises the following steps:
[0051] Acquire data of a software development project, where the data of the software development project includes data of various branch projects constituting the project;
[0052] Process the acquired branch project data, calculate the difficulty level of the branch project, and acquire the branch project data of the same difficulty level closest to the current time from the database, and calculate the standard time of the corresponding branch project based on the acquired data;
[0053] Obtain the actual progress Sjjd of the branch project fed back by the software developers, calculate the standard progress Bzjd according to the standard time of the corresponding branch project, and calculate the difference between the actual progress Sjjd and the standard progress Bzjd, compare the difference with the set threshold range, and execute the corresponding early warning strategy according to the comparison result;
[0054] Obtain the time actually spent on completing some branch projects in the software development, calculate the remaining time spent on the entire software development project, and predict the completion time of the software development based on the remaining time;
[0055] Obtain the time required by the customer, compare the time requirement with the software development completion time, and make corresponding strategy adjustments based on the comparison results.
[0056] (III) Beneficial effects
[0057] The present invention provides a software development progress early warning method and system, which has the following beneficial effects:
[0058] 1. The present invention records a software development progress warning system, which, when used, obtains data of branch projects based on the classification of existing software development projects, and rates branch projects, and predicts the time used for the project according to the results of the project rating. The overall prediction accuracy is relatively high, and the project warning is realized according to the difference between the actual progress and the predicted progress, and the software development completion time can be predicted, and the corresponding strategy can be dynamically adjusted according to the customer's requirements, so as to ensure that the software development can be completed smoothly on time, effectively avoiding the existing software development progress warning system that only has warnings but cannot generate corresponding strategies according to the warnings, and avoids the defect that the software development progress is slow and cannot be adjusted quickly, resulting in the failure of the software development to be completed smoothly. The use effect is good and has a good use prospect;
[0059] 2. The present invention records a software development progress warning system, which fully considers the number of customer needs, the complexity of customer needs and the overall difficulty of combining the needs when calculating the difficulty level, and the result of difficulty level calculation is more representative. At the same time, when predicting the standard time of branch projects, it fully considers the influence of software developer experience and team size, so that the calculated standard time of the corresponding branch project is more accurate. Therefore, it is more reasonable and accurate to use it to compare with the actual progress, and the accuracy of subsequent calculations based on the data is also correspondingly improved, the warning effect is good, and it has a good prospect for use.
[0060] 3. The present invention records a software development progress warning system, which can predict the completion time of software development, judge whether it can be completed within the time required by the customer based on the predicted software development completion time, and execute corresponding strategies in different situations. There is no need for management personnel to understand the software development progress and formulate corresponding plans separately, which can greatly reduce the workload of management personnel, and its strategy plan is relatively reasonable, which can effectively avoid multiple adjustments, shorten the adjustment time, and improve the efficiency of software development. The overall use effect is good and has a good prospect for use. BRIEF DESCRIPTION OF THE DRAWINGS
[0061] Figure 1 This is a structural block diagram of a software development progress early warning system of the present invention;
[0062] Figure 2 The present invention is a flowchart of the steps of a software development progress early warning method. DETAILED DESCRIPTION
[0063] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0064] Design significance
[0065] The solution adopted by the existing software development progress warning system is mainly to judge customer needs, directly predict the progress of software development based on customer demand data, and then compare the predicted development progress with the actual development progress, and judge whether the development progress is too slow based on the comparison results. However, in the actual software development process, the difficulty of requirements varies, and when there are multiple requirements, the response will be complicated when multiple requirements are combined. Moreover, at different stages of software development, affected by experience, the time taken to develop requirements of the same difficulty is also different. Therefore, the software development process is not a simple division of time directly according to requirements. The accuracy of existing system predictions is relatively poor, the prediction results are inaccurate, and false alarms often occur.
