Water drain pipe and installation method and maintenance method thereof
By pre-buried the drain pipe section during the pouring of the bridge body and sealed and connected with the cement and asphalt layers, the problem of poor sealing effect of existing drain pipes is solved, and a more efficient construction and maintenance process is achieved.
Patent Information
- Application Number
- CN202410967680.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-11-08
AI Technical Summary
During the installation of existing bridge drainage pipes, the sealing effect between the reserved holes or rear drilled holes and the outer surface of the drainage pipe is poor, which increases the construction steps and causes inconvenience in maintenance. In addition, concrete protection is found in the beam body at the drainage pipe position. Layer peeling and steel bar corrosion problems.
The embedded section is used to pre-embed and fixed when pouring the bridge body. The inlet section and the grate section are paved and sealed with the cement and asphalt layer. The outlet section is sealed with the embedded section to form an assembled drain pipe, which simplifies the installation and maintenance process. .
The sealing effect between the drain pipe and the bridge body is improved, the construction period is shortened, the maintenance cost and time is reduced, and the overall construction efficiency and maintenance efficiency are improved.
Smart Images

Figure CN118911005A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of highway bridge engineering, and more specifically, relates to a drainage pipe and an installation method and a maintenance method thereof. Background Art
[0002] Conventional bridge drainage pipes are vertical and horizontal. The vertical drainage pipe drainage system is more suitable for use because of its strong drainage capacity. In order to quickly drain the water on the bridge surface and prevent rainwater from stagnating on the bridge deck and seeping into the beam body to affect the durability of the bridge, in addition to setting up longitudinal and transverse slope drainage on the bridge deck, a certain number of drainage pipes need to be set up on the bridge deck when designing the bridge to form a complete drainage system.
[0003] At present, the material of conventional vertical drain pipes on bridges is cast iron or PVC pipes, which are installed as a whole. The installation of integrated drain pipes requires reserving channels when the beam is prefabricated, or drilling holes on the beam flanges after the beam is erected, and then installing the drain pipes. Finally, the inner wall of the hole and the outer wall of the drain pipe are sealed by pouring concrete.
[0004] The sealing between the inner wall of the reserved hole or the post-drilled hole and the outer surface of the drain pipe increases the construction steps of the drain pipe installation, and the sealing effect is poor. After a long time, water seepage from the outer wall of the drain pipe causes rust, cracking, and local peeling of the concrete on the flange of the side beam and the outer side of the web. What's worse, the beam body at the location of the drain pipe has large-area peeling of the concrete protective layer and serious rust of the steel bars. When repairing and replacing the drain pipe, the integrated drain pipe needs to be completely dismantled and reinstalled, which makes it inconvenient to repair. Summary of the invention
[0005] The purpose of the present invention is to provide a drain pipe and its installation method and maintenance method, so as to solve the technical problems in the prior art that the sealing between the inner wall of the reserved hole or the post-drilled hole and the outer surface of the drain pipe increases the construction steps of the drain pipe installation, and the sealing effect is poor, which poses a safety hazard to the bridge. When repairing and replacing the drain pipe, the integrated drain pipe needs to be completely dismantled and reinstalled, resulting in inconvenience in its maintenance.
[0006] To achieve the above-mentioned purpose, in a first aspect, the technical solution adopted by the present invention is: to provide a drainage pipe for installation on a bridge body, wherein a cement layer and an asphalt layer are sequentially laid on the top surface of the bridge body, and the drainage pipe comprises:
[0007] The embedded section is used to be embedded in the bridge body when the bridge body is cast;
[0008] An inlet section is arranged in the cement layer, and the bottom of the inlet section is sealed and connected to the embedded section;
[0009] A grate section is arranged in the asphalt layer, and the bottom of the grate section is sealed and connected to the inlet section;
[0010] An outlet section is arranged below the bridge body, and a top of the outlet section is sealed and connected to the embedded section; and
[0011] The main drainage section is arranged below the bridge body, and the top of the main drainage section is sealed and connected to the outlet section.
