Assembly type foundation pit supporting beam section convenient to disassemble and prefabricating method thereof
Through the prefabricated foundation pit support beam section that is easy to dismantle, combined with the design of beam sleeves and embedded pipes, the problems of long construction cycles and difficult demolition in the existing foundation pit support system are solved, and the safety and efficiency of foundation pit support are achieved. Fast, low cost and recyclable significantly reduces the cost and carbon emissions of support within the foundation pit.
Patent Information
- Application Number
- CN202411214353.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-31
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-08-31
AI Technical Summary
In the existing foundation pit support system, cast-in-place reinforced concrete supports have problems such as long construction cycle, difficulty in demolition, difficulty in recycling, short service life and high cost, especially in foundation pits with ground pressure and square shape.
Adopt prefabricated foundation pit support beam sections that are easy to remove, including rectangular reinforced concrete, beam sleeve, longitudinal embedded pipe and transverse embedded pipe. The design of beam sleeves and the layout of embedded pipes can achieve rapid removal and reuse, combined with standardization Dimensions and structures simplify prefabrication processes and reduce costs.
It realizes the safety, efficiency, fast, low cost and recyclable foundation pit support, shortens the construction cycle, reduces carbon emissions, extends the service life of the support beam section, and significantly reduces the cost of support in the foundation pit.
Smart Images

Figure CN118880910A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction engineering, and in particular to an easily dismantled assembled reinforced concrete foundation pit support beam section and a prefabrication method thereof. Background Art
[0002] In foundation pit projects, foundation pit support beams can effectively support the surrounding soil, form a stable support system, and ensure the stability of the foundation pit, playing a very important role in foundation pit excavation.
[0003] In situations where the ground stress is large, cast-in-place reinforced concrete internal support is the best choice. It has the advantages of flexible design, good integrity, high pressure resistance and high reliability. However, it also has the disadvantages of long construction period, difficult demolition, difficult recycling, short service life and high cost.
[0004] In order to overcome the shortcomings of cast-in-place concrete support, prefabricated reinforced concrete support is used in foundation pits with greater ground pressure and square shape. The advantages of prefabricated support beams are easy to dismantle and install, recyclable and reused, and shortening the construction period. Summary of the invention
[0005] The purpose of the present invention is to solve the problems existing in the current foundation pit support system, to provide an assembled foundation pit support beam section that is easy to dismantle and a prefabrication method thereof, thereby achieving the purpose of safe, efficient, fast, low-cost and recyclable foundation pit support.
[0006] The present invention solves the above problems by adopting the following scheme: The assembled foundation pit support beam section which is easy to dismantle comprises a rectangular reinforced concrete, a beam sleeve, a longitudinal embedded pipe and a transverse embedded pipe. The beam sleeve is sleeved on the rectangular reinforced concrete, and comprises an end steel plate, an angle steel, a side steel plate, a top steel plate and a bottom steel plate; a first hole is arranged on the end steel plate, and a second hole is arranged on the side steel plate; the tube wall at one end of the longitudinal embedded pipe is welded to the inner wall of the first hole to form a longitudinal rebar insertion hole, and the other end penetrates into the rectangular reinforced concrete and is parallel to the angle steel; the tube walls at both ends of the transverse embedded pipe are respectively welded to the hole walls of the second hole on the side steel plates on both sides to form a transverse rebar insertion hole, and are perpendicular to the angle steel; the longitudinal embedded pipe and the transverse embedded pipe do not intersect.
[0007] Preferably, the longitudinal reinforcing bar insertion holes and the transverse reinforcing bar insertion holes have the same hole diameter.
[0008] Preferably, the vertical spacing between adjacent longitudinal rebar insertion holes or transverse rebar insertion holes is the same, and the distance between the uppermost longitudinal rebar insertion hole and the upper edge of the beam sleeve is equal to the distance between the lowermost transverse rebar insertion hole and the lower edge of the beam sleeve.
[0009] Preferably, the longitudinal rebar insertion holes are in two rows, and the transverse rebar insertion holes are in one row; the distance between the two rows of longitudinal rebar insertion holes is equal to twice the distance between the transverse rebar insertion holes and the end face steel plate.
[0010] Preferably, the longitudinal embedded pipe is a steel pipe with a threaded outer side and a smooth inner side, one end of the steel pipe penetrating into the rectangular reinforced concrete is sealed and the other end is open; the transverse embedded pipe is a steel pipe with a threaded outer side and a smooth inner side, and both ends of the steel pipe are open.
[0011] Preferably, buckles are welded on the side steel plates of the beam sleeve, and the buckles are evenly arranged on the side steel plates.
