Cantilever pouring arch bridge construction method based on multi-objective optimization
Through the multi-objective optimization construction method, combined with simulation modeling and real-time monitoring, the problem of poor structural stability in the construction of cantilever cast concrete arch bridges is solved, and multiple goals are taken into account and safety improvements are achieved during the construction process.
Patent Information
- Application Number
- CN202410941111.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-07-15
AI Technical Summary
During the construction of cantilever cast concrete arch bridge, the structure stability after the arch ring section increases, and the cable force adjustment is complex, resulting in high-altitude operation risks. The existing technology lacks multi-objective optimization solutions, making it difficult to ensure the stress and deformation during the construction process. Safety.
Using a construction method based on multi-objective optimization, through simulation parameterized modeling and finite element analysis, a multi-objective optimization program is introduced to solve the reasonable clamping force, and the longitudinal and lateral offset angles are monitored in real time, and the anchors and clamping are used to perform. Structural connections and adjustments ensure the safety of the construction process.
The multiple goals are taken into account during the construction process, the structure's stress and deformation safety is improved, the number of cable force adjustments is reduced, the risk of high-altitude operations is reduced, and the construction stability and safety is ensured.
Smart Images

Figure CN118940359A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge construction, and in particular to a cantilever cast arch bridge construction method based on multi-objective optimization. Background Art
[0002] The construction process of the arch ring segments of cantilever cast concrete arch bridges is actually a process of constantly updating and establishing a new structural self-balance based on the balance of the old structure. With the increase of the arch ring cantilever segments, the process of establishing the new balance becomes more complicated and its stability becomes worse. The maximum cantilever state is the most dangerous and unstable state, and it is not suitable to adjust the cables on a large scale in this state. On the other hand, the buckle towers, buckle cables and anchor cables of cantilever cast concrete arch bridges are all temporary structures, and their safety factors are generally smaller than those of permanent structures such as cable towers and cable stays of concrete cable-stayed bridges of the same span. Repeated tensioning and adjustment of buckles and anchor cables can easily lead to the failure of the working anchors. In addition, the tensioning and adjustment of cable forces during the construction process are generally carried out on higher buckle towers, and the risk of high-altitude operations is relatively high.
[0003] Determining the reasonable construction cable force of a large-span cantilever cast reinforced concrete arch bridge is a very complex system problem. Under the premise of minimizing the number of tensioning and cable adjustment, it is necessary to ensure the stress and deformation safety of the coupling body of the tower-cable and cantilever arch ring structure during construction, and to meet the stress and linear requirements of the arch ring structure after the bridge is completed. This is a multi-objective optimization problem. There is a lack of relevant solutions in the existing technology.
[0004] In view of this, a construction method of cantilevered arch bridge based on multi-objective optimization is proposed. Summary of the invention
[0005] The purpose of the present invention is to provide a cantilevered arch bridge construction method based on multi-objective optimization to solve the problems pointed out in the background technology.
[0006] The above technical objectives of the present invention are achieved through the following technical solutions:
[0007] A method for constructing a cast-in-place arch bridge based on multi-objective optimization comprises the following steps:
[0008] The whole process of construction is simulated and parametrically modeled, and the established parametric finite element model is analyzed. The relevant analysis results are extracted and output files are imported into the multi-objective optimization program to complete the multi-objective optimization solution of the reasonable construction cable force of the cantilever concrete arch bridge and obtain the cable force during construction.
[0009] Construction of anchors and anchor towers on junction piers;
[0010] According to the cable force obtained during construction by solving multiple objectives, the main arch ring is constructed, and the anchor is used as the rear anchor system of the main arch ring, and the anchor is anchored to the buckle tower through the anchor cable, and the other side of the buckle tower is anchored to the main arch ring through the cable;
[0011] The specific process of constructing the main arch ring is as follows:
[0012] The current segment arch box is cantilever cast, and the arch box is connected to the buckle tower by the buckle cable, and the buckle cable is tensioned according to the buckle cable force obtained by multi-objective solution. After the tensioning is completed, the longitudinal offset angle and the lateral offset angle of the buckle cable are monitored in real time. When the longitudinal offset angle and the lateral offset angle of the buckle cable exceed the preset limit, an alarm is issued. The longitudinal offset angle refers to the offset angle in the vertical plane, and the lateral offset angle refers to the offset angle in the horizontal plane.