[0066] In the process of software development, the use of project progress management can improve the efficiency and quality of software development, improve software project management, improve the quality of enterprise products, improve the economic benefits of enterprises, and at the same time improve the competitiveness of enterprises; however, if the progress management method adopted in the software development process is unscientific and imperfect, it will not only fail to play the above role, but will even hinder the development of enterprises and bring adverse effects. The quality of products will affect customer satisfaction, the brand image of the enterprise itself, and the future development of the enterprise. Therefore, in the development process, whether the software project progress management is scientific or not is very important. To improve the software project progress management, we have developed a software development progress early warning system.
[0067] R&D content
[0068] Embodiment 1, as Figure 1 As shown, a software development progress warning system includes a data acquisition module, a project rating module, an abnormality warning module, a progress analysis module and a comprehensive control module.
[0069] Data collection
[0070] Software development progress warning is based on the prediction of software progress to determine whether the actual software development progress is lagging behind. Therefore, it requires relevant data in the software development process, and the collection of relevant data in the software development process is based on the data acquisition module.
[0071] The data acquisition module is used to acquire the data of the software development project, and the data of the software development project includes the data of each branch project constituting the project.
[0072] Because software development projects consist of many parts, during the entire process, the entire project will be divided into various parts, and then the divided branch projects will be developed sequentially or simultaneously.
[0073] This patent is based on the early warning of the progress of existing software development projects after segmentation. It does not require the software development projects to be segmented again separately, thereby improving the efficiency of the entire software development progress early warning system.
[0074] The data of branch projects include software development progress data, customer demand data in the branch projects after division, and the difficulty of realizing customer demand (in the process of dividing the software development project into branch projects, the customer demand in the branch projects will be rated, generally divided into level one ordinary difficulty, level two difficult and level three difficult).
[0075] Level setting
[0076] After the data of the branch projects are obtained, in order to better predict the branch projects, it is necessary to formulate a set of standards for the branch projects, that is, to rate the difficulty of the branch projects, and the rating is based on the project rating module.
[0077] The project rating module is used to process the acquired branch project data, calculate the difficulty level of the branch project, obtain the branch project data of the same difficulty level closest to the current time from the database, and calculate the standard time of the corresponding branch project based on the acquired data;
[0078] The calculation formula for the difficulty level of the branch project is as follows:
[0079]
[0080] In the formula, Nddj is the difficulty level of the branch project, A is the constant coefficient, n is the number of customer requirements in the branch project, and Fzxd i is the complexity of the i-th customer demand, Djxs is the level coefficient corresponding to the customer demand;
[0081] For example, there are three customer requirements in a branch project, and the levels of the three requirements are level 1, level 2, and level 3, respectively. A is 2, Djxs is 0.8, and the calculated difficulty level of the branch project is
[0082] The formula for calculating the standard time Bzsj of the corresponding branch project is as follows:
[0083]
[0084] In the formula, ceil() is a round-up function, Rs is the number of staff members of the branch project with the same difficulty level closest to the current time, Sysj is the time taken to complete the branch project with the same difficulty level closest to the current time, Rsdq is the number of staff members of the current branch project, It is the ratio of the i-th staff member's experience to the speed of his / her personal development of branch projects; the staff member's experience is the number of branch projects of the same difficulty level and higher difficulty level completed.
[0085] α is a constant coefficient, 5<α<7, and β is the number of times the former branch project staff has worked on branch projects.
[0086] is the average difficulty level that a single person can complete in a single day. For example, if an old employee completes 15 branch projects of the same difficulty level and α is 6, then the bonus ratio is
[0087] For example, a new employee completes three branch projects of the same difficulty level, and α is 6, then the bonus ratio is
[0088]
[0089] Add up the difficulty levels that all members of the team can complete in a single day, predict the difficulty level that the team can complete in a single day, and then divide the total difficulty level of the branch project by the difficulty level that the team can complete in a single day to calculate the number of days.
[0090] For example, the difficulty level that all team members can complete in a single day is The total difficulty level Nddj of the branch project is 6.79, so the standard time of the corresponding branch project is sky.
