Hot-rolled strip steel endless continuous casting and rolling production resource allocation method, equipment and medium

Optimizing the headless continuous casting and rolling production of hot-rolled strip steel through greedy algorithms and orderly multi-backpacking problem model, solving the problems of delay in order delivery and low resource utilization, achieving the maximum utilization of production resources and cost reduction, and improving Productivity.

CN118886648AActive Publication Date: 2024-11-01WISDRI ENG & RES INC LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410906072.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2024-11-01
Estimated Expiration
2044-07-08

AI Technical Summary

Technical Problem

The prior art has problems such as delay in order delivery, low resource utilization, and difficulty in further improving production efficiency and costs in hot-rolled strip steel headless continuous casting and continuous rolling production, and the prior art cannot maximize the utilization of production resources.

Method used

Using greedy algorithm and orderly multi-backpack problem model, we can determine the production priority and rolling order of steel grades by prioritizing the determination of steel grades with short lead time and large total rolling volume, and reasonably allocate the pouring times and production weight to achieve steel Optimize resource combination between species and thickness specifications.

Benefits of technology

The production resources of hot-rolled strip steel headless continuous casting and continuous rolling are maximized, which reduces the randomness and volatility brought about by manual scheduling, improves production efficiency and reduces production costs, and ensures that orders are within the lead time. Finish.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118886648A_ABST
    Figure CN118886648A_ABST
Patent Text Reader

Abstract

According to a theoretical method of an ordered multi-knapsack problem, a greedy algorithm, namely a loop statement, is adopted, the problems of intelligent production scheduling of endless continuous casting and rolling of the hot-rolled strip steel and combination optimization of different steel types and different thicknesses and widths in the production scheduling process are solved, and on the premise that machining constraint conditions are met, through reasonable rolling planning, the production efficiency is improved. According to the method, all aspects of requirements in a production task are met, a global optimal solution can be quickly found, and the penalty value is minimum (namely, a production sequence when the penalty value is minimum). The method is applied to the rolling production process of endless continuous casting and rolling of the hot-rolled strip steel, maximum utilization of endless continuous casting and rolling production resources of the hot-rolled strip steel (the ratio of the total income to the total cost reaches the maximum) can be achieved, it is guaranteed that production of orders is completed within the delivery time, the problems of randomness and volatility caused by manual scheduling are reduced, and the production efficiency is improved. The production efficiency is improved; and the production cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of headless continuous casting and rolling, and more specifically, to a method, equipment and medium for allocating production resources for headless continuous casting and rolling of hot-rolled strip steel. Background Art

[0002] Compared with hot rolling, headless continuous casting and rolling of hot-rolled strip has the advantages of less time consumption, high yield rate and low process energy consumption, and can stably mass-produce ultra-thin plates and strips. The rolled steel varieties and application range are wide, and the rolled products have the characteristics of high dimensional accuracy and good uniformity of organizational performance. For enterprises, it can reduce costs and improve production efficiency. However, due to the lack of scientific and reasonable overall production planning, many enterprises have not fully released the potential of headless continuous casting and rolling technology for hot-rolled strip. In the rolling production process, enterprises may have a large number of orders, and the manual scheduling in the existing technology may lead to problems such as delayed order delivery and reduced resource utilization. When encountering urgent orders, they cannot make adjustments quickly, which in turn affects subsequent orders.

[0003] In addition, although there are some domestic studies on production scheduling issues, most of them have not been truly applied to the actual production in the field of headless continuous casting and rolling technology of hot-rolled strip, and the existing relevant technical means cannot maximize the utilization of production resources and cannot reduce the randomness and volatility problems caused by manual scheduling, making it difficult to further improve production efficiency and reduce production costs. Summary of the invention

[0004] In response to at least one defect or improvement need in the prior art, the present application provides a method, equipment and medium for allocating production resources for headless continuous casting and rolling of hot rolled strip, which are used to at least maximize the utilization of production resources for headless continuous casting and rolling of hot rolled strip.

[0005] To achieve the above objectives, in a first aspect, the present application provides a method for allocating production resources for headless continuous casting and rolling of hot-rolled strip steel, comprising:

[0006] According to the secondary judgment of giving priority to the steel with short delivery time and the steel with large total rolling volume, the priority judgment results of different steel grades under different production tasks are obtained through the greedy algorithm;

[0007] Based on the ordered multi-knapsack problem model and following the thick-thin-thick rolling schedule, the minimum thickness jump penalty value is obtained through a greedy algorithm to obtain the rolling order between different specifications of the same steel grade in the same production task.

[0008] Under the first constraint condition that the total number of pouring times required for production is not greater than the number of pouring times that can be performed within the maximum delivery period and the total number of pouring times for each steel grade per day is not greater than the number of pouring times that can be performed per day, the number of pouring times for continuous casting of different steel grades per day for each production task is obtained;

[0009] According to the number of daily continuous castings of different steel grades in each production task, the production weight of each thickness is allocated according to the proportion of the total production volume of different thicknesses, and the production scheduling results of the corresponding steel grades in each production task are obtained respectively;

[0010] Based on one or more of the priority judgment results of the production of different steel grades under the different production tasks, the rolling order between different specifications of the same steel grade in the corresponding same production task, the number of daily continuous casting pours of different steel grades in each production task and the production scheduling results of the corresponding steel grades in each production task, the allocation of production resources for headless continuous casting and rolling of hot rolled strip is carried out.

