Information system integration project management system and management method
By dividing the project into multiple management cycles, analyzing and monitoring the use of funds, the problems of opacity and cost overrun in the existing technology are solved, and automated fund management and early warning are realized, and the accuracy and transparency of project fund management are improved. .
Patent Information
- Application Number
- CN202410985394.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-11-12
AI Technical Summary
The existing project management information system has problems of unknown destinations and high financial pressure in the fund supervision of construction projects. This is mainly due to the long project cycle and the reliance on manual statistics, which leads to opaque use of funds and overspending costs.
By dividing the project into multiple management cycles, obtaining and analyzing the basic data of each cycle, calculating the usage of benchmark funds, conducting fund monitoring and early warning, an automated fund management and early warning mechanism is realized.
It reduces financial risks, reduces data inaccuracy caused by manual operations, improves the accuracy and objectivity of project management, ensures transparent use of funds, and reduces cost overruns.
Smart Images

Figure CN118941236A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of project management, relates to information integration technology, and specifically is an information system integrated project management system and management method. Background Art
[0002] The existing project management information system has the following defects:
[0003] 1. When carrying out integrated management of construction projects, due to the long project cycle and the large amount of financial data involved, it is easy to cause difficulties in fund supervision;
[0004] 2. The existing integrated project fund management method often relies on manual statistics and calculations by financial personnel, which easily leads to unknown whereabouts of funds, resulting in the project construction process facing the problem of heavy financial pressure;
[0005] Therefore, we propose an information system integration project management system and management method. Summary of the invention
[0006] In view of the deficiencies in the prior art, the purpose of the present invention is to provide an information system integrated project management system and a management method. The present invention is based on dividing the target engineering project into multiple project management cycles, respectively obtaining the quantitative value of the project additional reserve cycle, capital consumption, effective number of workers, type of work, construction materials and construction consumables procurement volume corresponding to each project management cycle, and obtaining the cycle basic data. The cycle basic data corresponding to each project management cycle is defined as the target project periodic basic data, which is used to obtain the periodic construction material benchmark capital usage and periodic labor benchmark capital usage corresponding to each project management cycle according to the target project periodic basic data analysis, and the periodic construction material benchmark capital usage, periodic labor benchmark capital usage and the quantitative value of the project additional reserve cycle are calculated to obtain the project cycle benchmark capital usage, and the project cycle benchmark capital usage is numerically compared with the actual project capital usage to obtain the project capital periodic monitoring data, which is used to perform periodic project early warning according to the project capital periodic monitoring data.
[0007] In order to achieve the above purpose, the present invention adopts the following technical solution: The specific working process of each module of an information system integrated project management system is as follows:
[0008] Data acquisition module: used to divide the target engineering project into multiple project management cycles, obtain the quantitative value of the project additional reserve cycle, capital consumption, effective number of workers, type of work, construction materials and purchase volume of construction consumables corresponding to each project management cycle, obtain the cycle basic data, and define the cycle basic data corresponding to each project management cycle as the target project periodic basic data;
[0009] Data analysis module: used to obtain the periodic construction material benchmark fund usage and periodic labor benchmark fund usage corresponding to each project management cycle according to the periodic basic data of the target project, calculate the periodic construction material benchmark fund usage, periodic labor benchmark fund usage and the quantitative value of the project additional reserve fund cycle to obtain the project periodic benchmark fund usage, compare the project periodic benchmark fund usage with the actual project fund usage, and obtain the project fund periodic monitoring data;
[0010] Project management module: used to conduct periodic project early warning based on periodic monitoring data of project funds.
[0011] Furthermore, the data acquisition module acquires the periodic basic data of the target project, as follows:
[0012] In the process of integrated management of the target engineering project, mq project management cycles are marked in chronological order and named as m1 to mq project management cycles respectively;
[0013] Conduct fund utilization analysis on the m1th project management cycle to obtain the cycle basic data corresponding to the m1th project management cycle;
[0014] Obtain the period basic data corresponding to the m2 to mq project management periods respectively;
[0015] The period basic data corresponding to the m1 to mq project management periods are defined as the target project periodic basic data.