[0091] The present invention records a software development progress warning system, which fully considers the number of customer requirements, the complexity of customer requirements and the overall difficulty of combining the requirements when calculating the difficulty level, and the result of difficulty level calculation is more representative. At the same time, when predicting the standard time of branch projects, it fully considers the influence of software developer experience and team size, so that the calculated standard time of the corresponding branch project is more accurate. Therefore, it is more reasonable and accurate to use it to compare with the actual progress, and the accuracy of subsequent calculations based on the data is also correspondingly improved, the warning effect is good, and it has a good prospect of use.
[0092] Abnormal warning
[0093] In the process of software development, sometimes in order to perfectly meet customer needs, it is necessary to consider many aspects. Therefore, jams may occur in the process. It is normal to get stuck as long as the jam time is within the preset fluctuation range. However, once the jam time is long, it will delay the progress of software development. At this time, it is necessary to alert the relevant technical personnel and management personnel to change the solution in time or ask other personnel to deal with the problem. This process is based on the abnormal warning module.
[0094] The abnormal warning module is used to obtain the actual progress Sjjd of the branch project fed back by the software developers, calculate the standard progress Bzjd according to the standard time of the corresponding branch project, and calculate the difference between the actual progress Sjjd and the standard progress Bzjd, compare the difference with the set threshold range, and execute the corresponding warning strategy according to the comparison result;
[0095] The calculation formula for the standard progress Bzjd based on the standard time of the corresponding branch project is as follows:
[0096]
[0097] Where Dqsj is the time it takes for software developers to feedback the actual progress Sjjd of the branch project, and Bzsj is the calculated standard time of the branch project.
[0098] Software developers will report the overall progress when they complete a certain stage, usually on a daily basis. They can also calculate the standard progress Bzjd after each reporting date based on the project schedule and then compare the results.
[0099] For example, on the 8th working day, calculate the standard progress
[0100] The threshold interval is set to [0-Fdz, 0+Fdz], and the calculation formula of the floating value Fdz is as follows:
[0101]
[0102] In the formula, int() is the floor rounding function;
[0103] Calculate
[0104] The corresponding early warning strategies are implemented according to the comparison results as follows:
[0105] When Sjjd-Bzjd is within the threshold interval [0-Fdz, 0+Fdz], no adjustment is made. This is a normal stuck time and can be expected. Therefore, there is no need to adjust the strategy at this stage.
[0106] When Sjjd-Bzjd is outside the threshold interval [0-Fdz, 0+Fdz] and Sjjd-Bzjd<0-Fdz, an abnormal progress warning is issued;
[0107] During the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(0,3), the first-level warning, is given. It is a long-term stuck stage. If the staff can handle it in a short time, there is no need to adjust the strategy;
[0108] In the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(3,8), secondary warning, increase the number of software developers;
[0109] This situation is quite serious and has been stuck for a long time, so corresponding adjustments are needed.
[0110] During the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(8,100), level 3 warning, replace the software development team, and increase the number of software developers;
[0111] This situation is very serious and usually cannot be handled by the staff. At this time, the software development team needs to be replaced to carry out the development work.
[0112] 0 is the most commonly used basic value. If the current development progress is too slow or too fast and it is determined that it does not affect the progress, it is used as the basis and 0 is adjusted to the corresponding positive or negative integer.
[0113] The above warning is used for branch projects where the standard time Bzsj is greater than 10 days. If it is less than 10 days, the project difficulty is low and there will be no jams normally. If there are jams, they are easy to find, so there is no need to calculate.
[0114] When Sjjd-Bzjd is outside the threshold interval [0-Fdz, 0+Fdz] and Sjjd-Bzjd>0+Fdz, review the data that has been developed during the software development process.
[0115] This situation is that the completion exceeds expectations. At this time, a review is conducted to reduce the occurrence of abnormalities and reduce the workload of subsequent verification.
[0116] Progress Analysis
[0117] Software development not only requires the management and control of each branch project, but also the management of the entire software development process. Therefore, it is also necessary to help managers judge the progress of the entire software development. The calculation of the entire software development process depends on the progress analysis module.
