A modular assembly and calibration device and method for ultra-long conveyor corridor steel structure

By using technical means such as guide support beam mechanism and coarse positioning mechanism during the assembly process of the ultra-long conveying corridor, the problems of assembly difficulty and assembly accuracy of high altitude operations are solved, and an efficient and automated assembly process is achieved, reducing labor intensity and assembly costs.

CN118895872BActive Publication Date: 2025-03-28SINOMA SUZHOU CONSTR
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411307477.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2025-03-28
Estimated Expiration
2044-09-19

AI Technical Summary

Technical Problem

The current corridor assembly has problems such as high-altitude assembly and poor assembly accuracy, difficult positioning, low assembly efficiency, low degree of automation and labor intensity.

Method used

A combined solution including guide support beam mechanism, coarse positioning mechanism, portable positioning loading and unloading mechanism, height adjustment mechanism, wedge-shaped heightener and angle adjustment mechanism is adopted. Through the coordinated work of these mechanisms, efficient positioning, assembly and calibration of the corridor box is achieved.

Benefits of technology

It effectively reduces the difficulty of assembly of high-altitude operations, improves the assembly and coordination accuracy and automation of modular box, reduces the difficulty of positioning and labor intensity, and improves the assembly efficiency and modularity of corridor box.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118895872B_ABST
    Figure CN118895872B_ABST
Patent Text Reader

Abstract

The present invention relates to a modular assembly and calibration device and method for an ultra-long conveying corridor steel structure, specifically comprising a corridor box body, wherein the corridor box body comprises a main support frame composed of side beams, a first cross beam, a second cross beam, and an intermediate cross beam, and further comprises a base frame, a bottom plate, an oblique side beam, a side plate, a top plate, and a top beam; the first cross beam and the second cross beam are fixedly arranged at the opposite ends of two groups of the side beams, and a plurality of groups of the intermediate cross beams are evenly arranged in the middle; the base frame is fixedly arranged on the lower side of the main support frame, and a bottom plate is fixedly arranged on the other side thereof; a plurality of groups of oblique side beams are arranged, which are evenly fixedly arranged on the two groups of side beams; the side plates are fixedly arranged on the two groups of side beams, and are arranged in parallel with the oblique side beams and fixed on the oblique side beams; the present invention can effectively reduce the assembly difficulty of high-altitude operations, improve the accuracy of assembly and cooperation between modular boxes, reduce the difficulty of positioning, improve the assembly efficiency, and improve the modularity of the corridor box body.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of corridor steel structures, and in particular to a modular assembly and calibration device and method for an ultra-long conveying corridor steel structure. Background Art

[0002] In recent years, relying on the huge demand for raw materials such as cement due to infrastructure construction, cement and other industries have developed rapidly, gradually forming a cement industry cluster with Southern Cement as the core, with more than 10 million tons of cement clinker shipped out annually. Except for a small part of these products that are transported by rail, most of them are transported to the dock by heavy trucks and then transported by water. This mode of transportation not only seriously restricts the product transportation capacity and increases logistics costs, but also puts the local area under certain traffic pressure and environmental risks.

[0003] To solve this problem, super-long conveyor corridors came into being. The conveyor belts are high temperature resistant and fully sealed. After operation, the cement clinker produced by upstream member enterprises is transported to the transfer station through the belt machine corridor, and then transported to the wharf by the transfer station through the belt machine corridor, and then transported to various places by water from the wharf for distribution. This is also a new transportation mode of air-water transport after river-sea transport.

[0004] The ultra-long conveyor corridor transports cement clinker to the dock, which not only greatly reduces the traffic of large trucks on the road and relieves the pressure of road transportation, but also realizes the "zero emission" transportation of goods and reduces the impact of dust, noise and exhaust gas on the environment. "

[0005] The assembled corridor is a mining supporting equipment that can greatly shorten the project construction period and reduce construction costs. It is a belt conveyor corridor closure device that can be used in mining sand and gravel yards, metallurgy, coal and other industries to close bulk material transportation and reduce dust and noise pollution in the transportation process.

[0006] The assembled corridor is one step faster in construction. The assembled corridor adopts modular design and split processing. The whole is composed of corridor base frame, corridor upper frame, corridor side beam, lighting board, support position, reinforcement support and other parts. Different parts are transported to the project site for assembly, which can greatly shorten the project construction period and reduce construction costs. The assembled corridor is hoisted as a whole. The internal design has a fixed position for the cable tray. Before on-site hoisting, the top can be directly sealed and assembled, and hoisted as a whole. The assembled corridor is sealed and environmentally friendly. The patterned plate at the bottom of the corridor is cut by laser cutting. The entire ground is seamlessly connected, with good sealing, no dust leakage, and environmentally friendly production.

[0007] The components of the assembled corridor include corridor base frame, reinforcement support, corrugated side plate, bottom pattern plate, corridor side beam, lighting plate, corridor upper frame, support position, etc. The corridor is also equipped with fixed positions for cables, lighting devices and surveillance cameras.

[0008] The assembled corridor has high bearing capacity and structural strength, and is flexible and convenient to install. The combined connection is achieved by bolting the connecting plates on the vertical surface of the corridor. Compared with the traditional belt conveyor corridor, the construction period is short, the project volume can be closed, and the construction cost is reduced.

[0009] As disclosed in application number 202122047517.4, an assembled corridor comprises corridor A and corridor B, wherein corridor A comprises an upper support frame, two side beams and a lower support plate, wherein the upper support frame and the lower support plate are fixedly connected to the upper and lower edges of the side beams at both ends respectively by bolts, the upper surface of the upper support frame is provided with a color steel tile, the two ends of the side beam are respectively vertical inclined surfaces, and the inner and outer side walls of one end of the vertical surface of the side beam are welded with connecting plates, connecting holes are opened on the connecting plates, and a frame is fixedly connected to the edge of one end of the inclined surface of the side beam, and connecting holes are opened at the edges of the frame. The structures of the corridor A and corridor B are the same, and the connecting plates on the vertical surfaces of the corridor A and corridor B are fixedly connected by bolts. The utility model has the advantages of high bearing capacity and structural strength of the corridor, good production quality of the corridor, short construction period, low construction cost, flexible and convenient construction, etc.