[0013] Repeat the above steps until the main arch ring is completed, and after the closure is completed, remove the buckle cables, anchor cables and buckle towers.
[0014] In a preferred embodiment, the method further includes the following steps: after the tensioning of the cables is completed, the lateral offset angle of the tensioned cables is used as a statistical object to calculate the overlap of the range of values of the lateral offset angle of the tensioned cables in adjacent unit times; if the overlap in a certain adjacent unit time is lower than a preset value, and the overlap in a subsequent preset number of adjacent unit times meets the preset value, an alarm is issued.
[0015] In a preferred embodiment, the step is also included: after the tensioning of the buckle cable is completed, an offset angle monitoring device is installed to realize real-time monitoring of the longitudinal offset angle and the lateral offset angle of the buckle cable, the offset angle monitoring device includes: a fixed base, a support frame, two rotation monitoring units, a dual-axis motor, a first friction wheel and a second friction wheel, the support frame is arranged on the fixed base, the dual-axis motor is arranged on the support frame, the first friction wheel and the second friction wheel are respectively connected to the two shafts of the dual-axis motor, the rotation monitoring unit includes a rotating ring and a strain gauge, the rotating ring is arranged on the support frame, the strain gauge is arranged on the inner side wall of the rotating ring, the first friction wheel and the second friction wheel respectively contact one of the rotating rings to drive the corresponding rotating ring to rotate; after the tensioning of the buckle cable is completed, the fixed base is installed on the arch box, the buckle cable passes through the two rotating rings, the strain gauge contacts the buckle cable, and the dual-axis motor is used to drive the rotating ring to reciprocate.
[0016] In a preferred embodiment, the support frame includes a support column and a semi-tube type placement plate, the support column is arranged on the fixed base, the semi-tube type placement plate is arranged on the support column, the semi-tube type placement plate is provided with two placement grooves, and the rotating ring limit is located in the placement grooves.
[0017] In a preferred embodiment, the semi-tube type placement plate includes a plate body, a first closing plate and a second closing plate, the first closing plate and the second closing plate are respectively fixed to the two ends of the plate body by bolts, and the placement grooves are respectively formed between the first closing plate and the plate body and between the second closing plate and the plate body.
[0018] In a preferred embodiment, the side of the placement groove is provided with a limiting rib, and the side of the rotating ring is provided with a limiting groove that cooperates with the limiting rib.
[0019] In a preferred embodiment, the strain gauge is configured to be U-shaped.
[0020] In a preferred embodiment, the step of monitoring the cable tension after the cable tensioning is completed and adjusting the cable tension according to the monitoring result so that all the cable tensions meet the multi-objective solution range requirements is included.
[0021] In a preferred embodiment, the step is further included: after the cable is tensioned, a cable force detection device is installed to monitor the cable force, the cable force monitoring device includes a bracket, a pressure assembly and two gripping assemblies, an intermediate placement bin is provided in the middle of the bracket, the pressure assembly includes an actuating device, a pressure gauge, a stroke metering device and a pressure block, the actuating device is fixed on the bracket, the pressure gauge is provided between the actuating device and the pressure block, the pressure block passes through the intermediate placement bin, the stroke metering device is installed on the side of the pressure block, and is used to measure the stroke of the pressure block, and the two gripping assemblies are respectively provided at both ends of the bracket.
[0022] In a preferred embodiment, the actuating device is configured as a cylinder or an electric push rod.
[0023] In a preferred embodiment, the travel metering device comprises a measuring wheel and a wheel speed meter, the circumference of the measuring wheel abuts against the pressure block, and the wheel speed meter is used to measure the wheel speed of the measuring wheel.
[0024] In a preferred embodiment, a first V-shaped groove is provided at the bottom of the pressing block.