[0012] In combination with the first aspect, in a possible implementation manner, the embedded segment includes:
[0013] A pre-buried pipe, pre-buried in the bridge body, and
[0014] The lower edge sealing stiffening rib is arranged around the bottom end of the outer peripheral surface of the embedded pipe.
[0015] In combination with the first aspect, in a possible implementation manner, the embedded segment further includes:
[0016] An upper edge stiffening rib is disposed around the top end of the outer peripheral surface of the embedded pipe; and
[0017] The middle stiffening rib is arranged around the middle part of the outer peripheral surface of the embedded pipe.
[0018] In combination with the first aspect, in a possible implementation manner, the embedded section and the inlet section, and the embedded section and the outlet section are both threadedly connected.
[0019] In combination with the first aspect, in a possible implementation manner, the embedded section is an internal thread, and the inlet section and the outlet section are external threads.
[0020] In combination with the first aspect, in a possible implementation, the drainage main section and the outlet section, as well as the drainage main section and the bridge body are connected via fixed pipe clamps.
[0021] In combination with the first aspect, in a possible implementation manner, the drainage main body section includes:
[0022] A vertical drainage pipe, disposed below the bridge body and sealed to the bottom of the outlet section; and
[0023] A multi-directional elbow connecting pipe is arranged below the bridge body and is sealed and connected to the vertical drainage pipe.
[0024] In a second aspect, the present invention further provides a method for installing a drain pipe, using the drain pipe described above, comprising the following steps:
[0025] A. Beam prefabrication stage: the embedded section is placed at the designated position inside the bridge body during pouring and positioned, and the embedded section is fixed when the bridge body is poured and formed;
[0026] B. Bridge deck cement paving stage: install the entrance section on top of the embedded section, seal the connection between the two, and then pave and pour the cement layer;
[0027] C. Bridge deck asphalt paving stage: install the grate section on the top of the entrance section, seal the connection between the two, and then pave and pour the asphalt layer;
[0028] D. Drainage system installation stage: seal the outlet section to the bottom of the embedded section, then connect the top of the drainage main section to the bottom of the outlet section and seal it to form a complete drainage system.
[0029] In combination with the second aspect, in a possible implementation method, during the beam prefabrication stage and the bridge deck cement paving stage, the embedded section and the entrance section are lined with support inner molds, and the support inner molds are removed after the beam is cast or the cement layer is paved.
[0030] In a third aspect, the present invention further provides a method for repairing a drain pipe, using the drain pipe described above and replacing it by the drain pipe installation method described above, comprising the following steps:
[0031] A. Dismantling of existing drainage pipes: After dismantling the damaged existing drainage pipes, grind the cross sections of the existing bridge body and the holes in the cement layer and remove the rust from the steel bars. Place the new embedded sections in the holes of the bridge body, and fill the gap between the inner wall of the hole of the bridge body and the outer wall of the embedded section with micro-expansion cement mortar or glue.
[0032] B. Installation of other components: After the embedded section is installed, install the inlet section into the cement layer and seal it with the embedded section, install the grate section into the asphalt layer and seal it with the inlet section, and after the elevation of the inlet section and the grate section is adjusted, fill the gap between the inlet section and the cement layer, and the gap between the grate section and the asphalt layer with cement mortar to make it dense;
[0033] C. Docking with the existing drainage system: seal the outlet section to the bottom of the embedded section, and seal the outlet section to the existing drainage main section to complete the repair and replacement of the drain pipe.
[0034] The beneficial effect of the drain pipe provided by the present invention is that: compared with the prior art, the present invention embeds and fixes the embedded section together when the bridge body is cast, which does not require subsequent drilling of the bridge body and improves the sealing effect between the embedded section and the bridge body. The installation of the inlet section is constructed together with the cement layer, and the installation of the grate section is constructed together with the asphalt layer. The installation of the drain pipe can be completed during the bridge construction process as a whole, shortening the construction period. When the drain pipe located inside the bridge needs to be repaired and replaced, the drainage main section can be retained. The design of the assembled drain pipe can reduce maintenance costs and improve maintenance efficiency.
