Ship lift service gate pull rod shaft dismounting and mounting tool and dismounting and mounting method thereof

By designing the disassembly and assembly tooling of the support mechanism and axial drive mechanism, the difficulty and safety risks of the ship lifting work gate lever shaft in the suspended state are solved, and efficient and safe disassembly and assembly operations are achieved.

CN118905607AInactive Publication Date: 2024-11-08YICHANG THREE GORGES NAVIGATION ENG TECH CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411079189.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

It is difficult to disassemble and assemble the working gate lever shaft of the ship lifter in a suspended state, and the existing methods are inefficient and have safety risks.

Method used

A disassembly and assembly tool including a support mechanism and an axial drive mechanism is designed. The pull rod is limited by the support mechanism, and the axial drive mechanism realizes axial pulling and disassembly, simplifying the disassembly and improving efficiency and safety.

Benefits of technology

It effectively reduces the difficulty of disassembly and assembles the tie rod shaft, improves work efficiency and safety, avoids the risk of brutal construction and shaft drops, and ensures a fast and safe maintenance process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118905607A_ABST
    Figure CN118905607A_ABST
Patent Text Reader

Abstract

The invention provides a ship lift service gate pull rod shaft disassembling and assembling tool and a disassembling and assembling method thereof. The ship lift service gate pull rod shaft disassembling and assembling tool comprises a supporting mechanism used for supporting and limiting the middle of a pull rod. The supporting mechanism is arranged at the thinnest part of the middle part of the pull rod; the supporting mechanism is fixedly connected with upstream and downstream wall surfaces of the side surface of the pull rod through positioning plates at two ends respectively; the axial driving mechanism is used for axially pulling and disassembling the main shaft of the pull rod; the axial driving mechanism comprises a fixed connecting plate, and a semicircular plate is fixedly mounted on the other side of the fixed connecting plate through an inner supporting structure; an adjusting nut is welded to the center of the semicircular plate, an adjusting screw rod is installed at the position of the adjusting nut through thread transmission, a hand wheel is fixed to the outer end of the adjusting screw rod, a pulling plate is rotationally matched with the outer end of the adjusting screw rod through a limiting ring, and jacking columns are symmetrically installed on the outer end face of the pulling plate. And in addition, the structure is simple, the operation is convenient and fast, and the working efficiency and the safety can be effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of disassembling and assembling workpieces, in particular to a disassembling and assembling tool for a pull rod shaft of a working gate of a ship lift and a disassembling and assembling method thereof. Background Art

[0002] The upper and lower gates are passages for ships to enter and exit the ship compartment, and are integral U-shaped structures. The working gates of the upper and lower gates of the ship lift have the function of bearing the water level of the upstream and downstream channels and docking with the ship compartment. The upper and lower gate working gates are both equipped with large-span horizontal small doors that can be opened and closed in a rotating manner. The working gate is a key component in the ship lift used to control the entry and exit of ships in the ship compartment, and has the function of bearing the water level and docking with the ship compartment. It can adapt to the amplitude of the water level, and adapt to the water level changes of the downstream channel through the step-by-step adjustment of the hydraulic hoist. It is arranged at the front end of the upper and lower gates of the ship lift. When passing through the ship, the ship compartment docks with the downstream water area through it. When the upstream working gate is watertight and repaired, the working gate needs to be lowered to the maintenance platform, and the spare pull rod needs to be installed; when the downstream working gate is watertight and repaired, the working gate needs to be lifted to the maintenance height, and the original lifting rod needs to be removed. When installing (removing) the tie rod, the first step is to install (pull out) the tie rod shaft. The shaft between the first section of the boom and the cylinder piston rod lifting head is tightly fitted, and both ends of the tie rod shaft are suspended in the air. The shaft cannot be removed using normal removal methods, so the tie rod shaft is difficult to disassemble and install.

[0003] The original method of dismantling the shaft was to use a 16P sledgehammer to knock the wall side of the shaft in the manned cage, and use a crane hook to hang a sling to protect the other end of the shaft, and finally remove the shaft smoothly through continuous knocking. This method requires a lot of equipment and personnel, the disassembly and assembly method is inefficient, and there are safety risks during the disassembly and assembly process. Summary of the invention

[0004] In order to solve the above technical problems, the purpose of the present invention is to provide a disassembly and assembly tool for the tie rod shaft of the working gate of the ship lift and a disassembly and assembly method thereof. The present invention designs and trial-produces a tie rod disassembly and assembly tool based on the working environment and structural characteristics of the disassembly and assembly of the tie rod of the working gate of the ship lift. The tool includes a supporting mechanism and an axial driving mechanism, which can effectively reduce the difficulty of disassembling and installing the tie rod shaft in a suspended working condition. In addition, the structure is simple and easy to operate, which can effectively improve work efficiency and safety.

