Water conservancy channel slope protection laying device and method
By designing a concrete conveying mechanism of inclined laying frames and multi-stage plate group in the slope protection construction of water conservancy channels, the problem of uneven distribution of concrete is solved, and the uniform distribution and scraping of concrete is achieved, the construction efficiency is improved, and the difficulty is reduced. It also integrates wire mesh laying and scraping equipment to provide convenient construction solutions.
Patent Information
- Application Number
- CN202411208873.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the slope protection construction of existing water conservancy channels, the concrete unloading is unevenly distributed, resulting in low construction efficiency and high difficulty, requiring manual intervention and high cost.
A slope protection laying device for water conservancy channels is designed, including a laying frame arranged inclinedly, a concrete conveying mechanism and a multi-stage plate set. The uniform distribution of concrete is achieved through conveyor belts and blanking troughs, and the scraping operation is carried out in combination with the scraper structure. Integrated wire mesh laying and scraping equipment.
It realizes uniform distribution and scraping of concrete on the inclined surface, improves construction efficiency, reduces construction difficulty, reduces manual intervention, and is convenient for equipment integration and is suitable for water conservancy engineering construction.
Smart Images

Figure CN118880818A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of water conservancy engineering, and in particular to a device and method for laying slope protection for a water conservancy channel. Background Art
[0002] Water conservancy projects require the construction of different types of hydraulic structures such as dams, dikes, spillways, sluices, water inlets, channels, ferries, rafts, fishways, etc. to achieve their goals; the slope protection on both sides of the river in water conservancy projects generally requires paving and construction. Water conservancy river slope protection is an important facility to protect the river and prevent soil erosion. However, traditional river slope protection construction methods mostly use manual construction, which is not only inefficient, but also difficult to ensure construction quality, and is gradually being eliminated.
[0003] In the prior art, machinery is generally used for construction. During the laying process, people generally use a truss as the foundation and set a walking frame at the upper and lower ends to serve as a mobile foundation. However, due to the relatively simple structure, during construction, wire mesh laying, concrete pouring and leveling operations all require separate equipment, which makes construction inconvenient.
[0004] Another example is the invention patent with patent number 202310419111.5, which discloses a river bank protection and construction device, including a trough-type adaptive opening flow channel mechanism, a negative feedback residual pressure sensing mechanism, a top walking component and a bottom walking component. In order to solve the influence of different slopes and material fluidity on the falling speed of materials, the present invention creatively proposes a negative feedback residual pressure sensing mechanism, which changes the friction between the fixed friction plate and the sliding friction plate through a pressure sensing component that can sense the amount of accumulated material at the bottom, thereby adaptively adjusting and matching the opening amplitude of the transmission belt. After the slope and material fluidity reach the adjustment mechanism, it can also be compensated by a belt-type baffle assembly, thereby further expanding the scope of application of the device. This structure also uses a straight-through discharge port. Although it can adjust the flow of the discharge, during the lower discharge process, the upper discharge is still in progress, and there will be more on the top and less on the bottom.
[0005] Based on this, a straight-through dropping structure is generally used in the prior art to unload concrete. Since the slope protection is an inclined structure, this structure will result in more unloading at the upper part and less unloading at the lower part, resulting in uneven overall distribution of concrete. Subsequent operations using a scraper will result in great construction difficulty, require manual intervention, be time-consuming and labor-intensive, and have high construction costs. Based on this, it is necessary to study a device and method for laying slope protection for a water conservancy channel. Summary of the invention
[0006] In view of this, the purpose of the present invention is to provide a water conservancy channel slope protection laying device and method, which effectively solves the problem that the existing concrete unloading is unevenly distributed, which brings great trouble to the subsequent scraping and leveling operation, and still requires manual or special scraping and leveling equipment for leveling, resulting in low construction efficiency and great construction difficulty.
