Physical model construction method synchronized with engineering construction condition

By deepening the geometric decomposition and attribute information of the building BIM design model and combining 3D printing technology, the real-life sand table of the project has been constructed, which has solved the problem of refinement and intuitiveness of project progress management and improved the on-site management and control capabilities.

CN118940368APending Publication Date: 2024-11-12CHINA POWER CONSRTUCTION GRP GUIYANG SURVEY & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410970203.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing information fusion method cannot precisely control the project progress, and the construction characteristics of the unit project are not intuitive and lacks the visual management capabilities at the project construction site.

Method used

By geometric decomposition and deepening of the BIM design model of the target building, a BIM model of the construction process is constructed, and physical components are obtained through 3D printing. Finally, the real-life sand table of the project is built based on the physical components, so as to achieve refined management and intuitiveness of the project progress exhibit.

Benefits of technology

The on-site control capabilities have been greatly improved. Through the 3D printing technology of partitioned colors, materials and QR code labels, the construction characteristics of unit projects and division projects are more intuitive and visual, realizing dynamic visualization of construction process presentation and progress monitoring.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118940368A_ABST
    Figure CN118940368A_ABST
Patent Text Reader

Abstract

The invention discloses a physical model construction method synchronous with engineering construction conditions, and belongs to the technical field of water conservancy and hydropower engineering construction.According to the scheme, geometric decomposition is carried out on a target building BIM design model in combination with the project site actual construction progress, information deepening is carried out on decomposed unit engineering component attributes, a construction process BIM model is constructed, and the construction process BIM model is constructed; 3D printing is carried out on the BIM model in the construction process, entity components are obtained, the engineering progress and the material consumption degree of unit engineering components are verified, and finally a project construction condition live-action sand table is constructed based on the entity components and a sand table foundation. The problems that an existing information fusion method cannot finely control the project progress and the construction feature representation of the unit project is not intuitive are solved, the construction features of the unit project and the branch project are more intuitively and visually displayed, and the field control capability is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of water conservancy and hydropower engineering construction, and specifically relates to a physical model construction method synchronized with engineering construction conditions. Background Art

[0002] The progress management of hydropower and water conservancy projects plays a vital role in engineering projects. By rationally formulating and implementing engineering progress plans, strengthening progress tracking and monitoring, optimizing resource allocation, controlling project risks, and strengthening communication and collaboration, we can ensure that the projects are completed on time, with quality and quantity. At present, the main means of progress management at the technical level are: network planning technology (Gantt chart or Gantt chart) for construction period optimization and adjustment, forward line analysis method / critical path method (CPM) progress comparison and adjustment, information management system, etc. As an important engineering project management tool, network planning technology has the advantages of systematicity, flexibility, and scientificity. At the same time, it also has obvious disadvantages such as complexity, cumbersome calculations, high requirements for management personnel, and relatively poor visualization.

[0003] BIM technology has applications in project progress management, such as real-time progress monitoring, construction simulation and optimization, comprehensive information integration and collaborative work, and its virtual visualization provides a new technical solution for progress management, but it has disadvantages such as dependence on BIM software platform or display engine and lack of physical scene display and application. CN113807685A proposes a BIM-based hydraulic tunnel construction progress information management method, which divides and encodes a single tunnel model according to a certain step length, realizes the collection and effective management of various progress information in the tunnel construction process, and realizes multi-directional query.

[0004] 3D printing technology is in a stage of rapid development in the field of engineering construction, with its high construction efficiency, high printing accuracy, personalization, customization, and low cost. The technology maturity is constantly improving and its application fields are wide. CN111179727A uses a combination of physical sandbox and display screen to display information at all levels of on-site construction management in various forms, mainly to improve the experience of classroom education. CN116305385A designs a BIM model for 3D printing, and relies on the printed components to enter the corresponding data and post QR code information display, which basically realizes the construction method of combining BIM with 3D printing technology. Although the above patents involve 3D printing of building components and progress management based on 3D printed components, they lack the ability to integrate information at the unit engineering component level and refine progress, engineering quality and other information management on this basis. Summary of the invention