[0005] In order to realize the above technical features, the object of the present invention is achieved as follows: a ship lift working gate tie rod shaft disassembly and assembly tool, comprising a support mechanism for supporting and limiting the middle part of the tie rod; the support mechanism is arranged at the thinnest part of the middle part of the tie rod; the support mechanism is fixedly connected to the upstream and downstream walls of the side of the tie rod through positioning plates at both ends; Also included is an axial drive mechanism for axially pulling and disassembling the main shaft of the pull rod; The axial drive mechanism comprises a fixed connecting plate, and a semicircular plate is fixedly mounted on the other side of the fixed connecting plate through an inner supporting structure; An adjusting nut is welded at the center of the semicircular plate, an adjusting screw is installed at the position of the adjusting nut through threaded transmission, a hand wheel is fixed to the outer end of the adjusting screw, and the outer end of the adjusting screw is rotatably matched with a pull plate through a limit ring, and a top column is symmetrically installed on the outer end surface of the pull plate.

[0006] The supporting mechanism includes frame supports arranged in pairs, a U-shaped ear seat is fixed to the middle part of the outer wall of the frame support, a push rod is installed on the U-shaped ear seat through a first nut arranged in pairs, a positioning plate is welded and fixed to the end of the push rod, and an expansion bolt hole for passing the expansion bolt is processed on the positioning plate. The positioning plate is anchored to the upstream and downstream walls through the expansion bolts passing through the expansion bolt holes; an ear plate is provided on the outer wall of the butt end of the frame support, and during installation, the paired ear plates are fixedly connected by a bolt assembly.

[0007] The U-shaped ear seat is fixed on the outer side wall of the frame support by welding.

[0008] The push rod adopts a threaded column at one end of the U-shaped ear seat, and the threaded column and the first nut form a threaded match and are used to adjust the extension length of the push rod.

[0009] The inner support structure comprises L-shaped connecting plates arranged in pairs between the fixed connecting plates and the semicircular plates, and a T-shaped connecting plate is fixedly installed at the middle lower part of the two groups of L-shaped connecting plates.

[0010] The fixed connection plate is an annular plate, on which a plurality of evenly arranged through holes are processed.

[0011] A handle is fixed on the outer wall of the hand wheel.

[0012] A method for disassembling a pull rod shaft of a ship lift working gate, the method being implemented by using any one of the ship lift working gate pull rod shaft disassembly and assembly tools, comprising the following steps: S1.1, raise the working gate cylinders on both sides synchronously and slowly until the suspension rods under the cylinders reach the locking beam position and lock, thus meeting the conditions for shaft removal; S1.2, install the support mechanism to the thinnest part of the middle of the tie rod, use the bolt assembly to connect and tighten the left and right frame supports of the support mechanism, adjust the top rod, push the positioning plate to the upstream and downstream walls of the side of the tie rod, and finally use the expansion bolts to position and fix it; S1.3, drop the axial drive mechanism flatly to the shaft hole on the working gate pull rod, align the through hole of the fixed connecting plate with the hole of the clamping plate bolt on the shaft of the working gate pull rod, and install the bolts to fix the axial drive mechanism to the pull rod; S1.4, turn the hand wheel of the axial drive mechanism clockwise to rotate the adjusting screw to the appropriate position, and use the snap ring to connect the tie rod shaft eye to the top column of the axial drive mechanism; S1.5, after confirming that the connection is firm, turn the hand wheel counterclockwise to unscrew the adjusting screw, pull the working gate tie rod shaft axially out of the shaft hole, enter the supporting structure inside the tooling, and pull the working gate tie rod shaft completely out of the shaft hole; S1.6, lift away the working gate tie rod shaft, and then complete the disassembly of the entire working gate tie rod shaft.