[0035] The beneficial effect of the installation method of the drain pipe provided by the present invention is that compared with the prior art, the present invention forms and fixes the embedded section together during the pouring stage of the bridge body, reducing the subsequent drilling and sealing steps, and the inlet section is constructed together with the bridge deck cement paving, and the outlet section is constructed together with the bridge deck asphalt paving, thereby improving the overall construction efficiency.
[0036] The beneficial effect of the repair method of the drain pipe provided by the present invention is that compared with the prior art, when repairing and replacing the drain pipe, the present invention directly removes the damaged part in the bridge body, and installs a new embedded section after processing the holes, so that it is sealed and fixed to the bridge body, and then the inlet section, the grate section and the outlet section are installed in turn, and finally the outlet section is sealed and connected with the existing drainage main section to form a new drainage system with low replacement cost and high efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0038] Figure 1 A schematic diagram of the installation of a drain pipe provided in an embodiment of the present invention;
[0039] Figure 2 A schematic diagram of the structure of a drain pipe provided in an embodiment of the present invention;
[0040] Figure 3 A schematic diagram of the structure of the embedded section during installation provided by an embodiment of the present invention;
[0041] Figure 4 A schematic diagram of the structure of the embedded section during maintenance and replacement provided by an embodiment of the present invention.
[0042] Among them, the reference numerals in the figures are as follows:
[0043] 1. Bridge body; 2. Cement layer; 3. Asphalt layer; 4. Embedded section; 41. Embedded pipe; 42. Lower edge sealing stiffening rib; 43. Upper edge stiffening rib; 44. Middle stiffening rib; 5. Inlet section; 6. Grate section; 61. Grate pipe; 62. Grate; 7. Outlet section; 8. Drainage main section; 81. Vertical drainage pipe; 82. Multi-directional elbow connecting pipe; 9. Fixed pipe clamp. DETAILED DESCRIPTION
[0044] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present invention clearer, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the described embodiments are only part of the embodiments of the present application, rather than all the embodiments, and the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of this application.
[0045] The drain pipe and its installation method and maintenance method provided by the present invention are now described.
[0046] like Figure 1 and Figure 2 As shown, a first embodiment of the present invention provides a drain pipe for installation on a bridge body 1, wherein a cement layer 2 and an asphalt layer 3 are sequentially laid on the top surface of the bridge body 1, and the drain pipe comprises an embedded section 4, an inlet section 5, a grate section 6, an outlet section 7 and a drainage main section 8; the embedded section 4 is used to be embedded in the bridge body 1 when the bridge body 1 is cast; the inlet section 5 is arranged in the cement layer 2, and the bottom of the inlet section 5 is sealed and connected to the embedded section 4; the grate section 6 is arranged in the asphalt layer 3, and the bottom of the grate section 6 is sealed and connected to the inlet section 5; the outlet section 7 is arranged below the bridge body 1, and the top of the outlet section 7 is sealed and connected to the embedded section 4; the drainage main section 8 is arranged below the bridge body 1, and the top of the drainage main section 8 is sealed and connected to the outlet section 7.
[0047] Specifically, in this embodiment, the embedded section 4, the inlet section 5, the grate section 6, the outlet section 7 and the drainage main section 8 are all circular tubular structures.
[0048] Compared with the prior art, the drain pipe provided in the present embodiment embeds and fixes the embedded section 4 together when the bridge body 1 is cast, which does not require subsequent drilling of holes in the bridge body 1 and improves the sealing effect between the embedded section 4 and the bridge body 1. The installation of the inlet section 5 is constructed together with the cement layer 2, and the installation of the grate section 6 is constructed together with the asphalt layer 3. The installation of the drain pipe can be completed during the bridge construction process, shortening the construction period. When the drain pipe located inside the bridge needs to be repaired and replaced, the drainage main section 8 can be retained. The design of the assembled drain pipe can reduce maintenance costs and improve maintenance efficiency.
[0049] like Figure 2 As shown, a specific implementation mode provided by the present invention based on the first implementation mode is as follows:
[0050] The embedded section 4 includes an embedded pipe 41 and a lower edge sealing stiffening rib 42 . The embedded pipe 41 is embedded in the bridge body 1 , and the lower edge sealing stiffening rib 42 is arranged around the bottom end of the outer peripheral surface of the embedded pipe 41 .