[0007] To achieve the above-mentioned purpose, the technical scheme adopted by the present invention is: a water conservancy channel slope protection laying device, comprising a laying frame and a concrete conveying mechanism; the laying frame is arranged in an inclined manner; the concrete conveying mechanism comprises a conveyor belt, a multi-stage paddle and a material dropping trough; the conveyor belt is rotatably arranged in the middle area of the laying frame, the material dropping trough is arranged on both sides of the conveyor belt, the multi-stage paddle comprises a plurality of paddle groups extending along the direction of the conveyor belt, and the material dropping trough has a sub-material dropping trough corresponding to each group of paddle groups; the root of the paddle group is fixed at the end of the sub-material dropping trough and extends obliquely toward the upstream direction of the conveyor belt; the ends of the plurality of paddle groups gradually extend from the edge of the conveyor belt to the middle of the conveyor belt in sequence along the conveying direction of the conveyor belt, and the concrete distributed on the conveyor belt is scraped to the corresponding sub-material dropping trough in different areas; the upper and lower parts of the laying frame are respectively provided with an upper walking frame body and a lower walking frame body; the upper walking track and the lower walking track are respectively provided on the upper and lower parts of the channel to be laid; the upper walking frame body and the lower walking frame body are provided with moving wheels that can move on the walking track.
[0008] Furthermore, the paddle group includes a left paddle and a right paddle, which are symmetrically arranged above the conveyor belt, and their roots are fixed on the blanking trough to form an eight-shaped structure, and the gap between the left paddle and the right paddle gradually decreases along the conveyor belt direction.
[0009] Furthermore, a limiting scraper is arranged upstream of the conveyor belt, the lower surface of the limiting scraper is parallel to the surface of the conveyor belt, and the gap between the left and right paddles is equidistantly reduced along the conveyor belt direction.
[0010] Furthermore, a reinforcing rod is provided between the left shift plate and the right shift plate.
[0011] Furthermore, a bracket is arranged on the laying frame, the material distribution trough is fixed on the bracket, and rollers are arranged on the bracket, and the rollers are located below the upper layer of the conveyor belt.
[0012] Furthermore, a support frame is arranged in the middle of the laying frame, on which a roller shaft for supporting the wire mesh roller is arranged, and a plurality of guide frames are arranged on the laying frame, on which guide rollers are arranged, and the wire mesh is laid flat under the laying frame through the guidance of the guide rollers.
[0013] Furthermore, the guide frame is arranged on one side of the laying frame, and a scraper frame is arranged on the other side of the laying frame. A scraper is arranged at the lower end of the scraper frame, and the scraper is above the guide roller.
[0014] Furthermore, the support frames and guide frames are provided in multiple groups correspondingly, so that the wire mesh rollers are arranged in the middle area of the laying frame in the form of multiple groups.
[0015] Furthermore, a feeding hopper is provided above the conveyor belt, the feeding hopper is arranged to be inclined upward and is connected to the upper end of the conveyor belt.
[0016] A method for laying a water conservancy channel slope protection laying device comprises the following steps: Step 1: Set up the equipment Clean the construction site, set up the upper and lower walking tracks on the riverbed and slope protection, and then assemble the laying frame, upper walking frame body and lower walking frame on the upper and lower walking tracks; Step 2: Install the wire mesh roll The wire mesh roll is set up on the support frame, and then the wire mesh is pulled around the guide roller from one side and extended to the other side of the laying frame. Then the wire mesh is anchored on the slope protection surface with an anchor seat, and it is ensured that the wire mesh is parallel to the slope protection in a taut state; Step 3: Start the concrete pouring equipment and conveyor Start the conveyor drive motor, move the concrete pouring equipment to the upper end of the conveyor belt, pour concrete on the conveyor belt from the upstream, and the concrete is distributed on the conveyor belt in a state of equal thickness under the action of the limit scraper; driven by the drive motor, the concrete is scraped by the multi-stage scraper to the corresponding distribution trough, and each distribution trough distributes the obtained concrete to the slope protection surface; Step 4: Start the moving wheels of the walking frame Start the moving wheels to move the upper and lower traveling frames on the track, and drive the various drop troughs to move horizontally, forming multiple drop points on the slope protection surface; continuously lower the wire mesh during the movement, and use the scraper on the rear side to scrape the concrete flat; Step 5: Cut the wire mesh After the construction is completed, cut the wire mesh and apply the anchor seat to the cut end of the wire mesh.