[0005] The purpose of the present invention is to address the problems that the existing information fusion methods cannot precisely control the progress of the project and the construction characteristics of the unit project are not intuitive, and propose a physical model construction method that is synchronized with the project construction situation. This scheme geometrically decomposes the BIM design model of the target building in combination with the actual construction progress of the project site, deepens the information on the attributes of the decomposed unit project components, constructs a BIM model of the construction process, and then 3D prints the BIM model of the construction process to obtain the physical components and verify the progress of the unit project components. Finally, based on the physical components and the progress of the project, a real-life sand table of the project is constructed, which solves the problems that the existing information fusion methods cannot precisely control the progress of the project and the construction characteristics of the unit project are not intuitive, and more intuitively and visually displays the construction characteristics of the unit project and the sub-project, greatly improving the on-site control capabilities.

[0006] In order to solve the above technical problems, the present invention provides a method for constructing a physical model in sync with the engineering construction situation, comprising the following steps:

[0007] S1. Create a construction process BIM model based on the BIM design model of the target building, and set attribute information of the construction process BIM model;

[0008] S2, 3D printing is performed based on the BIM model and attribute information of the construction process to obtain a physical component;

[0009] S3. Calculate the printing material consumption of the unit engineering components and verify the engineering progress and the degree of construction material consumption;

[0010] S4. Build a real-life sand table of the project construction situation based on physical components and engineering progress.

[0011] Preferably, the S1 comprises the following steps:

[0012] S11. Create a BIM design model of a target building and set design attribute information, where the design attribute information includes material parameters, design engineering quantities, design reports and drawing files;

[0013] S12, based on the BIM design model of the target building and the actual construction progress of the project site, geometric decomposition is performed, and the attribute information of the unit engineering components of the BIM design model of the target building is deepened with construction information, thereby constructing a BIM model of the construction process;

[0014] S13. Output the BIM model of the construction process through BIM design software.

[0015] Preferably, the step of deepening the construction information of the property information of the unit engineering components of the BIM design model of the target building comprises:

[0016] Combining design attribute information and construction information, the unit engineering components of the BIM model of the construction process are divided into several areas, and by setting labels in different areas, the construction of a virtual model synchronized with the on-site construction information of the building is completed; different labels represent different information.

[0017] Preferably, the geometric decomposition refers to geometrically dividing the BIM design model of the target building according to the WBS structure of the building and the actual situation on site; the attribute information deepening refers to assigning construction information to the BIM model components of the construction process according to the actual situation on site.

[0018] Preferably, S2 comprises the following steps:

[0019] S21, based on the attribute information of the BIM model of the construction process, modify and convert it according to the recognition format requirements of the 3D printing device to form a 3D model file of the BIM model of the construction process;

[0020] S22, using a 3D printing device, taking the 3D model file as input, and driving the 3D printing device to print a unit engineering component;

[0021] S23. For different unit engineering components, different identifiers are combined to print out the physical components.

[0022] Preferably, the identification includes:

[0023] Different areas are printed with materials of different colors or different materials as information on the project progress and quality inspection grade. Corresponding QR code labels are set on the surfaces of different unit project components, and the corresponding design attribute information, construction information and the absolute completion time information of the building constructed by the unit project are obtained by scanning the QR code labels.

[0024] Preferably, S3 comprises the following steps:

[0025] S31, obtaining the weight of the current physical component and the total weight of the completed physical components, and calculating the ratio between the two;

[0026] S32, obtaining the printing material consumption of the current unit engineering component and the printing material consumption of the completed engineering component, and calculating the ratio between the two;

[0027] S33, obtaining the material consumption of the unit project corresponding to the on-site construction of the current unit project component and the material consumption of the completed unit project and the ratio between the two;

[0028] S34, comparing the ratios calculated by S31, S32, and S33, if the differences among the three are within the self-defined range, the printing material consumption is basically matched with the material consumption of the unit project of on-site construction; if the differences among the three are not within the self-defined range, manual verification is performed.

[0029] Preferably, S4 comprises the following steps:

[0030] S41. Construct a physical sand table of the engineering building through the completed physical components;

[0031] S42. Based on the project site and engineering progress, combined with the physical sand table of the engineering buildings, a real-life sand table of the project construction situation is constructed.