[0025] In a preferred embodiment, end housing bins are provided at both ends of the bracket, and a first ring outlet, a top opening and a second ring outlet are provided at the bottom of the end housing bin, and the top opening is provided between the first ring outlet and the second ring outlet. The gripping assembly comprises a gripping ring, a driving wheel, a first acting wheel, a second acting wheel, a motor, a top block and a downward pressing driving device. The driving wheel, the first acting wheel, the second acting wheel and the motor are provided in the end housing bin, and the motor is connected to the driving wheel for driving the driving wheel to rotate. The first acting wheel and the second acting wheel are respectively provided on both sides of the driving wheel and are driven to rotate by the driving wheel. A notch is provided on the gripping ring, and the notch has a first end and a second end. During operation, the gripping ring is topped by the first acting wheel and / or the second acting wheel and passes through the first ring outlet. The first end is located in the end housing bin, and the second end enters and exits the end housing bin via the second ring outlet. The downward pressing driving device is provided at the top of the end housing bin, and the top block is connected to the downward pressing driving device and inserted into the end housing bin, and is provided corresponding to the top opening.
[0026] In a preferred embodiment, the downward pressing driving device is configured as a cylinder or an electric telescopic rod, and a second V-shaped groove is provided at the bottom of the abutting block.
[0027] In a preferred embodiment, the central angle of the notch and the corresponding gripping ring is 60-150 degrees.
[0028] In a preferred embodiment, the gripping assembly further comprises a first linkage wheel and a second linkage wheel, wherein the circumference of the first linkage wheel fits the driving wheel and the first action wheel, and the circumference of the second linkage wheel fits the driving wheel and the second action wheel.
[0029] Compared with the prior art, the present invention provides a cast-in-place arch bridge construction method based on multi-objective optimization, which obtains a parametric finite element model through simulation parametric modeling, obtains analysis results by analyzing the parametric finite element model, and imports the analysis results into a multi-objective optimization program to achieve multi-objective solution, thereby obtaining a cable force that meets the requirements of achieving multiple objectives, thereby achieving multi-objective considerations during the construction process.
[0030] At the same time, in order to realize real-time monitoring during the construction process and realize monitoring of multiple engineering inspection targets, after the cable is tensioned, the longitudinal offset angle and lateral offset angle of the cable are monitored in real time. By judging whether the longitudinal offset angle and the lateral offset angle exceed the preset limit, it is judged whether the working condition is normal. Specifically, when the lateral offset angle and the lateral offset angle of the cable exceed the limit, it may indicate that there is an abnormality in the cable or the tower, and timely inspection is required. The abnormal longitudinal offset angle generally corresponds to abnormal cable status, and the abnormal lateral offset generally corresponds to abnormal tower status, such as tilting or twisting of the tower. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 The invention relates to a structural schematic diagram of a cantilevered arch bridge applied to a cantilevered arch bridge construction method based on multi-objective optimization.
[0032] Figure 2 The present invention relates to a structural schematic diagram of an offset angle detection device used in a cantilevered arch bridge construction method based on multi-objective optimization (first viewing angle)
[0033] Figure 3 The present invention relates to a structural schematic diagram of an offset angle detection device used in a cantilevered arch bridge construction method based on multi-objective optimization (second perspective)
[0034] Figure 4 The present invention relates to a structural schematic diagram of a cable force monitoring device used in a cast-in-place arch bridge construction method based on multi-objective optimization.
[0035] Figure 5 The present invention relates to a first-view structural schematic diagram of an end placement bin of a cable force monitoring device used in a cast-in-place arch bridge construction method based on multi-objective optimization.
[0036] Figure 6 The present invention relates to a structural schematic diagram of a second perspective of an end placement bin of a cable force monitoring device used in a cantilever cast arch bridge construction method based on multi-objective optimization.