[0013] A method for installing a pull rod shaft of a ship lift working gate, the method being implemented by using the ship lift working gate pull rod shaft disassembly and assembly tool, comprising the following steps: S2.1, hoist the tie rod until it is ready for shaft removal; S2.2, drop the axial drive mechanism flatly to the shaft hole of the working gate tie rod shaft, align the bolt hole of the fixed connection plate with the hole of the clamping plate bolt on the working gate tie rod shaft, and install the bolts to fix the axial drive mechanism to the tie rod; S2.3, transport the working gate pull rod shaft to the inner support structure of the axial drive mechanism; S2.4, add thin sleepers or rubber to adjust the position of the working gate tie rod shaft radially up, down, left, and right, align the working gate tie rod shaft with the hole of the clamping plate bolt, turn the hand wheel to rotate the adjusting screw to the appropriate position, and make the front end plane of the top column face the end face of the shaft; S2.5, after the connection is secure, turn the axial drive mechanism clockwise to screw in the adjusting screw, and push the working gate tie rod shaft axially into the shaft hole until the working gate tie rod shaft is fully pushed to the working position; S2.6, dismantle the axial drive mechanism; S2.7, install the shaft end clamp and clamp bolts; S2.8, the working gate pull rod shaft is installed.

[0014] The present invention has the following beneficial effects: 1. The present invention provides a shaft disassembly and assembly tool, in which the axial drive mechanism can support and stabilize the pull rod shaft to be disassembled (assembled) through the T-shaped connecting plate at the bottom of the tool, and connect the top column with the lifting ring of the pull rod shaft by using a retaining ring, so that when the hand wheel is turned, the top column can be moved axially, and finally the pull rod shaft is pushed (pulled) to move axially to complete the removal or installation operation of the pull rod shaft, which can improve the efficiency of disassembly and assembly of the shaft, avoid rough construction, and ensure rapid maintenance.

[0015] 2. The shaft disassembly and assembly tool provided by the present invention can limit the radial X and Y directions of the shaft, so that the shaft can move axially to avoid radial skewness of the shaft (the part that has not yet entered the shaft hole) during the disassembly (assembly) process. By turning the hand wheel to rotate the screw rod and move it axially, the top column pushes the shaft in for installation or pulls it out for removal, which can improve the safety of the shaft disassembly (assembly) process. The tail deviation safety problem that occurs during the shaft disassembly (assembly) process is eliminated to ensure safety during the disassembly (assembly) process.

[0016] 3. The present invention provides a shaft disassembly and assembly tool, and the support mechanism can support and stabilize the pull rod to be disassembled (assembled) through the T-shaped connecting plate of the tool frame support, and is arranged on the side walls at both ends of the side of the pull rod through expansion bolts, and the posture of the pull rod to be disassembled (assembled) is fixed and positioned in the upstream and downstream directions. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0018] Figure 1 This is a side view of the pull rod shaft to be disassembled according to the present invention.

[0019] Figure 2 This is the front view of the pull rod shaft to be disassembled and assembled according to the present invention.

[0020] Figure 3 It is the front view of the axial drive mechanism of the present invention.

[0021] Figure 4 It is a top view of the axial drive mechanism of the present invention.

[0022] Figure 5 It is the right side view of the axial drive mechanism of the present invention.

[0023] Figure 6 For the present invention Figure 3 Medium AA view.

[0024] Figure 7 It is a three-dimensional diagram of the axial drive mechanism of the present invention.

[0025] Figure 8 It is the front view of the supporting mechanism of the present invention.

[0026] Fig. 9 It is a top view of the support mechanism of the present invention.

[0027] Fig.10 It is the right side view of the supporting mechanism of the present invention.

[0028] Fig.11 It is a three-dimensional diagram of the support mechanism of the present invention.

[0029] Fig.12 This is a preliminary state diagram of the present invention during the disassembly process of the working gate pull rod shaft.

[0030] Fig.13 This is a diagram of the complete exit state of the working gate pull rod shaft during the disassembly process of the present invention.

[0031] Fig.14 The present invention is a flow chart for disassembling the working gate pull rod shaft.

[0032] Fig.15 The present invention is a flow chart for installing the working gate pull rod shaft.

[0033] In the figure: fixed connecting plate 1, T-shaped connecting plate 2, L-shaped connecting plate 3, semicircular plate 4, adjusting screw 5, handwheel 6, handle 7, top column 8, limiting ring 9, pull plate 10, adjusting nut 11, frame support 12, ear plate 13, U-shaped ear seat 14, first nut 15, push rod 16, positioning plate 17, bolt assembly 18, working gate pull rod shaft 19, pull rod shaft lifting eye 20, shaft end clamping plate 21, clamping plate bolt 22, short pull rod 23, long pull rod 24. DETAILED DESCRIPTION

[0034] The embodiments of the present invention are further described below in conjunction with the accompanying drawings.