[0010] However, most of the current corridors have problems such as difficulty in assembly at high altitude, poor assembly accuracy between modular boxes, difficulty in positioning, low assembly efficiency, low degree of assembly automation, high assembly labor intensity, and low degree of modularization of corridor boxes. Summary of the invention

[0011] The technical problem to be solved by the present invention is to reduce the difficulty of assembly in high-altitude operations, improve the accuracy of assembly and coordination between modular boxes, reduce the difficulty of positioning, improve assembly efficiency, and improve the degree of assembly automation, thereby reducing the labor intensity of assembly and improving the modularity of the corridor box.

[0012] In order to solve the above technical problems, the present invention provides a modular assembly and calibration device for an ultra-long conveying corridor steel structure, including a corridor box body, wherein the corridor box body includes a main support frame composed of side beams, a first cross beam, a second cross beam, and an intermediate cross beam, and also includes a bottom frame, a bottom plate, an oblique side beam, a side plate, a top plate, and a top beam; the first cross beam and the second cross beam are fixedly arranged at the opposite ends of two groups of the side beams, and multiple groups of the intermediate cross beams are evenly arranged in the middle; the bottom frame is fixedly arranged on the lower side of the main support frame, and a bottom plate is fixedly arranged on the other side of the bottom frame; multiple groups of oblique side beams are arranged, and are evenly fixed on the two groups of side beams; the side plates are fixedly arranged on the two groups of side beams, and are arranged parallel to the oblique side beams and fixed on the oblique side beams; the top plate is fixedly arranged on the upper side of the oblique side beams and arranged opposite to the bottom plate; top beams are fixedly arranged at both ends of the top plate near the first cross beam and the second cross beam, and are fixedly connected to the oblique side beams;

[0013] A guide support beam mechanism with a preset guide is fixedly arranged on the lower side of the corridor box;

[0014] A rough positioning mechanism for preliminary positioning is fixedly arranged on the corridor box;

[0015] Preferably, the guide support beam mechanism comprises an I-shaped main steel beam; the I-shaped main steel beam is provided in multiple groups, one side of which is fixedly provided on the main support frame on the corridor box body;

[0016] Preferably, the rough positioning mechanism includes a positioning boss, a positioning groove, a reference side surface, a fixed mounting boss, a side leaning base, a side leaning reference surface, an end face reference surface, a rough positioning slot hole, and a three-level guide positioning column; a positioning boss is provided at one end of the I-beam main steel beam, and a positioning groove is provided at the end facing it, so that its straightness is initially determined during splicing; multiple groups of fixed mounting bosses are provided on the main support frame, and the side leaning base is provided on the fixed mounting boss, and the side leaning base is provided on the side leaning base, and the side leaning reference surface is provided on the fixed mounting boss, and the end face reference surface is provided on the fixed mounting boss, and the multiple groups of the end face reference surfaces fixed to the same I-beam main steel beam are at the same height, and the multiple groups of the side leaning reference surfaces are coplanar; the side surface of the I-beam main steel beam in contact with the side leaning reference surface is the reference side surface; two groups of three-level guide positioning columns are fixedly provided on one side of the two groups of side beams close to the first cross beam, and coarse positioning slots are fixedly provided on the opposite side;

[0017] Preferably, the modular assembly and calibration device for the steel structure of the super-long conveyor corridor also includes a portable positioning and loading and unloading mechanism, which includes a conical boss, a conical groove, a worm right-angle commutator, a screw, a ball head surface, a limiting hole, a fixed pin shaft, a pull-in bearing seat, a pull-in bearing, a pull-in support plate, a push-out bearing seat, a push-out bearing, a push-out support sleeve, and a conical support surface; the conical boss is fixedly arranged on the first crossbeam, and the conical groove is fixedly arranged on the second crossbeam, and the two are arranged oppositely; the worm right-angle commutator is fixedly arranged on the first crossbeam, and is arranged oppositely to the conical boss, and the screw runs through the worm right-angle commutator and passes through the A conical boss and a conical groove, a limiting hole is provided at the shaft end of the screw rod close to the conical groove, and a ball head surface is provided at the shaft end thereof, the fixing pin shaft is movably arranged in the limiting hole, the pull-in bearing seat is fixedly arranged on the second cross beam and arranged facing the conical groove, the push-out bearing seat is fixedly arranged on the side of the pull-in bearing seat away from the conical groove, the pull-in bearing is fixedly arranged in the pull-in bearing seat, the pull-in support plate is fixedly arranged in the pull-in bearing, the push-out bearing is fixedly arranged in the push-out bearing seat, the push-out support sleeve is fixedly arranged in the push-out bearing, and a conical support surface is provided on the side of the push-out support sleeve close to the ball head surface;

[0018] Preferably, the pull-in bearing and the push-out bearing are thrust angular contact ball bearings, and the pull-in support plate and the push-out support sleeve are close to the large-surface inner ring;

[0019] Preferably, the modular assembly and calibration device for the steel structure of the super-long conveying corridor further includes a support column mechanism, which includes a base, a support arm, a support seat, a support fixing plate, a height adjustment seat, and a core column; the support arm is provided with multiple groups, which are fixedly arranged on the base, the support seat is provided with multiple groups, which are evenly distributed on the support arm, the height adjustment seat is fixedly arranged on the support arm on a side away from the base, the support fixing plate is fixedly arranged on a group of the support seats close to the height adjustment seat, and the core column is movably arranged in the height adjustment seat;

[0020] Preferably, the modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a height adjustment mechanism, which includes a U-shaped limit groove, a height limit hole, a height limit shaft, a semicircular locking protrusion, a locking screw and a locking nut; a height limit hole is provided on the core column, and two corresponding groups of U-shaped limit grooves are provided on the height adjustment seat on both sides corresponding to the height limit hole, the height limit shaft passes through the height limit hole, and both ends are movably arranged in the U-shaped limit groove, and two groups of semicircular locking protrusions are movably arranged in the U-shaped limit groove to move toward each other and fit with the height limit shaft, the locking screw is fixedly arranged on the semicircular locking protrusion, and is fixedly arranged on the height adjustment seat by threads, and is locked by the locking nut;