[0118] The progress analysis module obtains the time actually spent on completing some branch projects in the software development, calculates the remaining time spent on the entire software development project, and predicts the completion time of the software development based on the remaining time;
[0119] The formula for calculating the remaining time Sysc for the entire software development project is as follows:
[0120]
[0121] In the formula, B is the number of branch projects that are actually completed in the software development, C is the number of all branch projects in the software development, and D is the number of remaining unfinished branch projects. C = B + D, Sjsc i Nddj is the usage time of the completed i-th branch project. i is the difficulty level of the completed i-th branch project, The total difficulty level of the remaining unfinished branch projects. is the time to start the i-th remaining unfinished project.
[0122] In the actual software development process, the next branch project is not started after the completion of one branch project. Usually, there will be cross-projects involved, so multiple branch projects will be started at the same time.
[0123] Therefore, it is necessary to calculate the overall development time and the corresponding total difficulty of each branch project, so as to calculate the time required for each difficulty, and then calculate the difficulty level of all unfinished branch projects, so as to calculate the remaining time Sysc spent on the software development project.
[0124] After knowing the remaining time Sysc, the software development completion time under normal circumstances can be calculated by the remaining time Sysc.
[0125] The calculation formula for predicting the software development completion time based on the remaining time is as follows:
[0126]
[0127] Among them, Wcsj is the predicted time for software development to be completed, Kfsc is the number of days used for software development so far, and Dqrq is the current date.
[0128] During the software development project, Kfsc days are used. The daily working hours can be used to calculate the number of days required by the remaining time and the daily working hours. Adding the current date, the completion time of the software development can be calculated.
[0129] Comprehensive Control
[0130] After understanding the time it takes to complete your own software development, you also need to compare the time it takes to complete the software development with the time required by the customer to determine whether the time is sufficient and whether other measures are needed. This process is based on the comprehensive control module.
[0131] The comprehensive control module obtains the time required by the customer, compares the time requirement with the software development completion time, and performs corresponding strategy adjustments based on the comparison results.
[0132] When comparing the customer's required time with the software development completion time, compare the order of the customer's required time Sjyq and the software development completion time Wcsj;
[0133] If the software development completion time Wcsj is before the customer's required time Sjyq or is on the same day, no adjustment will be made;
[0134] If the software development completion time Wcsj is behind the customer required time Sjyq, an early warning is issued and the strategy is adjusted to increase the number of software developers.
[0135] The present invention records a software development progress warning system, which, when in use, obtains data of branch projects based on the classification of existing software development projects, and rates the branch projects, and predicts the time used for the projects according to the results of the project rating. The overall prediction accuracy is relatively high, and the project warning is realized according to the difference between the actual progress and the predicted progress, and the software development completion time can be predicted, and the corresponding strategy can be dynamically adjusted according to the customer's requirements, so as to ensure that the software development can be completed smoothly on time, effectively avoiding the existing software development progress warning system that only has warnings but cannot generate corresponding strategies according to the warnings, and avoids the defect that the software development progress is slow and cannot be quickly adjusted, resulting in the failure of the software development to be successfully completed. The use effect is good and has a good prospect for use.
[0136] The calculation formula for increasing the number of software developers is as follows:
[0137]
[0138] Where Zjsl is the number of additional software developers, and Syxs is the adaptation coefficient of the newly added software developers.
[0139] Wcsj-Sjyq is the time difference, The total working hours of the additional personnel are calculated by dividing the remaining time difference Sjyq-Dqrq, which is the total working hours of the team every day. Then multiply it by the number of people, which is the total working hours of an individual every day. At this time, divide it by each person's daily workload to calculate the number of additional personnel to be added.
[0140] In practice, the additional personnel are all employees with rich experience, so their efficiency is higher than that of normal employees. Therefore, this calculation method retains a certain amount of time, so there is no need to reserve days separately.
[0141] The calculation formula for the newly added software developer adaptability coefficient is as follows:
[0142]
[0143] In the formula, δ and η are constant coefficients, -0.1<δ<0, η>2.
[0144] As the number of personnel increases, the convenience of personnel work allocation and management decreases. Therefore, their actual work efficiency cannot reach the set value. Therefore, software developers are required to adapt to the coefficient and make corresponding adjustments to make the increased number of personnel accurate and effective.
