Rail train operation control method, simulation system, equipment, medium and program
By simulating the target operation data of rail trains and using ATS, CI and ZC models to generate actual operation diagrams, the problem of poor simulation results in the existing technology is solved, and the operation efficiency and safety of the rail transit system are improved. Emergency response.
Patent Information
- Application Number
- CN202410862090.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-28
- Publication Date
- 2024-11-12
AI Technical Summary
The existing train operation map preparation is low, resulting in poor simulation results, and the rapid and accurate concurrent simulation cannot be achieved, and the consequences of large-scale operation map adjustment cannot be accurately calculated. There are certain risks in actual operation, especially in emergency scenarios. The effectiveness of emergency measures cannot be verified.
By obtaining the target operation data of the rail train for simulation, using ATS, CI and ZC models to generate operation simulation results, generate actual operation diagrams, and control train operation based on actual and reference operation diagrams, calculate errors and adjust operation speed and equipment status, so as to Optimize the operational efficiency and safety of rail transit systems.
It improves simulation effect and practicality, can accurately predict operation diagrams, correct operation diagram errors, optimize the operation efficiency and safety of rail transit systems, and support rapid response to emergency situations.
Smart Images

Figure CN118938706A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of train simulation technology, and in particular to a rail train operation control method, simulation system, equipment, medium and program. Background Art
[0002] Signal systems are key equipment in the rail transit sector. As the intelligent brain of rail transit, they provide a powerful guarantee for safe and efficient train operations. With the expansion of rail transit networks, the increase in train operation modes, the diversification of signal systems, increased passenger travel demands, and the evolution of interconnected and multi-system operating models, the existing train timetable compilation faces the need to meet more precise transportation plans. However, in actual operation, the optimization of train timetable compilation is difficult due to the low level of intelligent and refined transportation plan formulation, the low level of intelligent diagram compilation, the poor adaptability of the diagram, and the lack of cross-line train timetable evaluation methods.
[0003] In related technologies, the simulation function of the operation diagram is relatively simple and differs greatly from the real environment, resulting in the inability to achieve fast and accurate concurrent simulation; it is impossible to accurately calculate the consequences of large-scale operation diagram adjustments; the actual implementation effect of the operation diagram often needs to be verified during actual on-site operations, which involves certain risks. At the same time, it does not have the ability to deduce trends in emergency scenarios and cannot verify the effectiveness of emergency measures. Summary of the Invention
[0004] The present application provides a rail train operation control method, simulation system, equipment, medium and program to solve the problems in related technologies that the actual simulation process of the train and the actual operation process may be quite different, resulting in poor simulation effect, and thus poor accuracy, applicability and practicality in controlling the operation of the train.
[0005] A first aspect embodiment of the present application provides a rail train operation control method, comprising the following steps: obtaining target operation data of at least one rail train, wherein the target operation data includes the operation data of the rail train from the previous station to the current station; performing operation simulation according to the target operation data of the at least one rail train to obtain an operation simulation result of the at least one rail train, and generating a corresponding actual operation diagram according to the operation simulation result of the at least one rail train; and controlling the operation of the at least one rail train according to the actual operation diagram and the reference operation diagram.
[0006] Optionally, the operation simulation is performed based on the target operation data of the at least one rail train to obtain the operation simulation result of the at least one rail train, including: identifying all operation data of the target operation data; determining a simulation model according to the type of the operation data, inputting all the operation data into the corresponding simulation model respectively, and the simulation model outputs the operation simulation result.
[0007] Optionally, all the operation data include operation diagram information, station diagram status and train position, wherein the operation diagram information includes the operation plan of the track line, the timetable corresponding to different train identifications, the operation path and return relationship, and the station diagram status; wherein the station diagram status includes the track occupancy status, the station equipment status, and the signal status, and the station equipment status includes the signal, section and switch status, and the simulation model includes the ATS (Automatic Train Supervision) model, the on-board model, the CI (Computer Interlocking) model and the ZC (Zone Controller) model.
[0008] Optionally, all the operation data are input into corresponding simulation models respectively, and the simulation model outputs operation simulation results, including: inputting the operation diagram information, the station diagram status and the train position into the ATS model, and the ATS model outputs train plan information, equipment control information and operation diagram running results; inputting the CI control command into the CI model, and the CI model outputs station equipment status information, wherein the CI control command is determined based on the equipment control information; inputting the train position and the station equipment status information into the ZC model, and the ZC model outputs movement authorization; inputting the train plan information and the movement authorization into the on-board model, and the on-board model outputs train operation information, wherein the train operation information includes train position, speed and direction.