[0021] Preferably, the modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a wedge-shaped height increaser, which includes a base cavity, a lifting motor, a rotating screw, a nut fixing block, a guide rail, a slider, a wedge-shaped push block, a trapezoidal push block, a roller, a short shaft, and a lifting platform; the base cavity is fixedly arranged on the supporting fixing plate, the lifting motor is fixedly arranged on the side wall of the base cavity and is fixedly connected to the rotating screw, the nut fixing block is movably connected to the rotating screw through a screw nut, and can reciprocate linearly along the axis direction of the rotating screw, the guide rail is fixedly arranged in the base cavity and arranged parallel to the rotating screw, the wedge-shaped push block is movably arranged on the guide rail through the slider, and one end of the wedge-shaped push block is fixedly connected to the nut fixing block, the roller is fixedly arranged on the trapezoidal push block through the short shaft, and the lifting platform is fixedly arranged on the trapezoidal push block;

[0022] Preferably, the modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes an angle adjustment mechanism, which includes a corner bracket, a hinge hole, a reference column, an arc-shaped guide groove, a fixing pin hole, and a support pad; the corner bracket is provided with two groups, which are fixedly arranged on both sides of the core column facing each other, and the corner bracket is provided with a hinge hole to realize the movable hinge connection with the core column, and two groups of reference columns are fixedly arranged on the core column, and the corner bracket is provided with an arc-shaped guide groove at the position of the reference column, and is provided with an angle mark; the corner bracket is provided with multiple groups of fixing pin holes, and the support pad is fixedly arranged on the side of the two groups of corner brackets away from the hinge hole; the other side of the support pad is fixedly arranged on the bottom surface of the I-beam main steel beam;

[0023] An assembly method for a modular assembly and calibration device for an ultra-long conveying corridor steel structure, comprising the following steps: S1, during assembly, the support column mechanism is assembled first, and after the guide support beam mechanism is assembled and its accuracy is checked, the corridor box is installed;

[0024] S2. When assembling the support column mechanism, the lifting motor drives the rotating screw to rotate, thereby realizing the linear motion of the nut fixing block along the axis direction of the rotating screw, and driving the wedge-shaped push block to move linearly along the guide rail. The wedge-shaped inclined surface on the wedge-shaped push block pushes the roller on the wedge-shaped push block to realize the lifting and lowering of the trapezoidal push block, thereby realizing the lifting and lowering of the lifting platform, realizing the linear motion of the core column along the direction of the height adjustment seat, and realizing the height adjustment of the support column mechanism;

[0025] S3, loosen the locking screws on both sides of the height limiting shaft to adjust the height of the core column. After the height adjustment is completed, limit the height limiting shaft at both ends through the locking screws and fix it by locking with the locking nuts.

[0026] S4, according to the different heights of the support column mechanism, the I-shaped main steel beam is at a certain angle to the horizontal plane, and the angle is accurately set relative to the reference column through the angle mark on the arc guide groove to adjust the angle. After the angle is adjusted, the support pad is assembled and then the I-shaped main steel beam is assembled;

[0027] S5. According to the cooperation between the positioning boss and the positioning groove, the two groups of I-beam main steel beams are spliced ​​preferentially. During the splicing, one of the reference side surfaces is used as a reference, and a light aligner is used to calibrate the other I-beam main steel beam to be spliced, so that the straightness of the reference side surfaces on the two I-beam main steel beams meets the standard; before installing the corridor box, the side reference surface and the end reference surface are milled after pre-assembly, and the straightness accuracy meets the standard. When installing the corridor box, the fixed installation boss cooperates with the upper end surface of the I-beam main steel beam through the end reference surface, and the side reference table cooperates with the reference side surface through the side reference surface to achieve preliminary positioning of the straightness; one group of corridor boxes approaches the other group of already fixed corridor boxes along the I-beam main steel beam, and the coarse positioning slots on one group of corridor boxes are inserted into the three-level guide positioning columns on the other group of corridor boxes for further positioning;

[0028] S6, the worm right-angle commutator drives the screw to rotate and move linearly along its axis, and the fixed pin on the limiting hole pushes the pull-in support plate to move linearly, so that the conical groove and the conical boss cooperate to achieve the close contact of the two gallery boxes to complete the assembly; when it needs to be dismantled, the worm right-angle commutator drives the screw to rotate and move linearly in the opposite direction of its axis, and the ball head surface is close to the conical support surface, thereby pushing the push-out support sleeve to move linearly, so that the conical groove and the conical boss are out of cooperation;

[0029] Compared with the prior art, the present invention has the following beneficial effects:

[0030] 1. By setting up the guide support beam mechanism, a simple and efficient positioning guide is effectively established between the corridor box and the support column mechanism, which greatly reduces the difficulty of assembling the corridor box at high altitude and improves the precision guidance of the assembly and coordination between the modular boxes.

[0031] 2. By setting up a rough positioning mechanism, preliminary positioning is performed before positioning and assembly, which effectively reduces the difficulty of positioning and improves assembly efficiency; at the same time, it also provides a smaller error range for further positioning and assembly, thereby improving the work efficiency of positioning and assembly.

[0032] 3. By setting up a portable positioning and loading and unloading mechanism, the two groups of boxes can be accurately positioned and automatically aligned by pulling the motor screw, which improves the degree of automation of assembly, improves assembly efficiency, and reduces assembly labor intensity; in addition, it provides automated dismantling conditions for later dismantling and improves the modularity of the corridor box.

[0033] 4. By setting up a height adjustment mechanism, the core column can be effectively tightened after changing the height of the column. On the premise of ensuring that the column has a height adjustment function, the overall structural stability of the column is guaranteed.

[0034] 5. By setting a wedge-shaped height increaser, facing the overall assembly error, a wedge-shaped height increaser is set to adjust the height error generated during the assembly process of the corridor box, thereby reducing the high-precision requirements for the modular box and reducing the high-precision assembly manufacturing cost of the box.