[0011] Furthermore, the formula characterizing the ordered multi-knapsack problem model includes:

[0012]

[0013] Among them, P i =P wi +P gi +P hi ; The width jump penalty value between slab i and slab (i+1) of each steel grade is P wi , the thickness jump penalty value is P gi , the hardness jump penalty value is P hi ; The penalty value between slab i and slab (i+1) is P i ; The total penalty value is P; n is the number of thickness specifications for each type of steel;

[0014] The second constraint condition corresponding to the ordered multi-knapsack problem model includes:

[0015]

[0016] Among them, L i is the rolling weight of slab i in one day; W is the total rolling amount; L sum It is the total amount that the production line can roll in one day.

[0017] Furthermore, the secondary determination based on the priority given to the steel type with short delivery period and the priority given to the steel type with large total amount of rolling required includes:

[0018] Make the first judgment based on the delivery time of different steel grades for each production task, and give priority to the one with the shortest delivery time;

[0019] If the delivery dates are the same, a second determination will be made based on the total amount of different steel grades that need to be rolled for each production task, and the steel grades that require a larger total amount of rolling will be produced first.

[0020] Furthermore, the method based on the ordered multi-knapsack problem model and following the thick-thin-thick rolling schedule, obtaining the minimum thickness jump penalty value through a greedy algorithm to obtain the rolling order between different specifications of the same steel grade in the same production task includes:

[0021] The smallest value of the thickness specification under the same steel grade is selected as the minimum point, and the values ​​on both sides of this point are selected from the remaining thickness specifications to complete a thickness specification sorting, and this point is the only minimum point in the sorting;

[0022] After completing the sorting of the thickness specifications once, the thickness jump penalty value is obtained; the model formula of the thickness jump penalty value includes:

[0023] ΔH i =|H i -H i+1 |;

[0024]

[0025] Constraints: α+β=1,α·β≥0;

[0026] Among them, H i is the rolling target thickness of slab i; ΔH i is the target thickness absolute jump of slab I; H′ i is the relative jump amount of the target thickness of slab I; α and β are the thickness jump penalty coefficients; P g is the thickness jump penalty value;

[0027] A greedy algorithm is used to loop the above thickness specification sorting method. Each sorting is different. The final thickness jump penalty values ​​of all sortings are combined to retain the thickness specification sorting with the smallest thickness jump penalty value.

[0028] Further, under the first constraint that the total number of pouring times required for production is not greater than the number of pouring times that can be performed within the maximum delivery period and the total number of pouring times for each steel grade per day is not greater than the number of pouring times that can be performed per day, obtaining the number of pouring times for continuous casting of different steel grades for each production task per day includes:

[0029] After obtaining all possible daily pouring orders for each steel grade within the maximum delivery period, the pouring order orders of different steel grades are combined through a loop statement to find the optimal solution that meets the first constraint condition, thereby obtaining the daily continuous casting pouring times of different steel grades for each production task;

[0030] The first constraint condition includes:

[0031]

[0032] Where D is the maximum delivery time in the production task; k is the number of pouring times that the production line can perform per day; r is the number of steel types; N i is the number of required castings obtained according to the total amount of rolling required for each type of steel in each production task; m is the number of types of steel rolled in one day; p is the number of castings of each type of steel rolled in one day; N xy It is the daily casting times of different steel grades for each production task within the delivery period.

[0033] Furthermore, according to the number of daily continuous castings of different steel grades for each production task, the production weight of each thickness is allocated according to the proportion of the total production volume of different thicknesses, and the production scheduling results of the corresponding steel grades in each production task are obtained respectively, including:

[0034] According to the number of pours of continuous casting of different steel grades per day and the unit pouring weight of each production task, the total daily production volume of each steel grade is obtained;

[0035] After determining the total daily production volume, the daily production weight q of different thickness specifications is allocated according to the ratio of the total production volume of different thickness specifications of the same steel grade in the production task to the total production volume of the steel grade required in the production task. The specific formula includes:

[0036]

[0037] Among them, E i It indicates the total required production volume of the i-th thickness specification of a certain steel grade in the production task; It indicates the total amount of steel required to be produced in the production task; Q indicates the total daily production amount of each steel type; q indicates the daily production weight of different thickness specifications.

[0038] In a second aspect, the present application provides an electronic device comprising at least one processing unit and at least one storage unit, wherein the storage unit stores a computer program, and when the computer program is executed by the processing unit, the processing unit is enabled to perform the steps of any of the above-mentioned production resource allocation methods.