[0012] A method for prefabricating an assembled foundation pit support beam section that is easy to dismantle comprises the following steps: 1) Clean the concrete residues remaining in the mold placement area, clean the joints between the side mold and the end mold, and the joints between the side mold, the end mold and the bottom mold; 2) Weld the beam sleeve, four angle steels and two end steel plates into a frame, and weld the side steel plates and bottom steel plates on the frame; 3) The transverse embedded pipe is inserted into the second hole and fixed by welding, and the longitudinal embedded pipe is inserted into the first hole and fixed by welding; 4) Connect the transverse embedded pipe and the longitudinal embedded pipe with vertical steel bars, and weld and fix the contact between the vertical steel bars and the transverse embedded pipe and the longitudinal embedded pipe; 5) Steel bar binding; 6) After the reinforcement is tied, weld the top steel plate to form the beam sleeve; 7) Apply water-based release agent on the bottom mold; 8) Place the welded beam sleeve on the bottom mold; 9) Apply water-based release agent on the side form and end form before installation. During installation, ensure that the side form and end form are completely attached to the beam sleeve; 10) Pour concrete into the mold. Before pouring, seal the ends of the longitudinal and transverse embedded pipes with gypsum. Ensure that the longitudinal and transverse embedded pipes do not deviate before pouring. After pouring, vibrate with a vibrator until no bubbles are generated. 11) After the rectangular reinforced concrete has formed strength, it is demoulded and cured. After the curing is completed, it is demoulded; 12) After demoulding is completed, scrape off the excess concrete on the surface of the beam sleeve, remove the sealing plaster of the longitudinal embedded pipes and transverse embedded pipes, apply a protective layer on the concrete surface, and brush anti-rust paint on the surface of the beam sleeve and the inner walls of the longitudinal embedded pipes and transverse embedded pipes.
[0013] Beneficial effects of the present invention: 1. The present invention provides an assembled foundation pit support beam section that is easy to dismantle, and transfers the cast-in-place reinforced concrete support beam operation at the foundation pit site to a factory or off-site for prefabrication in advance, thereby realizing the assembly construction of the support in the foundation pit, shortening the construction period of the support in the foundation pit, and accelerating the progress of the entire project.
[0014] 2. The reinforced concrete beam sections provided by the present invention have standardized sizes and structures, which not only simplifies prefabrication (requires few templates, and the prefabrication process is also easy to standardize), but also facilitates transportation, dismantling and reuse, greatly reducing costs. The standardization can be achieved within a foundation pit, or on a larger scale, such as a district in a city, a county, a province, or even the whole country, achieving greater social and economic benefits.
[0015] 3. The present invention provides a method for connecting rebars of assembled foundation pit support beam sections that are easy to dismantle. The foundation pit support beam sections can be completely recovered after use and can be reused, which greatly reduces the cost of support in the foundation pit and significantly reduces carbon emissions compared to traditional cast-in-place reinforced concrete support beams.
[0016] 4. The present invention provides a beam sleeve, which is wrapped around a rectangular reinforced concrete body, thereby well protecting the rectangular reinforced concrete body (especially protecting the opening part at the beam end to avoid structural weakening); the increased steel consumption can be offset by reducing the reinforcement ratio of the foundation pit support beam section, and will not significantly increase the support cost; the beam sleeve protects the integrity of the shape of the support beam, reduces the probability of damage to the foundation pit support beam section during use, extends the service life of the foundation pit support beam section, increases the number of recycling times of the foundation pit support beam section, and reduces the cost of a single foundation pit support.
[0017] 5. When the foundation pit support beam section is prefabricated, the present invention applies anti-rust paint on the surface of the beam sleeve and applies a protective layer on the surface of the concrete, which effectively protects the beam sleeve and concrete part on the surface of the foundation pit support beam section to prevent them from being corroded, thereby increasing the service life of the foundation pit support beam section and reducing the unit cost of the support in the foundation pit.
[0018] 6. The assembled foundation pit support beam provided by the present invention has a simple connection method and is very suitable for occasions where the shape is square and the inner support only bears axial force. The assembled support beam with this connection method is also very easy to dismantle, which greatly simplifies the dismantling work and reduces the dismantling cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 Schematic diagram of the overall structure of the assembled foundation pit support beam section for easy dismantling; Figure 2 Schematic diagram of the beam sleeve and some steel bars of the prefabricated foundation pit support beam section for easy removal; Figure 3Schematic diagram of the beam sleeve of the prefabricated foundation pit support beam section for easy removal; Figure 4 Schematic diagram of the overall structure of the welded buckle loops of the assembled foundation pit support beam section for easy dismantling; Figure 5 Schematic diagram of the axial connection structure of two beams of the assembled foundation pit support beam section for easy dismantling; Figure 6 Schematic diagram of the axial connection structure of two beams with welded buckles for easy dismantling of the assembled foundation pit support beam section; Figure 7 Schematic diagram of the four-beam cross connection structure of the assembled foundation pit support beam section for easy dismantling; Figure 8 Schematic diagram of the formwork in the prefabrication method of assembled foundation pit support beam sections for easy dismantling.