[0035] 6. By setting up an angle adjustment mechanism, the angle adjustment mechanism is set up to meet the requirements of up and down slopes, thereby improving the overall applicability of the ultra-long conveying corridor. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] The present invention is further described in detail below in conjunction with the accompanying drawings:

[0037] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention;

[0038] Figure 2 It is a left side view of the present invention;

[0039] Figure 3 for Figure 2 Schematic diagram of the structure of the cross section in the AA direction;

[0040] Figure 4 A left view of the gallery box of the present invention;

[0041] Figure 5 The front view of the corridor box of the present invention;

[0042] Figure 6 A right view of the gallery box of the present invention;

[0043] Figure 7 for Figure 5 Structural schematic diagram of the cross section in the middle BB direction;

[0044] Figure 8 for Figure 7 A partial enlarged schematic diagram of the middle C area;

[0045] Fig. 9 for Figure 3 A partial enlarged schematic diagram of the middle D area;

[0046] Fig.10 for Figure 2 A partial enlarged schematic diagram of the middle E area;

[0047] Fig.11 The front view of the wedge-shaped height increaser of the present invention;

[0048] Fig.12 for Fig.11Schematic diagram of the structure of the cross section in the FF direction;

[0049] Fig.13 for Fig.11 Schematic diagram of the structure of the cross section in the GG direction;

[0050] Fig.14 for Figure 3 A partial enlarged schematic diagram of the middle H region;

[0051] In the figure: 1. Corridor box; 101. Main support frame; 102. Side beam; 103. First cross beam; 104. Second cross beam; 105. Middle cross beam; 106. Base frame; 107. Bottom plate; 108. Oblique side beam; 109. Side plate; 110. Top plate; 111. Top beam; 2. Guide support beam mechanism; 201. I-beam main steel beam; 3. Rough positioning mechanism; 301. Positioning boss; 302. Positioning groove; 303. Reference side; 304. Fixed mounting boss ; 305, side reference platform; 306, side reference surface; 307, end reference surface; 308, coarse positioning slot; 309, three-level guide positioning column; 4, portable positioning and loading and unloading mechanism; 401, conical boss; 402, conical groove; 403, worm right angle commutator; 404, screw; 405, ball head surface; 406, limit hole; 407, fixed pin; 408, pull in bearing seat; 409, pull in bearing; 410, pull in support plate; 411, push Out of the bearing seat; 412, push out the bearing; 413, push out the support sleeve; 414, conical support surface; 5, support column mechanism; 501, base; 502, support arm; 503, support seat; 504, support fixing plate; 505, height adjustment seat; 506, core column; 6, height adjustment mechanism; 601, U-shaped limit groove; 602, height limit hole; 603, height limit shaft; 604, semicircular locking protrusion; 605, locking screw; 606, locking nut; 7. Wedge-shaped height increaser; 701. base cavity; 702. lifting motor; 703. rotating screw; 704. nut fixing block; 705. guide rail; 706. slider; 707. wedge-shaped push block; 708. trapezoidal push block; 709. roller; 710. short shaft; 711. lifting platform; 8. angle adjustment mechanism; 801. corner bracket; 802. hinge hole; 803. reference column; 804. arc guide groove; 805. fixing pin hole; 806. support pad; DETAILED DESCRIPTION

[0052] Embodiment 1:

[0053] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0054] See also Figure 1-Figure 14 A modular assembly and calibration device for an ultra-long conveying corridor steel structure, comprising a corridor box 1, wherein the corridor box 1 comprises a main support frame 101 composed of side beams 102, a first cross beam 103, a second cross beam 104, and an intermediate cross beam 105, and further comprises a bottom frame 106, a bottom plate 107, an oblique side beam 108, a side plate 109, a top plate 110, and a top beam 111; the first cross beam 103 and the second cross beam 104 are fixedly arranged at the opposite ends of two groups of the side beams 102, and a plurality of groups of the intermediate cross beams 105 are evenly arranged in the middle; the bottom frame is fixedly arranged on the main support frame 1 01, and a bottom plate 107 is fixedly arranged on the other side thereof. The oblique side beams 108 are provided with multiple groups, and are evenly fixedly arranged on the two groups of the side beams 102. The side plates 109 are fixedly arranged on the two groups of the side beams 102, and are arranged in parallel with the oblique side beams 108 and fixed on the oblique side beams 108. The top plate 110 is fixedly arranged on the upper side of the oblique side beams 108, and is arranged facing the bottom plate 107. Top beams 111 are fixedly arranged at both ends of the top plate 110 near the first cross beam 103 and the second cross beam 104, and are fixedly connected to the oblique side beams 108.

[0055] A guide support beam mechanism 2 with a preset guide is fixedly arranged on the lower side of the corridor box body 1;

[0056] A rough positioning mechanism 3 for preliminary positioning is fixedly arranged on the corridor box body 1;

[0057] In some embodiments, see Figure 5 The guide support beam mechanism 2 includes an I-shaped main steel beam 201; the I-shaped main steel beam 201 is provided with multiple groups, one side of which is fixedly provided on the main support frame 101 on the corridor box 1; by providing the guide support beam mechanism, a simple and efficient positioning guide is effectively established between the corridor box and the support column mechanism, which greatly reduces the difficulty of assembling the corridor box at high altitude and improves the precision guidance of the assembly and cooperation between the modular boxes.

[0058] In some embodiments, see Figure 6The coarse positioning mechanism 3 includes a positioning boss 301, a positioning groove 302, a reference side 303, a fixed mounting boss 304, a side reference platform 305, a side reference surface 306, an end reference surface 307, a coarse positioning slot 308, and a three-level guide positioning column 309; one end of the I-beam main steel beam 201 is provided with a positioning boss 301, and the opposite end is provided with a positioning groove 302, so that the straightness is initially determined when splicing; the main support frame 101 is provided with multiple groups of fixed mounting bosses 304, the fixed mounting bosses 304 are provided with side reference platforms 305, and the side reference platforms 305 are provided with side reference surfaces. 306, an end reference surface 307 is arranged on the fixed mounting boss 304, and multiple groups of the fixed mounting bosses 304 fixed to the same I-beam main steel beam 201 have multiple groups of the end reference surfaces 307 at the same height, and multiple groups of the side reference surfaces 306 are coplanar; the side of the I-beam main steel beam 201 in contact with the side reference surface 306 is the reference side surface 303; two groups of three-level guide positioning columns 309 are fixedly arranged on one side of the two groups of side beams 102 close to the first cross beam 103, and a coarse positioning slot 308 is fixedly opened on the opposite side; when in use, according to the positioning boss 301, the positioning groove 302 Cooperate with each other, preferentially splice the two groups of I-beam main steel beams 201. During splicing, take one of the reference side surfaces 303 as a reference, use a light aligner to calibrate the other I-beam main steel beam 201 to make the straightness of the reference side surfaces 303 on the two I-beam main steel beams 201 meet the standard; before installing the corridor box body 1, the side reference surface 306 and the end reference surface 307 are milled after pre-assembly, and the straightness accuracy meets the standard. When installing the corridor box body 1, the fixed installation boss 304 cooperates with the upper end surface of the I-beam main steel beam 201 through the end reference surface 307, and the side reference surface 306 and the end reference surface 307 are milled after pre-assembly, and the straightness accuracy meets the standard. The alignment table 305 achieves preliminary positioning of straightness through the side reference surface 306 and the reference side surface 303; one group of the corridor boxes 1 approaches another group of the already fixed corridor boxes 1 along the I-beam main steel beam 201, and the coarse positioning slots 308 on one group of the corridor boxes 1 are inserted into the three-level guide positioning columns 309 on the other group of the corridor boxes 1 for further positioning; by setting up a coarse positioning mechanism, preliminary positioning is performed before positioning and assembly, which effectively reduces the difficulty of positioning and improves the assembly efficiency; at the same time, it also provides a smaller error range for further positioning and assembly, thereby improving the work efficiency of positioning and assembly.