[0039] In a third aspect, the present application provides a storage medium storing a computer program executable by an access authentication device, wherein when the computer program runs on the access authentication device, the access authentication device is enabled to perform the steps of any of the above-mentioned production resource allocation methods.

[0040] In general, the above technical solutions conceived by the present application can achieve the following beneficial effects compared with the prior art:

[0041] This application uses a greedy algorithm, i.e., a loop statement, based on the theoretical method of the ordered multi-knapsack problem, to solve the intelligent scheduling of hot-rolled strip headless continuous casting and rolling and the combinatorial optimization problem between different steel grades and different thicknesses and widths in the production scheduling process. Under the premise of satisfying the processing constraints, through reasonable rolling planning, it completes all aspects of the production task. It can quickly find the global optimal solution to minimize the penalty value (i.e., find the production order that minimizes the penalty value). This application is applied to the rolling production process of hot-rolled strip headless continuous casting and rolling, which can maximize the utilization of production resources for hot-rolled strip headless continuous casting and rolling (the ratio of total revenue to total cost is maximized), ensure that the order is completed within the delivery period, reduce the randomness and volatility problems caused by manual scheduling, improve production efficiency and reduce production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0043] Figure 1 A core flow chart of a method for allocating production resources for headless continuous casting and rolling of hot-rolled strip provided in an embodiment of the present application;

[0044] Figure 2 A complete flow chart of a method for allocating production resources for headless continuous casting and rolling of hot-rolled strip provided in an embodiment of the present application;

[0045] Figure 3 A block diagram of an electronic device provided in an embodiment of the present application and suitable for implementing the production resource allocation method described above. DETAILED DESCRIPTION

[0046] In order to make the purpose, technical solutions and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not intended to limit the present application. In addition, the technical features involved in each embodiment of the present application described below can be combined with each other as long as they do not conflict with each other.

[0047] The terms "first", "second" or "nth" in the specification, claims or the above-mentioned drawings of this application are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" or "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units inherent to these processes, methods, products or devices.

[0048] During the rolling production process, the company may have a large number of orders, and the manual production scheduling in the existing technology may cause problems such as delayed order delivery and reduced resource utilization. When encountering urgent orders, it is impossible to make adjustments quickly, which in turn affects subsequent orders. In addition, although there are some domestic studies on production scheduling issues, most of them have not been truly applied to the actual production in the field of headless continuous casting and rolling technology for hot-rolled strip, and the existing relevant technical means cannot maximize the utilization of production resources and cannot reduce the randomness and volatility problems caused by manual scheduling, making it difficult to further improve production efficiency and further reduce production costs. In view of this technical status, the present application provides a method, equipment and medium for allocating production resources for headless continuous casting and rolling of hot-rolled strip, which are used to at least maximize the utilization of production resources for headless continuous casting and rolling of hot-rolled strip.

[0049] refer to Figure 1 and Figure 2 An embodiment of the present application provides a method for allocating production resources for headless continuous casting and rolling of hot-rolled strip steel. The method for allocating production resources may include the following steps 1 to 5.

[0050] In some embodiments, some preparation work is required before allocating production resources for hot-rolled strip endless casting and rolling. The following is an example of using the production information of two types of steel "Q215B" and "SPHC" in Contract 1 and one type of steel "SPHC" in Contract 2 for production scheduling (production resource allocation) of hot-rolled strip endless casting and rolling.

[0051] First, different contracts (in this application, contracts, orders and production tasks are regarded as the same thing. The birth of a contract or order for steel production means the start of a steel production task. The same contract may include multiple orders, and each order is distinguished by a contract number) and the production requirements of different types of steel in the contract are summarized into a table to unify the known necessary conditions in the production process and the assumed conditions of the production environment.

[0052] More specifically, the known conditions in Contract 1 and Contract 2 are summarized into a table according to "Contract Number", "Steel Type", production specifications of different steel types such as "Thickness", "Width", and production information such as "Steel Coil Weight", "Delivery Date", and "Total Quantity" under different specifications of each steel type. It is important to distinguish between different types of steel types in the same contract and the same type of steel types in different contracts. The division method is shown in Table 1.

[0053] Table 1 Summary of production information in the contract of this embodiment

[0054]

[0055]

[0056] Assume that there is one hot-rolled strip production line in the production conditions, including two parts of equipment: a continuous casting unit and a rolling unit. The total weight of steel that can be produced every day is 4800 to 6000 tons, and the weight of one continuous casting is 1200 tons.