[0020] In the figure: 1. Rectangular reinforced concrete; 2. Beam sleeve; 201. End steel plate; 202. Angle steel; 203. Side steel plate; 204. Top steel plate; 205. Bottom steel plate; 206-1. First hole; 206-2. Second hole; 207. Longitudinal rebar hole; 208. Transverse rebar hole; 209. Buckle; 3. Longitudinal embedded pipe; 4. Transverse embedded pipe; 5. Connecting steel bar; 6. Longitudinal rebar; 7. Vertical rebar; 8. Connecting steel plate; 9. Bottom form; 10. Side form; 11. End form. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] The assembled foundation pit support beam section which is easy to dismantle comprises a rectangular reinforced concrete 1, a beam sleeve 2, a longitudinal embedded pipe 3 and a transverse embedded pipe 4. The beam sleeve 2 is sleeved on the rectangular reinforced concrete 1, and the beam sleeve 2 comprises an end steel plate 201, an angle steel 202, a side steel plate 203, a top steel plate 204 and a bottom steel plate 205; a first hole 206-1 is arranged on the end steel plate 201, and a second hole 206-2 is arranged on the side steel plate 203; a tube wall at one end of the longitudinal embedded pipe 3 is welded to the inner wall of the first hole 206-1 to form a longitudinal reinforcing bar hole 207, and the other end penetrates into the rectangular reinforced concrete 1 and is parallel to the angle steel 202; tube walls at both ends of the transverse embedded pipe 4 are respectively welded to the hole walls of the second hole 206-2 on the side steel plates 203 on both sides to form a transverse reinforcing bar hole 208, and are perpendicular to the angle steel 202; the longitudinal embedded pipe 3 and the transverse embedded pipe 4 do not intersect.
[0023] The diameters of the longitudinal reinforcing bar insertion holes 207 and the transverse reinforcing bar insertion holes 208 are the same.
[0024] The vertical spacings between adjacent longitudinal rebar insertion holes 207 or transverse rebar insertion holes 208 are the same, and the distance between the uppermost longitudinal rebar insertion hole 207 and the upper edge of the beam sleeve 2 is equal to the distance between the lowermost transverse rebar insertion hole 208 and the lower edge of the beam sleeve 2.
[0025] The longitudinal reinforcing bar holes 207 are in two rows, and the transverse reinforcing bar holes 208 are in one row; the distance between the two rows of longitudinal reinforcing bar holes 207 is equal to twice the distance between the transverse reinforcing bar holes 208 and the end face steel plate 201.
[0026] When the transverse reinforcing bar holes 207 and the longitudinal reinforcing bar holes 208 are spliced in the foundation pit supporting beam section, the connecting steel bars 5 are inserted into the transverse reinforcing bar holes 207 and the longitudinal reinforcing bar holes 208 .
[0027] The longitudinal embedded pipe 3 is a steel pipe with a threaded outer side and a smooth inner side. The steel pipe penetrates into the rectangular reinforced concrete 1 and is sealed at one end and open at the other end. The transverse embedded pipe 4 is a steel pipe with a threaded outer side and a smooth inner side. Both ends of the steel pipe are open.
[0028] Buckles 209 are welded on the side steel plates 203 of the beam sleeve 2 , and the buckles 209 are evenly arranged on the side steel plates 203 .
[0029] A method for prefabricating an assembled foundation pit support beam section that is easy to dismantle comprises the following steps: 1) Clean the concrete residues remaining in the mold placement area, clean the joints between the side mold 10 and the end mold 11, and the joints between the side mold 10 and the end mold 11 and the bottom mold 9; 2) Welding the beam sleeve 2, four angle steels 202 and two end steel plates 201 into a frame, and welding the side steel plates 203 and the bottom steel plates 205 on the frame; 3) The transverse embedded pipe 4 is inserted into the second hole 206-2 and fixed by welding, and the longitudinal embedded pipe 3 is inserted into the first hole 206-1 and fixed by welding; 4) Connect the transverse embedded pipe 4 and the longitudinal embedded pipe 3 with the vertical steel bar 7, and weld and fix the contact between the vertical steel bar 7, the transverse embedded pipe 4 and the longitudinal embedded pipe 3; 5) Steel bar binding: the ends of the longitudinal steel bars 6 are tied to the longitudinal embedded pipes 3; 6) After the reinforcement is tied, the top steel plate 204 is welded to form the beam sleeve 2; 7) Apply a water-based release agent on the bottom mold 9; 8) placing the welded beam sleeve 2 on the bottom mold 9; 9) Apply water-based release agent on the side mold 10 and the end mold 11 before installation. During installation, ensure that the side mold 10 and the end mold 11 are completely attached to the beam sleeve 2; 10) Pour concrete into the mold. Before pouring, the ends of the longitudinal embedded pipe 3 and the transverse embedded pipe 4 are sealed with gypsum. Before pouring, ensure that the longitudinal embedded pipe 3 and the transverse embedded pipe 4 do not deviate. After pouring, vibrate with a vibrator until no bubbles are generated; 11) After the rectangular reinforced concrete 1 has formed strength, it is demoulded and cured, and after the curing is completed, it is demoulded; 12) After demolding is completed, scrape off the excess concrete on the surface of the beam sleeve 2, remove the sealing plaster of the longitudinal embedded pipes 3 and the transverse embedded pipes 4, apply a protective layer on the concrete surface, and brush anti-rust paint on the surface of the beam sleeve 2 and the inner walls of the longitudinal embedded pipes 3 and the transverse embedded pipes 4.
