Project risk management and control method, equipment, medium and product

Through multi-dimensional risk identification and evaluation, combined with project promotion data, automated risk monitoring and response strategy formulation, the problem of inefficient risk management in the existing technology is solved, and the efficiency and accuracy of project risk management is achieved.

CN118941093APending Publication Date: 2024-11-12NANJING NINGZHENG ENG CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411168670.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing technology is inefficient in project risk control and cannot conduct risk monitoring in depth at every angle. Especially in projects with large operating areas and many cross-operations, it is difficult to meet the risk control requirements under the new situation.

Method used

By obtaining project R&D plans for multi-dimensional risk identification, risk assessment is carried out based on a collection of risk information, obtaining risk levels, forming a risk control list, and combining project promotion data for risk monitoring, identifying key risk points, conducting risk response analysis and strategy formulation, and using Automation tools and systems integrate to collect data in real time or regularly, reducing frequent access by on-site managers.

Benefits of technology

It improves the efficiency and accuracy of project risk monitoring and management, can automate risk assessment, ensure timely response to project risks, and improves the transparency and comprehensibility of risk management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118941093A_ABST
    Figure CN118941093A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of risk management and control, in particular to a project risk management and control method and device, a medium and a product, and the method comprises the steps: carrying out the multi-dimensional risk identification based on a project research and development plan, obtaining a risk information set, carrying out the risk assessment based on the risk information set, obtaining a risk level corresponding to each risk description, and carrying out the management and control of the project risk. And integrating the risk information set and the risk level corresponding to each risk description to obtain a risk management and control list. And then risk monitoring is carried out based on the project promotion data and the risk management and control list, a key risk point is determined, and finally, risk coping analysis is carried out on the key risk point, and a risk coping strategy is determined. Through an automatic tool and system integration mode, project promotion data can be collected in real time or at regular intervals, a manager does not need to frequently go to a project site, risk assessment is automatically carried out based on the project promotion data and a risk management and control list, and the efficiency and accuracy of project risk monitoring management are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of risk management and control, and in particular to a project risk management and control method, equipment, medium and product. Background Art

[0002] During the production operation of the project, in order to ensure the safety of the production operation, it is often necessary to provide the operators with necessary safety risk training before the operation, and to perform corresponding risk monitoring operations during the production operation to avoid the occurrence of danger.

[0003] The existing risk monitoring methods are as follows: For various high-risk operations at the project operation site, safety managers conduct on-site risk control through on-site inspections and spot checks. However, this carpet-style inspection method that relies on safety managers to go deep into the site cannot go deep into every angle of the site, which can easily lead to inadequate project risk control. At the same time, for projects with large operating areas and many cross-operations, the method of in-depth on-site risk control is inefficient and cannot meet the requirements of risk control under the new situation.

[0004] Therefore, how to solve the above-mentioned defects in risk management is an urgent problem to be solved by technical personnel in this field. Summary of the invention

[0005] The purpose of this application is to provide a project risk management method, equipment, medium and product to solve at least one of the above technical problems.

[0006] The above invention objectives of the present application are achieved through the following technical solutions: In the first aspect, the present application provides a project risk management method, which adopts the following technical solution: A project risk management method, comprising: Acquire a project development plan, perform multi-dimensional risk identification based on the project development plan, and obtain a risk information set, wherein the risk information set includes: multiple risk dimensions and multiple risk descriptions corresponding to each risk dimension; Performing risk assessment based on the risk information set to obtain a risk level corresponding to each of the risk descriptions, and obtaining a risk management list by combining the risk information set and the risk level corresponding to each of the risk descriptions; Obtain project progress data, and conduct risk monitoring based on the project progress data and the risk control list to determine key risk points; Conduct risk response analysis on the key risk points, determine risk response strategies, and send the risk response strategies to the project leader so that the project leader can respond to the risks of project advancement.

[0007] By adopting the above technical solution, multi-dimensional risk identification is performed based on the project development plan to obtain a risk information set. Then, risk assessment is performed based on the risk information set to obtain the risk level corresponding to each risk description, and the risk information set and the risk level corresponding to each risk description are combined to obtain a risk control list. Then, risk monitoring is performed based on the project advancement data and the risk control list to determine the key risk points. Finally, risk response analysis is performed on the key risk points to determine the risk response strategy, and the risk response strategy is sent to the project leader. Through automated tools and system integration, project advancement data can be collected in real time or regularly without the need for managers to frequently visit the project site, and risk assessment is automatically performed based on the project advancement data and the risk control list, thereby improving the efficiency and accuracy of project risk monitoring and management.

[0008] In a preferred example, the present application may be further configured as follows: the risk monitoring based on the project progress data and the risk control list to determine key risk points includes: Based on the risk dimensions in the risk control list, the project progress data is classified to obtain project sub-data corresponding to each risk dimension; Obtain a target analysis method corresponding to a target risk dimension, perform risk analysis on the target project sub-data corresponding to the target risk dimension according to the target analysis method, and determine key risk points, wherein the target risk dimension is any one of the risk dimensions.