[0057] Determine the modeling idea. The main problem of production scheduling is the combination optimization problem between different contracts and different steel grades, different thicknesses and widths. The model used is mainly the ordered multi-knapsack problem model. Under the condition of meeting the processing constraints, through reasonable rolling planning, all requirements in the contract are met and the penalty value is minimized. More specifically:

[0058] During the production scheduling process, within the same unit rolling plan, the width, thickness and hardness jumps between two adjacent slabs are subject to certain range restrictions. Once the range is exceeded, it is considered an infeasible solution. In this example, the penalty values ​​of two types of steel "Q215B" and "SPHC" in Contract 1 and one type of steel "SPHC" in Contract 2 need to be calculated respectively. The width jump penalty value between slab i and slab i+1 of each steel type is defined as P wi , the thickness jump penalty value is defined as P gi , the hardness jump penalty value is set to P hi , then P i =P wi +P gi +P hi is the penalty value generated between slab i and slab i+1. According to the ordered multi-knapsack problem model theory, the penalty value generated under various constraints in the rolling unit plan is used as the item cost (i.e., production cost, or total overhead). The total penalty value P should be minimized when modeling:

[0059]

[0060] The total amount of hot-rolled strip steel production line that can be rolled in one day L sum=4800~6000t as the backpack capacity. Since the jump value between the same thickness and width is 0, n in formula (1) is the thickness specification number of each type of steel, and slab i is the thickness specification of each type. The thickness specification number of steel type "Q215B" in Contract 1 is n=8, the thickness specification number of "SPHC" is n=10, and the thickness specification number of steel type "SPHC" in Contract 2 is n=6. L i It is stipulated that the rolling weight of slab i in one day, then the modeling should satisfy the requirement that the total rolling amount W is maximum and does not exceed the knapsack capacity. The corresponding constraints of the ordered multi-knapsack problem model include equations (2) and (3).

[0061]

[0062] In order to minimize the penalty value (i.e., minimize the production cost or minimize the total overhead) during the combinatorial optimization process, and to ensure that the production scheduling is not affected by too many parameters, this embodiment uses a greedy algorithm and a loop statement to continuously narrow the scope of the problem, and ultimately obtains the optimal solution to the ordered multi-knapsack problem model.

[0063] The overall idea of ​​this application is to determine that the model used in the production scheduling problem is an ordered multi-knapsack problem model, select a greedy algorithm as the optimization algorithm, use a loop statement, continuously narrow the scope of the problem, and finally obtain the optimal solution of the ordered multi-knapsack problem model, that is, to obtain the production order that minimizes the penalty value.

[0064] Step 1: Based on the secondary judgment of giving priority to the steel with short delivery time and giving priority to the steel with large total rolling volume, the priority judgment results of different steel types under different production tasks are obtained through the greedy algorithm.

[0065] In some embodiments, known conditions and assumed conditions are used to determine the production priority of different steel grades under different contracts in the summarized table, as described in more detail below.

[0066] Enter the production information table summarized in the above preparation work, and make the first judgment based on the delivery period of different steel types in each contract. If the delivery period is short, production will be given priority. If the delivery period is the same, make a second judgment based on the total amount of steel types that need to be rolled in each contract, and the steel type with a larger total amount of rolling will be given priority. After summarizing, it can be seen that the delivery period of steel type "Q215B" with contract number '101' and steel type "SPHC" with contract number '201' are both 3 days, and the total amount of rolling required for steel type "Q215B" is greater than the total amount of rolling required for steel type "SPHC". The delivery period of steel type "SPHC" with contract number '102' is 5 days, which is longer than the delivery period of the first two types of steel types. Therefore, the final rolling priority order is steel type "Q215B" with contract number '101', steel type "SPHC" with contract number '201', and steel type "Q215B" with contract number '102'.

[0067] Steel grade "SPHC" with contract number '201' and steel grade "SPHC" with contract number '102'.

[0068] Step 2: Based on the ordered multi-knapsack problem model and following the thick-thin-thick rolling schedule, the minimum thickness jump penalty value is obtained by a greedy algorithm to obtain the rolling order between different specifications of the same steel grade in the same production task. In some embodiments, step 2 may specifically include:

[0069] Step 21: Since the jump value between the same thickness and width is 0, the width of steel of different specifications in the production information remains unchanged, so the width jump is not considered at this time, and the thickness jump is given priority. Slab i is each type of thickness specification.

[0070] Step 22: For the production rolling of the same steel type, in terms of rolling thickness variation, the thick-thin-thick rolling procedure requirements are followed. Therefore, the minimum value of the thickness specification under the steel type is selected as the minimum point. The minimum thicknesses of the steel type "Q215B" with contract number '101', the steel type "SPHC" with contract number '201', and the steel type "SPHC" with contract number '102' are 1.15cm, 1.3cm, and 1.05cm, respectively. Referring to Table 1, the values ​​on both sides of the minimum point are selected from the remaining thickness specifications to complete a thickness specification sorting, and the minimum point must be the only minimum point in the sorting. After completing a sorting, the penalty value is calculated according to the model formula of the thickness jump penalty value (including equations (4) to (7)):

[0071] ΔH i =|H i -H i+1 | (4)

[0072]

[0073] Corresponding constraints: α+β=1,α·β≥0 (7)

[0074] Among them, H i is the rolling target thickness of slab i; ΔH i is the absolute jump amount of target thickness of slab i; H′ i is the relative jump amount of the target thickness of slab i; n is the number of thickness specifications of each type of steel; α and β are thickness jump penalty coefficients, which can both be taken as 0.5.