[0009] Optionally, controlling the operation of at least one rail train according to the actual operation diagram and the reference operation diagram includes: calculating the error between the reference operation diagram and the actual operation diagram; and adjusting the operating speed of the at least one rail train to the next station and the control state of the station equipment based on the error.
[0010] Optionally, after controlling the operation of at least one rail train according to the actual operation diagram and the reference operation diagram, it includes: obtaining a reference operation diagram and an actual operation diagram for a target period; and determining operational requirements based on the reference operation diagram and the actual operation diagram.
[0011] The second aspect of the present application provides an operation simulation system for a train track, comprising: a simulation sub-module, wherein the simulation sub-module includes an ATS module, an on-board module, a CI module and a ZC module; a shared database for storing operation data of multiple station intervals; a simulation management module communicatively connected to the shared database and the simulation sub-module, for calling the operation data of the shared database according to the simulation requirements of each simulation sub-module to perform corresponding simulation operations and generate an actual operation diagram; and an effect evaluation module for evaluating the actual operation diagram and the reference operation diagram to obtain an evaluation result.
[0012] The third aspect of the present application provides an electronic device, comprising: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the rail train operation control method as described in the above embodiment.
[0013] The fourth aspect of the present application provides a computer-readable storage medium on which a computer program is stored. The program is executed by a processor to implement the rail train operation control method as described in the above embodiment.
[0014] The fifth embodiment of the present application provides a computer program product, which, when executed, is used to implement the rail train operation control method as described in the above embodiment.
[0015] Therefore, this application has at least the following beneficial effects:
[0016] The embodiment of the present application can perform operation simulation based on the target operation data of at least one rail train to obtain the operation simulation result of at least one rail train, generate a corresponding actual operation diagram according to the operation simulation result of the at least one rail train, and control the operation of at least one rail train according to the actual operation diagram and the reference operation diagram, so that the actual operation diagram of the previous station interval can accurately predict the operation diagram of the next interval stage, improve the simulation effect, and have strong applicability and practicality. It can also control the operation of at least one rail train, correct the error between the actual operation diagram and the reference operation diagram as much as possible, and optimize the operation performance and passenger flow distribution of rail transit based on the final operation diagram result, effectively improving the operational efficiency and safety of the rail transit system.
[0017] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0019] Figure 1This is a flow chart of a rail train operation control method provided according to an embodiment of the present application;
[0020] Figure 2 is a block diagram of a rail train operation simulation system according to an embodiment of the present application;
[0021] Figure 3 This is an example diagram of a rail train operation simulation system according to an embodiment of the present application;
[0022] Figure 4 Schematic diagram of the structure of an electronic device according to an embodiment of the present application. DETAILED DESCRIPTION
[0023] The following describes in detail embodiments of the present application, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.
[0024] The main shortcomings of the verification and evaluation of existing system operation diagrams in the urban rail transit industry in related technologies are as follows:
[0025] 1) The operation diagram simulation function is relatively simple. The simulation time and verification time are often limited to 1:1 simulation. Moreover, the various models in the signal system differ greatly from the real environment, making it impossible to simulate their main functions and achieve fast and accurate concurrent simulation.
[0026] 2) Users cannot accurately predict the consequences of large-scale operation chart adjustments and rely heavily on personal experience. When the adjustment range of the operation chart adjustment algorithm is large, users cannot accurately assess the subsequent operation trend of the operation chart.
[0027] 3) The actual implementation effect of the operation diagram often needs to be verified during actual on-site operations, which involves certain risks. At the same time, it is not possible to deduce trends in emergency scenarios and verify the effectiveness of emergency measures.
[0028] Therefore, this application can develop a comprehensive rail transit system simulation platform by integrating artificial intelligence technology and multi-agent simulation technology; this technical solution can implement station simulation, line simulation and network simulation at different levels of stations, lines and networks, thereby realizing detailed simulation and evaluation of the entire rail system.
[0029] The purpose of this application is to provide real-time operation information, historical passenger flow data processing, and a realistic representation of physical facilities through high-level simulation and analysis of the operation of the rail transit system, so as to help managers and engineers accurately predict the operation diagrams at different time periods and optimize the operation performance and passenger flow distribution of rail transit based on the operation diagrams; at the same time, it also supports the rapid response and handling of emergency situations, ensuring the stable operation of the rail transit system under various circumstances.