[0145] The present invention records a software development progress warning system, which can predict the completion time of software development, judge whether it can be completed within the time required by the customer based on the predicted software development completion time, and execute corresponding strategies under different circumstances. There is no need for management personnel to understand the software development progress and formulate corresponding plans separately, which can greatly reduce the workload of management personnel. Moreover, its strategy plan is relatively reasonable and can effectively avoid multiple adjustments. At the same time, it shortens the adjustment time, improves the efficiency of software development, has good overall use effect, and has a good use prospect.
[0146] Example 2
[0147] like Figure 2 As shown, a software development progress early warning method includes the following steps:
[0148] Acquire data of a software development project, where the data of the software development project includes data of various branch projects constituting the project;
[0149] Process the acquired branch project data, calculate the difficulty level of the branch project, and acquire the branch project data of the same difficulty level closest to the current time from the database, and calculate the standard time of the corresponding branch project based on the acquired data;
[0150] Obtain the actual progress Sjjd of the branch project fed back by the software developers, calculate the standard progress Bzjd according to the standard time of the corresponding branch project, and calculate the difference between the actual progress Sjjd and the standard progress Bzjd, compare the difference with the set threshold range, and execute the corresponding early warning strategy according to the comparison result;
[0151] The corresponding early warning strategies are implemented according to the comparison results as follows:
[0152] When the difference is within the threshold range, no adjustment is made;
[0153] When the difference is outside the threshold range, an abnormal progress warning is issued;
[0154] Obtain the time actually spent on completing some branch projects in the software development, calculate the remaining time spent on the entire software development project, and predict the completion time of the software development based on the remaining time;
[0155] Obtain the time required by the customer, compare the time requirement with the software development completion time, and make corresponding strategy adjustments based on the comparison results.
[0156] When comparing the customer's required time with the software development completion time, compare the order of the customer's required time and the software development completion time;
[0157] If the software development completion time is before the customer's required time or on the same day, no adjustment will be made;
[0158] If the software development completion time is behind the customer's requirement, an early warning will be issued and the strategy will be adjusted to increase the number of software developers.
[0159] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters in the formula are set by technicians in this field according to actual conditions.
[0160] The above embodiments may be implemented in whole or in part by software, hardware, firmware or any other combination thereof. When implemented using software, the above embodiments may be implemented in whole or in part in the form of a computer program product. A person of ordinary skill in the art may appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein may be implemented in electronic hardware, or in a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution.
[0161] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, and may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0162] The above description is only a specific implementation manner of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application.
Claims
1. A software development progress early warning system, It is characterized in that include: A data acquisition module is used to acquire data of a software development project, where the data of the software development project includes data of various branch projects constituting the project; The project rating module is used to process the acquired branch project data, calculate the difficulty level of the branch project, obtain the branch project data of the same difficulty level closest to the current time from the database, and calculate the standard time of the corresponding branch project based on the acquired data; The abnormal warning module is used to obtain the actual progress Sjjd of the branch project fed back by the software developers, calculate the standard progress Bzjd according to the standard time of the corresponding branch project, and calculate the difference between the actual progress Sjjd and the standard progress Bzjd, compare the difference with the set threshold range, and execute the corresponding warning strategy according to the comparison result; The progress analysis module is used to obtain the time actually spent on completing some branch projects in the software development, calculate the remaining time spent on the entire software development project, and predict the completion time of the software development based on the remaining time; The comprehensive control module is used to obtain the time required by customers, compare the time requirements with the software development completion time, and perform corresponding strategy adjustments based on the comparison results.
2. A software development progress early warning system according to claim 1, Features: The calculation formula for the difficulty level of the branch project is as follows: In the formula, Nddj is the difficulty level of the branch project, A is the constant coefficient, n is the number of customer requirements in the branch project, and Fzxd i is the complexity of the i-th customer demand, Djxs is the level coefficient corresponding to the customer demand; The formula for calculating the standard time Bzsj of the corresponding branch project is as follows: Where ceil() is a round-up function, Rs is the number of staff members of the branch project with the same difficulty level closest to the current time, Sysj is the time taken to complete the branch project with the same difficulty level closest to the current time, Rsdq is the number of staff members of the current branch project, The bonus ratio of the i-th staff member's experience to the speed of his / her personal development branch project; α is a constant coefficient, 8<α<10, and β is the number of times the former branch project staff has worked on branch projects.