[0075] Step 23: Adopt the greedy algorithm, loop the thickness specification sorting method in step 22, each sorting is different, and the thickness jump penalty value of all sortings is combined to retain the thickness specification sorting with the smallest thickness jump penalty value. The production thickness sorting corresponding to the minimum thickness jump penalty value of the steel grade "Q215B" with contract number '101' is: [2.0, 1.8, 1.6, 1.5, 1.15, 1.2, 1.3, 1.4]; the production thickness sorting corresponding to the minimum thickness jump penalty value of the steel grade "SPHC" with contract number '201' is: [4.0, 3.5, 3.0, 1.3, 1.4, 2.75]; the production thickness sorting corresponding to the minimum thickness jump penalty value of the steel grade "SPHC" with contract number '102' is: [4.0, 3.5, 3.0, 2.75, 1.4, 1.05, 1.1, 1.15, 1.2, 1.3].

[0076] Step 3: Under the constraint that the total number of pours required for production is not greater than the number of pours that can be performed within the maximum delivery period and the total number of pours for each steel grade per day is not greater than the number of pours that can be performed per day, obtain the number of pours for continuous casting of different steel grades per day for each production task. In some embodiments, step 3 may specifically include:

[0077] Step 31: Assuming that the total daily production capacity of the hot strip endless casting and rolling production line is 6000t and the weight of one casting of the equipment is 1200t, the number of castings that can be performed per day can be calculated. (symbol indicates rounding up); according to the total rolling amount M required for each type of steel in each contract i Calculate the number of pours required The number of pouring times for steel type "Q215B" with contract number '101', steel type "SPHC" with contract number '201' and steel type "SPHC" with contract number '102' are 5, 2 and 6 respectively.

[0078] Step 32: In order to ensure that the production of each contract steel grade can be completed within the delivery period, the number of pouring times N of each contract steel grade per day within the delivery period is allocated according to the following constraints: xy The constraints are:

[0079]

[0080] Where D is the maximum delivery period in the contract, r is the number of steel types, m is the number of steel types rolled in one day, and p is the number of pouring times of each steel type rolled in one day. Constraint (8) ensures that the total number of pouring times required for production is not greater than the number of pouring times that can be performed within the maximum delivery period; constraint (9) ensures that the total number of pouring times of each steel type per day is not greater than the number of pouring times that can be performed per day.

[0081] In some embodiments, step 32 may further include the following sub-steps:

[0082] Step 321: For a certain steel grade I, if its delivery period d is greater than or equal to the number of castings N calculated in step 31 i , then write N i A sequence of 1s [1,1,…,1,1], indicating that this type of steel has N i The number of pouring times per day is one pouring per day. For the rest of the delivery period of this steel grade (dN i ) The number of watering times per day is represented by 0, and the final sequence is [1,1,…,1,0,…,0,0], where element 1 has N i , element 0 has (dN i ), the elements in this sequence can be arranged in different ways to represent the possible order of daily pouring times of steel type I within its delivery period d. For steel type "SPHC" with contract number '201', the delivery period of 3 days is greater than its pouring times 2, so the final sequence is [1,1,0], and the random ordering of the elements in this sequence is the possible order of daily pouring times of this steel type within 3 days.

[0083] Step 322: For a certain steel grade I, if its delivery period d is less than the number of castings N calculated in step 31 i , then N i decomposed into d sets of positive integers [s1,s2,…,s d ], the elements in this sequence can be arranged in different ways to represent the possible order of daily pouring times of steel type I within its delivery period d. The steel type "SPHC" with contract number '102' has a delivery period of 5 days, which is less than the number of pouring times 6, so the final sequence is [2, 1, 1, 1, 1]. The random ordering of the elements in this sequence is the possible order of daily pouring times of this steel type within 5 days; similarly, the sequence obtained for the steel type "Q215B" with contract number '101' is [2, 2, 1]. The random ordering of the elements in this sequence is the possible order of daily pouring times of this steel type within 3 days of delivery.

[0084] Step 323: After obtaining the possible ordering of daily castings for each type of steel in the contract under the two cases through steps 321 and 322, if the delivery period d of the steel type is less than the maximum delivery period D in the contract, (Dd) 0 elements are added after the sorted sequence to represent all possible daily casting orders for each type of steel within the maximum delivery period. Since a steel type can only be produced within its own delivery period, the position of the 0 element added after the sequence is fixed in the sequence, and the 0 element indicates that the steel type is not produced. In this embodiment, the maximum delivery period among all the steel types is D=5. For the steel type "SPHC" with a contract number of '201' and a delivery period of 3 days, 5-3=2 0 elements are added to the sequence of all possible sortings obtained in step 321. For example, one of the possibilities [1,0,1] is added with 2 0 elements to obtain [1,0,1,0,0], which is the possible daily pouring order within the maximum delivery period of 5 days. The positions of the last two 0 elements in the sequence are fixed; similarly, for the steel type "SPHC" with a contract number of '201' ...

