Park multi-energy collaborative planning method, device and equipment considering island operation mode and storage medium

By building a multi-energy collaborative planning model in the island mode in a multi-energy park, and using scene trees and objective functions to optimize energy supply, the problem of power supply reliability in the island operating mode is solved, and energy flexibility and efficiency improvement is achieved.

CN118886644APending Publication Date: 2024-11-01STATE GRID ECONOMIC TECH RES INST CO LTD +2

Patent Information

Application Number
CN202410904515.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

In multi-energy parks, how to ensure power supply reliability in the isolated island operation mode, especially in the event of external power grid failure, achieve synergy and complementarity of energy supply, and improve the flexibility and efficiency of energy use.

Method used

By obtaining the energy network data of the park, a scene tree of the island mode is generated, and based on the objective function that minimizes the total planning cost and the minimum energy loss expectations, a multi-energy collaborative planning model is built, and energy supply is controlled in real time, and energy disposal strategies and energy storage are adopted. Strategy to maintain supply and demand balance.

Benefits of technology

Optimize energy use, improve the reliability of power supply in the park, and can reasonably plan energy allocation according to the fault level, improving the stability and flexibility of the energy system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118886644A_ABST
    Figure CN118886644A_ABST
Patent Text Reader

Abstract

The invention discloses a park multi-energy collaborative planning method and device considering an island operation mode, equipment and a storage medium. The method comprises the steps of obtaining energy network data of a current target multi-energy park; generating a scene tree containing a plurality of island modes according to the power failure reasons causing the island modes of the multi-energy park; according to the objective function, the energy network data and the scene tree, constructing a multi-energy collaborative planning model considering the park in the island operation mode; and when the multi-energy collaborative planning model operates, controlling each energy plan in the target multi-energy park in real time based on a planning result output by the multi-energy collaborative planning model. When an external power grid breaks down, an energy supply strategy is adjusted according to actual requirements, and the flexibility and efficiency of energy use are improved; the grades of the power grid power failure faults are divided based on the scene tree, reasonable planning and distribution of energy in the park are facilitated according to the priority of the faults, and the operation stability of an energy system in the park is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of distribution network planning and design, and in particular to a method, device, equipment and storage medium for collaborative planning of multiple energy sources in a park considering an isolated island operation mode. Background Art

[0002] With the continuous development of distribution network planning technology, improving energy quality and developing clean energy have become the consensus of countries around the world. Multi-energy parks have gradually been put on the agenda because of their characteristics of coupling multiple energy sources, coordinating and dispatching various energy supply systems, improving energy utilization and reducing the economic cost of energy systems.

[0003] Multi-energy parks are the most intuitive manifestation of the energy Internet. With the gradual development of multi-energy parks, the increasing proportion of renewable energy access such as wind power and photovoltaics, the continuous investment in energy storage equipment, and the continuous enrichment of park energy types, the island operation mode has gradually become possible.

[0004] At the same time, for industrial parks with high requirements for power supply reliability, how to make reliable multi-energy coordination plans to address functional problems caused by random failures in the industrial park power grid has become a technical problem that technical personnel in this field need to solve urgently. Summary of the invention

[0005] The present invention provides a method, device, equipment and storage medium for collaborative planning of multiple energy sources in a park under an isolated operation mode, so as to plan a reliable operation plan for the park under the isolated operation mode.

[0006] In order to achieve the above effect, an embodiment of the present invention provides a method for collaborative planning of multiple energy sources in a park considering an isolated island operation mode, the method comprising:

[0007] The energy network data of the current target multi-energy park is obtained, wherein the energy network data at least includes typical load curve data of the park, light intensity data, and island scene data.

[0008] According to the reasons for the power outage that causes the island mode in the multi-energy park, a scenario tree containing several island modes is generated.

[0009] According to the first objective function, the second objective function, the energy network data and the scenario tree, a multi-energy collaborative planning model considering the park under the island operation mode is constructed; wherein, the first objective function reflects the minimization of the total planning cost of the park, and the second objective function reflects the minimum energy loss expectation of the park under the island mode.

[0010] When the multi-energy collaborative planning model is running, the energy plans within the target multi-energy park are controlled in real time based on the planning results output by the multi-energy collaborative planning model; wherein the planning results include control collaborative planning reflecting the grid-connected mode and control collaborative planning reflecting the island mode.

[0011] Furthermore, according to the power outage cause causing the multi-energy park island mode, a scenario tree containing several island modes is generated, including:

[0012] According to the power outage causes of the multi-energy park island mode, a scenario tree including the first island mode, the second island mode and the third island mode is generated; among them, the first island mode is caused by a small-scale fault, the second island mode is caused by an unconventional or large-scale fault, and the third island mode is caused by a pre-arranged power outage.

[0013] Further, generating a scenario tree including a first island mode, a second island mode and a third island mode according to the power outage cause of the multi-energy park island mode includes:

[0014] According to the power outage cause of the multi-energy park island mode, a scenario tree including the first island mode, the second island mode and the third island mode is generated, and the probability density function of each island mode is:

[0015]

[0016] Among them, I is the island type, Tdur is the duration, Docc is the occurrence date, and Tstart is the start time. is the joint probability density function of I, Tdur, Docc and Tstart, i, tdur, docc and tstart are the values ​​of I, Tdur, Docc and Tstart respectively, f I (i) is the probability density function of I, is the conditional probability density function of Tdur, is the conditional probability density function of DOC, is the conditional probability density function of Tstart.

[0017] Furthermore, the first objective function reflects minimizing the total planning cost of the park.

