Dike structure and construction method thereof
By designing an embankment structure with a base plate, upstream wall and downstream wall, the use of embankment backfill soil and the length of slopes in front and behind embankment is reduced, the problem of large amount of construction soil in the existing technology is solved, and the construction is improved Efficiency and material utilization.
Patent Information
- Application Number
- CN202411129859.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-12
AI Technical Summary
The existing embankment structure requires a large amount of clay soil during the construction process, which leads to soil extraction sites or nearby farmland extraction, resulting in long distances of construction roads or farmland loss.
Design an embankment structure, including the slope in front of the embankment, the slope behind the embankment and the waveproof wall. By setting up the bottom plate, upstream wall and downstream wall, the overall length of the waveproof wall will be increased, the filling space will be reduced, and the amount of backfill will be reduced. Through specific slopes and overlap edge configurations, the length of the slopes in front and back of the dike is shortened, and materials such as asphalt concrete pavement and concrete pavement are used to improve construction efficiency.
It reduces the use of backfill soil on embankment, saves materials, shortens construction time, reduces construction costs, and avoids loss of farmland.
Smart Images

Figure CN118932931A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of water conservancy projects, and in particular to a levee structure and a construction method thereof. Background Art
[0002] In the related technologies, our country's new round of embankment construction started from the emergency waterway project of the dam at the junction of Jiangsu and Zhejiang in the Taihu Lake Basin. After more than 20 years of development, we have designed slope embankments such as homogeneous clay soil embankments, homogeneous sandy soil embankments, and sand-crushed soil mixed embankments. Since the wave-breaking walls of the existing embankments are not high, the amount of clay soil backfilling is relatively large. A large amount of clay soil is required during the construction process. It is necessary to take soil from the soil borrowing site or from nearby farmland. If soil is taken from the soil borrowing site, it will involve the problem of long construction roads and transportation distances, and it may be necessary to build construction access roads; if soil is taken from nearby farmland, part of the farmland will be lost. Summary of the invention
[0003] The present application aims to solve at least one of the technical problems existing in the prior art. To this end, one purpose of the present application is to propose a dike structure that can reduce the amount of backfill soil used in the dike and the length of the front slope and the back slope of the dike, save materials, and improve construction efficiency.
[0004] Another object of the present application is to propose a construction method applicable to the above-mentioned embankment structure.
[0005] According to an embodiment of the present application, the embankment structure includes: a front slope and a rear slope, which are respectively arranged at the river bank mud surface line and extend obliquely toward each other; a wave-breaking wall, which is arranged between the front slope and the rear slope, and the front slope and the rear slope are respectively located upstream and downstream of the wave-breaking wall, and the wave-breaking wall, the front slope, the rear slope and the river bank mud surface line define a filling space suitable for filling embankment backfill soil; wherein the wave-breaking wall has a bottom plate extending between the front slope and the rear slope, and an upstream wall and a downstream wall extending in the height direction are formed on the side of the bottom plate away from the filling space, the front slope is connected to the bottom of the upstream wall, and the rear slope is connected to the bottom of the downstream wall.
[0006] According to the embankment structure of the embodiment of the present application, the embankment structure has a wave-breaking wall and a front slope and a rear slope of the embankment. The wave-breaking wall has a bottom plate, an upstream wall and a downstream wall. The upstream wall and the downstream wall can be connected to the bottom plate and extend in the height direction. The front slope of the embankment is connected to the bottom of the upstream wall, and the rear slope of the embankment is connected to the bottom of the downstream wall. The upstream wall and the downstream wall can increase the overall length of the wave-breaking wall. When the maximum height of the upstream wall and the downstream wall at the river bank mud surface line remains unchanged, the bottom plate can be closer to the river bank mud surface line, thereby reducing the filling space and reducing the total amount of embankment backfill soil required. The front slope and the rear slope of the embankment are respectively connected to the bottom of the upstream wall and the bottom of the downstream wall, which reduces the length of the front slope and the rear slope of the embankment, thereby reducing construction time and saving materials.