[0085] The steel type "SPHC" with a contract number of '102' and the steel type "Q215B" with a contract number of '101' are respectively added with 5-5=0 zero elements and 5-3=2 zero elements after all possible sequence numbers obtained in step 322.

[0086] Step 324: After obtaining all possible daily pouring orders for each steel grade within the maximum delivery period, the pouring order orders of different steel grades are combined through loop statements to find the optimal solution that meets the constraint conditions (8) and (9) in step 32, thereby obtaining the daily pouring order of each type of steel grade. Finally, the optimal pouring order combination of the three types of steel grades in the contract is obtained, as shown in Table 2.

[0087] Table 2 Optimal pouring combinations of three types of steel in the contract

[0088] Day 1 the next day Day 3 Day 4 Day 5 101-Q215B 2 pouring times 1 pouring 2 pouring times 0 pouring times 0 pouring times 201-SPHC 1 pouring 0 pouring times 1 pouring 0 pouring times 0 pouring times 102-SPHC 1 pouring 1 pouring 1 pouring 1 pouring 2 pouring times

[0089] The three types of steel can be produced within their respective delivery periods, with a total casting frequency of 5+2+6=13 times <5*5=25 times, and the sum of the casting frequencies of the three types of steel per day is less than 5.

[0090] Step 4: according to the number of continuous castings of different steel grades per day for each production task, the production weight of each thickness is allocated according to the proportion of the total production volume of different thicknesses, and the production scheduling results of the corresponding steel grades in each production task are obtained respectively. In some embodiments, step 4 may also specifically include:

[0091] The total daily production volume Q of each steel grade is determined based on the daily distribution of pours during the delivery period of each contract and the unit pouring weight.

[0092] After determining the total daily production volume Q, allocate the daily production weight q of different thicknesses according to the ratio of the total production volume of the same steel grade with different thicknesses in the order to the total production volume of the steel grade required in the contract.

[0093]

[0094] Where E i It indicates the total required production volume of the i-th thickness specification of a certain steel grade in the production information summary table in the contract; Indicates the total amount of steel required to be produced in the contract. The production scheduling results of the three types of steel in the contract within the maximum delivery period are shown in Table 3.

[0095] Table 3 Production scheduling results of three types of steel in the contract within the maximum delivery period

[0096]

[0097]

[0098] Step 5: Allocate production resources for headless continuous casting and rolling of hot-rolled strip based on one or more of the priority determination results for production of different steel grades under different production tasks obtained in step 1, the rolling order between different specifications of the same steel grade in the corresponding same production task obtained in step 2, the daily continuous casting times of different steel grades in each production task obtained in step 3, and the production scheduling results of corresponding steel grades in each production task obtained in step 4.

[0099] After completing the allocation and scheduling of production resources, the production scheduling table and rolling sequence diagram can be output to simulate production.

[0100] This application uses a greedy algorithm, i.e., a loop statement, based on the theoretical method of the ordered multi-knapsack problem, to solve the intelligent scheduling of hot-rolled strip headless continuous casting and rolling and the combinatorial optimization problem between different steel grades and different thicknesses and widths in the production scheduling process. Under the premise of satisfying the processing constraints, through reasonable rolling planning, it completes all aspects of the production task. It can quickly find the global optimal solution to minimize the penalty value (i.e., find the production order that minimizes the penalty value). This application is applied to the rolling production process of hot-rolled strip headless continuous casting and rolling, which can maximize the utilization of production resources for hot-rolled strip headless continuous casting and rolling (the ratio of total revenue to total cost is maximized), ensure that the order is completed within the delivery period, reduce the randomness and volatility problems caused by manual scheduling, improve production efficiency and reduce production costs.

[0101] Figure 3 A block diagram of an electronic device suitable for implementing the production resource allocation method described above according to an embodiment of the present application is schematically shown. Figure 3The electronic device shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0102] like Figure 3 As shown, the electronic device 1000 described in this embodiment includes: a processor 1001, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 1002 or a program loaded from a storage part 1008 into a random access memory (RAM) 1003. The processor 1001 may include, for example, a general-purpose microprocessor (e.g., a CPU), an instruction set processor and / or a related chipset and / or a special-purpose microprocessor (e.g., an application-specific integrated circuit (ASIC)), and the like. The processor 1001 may also include an onboard memory for caching purposes. The processor 1001 may include a single processing unit or multiple processing units for performing different actions of the production resource allocation method flow according to an embodiment of the present application.

[0103] In RAM 1003, various programs and data required for the operation of system 1000 are stored. Processor 1001, ROM 1002 and RAM 1003 are connected to each other via bus 1004. Processor 1001 performs various operations of the production resource allocation method flow according to the embodiment of the present application by executing the program in ROM 1002 and / or RAM 1003. It should be noted that the program can also be stored in one or more memories other than ROM 1002 and RAM 1003. Processor 1001 can also perform various operations of the production resource allocation method flow according to the embodiment of the present application by executing the program stored in the one or more memories.