[0018] The second objective function reflects the expected minimum energy loss of the park in the island mode, including penalties for insufficient energy supply and energy abandonment.

[0019] Furthermore, the first objective function is expressed as:

[0020] obj1:min C total=C Inv +C Ope +C Mai +C CO2

[0021] Among them, C total is the total planning cost of the park, C Inv is the annual value of equipment investment cost, C Ope is the annual operating cost in the grid-connected mode, C Mai is the annual maintenance cost in the grid-connected mode, C CO2 is the annual carbon tax cost in the grid-connected mode.

[0022] The second objective function is expressed as:

[0023]

[0024] Among them, C loss is the expected loss in the island mode, g s (u s ) is the loss in scene s.

[0025] Furthermore, when the multi-energy collaborative planning model is running, based on the planning results output by the multi-energy collaborative planning model, each energy plan in the target multi-energy park is controlled in real time, including:

[0026] The multi-energy collaborative planning model is run, and based on the planning results output by the multi-energy collaborative planning model, the energy planning in the grid-connected mode and the energy planning in the island mode within the target multi-energy park are controlled in real time.

[0027] Among them, the control collaborative planning in the grid-connected mode meets the upper-level power grid exchange power constraints, equipment operation constraints and power balance constraints.

[0028] The control collaborative planning in the island mode adopts the energy abandonment strategy to maintain the balance between supply and demand, while bearing the corresponding energy abandonment penalty.

[0029] Furthermore, the energy abandonment strategy includes:

[0030] Initialize the operation status of the isolated campus.

[0031] It uses CHP and PV for electricity, and CHP, GB and HP for heating.

[0032] If CHP and PV can meet the electricity load demand, the excess electricity will be stored in ES; when ES reaches the energy storage limit, power will be abandoned.

[0033] If CHP, GB and HP can meet the heat load demand, the excess heat energy will be stored in HS; when HS reaches the upper limit of energy storage, heat abandonment will be generated.

[0034] If CHP and PV cannot meet the power load demand, ES will be called for discharge; if the ES storage capacity is insufficient, NEL will be cut off. If the power load demand still cannot be met after NEL is cut off, PEL will be cut off.

[0035] If CHP, GB and HP cannot meet the heat demand, HS will be called to release heat; if the HS heat storage capacity is insufficient, NHL will be removed; if the heat load demand still cannot be met after NHL is removed, PHL will be removed.

[0036] Another embodiment of the present invention provides a multi-energy collaborative planning device for a park in an isolated island operation mode, comprising:

[0037] The data acquisition module is used to obtain the energy network data of the current target multi-energy park, and the energy network data at least includes typical load curve data of the park, light intensity data, and island scene data.

[0038] The scenario generation module is used to generate a scenario tree containing several island modes according to the power outage causes that cause the island mode of the multi-energy park.

[0039] A model building module is used to build a multi-energy collaborative planning model for the park under the island operation mode based on the first objective function, the second objective function, the energy network data and the scenario tree; wherein the first objective function reflects the minimization of the total planning cost of the park, and the second objective function reflects the minimum energy loss expectation of the park under the island mode.

[0040] A collaborative planning module is used to control the energy planning of the target multi-energy park in real time based on the planning results output by the multi-energy collaborative planning model when the multi-energy collaborative planning model is running; wherein the planning results include control collaborative planning reflecting the grid-connected mode and control collaborative planning reflecting the island mode.

[0041] Another embodiment of the present invention provides a computer device, including a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, and when the processor executes the computer program, it implements the method for collaborative planning of multiple energy sources in a campus considering the isolated island operation mode as described above.

[0042] Yet another embodiment of the present invention provides a computer-readable storage medium storing a computer program, wherein when the device where the computer-readable storage medium is located executes the computer program, the method for collaborative planning of multiple energy sources in a campus considering the isolated island operation mode as described above is implemented.

[0043] Compared with the prior art, the embodiments of the present invention have the following advantages:

[0044] (1) Optimizing energy use: Coordinated planning of multi-energy parks in isolated operation mode is carried out based on park network information. When an external power grid fails, the energy supply strategy can be adjusted according to actual needs to ensure the energy supply of local users, achieve coordination and complementarity among multiple energy sources, and improve the flexibility and efficiency of energy use.

[0045] (2) Improving the reliability of the campus energy supply: Based on the scenario tree, the levels of power outages in the power grid are classified and different energy coordination schemes are planned in a targeted manner. This helps to reasonably plan and allocate energy within the campus according to the priority of the faults, optimize the allocation of resources, and improve the stability of the energy system operation within the campus. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] Figure 1 It is a flowchart of the steps of a method for collaborative planning of multiple energy sources in a park under an isolated island operation mode in one embodiment of the present invention;

[0047] Figure 2 It is a scene tree representation diagram of a park island scene in one embodiment of the present invention;

[0048] Figure 3 This is a flow chart of a “reliable operation strategy” in an island mode in one embodiment of the present invention;

[0049] Figure 4 It is a total cost of park planning and its composition diagram of one embodiment of the present invention;

[0050] Figure 5 It is an island mode loss expectation and its composition diagram of one embodiment of the present invention;

[0051] Figure 6 1 is a diagram of type I island and type III island ENS of one embodiment of the present invention;

[0052] Figure 7 is a diagram of a type II island ENS according to one embodiment of the present invention;

[0053] Figure 8 It is a structural block diagram of a multi-energy collaborative planning device for a park considering an isolated island operation mode in one embodiment of the present invention;

[0054] Fig. 9 It is a structural diagram of a computer device provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0055] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. The purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0056] In the description of this application, the terms "first", "second", "third", etc. are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first", "second", "third", etc. may explicitly or implicitly include one or more of the feature. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0057] In the description of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be a connection between the two elements. The terms "vertical", "horizontal", "left", "right", "upper", "lower" and similar expressions used herein are only for illustrative purposes, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0058] In the description of this application, it should be noted that, unless otherwise defined, all technical and scientific terms used in the present invention have the same meaning as those commonly understood by those skilled in the art. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood by specific circumstances.

