Anti-seismic construction process for urban expressway viaduct

Through seismic design and segment beam assembly process, combined with friction swing support and epoxy resin sealing technology, the problems of large seismic displacement and poor linear control accuracy in overpass construction are solved, and efficient and stable overpass construction is achieved, reducing construction difficulty and environmental impact.

CN118880754APending Publication Date: 2024-11-01QINGDAO ZHONGJIAN COMBINATION CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411222930.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The existing urban expressway overpass construction technology has problems such as large displacement during earthquakes, risk of adjacent cross-collision, difficulty in construction, difficulty in ensuring quality, large environmental impact, and poor linear control accuracy.

Method used

The construction technology adopts seismic design, foundation treatment, pile foundation construction, segment beam assembly, loading and pre-pressing, bridge deck paving, reinforcement and protection, acceptance and maintenance, including the use of friction swing support for seismic design and prefabricated segment boxes Beam, cantilever assembly, epoxy sealing and temporary tensioning technology ensure structural stability and linear accuracy.

Benefits of technology

It achieves good earthquake resistance, reduces the relative displacement of the beam end, reduces construction difficulty and environmental impact, improves linear control accuracy, and ensures the stability and safety of the viaduct.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880754A_ABST
    Figure CN118880754A_ABST
Patent Text Reader

Abstract

The invention discloses an anti-seismic construction technology for an urban expressway viaduct. The anti-seismic construction technology comprises the steps that firstly, anti-seismic design is conducted; 2, foundation treatment; thirdly, pile foundation construction is conducted; step 4, assembling the segmental beams; step 5, loading and pre-pressing; step 6, paving a bridge deck; 7, reinforcement and protection are conducted; step 8, acceptance and maintenance; the reasonable natural vibration period of the friction pendulum support is designed to be smaller than the system period of the viaduct main body structure, meanwhile, the system period of the segmental box girder is close to that of the supporting joint, the good anti-seismic effect is achieved, meanwhile, relative displacement of the girder ends is reduced, and the possibility of mutual collision is reduced; the working procedures of formwork erecting, reinforcing steel bar binding, cast-in-place and the like are omitted on site, the site construction difficulty is reduced to the maximum extent, the site construction quality is guaranteed, interference to the surrounding environment and traffic is avoided, and good economic and environmental benefits are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of viaduct construction, in particular to an earthquake-resistant construction process for an urban expressway viaduct. Background Art

[0002] As an important part of urban transportation, urban expressway viaducts achieve rapid passage of vehicles and reduce ground traffic pressure by building elevated bridges on urban traffic arteries. Their main function is to improve urban traffic efficiency, shorten travel time, reduce traffic congestion, and provide efficient and safe passage conditions for various types of vehicles. The structural design of viaducts usually considers their bearing capacity, stability, durability and seismic performance. The bearing capacity of piers and bridges is determined according to road traffic volume, vehicle quality and other conditions, and attention is paid to the basic seismic design.

[0003] The existing construction technology of urban expressway viaducts has the following defects: First, the viaducts based on friction pendulum shock-absorbing bearings have large displacements during earthquakes, and adjacent spans have the risk of colliding with each other due to the phase difference; second, the traditional construction method requires processes such as supporting formwork, tying steel bars and pouring on site, which is not only difficult to construct, but also difficult to ensure the construction quality, and has a great impact on the surrounding environment; third, the linear control accuracy is poor, and errors will accumulate when splicing different sections, affecting the accuracy of the entire viaduct line. Summary of the invention

[0004] The object of the present invention is to provide a seismic-resistant construction process for an urban expressway viaduct to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above object, the present invention provides the following technical solution: an earthquake-resistant construction process for an urban expressway viaduct, comprising step one, earthquake-resistant design; step two, foundation treatment; step three, pile foundation construction; step four, segment beam assembly; step five, loading and preloading; step six, bridge deck paving; step seven, reinforcement and protection; step eight, acceptance and maintenance; In the above step 1, an earthquake-resistant structure is designed; In the above step 2, the foundation is cleaned, excavated, reinforced, etc.; In the above step 3, drilling construction, steel cage production and installation, concrete pouring and other process operations are carried out according to the design requirements; In the above step 4, the segmental beam is assembled by using a cantilever assembly process; In the above step 5, after the segments are assembled, loading and preloading are performed; In the above step six, the bridge deck paving construction is carried out according to the design requirements; In the above step seven, appropriate reinforcement measures are selected to reinforce the viaduct and provide protective measures; In the above step eight, the project is inspected and maintained in accordance with relevant standards and regulations.