[0016] Furthermore, the data acquisition module acquires the period basic data corresponding to the m1-th project management period, as follows:
[0017] Get the purchase quantities of the first to k types of construction materials and the first to k construction consumables;
[0018] Obtain a work list of project construction personnel corresponding to the m1th project management cycle, and classify the construction personnel used in the m1th project management cycle into the first to jth types of work according to the work list of project construction personnel;
[0019] Obtain the cumulative effective working times corresponding to the first to j-th types of work in the m1-th project management cycle, and obtain the effective working times of the first to j-th types of work;
[0020] Obtain the actual usage of project funds corresponding to the m1th project management period to obtain the first fund consumption;
[0021] Obtain the project additional reserve corresponding to the target engineering project, calculate the ratio of the project additional reserve to mq, and obtain the quantitative value of the project additional reserve period;
[0022] The first capital consumption, the quantitative value of the project additional reserve cycle, the effective number of people working from the first to the jth type of work, the first to the jth type of work, the first to the kth construction consumables procurement volume and the first to the kth type of construction materials are defined as the cycle basic data corresponding to the m1th project management cycle.
[0023] Furthermore, the data acquisition module acquires the purchase quantities of the first to k-th types of construction materials and the first to k-th construction consumables, as follows:
[0024] Obtain a project construction material procurement list corresponding to the m1th project management cycle, and classify the construction materials used in the m1th project management cycle into first to kth types of construction materials according to the project construction material procurement list;
[0025] Obtain the material quantities corresponding to the first to k-th types of construction materials respectively, and obtain the purchase quantities of the first to k-th construction consumables;
[0026] Get the effective number of people working for the first to j-th types of work and the first to j-th types of work.
[0027] Furthermore, the data analysis module acquires the periodic monitoring data of the project funds, as follows:
[0028] Obtain the periodic basic data of the target project, and obtain the periodic basic data corresponding to the m1 to mq project management periods respectively according to the periodic basic data of the target project;
[0029] Obtain the periodic construction material benchmark fund usage corresponding to the m1th project management period;
[0030] Obtain the period labor benchmark fund usage corresponding to the m1th project management period;
[0031] Obtain the project cycle benchmark fund usage corresponding to the m1th project management cycle;
[0032] The project cycle benchmark fund usage corresponding to the m1th project management cycle is obtained by calculating the project additional reserve cycle quantified value, cycle construction material benchmark fund usage, and cycle construction material benchmark fund usage;
[0033] Calculate the project cycle benchmark fund usage corresponding to the m1th project management cycle;
[0034] Repeat the process of obtaining the project cycle benchmark fund usage corresponding to the m1th project management cycle, and obtain the project cycle benchmark fund usage corresponding to the m2th to mqth project management cycles respectively;
[0035] Obtain the actual usage of project funds corresponding to the m1 to mq project management cycles of the target project's periodic basic data;
[0036] The actual usage of project funds corresponding to each project management cycle is compared with the benchmark usage of project funds in the project cycle to obtain the periodic monitoring data of project funds.
[0037] Furthermore, the data analysis module obtains the periodic construction material benchmark fund usage corresponding to the m1-th project management period, as follows:
[0038] Obtain the period basic data corresponding to the m1th project management period, and obtain the first to kth construction consumables procurement quantities and the first to kth types of construction materials respectively according to the period basic data corresponding to the m1th project management period;
[0039] Obtain the market price range values corresponding to the first to k-th types of construction materials respectively, obtain the market price range values corresponding to multiple construction materials respectively, obtain the median of each market price range value respectively, obtain the median of the market price range value corresponding to each type of construction material respectively, and name them as the first to k-th material benchmark price values respectively;
[0040] The purchase amount of the first to k construction consumables and the first to k material benchmark price values are calculated to obtain the period construction material benchmark capital usage;
[0041] Calculate the baseline funding usage for periodic construction materials.