[0035] Embodiment 1: See also Figure 1-15 , a disassembly and assembly tool for the pull rod shaft of the working gate of a ship lift, including a support mechanism for supporting and limiting the middle part of the pull rod; the support mechanism is arranged at the thinnest part of the middle part of the pull rod; the support mechanism is fixedly connected to the upper and downstream walls of the side of the pull rod through the positioning plates 17 at both ends; and also includes an axial driving mechanism for axially pulling and disassembling the main shaft of the pull rod; the axial driving mechanism includes a fixed connecting plate 1, and a semicircular plate 4 is fixedly installed on the other side of the fixed connecting plate 1 through an internal supporting structure; an adjusting nut 11 is welded at the center of the semicircular plate 4, and an adjusting screw 5 is installed at the position of the adjusting nut 11 through threaded transmission, and a hand wheel 6 is fixed to the outer end of the adjusting screw 5, and a pull plate 10 is rotatably matched with the outer end of the adjusting screw 5 through a limiting ring 9, and a top column 8 is symmetrically installed on the outer end surface of the pull plate 10. Improve the disassembly and assembly efficiency and construction safety and reliability of the pull rod of the working gate of the ship lift. By adopting the tooling of the present invention through basic positioning and driving mechanism, the disassembly and assembly process is simplified, the construction difficulty and potential safety risks are reduced, and the risks of rough construction and the pull rod shaft falling are eliminated, ensuring the safe and stable construction.

[0036] Furthermore, the support mechanism includes frame supports 12 arranged in pairs, a U-shaped ear seat 14 is fixed to the middle part of the outer wall of the frame support 12, a push rod 16 is installed on the U-shaped ear seat 14 through a first nut 15 arranged in pairs, a positioning plate 17 is welded and fixed to the end of the push rod 16, and an expansion bolt hole for passing the expansion bolt is processed on the positioning plate 17. The positioning plate 17 is anchored to the upstream and downstream walls through the expansion bolts passing through the expansion bolt holes; the outer wall of the butt end of the frame support 12 is provided with an ear plate 13. When installed, the paired ear plates 13 are fixedly connected by bolt assemblies 18. Through the above-mentioned support mechanism Furthermore, the U-shaped ear seat 14 is fixed by welding to the outer side wall of the frame support 12. The U-shaped ear seat 14 facilitates the extension adjustment of the top rod 16 to adapt to lock chambers of different widths, thereby enhancing its adaptability.

[0037] Furthermore, the push rod 16 has a threaded column at one end located at the U-shaped ear seat 14, and the threaded column is threadedly matched with the first nut 15 and is used to adjust the extension length of the push rod 16. Through the above-mentioned threaded column, it is convenient to form a threaded match with the first nut 15, and then it is convenient to adjust the extension length and position of the push rod 16.

[0038] Furthermore, the inner support structure includes L-shaped connecting plates 3 arranged in pairs between the fixed connecting plate 1 and the semicircular plate 4, and a T-shaped connecting plate 2 is fixedly installed in the middle lower part of the two groups of L-shaped connecting plates 3. The above-mentioned inner support structure facilitates the support of the working gate pull rod shaft 19 during the disassembly process, and also facilitates stable and reliable support during the subsequent disassembly process.

[0039] Furthermore, the fixed connecting plate 1 is an annular plate, on which a plurality of evenly arranged through holes 101 are processed. The annular plate is conveniently matched with the hole position of the clamping bolt 22 of the pull rod, and the axial drive mechanism is fixed on the outer wall of the pull rod and installed in a suspended manner, ensuring the convenience and reliability of subsequent disassembly operations.

[0040] Furthermore, a handle 7 is fixed on the outer wall of the hand wheel 6. The handle 7 facilitates the subsequent manual rotation of the hand wheel 6, and then the hand wheel 6 drives the adjusting screw 5, and the threaded transmission between the adjusting screw 5 and the adjusting nut 11 drives the pull plate 10, and then the pull plate 10 drives the top column 8.