[0006] As a further technical solution of the present invention, in the step one, a friction pendulum bearing is used for earthquake resistance, and the isolation period of the friction pendulum bearing is set so that the system period is greater than the natural vibration period of the structure, thereby achieving the purpose of seismic reduction and isolation. By setting the system period to be more than twice the natural vibration period, a good isolation rate can be obtained. In addition, the system periods of the segmental beams and the support nodes are designed to be close to each other, thereby reducing the relative displacement of the beam ends, creating conditions for the setting of the beam seam width and the expansion joint, and avoiding collision between the beam ends. By setting a reasonable system isolation period, the relative displacement of the two can be controlled within a small range of less than 10 cm. The smaller the relative displacement of the beam ends, the lower the probability of collision.

[0007] As a further technical solution of the present invention, in the step four, the production of prefabricated segmental box girders is carried out in batches to ensure that the quality of each batch is strictly controlled and meets the design requirements. The prefabricated segmental box girders are transported to the construction site after production is completed, a bridge-building machine is set up on site, and the box girders are accurately lifted to the predetermined design elevation and coordinate position using the bridge-building machine. The segmental box girders are then spliced ​​in sequence until the last section of the beam is assembled in place. During the entire assembly process, the connection status between the beam sections is monitored and evaluated to ensure the stability and smoothness of the connection, thereby ensuring that the entire structure can remain stable and safe after completion. After the assembly is completed, the temporary prestress applied previously is removed, and the principle of no tensile stress being generated in the joints is followed to ensure the stability and safety of the entire viaduct structure.

[0008] As a further technical solution of the present invention, in step four, in order to accurately control the position and geometric shape of the segmental beam, it is necessary to set reference control points on each segment. Before temporary tensioning, these reference points will be converted into specific construction control coordinates. These coordinates are further subdivided into axis control points and elevation control points. Using measuring tools such as levels and total stations, the spatial position of the segmental beam is accurately measured and located according to these construction control coordinates. When assembling the next segmental beam, if errors are found in the linear shape between the beam segments, corrective measures are taken. For the parts with larger errors, wedges are used to make adjustments to ensure the accuracy and stability of the entire structure.

[0009] As a further technical solution of the present invention, in the step four, during the splicing operation of the segmental beams, in order to ensure the stability of the overall structure through prestressing, epoxy resin material is used to seal the joints, effectively blocking the potential damage of air and moisture to the prestressed tendons. After the gluing is completed, a temporary tensioning operation is implemented, which helps the rapid curing of the epoxy resin and ensures that the joints are in a tight fit, thereby ensuring the stability and durability of the overall structure.

[0010] As a further technical solution of the present invention, in step four, after the segmental beam is hoisted, a trial assembly step is first performed, the purpose of which is to predetermine the position of the beam segment, thereby reducing the adjustment time after the subsequent application of epoxy resin. During the trial assembly, segmental beam No. 1 is used as a reference, and an eight-point coordinate system is used to finely adjust the spatial position of the segmental beam to be spliced. At the same time, the elevation of the beam segment, the center axis and the alignment of the prestressed duct joints are checked and verified to ensure that all beam segments can be fully matched when spliced, thereby ensuring the accuracy and stability of the overall structure.

[0011] As a further technical solution of the present invention, in the step four, when preparing the epoxy resin glue, the ambient temperature and the expected curing time must be carefully considered. After confirming that the beam section is positioned accurately and all preparations before gluing are ready, the mixing of the glue mortar is started. The mixing and spreading process needs to be completed within the specified time to avoid premature hardening of the glue mortar. Manual spreading is adopted to ensure that the coating reaches a sufficient thickness. At the same time, special attention is paid to the coating of key parts such as shear keys and channels to ensure the uniformity of the coating. Special sealing measures are taken around the prestressed channels to prevent leakage or cross-grouting problems that may occur during the grouting process.