[0017] The beneficial effect of the above technical scheme is as follows: the present invention mainly aims at the situation that during the construction of concrete on the slope, the concrete fluid is allowed to remain freely in a straight flow channel, and more concrete is distributed in the upper part and less in the lower part. Based on this problem, the present invention provides a device that allows concrete to be evenly distributed on the inclined surface. In the structure, a conveyor belt is used as a conveying structure, and a multi-level distributed paddle group is used to gradually scrape different areas of the conveyor belt, that is, the surface of the conveyor belt is divided into multiple areas from the outside to the inside, and each area is scraped by a corresponding paddle, so that the concrete in the corresponding area enters the corresponding distribution trough, and falls from the drop port of the distribution trough to the slope protection surface, so as to achieve the purpose of continuous input and uniform distribution of concrete on the slope protection surface.
[0018] In the above method, in order to further achieve the uniformity purpose, the uniformity deviation of concrete is solved by using the upstream limiting scraper to make the concrete thickness on the surface of the conveyor belt equal, and the distribution gap of the paddle group is set accordingly, so that the concrete can be more evenly distributed on the surface of the slope. The whole process is simple to operate, does not require human intervention, and greatly improves the construction efficiency.
[0019] At the same time, the present invention is also provided with a wire mesh laying device and a scraper device, and the structure is integrated on the laying frame. The integration of the structure benefits from the uniform laying of concrete, which provides the possibility for the integration of equipment. The use of ordinary scraper equipment can realize the scraping operation of concrete.
[0020] Therefore, the present invention has a novel structure and reasonable equipment setting, which realizes the purpose of uniformly distributing and laying concrete on an inclined surface. After the material is transferred, the concrete enters each drop trough and falls into the corresponding position of the slope protection. Subsequently, a simple scraper structure is adopted to realize the scraping operation of the concrete. The construction is convenient, the construction efficiency is improved, and the construction difficulty is reduced. The structure integrates wire mesh laying, concrete pouring and scraping equipment, has various functions, and a stable structural setting, which provides convenient equipment for people to implement slope protection construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the implementation structure of the present invention; Figure 2 It is a schematic diagram of the three-dimensional structure of the present invention; Figure 3 It is a schematic diagram of the three-dimensional structure from another viewing angle of the present invention; Figure 4 It is a schematic diagram of the main structure of the present invention; Figure 5 It is a right view structural schematic diagram of the present invention; Figure 6 It is a schematic diagram of the top view of the structure of the present invention; Figure 7 It is a bottom view structural schematic diagram of the present invention; Figure 8 It is a rear view structural schematic diagram of the present invention; Fig. 9 It is a left-side structural schematic diagram of the present invention; Fig.10 It is a schematic diagram of the implementation structure of the conveyor belt; Fig.11 for Fig.10 Schematic diagram of the top view structure.
[0022] Figure markings: 1-slope protection, 2-laying frame, 3-upper walking frame, 4-lower walking frame, 5-moving wheel, 6-conveyor belt, 7-paddle group, 71-left paddle, 72-right paddle, 73-reinforcement rod, 8-feeding chute, 81-sub-feeding chute, 82-feeding channel, 9-connecting rod, 10-support frame, 11-wire mesh roller, 12-guide roller, 13-scraper frame, 14-scraper, 15-limiting scraper, 16-feeding hopper, 17-driving motor, 18-wire mesh, 19-anchor seat, 20-zone 1, 21-zone 2, 22-zone 3, 23-zone 4, 24-zone 5. DETAILED DESCRIPTION
[0023] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments: Embodiment 1. This embodiment aims to provide a device for laying slope protection for a water conservancy channel. It is mainly aimed at the problem that during the construction of concrete on a slope, the concrete fluid is allowed to remain freely in a straight flow channel, which may result in more concrete distributed on the upper part and less on the lower part. Based on this problem, the present invention provides a device for evenly distributing concrete on an inclined surface. In this structure, a conveyor belt is used as a conveying structure, and a multi-level distributed paddle group is used to gradually scrape different areas of the conveyor belt, that is, the surface of the conveyor belt is divided into multiple areas from the outside to the inside, and each area is scraped by a corresponding paddle, so that the concrete in the corresponding area enters the corresponding distribution trough, and falls from the drop port of the distribution trough to the slope protection surface, so as to achieve the purpose of continuous input and even distribution of concrete on the slope protection surface.