[0007] In some embodiments of the present application, the bottom plate extends in the horizontal direction, the upstream wall is arranged at one end of the bottom plate close to the front slope of the dike, and the front slope of the dike extends obliquely toward the upstream wall; the downstream wall is arranged at one end of the bottom plate close to the rear slope of the dike, and the rear slope of the dike extends obliquely toward the downstream wall; wherein the slopes of the front slope of the dike and the rear slope of the dike are i1 and i2 respectively, and satisfy: 1 / 1.5≤i1≤1 / 3, 1 / 1.5≤i2≤1 / 3. .
[0008] In some embodiments of the present application, a first overlapping edge overlapping the front slope of the embankment is formed on the upstream wall, the distance between the first overlapping edge and the bottom plate in the height direction is L1, the height of the upstream wall is H1, and satisfies: 0≤L1≤1 / 2H1; a second overlapping edge overlapping the rear slope of the embankment is formed on the downstream wall, the distance between the second overlapping edge and the bottom plate in the height direction is L2, the height of the downstream wall is H2, and satisfies: 0≤L2≤1 / 2H2.
[0009] In some embodiments of the present application, a filling groove is defined between the base plate, the upstream wall and the downstream wall, and the embankment structure also includes: a embankment top pavement layer, the embankment top pavement layer is filled in the filling groove, and the embankment top pavement layer is constructed as an asphalt concrete pavement or a concrete pavement.
[0010] In some embodiments of the present application, the asphalt concrete pavement includes: a fine-grained asphalt concrete layer, a coarse-grained asphalt concrete layer, a fly ash three-slag layer and a slag layer.
[0011] In some embodiments of the present application, the embankment structure further includes: a front embankment slope protection layer and a back embankment slope protection layer, the front embankment slope protection layer covers the surface of the front embankment slope facing the filling space, and the back embankment slope protection layer covers the surface of the back embankment slope away from the filling space.
[0012] In some embodiments of the present application, a retaining wall in front of the dike is provided at the edge of the slope in front of the dike away from the wave-breaking wall.
[0013] In some embodiments of the present application, the embankment structure also has an excavated slope, which is lower than the river bank mud surface line; the retaining wall in front of the embankment includes: a retaining wall base plate, which is located in the excavated slope; a wall body, one end of which is connected to the retaining wall base plate and extends in the height direction, the thickness of the wall body gradually decreases in the direction approaching the retaining wall top, and the wall body is constructed as a cast-in-place block stone wall; a retaining wall top, which is arranged at the other end of the wall body and connected to the slope in front of the embankment.
[0014] In some embodiments of the present application, reinforcing ribs are provided inside the bottom plate, inside the upstream wall, and inside the downstream wall.
[0015] The following briefly describes a construction method for a levee structure according to an embodiment of the present application.
[0016] The construction method according to the embodiment of the present application is applied to the embankment structure of the above-mentioned embodiment, and the construction method includes: S1, constructing a retaining wall; S2, filling the filling space with embankment backfill soil to form an embankment foundation; S3, constructing the front slope and the rear slope of the embankment in the horizontal direction of the embankment foundation; S4, pouring concrete on the basis of the embankment foundation, the front slope and the rear slope to form the wave-breaking wall; S5, constructing the embankment top pavement layer on the wave-breaking wall.
[0017] According to the construction method of the embodiment of the present application, the construction method can make the filling space smaller, reduce the total amount of embankment backfill soil required, and the front slope and the back slope of the embankment are respectively connected to the bottom of the upstream wall and the bottom of the downstream wall, reducing the length of the front slope and the back slope of the embankment, thereby reducing construction time and saving materials.
[0018] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0020] Figure 1 is a schematic cross-sectional view of a levee structure according to an embodiment of the present application;
[0021] Figure 2 It is a flow chart of a construction method for a levee structure according to an embodiment of the present application.