[0042] Furthermore, the data analysis module obtains the periodic manual benchmark fund usage, as follows:
[0043] According to the period basic data corresponding to the m1th project management period, the effective number of workers of the first to jth types of work and the first to jth types of work are obtained respectively;
[0044] Obtain the market price range values corresponding to the first to j-th types of work respectively, obtain the market price range values corresponding to multiple construction work types, obtain the median of the market price range values corresponding to each construction work type respectively, obtain the median of the market price range values corresponding to each type of work, and name them as the first to k-th work type benchmark price values respectively;
[0045] The effective working hours of the first to jth types of work and the benchmark price values of the first to kth types of work are calculated to obtain the period labor benchmark fund usage;
[0046] Calculate the periodic manual benchmark fund usage;
[0047] Among them, Gcl is the benchmark capital usage of construction materials during the period, Glj1 to Gljj are the effective number of workers from the first to the jth type of work, and Gjj1 to Gjjj are the benchmark price values from the first to the kth type of work;
[0048] The first capital consumption and the project additional reserve period quantitative value are obtained according to the period basic data corresponding to the m1th project management period.
[0049] Furthermore, the data analysis module compares the actual amount of project funds used with the project period benchmark funds used, as follows:
[0050] When the actual amount of project funds used is greater than the baseline amount of funds used during the project cycle, the project management cycle is judged to be the first type of project management cycle;
[0051] When the actual usage of project funds is less than or equal to the benchmark usage of project funds during the project period, the project management period is determined to be the second type of project management period.
[0052] Furthermore, the project management module performs periodic project early warning, as follows:
[0053] Obtain periodic monitoring data on project funds;
[0054] For the first type of project management cycle, the project management system issues warnings for abnormal fund use and strengthens supervision of the first to jth types of work and the first to kth types of construction materials;
[0055] For the second type of project management cycle, the project management system does not issue warnings for abnormal fund use.
[0056] An information system integration project management method includes the following specific steps:
[0057] Step Y1: Obtain periodic basic data of the target project;
[0058] Step Y2: Analyze the use of funds based on the periodic basic data of the target project to obtain the periodic monitoring data of the project funds;
[0059] Step Y3: Conduct periodic project early warning based on periodic monitoring data of project funds.
[0060] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0061] 1. The present invention can reduce the financial risk of the overall project by dividing the target engineering project into multiple project management cycles for periodic fund management. If funding problems or cost overruns occur in a certain cycle, the funding plan of the subsequent cycle can be used to adjust and supplement the cost, thereby reducing the negative impact on the overall project.
[0062] 2. The present invention automatically obtains the project cycle benchmark fund usage and compares it with the actual project fund usage, thereby reducing data inaccuracy caused by negligence or errors in manual operations and improving the accuracy and objectivity of project management. BRIEF DESCRIPTION OF THE DRAWINGS
[0063] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.
[0064] Figure 1 is the overall system block diagram of the present invention;
[0065] Figure 2 It is a diagram of the implementation steps of the present invention. DETAILED DESCRIPTION
[0066] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0067] Embodiment 1
[0068] See also Figure 1 , the present invention provides a technical solution: an information system integrated project management system, comprising a data acquisition module, a data analysis module, a project management module and a server, wherein the data acquisition module, the data analysis module and the project management module are respectively connected to the server, and the server controls the data acquisition module, the data analysis module and the project management module respectively;
[0069] The data acquisition module acquires the periodic basic data of the target project;
[0070] In the process of integrated management of the target engineering project, mq project management cycles are marked in chronological order and named as m1 to mq project management cycles respectively;
[0071] It should be noted here that:
[0072] In this application, mq specifically refers to the quantity value corresponding to the project management cycle, and mq is an integer greater than 0;
[0073] Analyze the use of funds for the m1th project management cycle and obtain the first cycle project fund usage;
[0074] The details are as follows:
[0075] Obtain a project construction material procurement list corresponding to the m1th project management cycle, and classify the construction materials used in the m1th project management cycle into first to kth types of construction materials according to the project construction material procurement list;
[0076] Obtain the material quantities corresponding to the first to k-th types of construction materials respectively, and obtain the purchase quantities of the first to k-th construction consumables;
[0077] It should be noted here that:
[0078] In the present application, k specifically refers to the quantity value corresponding to the consumable type used in the m1th project management cycle, and k is an integer greater than 0;