[0009] In a preferred example, the present application may be further configured as follows: performing risk analysis on the target project sub-data corresponding to the target risk dimension according to the target analysis method to determine key risk points, including: When the target risk dimension is construction safety, visual analysis is performed on the first project sub-data of the image type in a visual analysis manner to determine a visual analysis result, wherein the first project sub-data is a monitoring image of the construction site; When the target risk dimension is delivery risk, a progress deviation analysis is performed on the second project sub-data according to the project progress monitoring method to determine a progress deviation analysis result, wherein the second project sub-data is progress data representing the actual progress of the project; The key risk points are determined by combining the visual analysis results and the progress deviation analysis results.

[0010] In a preferred example, the present application may be further configured as follows: when the key risk point is delivery delay, the risk response analysis is performed on the key risk point to determine the risk response strategy, including: Extract key information based on the progress report in the second project sub-data to determine the current progress of the project and the planned progress of the project, wherein the current progress of the project lags behind the planned progress of the project; Based on the current progress of the project and the planned progress of the project, a cause analysis is performed to determine the cause of the delayed progress. When the cause of the delayed progress is insufficient human resources, the risk response strategy is determined to be personnel scheduling.

[0011] In a preferred example, the present application may be further configured as follows: after the risk level corresponding to the risk information set and each risk description is integrated to obtain a risk control list, the following further includes: Performing visual display analysis based on the multiple risk dimensions in the risk information set to determine a multi-dimensional display model; The risk control list is visualized in the multi-dimensional display model, wherein multiple risk descriptions corresponding to the same risk dimension are within the same dimension in the multi-dimensional display model, and the risk level is used to determine the display form.

[0012] In a preferred example, the present application may be further configured as follows: performing risk assessment based on the risk information set to obtain a risk level corresponding to each risk description includes: Performing a quantitative assessment based on the target risk description in the risk information set to determine the risk possibility and risk impact degree corresponding to the target risk description, wherein the target risk description is any risk description; A risk assessment matrix is ​​obtained, and a location point is determined based on the risk assessment matrix, the risk possibility and the risk impact degree corresponding to each of the target risk descriptions, to obtain a risk level corresponding to each of the risk descriptions.

[0013] In a second aspect, the present application provides an electronic device, which adopts the following technical solution: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute the above-mentioned project risk management method.

[0014] In a third aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution: A computer-readable storage medium stores a computer program, which, when executed in a computer, causes the computer to execute the project risk management method described above.

[0015] In a fourth aspect, the present application provides a computer program product, which adopts the following technical solution: A computer program product includes a computer program, and when the computer program is executed by a processor, the project risk management method is implemented.

[0016] In summary, the present application includes at least one of the following beneficial technical effects: Based on the project development plan, multi-dimensional risk identification is carried out to obtain a risk information set. Then, risk assessment is carried out based on the risk information set to obtain the risk level corresponding to each risk description, and the risk information set and the risk level corresponding to each risk description are combined to obtain a risk control list. Then, risk monitoring is carried out based on the project progress data and the risk control list to determine the key risk points. Finally, risk response analysis is carried out on the key risk points, risk response strategies are determined, and the risk response strategies are sent to the project leader. Through automated tools and system integration, project progress data can be collected in real time or regularly without the need for managers to frequently visit the project site, and risk assessment is automatically carried out based on the project progress data and the risk control list, which improves the efficiency and accuracy of project risk monitoring and management. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a flowchart of a project risk management method in one embodiment of the present application; Figure 2 It is a structural schematic diagram of a project risk management and control device in one embodiment of the present application; Figure 3 It is a structural schematic diagram of an electronic device according to one embodiment of the present application. DETAILED DESCRIPTION

[0018] The following combination Figures 1 to 3 This application is described in further detail.

[0019] This specific embodiment is merely an explanation of the present application and is not a limitation of the present application. After reading this specification, those skilled in the art may make modifications to the present embodiment without any creative contribution as needed, but as long as they are within the scope of the present application, they are protected by the patent law.

[0020] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0021] In addition, the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article, unless otherwise specified, generally means that the associated objects before and after are in an "or" relationship.

[0022] The embodiments of the present application are further described in detail below in conjunction with the drawings in the specification.

[0023] The embodiment of the present application provides a project risk management method, which is executed by an electronic device, which can be a server or a terminal device, wherein the server can be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides cloud computing services. The terminal device can be a smart phone, a tablet computer, a laptop computer, a desktop computer, etc., but is not limited to this. The terminal device and the server can be directly or indirectly connected via wired or wireless communication, and the embodiment of the present application does not limit this. Figure 1 As shown, the method includes step S101, step S102, step S103 and step S104, wherein: Step S101: Obtain a project development plan, perform multi-dimensional risk identification based on the project development plan, and obtain a risk information set, wherein the risk information set includes: multiple risk dimensions and multiple risk descriptions corresponding to each risk dimension.