[0022] Reference numerals:
[0023] 10. Embankment structure;
[0024] 11. Slope in front of the embankment; 12. Slope behind the embankment;
[0025] 13. Wave-breaking wall; 131. Bottom plate; 132. Upstream wall; 133. Downstream wall;
[0026] 14. Backfill soil for embankment; 15. Road surface layer on the top of embankment; 16. Slope protection layer in front of embankment; 17. Slope protection layer behind embankment;
[0027] 18. Retaining wall in front of the embankment; 181. Retaining wall base plate; 182. Wall; 183. Retaining wall top;
[0028] 101. Riverbank mud surface line; 102. Excavation slope. DETAILED DESCRIPTION
[0029] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.
[0030] Reference below Figure 1-Figure 2 The levee structure 10 according to an embodiment of the present application is described. The levee structure 10 includes a front levee slope 11, a rear levee slope 12, and a wave-breaking wall 13. The front levee slope 11 and the rear levee slope 12 are respectively arranged at a river bank mud surface line 101 and extend obliquely toward each other. The wave-breaking wall 13 is arranged between the front levee slope 11 and the rear levee slope 12. The front levee slope 11 and the rear levee slope 12 are respectively located upstream and downstream of the wave-breaking wall 13. The rear slope 12 and the riverbank mud surface line 101 define a filling space suitable for filling the embankment backfill 14, wherein the wave-breaking wall 13 has a bottom plate 131 extending between the front embankment slope 11 and the rear embankment slope 12, and the side of the bottom plate 131 facing away from the filling space is formed with an upstream wall 132 and a downstream wall 133 extending in the height direction, the front embankment slope 11 is connected to the bottom of the upstream wall 132, and the rear embankment slope 12 is connected to the bottom of the downstream wall 133.
[0031] At present, our country's new round of levee construction started from the emergency project of dam waterway at the junction of Jiangsu and Zhejiang in the Taihu Lake Basin. After more than 20 years of development, homogeneous clay soil levee, homogeneous sandy soil levee, sand-crushed soil mixed slope levee, etc. have been designed. Since the wave-breaking wall of the existing levee is not high, the amount of clay soil backfilling is relatively large. A large amount of clay soil is needed during the construction process. It is necessary to take soil from the soil borrowing site or the nearby farmland. If soil is taken from the soil borrowing site, it will involve the problem of long construction roads and transportation distances, and it may be necessary to build construction access roads; if soil is taken from the nearby farmland, part of the farmland will be lost.
[0032] Specifically, the embankment structure 10 includes a front slope 11, a rear slope 12 and a wave-breaking wall 13. The front slope 11 and the rear slope 12 can be respectively arranged at the river bank mud surface line 101, and the front slope 11 and the rear slope 12 can extend obliquely toward each other. The wave-breaking wall 13 can be arranged between the front slope 11 and the rear slope 12, and the front slope 11 and the rear slope 12 can be respectively located upstream and downstream of the wave-breaking wall 13. The wave-breaking wall 13, the front slope 11 and the rear slope 12 can define a filling space, and the filling space can be used to fill the embankment backfill 14. In some embodiments, the embankment backfill 14 can be made of clay, and the embankment backfill 14 needs to be filled into the filling space. The wave-breaking wall 13 can be arranged above the embankment backfill 14, and the front slope 11 and the rear slope 12 are respectively arranged on the sides of the embankment backfill 14.