[0037] In the picture
[0038] Anchor 1; buckle tower 2; main arch ring 3; anchor cable 4; buckle cable 5; bracket 6; intermediate placement bin 7; end placement bin 8; first ring outlet 9; second ring outlet 10; actuating device 11; stroke metering device 12; pressure block 13; first V-shaped slot 14; gripping ring 15; notch 16; driving wheel 17; first action wheel 18; second action wheel 19; motor 20; abutment block 21; second V-shaped slot 22; downward pressure driving device 23; first linkage wheel 24; second linkage wheel 25; offset angle monitoring device 26; fixed base 27; support column 28; plate body 29; placement groove 30; first closing plate 31; second closing plate 32; double-axis motor 33; first friction wheel 34; second friction wheel 35; rotating ring 36; strain gauge 37. DETAILED DESCRIPTION
[0039] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0040] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed. However, as long as they are within the scope of the claims of the present invention, they are protected by the patent law.
[0041] like Figures 1 to 6 As shown, a method for constructing a cantilevered arch bridge based on multi-objective optimization includes the following steps:
[0042] S1. Simulate the parametric modeling of the whole construction process structure, analyze the established parametric finite element model, extract the relevant analysis results and output the file, import the output file into the multi-objective optimization program, complete the multi-objective optimization solution of the reasonable construction cable force of the suspended concrete arch bridge, and obtain the cable force during construction;
[0043] S2, construction anchor and buckle tower 2 on the junction pier;
[0044] S3. According to the cable force obtained during construction through multi-objective solution, the main arch ring 3 is constructed, and the anchor 1 is used as the rear anchor system of the main arch ring 3. The anchor 1 is anchored to the cable tower 2 through the anchor cable 4, and the other side of the cable tower 2 is anchored to the main arch ring 3 through the cable 5.
[0045] The specific process of constructing the main arch ring 3 is as follows:
[0046] T1. Cantilever cast the arch box of the current segment, and connect the arch box with the buckle tower by using the buckle cable 5, and tension the buckle cable 5 according to the buckle cable force obtained by multi-objective solution. After tensioning, the longitudinal offset angle and the lateral offset angle of the buckle cable 5 are monitored in real time. When the longitudinal offset angle and the lateral offset angle of the buckle cable 5 exceed the preset limit, an alarm is issued. The longitudinal offset angle refers to the offset angle in the vertical plane, and the lateral offset angle refers to the offset angle in the horizontal plane;
[0047] T2. Repeat the above steps until the main arch ring 3 is completely closed. After the closing is completed, remove the buckle cable 5, anchor cable and buckle tower.
[0048] The present invention provides a method for constructing a cantilevered arch bridge based on multi-objective optimization, which obtains a parametric finite element model through simulation parametric modeling, obtains analysis results through analysis of the parametric finite element model, and imports the analysis results into a multi-objective optimization program to achieve multi-objective solution, and obtains a cable force that meets the needs of achieving multiple goals, so that multiple goals can be taken into account during the construction process. This process can be implemented with reference to the relevant content in the doctoral dissertation "Cable force optimization and arch ring stress regulation during the construction period of a large-span cantilever cast concrete arch bridge" submitted by "Peng Wenping" in June 2020.
[0049] At the same time, in order to realize real-time monitoring during the construction process and realize monitoring of multiple engineering inspection targets, after the tensioning of the cable 5 is completed, the longitudinal offset angle and the lateral offset angle of the cable 5 are monitored in real time. By judging whether the longitudinal offset angle and the lateral offset angle exceed the preset limit, it is judged whether the working condition is normal. Specifically, when the lateral offset angle and the lateral offset angle of the cable 5 exceed the limit, it may indicate that there is an abnormality in the cable 5 or the tower, and timely inspection is required. The abnormal longitudinal offset angle generally corresponds to an abnormal state of the cable 5, and the abnormal lateral offset generally corresponds to an abnormal state of the tower, such as the tower being tilted or twisted.
[0050] The method of multi-objective solution has been fully documented in Peng Wenping’s doctoral dissertation: Research on cable force optimization and arch ring stress regulation during construction of large-span cantilever cast-concrete arch bridges, and will not be elaborated here.