[0059] In some embodiments, see Figure 6 , Figure 8 , Fig. 9The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a portable positioning and loading and unloading mechanism 4, which includes a conical boss 401, a conical groove 402, a worm right-angle commutator 403, a screw 404, a ball head surface 405, a limiting hole 406, a fixed pin 407, a pull-in bearing seat 408, a pull-in bearing 409, a pull-in support plate 410, a push-out bearing seat 411, a push-out bearing 412, a push-out support sleeve 413, and a conical support surface 414; the conical boss 401 is fixedly arranged on the first crossbeam 103, and the conical groove 402 is fixedly arranged on the second crossbeam 104, and the two are arranged opposite to each other; the worm right-angle commutator 403 is fixedly arranged on the first crossbeam 103 and arranged opposite to the conical boss 401. The screw rod 404 passes through the worm right-angle commutator 403 and passes through the conical boss 401 and the conical groove 402. A limiting hole 406 is provided at the shaft end of the screw rod close to the conical groove 402, and a ball head surface 405 is provided at the shaft end. The fixed pin shaft 407 is movably arranged in the limiting hole 406. The pull-in bearing seat 408 is fixedly arranged on the second crossbeam 104 and arranged opposite to the conical groove 402. The push-out bearing seat 411 is fixedly arranged on the side of the pull-in bearing seat 408 away from the conical groove 402. 9 is fixedly arranged in the pull-in bearing seat 408, the pull-in support plate 410 is fixedly arranged in the pull-in bearing 409, the push-out bearing 412 is fixedly arranged in the push-out bearing seat 411, and the push-out support sleeve 413 is fixedly arranged in the push-out bearing 412. The push-out support sleeve 413 is provided with a conical support surface 414 on the side close to the ball head surface 405; when in use, the worm right-angle commutator 403 drives the screw rod 404 to rotate and move linearly along its axis, and the fixed pin shaft 407 on the limiting hole 406 pushes the pull-in support plate 410 to move linearly, thereby realizing that the conical surface groove 402 cooperates with the conical surface boss 401 to realize two The corridor box 1 is tightly attached to complete the assembly; when it needs to be dismantled, the worm right-angle commutator 403 drives the screw 404 to rotate and move linearly in the opposite direction of its axis, and the ball head surface 405 is tightly attached to the conical support surface 414, thereby pushing the ejection support sleeve 413 to move linearly, so that the conical groove 402 and the conical boss 401 are disengaged; by setting up a portable positioning and loading and unloading mechanism, the two groups of boxes can be accurately positioned and automatically aligned by pulling the motor screw, and the degree of automation of assembly is improved, the assembly efficiency is improved, and the labor intensity of assembly is reduced; in addition, it provides automated dismantling conditions for later dismantling, thereby improving the modularity of the corridor box.

[0060] In some embodiments, see Fig. 9The pull-in bearing 409 and the push-out bearing 412 are thrust angular contact ball bearings, and the pull-in support plate 410 and the push-out support sleeve 413 are close to the large-surface inner ring;

[0061] In some embodiments, see Figure 2 The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a support column mechanism 5, which includes a base 501, a support arm 502, a support seat 503, a support fixing plate 504, a height adjustment seat 505, and a core column 506; the support arm 502 is provided with multiple groups, which are fixedly arranged on the base 501, the support seat 503 is provided with multiple groups, which are evenly distributed on the support arm 502, the height adjustment seat 505 is fixedly arranged on the support arm 502 away from the side of the base 501, the support fixing plate 504 is fixedly arranged on a group of the support seats 503 close to the height adjustment seat 505, and the core column 506 is movably arranged in the height adjustment seat 505;

[0062] In some embodiments, see Fig.10 The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a height adjustment mechanism 6, which includes a U-shaped limit groove 601, a height limit hole 602, a height limit shaft 603, a semicircular locking protrusion 604, a locking screw 605, and a locking nut 606; a height limit hole 602 is provided on the core column 506, and two corresponding groups of U-shaped limit grooves 601 are provided on the height adjustment seat 505 on both sides corresponding to the height limit hole 602. The height limit shaft 603 passes through the height limit hole 602, and both ends are movably arranged in the U-shaped limit groove 601. Two groups of semicircular locking protrusions 604 are movably arranged in the U-shaped limit groove 601, and the U-shaped limit groove 601 is provided with two groups of semicircular locking protrusions 604 that are movably arranged toward each other. The height limiting shaft 603 fits well, and the locking screw 605 is fixedly arranged on the semicircular locking protrusion 604, and is fixedly arranged on the height adjustment seat 505 by means of a thread, and is locked by means of the locking nut 606; when in use, the locking screws 605 on both sides of the height limiting shaft 603 are loosened to adjust the height of the core column 506. After the height adjustment is completed, the height limiting shaft 603 is limited at both ends by means of the locking screw 605, and is fixed by means of the locking nut 606; by setting up a height adjustment mechanism, the core column can be effectively tightened after the height of the column is changed, and the overall structural stability of the column is guaranteed while ensuring that the column has a height adjustment function.