[0012] As a further technical solution of the present invention, in the step four, the main purpose of the temporary tensioning technology is to ensure that the joints between the segments are tightly fitted after the epoxy resin glue is applied, to avoid relative displacement between the segments, so as to ensure that the segments can be smoothly combined into an integral structure. The temporary tensioning operation should be carried out immediately after the epoxy resin glue is applied to make full use of the viscosity of the colloid. In this process, the top plate and bottom plate prefabricated blocks of the prefabricated beam segment are selected as temporary tensioning pedestals, and precision-rolled threaded steel rods are used as prestressed tendons for tensioning. The control principle of the tensioning force is to ensure that no tensile stress is generated in any cross section of the segment, thereby ensuring the stability and safety of the overall structure.

[0013] As a further technical solution of the present invention, in step five, after the segments are assembled, they are loaded and preloaded. This step can simulate the actual load conditions, check the connection conditions between the segment beams and the stability of the overall structure. When the prestressed steel bars are tensioned for the first time, the prestress loss must be accurately measured and compared with the theoretical prestress loss value. If the actual loss value is found to be too large or too small, the tensioning force must be adjusted in time to ensure that the performance of the prestressed steel bars is fully utilized.

[0014] As a further technical solution of the present invention, in step eight, the project is inspected and accepted in accordance with relevant standards and regulations to ensure that the project quality meets the design requirements, and the viaduct is regularly maintained, including cleaning, inspection, repair and other work, to ensure the long-term stable operation of the viaduct.

[0015] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention is designed with a reasonable natural vibration period of the friction pendulum bearing, which is smaller than the system period of the main structure of the viaduct, and at the same time, the system period of the segment box girder and the support node is close to each other, while obtaining a good seismic effect, the relative displacement of the beam ends is reduced, and the possibility of mutual collision is reduced. Through segment prefabrication and cantilever assembly, the processes of supporting formwork, tying steel bars and pouring on site are omitted on site, the difficulty of on-site construction is minimized, the quality of on-site construction is ensured, and interference with the surrounding environment and traffic is avoided, with good economic and environmental benefits. At the same time, by setting reference control points on the segment beams, the linear error between beams is controlled, the linear control accuracy is effectively improved, and the problem of accumulation of splicing errors between different stages is avoided. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 is a flow chart of the method of the present invention; Figure 2 It is a structural schematic diagram of the friction pendulum support of the present invention; Figure 3 It is a schematic diagram of the eight-point coordinate system of the present invention. DETAILED DESCRIPTION