[0024] For the embodiment of the present application, the project development plan is used to provide detailed information and context of the project, and to help identify and analyze potential risks. Since the project development plan provides the team with a comprehensive view of project goals, tasks, resources, schedules, and expected results, the information included in the project development plan is essential for risk identification. The information items included in the project development plan can be set by the user according to actual conditions, and the embodiment of the present application is no longer limited. The project development plan includes but is not limited to: project goals and scope, task decomposition and arrangement, resource allocation, key milestones, project constraints and assumptions, etc. In the process of project advancement, due to the complexity of the project and the large amount of work, there will be multi-dimensional risks in the process of project advancement, wherein the risk dimensions include but are not limited to: technical risks, delivery risks, construction safety risks, market risks, financial risks, supply chain risks, etc., and each risk dimension is closely related to the successful implementation of the project. Furthermore, for each risk dimension, an in-depth risk identification is conducted on the project R&D plan to identify the detailed risks of the risk dimension in the project R&D plan. The risk identification methods include but are not limited to: brainstorming, Delphi method, SWOT analysis, etc., and the analyzed risk details are recorded as risk descriptions to ensure that each risk description can be clearly and specifically described and include sufficient information for subsequent risk assessment and management.

[0025] Step S102: Perform risk assessment based on the risk information set to obtain the risk level corresponding to each risk description, and obtain a risk management list by combining the risk information set and the risk level corresponding to each risk description.

[0026] For the embodiment of the present application, a quantitative assessment is performed based on the risk dimensions and corresponding risk descriptions in the risk information set to determine the risk level corresponding to the risk description. For the quantitative assessment, a quantitative assessment model is obtained, and historical data is input into the quantitative assessment model for risk assessment to determine the probability and impact of each risk description, and then the corresponding risk level is determined, wherein the historical data is the probability and impact of each risk in the completed project, and the risk level is usually expressed as high, medium, and low, which is used to reflect the comprehensive assessment results of the possibility, impact, and controllability of the risk corresponding to the risk description. Then, the risk information set and the risk level corresponding to each risk description are combined to obtain a risk control list. The risk control list facilitates the project leader to clearly understand the various risks and their risk levels in the project, improves the transparency of risks, and enables team members to more accurately identify and understand potential risks in the project.

[0027] Step S103: Obtain project progress data, and conduct risk monitoring based on the project progress data and the risk management and control list to determine key risk points.

[0028] For the embodiment of the present application, the project advancement data is data that can characterize the actual progress, cost, quality, resource use, etc. of the project. There are many ways to obtain the project advancement data, which are not limited in the embodiment of the present application. For example, the electronic device is connected to the project management system to directly export or query the required project advancement data; the project advancement data is obtained through the progress report, cost report or other report regularly submitted by the project team. Then, risk monitoring is performed based on the project advancement data and the risk control list to determine the key risk points, wherein the key risk points can be the risk points that have been exposed during the project advancement process, and can also be the risk points that are predicted to occur during the project advancement process. Regarding the risk monitoring method, the embodiment of the present application is no longer limited. Since the characteristics of data of different risk dimensions are different, the required data analysis methods are also different. Therefore, based on the risk dimensions in the risk control list, the project advancement data is classified to obtain the project sub-data corresponding to each risk dimension; the target analysis method corresponding to the target risk dimension is obtained, and the target project sub-data corresponding to the target risk dimension is analyzed according to the target analysis method to determine the key risk points. In this way, the risk analysis is performed using an analysis method that matches the characteristics of the project recommendation data, which improves the accuracy of the key risk points determined. Through automated tools and system integration, project progress data can be collected in real time or regularly without the need for managers to frequently visit the project site. Risk assessments can be automatically performed based on project progress data and risk control lists, improving the efficiency and accuracy of project risk monitoring and management.

[0029] Step S104: Conduct risk response analysis on key risk points, determine risk response strategies, and send the risk response strategies to the project leader so that the project leader can respond to the risks of project advancement.

[0030] For the embodiments of the present application, in order to minimize the impact of risks on the project and effectively manage risks, it is necessary to take timely and effective response strategies to reduce the possibility of risk occurrence or the impact of risks when monitoring the existence of risks in the project. Therefore, risk response analysis is performed on key risk points to determine risk response strategies. The types of risk response strategies include: risk aversion, risk reduction, risk transfer and risk acceptance, among which risk aversion refers to avoiding the occurrence of risks and eliminating risks by changing plans or strategies; risk reduction is to reduce the possibility of risk occurrence or mitigate the impact of risks after they occur by taking a series of measures; risk transfer is to transfer risks to other entities or individuals, such as purchasing insurance; risk acceptance refers to actively or passively accepting risks and preparing to deal with their possible consequences. Therefore, the risk response strategy determined for key risk points can be at least one of the four types. The specific implementation of the risk response strategy is no longer limited in this application, and users can set it according to actual conditions. In one achievable method, the electronic device pre-sets the correspondence between key risk points and risk response strategies, but the correspondence is not a simple one-to-one relationship. One key risk point can correspond to multiple types of risk response strategies, so that the risk response strategy can be quickly and accurately determined according to the correspondence. Then, the risk response strategy is sent to the project leader to ensure that the project leader has a clear understanding of the risk situation of the project, so that the project leader can perform relevant operations according to the risk response strategy to ensure that the risk is properly dealt with, thereby ensuring the smooth progress of the project.