[0030] like Figure 1 , Figure 2 and Figure 3As shown, it is a schematic diagram of the overall structure of an assembled foundation pit support beam section that is easy to dismantle, a schematic diagram of the beam sleeve and part of the steel bars of the assembled foundation pit support beam section that is easy to dismantle, and a schematic diagram of the beam sleeve of the assembled foundation pit support beam section that is easy to dismantle. The beam sleeve 2 wraps the rectangular reinforced concrete 1, wherein the beam sleeve is formed by welding the end steel plate 201, the angle steel 202, the side steel plate 203, the top steel plate 204 and the bottom steel plate 205. The two end heads of the beam sleeve 2 have the same structure, and the end heads are composed of a Q390 rectangular end steel plate 201 with a length × height of 1 m × 0.8 m and a thickness of 2 cm, two Q390 rectangular side steel plates 203 with a length × width of 0.6 m × 0.5 m and a thickness of 1 cm, a Q390 rectangular top steel plate 204 with a length × width of 0.8 m × 0.5 m and a thickness of 1 cm, and a Q390 rectangular steel plate 205 with a length × width of 0.8 m × 0.5 m and a thickness of 1 cm. The Q390 rectangular bottom steel plate 205 with a length of 4.96 m is welded, and the two ends are welded and connected by four L100×10 angle steels with a length of 4.96 m. Six first holes 206-1 are set on the end steel plate 201, and three second holes 206-2 are set on the side steel plate 203. The apertures of the first holes 206-1 and the second holes 206-2 are the same, both of which are 40 mm. The vertical spacing between adjacent longitudinal reinforcement holes 207 or transverse reinforcement holes 208 is the same, which is 20 cm. The distance between the top longitudinal reinforcement hole 207 and the upper edge is the same as the distance between the bottom transverse reinforcement hole 208 and the lower edge, which is 25 cm. The first holes 206-1 and the second holes 206-2 at both ends of the beam sleeve 2 are arranged in the same way. The longitudinal embedded pipe 3 is 1 m long, and is a stainless steel pipe with an outer diameter of 40 mm and an inner diameter of 36 mm. The longitudinal embedded pipe 3 is embedded at both ends of the rectangular reinforced concrete 1 along the axial direction of the beam, and 6 longitudinal embedded pipes 3 are embedded at each end. One end of the longitudinal embedded pipe 3 is open and is located on the end steel plate 201 of the beam sleeve 2, overlapping with the first hole 206-1. One end of the longitudinal embedded pipe 3 is sealed, and the sealed section is located in the rectangular reinforced concrete 1. The transverse embedded pipe 4 is 1 m long, and is a stainless steel pipe with an outer diameter of 40 mm and an inner diameter of 36 mm. It is embedded at both ends of the rectangular reinforced concrete 1 perpendicular to the axial direction of the beam, and three transverse embedded pipes 4 are embedded at each end. Both ends of the transverse embedded pipe 4 are open, and the openings are located on the side steel plate 203 of the beam sleeve 2, which overlaps with the second hole 206-2 on the side steel plate 203. The longitudinal embedded pipe 3 and the transverse embedded pipe 4 are arranged alternately.
[0031] like Figure 4As shown, it is a schematic diagram of the overall structure of the welded buckle of the assembled foundation pit support beam section which is easy to dismantle. Buckles 209 are welded on the sides of the beam sleeve 2 at both ends. The buckles 209 are evenly arranged in the vertical space on the sides of the beam sleeve 2. The buckles are hollow rectangular steel components. The cross-sectional height of each buckle is 20 cm, the width is 4 cm, and the length is 20 cm. The height of the internal hollow part is 18 cm, the width is 2 cm, and the length is 20 cm.
[0032] like Figure 5 , Figure 6 As shown, it is a schematic diagram of the axial connection structure of two beams of the assembled foundation pit support beam segment that is easy to dismantle and a schematic diagram of the axial connection structure of two beams with welded buckles of the assembled foundation pit support beam segment that is easy to dismantle. The two foundation pit support beam segments are connected by connecting steel bars 5 with a diameter of 36 mm. The connecting steel bars 5 are first inserted into the longitudinal embedded pipe 3 of the foundation pit support beam segment, and the other foundation pit support beam segment is hoisted and docked by a crane. The two foundation pit support beam segments are docked, and the above operations are repeated to complete the axial connection of multiple foundation pit support beam segments. Buckles 209 are welded on the side of the beam sleeve 2. After the foundation pit support beam segment is axially connected by connecting steel bars 5, a connecting steel plate 8 with a length of 60 cm, a height of 18 cm, and a width of 2 cm is used for connection. The connecting steel plate 8 is inserted into the buckles 209 at the ends of the two foundation pit support beam segments.
[0033] like Figure 7 As shown, it is a schematic diagram of the four-beam cross connection structure of the assembled foundation pit support beam section which is easy to dismantle. After the axial connection of the foundation pit support beam section is completed, the connecting steel bar 5 with a diameter of 36 mm is inserted into the transverse embedded pipe 4 at the axial connection node of the foundation pit support beam section, and the longitudinal embedded pipe 3 of the foundation pit support beam section is butt-jointed with the connecting steel bar 5 to complete the cross connection.
[0034] like Figure 8 As shown, the prefabricated mold of the foundation pit support beam section is formed by splicing a bottom mold 9, two side molds 10, and two end molds 11. The connection is fixed and locked by bolts, so that the bottom mold 9, the side mold 10, and the end mold 11 are tightly fixed together.
[0035] The longitudinal embedded pipe 3 and the transverse embedded pipe 4 are both steel pipes with smooth inner sides and threads on the outer sides.