[0079] And the types of consumables used in the m1 project management cycle include but are not limited to cement, bricks and steel bar building materials;
[0080] Obtain a work list of project construction personnel corresponding to the m1th project management cycle, and classify the construction personnel used in the m1th project management cycle into the first to jth types of work according to the work list of project construction personnel;
[0081] Obtain the cumulative effective working times corresponding to the first to j-th types of work in the m1-th project management cycle, and obtain the effective working times of the first to j-th types of work;
[0082] It should be noted here that:
[0083] j is the value of the type of project construction personnel corresponding to the m1th project management cycle. The types of work involved here include but are not limited to carpenters, bricklayers, plumbers and electricians;
[0084] In this application, the effective number of workers for a job is the product of the number of workers on duty every day in the m1th project management cycle and the number of working days in the cycle. Taking the first type of job as an example, if the number of workers corresponding to the first type of job in the m1th project management cycle is 3, and the 3 workers all work for 3 days in the m1th project management cycle, then the effective number of workers for the first type of job is 9;
[0085] Obtain the actual usage of project funds corresponding to the m1th project management period to obtain the first fund consumption;
[0086] Obtain the project additional reserve corresponding to the target engineering project, calculate the ratio of the project additional reserve to mq, and obtain the quantitative value of the project additional reserve period;
[0087] It should be noted here that:
[0088] The additional project reserve here refers to some difficult-to-quantify funds in the project construction process, excluding the labor salary cost and construction material cost, including but not limited to the funds for the use of machinery and equipment, material freight, etc.;
[0089] The first capital consumption, the quantitative value of the project additional reserve period, the effective number of workers from the first to the jth type of work, the first to the jth type of work, the first to the kth construction consumables procurement volume and the first to the kth type of construction materials are defined as the period basic data corresponding to the m1th project management period;
[0090] Acquire the periodic basic data corresponding to the project management periods m1 to mq respectively, and obtain the periodic basic data of the target project;
[0091] The data analysis module analyzes the use of funds based on the periodic basic data of the target project to obtain the periodic monitoring data of the project funds;
[0092] Obtain the periodic basic data of the target project, and obtain the periodic basic data corresponding to the m1 to mq project management periods respectively according to the periodic basic data of the target project;
[0093] Obtain the baseline capital usage for construction materials during the period, as follows:
[0094] Obtain the period basic data corresponding to the m1th project management period, and obtain the first to kth construction consumables procurement quantities and the first to kth types of construction materials respectively according to the period basic data corresponding to the m1th project management period;
[0095] Obtain the market price range values corresponding to the first to k-th types of construction materials respectively, obtain the market price range values corresponding to multiple construction materials respectively, obtain the median of each market price range value respectively, obtain the median of the market price range value corresponding to each type of construction material respectively, and name them as the first to k-th material benchmark price values respectively;
[0096] The purchase amount of the first to k construction consumables and the first to k material benchmark price values are calculated to obtain the period construction material benchmark capital usage;
[0097] The calculation of the base fund usage of construction materials in the period is as follows:
[0098] Zcl=Clj1×Cjj1+Clj2×Cjj2+……+Cljk×Cjjk;
[0099] Among them, Zcl is the benchmark capital usage of construction materials in the period, Clj1 to Cljk are the purchase quantities of the first to k construction consumables respectively, and Cjj1 to Cjjk are the benchmark price values of the first to k materials respectively;
[0100] Get the periodic manual benchmark fund usage, as follows:
[0101] According to the period basic data corresponding to the m1th project management period, the effective number of workers of the first to jth types of work and the first to jth types of work are obtained respectively;
[0102] Obtain the market price range values corresponding to the first to j-th types of work respectively, obtain the market price range values corresponding to multiple construction work types, obtain the median of the market price range values corresponding to each construction work type respectively, obtain the median of the market price range values corresponding to each type of work, and name them as the first to k-th work type benchmark price values respectively;
[0103] The effective working hours of the first to jth types of work and the benchmark price values of the first to kth types of work are calculated to obtain the period labor benchmark fund usage;
[0104] The periodic manual benchmark fund usage is calculated, and the specific formula configuration is as follows:
[0105] Gcl=Glj1×Gjj1+Glj2×Gjj2+……+Gljj×Gjjj;
[0106] Among them, Gcl is the benchmark capital usage of construction materials during the period, Glj1 to Gljj are the effective number of workers from the first to the jth type of work, and Gjj1 to Gjjj are the benchmark price values from the first to the kth type of work;