[0059] An embodiment of the present invention provides a method for collaborative planning of multiple energy sources in a park under isolated island operation mode. For details, see Figure 1 , Figure 1 The flowchart of the method for collaborative planning of multiple energy sources in a park under an isolated island operation mode in one embodiment of the present invention is shown, including steps S11-S14:

[0060] Step S11, obtaining energy network data of the current target multi-energy park, wherein the energy network data at least includes typical load curve data of the park, light intensity data, and island scene data.

[0061] Obtain parameters of energy equipment such as distributed power sources, gas boilers, combined heat and power units within the park, as well as basic data such as typical load curves, light intensity, energy prices, and island scenarios in the park.

[0062] By collecting equipment parameters and basic data information in the multi-energy park in advance, it is convenient to make reasonable coordinated planning of the park energy based on the above data.

[0063] Step S12, generating a scenario tree including several island modes according to the power outage cause causing the multi-energy park island mode.

[0064] Grid outages are caused by unexpected faults or pre-arranged outages. Faults have different severity levels and different impacts on the energy supply of the park, which is reflected in the duration of the outage. Therefore, the island mode of the park is divided into 3 categories, as shown in Table 1. Table 1 is the classification table of island modes:

[0065]

[0066]

[0067] Table 1

[0068] The first islanding mode: Type I islanding is caused by a small-scale fault that is easy to repair in the power grid. It lasts for a short time, generally 1 to 5 hours. Assume that its frequency of occurrence is λ I (times / a). The duration, occurrence date, and start time of a Type I island are uncertain.

[0069] The second island mode: Type II island is caused by unconventional and large-scale faults in the power grid, and the fault repair time is long, generally more than ten hours or even several days. Its occurrence frequency is low, assuming λ II (times / a), the duration, date of occurrence and start time of which are indeterminate.

[0070] The third islanding mode: Type III islanding is caused by a pre-arranged power outage in the power grid, and its occurrence frequency is assumed to be λ III (times / a), duration, occurrence date and start time are random but will be notified to the park in advance.

[0071] The random vector ξ is used to represent the island pattern, which consists of four random variables: island type I, duration Tdur, occurrence date Doc, and start time Tstart. ξ is defined as follows:

[0072] ξ=(I,T dur ,D occ ,T start )

[0073] The probability density function (PDF) of ξ, i.e. the joint PDF of I, Tdur, Docc and Tstart, is defined as follows:

[0074]

[0075] Where f(ξ) represents the PDF of ξ; represents the joint PDF of I, Tdur, Docc and Tstart; i, tdur, docc and tstart represent the values ​​of I, Tdur, Docc and Tstart respectively; f I (i) represents the PDF of I; Denote the conditional PDF of Tdur, given that I = i; Denote the conditional PDF of Docc, given that I = i and Tdur = tdur; Denote the conditional PDF of Tstart, given that I=I, Tdur=tdur and Docc=docc.

[0076] The four random variables are not independent, they are associated, and the conditional PDF shows that the latter random variable is constrained and affected by the previous random variable.

[0077] In the actual operation process, it is difficult to obtain an accurate PDF of ξ. Considering the influence of ξ, the planning model of the park is a stochastic optimization problem that is difficult to solve. The common method is to discretize the PDF of ξ and simulate ξ through a finite number of scenarios, thereby converting the stochastic optimization problem into a deterministic optimization problem. In addition, unlike a single random variable, the relationship and constraints of the four random variables in ξ need to be considered during the scenario generation process. Therefore, a scenario tree is used to generate the island scenario.

[0078] The scene tree has a top-down hierarchical tree structure, such as Figure 2 As shown, Figure 2 This is a scene tree representation of the park island scene. Nodes at different levels are connected by branches, representing their associations and constraints.

[0079] Starting from the root node of the L1 layer, three nodes are generated in the L2 layer according to the three island modes. For each node of L2, a node of the L3 layer is generated according to the conditional probability of the duration after the island type is determined. After the island type and duration are determined, a node of the L4 layer is generated according to the conditional probability of the occurrence date. Similarly, considering the conditional probability of the start time, a leaf node of the L5 layer is generated. The path from the root node to the leaf node is defined as the island scenario. Finally, S is generated. total Isolated island scenarios, including S I Type I island scenario, S II Type II island scenario and S III Type III island scenarios. Take scenario s as an example, s∈{1,2,…,S total}, assuming that the corresponding island type is i and the duration is The date of occurrence is Start time is The probability of occurrence of scenario s is:

[0080]

[0081] Among them, λ i represents the occurrence frequency of type i island; and Respectively and The conditional probability of TD i ,DO i and TS i Represents a set of durations, occurrence dates, and start times, including possible values ​​for durations, occurrence dates, and start times.

[0082] Generating a scenario tree based on different causes and types of power outages can clearly classify the operation status of the park, and clearly show the impact of various factors on the island mode in a hierarchical manner, which helps to transform random optimization problems into deterministic optimization problems, thereby establishing a model solution.