[0036] The buckle loop 209 is rectangular in shape, and the connecting steel plate 8 is a steel plate.
[0037] The transverse pre-buried pipe 4 is of the same model as the longitudinal pre-buried pipe 3 , and has the same outer diameter and hole diameter as those of the longitudinal pre-buried pipe 3 .
[0038] The surface of the beam sleeve of the prefabricated supporting beam is coated with anti-rust paint, and the surface of the concrete is coated with a protective layer.
[0039] Example 1 For a foundation pit, the outer dimensions of the underground continuous wall are 69 m×60 m. The inner support is arranged in an orthogonal brace. The inner support of the foundation pit is designed to be 4 layers. The cross-sectional width of the foundation pit support beam section is designed to be 1000 mm, the cross-sectional height is 800 mm, and the length of the foundation pit support beam section is designed to be 4000 mm.
[0040] Clean the concrete residues remaining in the mold placement area, clean the joints between the side mold 10 and the end mold 11, and the joints between the side mold 10 and the end mold 11 and the bottom mold 9; The beam sleeve is welded into a frame using four 4m long L100×10 angle steels 202 and two Q390 end steel plates 201 with a length of 1m, a width of 0.8m and a thickness of 20mm. The end steel plate 201 is provided with 6 first holes 206-1 according to the design, which are arranged in two columns and three rows. There are three first holes 206-1 in one column. The first holes 206-1 in two columns are arranged symmetrically along the central axis of the end steel plate 201. The vertical distance between the centers of adjacent holes in one column of the first holes 206-1 is the same, which is 200mm. The center of the top first hole 206-1 in one column of the first holes 206-1 is 150mm away from the upper edge of the end steel plate 201 and 650mm away from the lower edge of the end steel plate 201. mm, 2 first holes 206-1 in a row, the center horizontal spacing of the first holes 206-1 is 800mm, the diameter of the first hole 206-1 on the end steel plate 201 is 40 mm, and a Q390 side steel plate 203 with a length of 0.5 m, a width of 0.6 m and a thickness of 10 mm is welded on the frame, a total of four side steel plates 203, each side steel plate 203 is provided with 3 second holes 206-2 according to the design, and the 3 second holes 206-2 are in a row, and the center spacing of the vertically adjacent second holes 206-2 is 200 mm, the uppermost second hole 206-2 is 50 mm away from the upper edge of the side steel plate 203, 550 mm away from the lower edge, 380 m away from the left edge, and 120 mm away from the right edge, the diameter of the second hole 206-2 on the side steel plate 203 is 40 mm, the welding length is 0.5 m, the width is 0.8 m and the thickness is 10 mm bottom steel plate 205; Three transverse embedded pipes 4 are arranged at both ends of the foundation pit support beam section. The transverse embedded pipes 4 are stainless steel pipes with an outer diameter of 40 mm, an inner diameter of 36 mm and a length of 1 m. Both ends of the transverse embedded pipes 4 are open. The transverse embedded pipes 4 are inserted into the second hole 206-2. The transverse embedded pipes 4 are welded and fixed to the side steel plate 203. Six longitudinal embedded pipes 3 are arranged at both ends of the foundation pit support beam section. The longitudinal embedded pipes 3 are stainless steel pipes with an outer diameter of 40 mm, an inner diameter of 36 mm and a length of 1 m. One end of the longitudinal embedded pipes 3 is open and the other end is sealed. The sealed end is located on the inner side. The open end of the longitudinal embedded pipe 3 is inserted into the first hole 206-1. The longitudinal embedded pipe 3 is welded and fixed to the end face steel plate 201. Two 18 mm HRB400 vertical steel bars 7 with a length of 600 mm are used to connect the transverse embedded pipe 4 and the longitudinal embedded pipe 3. The vertical steel bars 7 are welded and fixed at the contact points between the transverse embedded pipe 4 and the longitudinal embedded pipe 3. The longitudinal reinforcement is 18 mmHRB400, and the stirrup is 10 mmHRB336. The steel bars are tied according to the design, and the ends of some longitudinal steel bars 6 are tied to the longitudinal embedded pipes 3; After the reinforcement is tied, the top steel plate 204 is welded. The top steel plate 204 has a length of 0.5 m, a width of 0.8 m, and a thickness of 10 mm to form a beam sleeve 2. Apply a water-based release agent on the bottom mold 9; Place the welded beam sleeve 2 on the bottom mold 9; Apply water-based mold release agent on the side mold 10 and the end mold 11 before installation. During installation, ensure that the side mold 10 and the end mold 11 are completely attached to the beam sleeve 2; Pour concrete into the mold. When pouring, the ends of the longitudinal embedded pipe 3 and the transverse embedded pipe 4 are sealed with gypsum. When pouring, it should be ensured that the longitudinal embedded pipe 3 and the transverse embedded pipe 4 do not deviate. After pouring, vibrate with a vibrator until no bubbles are generated. After the rectangular reinforced concrete 1 has formed strength, it is demoulded and cured, and after the curing is completed, it is demoulded; After demolding is completed, scrape off the excess concrete on the surface of the beam sleeve 2, remove the sealing plaster of the longitudinal embedded pipe 3 and the transverse embedded pipe 4, apply a protective layer on the concrete surface, and brush anti-rust paint on the surface of the beam sleeve 2 and the inner walls of the longitudinal embedded pipe 3 and the transverse embedded pipe 4.