[0031] It can be seen that in the embodiment of the present application, multi-dimensional risk identification is performed based on the project development plan to obtain a risk information set, and then, risk assessment is performed based on the risk information set to obtain the risk level corresponding to each risk description, and the risk information set and the risk level corresponding to each risk description are combined to obtain a risk management list. Furthermore, risk monitoring is performed based on the project advancement data and the risk management list to determine key risk points. Finally, risk response analysis is performed on the key risk points to determine the risk response strategy, and the risk response strategy is sent to the project leader. Through automated tools and system integration, project advancement data can be collected in real time or regularly without the need for managers to frequently visit the project site, and risk assessment is automatically performed based on the project advancement data and the risk management list, thereby improving the efficiency and accuracy of project risk monitoring and management.

[0032] Furthermore, in order to improve the accuracy of the key risk points determined, in the embodiment of the present application, risk monitoring is performed based on the project progress data and the risk control list to determine the key risk points, including: Based on the risk dimensions in the risk management and control list, classify the project progress data to obtain the project sub-data corresponding to each risk dimension; Obtain a target analysis method corresponding to the target risk dimension, perform risk analysis on the target project sub-data corresponding to the target risk dimension according to the target analysis method, and determine key risk points, wherein the target risk dimension is any one of the risk dimensions.

[0033] For the embodiment of the present application, the project advancement data is a data set that can characterize the actual progress, cost, quality, resource use, etc. of the project, and has the characteristic of large data volume. If the project advancement data with huge data volume is used for risk analysis during the execution of risk monitoring, it will affect the speed of risk analysis and consume higher computing resources. At the same time, since the data of different risk dimensions have different characteristics and the required data analysis methods are also different, the accuracy of the key risk points determined can be improved by classifying the data and selecting the analysis method in a targeted manner.

[0034] In order to improve the speed of risk monitoring and the accuracy of key risk points, the project progress data is classified based on the risk dimensions in the risk control list to obtain the project sub-data corresponding to each risk dimension, so that the project sub-data can comprehensively characterize the relevant situation of the project in this risk dimension. For example, for the risk dimension of delivery risk, the corresponding project sub-data can be a project progress report, task list completion status, a timeline showing milestones, etc. The electronic device pre-stores the analysis method corresponding to each risk dimension, so that the analysis method can better analyze whether there is a risk and the specific situation of the risk from the project sub-data. Then, the target analysis method corresponding to the target risk dimension is obtained, and according to the target analysis method, the target project sub-data corresponding to the target risk dimension is subjected to risk analysis to determine the key risk points. Regarding the method of performing risk analysis on the target project sub-data, it is specifically as follows: when the target risk dimension is construction safety, the first project sub-data of the image type is visually analyzed in a visual analysis manner to determine the visual analysis result, wherein the first project sub-data is a monitoring image of the construction site; when the target risk dimension is delivery risk, the second project sub-data is analyzed for progress deviation in a project progress monitoring manner to determine the progress deviation analysis result, wherein the second project sub-data is progress data that characterizes the actual degree of advancement of the project; when the target risk dimension is technical risk, the third project sub-data is analyzed for technical feasibility in a feasibility analysis manner to determine the technical analysis result, wherein the third project sub-data is the overcoming of technical difficulties in the technical solution adopted by the project; the key risk points are determined by combining the visual analysis results, progress deviation analysis results and technical analysis results. The risk analysis process for other risk dimensions is no longer limited in the embodiments of the present application.

[0035] It can be seen that in the embodiment of the present application, based on the risk dimensions in the risk control list, the project advancement data is classified to obtain the project sub-data corresponding to each risk dimension, and then, according to the target analysis method corresponding to the target risk dimension, the target project sub-data corresponding to the target risk dimension is risk analyzed to determine the key risk points. After classifying the data and selecting the analysis method in a targeted manner, the accuracy of the key risk points determined can be improved.

[0036] Furthermore, in order to improve the accuracy of the key risk points determined, in the embodiment of the present application, risk analysis is performed on the target project sub-data corresponding to the target risk dimension according to the target analysis method to determine the key risk points, including: When the target risk dimension is construction safety, visual analysis is performed on the first item sub-data of the image type in a visual analysis manner to determine a visual analysis result, wherein the first item sub-data is a monitoring image of the construction site; For the embodiment of the present application, the construction site is usually a place where a variety of complex activities and different equipment meet. This diversity is often accompanied by a variety of potential safety risks. In order to ensure the life safety and physical health of the staff and improve work efficiency, construction safety monitoring is performed on the construction site. Specifically, when the target risk dimension is construction safety, monitoring images are collected from the monitoring system of the construction site so that the first project sub-data includes the shooting results of the construction site at different time periods and different angles, and obtains pre-set safety violation features, such as related illegal operations such as not wearing a safety helmet, as a reference for visual analysis. Then, the first project sub-data is visually analyzed frame by frame using a computer vision algorithm. This step includes target detection (identifying workers, equipment, etc.), behavior recognition (analyzing whether the workers' actions and behaviors comply with safety regulations) and scene understanding (judging the overall safety status of the construction site). Furthermore, the abnormal behavior or safety hazard detected in the first project sub-data is marked as a risk point and output in a visual manner, such as a risk point report, annotated images, etc.