[0033] Furthermore, the wave-breaking wall 13 has a bottom plate 131 extending between the front slope 11 and the rear slope 12 of the embankment, and the side of the bottom plate 131 away from the filling space forms an upstream wall 132 and a downstream wall 133, and the upstream wall 132 and the downstream wall 133 can both extend in the height direction, wherein the front slope 11 of the embankment can be connected to the bottom of the upstream wall 132, and the rear slope 12 of the embankment can be connected to the bottom of the downstream wall 133. By providing the upstream wall 132 and the downstream wall 133, the overall length of the wave-breaking wall 13 can be increased. On the basis of meeting the requirements of the "Design Code for Embankment Engineering", the maximum heights of the upstream wall 132 and the downstream wall 133 at the riverbank mud surface line 101 remain unchanged, and the bottom plate 13 1 can be closer to the river bank mud surface line 101, so that the filling space becomes smaller, the total amount of embankment backfill soil 14 required in the filling space will also be reduced, and the front slope 11 of the embankment and the rear slope 12 of the embankment can be connected to the bottom of the upstream wall 132 and the bottom of the downstream wall 133 respectively. When the overall height of the wave-breaking wall 13 remains unchanged, compared with the prior art, the connection between the front slope 11 of the embankment and the rear slope 12 and the upstream wall 132 and the downstream wall 133 is closer to the river bank mud surface line 101. Therefore, the materials required for the construction of the upstream wall 132 and the downstream wall 133 are reduced, the construction time is reduced, and the construction materials are saved. The height of the wave-breaking wall 13 is 1.5m-2.5m lower than that of the prior art.
[0034] In short, the levee structure 10 of the embodiment of the present application has a wave-breaking wall 13 and a front slope 11 and a rear slope 12. The wave-breaking wall 13 has a bottom plate 131, an upstream wall 132 and a downstream wall 133. The upstream wall 132 and the downstream wall 133 can be connected to the bottom plate 131 and extend in the height direction. The front slope 11 is connected to the bottom of the upstream wall 132, and the rear slope 12 is connected to the bottom of the downstream wall 133. The upstream wall 132 and the downstream wall 133 can make the wave-breaking wall The overall length of the wall 13 is increased. When the maximum heights of the upstream wall 132 and the downstream wall 133 at the river bank mud surface line 101 remain unchanged, the bottom plate 131 can be closer to the river bank mud surface line 101, thereby reducing the filling space and reducing the total amount of embankment backfill 14 required. In addition, the front slope 11 and the rear slope 12 of the embankment are respectively connected to the bottom of the upstream wall 132 and the bottom of the downstream wall 133, which reduces the length of the front slope 11 and the rear slope 12 of the embankment, thereby reducing construction time and saving materials.
[0035] like Figure 1As shown, in some embodiments of the present application, the bottom plate 131 is located between the front slope 11 and the rear slope 12 of the dike and extends in the horizontal direction, the upstream wall 132 can be arranged at one end of the bottom plate 131 close to the front slope 11 of the dike, and the front slope 11 of the dike can be inclined and extended toward the upstream wall 132, and the downstream wall 133 can be arranged at one end of the bottom plate 131 close to the rear slope 12 of the dike, and the rear slope 12 of the dike can be inclined and extended toward the downstream wall 133. The above arrangement can shorten the front slope of the dike. The distance between the far end of the slope 11 and the upstream wall 132, and the distance between the far end of the slope 12 behind the dike and the downstream wall 133, thereby reducing the engineering volume of the front dike slope 11 and the back dike slope 12, wherein the slope of the front dike slope 11 is i1, and the slope of the front dike slope 11 can meet the following conditions: 1 / 1.5≤i1≤1 / 3, the slope of the back dike slope 12 is i2, and the slope of the back dike slope 12 can meet the following conditions: 1 / 1.5≤i2≤1 / 3.