[0041] Example 2 In a subway foundation pit project, seven supports were used to maintain the stability of the underground continuous wall. The cross-sectional width of the designed foundation pit support beam section was 800 mm, the cross-sectional height was 800 mm, and the length of the designed foundation pit support beam section was 4000 mm.
[0042] Clean the concrete residues remaining in the mold placement area, clean the joints between the side mold 10 and the end mold 11, and the joints between the side mold 10 and the end mold 11 and the bottom mold 9; The beam sleeve 2 is welded into a frame using four 4 m long L100×10 angle steels 202 and two Q390 end face steel plates 201 with a length of 0.8 m, a width of 0.8 m and a thickness of 20 mm. The end face steel plate 201 is provided with six first holes 206-1 according to the design, which are arranged in two columns and three rows. There are three first holes 206-1 in one column. The first holes 206-1 in two columns are arranged symmetrically along the central axis of the end face steel plate 201. The vertical distance between the centers of adjacent holes in one column of the first holes 206-1 is the same, which is 200 mm. The center of the top first hole 206-1 is 150 mm away from the upper edge of the end face steel plate 201 and 650 mm away from the lower edge of the end face steel plate 201. There are two first holes 206-1 in one row, and the horizontal spacing between the centers of the first holes 206-1 is 600 mm. mm, the diameter of the first hole 206-1 on the end steel plate 201 is 40 mm, a Q390 side steel plate 203 with a length of 0.5 m, a width of 0.6 m and a thickness of 10 mm is welded on the frame, a total of four side steel plates 203, each side steel plate 203 is provided with three second holes 206-2 according to the design, the three second holes 206-2 are in a row, the center spacing of the vertically adjacent second holes 206-2 is 200 mm, the uppermost second hole 206-2 is 50 mm away from the upper edge of the side steel plate 203, 550 mm away from the lower edge, 280 mm away from the left edge, and 220 mm away from the right edge, the diameter of the hole on the side steel plate 203 is 40 mm, and a bottom steel plate 205 with a length of 0.5 m, a width of 0.6 m and a thickness of 10 mm is welded; Three transverse embedded pipes 3 are arranged at both ends of the foundation pit support beam section. The transverse embedded pipes 3 are stainless steel pipes with an outer diameter of 40 mm, an inner diameter of 36 mm and a length of 0.8 m. Both ends of the transverse embedded pipes 3 are open. The transverse embedded pipes 3 are inserted into the second hole 206-2. The transverse embedded pipes 3 are welded and fixed to the side steel plate 203. Six longitudinal embedded pipes 3 are arranged at both ends of the foundation pit support beam section. The longitudinal embedded pipes 3 are stainless steel pipes with an outer diameter of 40 mm, an inner diameter of 36 mm and a length of 1 m. One end of the longitudinal embedded pipes 3 is open and the other end is sealed. The sealed end is located on the inner side. The open end of the longitudinal embedded pipe 3 is inserted into the first hole 206-1. The longitudinal embedded pipe 3 is welded and fixed to the end face steel plate 201. Two 18 mm HRB400 vertical steel bars 7 with a length of 600 mm are used to connect the transverse embedded pipe 3 and the longitudinal embedded pipe 3. The vertical steel bars 7 are welded and fixed at the contact between the transverse embedded pipe 3 and the longitudinal embedded pipe 3; The longitudinal reinforcement is 18 mmHRB400, and the stirrup is 10 mmHRB336. The steel bars are tied according to the design, and the ends of some longitudinal steel bars 6 are tied to the longitudinal embedded pipes 3; After the reinforcement is tied, the top steel plate 204 is welded. The top steel plate 204 has a length of 0.5 m, a width of 0.6 m, and a thickness of 10 mm to form a beam sleeve 2. Apply a water-based release agent on the bottom mold 9; Place the welded beam sleeve 2 on the bottom mold 9; Apply water-based mold release agent on the side mold 10 and the end mold 11 before installation. During installation, ensure that the side mold 10 and the end mold 11 are completely attached to the beam sleeve 2; Pour concrete into the mold. During pouring, the ends of the longitudinal embedded pipe 3 and the transverse embedded pipe 3 are sealed with gypsum. During pouring, it should be ensured that the longitudinal embedded pipe 3 and the transverse embedded pipe 3 do not deviate. After pouring, vibrate with a vibrator until no bubbles are generated. After the rectangular reinforced concrete 1 has formed strength, it is demoulded and cured, and after the curing is completed, it is demoulded; After demolding is completed, scrape off the excess concrete on the surface of the beam sleeve 2, remove the sealing plaster of the longitudinal embedded pipe 3 and the transverse embedded pipe 4, apply a protective layer on the concrete surface, and brush anti-rust paint on the surface of the beam sleeve 2 and the inner walls of the longitudinal embedded pipe 3 and the transverse embedded pipe 4.
[0043] Example 3 A foundation pit, covering an area of 13000 mm 2 The design cross-sectional dimensions of the foundation pit support beam section are 800 mm in height and 1000 mm in width, and the design length of the foundation pit support beam section is 5 m.