[0107] Obtain the first fund consumption and the project additional reserve cycle quantitative value according to the cycle basic data corresponding to the m1th project management cycle;
[0108] The project cycle benchmark fund usage corresponding to the m1th project management cycle is obtained by calculating the project additional reserve cycle quantified value, cycle construction material benchmark fund usage, and cycle construction material benchmark fund usage;
[0109] Calculate the project cycle benchmark fund usage corresponding to the m1th project management cycle. The specific formula configuration is as follows:
[0110] Jzs=Fjj+Zcl+Gcl;
[0111] Among them, Jzs is the project cycle benchmark fund usage corresponding to the m1th project management cycle, Zcl is the cycle construction material benchmark fund usage, and Gcl is the cycle construction material benchmark fund usage;
[0112] Repeat the process of obtaining the project cycle benchmark fund usage corresponding to the m1th project management cycle, and obtain the project cycle benchmark fund usage corresponding to the m2th to mqth project management cycles respectively;
[0113] Obtain the actual usage of project funds corresponding to the m1 to mq project management cycles of the target project's periodic basic data;
[0114] Compare the actual amount of project funds used in each project management cycle with the benchmark amount of funds used in the project cycle to obtain the periodic monitoring data of project funds;
[0115] The numerical comparison process is as follows:
[0116] When the actual amount of project funds used is greater than the baseline amount of funds used during the project cycle, the project management cycle is judged to be the first type of project management cycle;
[0117] When the actual amount of project funds used is less than or equal to the project cycle benchmark amount of funds used, the project management cycle is judged to be the second type of project management cycle;
[0118] It should be noted here that:
[0119] In this application, there are abnormalities in fund management during the first type of project management cycle, and there are no abnormalities in fund management during the second type of project management cycle;
[0120] The data analysis module acquires the periodic monitoring data of project funds and transmits it to the project management module;
[0121] The project management module conducts periodic project early warning based on the periodic monitoring data of project funds;
[0122] Obtain periodic monitoring data on project funds;
[0123] For the first type of project management cycle, the project management system issues warnings for abnormal fund use and strengthens supervision of the first to jth types of work and the first to kth types of construction materials;
[0124] For the second type of project management cycle, the project management system does not issue warnings for abnormal fund use;
[0125] In this application, if corresponding calculation formulas appear, the above calculation formulas are all dimensionless and take their numerical calculations. The weight coefficients, proportional coefficients and other coefficients in the formulas are set to a result value obtained by quantifying each parameter. The size of the weight coefficient and the proportional coefficient can be determined as long as it does not affect the proportional relationship between the parameter and the result value.
[0126] Embodiment 2
[0127] See also Figure 2 Based on another concept of the same invention, an information system integration project management method is now proposed, comprising the following steps:
[0128] Step Y1: Obtain periodic basic data of the target project;
[0129] Step Y11: in the process of integrated management of the target engineering project, mq project management cycles are marked in chronological order and named as m1 to mq project management cycles respectively;
[0130] Step Y12: Analyze the use of funds for the m1th project management cycle to obtain the cycle basic data corresponding to the m1th project management cycle;
[0131] The step Y12 further includes the following specific steps:
[0132] Step Y121: Obtain the project construction material procurement list corresponding to the m1th project management cycle, and classify the construction materials used in the m1th project management cycle into the first to kth types of construction materials according to the project construction material procurement list;
[0133] Step Y122: Obtain the material quantities corresponding to the first to k-th types of construction materials respectively, and obtain the purchase quantities of the first to k-th construction consumables;
[0134] Step Y123: Obtain the project construction personnel work list corresponding to the m1th project management cycle, and classify the construction personnel used in the m1th project management cycle into the first to jth types of work according to the project construction personnel work list;
[0135] Step Y124: Obtain the cumulative effective working times corresponding to the first to j-th types of work in the m1-th project management period, and obtain the effective working times of the first to j-th types of work;
[0136] Step Y125: Obtain the actual usage of project funds corresponding to the m1th project management period to obtain the first fund consumption;
[0137] Step Y126: Obtain the project additional reserve corresponding to the target engineering project, calculate the ratio of the project additional reserve to mq, and obtain the quantitative value of the project additional reserve period;
[0138] Step Y127: define the first capital consumption, the quantitative value of the project additional reserve period, the effective number of workers from the first to the jth type of work, the first to the jth type of work, the first to the kth construction consumables procurement volume and the first to the kth type of construction materials as the period basic data corresponding to the m1th project management period;
[0139] Step Y13: acquiring the period basic data corresponding to the m1 to mq project management periods respectively, and obtaining the period basic data of the target project;