[0037] When the target risk dimension is delivery risk, the progress deviation analysis is performed on the second project sub-data according to the project progress monitoring method to determine the progress deviation analysis result, wherein the second project sub-data is the progress data representing the actual progress of the project; For the embodiment of the present application, project progress monitoring can ensure that the project can be completed on time. At the same time, it can also find abnormal situations and trends during the project execution process, so as to predict potential risks and ensure that the project finally delivers high-quality products. Therefore, when the target risk dimension is delivery risk, according to the project progress monitoring method, the second project sub-data is subjected to progress deviation analysis to determine the progress deviation analysis result. Specifically, the second project sub-data is progress data that characterizes the actual degree of advancement of the project, which generally includes the actual project start date, key milestone completion date, task completion percentage, etc. At the same time, the progress benchmark of the project is obtained, i.e., the key nodes and expected completion date in the project plan. The progress benchmark is usually based on the project plan, contract requirements, and the project team's joint planning of the delivery date. Then, deviation analysis is performed based on the actual completed second project sub-data and progress benchmark. When the actual progress of the project advancement is later than the progress benchmark, the progress deviation analysis result is determined to be delivery delay, otherwise, the progress deviation analysis result is determined to be normal. At the same time, when the target risk dimension is technical risk, a technical feasibility analysis is conducted on the third project sub-data in accordance with the feasibility analysis method to determine the technical analysis results, where the third project sub-data is the situation of overcoming technical difficulties in the technical solution adopted by the project; Combine visual analysis results and schedule deviation analysis results to identify key risk points.

[0038] For the embodiment of the present application, when the progress deviation analysis result is a delivery delay, the key risk point is determined to include the delivery delay; and the abnormal behavior or safety hazard detected in the visual analysis result is used as the information item included in the key risk point. Of course, there may be a situation where both the visual analysis result and the progress deviation analysis result are normal, in which case the key risk point is recorded as empty to indicate that the project is progressing normally.

[0039] It can be seen that in the embodiment of the present application, when the target risk dimension is construction safety, the first project sub-data of the image type is visually analyzed in a visual analysis manner to determine the visual analysis result. At the same time, when the target risk dimension is delivery risk, the second project sub-data is subjected to a progress deviation analysis in a project progress monitoring manner to determine the progress deviation analysis result. Finally, the key risk points are determined by combining the visual analysis results and the progress deviation analysis results. Selecting an analysis method that matches the characteristics of the project sub-data for risk analysis can improve the accuracy of the key risk points determined.

[0040] Furthermore, in order to ensure that the project is completed on time, in the embodiment of the present application, when the key risk point is delivery delay, a risk response analysis is performed on the key risk point to determine the risk response strategy, including: Extract key information based on the progress report in the second project sub-data to determine the current progress of the project and the planned progress of the project, wherein the current progress of the project lags behind the planned progress of the project; Based on the current project progress and the project planned progress, a cause analysis is conducted to determine the cause of the delayed progress. When the cause of the delayed progress is insufficient human resources, the risk response strategy is determined to be personnel scheduling.

[0041] For the embodiment of the present application, when the key risk point is the delivery delay, it is necessary to analyze the reasons for the delay in progress and take risk response strategies in time to ensure that the project is completed on time. Specifically, based on the progress report in the second project sub-data, key information is extracted to clarify which tasks have been completed, which tasks are in progress, and which tasks have not yet started, so as to determine the current progress of the project, and determine the project plan schedule from the progress benchmark according to the current date. Then, based on the current progress of the project and the project plan schedule, the cause analysis is performed to determine the reasons for the delay in progress, wherein the reasons for the delay in progress include but are not limited to: insufficient human resources, demand changes, technical difficulties, supply chain problems, etc. In the case of determining whether human resources are insufficient, the number, skills and experience of project team members are evaluated to meet the project. If human resources are obviously insufficient, the main reason for the delay in progress when the personnel are insufficient is characterized. When the reason for the delay in progress is insufficient human resources, the risk response strategy is determined to be personnel scheduling, and personnel scheduling includes but is not limited to: reallocating the workload of existing team members, recruiting additional personnel, borrowing human resources from other projects, etc., to ensure that the project can be completed on time.

[0042] It can be seen that in the embodiment of the present application, key information is extracted based on the progress report in the second project sub-data to determine the current progress of the project and the planned progress of the project. Then, cause analysis is performed based on the current progress of the project and the planned progress of the project to determine the reason for the delay in progress. When the reason for the delay in progress is insufficient human resources, the risk response strategy is determined to be personnel scheduling. In this way, a risk response strategy is adopted to ensure that the project is completed on time.

[0043] Furthermore, in order to improve the transparency and understandability of risk management, in the embodiment of the present application, after the risk information set and the risk level corresponding to each risk description are integrated to obtain the risk control list, it also includes: Conduct visual display analysis based on multiple risk dimensions in the risk information set and determine a multi-dimensional display model; The risk control list is visualized in a multi-dimensional display model, where multiple risk descriptions corresponding to the same risk dimension are within the same dimension of the multi-dimensional display model, and the risk level is used to determine the display format.