[0083] Step S13, based on the first objective function, the second objective function, the energy network data and the scenario tree, construct a multi-energy collaborative planning model considering the park in the island operation mode; wherein the first objective function reflects the minimization of the total planning cost of the park, and the second objective function reflects the minimum energy loss expectation of the park in the island mode.

[0084] This model has two objective functions: the first objective function is to minimize the total planning cost of the park, and its purpose is to optimize the planning scheme and the operation scheme in the grid-connected mode. The purpose of the second objective function is to ensure that the park meets the energy demand as much as possible by optimizing the operation scheme in the isolated island mode; to match the first objective function, the second objective function is expressed as the minimum energy loss expectation of the park in the isolated island mode, including the penalty for insufficient energy supply (Energy Not Supplied, ENS) and the penalty for energy abandoned (Energy Abandoned, EA) due to excessive equipment output.

[0085] The linear weighted sum method is used to transform the above two objective functions into a weighted objective function. The weight coefficient ω in the weighted objective function is adjusted to coordinate the relationship between economy and reliability.

[0086] The first objective function is to minimize the total planning cost of the park, which is expressed as an equal annual value:

[0087] obj1:min C total =C Inv +C Ope +C Mai +C CO2

[0088] Among them, C total is the total planning cost of the park; C Inv is the annual value of equipment investment cost; C Ope is the annual operating cost in the grid-connected mode; C Mai is the annual maintenance cost in the grid-connected mode; C CO2 It is the annual carbon tax cost in the grid-connected mode.

[0089] Assume that there are N candidate devices in the planning, C Inv The calculation is as follows:

[0090]

[0091] Among them, c Inv,m W represents the investment cost per unit capacity of equipment m; m Indicates the configuration capacity of device m; n m represents the life of equipment m; r represents the discount rate; It represents the annual value coefficient, which is used to convert the investment cost of equipment m into the equivalent annual value within its life span; m=1,2…,N.

[0092] C Ope Including the electricity purchase cost and natural gas consumption cost in the grid-connected mode, the calculation formula is as follows:

[0093] C Ope =c grid Pgrid T +sum(c gas G gas )

[0094] Among them, c grid =[c grid (t)] 1×8760 represents the electricity price vector, c grid (t) is the electricity price at time t; P grid =[P grid (t)] 1×8760 Indicates the power vector of electricity purchased from EPG in grid-connected mode, P grid (t) is the purchased power at time t in the grid-connected mode; c gas Represents the natural gas price; G gas =[G gas (t)] 1×8760 represents the natural gas power consumption vector in the grid-connected mode, G gas (t) is the natural gas power consumption at time t in the grid-connected mode; sum() represents the summation function.

[0095] C Mai The expression is:

[0096] C Mai =sum(c Mai P)

[0097] Among them, c Mai =[c Mai,m ] 1×M represents the variable maintenance cost vector per unit power of the equipment, c Mai,m is the variable maintenance cost per unit power of equipment m; P = [P m (t)] M×8760 Represents the device output power matrix in grid-connected mode, P m (t) is the output power of device m at time t in grid-connected mode.

[0098] C CO2 Including carbon tax costs generated by purchasing electricity from EPG and carbon tax costs generated by consuming natural gas:

[0099] C CO2 =c CO2 (sum(μ grid P grid )+sum(μ gas G gas ))

[0100] The second objective function is to minimize the expected loss in the park island mode and reduce ENS and EA as much as possible. The calculation formula is as follows:

[0101]

[0102] Among them, C loss represents the loss expectation in the island mode; g s (u s ) represents the loss in scene s, and the calculation formula is as follows:

[0103]

[0104] in, represents the loss of scene s; is the duration of scene s, c ENS represents the penalty vector of unit power ENS; and They represent the penalty per unit power ENS of PEL, NEL, PHL and NHL respectively; represents the ENS power vector at time t; and represents the ENS power of PEL, NEL, PHL and NHL at time t respectively; c EA represents the penalty vector of unit power EA; and denote the unit power EA penalty of electricity and heat respectively; represents the EA power vector at time t; and They represent the electrical and thermal EA powers at time t respectively.

[0105] The variables and constraints of the planning model are divided into three modules: planning module, grid-connected operation module and island operation module.

[0106] In the planning module, variables are represented by a vector x, which includes the capacity of each device, which should satisfy the upper and lower bounds of the device configuration capacity. x also provides device operation constraints for the two operation modules.

[0107] In the grid-connected operation module, variables are represented by vector y, including the output of each device and the power purchased from the grid, which should meet the device operation constraints and power balance constraints.

[0108] In the island operation module, the variables are represented by the vector u, which contains the output, ENS and EA of each device.

[0109] In order to distinguish different island scenes of the input, the variables in scene s are represented as vector u s In order to reduce the expected loss caused by ENS and EA, the island mode adopts a "reliable operation strategy". The park should meet the corresponding equipment operation constraints, power balance constraints and operation logic constraints, which are expressed in matrix form as follows:

[0110]

[0111] Where f(x,y) represents the total planning cost; E[g(u,ξ)] represents the expected loss in the island mode; E[] represents the expected calculation formula; ω is the weight coefficient, ω∈(0,1]; c, d and q are the coefficient column vectors of the objective function; A, B, C, D, E and F are the coefficient matrices corresponding to the variables in the constraints; a, b, m and n are the coefficient column vectors of the constraints; x u represents the upper limit of x.