[0140] Step Y2: Analyze the use of funds based on the periodic basic data of the target project to obtain the periodic monitoring data of the project funds;
[0141] Step Y21: Obtain the periodic basic data of the target project, and obtain the periodic basic data corresponding to the m1 to mq project management periods respectively according to the periodic basic data of the target project;
[0142] Step Y22: Obtain the baseline capital usage of construction materials during the period, as follows:
[0143] The step Y22 further includes the following specific steps:
[0144] Step Y221: Obtain the period basic data corresponding to the m1th project management period, and obtain the first to kth construction consumables procurement quantities and the first to kth types of construction materials respectively according to the period basic data corresponding to the m1th project management period;
[0145] Step Y222: Obtain the market price range values corresponding to the first to k-th types of construction materials respectively, obtain the market price range values corresponding to multiple construction materials respectively, obtain the median of each market price range value respectively, obtain the median of the market price range value corresponding to each type of construction material respectively, and name them as the first to k-th material benchmark price values respectively;
[0146] Step Y223: Calculate the first to k construction consumables purchase quantities and the first to k material benchmark price values to obtain the period construction material benchmark capital usage;
[0147] The calculation of the base fund usage of construction materials in the period is as follows:
[0148] Zcl=Clj1×Cjj1+Clj2×Cjj2+……+Cljk×Cjjk;
[0149] Among them, Zcl is the benchmark capital usage of construction materials in the period, Clj1 to Cljk are the purchase quantities of the first to k construction consumables respectively, and Cjj1 to Cjjk are the benchmark price values of the first to k materials respectively;
[0150] Step Y23: Obtain the periodic manual benchmark fund usage, as follows:
[0151] Step Y231: Obtain the first to j-th types of work and the first to j-th types of work's effective attendance numbers respectively according to the period basic data corresponding to the m1-th project management period;
[0152] Step Y232: respectively obtain the market price range values corresponding to the first to j-th types of work, obtain the market price range values corresponding to multiple construction work types, respectively obtain the median of the market price range values corresponding to each construction work type, obtain the median of the market price range values corresponding to each type of work type, and name them as the first to k-th work type benchmark price values;
[0153] Step Y233: Calculate the effective working hours of the first to j-th types of work and the benchmark price values of the first to k-th types of work to obtain the period labor benchmark fund usage;
[0154] The periodic manual benchmark fund usage is calculated, and the specific formula configuration is as follows:
[0155] Gcl=Glj1×Gjj1+Glj2×Gjj2+……+Gljj×Gjjj;
[0156] Among them, Gcl is the benchmark capital usage of construction materials during the period, Glj1 to Gljj are the effective number of workers from the first to the jth type of work, and Gjj1 to Gjjj are the benchmark price values from the first to the kth type of work;
[0157] Step Y24: Obtain the first capital consumption amount and the project additional reserve period quantitative value according to the period basic data corresponding to the m1th project management period;
[0158] Step Y25: Calculate the project cycle benchmark fund usage corresponding to the m1th project management cycle by using the project additional reserve cycle quantified value, the cycle construction material benchmark fund usage, and the cycle construction material benchmark fund usage;
[0159] Calculate the project cycle benchmark fund usage corresponding to the m1th project management cycle. The specific formula configuration is as follows:
[0160] Jzs=Fjj+Zcl+Gcl;
[0161] Among them, Jzs is the project cycle benchmark fund usage corresponding to the m1th project management cycle, Zcl is the cycle construction material benchmark fund usage, and Gcl is the cycle construction material benchmark fund usage;
[0162] Step Y26: Repeat the process of obtaining the project cycle benchmark fund usage corresponding to the m1th project management cycle, and obtain the project cycle benchmark fund usage corresponding to the m2th to mqth project management cycles respectively;
[0163] Step Y27: Obtain the actual usage of project funds corresponding to the m1 to mq project management periods of the target project periodic basic data;
[0164] Step Y28: Compare the actual usage of project funds corresponding to each project management cycle with the baseline usage of project funds in the project cycle to obtain periodic monitoring data of project funds;
[0165] The numerical comparison process is as follows:
[0166] Step Y281: When the actual amount of project funds used is greater than the project cycle benchmark amount of funds used, the project management cycle is determined to be a first type of project management cycle;
[0167] Step Y282: When the actual amount of project funds used is less than or equal to the project cycle benchmark amount of funds used, the project management cycle is determined to be a second type of project management cycle;
[0168] Step Y3: Conduct periodic project early warning based on periodic monitoring data of project funds;
[0169] Step Y31: Obtaining periodic monitoring data of project funds;
[0170] Step Y32: For the first type of project management cycle, the project management system issues an abnormal warning of fund use and strengthens supervision of the first to jth types of work and the first to kth types of construction materials;
[0171] Step Y33: For the second type of project management cycle, the project management system does not issue an abnormal warning for fund use.