[0044] For the embodiment of the present application, after obtaining the risk control list, a multi-dimensional display model is used to visualize the risk control list, which helps the project leader and team members to fully understand the risks of the project from multiple angles and multiple levels. The multi-dimensional visual display improves the transparency and comprehensibility of risk management.

[0045] Specifically, a visual display analysis is performed based on multiple risk dimensions in the risk information set to determine a multidimensional display model. For the process of visual display analysis, the display model type is selected according to the characteristics of the data corresponding to the risk dimension and the purpose of analysis. For example, a scatter plot, heat map, radar map, etc. can be selected. Therefore, the most suitable multidimensional display model is selected by comprehensively considering the number of risk dimensions, the complexity of the relationship, and the intuitiveness of the display effect. Then, the data in the risk control list is mapped to the corresponding dimensions of the multidimensional display model to ensure that each risk dimension has a corresponding representation in the model, and multiple risk descriptions corresponding to the same risk dimension are placed in the same dimension of the model. At the same time, the form of data display is determined according to the risk level. For example, different colors, sizes, shapes or animation effects can be used to represent different levels of risks. Among them, high risks can be represented by eye-catching red, while low risks can be represented by relatively low-key green.

[0046] It can be seen that in the embodiment of the present application, a visual display analysis is performed based on multiple risk dimensions in the risk information set to determine a multidimensional display model, and then the risk control list is visualized in the multidimensional display model. Visualizing the risk control list using a multidimensional display model helps project leaders and team members to fully understand the risks of the project from multiple angles and levels. The multidimensional visual display improves the transparency and comprehensibility of risk management.

[0047] Furthermore, in order to improve the overall efficiency and effectiveness of risk management, in the embodiment of the present application, risk assessment is performed based on the risk information set to obtain the risk level corresponding to each risk description, including: Perform a quantitative assessment based on the target risk description in the risk information set to determine the risk likelihood and risk impact level corresponding to the target risk description, where the target risk description is any risk description; Obtain the risk assessment matrix, and determine the location points based on the risk assessment matrix, the risk possibility and risk impact degree corresponding to each target risk description, and obtain the risk level corresponding to each risk description.

[0048] For the embodiment of the present application, a quantitative assessment is performed based on the target risk description in the risk information set to determine the risk possibility and risk impact degree corresponding to the target risk description. The quantitative assessment usually involves an assessment of the probability of risk occurrence and potential consequences. Then, a risk assessment matrix is ​​obtained, and the position point is determined based on the risk assessment matrix, the risk possibility and risk impact degree corresponding to each target risk description, and the risk level corresponding to each risk description is obtained. Specifically, the risk assessment matrix is ​​a tool for determining the risk level, usually a two-dimensional table, the horizontal axis represents the risk possibility, and the vertical axis represents the risk impact degree. Then, for the risk possibility and risk impact degree corresponding to each target risk description, the position point in the risk assessment matrix is ​​determined, and the level corresponding to the position point is recorded as the risk level corresponding to the target risk description. Through quantitative assessment, the risk possibility and risk impact degree can be determined more accurately, and through the determination of the risk assessment matrix and the position point, each risk description can obtain a clear risk level, which helps the project leader to quickly and accurately identify the risk, thereby facilitating the formulation of relevant risk management strategies and facilitating the subsequent improvement of the overall efficiency and effectiveness of risk management.

[0049] It can be seen that in the embodiment of the present application, a quantitative assessment is performed based on the target risk description in the risk information set to determine the risk possibility and risk impact level corresponding to the target risk description, and then, based on the risk assessment matrix, the risk possibility and risk impact level corresponding to each target risk description, the position point is determined to obtain the risk level corresponding to each risk description. The risk possibility and risk impact level can be determined more accurately through quantitative assessment, and each risk description can obtain a clear risk level through the determination of the risk assessment matrix and the position point, which helps the project leader to quickly and accurately identify risks, thereby facilitating the formulation of relevant risk management strategies and facilitating the subsequent improvement of the overall efficiency and effectiveness of risk management.

[0050] The above embodiment introduces a project risk management method from the perspective of method flow, and the following embodiment introduces a project risk management device from the perspective of a virtual module or a virtual unit. For details, please refer to the following embodiment.

[0051] The present application embodiment provides a project risk management device, such as Figure 2 As shown, the risk management and control device of this project may specifically include: The risk identification module 210 is used to obtain a project development plan, perform multi-dimensional risk identification based on the project development plan, and obtain a risk information set, wherein the risk information set includes: multiple risk dimensions and multiple risk descriptions corresponding to each risk dimension; The risk assessment module 220 is used to perform risk assessment based on the risk information set, obtain the risk level corresponding to each risk description, and obtain a risk management list by combining the risk information set and the risk level corresponding to each risk description; The risk monitoring module 230 is used to obtain project progress data, and to monitor risks based on the project progress data and the risk control list to determine key risk points; The risk response module 240 is used to perform risk response analysis on key risk points, determine risk response strategies, and send the risk response strategies to the project leader so that the project leader can respond to the risks of project advancement.