[0017] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0018] Please see attached Figure 1 -Attached Figure 3The present invention provides an embodiment: an earthquake-resistant construction process for an urban expressway viaduct, comprising step one, earthquake-resistant design; step two, foundation treatment; step three, pile foundation construction; step four, segment beam assembly; step five, loading preloading; step six, bridge deck paving; step seven, reinforcement and protection; step eight, acceptance and maintenance; In the above step 1, a friction pendulum bearing is used for earthquake resistance, and the isolation period of the friction pendulum bearing is set so that the system period is greater than the natural vibration period of the structure, thereby achieving the purpose of seismic reduction and isolation. The system period is set to be more than twice the natural vibration period to obtain a good isolation rate. In addition, the system periods of the segmental beam and the support node are designed to be close to each other, thereby reducing the relative displacement of the beam end, creating conditions for the setting of the beam seam width and the expansion joint, and avoiding collision between the beam ends. By setting a reasonable system isolation period, the relative displacement of the two can be controlled within a small range of less than 10 cm. The smaller the relative displacement of the beam end, the lower the probability of collision. In the above step 2, the foundation is cleaned, excavated, reinforced, etc.; In the above step 3, drilling construction, steel cage production and installation, concrete pouring and other process operations are carried out according to the design requirements; In the above step 4, the production of prefabricated segmental box girders is carried out in batches to ensure that the quality of each batch is strictly controlled and meets the design requirements. The prefabricated segmental box girders are transported to the construction site after production is completed, and a bridge-erecting machine is set up on site. The box girders are accurately lifted to the predetermined design elevation and coordinate position using this bridge-erecting machine, and then the segmental box girders are spliced ​​in sequence until the last beam segment is assembled in place. During the entire assembly process, the connection status between the beam segments is monitored and evaluated to ensure the firmness and smoothness of the connection, thereby ensuring that the entire structure can remain stable and safe after completion. After the assembly is completed, the temporary prestressing force applied previously is removed, and the principle of no tensile stress in the joints is followed to ensure the stability and safety of the entire viaduct structure, in order to accurately To control the position and geometry of the segmental beams, reference control points need to be set on each segment. Before temporary tensioning, these reference points will be converted into specific construction control coordinates. These coordinates are further subdivided into axis control points and elevation control points. Using measuring tools such as levels and total stations, the spatial position of the segmental beams is accurately measured and located based on these construction control coordinates. When assembling the next segmental beam, if errors are found in the linear shape between the beam segments, corrective measures are taken. For parts with large errors, wedges are used to make adjustments to ensure the accuracy and stability of the entire structure. In the splicing of segmental beams, in order to ensure the stability of the overall structure through prestressing, epoxy resin materials are used to seal the joints, which effectively blocks The potential damage of air and moisture to prestressed tendons. After the completion of gluing, temporary tensioning operation is carried out, which is conducive to the rapid curing of epoxy resin and ensures that the joints are in a tight fit, thereby ensuring the stability and durability of the overall structure. After the segmental beam is hoisted, the first step is to carry out a trial assembly step. Its purpose is to predetermine the position of the beam segment, thereby reducing the adjustment time after the subsequent application of epoxy resin. During the trial assembly, the No. 1 segmental beam is used as the benchmark, and the eight-point coordinate system is used to make fine adjustments to the spatial position of the segmental beam to be spliced. At the same time, the elevation of the beam segment, the center axis and the alignment of the prestressed duct joints are checked and verified to ensure that all beam segments can be fully matched when spliced ​​to ensure the accuracy and stability of the overall structure. When applying epoxy resin glue, the ambient temperature and the expected curing time must be carefully considered. After confirming that the beam segment is positioned accurately and all preparations before applying the glue are ready, start mixing the glue. The mixing and applying process needs to be completed within the specified time to avoid premature hardening of the glue. Manual application is adopted to ensure that the coating reaches a sufficient thickness. At the same time, special attention is paid to the application of key parts such as shear keys and channels to ensure the uniformity of the coating. Special sealing measures are taken around the prestressed channels to prevent leakage or cross-grouting problems that may occur during the grouting process. The main purpose of temporary tensioning technology is to ensure that the joints between segments after applying epoxy resin glue are tightly fitted to avoid relative displacement between segments, so as to ensure that the segments can be smoothly combined into an overall structure.Temporary tensioning operation should be carried out immediately after the epoxy resin glue is applied to make full use of the viscosity of the glue. In this process, the top plate and bottom plate prefabricated blocks of the prefabricated beam segment are selected as temporary tensioning pedestals, and the precision-rolled threaded steel rods are used as prestressed tendons for tensioning. The control principle of tensioning force is to ensure that no tensile stress is generated in any section of the segment, thereby ensuring the stability and safety of the overall structure; In the above step 5, after the segment is assembled, loading and preloading are carried out. This step can simulate the actual load condition, check the connection between the segment beams and the stability of the overall structure. When the prestressed steel bars are tensioned for the first time, the prestress loss must be accurately measured and compared with the theoretical prestress loss value. If the actual loss value is found to be too large or too small, the tensioning force must be adjusted in time to ensure that the performance of the prestressed steel bars is fully utilized; In the above step six, the bridge deck paving construction is carried out according to the design requirements; In the above step seven, appropriate reinforcement measures are selected to reinforce the viaduct and provide protective measures; In the above step eight, the project is inspected and accepted in accordance with relevant standards and regulations to ensure that the project quality meets the design requirements, and the viaduct is regularly maintained, including cleaning, inspection, repair and other work, to ensure the long-term stable operation of the viaduct.