[0172] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. An information system integration project management system and management method, characterized in that: include: Data acquisition module: used to divide the target engineering project into multiple project management cycles, obtain the quantitative value of the project additional reserve cycle, capital consumption, effective number of workers, type of work, construction materials and purchase volume of construction consumables corresponding to each project management cycle, obtain the cycle basic data, and define the cycle basic data corresponding to each project management cycle as the target project periodic basic data; Data analysis module: used to obtain the periodic construction material benchmark fund usage and periodic labor benchmark fund usage corresponding to each project management cycle according to the periodic basic data of the target project, calculate the periodic construction material benchmark fund usage, periodic labor benchmark fund usage and the quantitative value of the project additional reserve fund cycle to obtain the project periodic benchmark fund usage, compare the project periodic benchmark fund usage with the actual project fund usage, and obtain the project fund periodic monitoring data; Project management module: used to conduct periodic project early warning based on periodic monitoring data of project funds.
2. The information system integration project management system and management method according to claim 1, characterized in that: The data acquisition module acquires the periodic basic data of the target project, as follows: In the process of integrated management of the target engineering project, mq project management cycles are marked in chronological order and named as m1 to mq project management cycles respectively; Conduct fund utilization analysis on the m1th project management cycle to obtain the cycle basic data corresponding to the m1th project management cycle; Obtain the period basic data corresponding to the m2 to mq project management periods respectively; The period basic data corresponding to the m1 to mq project management periods are defined as the target project periodic basic data.
3. The information system integration project management system and management method according to claim 2, characterized in that: The data acquisition module acquires the period basic data corresponding to the m1th project management period, as follows: Get the purchase quantities of the first to k types of construction materials and the first to k construction consumables; Obtain a work list of project construction personnel corresponding to the m1th project management cycle, and classify the construction personnel used in the m1th project management cycle into the first to jth types of work according to the work list of project construction personnel; Obtain the cumulative effective working times corresponding to the first to j-th types of work in the m1-th project management cycle, and obtain the effective working times of the first to j-th types of work; Obtain the actual usage of project funds corresponding to the m1th project management period to obtain the first fund consumption; Obtain the project additional reserve corresponding to the target engineering project, calculate the ratio of the project additional reserve to mq, and obtain the quantitative value of the project additional reserve period; The first capital consumption, the quantitative value of the project additional reserve cycle, the effective number of people working from the first to the jth type of work, the first to the jth type of work, the first to the kth construction consumables procurement volume and the first to the kth type of construction materials are defined as the cycle basic data corresponding to the m1th project management cycle.
4. The information system integration project management system and management method according to claim 2, characterized in that: The data acquisition module acquires the purchase quantities of the first to k-th types of construction materials and the first to k-th construction consumables, as follows: Obtain a project construction material procurement list corresponding to the m1th project management cycle, and classify the construction materials used in the m1th project management cycle into first to kth types of construction materials according to the project construction material procurement list; Obtain the material quantities corresponding to the first to k-th types of construction materials respectively, and obtain the purchase quantities of the first to k-th construction consumables; Get the effective number of people working for the first to j-th types of work and the first to j-th types of work.