[0051] Furthermore, the method further includes the following steps: after the tensioning of the cable 5 is completed, the lateral offset angle of the tensioned cable 5 is used as a statistical object, and the overlap of the value range of the lateral offset angle of the tensioned cable 5 in adjacent unit times is calculated, where the value range refers to the range between the minimum and maximum values of the lateral offset angle of the cable 5 in unit time. If the overlap in a certain adjacent unit time is lower than a preset value, and the overlap of a subsequent preset number of adjacent unit times meets the preset value, an alarm is issued. For example, the preset value of the overlap of the value range of the lateral offset angle of the cable 5 in adjacent unit time is set to 90%. Within a continuous 2h, with 0.2h as the unit time, a total of 10 units, if within 10 unit times, the preset value of the overlap of the value range of the lateral offset angle in adjacent units is between 93% and 95%, it indicates that the situation is normal. If between two unit times, for example, between the 5th unit time and the 6th unit time, the overlap of the value range of the lateral offset angle of the cable 5 is 88%, which is lower than the preset limit of 90%, and the overlap of the adjacent unit times is restored, it indicates that the tower may have tilted or twisted abnormally and needs to be inspected.
[0052] Further, the method further comprises the following steps: after the tensioning of the buckle cable 5 is completed, an offset angle monitoring device 26 is installed to realize real-time monitoring of the longitudinal offset angle and the lateral offset angle of the buckle cable 5, wherein the offset angle monitoring device 26 comprises: a fixed base 27, a support frame, two rotation monitoring units, a dual-axis motor 33, a first friction wheel 34 and a second friction wheel 35, wherein the support frame is arranged on the fixed base 27, the dual-axis motor 33 is arranged on the support frame, the first friction wheel 34 and the second friction wheel 35 are respectively connected to the two shafts of the dual-axis motor 33, and the The rotation monitoring unit includes a rotating ring 36 and a strain gauge 37. The rotating ring 36 is arranged on the support frame, and the strain gauge 37 is arranged on the inner wall of the rotating ring 36. The first friction wheel 34 and the second friction wheel 35 respectively contact one of the rotating rings 36 to drive the corresponding rotating ring 36 to rotate. After the tensioning of the buckle cable 5 is completed, the fixed base 27 is installed on the arch box, the buckle cable 5 passes through the two rotating rings 36, and the strain gauge 37 contacts the buckle cable 5. The dual-axis motor 33 is used to drive the rotating ring 36 to rotate reciprocatingly.
[0053] During the reciprocating rotation of the rotating ring 36, the strain gauge 37 is driven to rotate. During the rotation of the strain gauge 37, when the distance between the strain gauge 37 and the surface of the buckle cable 5 changes, a signal change will occur. Therefore, the angular deviation of the buckle cable 5 can be determined by judging the position change of the strain gauge 37 and the buckle cable 5.
[0054] The advantage of using the strain gauge 37 to detect the angle is that the anchor cable is formed by winding a steel bundle, and the surface may have bumps and depressions. By using the strain gauge 37 for detection, the signal change pattern of the strain gauge 37 during one rotation can be recorded. When the signal change pattern is highly consistent over a sustained period of time, it indicates that the state of the cable 5 is stable. When the signal changes from one regular state to another regular state, it indicates that the state of the cable 5 has changed.
[0055] Specifically, the support frame includes a support column 28 and a semi-tube type mounting plate, the support column 28 is arranged on the fixed base 27, the semi-tube type mounting plate is arranged on the support column 28, the semi-tube type mounting plate is provided with two mounting grooves 30, the rotating ring 36 is limited in the mounting grooves 30, and an opening should be provided on the semi-tube type mounting plate to allow the first friction wheel 34 and the second friction wheel 35 to contact the rotating ring 36.
[0056] Furthermore, in order to facilitate arrangement, the semi-tube type placement plate includes a plate body 29, a first closing plate 31 and a second closing plate 32. The first closing plate 31 and the second closing plate 32 are respectively fixed to the two ends of the plate body 29 by bolts, and the placement grooves 30 are respectively formed between the first closing plate 31 and the plate body 29 and between the second closing plate 32 and the plate body 29.