[0051] The setting of the lower edge sealing stiffening rib 42 can, on the one hand, strengthen the strength of the embedded pipe 41, and on the other hand, facilitate the fixation of the embedded section 4 when the bridge body 1 is cast and prefabricated, and can also improve the sealing effect between the bottom of the embedded pipe 41 and the bridge body 1.
[0052] Furthermore, the embedded section 4 further includes an upper edge stiffening rib 43 and a middle stiffening rib 44 . The upper edge stiffening rib 43 is disposed around the top end of the outer circumference of the embedded tube 41 ; the middle stiffening rib 44 is disposed around the middle of the outer circumference of the embedded tube 41 .
[0053] The provision of the upper edge stiffening ribs 43 and the middle stiffening ribs 44 further improves the strength of the embedded pipe 41 and further facilitates the positioning of the embedded section 4 when the bridge body 1 is cast and prefabricated.
[0054] like Figure 2 As shown, a specific implementation mode provided by the present invention based on the first implementation mode is as follows:
[0055] The embedded pipe 41 and the inlet section 5 as well as the embedded pipe 41 and the outlet section 7 are both connected by threads.
[0056] Furthermore, the embedded pipe 41 is internally threaded, and the inlet section 5 and the outlet section 7 are externally threaded. The top pipe opening of the inlet section 5 is 1-2 cm lower than the upper surface of the cement layer 2.
[0057] The two ends of the embedded pipe 41 are respectively connected to the inlet section 5 and the outlet section 7 by threads, which can not only ensure the connection strength and sealing, but also improve the height adjustment accuracy of the inlet section 5 and the outlet section 7, and improve the stability during the installation of subsequent pipe sections.
[0058] The setting of the embedded pipe 41 as an internal thread can prevent the prefabrication and casting of the bridge body 1 from affecting the thread, and facilitates the screw-in connection of the inlet section 5 and the outlet section 7.
[0059] like Figure 1 to Figure 2 As shown, a specific implementation mode provided by the present invention based on the first implementation mode is as follows:
[0060] The drainage main section 8 and the outlet section 7 as well as the drainage main section 8 and the bridge body 1 are connected via fixed pipe clamps 9, which improves the installation strength and stability of the drainage main section 8.
[0061] like Figure 1 to Figure 2 As shown, a specific implementation mode provided by the present invention based on the first implementation mode is as follows:
[0062] The drainage main section 8 includes a vertical drainage pipe 81 and a multi-directional elbow pipe 82. The vertical drainage pipe 81 is arranged below the bridge body 1 and is sealed and connected to the bottom of the outlet section 7; the multi-directional elbow pipe 82 is arranged below the bridge body 1 and is sealed and connected to the vertical drainage pipe 81. The drainage efficiency of the drainage system is improved.
[0063] like Figure 2 As shown, a specific implementation mode provided by the present invention based on the first implementation mode is as follows:
[0064] The grate water section 6 includes a grate water pipe 61 and a grate 62 . The bottom of the grate water pipe 61 is sealedly connected to the top of the inlet section 5 , and the grate 62 is fixed on the top of the grate water pipe 61 .
[0065] Furthermore, in this embodiment, the opening of the grate water pipe 61 is 1-2 cm lower than the upper surface of the asphalt layer 3, an annular water-sealing glue is provided between the bottom of the grate water pipe 61 and the top of the inlet pipe, and the grate 62 is fixed to the opening of the grate water pipe 61 by adhesive glue. The construction efficiency is high and the sealing effect between the grate water pipe 61 and the inlet section 5 is good.