[0063] In some embodiments, see Figure 11-13The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a wedge-shaped height increaser 7, which includes a base cavity 701, a lifting motor 702, a rotating screw 703, a nut fixing block 704, a guide rail 705, a slider 706, a wedge-shaped push block 707, a trapezoidal push block 708, a roller 709, a short shaft 710, and a lifting platform 711; the base cavity 701 is fixedly arranged on the supporting fixing plate 504, and the lifting motor 702 is fixedly arranged on the base cavity The nut fixing block 704 is movably connected to the rotating screw 703 through the screw nut, and can reciprocate linearly along the axis direction of the rotating screw 703. The guide rail 705 is fixedly arranged in the base cavity 701 and arranged parallel to the rotating screw 703. The wedge-shaped push block 707 is movably arranged on the guide rail 705 through the slider 706, and one end of the wedge-shaped push block 707 is fixedly connected to the nut fixing block 704. Then, the roller 709 is fixedly arranged on the trapezoidal push block 708 through the short shaft 710, and the lifting platform 711 is fixedly arranged on the trapezoidal push block 708; when in use, the lifting motor 702 drives the rotating screw 703 to rotate, thereby realizing the linear motion of the nut fixing block 704 along the axial direction of the rotating screw 703, and driving the wedge-shaped push block 707 to move linearly along the guide rail 705, and the wedge-shaped inclined surface on the wedge-shaped push block 707 pushes the roller 709 on the wedge-shaped push block 707 to realize the lifting and lowering of the trapezoidal push block 708, thereby realizing the lifting and lowering of the lifting platform 711, realizing the linear motion of the core column 506 along the direction of the height adjustment seat 505, and realizing the height adjustment of the support column mechanism 5; by setting a wedge-shaped height increaser, facing the overall assembly error, a wedge-shaped height increaser is set to adjust the height error generated during the assembly process of the corridor box, thereby reducing the high-precision requirements for the modular box and reducing the high-precision assembly and manufacturing costs of the box.

[0064] In some embodiments, see Fig.14The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes an angle adjustment mechanism 8, which includes a corner bracket 801, a hinge hole 802, a reference column 803, an arc-shaped guide groove 804, a fixing pin hole 805, and a support pad 806; the corner bracket 801 is provided with two groups, which are fixedly arranged on both sides of the core column 506 facing each other, and the corner bracket 801 is provided with a hinge hole 802 to realize the movable hinge with the core column 506, and the core column 506 is fixedly provided with two groups of reference columns 803, and the corner bracket 801 is provided with an arc-shaped guide groove 804 at the position of the reference column 803, and is provided with an angle mark; the corner bracket 801 is provided with multiple groups of fixing pin holes 804 05. The support pad 806 is fixedly arranged on one side of the two groups of corner brackets 801 away from the hinge hole 802; the other side of the support pad 806 is fixedly arranged on the bottom surface of the I-beam main steel beam 201; when in use, according to the different heights of the support column mechanism 5, the I-beam main steel beam 201 is at a certain angle to the horizontal plane, and its angle is accurately set relative to the reference column 803 through the angle mark on the arc guide groove 804 to achieve angle adjustment. After adjusting the angle, the support pad 806 is assembled and then the I-beam main steel beam 201 is assembled; by setting the angle adjustment mechanism, the angle adjustment mechanism is set according to the requirements of up and down slopes, thereby improving the overall applicability of the super-long conveying corridor.

[0065] An assembly method for a modular assembly and calibration device for an ultra-long conveying corridor steel structure, comprising the following steps: S1, during assembly, the support column mechanism 5 is assembled first, and after assembling the guide support beam mechanism 2 and completing the accuracy check, the corridor box 1 is installed;

[0066] S2. When assembling the support column mechanism 5, the lifting motor 702 drives the rotating screw 703 to rotate, thereby realizing the linear motion of the nut fixing block 704 along the axis direction of the rotating screw 703, and driving the wedge-shaped push block 707 to linearly move along the guide rail 705. The wedge-shaped inclined surface on the wedge-shaped push block 707 pushes the roller 709 on the wedge-shaped push block 707 to realize the lifting and lowering of the trapezoidal push block 708, thereby realizing the lifting and lowering of the lifting platform 711, realizing the linear motion of the core column 506 along the direction of the height adjustment seat 505, and realizing the height adjustment of the support column mechanism 5;

[0067] S3, loosen the locking screws 605 on both sides of the height limiting shaft 603, adjust the height of the core column 506, and after the height adjustment is completed, limit the height limiting shaft 603 at both ends through the locking screws 605, and lock it with the locking nuts 606 to fix it.

[0068] S4. According to the different heights of the support column mechanism 5, the I-shaped main steel beam 201 is at a certain angle to the horizontal plane. The angle is accurately set relative to the reference column 803 through the angle mark on the arc guide groove 804 to adjust the angle. After the angle is adjusted, the support pad 806 is assembled and then the I-shaped main steel beam 201 is assembled.

[0069] S5. According to the cooperation between the positioning boss 301 and the positioning groove 302, the two groups of the I-beam main steel beams 201 are spliced ​​preferentially. During the splicing, one of the reference side surfaces 303 is used as a reference, and a light aligner is used to calibrate the other I-beam main steel beam 201 to make the straightness of the reference side surfaces 303 on the two I-beam main steel beams 201 meet the standard. Before installing the corridor box body 1, the side reference surface 306 and the end reference surface 307 are milled after pre-assembly, and the straightness accuracy meets the standard. The corridor box body 1 is installed. When the corridor boxes 1 are fixed, the fixed mounting boss 304 cooperates with the upper end face of the I-beam main steel beam 201 through the end face reference surface 307, and the side reference platform 305 cooperates with the reference side face 303 through the side reference surface 306 to achieve preliminary positioning of the straightness; one group of the corridor boxes 1 approaches the other group of the already fixed corridor boxes 1 along the I-beam main steel beam 201, and the rough positioning slots 308 on one group of the corridor boxes 1 are inserted into the three-level guide positioning columns 309 on the other group of the corridor boxes 1 for further positioning;

[0070] S6, the worm right-angle commutator 403 drives the screw rod 404 to rotate and move linearly along its axis, and the fixed pin shaft 407 on the limiting hole 406 pushes the pull-in support plate 410 to move linearly, so that the conical groove 402 and the conical boss 401 cooperate to achieve the close contact of the two corridor boxes 1, and complete the assembly; when it needs to be dismantled, the worm right-angle commutator 403 drives the screw rod 404 to rotate and move linearly in the opposite direction of its axis, and the ball head surface 405 is close to the conical support surface 414, thereby pushing the push-out support sleeve 413 to move linearly, so that the conical groove 402 and the conical boss 401 are out of cooperation;

[0071] Obviously, the above embodiments are merely examples for clearly explaining the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. However, these obvious changes or modifications derived from the spirit of the present invention are still within the protection scope of the present invention.