[0052] For the embodiments of the present application, multi-dimensional risk identification is performed based on the project development plan to obtain a risk information set, and then risk assessment is performed based on the risk information set to obtain the risk level corresponding to each risk description, and the risk information set and the risk level corresponding to each risk description are combined to obtain a risk management list. Further, risk monitoring is performed based on the project advancement data and the risk management list to determine key risk points, and finally, risk response analysis is performed on the key risk points to determine the risk response strategy, and the risk response strategy is sent to the project leader. Through the use of automated tools and system integration, project advancement data can be collected in real time or regularly without the need for managers to frequently visit the project site, and risk assessment is automatically performed based on the project advancement data and the risk management list, thereby improving the efficiency and accuracy of project risk monitoring and management.

[0053] In a possible implementation of the embodiment of the present application, the risk monitoring module 230, when performing risk monitoring based on project progress data and the risk control list to determine key risk points, is used to: Based on the risk dimensions in the risk management and control list, classify the project progress data to obtain the project sub-data corresponding to each risk dimension; Obtain a target analysis method corresponding to the target risk dimension, perform risk analysis on the target project sub-data corresponding to the target risk dimension according to the target analysis method, and determine key risk points, wherein the target risk dimension is any one of the risk dimensions.

[0054] In a possible implementation of the embodiment of the present application, when the risk monitoring module 230 performs risk analysis on the target project sub-data corresponding to the target risk dimension according to the target analysis method and determines the key risk points, it is used to: When the target risk dimension is construction safety, visual analysis is performed on the first item sub-data of the image type in a visual analysis manner to determine a visual analysis result, wherein the first item sub-data is a monitoring image of the construction site; When the target risk dimension is delivery risk, the progress deviation analysis is performed on the second project sub-data according to the project progress monitoring method to determine the progress deviation analysis result, wherein the second project sub-data is the progress data representing the actual progress of the project; Combine visual analysis results and schedule deviation analysis results to identify key risk points.

[0055] In a possible implementation of the embodiment of the present application, when the key risk point is delivery delay, When performing risk response analysis on key risk points and determining risk response strategies, the risk response module 240 is used to: Extract key information based on the progress report in the second project sub-data to determine the current progress of the project and the planned progress of the project, wherein the current progress of the project lags behind the planned progress of the project; Based on the current project progress and the project planned progress, a cause analysis is conducted to determine the cause of the delayed progress. When the cause of the delayed progress is insufficient human resources, the risk response strategy is determined to be personnel scheduling.

[0056] In a possible implementation of the embodiment of the present application, the project risk management and control device further includes: A visualization module is used to perform visualization analysis based on multiple risk dimensions in the risk information set and determine a multi-dimensional display model; The risk control list is visualized in a multi-dimensional display model, where multiple risk descriptions corresponding to the same risk dimension are within the same dimension of the multi-dimensional display model, and the risk level is used to determine the display format.

[0057] In a possible implementation of the embodiment of the present application, when the risk assessment module 220 performs risk assessment based on the risk information set and obtains the risk level corresponding to each risk description, it is used to: Perform a quantitative assessment based on the target risk description in the risk information set to determine the risk likelihood and risk impact level corresponding to the target risk description, where the target risk description is any risk description; Obtain the risk assessment matrix, and determine the location points based on the risk assessment matrix, the risk possibility and risk impact degree corresponding to each target risk description, and obtain the risk level corresponding to each risk description.

[0058] Technical personnel in the relevant field can clearly understand that, for the convenience and conciseness of description, the specific working process of a project risk management device described above can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.

[0059] An electronic device is provided in an embodiment of the present application, such as Figure 3 As shown, Figure 3The electronic device 300 shown includes: a processor 301 and a memory 303. The processor 301 and the memory 303 are connected, such as through a bus 302. Optionally, the electronic device 300 may also include a transceiver 304. It should be noted that in actual applications, the transceiver 304 is not limited to one, and the structure of the electronic device 300 does not constitute a limitation on the embodiments of the present application.

[0060] The processor 301 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array) or other programmable logic devices, transistor logic devices, hardware components or any combination thereof. It may implement or execute various exemplary logic blocks, modules and circuits described in conjunction with the disclosure of this application. The processor 301 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, etc.

[0061] The bus 302 may include a path to transmit information between the above components. The bus 302 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus 302 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 3 Only one thick line is used in the diagram, but it does not mean that there is only one bus or only one type of bus.

[0062] The memory 303 may be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited thereto.

[0063] The memory 303 is used to store the application code for executing the solution of the present application, and the execution is controlled by the processor 301. The processor 301 is used to execute the application code stored in the memory 303 to implement the contents shown in the above method embodiment.

[0064] The electronic devices include, but are not limited to, mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), and fixed terminals such as digital TVs, desktop computers, etc. It can also be a server, etc. Figure 3 The electronic device shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0065] An embodiment of the present application provides a computer-readable storage medium, on which a computer program is stored. When the computer-readable storage medium is run on a computer, the computer can execute the corresponding content in the aforementioned method embodiment.