[0066] like Figures 1 to 3 As shown, based on the same inventive concept, the second embodiment of the present invention provides a method for installing a drain pipe, comprising the following steps:
[0067] A. Beam prefabrication stage: the embedded section 4 is placed at the designated position inside the bridge body 1 when it is cast, and is positioned by the steel bars during the prefabrication of the bridge body 1 and the lower edge sealing stiffening ribs 42, upper edge stiffening ribs 43 and middle stiffening ribs 44 fixed on the embedded section 4. The embedded section 4 is connected and fixed when the bridge body 1 is cast;
[0068] B. Bridge deck cement paving stage: spirally install the inlet section 5 to the top of the embedded section 4, wrap the water-sealing tape around the connection between the two and set a ring-shaped water-tight strip, and then pave and pour the cement layer 2;
[0069] C. Bridge deck asphalt paving stage: install the grate section 6 on the top of the inlet section 5, set an annular water-sealing glue at the connection between the two, and then pave and pour the asphalt layer 3;
[0070] D. Drainage system assembly stage: seal the outlet section 7 to the bottom of the embedded section 4, then connect the top of the drainage main section 8 to the bottom of the outlet section 7 and set sealant, fix the drainage main section 8 by fixing the pipe clamp 9 to form a complete drainage system.
[0071] A specific implementation mode provided by the present invention based on the second implementation mode is as follows:
[0072] During the beam body prefabrication stage and the bridge deck cement paving stage, the embedded section 4 and the entrance section 5 are lined with supporting inner molds. After the beam body is cast or the cement layer 2 is paved, the supporting inner molds are taken out.
[0073] The provision of the supporting inner mold can reduce the damage to the embedded section 4 and the entrance section 5 caused by concrete vibration, thereby improving the stability and safety of the embedded section 4 and the entrance section 5.
[0074] Compared with the prior art, the installation method of the drainage pipe provided in the present embodiment forms and fixes the embedded section 4 together during the pouring stage of the bridge body 1, thereby reducing the subsequent drilling and sealing steps, and the inlet section 5 is constructed together with the bridge deck cement pavement, and the outlet section 7 is constructed together with the bridge deck asphalt pavement, thereby improving the overall construction efficiency.
[0075] like Figure 1 , Figure 2 and Figure 4 As shown, based on the same inventive concept, the third embodiment of the present invention provides a method for repairing a drain pipe, comprising the following steps:
[0076] A. Dismantling of existing drainage pipes: After dismantling the damaged existing drainage pipes, the holes of the existing bridge body 1 and cement layer 2 are polished and the steel bars are derusted, and a new embedded section 4 is placed in the hole of the bridge body 1. The new embedded section 4 includes an embedded pipe 41 and a lower edge sealing stiffening rib 42, which is inserted into the hole from the bottom of the bridge body 1 upwards. The upper edge stiffening rib 43 and the middle stiffening rib 44 are removed for easy installation, and the gap between the inner wall of the hole of the bridge body 1 and the outer wall of the embedded section 4 is filled with micro-expansion cement mortar or glued;
[0077] B. Installation of other components: After the embedded section 4 is installed, the inlet section 5 is installed in the cement layer 2 and sealed with the embedded section 4, and the grate section 6 is installed in the asphalt layer 3 and sealed with the inlet section 5. After the elevation adjustment of the inlet section 5 and the grate section 6 is completed, the gap between the inlet section 5 and the cement layer 2 and the gap between the grate section 6 and the asphalt layer 3 are filled with cement mortar for compaction;
[0078] C. Docking with the existing drainage system: seal the outlet section 7 to the bottom of the embedded section 4, and seal the outlet section 7 to the existing drainage main section 8 to complete the maintenance and replacement of the drain pipe.
[0079] Compared with the prior art, the repair method for the drain pipe provided in the present embodiment is that when repairing and replacing the drain pipe, the damaged part in the bridge body 1 is directly removed, and the new embedded section 4 is installed after the holes are processed so that it is sealed and fixed to the bridge body 1. Then the inlet section 5, the grate section 6 and the outlet section 7 are installed in turn, and finally the outlet section 7 is sealed and connected with the existing drainage main section 8 to form a new drainage system with low replacement cost and high efficiency.
[0080] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A drainage pipe, used for installation on a bridge body (1), wherein the top surface of the bridge body (1) is sequentially paved with a cement layer (2) and an asphalt layer (3), characterized in that: The drain pipe comprises: The embedded section (4) is used to be embedded in the bridge body (1) when the bridge body (1) is cast; An inlet section (5) is arranged in the cement layer (2), and the bottom of the inlet section (5) is sealed and connected to the embedded section (4); A water grate section (6) is arranged in the asphalt layer (3), and the bottom of the water grate section (6) is sealed and connected to the inlet section (5); An outlet section (7) is arranged below the bridge body (1), and the top of the outlet section (7) is sealed and connected to the embedded section (4); and A drainage main body section (8) is arranged below the bridge body (1), and the top of the drainage main body section (8) is sealed and connected to the outlet section (7).