[0032] Beneficial effects of the present invention:

[0033] 1. This solution geometrically decomposes the BIM design model of the target building in combination with the actual construction progress of the project site, deepens the information on the properties of the decomposed unit engineering components, constructs a BIM model of the construction process, and then 3D prints the BIM model of the construction process to obtain physical components and verify the engineering progress of the unit engineering components. Finally, based on the physical components and engineering progress, a real-life sand table of the project is constructed, which solves the problems that the existing information fusion method cannot precisely control the engineering progress and the construction characteristics of the unit engineering are not intuitive. It shows the construction characteristics of the unit engineering and sub-engineering in a more intuitive and visual way, greatly improving the on-site control capabilities.

[0034] 2. This scheme innovates the characteristic expression method of the physical components of the unit project and adopts the 3D printing technology of partition color (or material) + QR code label + time to more intuitively and visually display the construction characteristics of the unit project and the sub-project.

[0035] 3. The present invention realizes the matching of the proportional physical sand table with the on-site construction scene by constructing a physical sand table with real progress scene. Various types of engineering projects can carry out rich simulation demonstration applications based on the real-scene sand table, which greatly improves the on-site management and control capabilities.

[0036] 4. The present invention is based on a refined progress management mode of 3D printed components based on unit engineering components and their attribute information. The model's three-dimensional information, attribute information and 3D printing process control are associated to achieve a dynamic and visual presentation of the construction process.

[0037] 5. The present invention realizes the synchronization of monitoring the on-site construction situation and inspecting the engineering construction situation by comparing the relevant ratios of the printing material consumption, the material consumption of the unit project of on-site construction and the weight of the physical component, and at the same time, inspects the 3D printing process. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings. The drawings are only for the purpose of illustrating preferred embodiments and are not to be considered as limiting the present invention. Also, the same reference symbols are used throughout the drawings to represent the same parts.

[0039] Figure 1 A flow chart of a method for constructing a physical model in sync with the engineering construction situation of the present invention;

[0040] Figure 2 It is a schematic diagram of the overall process of the present invention;

[0041] Figure 3 It is a schematic diagram of printing different areas with different colors in an embodiment of the present invention. DETAILED DESCRIPTION

[0042] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific implementation method described herein is only an optimal embodiment of the present invention, which is only used to explain the present invention and does not limit the scope of protection of the present invention. All other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0043] Example 1: Figure 1 and Figure 2 As shown, a method for constructing a physical model in sync with the engineering construction situation includes the following steps:

[0044] S1. Create a construction process BIM model based on the BIM design model of the target building, and set the attribute information of the construction process BIM model.

[0045] Specifically, the S1 comprises the following steps:

[0046] S11. Create a BIM design model of a target building and set design attribute information, where the design attribute information includes material parameters, design engineering quantities, design reports and drawing files;

[0047] S12, based on the BIM design model of the target building and the actual construction progress of the project site, geometric decomposition is performed, and the attribute information of the unit engineering components of the BIM design model of the target building is deepened with construction information, thereby constructing a BIM model of the construction process;

[0048] S13. Output the BIM model of the construction process through BIM design software.

[0049] Specifically, the step of deepening the construction information of the property information of the unit engineering components of the BIM design model of the target building includes:

[0050] Combining design attribute information and construction information, the unit engineering components of the BIM model of the construction process are divided into several areas, and by setting labels in different areas, the construction of a virtual model synchronized with the on-site construction information of the building is completed; different labels represent different information.

[0051] It is understandable that the construction process BIM model is divided into several areas, and the identification is set in different areas, including: the model is further divided into two equal areas, left and right (or upper and lower), and different levels of color are assigned to represent different progress and quality inspection and evaluation level information. At the same time, it is necessary to prepare a QR code label corresponding to the unit project construction BIM model. By scanning the QR code, the design information and construction process information of the unit project can be viewed. It is also necessary to enter the absolute completion time information of the earliest and last completed unit project in a sub-project, sub-project or independent building composed of multiple unit projects.

[0052] Specifically, the geometric decomposition refers to dividing the BIM design model of the target building according to the WBS structure of the building; the attribute information deepening refers to assigning construction information to the BIM model components of the construction process according to the actual situation on site.