[0024] like Figure 1 , 10 As shown in 11, a water conservancy channel slope protection laying device includes a laying frame 2 and a concrete conveying mechanism; the laying frame 2 is arranged at an angle, and the laying frame 2 serves as a structural foundation and is arranged at an angle in the slope protection implementation structure. For the inclined construction structure, this embodiment is provided with an upper walking track and a lower walking track on the upper and lower parts of the channel to be laid; the upper and lower parts of the laying frame 2 are respectively provided with an upper walking frame body 3 and a lower walking frame body 4, and the upper walking frame body 3 and the lower walking frame body 4 are provided with moving wheels 5 that can move on the walking tracks; the moving wheel 5 is generally an electric drive wheel, which is driven by a motor to realize the movement of the moving wheel, and the upper and lower moving wheels move synchronously to achieve the translation purpose of the laying frame 2.
[0025] like Figure 2-9It is shown in the figure that in terms of concrete transportation, this embodiment adopts a concrete transportation mechanism to operate. In the specific structure, the concrete transportation mechanism includes a conveyor belt 6, a multi-stage plate and a material drop chute 8; the conveyor belt 6 is rotatably arranged in the middle area of the laying frame 2. In this embodiment, there is a space between the middle area and the two sides of the conveyor frame, and the material drop chute 8 is arranged in the space on both sides of the conveyor belt 6. In terms of structural layout, the two sides of the laying frame 2 are frame structures, and the frame structure has multiple connecting rods 9. The connecting rods 9 have a strengthening effect on the frame and reduce the dead weight of the equipment. The connecting rods are connected to each other by cross bars and pass through the space between the conveyor belts 6, and the overall stability is good.
[0026] In further structures, such as Figure 3 It is shown in the figure that a bracket is provided on the laying frame 2, a material drop chute 81 is fixed on the bracket, and rollers are provided on the bracket. The rollers are located below the upper layer of the conveyor belt 6. During implementation, the rollers can be arranged on the cross bar with an axle seat. Since there is more concrete on the conveyor belt 6, it is only necessary to support the upper conveyor belt 6, thereby realizing stable operation of the structure.
[0027] like Fig.10 As shown in the figure, the multi-stage paddle plate includes a plurality of paddle plate groups 7 extending along the direction of the conveyor belt 6. The material drop trough 8 has a sub-drop trough 81 corresponding to each group of paddle plate groups 7. The sub-drop trough 81 has a through-drop channel 82. The drop channel 82 is a structure with a larger upper end and a smaller lower end. During implementation, the drop channels on both sides are correspondingly arranged or staggered. In a preferred embodiment, a staggered arrangement is selected, so that the distribution of concrete can be more uniform, that is, a group of paddle plate groups has two drop paths.
[0028] like Fig.11 As shown in the figure, the root of the paddle group 7 is fixed at the end of the sub-drop trough 81 and extends obliquely toward the upstream direction of the conveyor belt 6; the ends of the multiple paddle groups 7 gradually extend from the edge of the conveyor belt 6 to the middle of the conveyor belt 6 in sequence along the conveying direction of the conveyor belt 6, and the concrete distributed on the conveyor belt 6 is scraped to the corresponding sub-drop trough 81 in sections; the present embodiment divides the conveyor belt 6 into a plurality of areas, such as the conveyor belt 6 area can be divided into a first area 20, a second area 21, a third area 22, a fourth area 23 and a fifth area 24 from the outside to the inside; wherein the fifth area 24 is in the middle, preferably a closed area, the fourth area 23, the third area 22, the second area 21 and the first area 20 are distributed outward in sequence, and the first area 20, the second area 21, the third area 22 and the fourth area 23 are areas separated on both sides, and the concrete of each section is scraped by the corresponding paddle group 7 and transported to the corresponding sub-drop trough.