[0036] In some embodiments of the present application, a first overlapping edge overlapping the front slope of the dike 11 is formed on the upstream wall 132, the distance between the first overlapping edge and the bottom plate 131 in the height direction is L1, the height of the upstream wall 132 is H1, and the distance between the first overlapping edge and the bottom plate 131 in the height direction satisfies the following relationship: 0≤L1≤1 / 2H1. By setting the distance between the first overlapping edge and the bottom plate 131 in the height direction within the above-mentioned range, the distance between the first overlapping edge and the bottom plate 131 in the height direction can be reduced. Under the condition that the slope of the front slope of the dike 11 remains unchanged, the distance between the first overlapping edge and the bottom plate 131 in the height direction is reduced, and the distance between the farthest end of the front slope of the dike 11 and the upstream wall 132 is reduced, thereby reducing the engineering volume of the front slope of the dike 11.
[0037] Furthermore, a second overlapping edge overlapping the rear slope 12 is formed on the downstream wall 133, the distance between the second overlapping edge and the bottom plate 131 in the height direction is L2, the height of the downstream wall 133 is H2, and the distance between the second overlapping edge and the bottom plate 131 in the height direction and the height of the downstream wall 133 satisfy the following relationship: 0≤L2≤1 / 2H2. By setting the distance between the second overlapping edge and the bottom plate 131 in the height direction within the above range, the distance between the second overlapping edge and the bottom plate 131 in the height direction can be reduced. Under the condition that the slope of the rear slope 12 remains unchanged, the distance between the second overlapping edge and the bottom plate 131 in the height direction is reduced, and the distance between the farthest end of the rear slope 12 and the downstream wall 133 is reduced, thereby reducing the engineering volume of the rear slope 12.
[0038] like Figure 1As shown, in some embodiments of the present application, a filling groove is defined between the bottom plate 131, the upstream wall 132 and the downstream wall 133, and the embankment structure 10 also includes a embankment top pavement layer 15, which can be filled in the filling groove, and the embankment top pavement layer 15 can be constructed as an asphalt concrete pavement or a concrete pavement, wherein the asphalt concrete pavement can include a fine-grained asphalt concrete layer, a coarse-grained asphalt concrete layer, a fly ash three-slag layer and a slag layer. In a specific embodiment, the thickness of the fine-grained asphalt concrete layer is 0.3 cm, the thickness of the coarse-grained asphalt concrete layer is 0.7 cm, the thickness of the fly ash three-slag layer is 0.2 cm, and the thickness of the slag layer is 0.2 cm. The concrete pavement can use C40 concrete with a thickness of 0.25 cm to 30 cm.
[0039] like Figure 1 As shown, in some embodiments of the present application, the embankment structure 10 further includes a front embankment slope protection layer 16 and a rear embankment slope protection layer 17. The front embankment slope protection layer 16 can cover the surface of the front embankment slope 11 facing the filling space, and the rear embankment slope protection layer 17 can cover the surface of the rear embankment slope 12 away from the filling space, wherein the front embankment slope protection layer 16 can be paved from top to bottom with a thickness of 30 cm C20 cast-in-place block stone, a thickness of 10 cm crushed stone cushion layer, and a thickness of 10 cm coarse sand cushion layer, but not limited thereto, the front embankment slope protection layer 16 can also be constructed in other structural forms according to actual needs. The rear embankment slope protection layer 17 can be constructed as turf to increase the service life of the rear embankment slope 12.
[0040] like Figure 1 As shown, in some embodiments of the present application, the embankment structure 10 also has an excavated slope 102, and the excavated slope 102 is lower than the river bank mud surface line 101. The front embankment slope 11 is provided with a front embankment retaining wall 18 at the edge away from the wave-breaking wall 13. The front embankment retaining wall 18 may include a retaining wall base plate 181, a wall body 182 and a retaining wall top 183. The retaining wall base plate 181 is located in the excavated slope 102, one end of the wall body 182 is connected to the retaining wall base plate 181 and extends in the height direction, the thickness of the wall body 182 gradually decreases in the direction approaching the retaining wall top 183, the wall body 182 is constructed as a cast-in-place block stone wall body 182, and the retaining wall top 183 is arranged at the other end of the wall body 182 and connected to the front embankment slope 11.