[0053] It can be understood that the geometric decomposition refers to the geometric subdivision of the BIM design model of the target building according to the WBS structure of the building and the actual situation on site; the attribute information deepening refers to the assignment of construction information to the BIM model components of the construction process according to the actual situation on site.

[0054] This embodiment innovates the characteristic expression method of the physical components of the unit project and adopts the 3D printing technology of partition color (or material) + QR code label + time to more intuitively and visually display the construction characteristics of the unit project and the sub-project.

[0055] S2. Perform 3D printing based on the BIM model and attribute information of the construction process to obtain physical components.

[0056] Specifically, S2 includes the following steps:

[0057] S21, based on the attribute information of the BIM model of the construction process, modify and convert it according to the recognition format requirements of the 3D printing device to form a 3D model file of the BIM model of the construction process;

[0058] It is understandable that in order to save printing materials and printing time, the component model of the unit engineering component can also be printed in a hollow form (the surface is continuous and complete, and the middle is empty) or other forms, wherein the contour thickness is determined comprehensively based on the printing ratio, material raw materials, and the structural complexity of the target building.

[0059] S22, using a 3D printing device, taking the 3D model file as input, and driving the 3D printing device to print a unit engineering component;

[0060] S23. For different unit engineering components, different identifiers are combined to print out the physical components.

[0061] Specifically, the identification includes:

[0062] Different areas are printed with materials of different colors or different materials as information on the project progress and quality inspection grade. Corresponding QR code labels are set on the surfaces of different unit project components, and the corresponding design attribute information, construction information and the absolute completion time information of the building constructed by the unit project are obtained by scanning the QR code labels.

[0063] This embodiment is based on a refined progress management mode of 3D printing components of unit engineering components and their attribute information. The three-dimensional information and attribute information of the model are associated with the 3D printing process control, thereby realizing the dynamic visualization presentation of the construction process.

[0064] S3. Calculate the printing material consumption of the unit engineering components and verify the engineering progress and the degree of construction material consumption.

[0065] Specifically, S3 includes the following steps:

[0066] S31, obtaining the weight of the current physical component and the total weight of the completed physical components, and calculating the ratio between the two;

[0067] S32, obtaining the printing material consumption of the current unit engineering component and the printing material consumption of the completed engineering component, and calculating the ratio between the two;

[0068] S33, obtaining the material consumption of the unit project corresponding to the on-site construction of the current unit project component and the material consumption of the completed unit project and the ratio between the two;

[0069] S34, comparing the ratios calculated by S31, S32, and S33, if the differences among the three are within the self-defined range, the printing material consumption is basically matched with the material consumption of the unit project of on-site construction; if the differences among the three are not within the self-defined range, manual verification is performed.

[0070] S4. Build a real-life sand table of the project construction situation based on physical components and engineering progress.

[0071] Specifically, S4 includes the following steps:

[0072] S41. Construct a physical sand table of the engineering building through the completed physical components;

[0073] S42. Based on the project site and engineering progress, combined with the physical sand table of the engineering buildings, a real-life sand table of the project construction situation is constructed.

[0074] This embodiment geometrically decomposes the BIM design model of the target building in combination with the actual construction progress of the project site, deepens the information of the decomposed unit engineering component attributes, builds a BIM model of the construction process, and then obtains the physical components and verifies the engineering progress of the unit engineering components by 3D printing the BIM model of the construction process. Finally, based on the physical components and the sand table foundation, a real-life sand table of the project construction situation is built. This solves the problem that the existing information fusion method cannot finely control the engineering progress and the construction characteristics of the unit engineering are not intuitive. It more intuitively and visually displays the construction characteristics of the unit engineering and the sub-engineering, greatly improving the on-site control capabilities.

[0075] Furthermore, Example 2 is an extension of Example 1, and is specifically as follows: Figure 1 and Figure 2 As shown, including:

[0076] S1: Create a BIM design model of the target building in the WBS unit and set the BIM model attribute information of the construction process.

[0077] S1-1: Create a BIM design model of the target building for progress management, and simultaneously improve its attribute information, mainly including: material parameters, design engineering quantities, design reports and drawing files.