[0029] In a further structure, the paddle group 7 includes a left paddle 71 and a right paddle 72, and the left paddle 71 and the right paddle 72 are symmetrically arranged on the blanking trough to form an eight-shaped structure, and the gap between the left paddle 71 and the right paddle 72 gradually decreases along the direction of the conveyor belt 6, and the middle left paddle and right paddle are butt-jointed together and have an arc-shaped guiding surface. This structure can scrape all the concrete on the conveyor belt 6, that is, it has the following characteristics; the paddle group 7 structure can make the concrete follow the corresponding partition conveyor belt 6 to the corresponding blanking port, and can scrape the concrete on the surface of the conveyor belt 6 to ensure that the surface of the conveyor belt 6 is clean, reduce the conveying load of the conveyor belt 6, improve the concrete conveying efficiency, avoid the concrete sticking to the surface of the conveyor belt 6, and increase the concrete conveying amount.
[0030] In further implementation, a reinforcing rod 73 is provided between the left shift plate 71 and the right shift plate 72 , and the reinforcing rod 73 can reinforce the separated left shift plate and the right shift plate, support them from the middle, improve the structural stability, and prevent the left shift plate 71 and the right shift plate 72 from deforming.
[0031] For ease of operation, a feeding hopper 16 is provided above the conveyor belt 6 in this embodiment. The feeding hopper 16 is arranged obliquely upward and is connected to the upper end of the conveyor belt 6 .
[0032] A support frame 10 is arranged in the middle of the laying frame 2, and a roller shaft for supporting a wire mesh roller 11 is arranged on the support frame 10. A plurality of guide frames are arranged on the laying frame 2, and guide rollers 12 are arranged on the guide frames. The wire mesh is laid flat under the laying frame 2 through the guidance of the guide rollers 2. During implementation, there are a plurality of guide rollers 12, and three are arranged in this embodiment, one on each side and two on both sides of the bottom, which are used to lay the wire mesh flat on the lower part of the laying frame 2 and be parallel to the slope protection 1 at intervals, and gradually release the wire mesh 18 with the movement, and ensure that the wire mesh 18 is in a straight state.
[0033] In this embodiment, the guide frame is arranged on one side of the laying frame 2, and a scraper frame 13 is arranged on the other side of the laying frame 2. A scraper 14 is arranged at the lower end of the scraper frame 13, and the scraper 14 is above the guide roller 12. The embodiment is also provided with a wire mesh laying device and a scraper device, and the structure is integrated into the laying frame 2. The integration of the structure benefits from the uniform laying of concrete, which provides the possibility for the integration of equipment, and the use of ordinary scraper equipment can realize the scraping operation of concrete.
[0034] In addition, a driving motor for driving the conveyor belt 6 can be arranged in the scraper frame, which is connected to the side of the laying frame through a connecting plate, and the driving motor 17 is arranged on the mounting plate.
[0035] A method for laying a water conservancy channel slope protection laying device comprises the following steps: Step 1: Set up the equipment Clean the construction site, set up the upper and lower walking tracks on the riverbed and the slope protection, and then assemble the laying frame 2, the upper walking frame body and the lower walking frame on the upper and lower walking tracks; Step 2: Install the wire mesh roll The wire mesh roll is set up on the support frame, and then the wire mesh is pulled around the guide roller from one side and extended to the other side of the laying frame 2, and then the wire mesh 18 is anchored on the slope protection surface with the anchor seat 19, and it is ensured that the wire mesh is parallel to the slope protection in a taut state; Step 3: Start the concrete pouring equipment and conveyor Start the conveyor drive motor 17, move the concrete pouring device to the upper end of the conveyor belt 6, pour concrete on the conveyor belt 6 from the upstream, and the concrete is distributed on the conveyor belt 6 in a state of equal thickness under the action of the limit scraper 15; driven by the drive motor, the concrete is scraped by the multi-stage scraper to the corresponding drop trough, and each drop trough distributes the obtained concrete to the slope protection surface; Step 4: Start the moving wheels of the walking frame Start the moving wheels to move the upper and lower traveling frames on the track, and drive the various drop troughs to move horizontally, forming multiple drop points on the slope protection surface; continuously lower the wire mesh during the movement, and use the scraper on the rear side to scrape the concrete flat; Step 5: Cut the wire mesh After the construction is completed, cut the wire mesh and apply the anchor seat to the cut end of the wire mesh.