Claims

1. A modular assembly and calibration device for an ultra-long conveyor corridor steel structure, characterized in that: The corridor box (1) comprises a main support frame (101) composed of side beams (102), a first cross beam (103), a second cross beam (104), and an intermediate cross beam (105), and further comprises a bottom frame (106), a bottom plate (107), an inclined side beam (108), a side plate (109), a top plate (110), and a top beam (111); the first cross beam (103) and the second cross beam (104) are fixedly arranged at opposite ends of two groups of the side beams (102), and a plurality of groups of the intermediate cross beams (105) are evenly arranged in the middle; the bottom frame is fixedly arranged at the lower side of the main support frame (101), and the other A bottom plate (107) is fixedly arranged on the side, a plurality of inclined side beams (108) are arranged and evenly fixedly arranged on two groups of side beams (102), the side plates (109) are fixedly arranged on the two groups of side beams (102), and are arranged in parallel with the inclined side beams (108), and are fixed on the inclined side beams (108), the top plate (110) is fixedly arranged on the upper side of the inclined side beams (108), and is arranged facing the bottom plate (107), and top beams (111) are fixedly arranged at both ends of the top plate (110) near the first cross beam (103) and the second cross beam (104), and are fixedly connected to the inclined side beams (108); A guide support beam mechanism (2) with a preset guide is fixedly arranged on the lower side of the corridor box (1); A rough positioning mechanism (3) for preliminary positioning is fixedly arranged on the corridor box (1); The guide support beam mechanism (2) comprises an I-shaped main steel beam (201); the I-shaped main steel beam (201) is provided in multiple groups, one side of which is fixedly provided on the main support frame (101) on the corridor box body (1); The coarse positioning mechanism (3) comprises a positioning boss (301), a positioning groove (302), a reference side (303), a fixed mounting boss (304), a side reference platform (305), a side reference surface (306), an end reference surface (307), a coarse positioning slot (308), and a three-level guide positioning column (309); one end of the I-beam main steel beam (201) is provided with a positioning boss (301), and the other end facing it is provided with a positioning groove (302) so that the straightness can be initially determined when splicing; a plurality of groups of fixed mounting bosses (304) are provided on the main support frame (101), and a side reference platform (305) is provided on the fixed mounting boss (304), and the side reference platform (305) is provided on the side reference surface (306). The aligning platform (305) is provided with a side reference surface (306), and the fixed mounting boss (304) is provided with an end face reference surface (307). Multiple groups of the fixed mounting bosses (304) fixed to the same I-beam main steel beam (201) have multiple groups of end face reference surfaces (307) at the same height, and multiple groups of the side reference surfaces (306) are coplanar; the side surface of the I-beam main steel beam (201) in contact with the side reference surface (306) is the reference side surface (303); two groups of three-level guide positioning columns (309) are fixedly provided on one side of the two groups of side beams (102) close to the first cross beam (103), and a coarse positioning slot (308) is fixedly opened on the opposite side.

2. The modular assembly and calibration device for the super-long conveyor corridor steel structure according to claim 1 is characterized in that: The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a portable positioning and loading and unloading mechanism (4), which includes a conical boss (401), a conical groove (402), a worm right-angle commutator (403), a screw (404), a ball head surface (405), a limiting hole (406), a fixed pin (407), a pull-in bearing seat (408), a pull-in bearing (409), a pull-in support plate (410), a push-out bearing seat (411), and a push-out bearing (412). 2), a push-out support sleeve (413), and a conical support surface (414); the conical boss (401) is fixedly arranged on the first crossbeam (103), and the conical groove (402) is fixedly arranged on the second crossbeam (104), and the two are arranged opposite to each other; the worm right-angle commutator (403) is fixedly arranged on the first crossbeam (103), and is arranged opposite to the conical boss (401), and the screw (404) passes through the worm right-angle commutator (403) and passes through the conical groove (402). The screw rod has a boss (401) and a conical groove (402); a limiting hole (406) is provided at the shaft end of the screw rod close to the conical groove (402); a ball head surface (405) is provided at the shaft end of the screw rod; the fixing pin (407) is movably arranged in the limiting hole (406); the pull-in bearing seat (408) is fixedly arranged on the second crossbeam (104) and arranged opposite to the conical groove (402); the push-out bearing seat (411) is fixedly arranged on the pull-in bearing seat (408) away from the On one side of the conical groove (402), the pull-in bearing (409) is fixedly arranged in the pull-in bearing seat (408), the pull-in support plate (410) is fixedly arranged in the pull-in bearing (409), the push-out bearing (412) is fixedly arranged in the push-out bearing seat (411), the push-out support sleeve (413) is fixedly arranged in the push-out bearing (412), and a conical support surface (414) is arranged on the side of the push-out support sleeve (413) close to the ball head surface (405).

3. The modular assembly and calibration device for the steel structure of an ultra-long conveying corridor according to claim 2 is characterized in that: The pull-in bearing (409) and the push-out bearing (412) are thrust angular contact ball bearings, and the pull-in support plate (410) and the push-out support sleeve (413) are close to the large-surface inner ring.

4. The modular assembly and calibration device for the steel structure of an ultra-long conveying corridor according to claim 3 is characterized in that: The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a support column mechanism (5), and the support column mechanism (5) includes a base (501), a support arm (502), a support seat (503), a support fixing plate (504), a height adjustment seat (505), and a core column (506); the support arm (502) is provided with a plurality of groups, which are fixedly arranged on the base (501); the support seat (503) is provided with a plurality of groups, which are evenly distributed on the support arm (502); the height adjustment seat (505) is fixedly arranged on a side of the support arm (502) away from the base (501); the support fixing plate (504) is fixedly arranged on a group of the support seats (503) close to the height adjustment seat (505); and the core column (506) is movably arranged in the height adjustment seat (505).

5. The modular assembly and calibration device for the super-long conveyor corridor steel structure according to claim 4 is characterized in that: The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a height adjustment mechanism (6), which includes a U-shaped limit groove (601), a height limit hole (602), a height limit shaft (603), a semicircular locking protrusion (604), a locking screw (605), and a locking nut (606); the core column (506) is provided with a height limit hole (602), and the height adjustment seat (505) on both sides corresponding to the height limit hole (602) is provided with two corresponding sets of U-shaped limit screws (603). The height limiting shaft (603) passes through the height limiting hole (602), and both ends are movably arranged in the U-shaped limiting groove (601). Two groups of semicircular locking protrusions (604) are movably arranged in the U-shaped limiting groove (601) and fit with the height limiting shaft (603). The locking screw (605) is fixedly arranged on the semicircular locking protrusions (604) and fixedly arranged on the height adjustment seat (505) by threads, and is locked by the locking nut (606).