[0041] Embodiment 2: A method for disassembling a pull rod shaft of a ship lift working gate, the method being implemented by using any one of the ship lift working gate pull rod shaft disassembly and assembly tools, comprising the following steps: S1.1, raise the working gate cylinders on both sides synchronously and slowly until the suspension rods under the cylinders reach the locking beam position and lock, thus meeting the conditions for shaft removal; S1.2, install the support mechanism to the thinnest part of the middle of the tie rod, use the bolt assembly 18 to connect and tighten the left and right frame supports 12 of the support mechanism, adjust the top rod 16, push the positioning plate 17 to the upstream and downstream walls of the side of the tie rod, and finally use the expansion bolts to position and fix it; S1.3, drop the axial drive mechanism flatly to the shaft hole on the working gate pull rod, align the through hole 101 of the fixed connecting plate 1 with the hole of the clamping plate bolt 22 on the working gate pull rod shaft 19, and install the bolts to fix the axial drive mechanism to the pull rod; S1.4, turn the hand wheel 6 of the axial drive mechanism clockwise to rotate the adjusting screw 5 to a suitable position, and use the snap ring 25 to connect the tie rod shaft lifting ring 20 to the top column 8 of the axial drive mechanism; S1.5, after confirming that the connection is stable, turn the hand wheel 6 counterclockwise to unscrew the adjusting screw 5, pull the working gate tie rod shaft 19 axially out of the shaft hole, enter the supporting structure inside the tooling, and pull the working gate tie rod shaft 19 completely out of the shaft hole; S1.6, lift the working gate tie rod shaft 19 away, thereby completing the disassembly of the entire working gate tie rod shaft 19.

[0042] Embodiment 3: A method for installing a pull rod shaft of a ship lift working gate, the method being implemented by using the ship lift working gate pull rod shaft disassembly and assembly tool, comprising the following steps: S2.1, hoist the tie rod until it is ready for shaft removal; S2.2, drop the axial drive mechanism flatly to the shaft hole of the working gate tie rod shaft 19, align the bolt hole of the fixed connecting plate 1 with the hole of the clamping plate bolt 22 on the working gate tie rod shaft 19, and install the bolts to fix the axial drive mechanism to the tie rod; S2.3, transport the working gate pull rod shaft 19 to the inner support structure of the axial drive mechanism; S2.4, add thin sleepers or rubber to adjust the position of the working gate tie rod shaft 19 radially up, down, left, and right, align the working gate tie rod shaft 19 with the hole of the clamping plate bolt 22, turn the hand wheel 6 to rotate the adjusting screw 5 to a suitable position, and make the front end plane of the top column 8 face the end face of the shaft; S2.5, after the connection is secure, turn the axial drive mechanism clockwise to screw in the adjusting screw 5, and push the working gate tie rod shaft 19 axially into the shaft hole until the working gate tie rod shaft 19 is completely pushed to the working position; S2.6, dismantle the axial drive mechanism; S2.7, install the shaft end clamping plate 21 and the clamping plate bolts 22; S2.8, the working gate pull rod shaft 19 is installed.

Claims

1. A disassembly and assembly tool for the pull rod shaft of a ship lift working gate, characterized in that: It comprises a support mechanism for supporting and limiting the middle part of the pull rod; the support mechanism is arranged at the thinnest part of the middle part of the pull rod; the support mechanism is fixedly connected to the upstream and downstream walls of the side of the pull rod through positioning plates (17) at both ends; Also included is an axial drive mechanism for axially pulling and disassembling the main shaft of the pull rod; The axial drive mechanism comprises a fixed connecting plate (1), and a semicircular plate (4) is fixedly mounted on the other side of the fixed connecting plate (1) via an internal support structure; An adjusting nut (11) is welded to the center of the semicircular plate (4), an adjusting screw (5) is installed at the position of the adjusting nut (11) through threaded transmission, a hand wheel (6) is fixed to the outer end of the adjusting screw (5), the outer end of the adjusting screw (5) is rotatably matched with a pull plate (10) through a limit ring (9), and a top column (8) is symmetrically installed on the outer end surface of the pull plate (10).

2. The disassembly and assembly tool for the pull rod shaft of the working gate of the ship lift according to claim 1, characterized in that: The support mechanism comprises frame supports (12) arranged in pairs, a U-shaped ear seat (14) is fixed to the middle part of the outer wall of the frame support (12), a push rod (16) is installed on the U-shaped ear seat (14) through a first nut (15) arranged in pairs, a positioning plate (17) is welded and fixed to the end of the push rod (16), an expansion bolt hole for passing the expansion bolt is processed on the positioning plate (17), and the positioning plate (17) is anchored to the upstream and downstream wall surfaces through the expansion bolts passing through the expansion bolt holes; an ear plate (13) is arranged on the outer wall of the butt end of the frame support (12), and when installed, the paired ear plates (13) are fixedly connected by a bolt assembly (18).

