Method for checking plausibility of prediction

By calculating the predictive credibility of energy production facilities in the local energy market and transmitting tips, the problem of inaccurate prediction of energy suppliers is solved, the market robustness and resource efficiency are improved, and the additional costs are reduced.

CN118891799APending Publication Date: 2024-11-01SIEMENS AG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202380028471.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2022-03-23
Filing Date
2023-02-20
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

In the local energy market, energy suppliers have reduced energy values ​​due to inaccurate predictions, resulting in increased additional costs, especially when ‘destructive’ events occur, and the prediction of energy values ​​is needed.

Method used

By calculating the predictive credibility of the energy production facility in the processor, calculating the confidence probability using the data set of influence variables, and comparing it with a preset threshold, transmitting prompts to the energy producer to improve the prediction, using linear polynomial or neural network calculations Probability and consider facility information, weather data and spatial distribution to improve prediction accuracy.

Benefits of technology

It improves the robustness of the local energy market, identify destructive events early, reduces the load on the superior power grid, optimizes resource efficiency, reduces the additional costs caused by prediction errors, and improves the utilization rate of renewable energy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118891799A_ABST
    Figure CN118891799A_ABST
Patent Text Reader

Abstract

The invention relates to a method for checking the plausibility of predictions relating to energy values that can be provided in the local energy market. Here, the local energy marketplace has a processor (40), the method comprising the steps of: transmitting a first data set to the processor (40), the first data set having information about a prediction of the first energy producer (1), i.e. An energy value provided by a first energy production facility of the first energy producer (1) over a prescribed time period; transmitting one or more additional data sets to the processor (40), the additional data sets having information on an influence variable (x1, x2,..., xp) that can influence the energy value that can be provided; calculating, by the processor (40), a probability (Y) that the prediction can be implemented based on the provided information about the influence variable; comparing, by the processor (40), the calculated probability with a preset threshold value; when below the threshold value, a corresponding prompt is prompted to be transmitted to the first energy producer by the processor (40).
Need to check novelty before this filing date? Find Prior Art

Description

[0001] The invention relates to a method for checking the credibility of a prediction and a device for checking the credibility of a prediction.

[0002] In a local overall energy system, for example in an urban area or a town, its n different energy subsystems, such as buildings, each have different energy technical facilities, such as energy production facilities, consumption facilities or storage facilities. The distribution, i.e., configuration and division of the energy generated and consumed in the entire system as efficiently as possible, as well as the exchange in the corresponding energy network, give rise to central optimization and coordination problems. However, since each energy subsystem only has knowledge of its own energy technical facilities, a central coordination platform is required in order to optimize the exchange between the energy subsystems and the energy network while complying with the technical limitations of the energy network. Such a central coordination platform can be provided by a local energy market (=LEM), for example, as described in document DE 10 2018 221 156A1 (Siemens AG) 10.06.2020.

[0003] However, participating in local energy market energy transactions, such as day-ahead transactions or intraday transactions, also has risks. If the forecast of the energy value to be provided is inaccurate, the energy supplier may incur additional costs: if the energy supplier can only provide less energy to the local energy market than the energy value provided before, it must obtain and pay the energy difference from other sources, such as the upper power grid.

[0004] The problem is particularly acute in the event of "disruptive" events, i.e. an unexpected reduction in the amount of energy that can be supplied due to malfunctions or external influences, such as snow accumulation in photovoltaic (PV) installations, malfunctions in combined heat and power (BHKW) plants or a lack of wind in wind turbines (PV = photovoltaics; BHKW = combined heat and power).

[0005] The technical problem to be solved by the present invention is to improve the prediction of the energy value that can be provided in the local energy market.

[0006] This object is achieved by a method having the features of independent claim 1 and by a device having the features of independent claim 11. Advantageous embodiments and developments of the invention are specified in the dependent claims.

[0007] The method according to the invention is used to perform a credibility check on a prediction of a first energy producer; the prediction here gives the energy value provided by the first energy production facility of the first energy producer in the local energy market within a specified time period. According to the terminology in the local energy market, this prediction is also referred to as "supply (Gebot)" below. According to the method, a first data set with information about the prediction of the first energy producer is transmitted to a processor, which is used in the local energy market for credibility check. According to the method, one or more additional data sets with information about influencing variables are transmitted to the processor, and the additional data sets may affect the energy value that can be provided. The processor is then able to calculate the probability that the prediction is realized. Therefore, this probability can be characterized by the term "confidence". This calculation of the probability is realized based on the information provided about the influencing variables. Next, the processor compares the calculated probability with a preset threshold value. If the calculated probability is lower than the threshold, the processor prompts the transmission of a corresponding prompt to the first energy producer.

[0008] The method according to the invention and / or one or more functions, features and / or steps of the method according to the invention and / or its configuration can be implemented in a computer-assisted manner.