[0030] The following describes the rail train operation control method, simulation system, device, medium and program of the embodiment of the present application with reference to the accompanying drawings. Specifically, Figure 1 A flow chart of a rail train operation control method provided in an embodiment of the present application.
[0031] like Figure 1 As shown, the rail train operation control method includes the following steps:
[0032] In step S101, target operation data of at least one rail train is acquired, wherein the target operation data includes operation data of the rail train from a previous station to a current station.
[0033] It is understandable that the embodiment of the present application can obtain target operation data of at least one rail train, so as to facilitate subsequent simulation using the target operation data to obtain simulation results.
[0034] It should be noted that the operation data includes operation diagram information, station diagram status and train position, among which the operation diagram information includes the operation plan of the track line, the timetable corresponding to different train identifications, the operation path and return relationship, and the station diagram status; among which, the station diagram status includes the track occupancy status, the station equipment status, and the signal status, and the station equipment status includes the signal, section and switch status.
[0035] In step S102, an operation simulation is performed based on target operation data of at least one rail train to obtain an operation simulation result of at least one rail train, and a corresponding actual operation diagram is generated based on the operation simulation result of at least one rail train.
[0036] It can be understood that the embodiment of the present application can perform operation simulation based on the target operation data of at least one rail train to obtain the operation simulation result of at least one rail train, and generate the corresponding actual operation diagram based on the operation simulation result of at least one rail train, so that the actual operation diagram of the previous station interval can accurately predict the operation diagram of the next interval stage, thereby improving the simulation effect, and having strong applicability and practicality.
[0037] In an embodiment of the present application, an operation simulation is performed based on the target operation data of at least one rail train to obtain an operation simulation result of at least one rail train, including: identifying all operation data of the target operation data; determining a simulation model according to the type of the operation data, inputting all the operation data into the corresponding simulation model respectively, and the simulation model outputting the operation simulation result.
[0038] Among them, the simulation models include ATS model, vehicle model, CI model and ZC model.
[0039] It is understandable that the embodiments of the present application can select different simulation models based on different types of operating data, and output operating simulation results based on different simulation models, thereby improving the accuracy and efficiency of the simulation.
[0040] In an embodiment of the present application, all operation data are input into the corresponding simulation model respectively, and the simulation model outputs the operation simulation result, including: inputting the operation diagram information, station diagram status and train position into the ATS model, and the ATS model outputs the train plan information, equipment control information and operation diagram running results; inputting the CI control command into the CI model, and the CI model outputs the station equipment status information, wherein the CI control command is determined based on the equipment control information; inputting the train position and station equipment status information into the ZC model, and the ZC model outputs the movement authorization; inputting the train plan information and movement authorization into the on-board model, and the on-board model outputs the train operation information, wherein the train operation information includes the train position, speed and direction.
[0041] It can be understood that the embodiment of the present application uses different simulation models to simulate different types of operation data to obtain simulation results, and then generates an actual operation diagram based on the simulation results. Each model simplifies its own functions and simplifies interface interactions, thereby improving simulation efficiency.
[0042] Specifically, if Figure 3 As shown, the above models are explained below: (1) ATS model: ATS mainly undertakes the function of traffic control in the signal system, and this patent extracts the core traffic control function.
[0043] Operation chart function, the module can load offline operation chart.
[0044] The route automatic triggering function enables the module to automatically select the route based on the destination information in the train number.
[0045] Input: operation diagram information, station map status, train location;
[0046] Output: train plan information, equipment control information, and operation diagram results.
[0047] (2) On-board model: The on-board module is mainly responsible for controlling the train speed in the signal system. This patent extracts the traction and braking train model.
[0048] The traction and braking model module can dynamically calculate the real-time acceleration of the train based on line information and train traction / braking force.
[0049] Input: train schedule information, movement authorization;
[0050] Output: Train information, including but not limited to location, speed, and direction.
[0051] (3) CI model: The CI model is mainly responsible for managing the ground equipment of the station in the information system. In the simulation, it mainly involves signals, sections, and switches. The functions extracted by this patent are as follows:
[0052] Device control function, which can process control commands and change device status.
[0053] The route unlocking function allows the route to be automatically unlocked after the train passes through it.
[0054] Input: CI control command;
[0055] Output: station equipment status information.