[0041] like Figure 1As shown, in some embodiments of the present application, the interior of the bottom plate 131, the interior of the upstream wall 132, and the interior of the downstream wall 133 are all provided with reinforcing ribs. The bottom plate 131, the upstream wall 132, and the downstream wall 133 can all be cast by concrete, and reinforcing ribs are provided when casting the concrete, so as to improve the structural strength of the embankment structure 10 while reducing the construction cost of the embankment structure 10. Furthermore, reinforcing ribs are provided inside and outside the upstream wall 132 and the downstream wall 133, and the reinforcing ribs on the outside of the bottom plate 131 can be connected to the reinforcing ribs on the outside of the upstream wall 132 and the downstream wall 133 to form a whole. The thickness of the bottom plate 131, the upstream wall 132, and the downstream wall 133 can generally be between 0.30m and 0.40m. Figure 2 As shown, the construction method for the embankment structure according to an embodiment of the present application is briefly described below.
[0042] The construction method according to an embodiment of the present application is applied to the embankment structure of the above embodiment, and the construction method includes:
[0043] S1. Build retaining wall. Build retaining wall on the excavated slope, and build retaining wall in sequence according to retaining wall base plate, wall body and retaining wall cap.
[0044] S2. Fill the filling space with backfill soil to form the embankment foundation. The compacted layer thickness of the embankment backfill soil should not be greater than 30cm.
[0045] S3. Construct the front slope and the back slope of the embankment in the horizontal direction of the embankment foundation. After the front slope and the back slope are constructed, the front slope protection layer and the back slope protection layer are constructed on the surface of the front slope and the back slope respectively. The front slope protection layer is paved from top to bottom with 30cm thick C20 cast-in-place block stone, 10cm thick crushed stone cushion layer and 10cm thick coarse sand cushion layer, and the back slope protection layer is made of turf.
[0046] S4, pouring concrete on the foundation of the embankment, the slope in front of the embankment and the slope behind the embankment to form the wave-breaking wall. First, fix the reinforcement and then pour concrete to form the wave-breaking wall.
[0047] S5, constructing a top embankment pavement layer on the wave-breaking wall. After compacting the concrete, fill the filling groove of the wave-breaking wall with a fine-grained asphalt concrete layer with a thickness of 0.3 cm, a coarse-grained asphalt concrete layer with a thickness of 0.7 cm, a fly ash three-slag layer with a thickness of 0.2 cm, and a slag layer with a thickness of 0.2 cm.
[0048] According to the construction method of the embodiment of the present application, the construction method can make the filling space smaller, reduce the total amount of embankment backfill soil required, and the front slope and the back slope of the embankment are respectively connected to the bottom of the upstream wall and the bottom of the downstream wall, reducing the length of the front slope and the back slope of the embankment, thereby reducing construction time and saving materials.
[0049] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0050] In the description of this application, "first feature" or "second feature" may include one or more of the features.
[0051] In the description of the present application, “plurality” means two or more.
[0052] In the description of the present application, a first feature being “on” or “under” a second feature may include that the first and second features are directly in contact with each other, or may include that the first and second features are not in direct contact with each other but are in contact with each other via another feature therebetween.
[0053] In the description of the present application, “above”, “over” and “above” a first feature to a second feature includes the first feature being directly above and obliquely above the second feature, or simply means that the first feature is horizontally higher than the second feature.
[0054] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials, or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0055] Although the embodiments of the present application have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the claims and their equivalents.
Claims
1. A dike structure, characterized in that: include: A front slope and a rear slope of the dike, wherein the front slope and the rear slope of the dike are respectively arranged at the mud surface line of the river bank and extend obliquely toward each other; A wave-breaking wall, wherein the wave-breaking wall is arranged between the front slope of the embankment and the rear slope of the embankment, and the front slope of the embankment and the rear slope of the embankment are respectively located upstream and downstream of the wave-breaking wall, and the wave-breaking wall, the front slope of the embankment, the rear slope of the embankment and the river bank mud surface line define a filling space suitable for filling the embankment backfill soil; wherein The wave-breaking wall has a bottom plate extending between the front slope of the dike and the rear slope of the dike, and an upstream wall and a downstream wall extending in the height direction are formed on the side of the bottom plate away from the filling space, the front slope of the dike is connected to the bottom of the upstream wall, and the rear slope of the dike is connected to the bottom of the downstream wall.