[0104] According to an embodiment of the present application, the electronic device 1000 may further include an input / output (I / O) interface 1005, which is also connected to the bus 1004. The system 1000 may further include one or more of the following components connected to the I / O interface 1005: an input part 1006 including a keyboard, a mouse, etc.; an output part 1007 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage part 1008 including a hard disk, etc.; and a communication part 1009 including a network interface card such as a LAN card, a modem, etc. The communication part 1009 performs communication processing via a network such as the Internet. A drive 1010 is also connected to the I / O interface 1005 as needed. A removable medium 1011, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 1010 as needed, so that the computer program read therefrom is installed into the storage part 1008 as needed.

[0105] The production resource allocation method flow according to the embodiment of the present application can be implemented as a computer software program. For example, the embodiment of the present application includes a computer program product, which includes a computer program carried on a computer-readable storage medium, and the computer program includes a program code for executing the production resource allocation method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from the network through the communication part 1009, and / or installed from the removable medium 1011. When the computer program is executed by the processor 1001, the above-mentioned functions defined in the system of the embodiment of the present application are executed. According to the embodiment of the present application, the system, equipment, device, module and / or unit described above, etc. can be implemented by a computer program module.

[0106] The embodiments of the present application also provide a computer-readable storage medium, which may be included in the device / apparatus / system described in the above embodiments, or may exist independently without being assembled into the device / apparatus / system. The above computer-readable storage medium carries one or more programs, and when the above one or more programs are executed, the steps of the production resource allocation method according to the embodiments of the present application can be implemented.

[0107] According to an embodiment of the present application, the computer-readable storage medium may be a non-volatile computer-readable storage medium, for example, may include but is not limited to: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In an embodiment of the present application, the computer-readable storage medium may be any tangible medium containing or storing a program, which may be used by or in combination with an instruction execution system, an apparatus, or a device. For example, according to an embodiment of the present application, the computer-readable storage medium may include one or more memories other than the ROM 1002 and / or RAM 1003 described above.

[0108] It should be noted that the functional modules in the various embodiments of the present application can be integrated into a processing module, or each module can exist physically separately, or two or more modules can be integrated into one module. The above-mentioned integrated modules can be implemented in the form of hardware or in the form of software functional modules. If the integrated modules are implemented in the form of software functional modules and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on such an understanding, the technical solution of the present application is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product.

[0109] The flowchart and / or block diagram in the accompanying drawings illustrate the possible architecture, functions and operations of the system, method and computer program product according to various embodiments of the present application. In this regard, each box in the flowchart and / or block diagram can represent a part of a module, program segment or code, and a part of the above-mentioned module, program segment or code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in an order different from that marked in the accompanying drawings. It should also be noted that each box in the block diagram or flowchart, and the combination of the boxes in the block diagram or flowchart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0110] Those skilled in the art will appreciate that the features described in the various embodiments and / or claims of the present application may be combined and / or combined in a variety of ways, even if such combinations and / or combinations are not explicitly described in the present application. In particular, without departing from the spirit and teachings of the present application, the technical features described in the various embodiments and / or claims of the present application may be combined and / or combined in a variety of ways, and all of these combinations and / or combinations fall within the scope of the present application.

[0111] Although the present application has been shown and described with reference to specific exemplary embodiments of the present application, it should be understood by those skilled in the art that various changes in form and details may be made to the present application without departing from the spirit and scope of the present application as defined by the appended claims and their equivalents. Therefore, the scope of the present application should not be limited to the above-mentioned embodiments, but should be determined not only by the appended claims, but also by the equivalents of the appended claims.

Claims

1. A method for allocating production resources for hot-rolled strip endless continuous casting and rolling, characterized in that: include: According to the secondary judgment of giving priority to the steel with short delivery time and the steel with large total rolling volume, the priority judgment results of different steel grades under different production tasks are obtained through the greedy algorithm; Based on the ordered multi-knapsack problem model and following the thick-thin-thick rolling schedule, the minimum thickness jump penalty value is obtained through a greedy algorithm to obtain the rolling order between different specifications of the same steel grade in the same production task. Under the first constraint condition that the total number of pouring times required for production is not greater than the number of pouring times that can be performed within the maximum delivery period and the total number of pouring times for each steel grade per day is not greater than the number of pouring times that can be performed per day, the number of pouring times for continuous casting of different steel grades per day for each production task is obtained; According to the number of daily continuous castings of different steel grades in each production task, the production weight of each thickness is allocated according to the proportion of the total production volume of different thicknesses, and the production scheduling results of the corresponding steel grades in each production task are obtained respectively; Based on one or more of the priority judgment results of the production of different steel grades under the different production tasks, the rolling order between different specifications of the same steel grade in the corresponding same production task, the number of daily continuous casting pours of different steel grades in each production task and the production scheduling results of the corresponding steel grades in each production task, the allocation of production resources for headless continuous casting and rolling of hot rolled strip is carried out.