[0056] (4) ZC model: The ZC model is mainly responsible for managing trains in the signal system. The functions extracted by this patent are as follows:
[0057] The mobile authorization function can send mobile authorization to the train and tell the train's running path information in real time.
[0058] Input: train location, station equipment status information;
[0059] Output: Move authorization.
[0060] In step S103, the operation of at least one rail train is controlled according to the actual operation diagram and the reference operation diagram.
[0061] It can be understood that the embodiments of the present application can control the operation of at least one rail train according to the actual operation diagram and the reference operation diagram, so as to correct the error between the actual operation diagram and the reference operation diagram as much as possible, and optimize the operation performance and passenger flow distribution of rail transit based on the final operation diagram results, thereby effectively improving the operational efficiency and safety of the rail transit system.
[0062] In an embodiment of the present application, the operation of at least one rail train is controlled according to the actual operation diagram and the reference operation diagram, including: calculating the error between the reference operation diagram and the actual operation diagram; and adjusting the operating speed of at least one rail train to the next station and the control state of the station equipment based on the error.
[0063] It can be understood that the embodiment of the present application can adjust the running speed of the train to the next station and the control status of the station equipment based on the error between the reference operating diagram and the actual operating diagram, so as to correct the error between the actual operating diagram and the reference operating diagram as much as possible.
[0064] For example, when the actual arrival time of the train at the station in the actual operation diagram is later than the station time in the reference operation diagram, in order to compensate for this time error, the train's running speed at the next station is controlled to increase to the target speed. The target speed can be calculated based on the distance and time between stations. The target speed can reach the maximum speed at which the train can travel. In the case of a large time difference, the train is only controlled at the maximum speed at which it can travel to ensure the safety of the train. Based on the actual running speed of the train and the station equipment between each station, real-time calculations are performed to control the station equipment to be in normal opening or running state at the time of train arrival or before the train arrives.
[0065] In an embodiment of the present application, after controlling the operation of at least one rail train according to the actual operation diagram and the reference operation diagram, it includes: obtaining the reference operation diagram and the actual operation diagram of the target period; and determining the operating requirements based on the reference operation diagram and the actual operation diagram.
[0066] It can be understood that the embodiments of the present application can obtain the reference operation diagram and the actual operation diagram for the target period; determine the operating requirements based on the reference operation diagram and the actual operation diagram, so as to update the reference operation diagram according to the operating requirements and optimize the operating performance and passenger flow distribution of rail transit.
[0067] It should be noted that since the maximum speed of the train is fixed, there may be situations where the train cannot reach the destination on time according to the time point of the reference timetable. Therefore, it is necessary to determine the operational needs in combination with the reference timetable and the actual timetable.
[0068] According to the rail train operation control method proposed in the embodiment of the present application, an operation simulation is performed based on the target operation data of at least one rail train to obtain an operation simulation result of at least one rail train, a corresponding actual operation diagram is generated according to the operation simulation result of at least one rail train, and the operation of at least one rail train is controlled according to the actual operation diagram and the reference operation diagram, so that the actual operation diagram of the previous station interval can accurately predict the operation diagram of the next interval stage, thereby improving the simulation effect, and having strong applicability and practicality. The operation of at least one rail train is controlled, the error between the actual operation diagram and the reference operation diagram is corrected as much as possible, and the operation performance and passenger flow distribution of rail transit are optimized based on the final operation diagram result, thereby effectively improving the operational efficiency and safety of the rail transit system.
[0069] Next, the train track operation simulation system proposed in accordance with the embodiments of the present application will be described with reference to the accompanying drawings.
[0070] Figure 2 It is a block diagram of a train track operation simulation system according to an embodiment of the present application.
[0071] like Figure 2 As shown, the train track operation simulation system 10 includes: a simulation submodule 100 , a shared database 200 , a simulation management module 300 and an effect evaluation module 400 .
[0072] Among them, the simulation sub-module 100 includes an ATS module, an on-board module, a CI module and a ZC module; the shared database 200 is used to store the operation data of multiple station intervals; the simulation management module 300, which is communicatively connected to the shared database and the simulation sub-module, is used to call the operation data of the shared database according to the simulation requirements of each simulation sub-module 100 to perform corresponding simulation operations and generate an actual operation diagram; the effect evaluation module 400 is used to evaluate the actual operation diagram and the reference operation diagram to obtain an evaluation result.