[0019] Based on the above, the advantages of the present invention are: the present invention uses friction pendulum bearings for earthquake resistance, and its principle is to reduce the effect of earthquakes through various high-damping devices or materials, and use smaller bearing stiffness to isolate the bridge structure from the earthquake effect that causes damage. When using seismic isolation design, due to the differences in dynamic characteristics between different spans, the vibration phases of adjacent spans are often not synchronized when an earthquake occurs, resulting in the collision of the beam ends or the distance between them is too large to tear the telescopic device. Therefore, when designing seismic isolation, it is very necessary to consider the decisive factors that affect the relative displacement of the beam ends. By designing a reasonable natural vibration period of the friction pendulum bearing, it can be made smaller than the main body of the viaduct. The structural system period is shortened, and the system period of the segmental box girder and the supporting node is made close to each other. While obtaining a good seismic effect, the relative displacement of the beam ends is reduced, and the possibility of mutual collision is reduced. Through segment prefabrication and cantilever assembly, the processes of supporting formwork, tying steel bars and pouring on site are omitted, which minimizes the difficulty of on-site construction, ensures the quality of on-site construction, avoids interference with the surrounding environment and traffic, and has good economic and environmental benefits. At the same time, by setting reference control points on the segmental beams, the linear error between beams is controlled, which effectively improves the linear control accuracy and avoids the problem of accumulation of splicing errors between different stages.

[0020] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A seismic construction process for an urban expressway viaduct, comprising step 1, seismic design; step 2, foundation treatment; step 3, pile foundation construction; step 4, segment beam assembly; step 5, loading preloading; step 6, bridge deck paving; step 7, reinforcement and protection; step 8, acceptance and maintenance; characterized in that: In the above step 1, an earthquake-resistant structure is designed; In the above step 2, the foundation is cleaned, excavated, reinforced, etc.; In the above step 3, drilling construction, steel cage production and installation, concrete pouring and other process operations are carried out according to the design requirements; In the above step 4, the segmental beam is assembled by using a cantilever assembly process; In the above step 5, after the segments are assembled, loading and preloading are performed; In the above step six, the bridge deck paving construction is carried out according to the design requirements; In the above step seven, appropriate reinforcement measures are selected to reinforce the viaduct and provide protective measures; In the above step eight, the project is inspected and maintained in accordance with relevant standards and regulations.

2. The seismic construction process for an urban expressway viaduct according to claim 1, characterized in that: In the step one, a friction pendulum bearing is used for earthquake resistance, and the isolation period of the friction pendulum bearing is set so that the system period is greater than the natural vibration period of the structure, thereby achieving the purpose of seismic reduction and isolation. By setting the system period to be more than twice the natural vibration period, a good isolation rate can be obtained. In addition, the system periods of the segmental beam and the support node are designed to be close to each other, thereby reducing the relative displacement of the beam ends, creating conditions for the setting of the beam seam width and the expansion joint, and avoiding collision between the beam ends. By setting a reasonable system isolation period, the relative displacement of the two can be controlled within a small range of less than 10 cm. The smaller the relative displacement of the beam ends, the lower the probability of collision.

3. The earthquake-resistant construction process for an urban expressway viaduct according to claim 1, characterized in that: In the step 4, the prefabricated segmental box girders are manufactured in batches to ensure that the quality of each batch is strictly controlled and meets the design requirements. The prefabricated segmental box girders are transported to the construction site after production is completed, a bridge-building machine is set up on site, and the box girders are accurately lifted to the predetermined design elevation and coordinate position using the bridge-building machine. The segmental box girders are then spliced ​​in sequence until the last beam segment is assembled in place. During the entire assembly process, the connection status between the beam segments is monitored and evaluated to ensure the stability and smoothness of the connection, thereby ensuring that the entire structure can remain stable and safe after completion. After assembly is completed, the temporary prestress applied previously is removed, and the principle of no tensile stress being generated in the joints is followed to ensure the stability and safety of the entire viaduct structure.