3. A software development progress early warning system according to claim 2, Features: The calculation formula for the standard progress Bzjd based on the standard time of the corresponding branch project is as follows: Where Dqsj is the time it takes for software developers to feedback the actual progress Sjjd of the branch project, and Bzsj is the calculated standard time of the branch project.
4. A software development progress early warning system according to claim 3, Features: The threshold interval is set to [0-Fdz, 0+Fdz], and the calculation formula of the floating value Fdz is as follows: In the formula, int() is the floor rounding function; The corresponding early warning strategies are implemented according to the comparison results as follows: When Sjjd-Bzjd is within the threshold interval [0-Fdz, 0+Fdz], no adjustment is made; When Sjjd-Bzjd<0-Fdz, an abnormal progress warning is issued; During the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(0,3), the first-level warning, is given; In the process of abnormal progress warning, 0-Fdz-(Sjjd-Bzjd)∈(3,8), secondary warning, increase the number of software developers; During the abnormal progress warning process, 0-Fdz-(Sjjd-Bzjd)∈(8,100), level 3 warning, replace the software development team, and increase the number of software developers; When Sjjd-Bzjd>0+Fdz, review the data that has been developed during the software development process.
5. A software development progress early warning system according to claim 4, Features: The formula for calculating the remaining time Sysc for the entire software development project is as follows: In the formula, B is the number of branch projects that are actually completed in the software development, C is the number of all branch projects in the software development, D is the number of remaining unfinished branch projects, Sjsc i Nddj is the usage time of the completed i-th branch project. i is the difficulty level of the completed i-th branch project, The total difficulty level of the remaining unfinished branch projects. is the time to start the i-th remaining unfinished project.
6. A software development progress early warning system according to claim 5, Features: The calculation formula for predicting the software development completion time based on the remaining time is as follows: Among them, Wcsj is the predicted time for software development to be completed, Kfsc is the number of days used for software development so far, and Dqrq is the current date.
7. A software development progress early warning system according to claim 6, Features: When comparing the customer's required time with the software development completion time, compare the order of the customer's required time Sjyq and the software development completion time Wcsj; If the software development completion time Wcsj is before the customer's required time Sjyq or is on the same day, no adjustment will be made; If the software development completion time Wcsj is behind the customer required time Sjyq, an early warning is issued and the strategy is adjusted to increase the number of software developers.
8. A software development progress early warning system according to claim 7, Features: The calculation formula for increasing the number of software developers is as follows: Where Zjsl is the number of additional software developers, and Syxs is the adaptation coefficient of the newly added software developers.
9. A software development progress early warning system according to claim 8, Features: The calculation formula for the newly added software developer adaptability coefficient is as follows: In the formula, δ and η are constant coefficients, -0.1<δ<0, η>2.
10. A software development progress warning method, using any system described in claim 1 to claim 9, It is characterized in that The steps include: Acquire data of a software development project, where the data of the software development project includes data of various branch projects constituting the project; Process the acquired branch project data, calculate the difficulty level of the branch project, and acquire the branch project data of the same difficulty level closest to the current time from the database, and calculate the standard time of the corresponding branch project based on the acquired data; Obtain the actual progress Sjjd of the branch project fed back by the software developers, calculate the standard progress Bzjd according to the standard time of the corresponding branch project, and calculate the difference between the actual progress Sjjd and the standard progress Bzjd, compare the difference with the set threshold range, and execute the corresponding early warning strategy according to the comparison result; Obtain the time actually spent on completing some branch projects in the software development, calculate the remaining time spent on the entire software development project, and predict the completion time of the software development based on the remaining time; Obtain the time required by the customer, compare the time requirement with the software development completion time, and make corresponding strategy adjustments based on the comparison results.