6. The modular assembly and calibration device for the steel structure of an ultra-long conveying corridor according to claim 5 is characterized in that: The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes a wedge-shaped height increaser (7), and the wedge-shaped height increaser (7) includes a base cavity (701), a lifting motor (702), a rotating screw (703), a nut fixing block (704), a guide rail (705), a slider (706), a wedge-shaped push block (707), a trapezoidal push block (708), a roller (709), a short shaft (710), and a lifting platform (711); the base cavity (701) is fixedly arranged on the supporting fixing plate (504), the lifting motor (702) is fixedly arranged on the side wall of the base cavity (701), and is fixedly connected to the rotating screw (703), and the base cavity (701) is fixedly arranged on the side wall of the base cavity (701), and is fixedly connected to the rotating screw (703). The nut fixing block (704) is movably connected to the rotating screw (703) through a screw nut, and reciprocates linearly along the axial direction of the rotating screw (703). The guide rail (705) is fixedly arranged in the base cavity (701) and is arranged parallel to the rotating screw (703). The wedge-shaped push block (707) is movably arranged on the guide rail (705) through the slider (706), and one end of the wedge-shaped push block (707) is fixedly connected to the nut fixing block (704). The roller (709) is fixedly arranged on the trapezoidal push block (708) through the short shaft (710). The lifting platform (711) is fixedly arranged on the trapezoidal push block (708).

7. The modular assembly and calibration device for the steel structure of an ultra-long conveying corridor according to claim 6 is characterized in that: The modular assembly and calibration device for the steel structure of the super-long conveying corridor also includes an angle adjustment mechanism (8), which includes a corner bracket (801), a hinge hole (802), a reference column (803), an arc-shaped guide groove (804), a fixing pin hole (805), and a support pad (806); the corner bracket (801) is provided with two groups, which are fixedly arranged on both sides of the core column (506) facing each other, and the corner bracket (801) is provided with a hinge hole (802) to realize a movable hinge with the core column (506). Two groups of reference columns (803) are fixedly arranged on the core column (506); the corner bracket (801) is provided with an arc-shaped guide groove (804) at the position of the reference column (803) and is provided with an angle mark; the corner bracket (801) is provided with multiple groups of fixing pin holes (805); the support pad (806) is fixedly arranged on the side of the two groups of corner brackets (801) away from the hinge hole (802); the other side of the support pad (806) is fixedly arranged on the bottom surface of the I-beam main steel beam (201).

8. The assembly method of the modular assembly and calibration device for the super-long conveyor corridor steel structure according to claim 7 is characterized in that: The steps include: S1. During assembly, the support column mechanism (5) is assembled first, and after the guide support beam mechanism (2) is assembled and its accuracy is checked, the corridor box (1) is installed; S2. When assembling the support column mechanism (5), the lifting motor (702) drives the rotating screw (703) to rotate, thereby realizing the linear motion of the nut fixing block (704) along the axis direction of the rotating screw (703), and driving the wedge-shaped push block (707) to move linearly along the guide rail (705). The wedge-shaped inclined surface on the wedge-shaped push block (707) pushes the roller (709) on the wedge-shaped push block (707) to realize the lifting and lowering of the trapezoidal push block (708), thereby realizing the lifting and lowering of the lifting platform (711), realizing the linear motion of the core column (506) along the direction of the height adjustment seat (505), and realizing the height adjustment of the support column mechanism (5); S3, loosen the locking screws (605) on both sides of the height limiting shaft (603), adjust the height of the core column (506), and after the height adjustment is completed, limit the height limiting shaft (603) at both ends by the locking screws (605), and lock and fix it by the locking nuts (606); S4, according to the difference in height of the support column mechanism (5), the I-shaped main steel beam (201) is at a certain angle to the horizontal plane, and the angle is accurately set relative to the reference column (803) through the angle mark on the arc guide groove (804) to achieve angle adjustment. After the angle is adjusted, the support pad (806) is assembled and then the I-shaped main steel beam (201) is assembled; S5. Based on the cooperation between the positioning boss (301) and the positioning groove (302), the two groups of I-beam main steel beams (201) are preferentially spliced. During the splicing, one of the reference side surfaces (303) is used as a reference, and a light aligner is used to calibrate the other I-beam main steel beam (201) to be spliced, so that the straightness of the reference side surfaces (303) on the two I-beam main steel beams (201) meets the standard; before installing the corridor box (1), the side reference surface (306) and the end reference surface (307) are milled after pre-assembly, and the straightness accuracy meets the standard, and the corridor box (1) is installed. When the fixed installation boss (304) cooperates with the upper end face of the I-beam main steel beam (201) through the end face reference surface (307), and the side reference platform (305) cooperates with the reference side face (303) through the side reference surface (306) to achieve preliminary positioning of straightness; one group of the corridor boxes (1) approaches the other group of the already fixed corridor boxes (1) along the I-beam main steel beam (201), and the rough positioning slots (308) on one group of the corridor boxes (1) are inserted into the three-level guide positioning columns (309) on the other group of the corridor boxes (1) for further positioning; S6. The worm gear right-angle commutator (403) drives the screw (404) to rotate and move linearly along its axis, and the fixed pin shaft (407) on the limiting hole (406) pushes the pull-in support plate (410) to move linearly, thereby realizing the cooperation between the conical groove (402) and the conical boss (401) to achieve the close contact of the two corridor boxes (1) to complete the assembly; when removal is required, the worm gear right-angle commutator (403) drives the screw (404) to rotate and move linearly in the opposite direction of its axis, and the ball head surface (405) is in close contact with the conical support surface (414), thereby pushing the push-out support sleeve (413) to move linearly, so that the conical groove (402) and the conical boss (401) are out of cooperation.

Citation Information

Patent Citations

  • Assembled corridor

    CN215670055U

  • Apparatus and methods for truss assembly

    CA2946629A1

  • Non-road walking inner track mechanical system for fabricated building construction and construction method

    CN116122595A