[0078] S1-2: Based on the BIM design model of the target building and the actual construction progress of the project site, geometric decomposition and attribute information deepening are carried out to build a BIM model of the construction process. Geometric decomposition refers to the segmentation of the BIM design model of the target building according to the WBS structure of the building (divided into unit projects, sub-projects, sub-projects and unit projects); after the segmentation, the components of the unit project BIM model correspond to the unit project entities of the building. Attribute information deepening is to give construction information to the unit project components of the BIM design model of the target building according to the actual situation on site, including construction logs / weekly reports / monthly reports, progress information, material consumption, engineering measurement, and quality inspection and evaluation information.

[0079] S1-3: Combined with the attribute information of the unit project BIM model, the model can be further divided into two equal areas, left and right (or top and bottom), and given different levels of color, representing different progress and quality inspection and evaluation level information. At the same time, it is necessary to prepare a QR code label corresponding to the unit project construction BIM model. By scanning the QR code, you can view the design information and construction process information of the unit project. It is also necessary to enter the absolute completion time information of the earliest and last completed unit project in a certain part of the project or independent building. At this point, the construction of a virtual model synchronized with the on-site construction information of the building has been completed.

[0080] S1-4: Use BIM design software to output the WBS unit engineering construction BIM model (including the above attribute information) and simultaneously output the overall model of the target building.

[0081] S2: Perform 3D printing based on the unit engineering BIM model and output physical components.

[0082] S2-1: The WBS unit engineering BIM model file is modified and converted according to the format requirements that can be recognized by the 3D printing equipment. Generally, software such as Mesh mixer, Cura and Slic3r are used to complete this work. In order to save printing materials and printing time, the above component model can also be converted into a hollow shape (the surface is continuous and complete, and the middle is empty). The contour thickness is determined based on the printing ratio, material raw materials, and the structural complexity of the target building. It is preferably 6 to 20 mm, and the contour thickness value of the printed component at the bottom elevation is large, and the contour thickness value of the printed component at the high elevation is small.

[0083] S2-2: Input the file formed by S2-1 into the 3D printing device, and drive the 3D printing device in real time to print the unit engineering components. At the same time, the partition color information, QR code label information, and completion time information of the unit engineering BIM model attributes need to be input into the 3D printing device, and matched and associated with the corresponding material color control module and printing information control module.

[0084] S2-3: During the printing process, for specific unit engineering components, they are divided into two areas, left and right (or top and bottom), for printing, with a clear dividing line between the areas; based on the WBS unit engineering construction BIM model of S1-3, different colors or materials are used to print different areas according to their progress completion status (ahead, behind, on time) and quality inspection and evaluation level (qualified, excellent), to intuitively express the progress and quality of the parts. Figure 3 As shown in the figure, the first color bar indicates that the progress is on time and the quality is satisfactory. The second color bar indicates that the progress is behind schedule and the quality is excellent.

[0085] S2-4: After the construction unit engineering components are printed by area and color, a QR code component is directly printed at a suitable position where it can be displayed using a 3D printing device to form a unified whole with the aforementioned components.

[0086] S2-5: The 3D printed components of the corresponding unit projects that are completed earliest or last in a certain part of a project or an independent building shall be directly printed at the appropriate location to display the actual construction completion time of the corresponding unit projects, so as to intuitively grasp the absolute time. The time information component shall form an integral part with the aforementioned 3D printed components.

[0087] S2-6: For unit engineering components printed in a hollow form, they can also be printed as transparent components, with small bulbs of different colors (corresponding to the colors in S1-3 and S2-3) built in the components. Different progress and quality inspection level information can be reflected through different light colors of the bulbs.

[0088] S2-7: When the 3D printing equipment has the ability to print large components, the overall model of the target building in S1-4 can be directly input. When the attribute information of a unit project is adjusted to the completed state, the 3D printing equipment is automatically driven through data link to print the unit project components according to the S2 process, directly forming the overall progress physical entity model.

[0089] S2-8: Calculate the printing material consumption of unit engineering components, and weigh the 3D printed unit engineering components, calculate the current component weight, the total weight of the components of the completed engineering parts and the ratio between the two; calculate the printing material consumption of the current unit engineering and the completed engineering parts and the ratio between the two; calculate the material consumption of the unit engineering corresponding to the on-site construction of the current unit engineering components, the material consumption of the completed engineering parts and the ratio between the two; conduct a horizontal comparison. If the above ratios are equal or similar, it means that the printing and construction material consumption of the current unit engineering is basically matched with the printing and material consumption of the completed engineering parts; if there is a large difference in the ratio between the two, further manual verification is required.