4. The earthquake-resistant construction process for an urban expressway viaduct according to claim 3 is characterized in that: In the step 4, in order to accurately control the position and geometric shape of the segmental beam, it is necessary to set reference control points on each segment. Before temporary tensioning, these reference points will be converted into specific construction control coordinates. These coordinates are further subdivided into axis control points and elevation control points. Using measuring tools such as levels and total stations, the spatial position of the segmental beam is accurately measured and located according to these construction control coordinates. When assembling the next segmental beam, if errors are found in the linear shape between the beam segments, corrective measures are taken. For parts with larger errors, wedges are used to make adjustments to ensure the accuracy and stability of the entire structure.

5. The earthquake-resistant construction process for an urban expressway viaduct according to claim 3, characterized in that: In the step 4, during the splicing operation of the segmental beams, in order to ensure the stability of the overall structure through prestressing, epoxy resin material is used to seal the joints, which effectively blocks the potential damage of air and moisture to the prestressed tendons. After the gluing is completed, temporary tensioning operation is implemented, which helps the rapid curing of the epoxy resin and ensures that the joints are in a tight fit, thereby ensuring the stability and durability of the overall structure.

6. The earthquake-resistant construction process for an urban expressway viaduct according to claim 5, characterized in that: In the step 4, after the segmental beam is hoisted, a trial assembly step is first performed, the purpose of which is to predetermine the position of the beam segment, thereby reducing the adjustment time after the subsequent application of epoxy resin. During the trial assembly, segmental beam No. 1 is used as a reference, and an eight-point coordinate system is used to finely adjust the spatial position of the segmental beam to be spliced. At the same time, the elevation of the beam segment, the center axis and the alignment of the prestressed duct joints are checked and verified to ensure that all beam segments can be fully matched when spliced, thereby ensuring the accuracy and stability of the overall structure.

7. The earthquake-resistant construction process for an urban expressway viaduct according to claim 5, characterized in that: In the step 4, when preparing the epoxy resin glue, the ambient temperature and the expected curing time must be carefully considered. After confirming that the beam segment is positioned accurately and all preparations before applying the glue are ready, start mixing the glue. The mixing and applying process needs to be completed within the specified time to avoid premature hardening of the glue. Manual application is adopted to ensure that the coating reaches a sufficient thickness. At the same time, special attention is paid to the application of key parts such as shear keys and channels to ensure the uniformity of the coating. Special sealing measures are taken around the prestressed channels to prevent leakage or cross-grouting problems that may occur during the grouting process.

8. The earthquake-resistant construction process for an urban expressway viaduct according to claim 5, characterized in that: In the step 4, the main purpose of the temporary tensioning technology is to ensure that the joints between the segments are tightly fitted after the epoxy resin glue is applied, to avoid relative displacement between the segments, so as to ensure that the segments can be smoothly combined into an integral structure. The temporary tensioning operation should be carried out immediately after the epoxy resin glue is applied to make full use of the viscosity of the glue. In this process, the top plate and bottom plate prefabricated blocks of the prefabricated beam segment are selected as temporary tensioning pedestals, and the precision-rolled threaded steel rods are used as prestressed tendons for tensioning. The control principle of the tensioning force is to ensure that no tensile stress is generated in any cross section of the segment, thereby ensuring the stability and safety of the overall structure.

9. The earthquake-resistant construction process for an urban expressway viaduct according to claim 1, characterized in that: In step five, after the segments are assembled, they are loaded and preloaded. This step can simulate the actual load conditions and check the connection between the segment beams and the stability of the overall structure. When the prestressed steel bars are tensioned for the first time, the prestress loss must be accurately measured and compared with the theoretical prestress loss value. If the actual loss value is found to be too large or too small, the tensioning force must be adjusted in time to ensure that the performance of the prestressed steel bars is fully utilized.

10. The earthquake-resistant construction process for an urban expressway viaduct according to claim 1, characterized in that: In the step eight, the project is inspected and accepted in accordance with relevant standards and regulations to ensure that the project quality meets the design requirements, and the viaduct is regularly maintained, including cleaning, inspection, repair and other work, to ensure the long-term stable operation of the viaduct.