5. The information system integration project management system and management method according to claim 1, characterized in that: The data analysis module acquires the periodic monitoring data of project funds, as follows: Obtain the periodic basic data of the target project, and obtain the periodic basic data corresponding to the m1 to mq project management periods respectively according to the periodic basic data of the target project; Obtain the periodic construction material benchmark fund usage corresponding to the m1th project management period; Obtain the period labor benchmark fund usage corresponding to the m1th project management period; Obtain the project cycle benchmark fund usage corresponding to the m1th project management cycle; The project cycle benchmark fund usage corresponding to the m1th project management cycle is obtained by calculating the project additional reserve cycle quantified value, cycle construction material benchmark fund usage, and cycle construction material benchmark fund usage; Calculate the project cycle benchmark fund usage corresponding to the m1th project management cycle; Repeat the process of obtaining the project cycle benchmark fund usage corresponding to the m1th project management cycle, and obtain the project cycle benchmark fund usage corresponding to the m2th to mqth project management cycles respectively; Obtain the actual usage of project funds corresponding to the m1 to mq project management cycles of the target project's periodic basic data; The actual usage of project funds corresponding to each project management cycle is compared with the benchmark usage of project funds in the project cycle to obtain the periodic monitoring data of project funds.
6. The information system integration project management system and management method according to claim 5, characterized in that: The data analysis module obtains the periodic construction material benchmark fund usage corresponding to the m1th project management period, as follows: Obtain the period basic data corresponding to the m1th project management period, and obtain the first to kth construction consumables procurement quantities and the first to kth types of construction materials respectively according to the period basic data corresponding to the m1th project management period; Obtain the market price range values corresponding to the first to k-th types of construction materials respectively, obtain the market price range values corresponding to multiple construction materials respectively, obtain the median of each market price range value respectively, obtain the median of the market price range value corresponding to each type of construction material respectively, and name them as the first to k-th material benchmark price values respectively; The purchase amount of the first to k construction consumables and the first to k material benchmark price values are calculated to obtain the period construction material benchmark capital usage; Calculate the baseline funding usage for periodic construction materials.
7. The information system integration project management system and management method according to claim 6, characterized in that: The data analysis module obtains the periodic manual benchmark fund usage, as follows: According to the period basic data corresponding to the m1th project management period, the effective number of workers of the first to jth types of work and the first to jth types of work are obtained respectively; Obtain the market price range values corresponding to the first to j-th types of work respectively, obtain the market price range values corresponding to multiple construction work types, obtain the median of the market price range values corresponding to each construction work type respectively, obtain the median of the market price range values corresponding to each type of work, and name them as the first to k-th work type benchmark price values respectively; The effective working hours of the first to jth types of work and the benchmark price values of the first to kth types of work are calculated to obtain the period labor benchmark fund usage; Calculate the periodic manual benchmark fund usage; The first capital consumption and the project additional reserve period quantitative value are obtained according to the period basic data corresponding to the m1th project management period.
8. The information system integration project management system and management method according to claim 6, characterized in that: The data analysis module compares the actual amount of project funds used with the project period benchmark funds used, as follows: When the actual amount of project funds used is greater than the baseline amount of funds used during the project cycle, the project management cycle is judged to be the first type of project management cycle; When the actual usage of project funds is less than or equal to the benchmark usage of project funds during the project period, the project management period is determined to be the second type of project management period.
9. The information system integration project management system and management method according to claim 1, characterized in that: The project management module performs periodic project early warning, as follows: Obtain periodic monitoring data on project funds; For the first type of project management cycle, the project management system issues warnings for abnormal fund use and strengthens supervision of the first to jth types of work and the first to kth types of construction materials; For the second type of project management cycle, the project management system does not issue warnings for abnormal fund use.
10. An information system integration project management method, applicable to an information system integration project management system as claimed in any one of claims 1 to 9, characterized in that: The management method comprises the following specific steps: Step Y1: Obtain periodic basic data of the target project; Step Y2: Analyze the use of funds based on the periodic basic data of the target project to obtain the periodic monitoring data of the project funds; Step Y3: Conduct periodic project early warning based on periodic monitoring data of project funds.
Citation Information
Patent Citations
Distribution network project management current situation evaluation method and apparatus
CN106503920A
Management method for construction project whole process multidimensional cost management system
CN108256821A
Construction log management method and system and readable storage medium
CN108304995A
Engineering project cost assessment material cost dynamic monitoring analysis management system based on data analysis
CN114399338A
Engineering project progress analysis method and device, electronic equipment and storage medium
CN116485326A
Cited By
Decoration whole process management system based on BIM technology
CN120146781A