[0090] S3: Construct a physical sandbox of the engineering building that is synchronized with the actual progress on site.

[0091] S3-1: The 3D printed components corresponding to the completed unit projects form the sand table foundation through stacking and pasting. The 3D printed components corresponding to the newly completed unit projects are updated on the existing basis, that is, the virtual progress appearance is restored to the physical real scene sand table.

[0092] S3-2: In order to better present the actual appearance of the site, the topographic information after the excavation of the project foundation pit can be processed and combined with the physical sand table of the engineering building to form a real-scene sand table of the project, so as to realize the physical presentation of the on-site construction scene.

[0093] S4: Application of physical sandbox for engineering projects synchronized with the actual progress on site.

[0094] 1) Sand table simulation of the construction plan. The construction machinery and construction site layout on site are 3D printed in equal proportion and placed in the corresponding design position on the sand table. The feasibility and effect of the construction plan can be deduced and demonstrated based on the real scene of the sand table.

[0095] 2) Sand table simulation of safety control measures. The construction site, machinery layout, safety measures and facilities in the process are 3D printed in equal proportions and placed in the corresponding design positions on the sand table. The layout of components is dynamically adjusted in combination with the construction process to realize safety hazard inspection based on the real scene of the sand table and demonstration of safety control plans.

[0096] 3) Sand table simulation for disaster response and risk assessment. For example, for flood simulation, appropriate water flow input (matching the characteristic flood of the corresponding frequency) can be set in the upper reaches of the river, and the flood risk and flood retreat process faced by the project area can be visually observed on the sand table when the characteristic flood passes. For example, for rockfall geological disasters, stones of a reasonable volume can be placed on the steep part of the sand table to simulate the rolling process of rocks falling from high places, the landing area, and related damage information.

[0097] 4) Virtual-real comparison and mutual verification of real scene simulation and virtual space simulation. Based on the construction process BIM model constructed by S1-2, virtual simulation analysis is carried out according to the supporting knowledge base and algorithm library, and the output results are compared with the real scene sand table simulation results. The two verify the simulation results to ensure the correctness of the results.

[0098] Example 3: In conjunction with the progress control process of a concrete gravity dam of a hydropower station, the specific implementation steps of the method of the present invention are discussed as follows:

[0099] The first step is to construct a typical dam section and the overall BIM design model of the concrete dam, including the concrete structure of the retaining dam section and the overflow dam section; simultaneously improve its attribute information, mainly including: material parameters (concrete strength grade, grading, etc.), design engineering quantity (overall concrete engineering quantity of the dam, single dam section engineering quantity), design documents (design report, calculation draft and design drawings), etc.

[0100] The second step is to hand over the BIM design model to the construction site participating units, and conduct geometric decomposition and attribute information deepening in combination with the actual construction progress of the project site to build a BIM model of the construction process. For example, according to the on-site WBS model structure decomposition method, the 105.00-108.00m elevation of the 2# retaining dam section is regarded as a concrete pouring warehouse unit project, that is, the BIM model of this dam section is segmented; the 105.00m elevation plane and the 108.00m elevation plane can be used as two segmentation planes to perform segmentation operations with the BIM model of the dam section to form the unit engineering BIM model component corresponding to the unit engineering. At the same time, the corresponding construction information is given to the unit engineering BIM model component, including construction log / weekly / monthly report, progress information (opening warehouse, first warehouse, acceptance time, etc.), material consumption (manpower, machine hours, etc.), engineering measurement (concrete engineering quantity, steel bar quantity, water stop engineering quantity, etc.), quality inspection and evaluation information (inspection and evaluation level of the concrete pouring warehouse, flatness, concrete test information, acceptance form, etc.), etc.

[0101] Step 3: Output the unit engineering BIM model components (including attribute information) as a separate BIM model file.