[0073] It can be understood that the embodiment of the present application can generate an actual operation diagram based on the operation data of the shared database executed according to the simulation requirements of each simulation sub-module, so that the actual operation diagram of the previous station interval can accurately predict the operation diagram of the next interval stage, improve the simulation effect, and have strong applicability and practicality. The evaluation results are obtained based on the actual operation diagram and the reference operation diagram to correct the errors between the actual operation diagram and the reference operation diagram as much as possible, and optimize the operation performance and passenger flow distribution of the rail transit based on the final operation diagram results, effectively improving the operational efficiency and safety of the rail transit system.
[0074] Specifically, (1) Figure 3 As shown in the figure, the simulation management model is responsible for managing the coordinated operation of the entire system. This module provides control information and shared information. The control information mainly coordinates the status of the entire simulation signal system and controls the progress of each submodule according to the specified step size.
[0075] Input: system step length, simulation submodule information, simulation submodule step length, simulation control information (start, pause, accelerate, decelerate, end);
[0076] Output: simulation control information (start, pause, accelerate, decelerate, end, send to sub-module).
[0077] (2) Shared information is the data sharing pool of the entire analog signal system, which includes cycle information, release module information, data information, etc. Shared information also has a data caching function, which can set the data retention time according to the configuration information for the entire system to replay, or jump back to a certain cache point when an abnormality occurs.
[0078] (3) Effect evaluation module: This module is mainly responsible for displaying the actual results of the operation diagram to the outside world and providing evaluation and analysis results.
[0079] Input: actual graph of running graph;
[0080] Output: running chart results, evaluation and analysis results.
[0081] According to the train track operation simulation system proposed in the embodiment of the present application, the operation data of the shared database is called according to the simulation requirements of each simulation sub-module to perform corresponding simulation operations to generate an actual operation diagram, so that the actual operation diagram of the previous station interval can accurately predict the operation diagram of the next interval stage, thereby improving the simulation effect, and having strong applicability and practicality. Evaluation results are obtained based on the actual operation diagram and the reference operation diagram to correct the errors between the actual operation diagram and the reference operation diagram as much as possible, and the operation performance and passenger flow distribution of the rail transit are optimized based on the final operation diagram results, thereby effectively improving the operational efficiency and safety of the rail transit system.
[0082] Figure 4 This is a schematic diagram of the structure of an electronic device provided in an embodiment of the present application. The electronic device may include:
[0083] Memory 401 , processor 402 , and computer programs stored in the memory 401 and executable on the processor 402 .
[0084] When the processor 402 executes the program, the rail train operation control method provided in the above embodiment is implemented.
[0085] Furthermore, the electronic device further includes:
[0086] The communication interface 403 is used for communication between the memory 401 and the processor 402 .
[0087] The memory 401 is used to store computer programs that can be run on the processor 402 .
[0088] The memory 401 may include a high-speed RAM (Random Access Memory) memory, and may also include a non-volatile memory, such as at least one disk memory.
[0089] If the memory 401, the processor 402, and the communication interface 403 are implemented independently, the communication interface 403, the memory 401, and the processor 402 can be connected to each other via a bus and communicate with each other. The bus can be an ISA (Industry Standard Architecture) bus, a PCI (Peripheral Component Interconnect) bus, or an EISA (Extended Industry Standard Architecture) bus. The bus can be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 4 Only one thick line is used in the diagram, but this does not mean that there is only one bus or one type of bus.
[0090] Optionally, in a specific implementation, if the memory 401, the processor 402 and the communication interface 403 are integrated on a chip, the memory 401, the processor 402 and the communication interface 403 can communicate with each other through an internal interface.
[0091] The processor 402 may be a CPU (Central Processing Unit), or an ASIC (Application Specific Integrated Circuit), or one or more integrated circuits configured to implement the embodiments of the present application.
[0092] An embodiment of the present application also provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the above-mentioned rail train operation control method is implemented.
[0093] An embodiment of the present application also provides a computer program product, which, when executed, is used to implement the rail train operation control method as described in the above embodiment.
[0094] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or N embodiments or examples in a suitable manner. In addition, those skilled in the art can combine and combine different embodiments or examples described in this specification and features of different embodiments or examples without contradiction.
[0095] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be understood to indicate or imply relative importance or implicitly specify the number of technical features indicated. Thus, a feature specified as "first" or "second" may explicitly or implicitly include at least one such feature. In the description of this application, "N" means at least two, for example, two, three, etc., unless otherwise specifically defined.