[0057] In order to limit the position of the rotating ring 36 , a limiting rib is provided on the side of the placement groove 30 , and a limiting groove matched with the limiting rib is provided on the side of the rotating ring 36 .
[0058] More specifically, the strain gauge 37 is configured to be U-shaped.
[0059] Furthermore, the method further includes the step of monitoring the cable forces of the cable 5 after the cable 5 is completed, and adjusting the cable forces of the cable 5 according to the monitoring results so that the cable forces of all the cable 5 meet the requirements of the multi-objective solution range.
[0060] The present embodiment provides a method for constructing a cast-in-place arch bridge based on multi-objective optimization, which obtains a parametric finite element model through simulation parametric modeling, obtains analysis results through analysis of the parametric finite element model, and imports the analysis results into a multi-objective optimization program to achieve multi-objective solution, thereby obtaining a cable force that meets the requirements of achieving multiple objectives, thereby achieving a balance of multiple objectives during the construction process.
[0061] In order to monitor the cable 5 during the construction process, during the construction of the main arch ring 3, the cable forces of the cable 5 that have been tensioned are monitored, and adjustments are made based on the monitoring results so that the cable forces of all the cable 5 meet the requirements of the multi-objective solution range.
[0062] Specifically, after the tensioning of the cable is completed, a cable force detection device is installed to monitor the cable force of the cable 5. The cable force monitoring device is used to monitor the cable force of the cable 5. The cable force monitoring device includes a bracket 6, a pressure component and two gripping components. The middle of the bracket 6 is provided with an intermediate placement bin 7. The pressure component includes an action device 11, a pressure gauge, a stroke metering device 12 and a pressure block 13. The action device 11 is fixed on the bracket 6. The pressure gauge is provided between the action device 11 and the pressure block 13. The pressure block 13 passes through the intermediate placement bin 7. The stroke metering device 12 is installed on the side of the pressure block 13 to measure the stroke of the pressure block 13. The two gripping components are respectively provided at both ends of the bracket 6. During operation, the gripping component is used to grip the cable 5, and then the action device 11 is used to drive the pressure block 13 to apply pressure to the cable 5. The real-time cable force is obtained by relying on the data of the pressure sensor and the stroke metering device 12, so as to realize the convenient test of the cable force.
[0063] Specifically, the actuating device 11 is configured as a cylinder or an electric push rod.
[0064] Specifically, the stroke metering device 12 includes a measuring wheel and a wheel speed meter. The circumference of the measuring wheel abuts against the pressure block 13. The wheel speed meter is used to measure the wheel speed of the measuring wheel. When the pressure block 13 moves, it drives the measuring wheel to rotate. The wheel speed meter measures the rotation of the measuring wheel to obtain the stroke of the pressure block 13.
[0065] In order to achieve stable pressure on the buckle cable 5, a first V-shaped groove 14 is provided at the bottom of the pressing block 13, and the buckle cable 5 is stuck in the V-shaped groove, so that the pressing block 13 can apply pressure stably.
[0066] Furthermore, both ends of the bracket 6 are respectively provided with an end placement bin 8, and the bottom of the end placement bin 8 is provided with a first ring outlet 9, a top port and a second ring outlet 10, and the top port is arranged between the first ring outlet 9 and the second ring outlet 10. The gripping assembly includes a gripping ring 15, a driving wheel 17, a first action wheel 18, a second action wheel 19, a motor 20, an top block 21 and a downward pressure driving device 23. The driving wheel 17, the first action wheel 18, the second action wheel 19 and the motor 20 are arranged in the end placement bin 8, and the motor 20 is connected to the driving wheel 17 for driving the driving wheel 17 to rotate. The first action wheel 18 and the second action wheel 19 are respectively arranged on both sides of the driving wheel 17 and are driven to rotate by the driving wheel 17. A notch 16 is provided on the grasping ring 15, and the notch 16 has a first end and a second end. During operation, the grasping ring 15 is pushed against by the first acting wheel 18 and / or the second acting wheel 19, and passes through the first ring outlet 9. The first end is located in the end placement bin 8, and the second end enters and exits the end placement bin 8 via the second ring outlet 10. The downward pressing drive device 23 is arranged at the top of the end placement bin 8, and the pushing block 21 is connected to the downward pressing drive device 23 and inserted into the end placement bin 8, corresponding to the pushing opening.