2. The drain pipe according to claim 1, characterized in that: The embedded section (4) comprises: A pre-buried pipe (41) is pre-buried in the bridge body (1), and The lower edge sealing stiffening rib (42) is arranged around the bottom end of the outer peripheral surface of the embedded pipe (41).
3. The drain pipe according to claim 2, characterized in that: The embedded section (4) further comprises: An upper edge stiffening rib (43) is disposed around the top end of the outer peripheral surface of the embedded pipe (41); and The middle stiffening rib (44) is arranged around the middle of the outer peripheral surface of the embedded pipe (41).
4. The drain pipe according to claim 1, characterized in that: The embedded section (4) and the inlet section (5), and the embedded section (4) and the outlet section (7) are both connected by threads.
5. The drain pipe according to claim 4, characterized in that: The embedded section (4) is internally threaded, and the inlet section (5) and the outlet section (7) are externally threaded.
6. The drain pipe according to claim 1, characterized in that: The drainage main section (8) and the outlet section (7), as well as the drainage main section (8) and the bridge body (1) are connected via fixed pipe clamps (9).
7. The drain pipe according to claim 1, characterized in that: The drainage main body section (8) comprises: a vertical drainage pipe (81), arranged below the bridge body (1) and sealedly connected to the bottom of the outlet section (7); and A multi-directional elbow pipe (82) is arranged below the bridge body (1) and is sealed and connected to the vertical drainage pipe (81).
8. A method for installing a drain pipe, characterized in that: The drain pipe according to any one of claims 1 to 7 is used, comprising the following steps: A. Beam prefabrication stage: the embedded section (4) is placed at a designated position inside the bridge body (1) during pouring and positioned, and the embedded section (4) is fixed when the bridge body (1) is poured and formed; B. Bridge deck cement paving stage: install the entrance section (5) on the top of the embedded section (4), seal the connection between the two, and then pave and pour the cement layer (2); C. Bridge deck asphalt paving stage: install the grate section (6) on the top of the inlet section (5), seal the connection between the two, and then pave and pour the asphalt layer (3); D. Drainage system assembly stage: the outlet section (7) is sealed and connected to the bottom of the embedded section (4), and then the top of the drainage main section (8) is connected to the bottom of the outlet section (7) and sealed to form a complete drainage system.
9. The method for installing a drain pipe according to claim 8, characterized in that: During the beam body prefabrication stage and the bridge deck cement paving stage, the embedded section (4) and the entrance section (5) are lined with supporting inner molds, and after the beam body is cast or the cement layer (2) is paved, the supporting inner molds are taken out.
10. A method for repairing a drain pipe, characterized in that: The drain pipe according to any one of claims 1 to 7 is replaced by the drain pipe installation method according to claim 8, comprising the following steps: A. Dismantling of the existing drainage pipe: After dismantling the damaged existing drainage pipe, the holes of the existing bridge body (1) and the cement layer (2) are polished and the steel bars are derusted, and the new embedded section (4) is placed in the hole of the bridge body (1), and the gap between the inner wall of the hole of the bridge body (1) and the outer wall of the embedded section (4) is filled with micro-expansion cement mortar or glued; B. Installation of other components: After the embedded section (4) is installed, the inlet section (5) is installed in the cement layer (2) and sealed with the embedded section (4); the grate section (6) is installed in the asphalt layer (3) and sealed with the inlet section (5); after the elevation of the inlet section (5) and the grate section (6) is adjusted, the gap between the inlet section (5) and the cement layer (2) and the gap between the grate section (6) and the asphalt layer (3) are filled with cement mortar to make them dense; C. Docking with the existing drainage system: the outlet section (7) is sealed and connected to the bottom of the embedded section (4), and the outlet section (7) is sealed and connected to the existing drainage main section (8), thus completing the maintenance and replacement of the drainage pipe.