[0112] In the above formulas representing the constraints of the planning model, formula (a) represents the configuration capacity limit of the equipment in the plan; formula (b) represents the inequality constraint when the park is operating in grid-connected mode, including the upper and lower limits of the equipment output; formula (c) represents the equality constraint when the park is operating in grid-connected mode, including the energy conversion constraints and power balance constraints of each device; correspondingly, formulas (d) and (e) represent the inequality constraints and equality constraints when the park is operating in island mode, including the operation logic constraints that the "reliable operation strategy" needs to meet.

[0113] Step S14, when the multi-energy collaborative planning model is running, based on the planning results output by the multi-energy collaborative planning model, the energy plans within the target multi-energy park are controlled in real time; wherein the planning results include control collaborative planning reflecting the grid-connected mode and control collaborative planning reflecting the island mode.

[0114] In the grid-connected mode, the park can exchange power with the grid. With the support of the upper-level grid, the park can meet all the electrical load requirements without energy shortage. The park operating in the grid-connected mode should meet the constraints of power exchange with the upper-level grid, equipment operation constraints and power balance constraints.

[0115] Among them, the energy exchange constraint with the upper power grid is expressed as:

[0116]

[0117] in, Indicates the maximum power that the EPG can transmit to the campus.

[0118] Electrical / thermal power balance constraints:

[0119]

[0120] Among them, P L1 (t) and P L2 (t) represent the PEL and NEL power at time t respectively; H L1 (t) and H L2 (t) represent the PHL and NHL power at time t, respectively.

[0121] In the island mode, in order to reduce ENS, the park adopts a "reliable operation strategy", relying on its own energy supply capacity, with the goal of meeting the electricity and heat load demands as much as possible, and adjusting the output of each device through the coordination and complementarity of each link. In order to meet the power demand of the park, the PV output is absorbed as completely as possible, and the CHP works in the "electricity determines heat" mode. Due to the electric-thermal coupling effect, when the power load of the park is high and the heat load is low (such as in summer), the system will have a surplus of heat output when meeting the power load supply, resulting in an imbalance in the supply and demand of heat energy. At this time, the park adopts an energy abandonment strategy to ensure the balance of supply and demand of the system, but at the same time it needs to bear the corresponding energy abandonment penalty. Therefore, the park meets the following operation strategies in the island mode, such as Figure 3 As shown, Figure 3 This is the flow chart of "Reliable Operation Strategy" in isolated island mode:

[0122] 1: Initialize the operation status.

[0123] 2: Use CHP (Combined Heating and Power), PV (Photovoltaic) for power supply, and CHP, GB (Gas Boiler) and HP (Heat Pump) for heating.

[0124] 3: If CHP and PV can meet the electric load demand, the excess electric energy will be stored in ES (ElEHtric Energy Storage System). If ES reaches the energy storage limit, power will be abandoned. At the same time, if CHP, GB and HP can meet the heat load demand, the excess heat will be stored in HS (heat storage). If HS reaches the energy storage limit, heat will be abandoned.

[0125] 4: If CHP and PV cannot meet the electric load demand, ES is called for discharge. If the ES has sufficient power storage, the electric load demand can be met; if CHP, GB and HP cannot meet the heat load demand, HS is called for heat release. If the HS has sufficient heat storage, the heat load demand can be met;

[0126] 5: Based on step 4, if the ES power storage capacity is insufficient, first cut off the NEL (Nonpriority Electrical Load). If the NEL is completely cut off and still cannot meet the power load demand, then cut off the PEL (Priority Electrical Load). If the HS heat storage capacity is insufficient, first cut off the NHL (Nonpriority Heat Load). If the NHL is completely cut off and still cannot meet the heat load demand, then cut off the PHL (Priority Heat Load).

[0127] Specifically, take a park in northern China as an example. The park has high requirements for energy supply reliability and hopes to improve energy supply reliability through park construction. Assuming that the planning period of the park is 15 years, the candidate equipment and its parameters are shown in Table 2 and Table 3. Considering the losses caused by ENS and EA in the island mode, assuming 290 yuan / kW, 70 yuan / kW, 60 yuan / kW, is 20 yuan / kW. In addition, assuming 1.35 yuan / kW, 1.2 yuan / kW. In order to reflect the volatility and seasonal differences of load and renewable energy, the data of three typical days in summer, winter and transition season and two extreme typical days in summer and winter are used to represent the situation throughout the year. The number of days in each typical day in a year is 100, 109, 152, 2 and 2. Among them, the electricity load on the extreme typical day in summer is 10% higher than that on the regular typical day, while the PV output is only 70%; the heat load on the extreme typical day in winter is 10% higher than that on the regular typical day.

[0128]

[0129] Table 2 Energy production and conversion equipment parameters

[0130]

[0131] Table 3 Energy production and conversion equipment parameters

[0132] The natural gas price is fixed at 2.71 yuan / m3, and the lower calorific value of natural gas is 9.7kWh / m3. The converted natural gas price is 0.28 yuan / kWh. The CO2 emission coefficients corresponding to the purchase of electricity from EPG and the consumption of natural gas are 0.137kg / kWh and 0.198kg / kWh respectively, and the carbon tax cost per kg is 0.02 yuan. The discount rate r is 8%.

[0133] The EPG power outage data and island mode parameters are provided by the local power supply company, and the island scenario is generated using a scenario tree, as shown in Table 4.