2. The production resource allocation method according to claim 1, characterized in that: The formulas characterizing the ordered multi-knapsack problem model include: Among them, P i =P wi +P gi +P hi ; The width jump penalty value between slab i and slab (i+1) of each steel grade is P wi , the thickness jump penalty value is P gi , the hardness jump penalty value is P hi ; The penalty value between slab i and slab (i+1) is P i ; The total penalty value is P; n is the number of thickness specifications for each type of steel; The second constraint condition corresponding to the ordered multi-knapsack problem model includes: Among them, L i is the rolling weight of slab i in one day; W is the total rolling amount; L sum It is the total amount that the production line can roll in one day.

3. The production resource allocation method according to claim 1, characterized in that: The secondary determination based on the priority given to the shortest delivery period and the priority given to the steel type with the largest total amount of rolling required includes: Make the first judgment based on the delivery time of different steel grades for each production task, and give priority to the one with the shortest delivery time; If the delivery dates are the same, a second determination will be made based on the total amount of different steel grades that need to be rolled for each production task, and the steel grades that require a larger total amount of rolling will be produced first.

4. The production resource allocation method according to claim 2, characterized in that: The method based on the ordered multi-knapsack problem model and following the thick-thin-thick rolling procedure, obtaining the minimum thickness jump penalty value through a greedy algorithm to obtain the rolling order between different specifications of the same steel grade in the same production task includes: The smallest value of the thickness specification under the same steel grade is selected as the minimum point, and the values ​​on both sides of this point are selected from the remaining thickness specifications to complete a thickness specification sorting, and this point is the only minimum point in the sorting; After completing the sorting of the thickness specifications once, the thickness jump penalty value is obtained; the model formula of the thickness jump penalty value includes: ΔH i =|H i -H i+1 |; Constraints: α+β=1,α·β≥0; Among them, H i is the rolling target thickness of slab i; ΔH i is the target thickness absolute jump of slab I; H′ i is the relative jump amount of the target thickness of slab I; α and β are the thickness jump penalty coefficients; P g is the thickness jump penalty value; A greedy algorithm is used to loop the above thickness specification sorting method. Each sorting is different. The final thickness jump penalty values ​​of all sortings are combined to retain the thickness specification sorting with the smallest thickness jump penalty value.

5. The method for allocating production resources according to claim 1, characterized in that: Under the first constraint condition that the total number of pouring times required for production is not greater than the number of pouring times that can be performed within the maximum delivery period and the total number of pouring times for each steel grade per day is not greater than the number of pouring times that can be performed per day, obtaining the number of pouring times for continuous casting of different steel grades for each production task per day includes: After obtaining all possible daily pouring orders for each steel grade within the maximum delivery period, the pouring order orders of different steel grades are combined through a loop statement to find the optimal solution that meets the first constraint condition, thereby obtaining the daily continuous casting pouring times of different steel grades for each production task; The first constraint condition includes: Where D is the maximum delivery time in the production task; k is the number of pouring times that the production line can perform per day; r is the number of steel types; N i is the number of required castings obtained according to the total amount of rolling required for each type of steel in each production task; m is the number of types of steel rolled in one day; p is the number of castings of each type of steel rolled in one day; N xy It is the daily casting times of different steel grades for each production task within the delivery period.

6. The method for allocating production resources according to claim 5, characterized in that: According to the number of continuous castings of different steel grades per day for each production task, the production weight of each thickness is allocated according to the proportion of the total production volume of different thicknesses, and the production scheduling results of the corresponding steel grades in each production task are obtained respectively, including: According to the number of pours of continuous casting of different steel grades per day and the unit pouring weight of each production task, the total daily production volume of each steel grade is obtained; After determining the total daily production volume, the daily production weight q of different thickness specifications is allocated according to the ratio of the total production volume of different thickness specifications of the same steel grade in the production task to the total production volume of the steel grade required in the production task. The specific formula includes: Among them, E i It indicates the total required production volume of the i-th thickness specification of a certain steel grade in the production task; It indicates the total amount of steel required to be produced in the production task; Q indicates the total daily production amount of each steel type; q indicates the daily production weight of different thickness specifications.

7. An electronic device, characterized in that: It comprises at least one processing unit and at least one storage unit, wherein the storage unit stores a computer program, and when the computer program is executed by the processing unit, the processing unit is enabled to execute the steps of the production resource allocation method according to any one of claims 1 to 6.

8. A storage medium, characterized in that: It stores a computer program executable by an access authentication device. When the computer program runs on the access authentication device, the access authentication device is enabled to execute the steps of the production resource allocation method according to any one of claims 1 to 6.

Citation Information

Patent Citations

  • Multi-target optimization method for casting sequence selection, ranking and casting time policy of continuous casting machine

    CN106055836A

  • Steelmaking production data analysis and optimization scheduling method for medium-thickness plate production line

    CN112926828A

  • Method and system for determining steel hot rolling production scheduling plan

    CN113537568A

  • Furnace batch plan optimization method and device and storage medium

    CN114386719A

  • Continuous casting-hot rolling operation scheduling method, device and equipment and storage medium

    CN117522101A