[0067] Under the above structural setting, when the motor 20 drives the driving wheel 17 to rotate, the driving wheel 17 drives the first acting wheel 18 and the second acting wheel 19 to rotate, and the first acting wheel 18 and the second acting wheel 19 drive the grasping ring 15 to rotate. During the rotation of the grasping ring 15, the notch 16 has a state of being located in the end placement bin 8 and a state of not being located in the end placement bin 8. When located in the end placement bin 8, it is in a grasping state. When not located in the end placement bin 8, the buckle rope 5 can be placed in the grasping ring 15 through the notch 16. After entering the grasping ring 15, the notch 16 enters the end placement bin 8 through the rotation of the first acting wheel 18, thereby grasping the buckle rope 5. After the grasping is completed, the downward pressure driving device 23 is used to drive the abutting block 21 to move, and the abutting block 21 extends out through the abutting opening to apply pressure to the buckle rope 5, thereby achieving stable grasping of the buckle rope 5. At the same time, after the abutting block 21 is extended, the abutting block 21 is located in the notch 16 , so that the gripping ring 15 cannot move, that is, the gripping ring 15 is locked by the action of the abutting block 21 .
[0068] In order to achieve stable pressure exerted by the push-up block 21 on the buckle cable 5 , the downward pressing drive device 23 is configured as a cylinder or an electric telescopic rod, and a second V-shaped groove 22 is provided at the bottom of the push-up block 21 .
[0069] In order to achieve a good gripping effect, the center angle of the gripping ring 15 corresponding to the notch 16 is 60-150 degrees.
[0070] In order to arrange the space reasonably, the gripping assembly also includes a first linkage wheel 24 and a second linkage wheel 25. The circumference of the first linkage wheel 24 fits the driving wheel 17 and the first action wheel 18, and the circumference of the second linkage wheel 25 fits the driving wheel 17 and the second action wheel 19.
[0071] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that the process, method, article or terminal device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or terminal device. In the absence of further restrictions, the elements defined by the sentence "include..." or "comprise..." do not exclude the existence of other elements in the process, method, article or terminal device including the elements. In addition, in this article, "greater than", "less than", "exceed" and the like are understood to exclude the number itself; "above", "below", "within" and the like are understood to include the number itself.
[0072] The above description of the embodiments is to facilitate the understanding and use of the present invention by those skilled in the art. It is obvious that those skilled in the art can easily make various modifications to the embodiments and apply the general principles described herein to other embodiments without creative work. Therefore, the present invention is not limited to the above embodiments. Improvements and modifications made by those skilled in the art based on the disclosure of the present invention without departing from the scope of the present invention should be within the protection scope of the present invention.
Claims
1. A method for construction of a suspended arch bridge based on multi-objective optimization, characterized in that: The steps include: The whole process of construction is simulated and parametrically modeled, a parametric finite element model is established, and the established parametric finite element model is analyzed, and relevant analysis results are extracted and output files are imported into the multi-objective optimization program to complete the multi-objective optimization solution of the reasonable construction cable force of the cantilever concrete arch bridge and obtain the cable force during construction; Construction of anchors and anchor towers on junction piers; According to the cable force obtained during construction by solving multiple objectives, the main arch ring is constructed, and the anchor is used as the rear anchor system of the main arch ring, and the anchor is anchored to the buckle tower through the anchor cable, and the other side of the buckle tower is anchored to the main arch ring through the cable; The specific process of constructing the main arch ring is as follows: The current segment arch box is cantilever cast, and the arch box is connected to the buckle tower by the buckle cable, and the buckle cable is tensioned according to the buckle cable force obtained by multi-objective solution. After the tensioning is completed, the longitudinal offset angle and the lateral offset angle of the buckle cable are monitored in real time. When the longitudinal offset angle and the lateral offset angle of the buckle cable exceed the preset limit, an alarm is issued. The longitudinal offset angle refers to the offset angle in the vertical plane, and the lateral offset angle refers to the offset angle in the horizontal plane. Repeat the above steps until the main arch ring is completed, and after the closure is completed, remove the buckle cables, anchor cables and buckle towers.
2. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 1, characterized in that: The method also includes the following steps: after the tensioning of the cables is completed, the lateral offset angle of the tensioned cables is used as the statistical object, and the overlap of the value range of the lateral offset angle of the tensioned cables in adjacent unit times is calculated; if the overlap in a certain adjacent unit time is lower than a preset value, and the overlap of a subsequent preset number of adjacent unit times meets the preset value, an alarm is issued.
3. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 2, characterized in that: It also includes the steps of: after the tensioning of the buckle cable is completed, installing an offset angle monitoring device to realize real-time monitoring of the longitudinal offset angle and the lateral offset angle of the buckle cable, the offset angle monitoring device includes: a fixed base, a support frame, two rotation monitoring units, a dual-axis motor, a first friction wheel and a second friction wheel, the support frame is arranged on the fixed base, the dual-axis motor is arranged on the support frame, the first friction wheel and the second friction wheel are respectively connected to the two shafts of the dual-axis motor, the rotation monitoring unit includes a rotating ring and a strain gauge, the rotating ring is arranged on the support frame, the strain gauge is arranged on the inner side wall of the rotating ring, the first friction wheel and the second friction wheel respectively contact one of the rotating rings to drive the corresponding rotating ring to rotate; after the tensioning of the buckle cable is completed, the fixed base is installed on the arch box, the buckle cable passes through the two rotating rings, the strain gauge contacts the buckle cable, and the dual-axis motor is used to drive the rotating ring to reciprocate.
4. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 3 is characterized in that: The support frame includes a support column and a semi-tube type placement plate, the support column is arranged on the fixed base, the semi-tube type placement plate is arranged on the support column, the semi-tube type placement plate is provided with two placement grooves, and the rotating ring limit is located in the placement grooves.
5. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 4, characterized in that: The semi-tube type placement plate includes a plate body, a first closing plate and a second closing plate. The first closing plate and the second closing plate are respectively fixed to the two ends of the plate body by bolts. The placement grooves are respectively formed between the first closing plate and the plate body and between the second closing plate and the plate body.
6. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 4, characterized in that: The side of the placement groove is provided with a limiting rib, and the side of the rotating ring is provided with a limiting groove matched with the limiting rib.
7. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 4, characterized in that: The strain gauge is arranged in a U shape.
8. A method for constructing a cantilevered arch bridge based on multi-objective optimization according to any one of claims 1 to 7, characterized in that: The method further includes the following steps: after the cable tensioning is completed, the cable forces are monitored, and adjustments are made according to the monitoring results so that the cable forces of all cables meet the requirements of the multi-objective solution range.
9. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 8, characterized in that: It also includes the following steps: after the cable is tensioned, a cable force detection device is installed to monitor the cable force, the cable force monitoring device includes a bracket, a pressure assembly and two gripping assemblies, an intermediate placement bin is provided in the middle of the bracket, the pressure assembly includes an actuating device, a pressure gauge, a stroke metering device and a pressure block, the actuating device is fixed on the bracket, the pressure gauge is provided between the actuating device and the pressure block, the pressure block passes through the intermediate placement bin, the stroke metering device is installed on the side of the pressure block, and is used to measure the stroke of the pressure block, and the two gripping assemblies are respectively provided at both ends of the bracket.
10. The method for constructing a cantilevered arch bridge based on multi-objective optimization according to claim 9, characterized in that: The actuating device is configured as a cylinder or an electric push rod.
Citation Information
Patent Citations
Arch bridge cantilever construction system and method
CN113235458A
Method and device for acquiring cable force of cable-stayed buckling method of Y-shaped arch bridge and medium
CN115983077A
Intelligent cable with fiber grating sensor or strain gauge sensor
CN216433324U
Bridge cable force detection device
CN216433345U
Cable bent tower deviation monitoring device
CN218723996U