[0134] In order to compare the effectiveness of the multi-objective planning method compared with the single-objective planning method that only considers the economic efficiency of the park, and the effectiveness of the multi-energy coupling energy supply method compared with the traditional independent energy supply method in improving the system operation economy and energy supply reliability, three examples are set as follows:

[0135] Case I: Multi-objective planning is adopted, with the lowest total cost of park planning and the lowest expected loss in island mode as the objective function, and the weight coefficient ω is set to 0.5; the system adopts a multi-energy coupling energy supply mode, and the candidate equipment includes CHP, PV, GB, HP, ES and HS.

[0136] Case II: Single-objective planning is adopted, and only the minimum total cost of park planning is taken as the objective function; the system adopts multi-energy coupling energy supply mode.

[0137] Case III: Multi-objective planning is adopted, and the weight coefficient ω is set to 0.5; the system adopts an independent energy supply mode, that is, in the park grid-connected mode, electric energy is supplied by EPG, and thermal energy is supplied by GB; in the park island mode, a backup diesel generator (Diesel Generator, DG) is used for power supply.

[0138]

[0139] Table 4 Island mode parameters and scenario generation

[0140] By solving, the equipment configuration capacity results are obtained, as shown in Table 5. The CHP and GB capacities of Case I are higher than those of Case II, while the HP capacity is lower than that of Case II. Therefore, Case I uses more natural gas for heating and reduces its dependence on EPG. The PV capacity of Case I is slightly lower than that of Case II, and the ESS capacity is much lower than that of Case II. The ES capacity is about 420 kWh lower than that of Case II, and the HS capacity is about 2300 kWh lower than that of Case II. Case III only uses GB as a heat source and is configured with a large-capacity GB; in addition, a DG of 823 kW is configured as a backup power source in island mode.

[0141]

[0142] Table 5 Equipment configuration capacity results

[0143] The total planning cost of the park Ctotal, the expected loss of the island mode Closs and its composition are as follows: Figure 4 and Figure 5 As shown, Figure 4 The total cost of the park planning and its composition diagram, Figure 5 This is the loss expectation of the island mode and its composition diagram.

[0144] Compared with Case I and Case II, the Ctotal of Case II is 10,600 yuan higher than that of Case I, accounting for only 0.17%. The Closs of Case II is about 2.6 times that of Case I, 33,800 yuan higher than that of Case I. Although the Ctotal of Case I is slightly higher, the Closs is lower. Therefore, the multi-objective planning method adopted in Case I takes into account the island mode of the park, which can effectively resist the impact of EPG power outages and enhance the energy supply reliability of the park.

[0145] Comparing Case I and Case III, although the investment cost of Case III is much lower than that of Case I, Case III is highly dependent on EPG when operating in grid-connected mode, and its operating cost is about 2.5 times that of Case I. The total planning cost of Case III is about 283.57 million yuan higher than that of Case I, an increase of 31%. When EPG fails, Case III lacks the support of EPG and can only be powered by backup DG, resulting in a serious shortage of energy supply. The Closs reaches 40,200 yuan, about twice that of Case I. Therefore, the use of multi-energy coupling in the park can not only reduce the cost of energy supply, but also improve the energy supply reliability of the park under EPG power outages.

[0146] The EENS of each case is shown in Table 6, which shows the energy supply reliability of the park in the island mode. Due to the multi-energy complementarity of Case I and Case II and the backup support of DG in Case III, the three cases have a certain reliability and can fully supply PEL and PHL. Since the EPG power outage has little impact on heating, Case I and Case III can also fully supply NHL, and Case II only has a small amount of NHL energy shortage. For NEL, the EENSe2 of the three cases is different, among which Case I is the lowest, Case III is the second, and Case II is the highest. This shows that the use of multi-objective planning can further tap the potential of multi-energy coupling and coordinated complementarity in the park, reduce EENSe2, and improve the energy supply reliability in the island mode.

[0147]

[0148]

[0149] Table 6 EENS results

[0150] Furthermore, the ENS of NEL of three examples are compared, such as Figure 6 and Figure 7 As shown, Figure 6 The ENS diagrams for type I and type III islands are shown in Figure 1. Figure 7 This is the type II island ENS diagram;.

[0151] Figure 6 The second half shows the ENS of the park running on a type I island from 17:00 to 19:00 on an extreme typical day in winter. During this period, the power load is high, and ENS occurs in all three cases. Case I and Case II only have ENS at 18:00 and 19:00, and the ENS of Case I is smaller than that of Case II, indicating that the EPG power outage has little impact on Case I. Case III has ENS throughout the entire period, and the ENS value is high, which is greatly affected by the EPG power outage.

[0152] Figure 6 The first half of the figure shows the park running in ENS with type III islanding. Since type III islanding occurs on a typical day in the transition season with low load, the impact on the park power supply is small. Case I and Case II can ensure reliable power supply in islanding mode without ENS. Case III has ENS from 11:00 to 14:00, but the value is low.

[0153] Figure 7 The ENS of the park when it is operating in a Type II island on an extreme typical day throughout the summer, when the electrical load is high but the PV output is low. ENS occurred in Case II and Case III. In Case II, ENS occurred between 6:00-9:00 and 22:00-0:00, and lasted for 6 hours; while in Case III, ENS occurred more concentratedly between 9:00-23:00, and lasted for 13 hours. The ENS of Case II and Case III are both high, but the total ENS of Case II is lower than that of Case III. At this time, the impact on Case I is small, and there is no ENS in Case I.