[0009] The plausibility checking device according to the invention is provided for carrying out the method.

[0010] The basic idea of ​​the invention is that the credibility of the received forecast is checked by a higher-level management level, namely a credibility checking device (hereinafter also referred to as a "monitoring system"). Therefore, one aspect of the invention is a central unit ("intelligence") of the local energy market, which assigns a "confidence rating" to the received energy supplier. The monitoring system constitutes the core mechanism of the local energy market, which processes the received supply and information related to the credibility check, such as facility information, weather information, and measured power to determine to what extent the received supply forecast can be realized ("confidence"). A probability between 0 and 1 is thus generated as an output, where 1 represents a 100% predicted probability that the supply can be met. Subsequently, when it is below a threshold value, which can be, for example, 0.5, a warning is output to the first energy producer who gave the forecast, warning the first energy producer that he should modify his supply.

[0011] The present invention improves the robustness of the local energy market as a whole.

[0012] By identifying disruptive events at an early stage, the quality of the supply in its subsequent implementation can be improved. This in turn enables better coordination within the local energy market in order to reduce the load on the higher-level grid when necessary.

[0013] The present invention makes it possible to better estimate and more effectively utilize storage capacity, such as a battery.

[0014] The invention reduces the additional costs incurred by local energy market participants due to forecast errors. This in turn reduces the incentive or necessity to make conservative supplies in the local energy market, such as only putting on 75% of the expected photovoltaic power generation. This improves local resource efficiency because more renewable energy is provided or traded on the local energy market, so that its potential is fully utilized. As a result, the local energy market is away from commercial logic and closer to physical reality.

[0015] Advantageous embodiments and developments of the invention are described in the dependent claims. The method according to the invention also correspondingly expands the independent device claim, and vice versa.

[0016] According to a preferred design of the present invention, the probability is calculated by means of a linear polynomial, for example, according to the following formula:

[0017] Y=β 0 +β 1 x 1 +β 2 x 2 +...+β p x p

[0018] variable x n (n=1, 2, ..., p) are influencing variables, such as external temperature, global radiation, installation angle, cloud cover in the next 15 minutes, etc. n is the weight coefficient of the influencing variable, n = 1, 2, ..., p; the weight coefficient can be obtained from historical data through logistic regression. β 0 represents a constant that may be necessary to correctly calculate the probability Y. The result Y is the desired probability: Y=0 indicates that the first energy production facility is completely shut down and cannot provide energy; Y=1 indicates that the first energy production facility can fully provide the predicted energy value.

[0019] According to a preferred design of the present invention, the probability is calculated with the aid of a neural network having sigmoid as an activation function of the output layer. The model parameters are determined here using binary cross entropy as a cost function. The cross entropy as a cost function is only used to determine the parameters (model training). In "continuous operation", the neural network no longer needs this function; here the output probability Y is ensured by the architecture of the output layer (sigmoid). The advantage is that it involves a completely nonlinear system, which can however also map linear polynomials.

[0020] According to a preferred embodiment of the invention, the prediction is compared with one or more other predictions for other energy production facilities that are similar to the first energy production facility. Unlike previous practices, in which each energy producer generates its own prediction without comparison between predictions, the prediction is verified based on similar facilities. This has the advantage that even for "silent" energy production facilities, i.e. energy production facilities without their own sensors, it is possible to check whether their predictions are credible based on the predictions of other energy producers with similar energy production facilities.

[0021] According to a preferred design of the present invention, the spatial distribution of the first energy production facility and other energy production facilities is taken into account in order to identify weather influences. Today, the number of professional consumers is very large: for example, private households are becoming energy producers through their own photovoltaic rooftop facilities. The present invention makes use of the large number of measurement locations or sensors that are available for use, as well as the local regional distribution of these measurement points or sensors. The spatial distribution of energy production facilities can be used to identify destructive (local) weather influences earlier and with a higher probability. For example, external influences occurring at each individual energy production facility, such as calm wind, snowfall or large areas of cloud cover, can be identified early and transmitted to other energy production facilities in the local energy market. In this way, the prediction quality of energy production facilities for renewable energy can be significantly improved.

[0022] According to a preferred design of the present invention, the influencing variables include facility information of the first energy production facility, such as geographic coordinates, orientation, installation position, tilt angle of the first energy production facility, and / or facility information of other energy production facilities.

[0023] For example, different installation specifications of energy production facilities can be used. For private photovoltaic facilities covered with snow, it is usually necessary to wait until the snow layer covering the photovoltaic modules and affecting their power generation melts or slides off. Since both processes depend on the orientation and the installation angle (steepness) of the photovoltaic modules, these phenomena can be easily transferred to other energy production facilities and / or energy production facility specifications. In this way, for example, the point in time at which a photovoltaic facility covered with snow will generate electricity again can be predicted very well.