[0044] Clean the concrete residues remaining in the mold placement area, clean the joints between the side mold 10 and the end mold 11, and the joints between the side mold 10 and the end mold 11 and the bottom mold 9; The beam sleeve 2 is welded into a frame using four 5 m long L100×10 angle steels 202 and two Q390 end face steel plates 201 with a length of 1 m, a width of 0.8 m and a thickness of 20 mm. The end face steel plate 201 is provided with 6 first holes 206-1 according to the design, which are arranged in two columns and three rows. There are 3 first holes 206-1 in one column. The first holes 206-1 in two columns are arranged symmetrically along the central axis of the end face steel plate 201. The vertical distance between the centers of adjacent first holes 206-1 in one column of the first holes 206-1 is the same, which is 200 mm. The center of the top first hole 206-1 in one column of the first holes 206-1 is 150 mm away from the upper edge of the end face steel plate 201 and 650 mm away from the lower edge of the end face steel plate 201. There are 2 first holes 206-1 in one row, and the horizontal spacing between the centers of the first holes 206-1 is 800 mm. mm, the diameter of the first hole 206-1 on the end steel plate 201 is 40 mm, a Q390 side steel plate 203 with a length of 0.5 m, a width of 0.6 m and a thickness of 10 mm is welded on the frame, a total of four side steel plates 203, each side steel plate 203 is provided with three second holes 206-2 according to the design, the three second holes 206-2 are in a row, the center spacing of the vertically adjacent second holes 206-2 is 200 mm, the uppermost second hole 206-2 is 50 mm away from the upper edge of the side steel plate 203, 550 mm away from the lower edge, 380 mm away from the left edge, and 120 mm away from the right edge, the diameter of the second hole 206-2 on the side steel plate 203 is 40 mm, and a bottom steel plate 205 with a length of 0.5 m, a width of 0.8 m and a thickness of 10 mm is welded; Three transverse embedded pipes 4 are arranged at both ends of the foundation pit support beam section. The transverse embedded pipes 4 are stainless steel pipes with an outer diameter of 40 mm, an inner diameter of 36 mm and a length of 1 m. Both ends of the transverse embedded pipes 4 are open. The transverse embedded pipes 4 are inserted into the second hole 206-2. The transverse embedded pipes 4 are welded and fixed to the side steel plate 203. Six longitudinal embedded pipes 3 are arranged at both ends of the foundation pit support beam section. The longitudinal embedded pipes 3 are stainless steel pipes with an outer diameter of 40 mm, an inner diameter of 36 mm and a length of 1 m. One end of the longitudinal embedded pipes 3 is open and the other end is sealed. The sealed end is located on the inner side. The open end of the longitudinal embedded pipe 3 is inserted into the first hole 206-1. The longitudinal embedded pipe 3 is welded and fixed to the end face steel plate 201. Two 18 mm HRB400 vertical steel bars 7 with a length of 600 mm are used to connect the transverse embedded pipe 4 and the longitudinal embedded pipe 3. The vertical steel bars 7 are welded and fixed at the contact points between the transverse embedded pipe 4 and the longitudinal embedded pipe 3. The longitudinal reinforcement is 18 mmHRB400, and the stirrup is 10 mmHRB336. The steel bars are tied according to the design, and the ends of some longitudinal steel bars 6 are tied to the longitudinal embedded pipes 3; After the reinforcement is tied, the top steel plate 204 is welded. The top steel plate 204 has a length of 0.5 m, a width of 0.8 m, and a thickness of 10 mm to form a beam sleeve 2. Apply a water-based release agent on the bottom mold 9; Place the welded beam sleeve 2 on the bottom mold 9; Apply water-based mold release agent on the side mold 10 and the end mold 11 before installation. During installation, ensure that the side mold 10 and the end mold 11 are completely attached to the beam sleeve 2; Pour concrete into the mold. When pouring, the ends of the longitudinal embedded pipe 3 and the transverse embedded pipe 4 are sealed with gypsum. When pouring, it should be ensured that the longitudinal embedded pipe 3 and the transverse embedded pipe 4 do not deviate. After pouring, vibrate with a vibrator until no bubbles are generated. After the rectangular reinforced concrete 1 has formed strength, it is demoulded and cured, and after the curing is completed, it is demoulded; After demolding is completed, scrape off the excess concrete on the surface of the beam sleeve 2, remove the sealing plaster of the longitudinal embedded pipe 3 and the transverse embedded pipe 4, apply a protective layer on the concrete surface, and brush anti-rust paint on the surface of the beam sleeve 2 and the inner walls of the longitudinal embedded pipe 3 and the transverse embedded pipe 4.