[0036] This embodiment achieves the purpose of evenly distributing concrete on an inclined surface. After the concrete is dispensed, it enters each drop trough and falls into the corresponding position of the slope protection. The drop points are independently distributed and can correspond to different positions of the slope protection. It is different from the through-type drop channel in the prior art. A simple scraper structure is then used to achieve the scraping and leveling of the concrete. The construction is convenient, the construction efficiency is improved, and the construction difficulty is reduced. The structure integrates wire mesh laying, concrete pouring and scraping equipment, has diverse functions, and a stable structural setting, providing convenient equipment for people to implement slope protection construction.
[0037] Embodiment 2: This embodiment further illustrates the concrete conveying structure.
[0038] In this embodiment, a limiting scraper 15 is provided upstream of the conveyor belt 6, the lower surface of the limiting scraper 15 is parallel to the surface of the conveyor belt 6, and the gap between the left shift plate 71 and the right shift plate 72 is equidistantly reduced along the direction of the conveyor belt 6; in this embodiment, the limiting scraper 15 is arranged at the end of the feeding hopper 16, so that the end of the feeding hopper 16 has a discharge port adapted to the width of the conveyor belt 6, and the bottom plate of the feeding hopper covers the upper part of the conveyor belt 6, so that the concrete is covered on the conveyor belt with equal thickness.
[0039] In order to further achieve the uniformity purpose, the upstream limiting scraper is used to make the concrete thickness on the surface of the conveyor belt 6 equal, and the distribution gap of the paddle group 7 is set accordingly. In the preferred method, the distribution gap is equidistantly distributed, so that the concrete can be more evenly distributed on the surface of the slope. The whole process is simple to operate, no human intervention is required, and the construction efficiency is greatly improved.
[0040] Example 3: This example further illustrates the wire mesh laying structure.
[0041] This embodiment is mainly suitable for slope protection with a large span. The wire mesh is laid in multiple groups to solve the problem of difficult construction of wire mesh rollers. In the specific structure, the support frame 10 and the guide frame are correspondingly provided with multiple groups, so that the wire mesh rollers are arranged in the form of multiple groups in the middle area of the laying frame 2. This embodiment uses multiple wire mesh rollers for construction, which facilitates the assembly of the wire mesh rollers and reduces the difficulty of construction.
Claims
1. A water conservancy channel slope protection laying device, characterized in that: The present invention comprises a laying frame and a concrete conveying mechanism; the laying frame is arranged in an inclined manner; the concrete conveying mechanism comprises a conveyor belt, a multi-stage paddle plate and a material dropping trough; the conveyor belt is rotatably arranged in the middle area of the laying frame, and the material dropping trough is arranged on both sides of the conveyor belt, the multi-stage paddle plate comprises a plurality of paddle plate groups extending along the direction of the conveyor belt, and the material dropping trough is provided with a sub-material dropping trough corresponding to each group of paddle plate groups; the root of the paddle plate group is fixed at the end of the sub-material dropping trough and extends obliquely toward the upstream direction of the conveyor belt; the ends of the plurality of paddle plate groups gradually extend from the edge of the conveyor belt to the middle of the conveyor belt in sequence along the conveying direction of the conveyor belt, and the concrete distributed on the conveyor belt is scraped to the corresponding sub-material dropping trough according to the partition; the upper and lower parts of the laying frame are respectively provided with an upper walking frame body and a lower walking frame body; the upper walking track and the lower walking track are respectively provided above and below the channel to be laid; the upper walking frame body and the lower walking frame body are provided with moving wheels that can move on the walking track.