[0024] The local energy market is provided not only with individual data of the corresponding energy producers, but also with other (measured) data of other energy producers. When using the facility information of other energy production facilities that are the same as the first energy production facility (same product, same or similar type), the characteristic behavior of other energy production facilities before failure can be used to predict the impending failure of the first energy production facility. For example, if multiple energy producers in the local energy market are connected to the same cogeneration device, then the characteristic behavior of all these cogeneration devices before failure can be used to predict the failure of the cogeneration device.

[0025] According to a preferred design of the present invention, the influencing variables include weather data and / or weather forecasts. The spatial distribution of energy production facilities can be used to identify destructive (local) weather influences earlier and with higher probability. For example, external influences such as calm, snowfall or large-scale cloud cover occurring at each individual energy production facility can be identified early and transmitted to other energy production facilities in the local energy market. This can significantly improve the forecast quality of renewable energy facilities.

[0026] According to a preferred design of the present invention, the influencing variables include data on energy values ​​provided in the past by the first energy production facility and / or other energy production facilities, thereby enabling predictions made under certain weather conditions to be compared with previous predictions made for the same weather conditions.

[0027] According to a preferred design of the present invention, the influencing variables include predictions about other energy production facilities, the first energy producer and / or other energy producers. Thus, the predictions made for certain weather conditions and / or certain configurations and / or states of energy production facilities can be compared with previous predictions made for the same or similar weather conditions and / or for the same or similar configurations and / or states of other energy production facilities.

[0028] According to a preferred design of the present invention, after transmitting one or more prompts to the first energy producer, the processed second forecast and other forecasts of the first energy producer transmitted to the processor are re-checked for plausibility. Here, prompts are transmitted to the first energy producer until the probability meets or exceeds a specified threshold. The advantage of this is that the quality of the forecast can be continuously checked and tracked, thereby achieving better coordination within the local energy market.

[0029] According to a preferred design of the present invention, the received forecast is automatically checked. The advantage here is that the cost of the local energy market operator to perform the credibility check is reduced.

[0030] According to a preferred design solution of the present invention, a “transfer learning” method can be applied, so that when a new energy producer is connected to a local energy market, relatively good prediction results can be achieved even with less available training data.

[0031] Further advantages, features and details of the invention are apparent from the exemplary embodiments described below and with reference to the drawings. They are shown schematically and not to scale:

[0032] Figure 1 A diagram showing the arrangement of credibility checks in a local energy market;

[0033] Figure 2 a view showing inputs and outputs of a credibility check; and

[0034] Figure 3 A diagram showing how cloud regions affect multiple energy production facilities.

[0035] Figure 1 An energy producer 1 is shown, which transmits a data set with information about a forecast to a local energy market 5, wherein the forecast gives information about the amount of energy that a first energy production facility 33 of the first energy producer 1 provides in the local energy market 5 within a specified time period, for example from 0:00 h to 24:00 h the following day. Such a forecast is called "offer" in the parlance of the local energy market 5. The data set arrives at a preprocessing device 2, where the data set is preprocessed; for example, a check is made as to whether the energy producer has a license to publish the forecast in the local energy market 5. From the preprocessing device, the data set is transmitted 12 to a plausibility check device 4 having a processor 40.

[0036] The plausibility check device 4 also receives one or more further data sets with information about the influencing variables x 1 、x 2 ,......,x p The information about the influencing variables may affect the energy value that can be provided. In the subsequent step, the credibility check device 4 calculates the probability of the prediction being realized based on the provided information about the influencing variables with the help of the processor 40. In the subsequent step, the credibility check device 4 compares the calculated probability with a preset threshold value with the help of the processor 40.

[0037] If the calculated probability is below a threshold value, the plausibility check device 4 causes 13 the preprocessing device 2 to transmit a corresponding message 11 to the first energy producer 1 .

[0038] In the other case, ie the calculated probability reaches or exceeds the threshold value, the credibility checking device 4 drives 13 the pre-processing device 2 to further process the prediction and transmit it 14 to the order matching device 3 .

[0039] Figure 2 A diagram showing the inputs and outputs of the plausibility check 4 is shown. First input (influencing variable) x 1 The second input (influencing variable) x is information about the first energy production facility, such as coordinates, rated power, installation specifications (such as orientation, installation position, tilt angle). 2 It is the information from external providers, such as weather forecasts and weather data. The third input (influencing variable) x 3 is information about the power generated in the past; both the values ​​of the first energy production facility and the values ​​of other similar energy production facilities in the local energy market 5 are of interest here. Fourth input (influencing variable) x 4 is information about the forecast, ie about the power provided; in addition to the forecast for the first energy production facility, the forecasts for other similar energy production facilities in the local energy market 5 are also considered. The output Y of the plausibility check 4 is the inferred probability that the forecast can be achieved.