[0066] The embodiment of the present application provides a computer program product, which includes a computer program, which implements the method in any of the above embodiments when executed by a processor. Compared with the related art, the embodiment of the present application performs multi-dimensional risk identification based on the project development plan to obtain a risk information set, and then performs risk assessment based on the risk information set to obtain the risk level corresponding to each risk description, and integrates the risk information set and the risk level corresponding to each risk description to obtain a risk control list. Then, risk monitoring is performed based on the project advancement data and the risk control list to determine the key risk points, and finally, risk response analysis is performed on the key risk points, risk response strategies are determined, and the risk response strategies are sent to the project leader. Through the method of automated tools and system integration, project advancement data can be collected in real time or regularly without the need for managers to frequently visit the project site, and risk assessment is automatically performed based on the project advancement data and the risk control list, thereby improving the efficiency and accuracy of project risk monitoring and management.

[0067] It should be understood that, although the steps in the flowchart of the accompanying drawings are displayed in sequence as indicated by the arrows, these steps are not necessarily executed in sequence in the order indicated by the arrows. Unless otherwise specified herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least a part of the steps in the flowchart of the accompanying drawings may include multiple sub-steps or multiple stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and their execution order is not necessarily sequential, but can be executed in turn or alternately with other steps or at least a part of the sub-steps or stages of other steps.

[0068] The above are only some implementation methods of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.

Claims

1. A project risk management method, characterized in that: include: Acquire a project development plan, perform multi-dimensional risk identification based on the project development plan, and obtain a risk information set, wherein the risk information set includes: multiple risk dimensions and multiple risk descriptions corresponding to each risk dimension; Performing risk assessment based on the risk information set to obtain a risk level corresponding to each of the risk descriptions, and obtaining a risk management list by combining the risk information set and the risk level corresponding to each of the risk descriptions; Obtain project progress data, and conduct risk monitoring based on the project progress data and the risk control list to determine key risk points; Conduct risk response analysis on the key risk points, determine risk response strategies, and send the risk response strategies to the project leader so that the project leader can respond to the risks of project advancement.

2. The project risk management method according to claim 1, characterized in that: The risk monitoring based on the project progress data and the risk control list to determine key risk points includes: Based on the risk dimensions in the risk control list, the project progress data is classified to obtain project sub-data corresponding to each risk dimension; Obtain a target analysis method corresponding to a target risk dimension, perform risk analysis on the target project sub-data corresponding to the target risk dimension according to the target analysis method, and determine key risk points, wherein the target risk dimension is any one of the risk dimensions.

3. The project risk management method according to claim 2, characterized in that: The step of performing risk analysis on the target project sub-data corresponding to the target risk dimension according to the target analysis method to determine key risk points includes: When the target risk dimension is construction safety, visual analysis is performed on the first project sub-data of the image type in a visual analysis manner to determine a visual analysis result, wherein the first project sub-data is a monitoring image of the construction site; When the target risk dimension is delivery risk, a progress deviation analysis is performed on the second project sub-data according to the project progress monitoring method to determine a progress deviation analysis result, wherein the second project sub-data is progress data representing the actual progress of the project; The key risk points are determined by combining the visual analysis results and the progress deviation analysis results.

4. The project risk management method according to claim 3, characterized in that: When the key risk point is delivery delay, the risk response analysis is performed on the key risk point to determine the risk response strategy, including: Extract key information based on the progress report in the second project sub-data to determine the current progress of the project and the planned progress of the project, wherein the current progress of the project lags behind the planned progress of the project; Based on the current progress of the project and the planned progress of the project, a cause analysis is performed to determine the cause of the delayed progress. When the cause of the delayed progress is insufficient human resources, the risk response strategy is determined to be personnel scheduling.

5. The project risk management method according to claim 1, characterized in that: After obtaining the risk control list by integrating the risk information set and the risk level corresponding to each risk description, the method further includes: Performing visual display analysis based on the multiple risk dimensions in the risk information set to determine a multi-dimensional display model; The risk control list is visualized in the multi-dimensional display model, wherein multiple risk descriptions corresponding to the same risk dimension are within the same dimension in the multi-dimensional display model, and the risk level is used to determine the display form.

6. The project risk management method according to claim 1, characterized in that: The risk assessment is performed based on the risk information set to obtain a risk level corresponding to each risk description, including: Performing a quantitative assessment based on the target risk description in the risk information set to determine the risk possibility and risk impact degree corresponding to the target risk description, wherein the target risk description is any risk description; A risk assessment matrix is ​​obtained, and a location point is determined based on the risk assessment matrix, the risk possibility and the risk impact degree corresponding to each of the target risk descriptions, to obtain a risk level corresponding to each of the risk descriptions.

7. An electronic device, characterized in that: include: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute the project risk management method according to any one of claims 1 to 6.

8. A computer-readable storage medium, characterized in that: A computer program is stored thereon, and when the computer program is executed in a computer, the computer is caused to execute the project risk management method described in any one of claims 1 to 6.

9. A computer program product, characterized in that The method comprises a computer program, wherein the computer program is executed by a processor to implement the project risk management method according to any one of claims 1 to 6.