2. The water conservancy channel slope protection laying device according to claim 1 is characterized in that: The paddle group includes a left paddle and a right paddle, which are symmetrically arranged above the conveyor belt, and their roots are fixed on the blanking trough to form an eight-shaped structure, and the gap between the left paddle and the right paddle gradually decreases along the conveyor belt direction.
3. The water conservancy channel slope protection laying device according to claim 2 is characterized in that: A limiting scraper is arranged upstream of the conveyor belt, the lower surface of the limiting scraper is parallel to the surface of the conveyor belt, and the gap between the left and right shifting plates is equidistantly reduced along the conveyor belt direction.
4. The hydraulic channel slope protection laying device according to claim 2 is characterized in that: A reinforcing rod is arranged between the left shift plate and the right shift plate.
5. The water conservancy channel slope protection laying device according to claim 1 is characterized in that: A bracket is arranged on the laying frame, the material distribution trough is fixed on the bracket, and rollers are arranged on the bracket, and the rollers are located below the upper layer of the conveyor belt.
6. The hydraulic channel slope protection laying device according to claim 1, characterized in that: A support frame is arranged in the middle of the laying frame, on which a roller shaft for supporting the wire mesh roller is arranged, and a plurality of guide frames are arranged on the laying frame, on which guide rollers are arranged, through which the wire mesh is laid flat under the laying frame.
7. The hydraulic channel slope protection laying device according to claim 6, characterized in that: The guide frame is arranged on one side of the laying frame, and a scraper frame is arranged on the other side of the laying frame. A scraper is arranged at the lower end of the scraper frame, and the scraper is above the guide roller.
8. The hydraulic channel slope protection laying device according to claim 7 is characterized in that: The support frames and guide frames are correspondingly provided in multiple groups, so that the wire mesh rollers are arranged in the middle area of the laying frame in the form of multiple groups.
9. The hydraulic channel slope protection laying device according to claim 1, characterized in that: A feeding hopper is arranged above the conveyor belt, the feeding hopper is arranged obliquely upward and is communicated with the upper end of the conveyor belt.
10. The laying method of the hydraulic channel slope protection laying device according to claim 1, characterized in that: The method comprises the following steps: Step 1: Set up the equipment Clean the construction site, set up the upper and lower walking tracks on the riverbed and slope protection, and then assemble the laying frame, upper walking frame body and lower walking frame on the upper and lower walking tracks; Step 2: Install the wire mesh roll The wire mesh roll is set up on the support frame, and then the wire mesh is pulled around the guide roller from one side and extended to the other side of the laying frame. Then the wire mesh is anchored on the slope protection surface with an anchor seat, and it is ensured that the wire mesh is parallel to the slope protection in a taut state; Step 3: Start the concrete pouring equipment and conveyor Start the conveyor drive motor, move the concrete pouring equipment to the upper end of the conveyor belt, pour concrete on the conveyor belt from the upstream, and the concrete is distributed on the conveyor belt in a state of equal thickness under the action of the limit scraper; driven by the drive motor, the concrete is scraped by the multi-stage scraper to the corresponding distribution trough, and each distribution trough distributes the obtained concrete to the slope protection surface; Step 4: Start the moving wheels of the walking frame Start the moving wheels to move the upper and lower traveling frames on the track, and drive the various drop troughs to move horizontally, forming multiple drop points on the slope protection surface; continuously lower the wire mesh during the movement, and use the scraper on the rear side to scrape the concrete flat; Step 5: Cut the wire mesh After the construction is completed, cut the wire mesh and apply the anchor seat to the cut end of the wire mesh.
Citation Information
Cited By
Channel construction device for hydraulic engineering
CN119877469A
Water conservancy project slope protection concrete integrated forming machine
CN121087929A