[0040] Figure 3 It is shown how to take into account the spatial distribution of the first energy production facility and the other energy production facilities in order to identify weather influences. During the day, the cloud area 30 passes over three photovoltaic energy production facilities 31, 32, 33 with a westerly wind of speed v, which are arranged at positions l1, l2, l3 in the west-east running direction of the cloud area 30. Positions l3 and l2 are spaced apart from each other by a distance l3-l2, and positions l2 and l1 are spaced apart from each other by a distance l2-l1. The cloud area 30 thus reaches the three photovoltaic energy production facilities 31, 32, and 33 successively at time points t1, t2, and t3. Since the cloud area 30 has an extension dimension z in its running direction, each of the three photovoltaic energy production facilities 31, 32, and 33 is covered by the cloud area 30 in the time period Δt=z / v.

[0041] If the cloud region 30 does not bring precipitation or rain, the energy production of the three photovoltaic energy production facilities 31, 32, and 33 is reduced at time points t1, t2, and t3 respectively due to the shading that occurs, and remains at the reduced level during the time period Δt, and then increases again due to direct sunlight after the cloud region 30 passes. Through the time point t1 at which the energy production of the first photovoltaic energy production facility 31 is reduced, the distances l2-l1 and l3-l2, and the wind speed v when the cloud region 30 passes over the photovoltaic energy production facilities 31, 32, and 33, the time points t2 and t3 at which the energy production of the other two photovoltaic energy production facilities 32 and 33 is also reduced can be calculated. This applies similarly to the increase in energy production after the cloud region 30 passes.

[0042] If the cloud region 30 brings snowfall, the energy production of the three photovoltaic energy production facilities 31, 32, 33 decreases at the time points t1, t2 and t3 respectively, due to the snow covering the photovoltaic modules of the three photovoltaic energy production facilities 31, 32, 33, and remains at the reduced level until the photovoltaic modules are no longer covered with snow, for example, by sweeping, sliding or melting. In the case of snowfall, at least the time points t2 and t3 of the reduction in energy production can be calculated from the reduction at the first photovoltaic energy production facility 31. The time point at which the photovoltaic modules are no longer covered with snow and the energy production increases again cannot be deduced solely from the speed of the cloud region 30, because other influencing factors such as the position, orientation and tilt angle of the photovoltaic modules also play a role here.

Claims

1. A method for plausibility checking a forecast about the energy value that can be provided in a local energy market, wherein: The local energy market has a processor (40), and the method comprises the following steps: - transmitting a first data set to the processor (40), the first data set having information about a forecast of a first energy producer (1), i.e. the energy value to be provided by a first energy production facility of the first energy producer (1) within a specified time period; - transmitting one or more further data sets to the processor (40), the further data sets having information on the influencing variables (x1, x2, . . . , x p ), wherein the influencing variables may affect the energy value that can be provided; - based on the information provided about the influencing variables, calculating by the processor (40) the probability (Y) that the prediction will be realized; - comparing the calculated probability with a preset threshold value by the processor (40); - when it falls below the threshold, the processor (40) causes a corresponding notification to be transmitted to the first energy producer.

2. The method according to claim 1, wherein: The probability (Y) is calculated using the following linear polynomial, namely: Y=β0+β1x1+β2x2+...+β p x p Among them, β n are weight coefficients of influencing variables, or the probabilities are calculated with the aid of a neural network having sigmoid as activation function of the output layer.

3. The method according to claim 2, wherein: The weight coefficient β n Obtained from historical data with the help of logistic regression.

4. A method according to any one of the preceding claims, wherein: The forecast is compared to one or more other forecasts for other energy production facilities that are similar to the first energy production facility.

5. The method according to claim 4, wherein: The spatial distribution of the first energy production facility and other energy production facilities is taken into account in order to identify weather influences.

6. A method according to any one of the preceding claims, wherein: The influencing variables include facility information, such as geographical coordinates, orientation, installation position, and inclination angle of the first energy production facility.

7. A method according to any one of the preceding claims, wherein: The influencing variables include weather data and / or weather forecasts.

8. A method according to any one of the preceding claims, wherein: The influencing variables include data on energy values ​​provided in the past by the first energy production facility and / or other energy production facilities.

9. A method according to any one of the preceding claims, wherein: The influencing variables include predictions regarding other energy production facilities, the first energy producer, and / or other energy producers.

10. A method according to any one of the preceding claims, wherein: After transmitting one or more prompts to the first energy producer (1), the processed second prediction and other predictions of the first energy producer (1) transmitted to the processor (40) are re-checked for credibility, and prompts are transmitted to the first energy producer (1) until the probability (Y) meets or exceeds a specified threshold.

11. A method according to any one of the preceding claims, wherein: Automatically check incoming forecasts.

12. A plausibility checking device (4) configured to carry out the method according to any one of the preceding claims.