3. The disassembly and assembly tool for the pull rod shaft of the working gate of the ship lift according to claim 2, characterized in that: The U-shaped ear seat (14) is fixed to the outer side wall of the frame support (12) by welding.

4. The disassembly and assembly tool for the pull rod shaft of the working gate of the ship lift according to claim 2, characterized in that: The push rod (16) has a threaded column at one end located on the U-shaped ear seat (14). The threaded column and the first nut (15) form a threaded fit and are used to adjust the extension length of the push rod (16).

5. The disassembly and assembly tool for the pull rod shaft of the working gate of the ship lift according to claim 1, characterized in that: The inner support structure comprises L-shaped connecting plates (3) arranged in pairs between the fixed connecting plates (1) and the semicircular plates (4), and a T-shaped connecting plate (2) is fixedly mounted in the middle lower part of the two groups of L-shaped connecting plates (3).

6. The disassembly and assembly tool for the pull rod shaft of the working gate of the ship lift according to claim 5, characterized in that: The fixed connection plate (1) is an annular plate, on which a plurality of evenly arranged through holes (101) are machined.

7. The disassembly and assembly tool for the pull rod shaft of the working gate of the ship lift according to claim 6, characterized in that: A handle (7) is fixed on the outer wall of the hand wheel (6).

8. A method for disassembling the pull rod shaft of a ship lift working gate, characterized in that: The method is implemented by using a ship lift working gate tie rod shaft disassembly tool as described in any one of claims 1 to 7, and comprises the following steps: S1.1, raise the working gate cylinders on both sides synchronously and slowly until the suspension rods under the cylinders reach the locking beam position and lock, thus meeting the conditions for shaft removal; S1.2, install the support mechanism to the thinnest part of the middle of the tie rod, use the bolt assembly (18) to connect and tighten the left and right frame supports (12) of the support mechanism, adjust the push rod (16), push the positioning plate (17) to the upstream and downstream walls of the side of the tie rod, and finally use expansion bolts to position and fix it; S1.3, drop the axial drive mechanism flatly to the shaft hole on the working gate pull rod, align the through hole (101) of the fixed connection plate (1) with the hole of the clamping plate bolt (22) on the working gate pull rod shaft (19), and install the bolts to fix the axial drive mechanism to the pull rod; S1.4, turn the hand wheel (6) of the axial drive mechanism clockwise to rotate the adjusting screw (5) to a suitable position, and use the snap ring (25) to connect the tie rod shaft lifting ring (20) to the top column (8) of the axial drive mechanism; S1.5, after confirming that the connection is secure, turn the hand wheel (6) counterclockwise to unscrew the adjusting screw (5), pull the working gate tie rod shaft (19) axially out of the shaft hole, enter the supporting structure inside the tooling, and pull the working gate tie rod shaft (19) completely out of the shaft hole; S1.6, lift the working gate tie rod shaft (19) away, thereby completing the disassembly of the entire working gate tie rod shaft (19).

9. A method for installing a pull rod shaft of a ship lift working gate, characterized in that: The method is implemented by using a ship lift working gate tie rod shaft disassembly tool as described in any one of claims 1 to 7, and comprises the following steps: S2.1, hoist the tie rod until it is ready for shaft removal; S2.2, drop the axial drive mechanism flatly to the axial hole of the working gate tie rod shaft (19), align the bolt hole of the fixed connection plate (1) with the hole of the clamping plate bolt (22) on the working gate tie rod shaft (19), and install the bolts to fix the axial drive mechanism to the tie rod; S2.3, moving the working gate pull rod shaft (19) to the inner support structure of the axial drive mechanism; S2.4, add thin sleepers or rubber to adjust the position of the working gate tie rod shaft (19) in the radial direction, align the working gate tie rod shaft (19) with the hole of the clamping plate bolt (22), turn the hand wheel (6) to rotate the adjusting screw (5) to a suitable position, and make the front end plane of the top column (8) face the end face of the shaft; S2.5, after the connection is secure, turn the axial drive mechanism clockwise to screw in the adjusting screw (5), and push the working gate tie rod shaft (19) axially into the shaft hole until the working gate tie rod shaft (19) is completely pushed to the working position; S2.6, dismantle the axial drive mechanism; S2.7, install the shaft end clamp (21) and the clamp bolt (22); S2.8, the working gate tie rod shaft (19) is installed.