2. The embankment structure according to claim 1, characterized in that: The bottom plate extends in the horizontal direction, the upstream wall is arranged at one end of the bottom plate close to the front slope of the dike, and the front slope of the dike extends obliquely toward the upstream wall; The downstream wall is arranged at one end of the bottom plate close to the rear slope of the dike, and the rear slope of the dike extends obliquely toward the downstream wall; The slopes of the front slope and the rear slope are i1 and i2 respectively, and satisfy the following conditions: 1 / 1.5≤i1≤1 / 3, 1 / 1.5≤i2≤1 / 3.
3. The embankment structure according to claim 2, characterized in that: The upstream wall is formed with a first overlapping edge overlapping the front slope of the dike, the distance between the first overlapping edge and the bottom plate in the height direction is L1, the height of the upstream wall is H1, and the following conditions are satisfied: 0≤L1≤1 / 2H1; A second overlapping edge overlapping the rear slope of the dike is formed on the downstream wall, the distance between the second overlapping edge and the bottom plate in the height direction is L2, the height of the downstream wall is H2, and the following is satisfied: 0≤L2≤1 / 2H2.
4. The embankment structure according to claim 3, characterized in that: A filling groove is defined between the bottom plate, the upstream wall and the downstream wall, and the embankment structure further comprises: The embankment top pavement layer is filled in the filling groove, and the embankment top pavement layer is constructed as an asphalt concrete pavement or a concrete pavement.
5. The embankment structure according to claim 4, characterized in that: The asphalt concrete pavement comprises: a fine-grained asphalt concrete layer, a coarse-grained asphalt concrete layer, a fly ash three-slag layer and a stone slag layer.
6. The embankment structure according to claim 1, characterized in that: The embankment structure further comprises: A slope protection layer in front of the embankment and a slope protection layer behind the embankment, wherein the slope protection layer in front of the embankment covers the surface of the slope in front of the embankment facing the filling space, and the slope protection layer behind the embankment covers the surface of the slope behind the embankment away from the filling space.
7. The embankment structure according to claim 1, characterized in that: The front slope of the dike is provided with a front retaining wall at an edge away from the wave-breaking wall.
8. The embankment structure according to claim 7, characterized in that: The embankment structure also has an excavated slope, and the excavated slope is lower than the river bank mud surface line; The retaining wall in front of the embankment comprises: A retaining wall bottom plate, wherein the retaining wall bottom plate is located within the excavated slope; A wall, one end of which is connected to the retaining wall bottom plate and extends in the height direction, the thickness of which gradually decreases in the direction approaching the retaining wall top, and the wall is constructed as a cast-in-place block stone wall; A retaining wall cap is arranged at the other end of the wall body and connected to the front slope of the embankment.
9. The embankment structure according to claim 1, characterized in that: Reinforcement ribs are arranged inside the bottom plate, inside the upstream wall and inside the downstream wall.
10. A construction method for a dike structure, characterized in that: The construction method is applied to the embankment structure according to any one of claims 1 to 9, and the construction method comprises: S1. Construction of retaining wall; S2, filling the filling space with embankment backfill soil to form an embankment foundation; S3. Construct the front slope and the back slope of the embankment in the horizontal direction of the embankment foundation; S4, pouring concrete on the foundation of the embankment, the slope in front of the embankment and the slope behind the embankment to form the wave-breaking wall; S5. Construct a top embankment pavement layer on the wave-breaking wall.