[0102] The fourth step is to modify and convert the unit engineering BIM model file according to the format requirements that can be recognized by the 3D printing equipment deployed on site. This work is generally completed using software such as Mesh mixer, Cura and Slic3r. The specific implementation process is as follows:

[0103] 1) Determine the formats supported by the 3D printing device. STL (Stereo Lithography) is a universal interface format used by 3D printing manufacturing equipment, but different 3D printing devices may also support other formats, such as OBJ, DAE, AMF, etc.

[0104] 2) Export the BIM model to an intermediate format. The BIM model can be exported to IFC format.

[0105] 3) Convert the intermediate format to a format supported by the 3D printing device by using specialized conversion software or plug-ins.

[0106] 4) Check and repair the STL file. You can use special STL file editing software to check and repair these errors.

[0107] 5) Import the STL file into the 3D printing slicing software. The slicing software is used to cut the 3D model into multiple thin layers and generate instructions to guide the 3D printer to print layer by layer.

[0108] 6) In the slicing software, you can adjust the parameters of the 3D model, such as setting the printing speed, layer thickness, filling density, etc. Then, use the slicing function to cut the model into multiple thin layers and generate printing instructions.

[0109] Step 5: Send the printing command to the 3D printer, set the printing scale to 1:500, and start the printing process. Output the 3D printed unit engineering component.

[0110] Step 6. Based on the attribute information of the concrete pouring bin unit project at an elevation of 105.00 to 108.00 m in the 2# retaining dam section, determine its progress completion status and quality inspection and evaluation level. Assume that the progress status of the unit project is: on time and the quality inspection and evaluation level is: excellent. The front and back sides of the above-mentioned 3D printed components can be manually painted light yellow and light blue with paint. (The initial setting of the progress completion status (ahead, behind, on time) corresponds to (yellow, light yellow, blue);) The quality inspection and evaluation level (qualified, excellent) corresponds to (purple, light blue); It is also possible to cover the surface of the typical surface of the 3D printed unit engineering component with paper of the corresponding color. At the same time, a QR code label (conventional technology) is generated based on the design information and construction information of the unit engineering component. The QR code label can be pasted on the surface of the 3D printed unit engineering component, or the QR code can be directly embedded in the component through laser printing / 3D.

[0111] Step 7: The 3D printed components corresponding to the completed engineering unit projects are stacked and pasted to form the sand table foundation. The above-mentioned completed 3D printed unit engineering components are placed at the elevation of 105.00-108.00m of the 2# retaining dam section. Its upstream and downstream air surfaces directly display its progress and quality information. On-site personnel can scan the QR code on the component to view the design and construction information of the 2# dam section 105.00-108.00m elevation pouring bin. The concrete gravity dam sand table model is synchronized with the actual on-site pouring progress, realizing the physical restoration of the progress appearance.

[0112] Step 8. In order to better present the actual appearance of the project site, the topographic information after the excavation of the concrete gravity dam foundation of the power station can be processed and combined with the physical sand table of the engineering building to form a real-scene sand table of the project, realizing the physical presentation of the on-site construction scene.

[0113] Step 9: Carry out engineering application based on the above project real-scene sand table. Typical application scenarios are as follows:

[0114] 1) Sand table simulation of the construction plan. The construction machinery and construction site layout on site are 3D printed in equal proportion and placed in the corresponding design position on the sand table. The feasibility and effect of the construction plan can be deduced and demonstrated based on the real scene of the sand table.

[0115] 2) Sand table simulation of safety control measures. The construction site, machinery layout, safety measures and facilities in the process are 3D printed in equal proportions and placed in the corresponding design positions on the sand table. The layout of components is dynamically adjusted in combination with the construction process to realize safety hazard inspection based on the real scene of the sand table and demonstration of safety control plans.

[0116] 3) Sand table simulation for disaster response and risk assessment. For example, for flood simulation, appropriate water flow input (matching the characteristic flood of the corresponding frequency) can be set in the upper reaches of the river, and the flood risk and flood retreat process faced by the project area can be visually observed on the sand table when the characteristic flood is moving. For example, for rockfall geological disasters, stones of a reasonable volume can be placed on the steep part of the sand table to simulate the rolling process of rocks falling from high places, the landing area, and related damage information.