[0096] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or N executable instructions for implementing a custom logical function or process step, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may be performed in a different order than shown or discussed, including performing functions in a substantially simultaneous manner or in a reverse order depending on the functions involved, which should be understood by those skilled in the art to which the embodiments of the present application pertain.
[0097] It should be understood that various parts of the present application can be implemented using hardware, software, firmware, or a combination thereof. In the above embodiment, the N steps or methods can be implemented using software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented using hardware, as in another embodiment, it can be implemented using any one or a combination of the following technologies known in the art: a discrete logic circuit having a logic gate circuit for implementing a logic function on a data signal, an application-specific integrated circuit having a suitable combination of logic gate circuits, a programmable gate array, a field programmable gate array, etc.
[0098] Those skilled in the art will understand that all or part of the steps in the method of the above embodiment can be completed by instructing related hardware through a program, and the program can be stored in a computer-readable storage medium. When the program is executed, it includes one or a combination of the steps of the method embodiment.
[0099] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in this field can change, modify, replace and modify the above embodiments within the scope of the present application.
Claims
1. A rail train operation control method, characterized in that: include: Acquire target operation data of at least one rail train, wherein the target operation data includes operation data of the rail train from a previous station to a current station; Performing operation simulation according to the target operation data of the at least one rail train to obtain an operation simulation result of the at least one rail train, and generating a corresponding actual operation diagram according to the operation simulation result of the at least one rail train; The operation of at least one rail vehicle is controlled according to the actual operation diagram and the reference operation diagram.
2. The rail train operation control method according to claim 1, characterized in that: The performing operation simulation according to the target operation data of the at least one rail train to obtain the operation simulation result of the at least one rail train comprises: Identify all operation data of the target operation data; A simulation model is determined according to the type of the operation data, all the operation data are input into corresponding simulation models respectively, and the simulation model outputs operation simulation results.
3. The rail train operation control method according to claim 2, characterized in that: All the operation data include operation diagram information, station diagram status and train position, wherein the operation diagram information includes the operation plan of the track line, the timetable corresponding to different train identifications, the operation path and return relationship, and the station diagram status; wherein the station diagram status includes the track occupancy status, the station equipment status, and the signal status, wherein the station equipment status includes the signal, section and switch status, and the simulation model includes the ATS model, the vehicle-mounted model, the CI model and the ZC model.
4. The rail train operation control method according to claim 3, characterized in that: The step of inputting all the operation data into corresponding simulation models respectively, and the simulation models outputting operation simulation results, comprises: The operation diagram information, the station diagram status and the train position are input into the ATS model, and the ATS model outputs train plan information, equipment control information and operation diagram running results; Inputting a CI control command into the CI model, the CI model outputting station equipment status information, wherein the CI control command is determined based on the equipment control information; Inputting the train position and the station equipment status information into the ZC model, and the ZC model outputs movement authorization; The train plan information and the movement authorization are input into the on-board model, and the on-board model outputs train operation information, wherein the train operation information includes the train position, speed and direction.
5. The rail train operation control method according to claim 1, characterized in that: The controlling the operation of at least one rail vehicle according to the actual operation diagram and the reference operation diagram comprises: Calculating the error between the reference operation diagram and the actual operation diagram; The running speed of the at least one rail train heading to the next station and the control state of the station equipment are adjusted based on the error.
6. The rail train operation control method according to claim 1, characterized in that: After controlling the operation of at least one rail vehicle according to the actual operation diagram and the reference operation diagram, the method further comprises: Obtain the reference operation diagram and actual operation diagram for the target period; Operational requirements are determined based on the reference operating diagram and the actual operating diagram.
7. A train track operation simulation system, characterized in that: include: A simulation submodule, wherein the simulation submodule includes an ATS module, an on-board module, a CI module and a ZC module; A shared database for storing operation data between multiple stations; A simulation management module in communication with the shared database and the simulation submodules, for calling the operation data of the shared database to perform corresponding simulation operations and generate an actual operation diagram according to the simulation requirements of each simulation submodule; The effect evaluation module is used to evaluate the actual operation diagram and the reference operation diagram to obtain an evaluation result.
8. An electronic device, characterized in that: include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the rail train operation control method as described in any one of claims 1 to 6.
9. A computer-readable storage medium having a computer program stored thereon, characterized in that: The program is executed by a processor to implement the rail train operation control method as described in any one of claims 1-6.
10. A computer program product comprising: A computer program or instruction, characterized in that when the computer program or instruction is executed, it implements the rail train operation control method described in any one of claims 1-6.