[0154] The method for collaborative planning of multiple energy sources in a park under an isolated operation mode of the present invention coordinates and plans the multi-energy park under an isolated operation mode according to the network information of the park. When a failure occurs in the external power grid, the energy supply strategy can be adjusted according to actual demand to ensure the energy supply of local users, achieve collaboration and complementarity among multiple energy sources, and improve the flexibility and efficiency of energy use. Dividing the levels of power outages based on the scenario tree and planning different energy coordination schemes in a targeted manner can help to reasonably plan and allocate energy within the park according to the priority of the failure, optimize the allocation of resources, and improve the stability of the operation of the energy system within the park.

[0155] The embodiment of the present invention further provides a device for collaborative planning of multiple energy sources in a park under an isolated island operation mode, which is used to execute the method for collaborative planning of multiple energy sources in a park under an isolated island operation mode as described above. Figure 8 The system structure block diagram of an embodiment of the present invention includes:

[0156] The data acquisition module 21 is used to obtain the energy network data of the current target multi-energy park, and the energy network data at least includes typical load curve data of the park, light intensity data, energy price data, and island scene data.

[0157] The scenario generation module 22 is used to generate a scenario tree including a plurality of island modes according to the power outage causes that cause the multi-energy park island mode.

[0158] The model building module 23 is used to construct a multi-energy collaborative planning model for the park under the island operation mode based on the first objective function, the second objective function, the energy network data and the scenario tree; wherein the first objective function reflects the minimization of the total planning cost of the park, and the second objective function reflects the minimum energy loss expectation of the park under the island mode.

[0159] The collaborative planning module 24 is used to control the various energy plans within the target multi-energy park in real time based on the planning results output by the multi-energy collaborative planning model when the multi-energy collaborative planning model is running; wherein the planning results include control collaborative planning reflecting the grid-connected mode and control collaborative planning reflecting the island mode.

[0160] The technical features and technical effects of the system proposed in the embodiment of the present invention are the same as those of the method proposed in the embodiment of the present invention, and are not described in detail here. Each module in the above system can be implemented in whole or in part by software, hardware, and a combination thereof. Each of the above modules can be embedded in or independent of a processor in a computer device in the form of hardware, or can be stored in a memory in a computer device in the form of software, so that the processor can call and execute operations corresponding to each of the above modules.

[0161] An embodiment of the present invention also provides a computer-readable storage medium, which includes a stored computer program; wherein, when the computer program is running, it controls the device where the computer-readable storage medium is located to execute the multi-energy collaborative planning method for a campus considering the island operation mode as described above.

[0162] The embodiment of the present invention further provides a computer device, Fig. 9 The present invention provides a structural block diagram of a preferred embodiment of a computer device, wherein the computer device includes a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, and when the processor executes the computer program, the method for collaborative planning of multiple energy sources in a campus considering an isolated island operation mode is implemented as described above.

[0163] Preferably, the computer program can be divided into one or more modules / units (such as computer program 1, computer program 2, ...), and the one or more modules / units are stored in the memory and executed by the processor to complete the present invention. The one or more modules / units can be a series of computer program instruction segments that can complete specific functions, and the instruction segments are used to describe the execution process of the computer program in the computer device.

[0164] The processor may be a central processing unit (CPU), or other general-purpose processors, a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor, or the processor may be any conventional processor. The processor is the control center of the computer device, and various parts of the computer device are connected using various interfaces and lines.

[0165] The memory mainly includes a program storage area and a data storage area, wherein the program storage area can store an operating system, an application required for at least one function, etc., and the data storage area can store related data, etc. In addition, the memory can be a high-speed random access memory, or a non-volatile memory, such as a plug-in hard disk, a smart memory card (SmartMedia Card, SMC), a secure digital (Secure Digital, SD) card, and a flash card (Flash Card), etc., or the memory can also be other volatile solid-state storage devices.

[0166] It should be noted that the above-mentioned computer device may include, but is not limited to, a processor and a memory. Those skilled in the art will understand that Fig. 9 The structural block diagram is merely an example of a computer device and does not constitute a limitation of the computer device, and may include more or less components than shown in the figure, or combine certain components, or different components.

[0167] In summary, the embodiments of the present invention provide a method, device, equipment and storage medium for collaborative planning of multiple energy sources in a park under an isolated operation mode, which coordinates and plans the multi-energy park under the isolated operation mode according to the park network information. When a failure occurs in the external power grid, the energy supply strategy can be adjusted according to actual needs to ensure the energy supply of local users, achieve collaboration and complementarity between multiple energy sources, and improve the flexibility and efficiency of energy use. Dividing the levels of power outages based on the scenario tree and planning different energy coordination schemes in a targeted manner can help to reasonably plan and allocate energy within the park according to the priority of the failure, optimize the allocation of resources, and improve the stability of the energy system operation within the park.

[0168] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A method for collaborative planning of multi-energy sources in a park under isolated island operation mode, characterized in that: include: Obtaining energy network data of the current target multi-energy park, wherein the energy network data at least includes typical load curve data of the park, light intensity data, and island scene data; According to the reasons for the power outages that caused the island mode of the multi-energy park, a scenario tree containing several island modes is generated; According to the first objective function, the second objective function, the energy network data and the scenario tree, a multi-energy collaborative planning model of the park considering the isolated island operation mode is constructed; wherein the first objective function reflects the minimization of the total planning cost of the park, and the second objective function reflects the minimum energy loss expectation of the park under the isolated island mode; When the multi-energy collaborative planning model is running, the energy plans within the target multi-energy park are controlled in real time based on the planning results output by the multi-energy collaborative planning model; wherein the planning results include control collaborative planning reflecting the grid-connected mode and control collaborative planning reflecting the island mode.