[0045] The above-mentioned embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The embodiments and features in the embodiments of the present application can be arbitrarily combined with each other without conflict. The protection scope of the present invention shall be the technical solutions recorded in the claims, including the equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
[0046] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0047] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An assembled foundation pit support beam section that is easy to dismantle, comprising a rectangular reinforced concrete (1), a beam sleeve (2), a longitudinal embedded pipe (3) and a transverse embedded pipe (4), characterized in that: The beam sleeve (2) is sleeved on the rectangular reinforced concrete (1), and the beam sleeve (2) comprises an end steel plate (201), an angle steel (202), a side steel plate (203), a top steel plate (204), and a bottom steel plate (205); a first hole (206-1) is provided on the end steel plate (201), and a second hole (206-2) is provided on the side steel plate (203); a tube wall at one end of the longitudinal embedded pipe (3) is welded to the inner wall of the first hole (206-1) to form a longitudinal reinforcement insertion hole (207), and the other end penetrates into the rectangular reinforced concrete (1) and is parallel to the angle steel (202); tube walls at both ends of the transverse embedded pipe (4) are respectively welded to the hole walls of the second hole (206-2) on the side steel plates (203) on both sides to form a transverse reinforcement insertion hole (208), and are perpendicular to the angle steel (202); the longitudinal embedded pipe (3) and the transverse embedded pipe (4) do not intersect.
2. The easily dismantled assembled foundation pit support beam section according to claim 1 is characterized in that: The longitudinal reinforcing bar insertion holes (207) and the transverse reinforcing bar insertion holes (208) have the same hole diameters.
3. The easily dismantled assembled foundation pit support beam section according to claim 1 is characterized in that: The vertical spacings of adjacent longitudinal reinforcement holes (207) or transverse reinforcement holes (208) are the same, and the distance between the uppermost longitudinal reinforcement hole (207) and the upper edge of the beam sleeve (2) is equal to the distance between the lowermost transverse reinforcement hole (208) and the lower edge of the beam sleeve (2).
4. The easily dismantled assembled foundation pit support beam section according to claim 1 is characterized in that: The longitudinal reinforcing bar insertion holes (207) are in two rows, and the transverse reinforcing bar insertion holes (208) are in one row; the distance between the two rows of longitudinal reinforcing bar insertion holes (207) is equal to twice the distance between the transverse reinforcing bar insertion holes (208) and the end face steel plate (201).
5. The easily dismantled assembled foundation pit support beam section according to claim 1 is characterized in that: The longitudinal embedded pipe (3) is a steel pipe with a threaded outer side and a smooth inner side. One end of the steel pipe that penetrates into the rectangular reinforced concrete (1) is sealed and the other end is open. The transverse embedded pipe (4) is a steel pipe with a threaded outer side and a smooth inner side. Both ends of the steel pipe are open.
6. The easily dismantled assembled foundation pit support beam section according to claim 1 is characterized in that: Buckles (209) are welded onto the side steel plates (203) of the beam sleeve (2), and the buckles (209) are evenly arranged on the side steel plates (203).
7. The method for prefabricating an easily dismantled assembled foundation pit support beam segment according to any one of claims 1 to 6, characterized in that: The following steps are involved: 1) cleaning the concrete residues remaining in the mold placement area, cleaning the joints between the side mold (10) and the end mold (11), and the joints between the side mold (10) and the end mold (11) and the bottom mold (9); 2) welding the beam sleeve (2), four angle steels (202) and two end steel plates (201) to form a frame, and welding the side steel plates (203) and the bottom steel plate (205) to the frame; 3) The transverse embedded pipe (4) is inserted into the second hole (206-2) and fixed by welding, and the longitudinal embedded pipe (3) is inserted into the first hole (206-1) and fixed by welding; 4) connecting the transverse embedded pipe (4) and the longitudinal embedded pipe (3) with vertical steel bars (7), and welding and fixing the vertical steel bars (7) at the contact points with the transverse embedded pipe (4) and the longitudinal embedded pipe (3); 5) Steel bar binding; 6) After the reinforcement is tied, the top steel plate (204) is welded to form the beam sleeve (2); 7) Apply a water-based release agent to the bottom mold (9); 8) placing the welded beam sleeve (2) on the bottom mold (9); 9) Apply a water-based release agent to the side mold (10) and the end mold (11) before installing them. During installation, ensure that the side mold (10) and the end mold (11) are completely attached to the beam sleeve (2); 10) pouring concrete into the mold, before pouring, the ends of the longitudinal embedded pipe (3) and the transverse embedded pipe (4) are sealed with gypsum, and before pouring, the longitudinal embedded pipe (3) and the transverse embedded pipe (4) are ensured not to deviate, and after pouring, the vibrator is used to vibrate until no bubbles are generated; 11) After the rectangular reinforced concrete (1) has formed strength, it is demoulded and cured. After the curing is completed, it is demoulded; 12) After demoulding is completed, remove the excess concrete on the surface of the beam sleeve (2), remove the sealing plaster on the longitudinal embedded pipe (3) and the transverse embedded pipe (4), apply a protective layer on the concrete surface, and apply anti-rust paint on the surface of the beam sleeve (2) and the inner wall of the longitudinal embedded pipe (3) and the transverse embedded pipe (4).
Citation Information
Patent Citations
Refrigerator plate insertion mechanism
CN102852233A
Masonry filler wall reinforcement and plastering constructional column and construction method thereof
CN105019579A
Prefabricated concrete structure for foundation pit support
CN109826202A
Precast prestressed beam-column joint torsion-resistant structure and installation method
CN110453778A
Assembly type concrete structure beam-column joint connecting structure
CN214784709U
Cited By
Foundation pit supporting beam section with beam sleeve
CN224605570U