[0117] 4) Virtual-real comparison and mutual verification of real scene simulation and virtual space simulation. Based on the constructed BIM model of the construction process, virtual simulation analysis is carried out according to the supporting knowledge base and algorithm library, and the output results are compared with the real scene sand table simulation results. The two verify the simulation results to ensure the correctness of the results.

[0118] The above specific embodiments are preferred embodiments of the present invention, and are not intended to limit the specific implementation scope of the present invention. The scope of the present invention includes but is not limited to the present specific embodiments. All equivalent changes made in accordance with the shape, structure, and method of the present invention are within the protection scope of the present invention.

Claims

1. A method for building a physical model in sync with the construction situation, It is characterized in that The steps include: S1. Create a construction process BIM model based on the BIM design model of the target building, and set attribute information of the construction process BIM model; S2, 3D printing is performed based on the BIM model and attribute information of the construction process to obtain a physical component; S3. Calculate the printing material consumption of the unit engineering components and verify the engineering progress and the degree of construction material consumption; S4. Build a real-life sand table of the project construction situation based on physical components and engineering progress.

2. A method for constructing a physical model in sync with the engineering construction situation according to claim 1, It is characterized in that The S1 comprises the following steps: S11. Create a BIM design model of a target building and set design attribute information, where the design attribute information includes material parameters, design engineering quantities, design reports and drawing files; S12, based on the BIM design model of the target building and the actual construction progress of the project site, geometric decomposition is performed, and the attribute information of the unit engineering components of the BIM design model of the target building is deepened with construction information, thereby constructing a BIM model of the construction process; S13. Output the BIM model of the construction process through BIM design software.

3. A method for constructing a physical model in sync with the engineering construction situation according to claim 2, It is characterized in that The deepening of the construction information of the attribute information of the unit engineering components of the BIM design model of the target building includes: Combining design attribute information and construction information, the unit engineering components of the BIM model of the construction process are divided into several areas, and by setting labels in different areas, the construction of a virtual model synchronized with the on-site construction information of the building is completed; different labels represent different information.

4. A method for constructing a physical model in sync with the engineering construction situation according to claim 3, Features: The geometric decomposition refers to geometrically dividing the BIM design model of the target building according to the WBS structure of the building and the actual situation on site; the attribute information deepening refers to assigning construction information to the BIM model components of the construction process according to the actual situation on site.

5. A method for constructing a physical model in sync with the engineering construction situation according to claim 1, It is characterized in that The S2 comprises the following steps: S21, based on the attribute information of the BIM model of the construction process, modify and convert it according to the recognition format requirements of the 3D printing device to form a 3D model file of the BIM model of the construction process; S22, using a 3D printing device, taking the 3D model file as input, and driving the 3D printing device to print a unit engineering component; S23. For different unit engineering components, different identifiers are combined to print out the physical components.

6. A method for constructing a physical model in sync with the engineering construction situation according to claim 5, It is characterized in that The identification includes: Different areas are printed with materials of different colors or different materials as information on the project progress and quality inspection grade. Corresponding QR code labels are set on the surfaces of different unit project components, and the corresponding design attribute information, construction information and the absolute completion time information of the building constructed by the unit project are obtained by scanning the QR code labels.

7. A method for constructing a physical model in sync with the engineering construction situation according to claim 1, It is characterized in that The S3 comprises the following steps: S31, obtaining the weight of the current physical component and the total weight of the completed physical components, and calculating the ratio between the two; S32, obtaining the printing material consumption of the current unit engineering component and the printing material consumption of the completed engineering component, and calculating the ratio between the two; S33, obtaining the material consumption of the unit project corresponding to the on-site construction of the current unit project component and the material consumption of the completed unit project and the ratio between the two; S34, comparing the ratios calculated by S31, S32, and S33, if the differences among the three are within the self-defined range, the printing material consumption is basically matched with the material consumption of the unit project of on-site construction; if the differences among the three are not within the self-defined range, manual verification is performed.

8. A method for constructing a physical model in sync with the engineering construction situation according to claim 1, It is characterized in that The S4 comprises the following steps: S41. Construct a physical sand table of the engineering building through the completed physical components; S42. Based on the project site and engineering progress, combined with the physical sand table of the engineering building, a real-life sand table of the project construction situation is constructed.