2. The method for collaborative planning of multiple energy sources in a park under isolated island operation mode as claimed in claim 1 is characterized in that: According to the power outage cause of the multi-energy park island mode, a scenario tree containing several island modes is generated, including: According to the power outage causes of the multi-energy park island mode, a scenario tree including the first island mode, the second island mode and the third island mode is generated; among them, the first island mode is caused by a small-scale fault, the second island mode is caused by an unconventional or large-scale fault, and the third island mode is caused by a pre-arranged power outage.

3. The method for collaborative planning of multiple energy sources in a park under isolated island operation mode as claimed in claim 2 is characterized in that: The generating of a scenario tree including a first island mode, a second island mode and a third island mode according to the power outage cause of the multi-energy park island mode includes: According to the power outage cause of the multi-energy park island mode, a scenario tree including the first island mode, the second island mode and the third island mode is generated, and the probability density function of each island mode is: ξ=(I,T dur ,D occ ,T start ) Among them, I is the island type, Tdur is the duration, Docc is the occurrence date, and Tstart is the start time. is the joint probability density function of I, Tdur, Docc and Tstart, i, tdur, docc and tstart are the values ​​of I, Tdur, Docc and Tstart respectively, f I (i) is the probability density function of I, is the conditional probability density function of Tdur, is the conditional probability density function of DOC, is the conditional probability density function of Tstart.

4. The method for collaborative planning of multiple energy sources in a park under isolated island operation mode as claimed in claim 1 is characterized in that: The first objective function reflects minimizing the total planning cost of the park; The second objective function reflects the minimum energy loss expectation of the park in the island mode, including energy supply shortage penalty and energy abandonment penalty.

5. The method for collaborative planning of multiple energy sources in a park under isolated island operation mode as claimed in claim 4 is characterized in that: The first objective function is expressed as: obj1:min C total =C Inv +C Ope +C Mai +C CO2 Among them, C total is the total planning cost of the park, C Inv is the annual value of equipment investment cost, C Ope is the annual operating cost in the grid-connected mode, C Mai is the annual maintenance cost in the grid-connected mode, C CO2 is the annual carbon tax cost in the grid-connected mode; The second objective function is expressed as: Among them, C loss is the expected loss in the island mode, g s (u s ) is the loss in scene s, and p(s) is the probability of scene s occurring.

6. The method for collaborative planning of multiple energy sources in a park under isolated island operation mode as claimed in claim 1, characterized in that: When the multi-energy collaborative planning model is running, based on the planning results output by the multi-energy collaborative planning model, each energy plan in the target multi-energy park is controlled in real time, including: Running the multi-energy collaborative planning model, and based on the planning results output by the multi-energy collaborative planning model, controlling the energy planning in the target multi-energy park in the grid-connected mode and the energy planning in the island mode in real time; Among them, the control collaborative planning in the grid-connected mode meets the upper-level grid exchange power constraints, equipment operation constraints and power balance constraints; The control collaborative planning in the island mode adopts the energy abandonment strategy to maintain the balance between supply and demand, while bearing the corresponding energy abandonment penalty.

7. The method for collaborative planning of multiple energy sources in a park under isolated island operation mode as claimed in claim 6 is characterized in that: The energy abandonment strategies include: Initialize the operation status of the isolated island park; It uses CHP and PV for electricity, and CHP, GB and HP for heating; If CHP and PV can meet the power load demand, the excess power will be stored in ES; when ES reaches the energy storage limit, power will be abandoned; If CHP, GB and HP can meet the heat load demand, the excess heat energy will be stored in HS; when HS reaches the upper limit of energy storage, heat abandonment will be generated; If CHP and PV cannot meet the load demand, ES will be called for discharge; if the ES storage capacity is insufficient, NEL will be cut off. If the load demand still cannot be met after NEL is cut off, PEL will be cut off; If CHP, GB and HP cannot meet the heat demand, HS will be called to release heat; if the HS heat storage capacity is insufficient, NHL will be removed; if the heat load demand still cannot be met after NHL is removed, PHL will be removed.

8. A multi-energy collaborative planning device for a park under an isolated island operation mode, characterized in that: include: A data acquisition module is used to obtain energy network data of the current target multi-energy park, wherein the energy network data at least includes typical load curve data of the park, light intensity data, and island scene data; A scenario generation module, used to generate a scenario tree including several island modes according to the power outage causes that cause the island mode of the multi-energy park; A model building module, used to build a multi-energy collaborative planning model for a park in an isolated island operation mode according to a first objective function, a second objective function, energy network data and a scenario tree; wherein the first objective function reflects minimizing the total planning cost of the park, and the second objective function reflects the minimum energy loss expectation of the park in the isolated island mode; A collaborative planning module is used to control the energy planning of the target multi-energy park in real time based on the planning results output by the multi-energy collaborative planning model when the multi-energy collaborative planning model is running; wherein the planning results include control collaborative planning reflecting the grid-connected mode and control collaborative planning reflecting the island mode.

9. A computer device, characterized in that: It includes a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor. When the processor executes the computer program, it implements the multi-energy collaborative planning method for a campus considering the island operation mode as described in any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, wherein when the device where the computer-readable storage medium is located executes the computer program, the method for collaborative planning of multiple energy sources in a campus considering an isolated island operation mode as described in any one of claims 1 to 7 is implemented.

Citation Information

Patent Citations

  • Comprehensive energy microgrid optimization control method considering random power failure energy supply reliability

    CN114529070A

  • Distribution network planning method and device, storage medium and computer equipment

    CN116993032A

Cited By

  • Park plan energy consumption management method and equipment based on multiple organizations, and medium

    CN121478821A