Prefabricated guardrail medial strip side-buried tube bundle grid constraint silicon core tube and construction method

The application of the Z-shaped fixed structure prepared by the hydraulic flat steel bending machine, the stainless steel tube bundle grid slot, and the standardized mobile hanger has solved the problems of cumbersome sequencing and low construction efficiency in silicon core pipeline construction, and achieved fast and stable silicon core pipeline installation.

CN118943985APending Publication Date: 2024-11-12CHINA RAILWAY FIRST GRP ELECTRICAL SERVICE ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410987798.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing construction process for silicon core pipelines suffers from problems such as cumbersome sequencing and fixing, low construction efficiency, and high difficulty in pipeline placement, especially in the construction of silicon core pipelines constrained by the side-buried pipe bundle grid in the central divider of prefabricated guardrails.

Method used

The construction method of the prefabricated guardrail central divider, combined with the use of a hydraulic flat steel bending machine to prepare a Z-shaped fixing structure, a stainless steel tube bundle grid slot fixing structure, and a standardized mobile hanger auxiliary installation device, includes the setting of reserved slots and support slots, the connection of angle steel columns, the welding of stainless steel tube bundle grid slots, the composition of standardized mobile hangers, and the installation steps of silicon core tubes.

Benefits of technology

It improves the construction speed and stability of silicon core tubes, simplifies the operation process, solves the problems of rapid fixing and layout sequence of pipelines, and reduces construction difficulty.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118943985A_ABST
    Figure CN118943985A_ABST
Patent Text Reader

Abstract

The invention provides a prefabricated guardrail medial strip side-buried tube bundle grid restraining silicon core tube and a construction method. The construction method comprises the following steps of prefabricated guardrail medial strip construction, road surface construction, silicon core tube installation supporting system construction, shaped movable hanging bracket auxiliary installation device construction, silicon core tube construction and silicon core tube encapsulation construction. According to the invention, the stability of the bracket is improved, the problems of rapid fixation and arrangement sequence of the silicon core pipe and high release difficulty caused by the problems of pipeline length, weight and the like are solved, and the bracket can obtain better technical economic and social benefits when being applied to practical engineering.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of construction of silicon core tubes in the central dividing zone of a prefabricated guardrail, and in particular to a silicon core tube constrained by a side-buried tube bundle grid in the central dividing zone of a prefabricated guardrail and a construction method. Background Art

[0002] The construction of highway communication pipelines is an important part of highway construction. After years of exploration and practice, the pipes used have transitioned from the earliest cement six-hole bricks to HDPE double-wall corrugated pipes and then to the silicon core pipes used later. However, the silicon core pipes have problems such as cumbersome sorting and fixing, low construction efficiency and high difficulty in laying pipelines. Research on the laying construction method of silicon core pipes is of great significance to engineering construction.

[0003] To sum up, for the construction of prefabricated guardrail central dividing zone side buried tube bundle grid constrained silicon core tube, it is very important to seek a prefabricated guardrail central dividing zone side buried tube bundle grid constrained silicon core tube with fast construction speed, simple operation, and high reliable construction quality and its construction method. Summary of the invention

[0004] The object of the present invention is to provide a prefabricated guardrail central dividing zone side-buried tube bundle grid constrained silicon core tube and a construction method to solve the above-mentioned technical problems.

[0005] In order to solve the above technical problems, the present invention provides a construction method for constraining silicon core tubes by side-buried tube bundle grids in the central dividing zone of a prefabricated guardrail, comprising the following steps:

[0006] Step 1: Construction of the central dividing strip of prefabricated guardrail: a reserved groove and a shelf groove are set on the central dividing strip of prefabricated guardrail; after the roadbed and cushion construction are completed, the central dividing strip of prefabricated guardrail is installed; the fixing rods are evenly arranged and installed in the reserved grooves; after the fixing rods are installed, a concrete leveling layer is poured to form a whole in the central dividing strip of prefabricated guardrails on both sides;

[0007] Step 2: Pavement construction: After the construction of the central median of the prefabricated guardrail is completed, the pavement construction is carried out on the upper side of the roadbed;

[0008] Step 3: Construction of the silicon core tube installation support system: the angle steel column is connected to the side of the central dividing strip of the prefabricated guardrail close to the concrete leveling layer; the two ends of the stainless steel tube bundle grille slot are connected to the angle steel column; the top sides of several of the stainless steel tube bundle grille slots are connected to the connecting rod; the "B"-shaped fixing piece is fixed to the connecting rod; so that the angle steel column, the stainless steel tube bundle grille slot, the connecting rod, and the "B"-shaped fixing piece form a silicon core tube installation support system;

[0009] Step 4: Construction of the auxiliary installation device for the standardized mobile hanger: The crossbar, the longitudinal bar and the hanger constitute the force-bearing frame of the standardized mobile hanger; a steel plate is arranged between the crossbar and the hanger; a sleeve is installed on the hanger, the sleeve is connected to the ring by a hanging rope, and the silicon core tube is inserted into the ring during installation;

[0010] Step 5: Silicon core tube construction: put different silicon core tubes into different positions of the stainless steel tube bundle grid slot;

[0011] Step 6: Silicon core tube encapsulation construction: After the installation of the silicon core tube is completed, the standardized mobile hanger is removed, and a precast concrete slab is installed on the upper part of the shelf groove; foam concrete, backfill soil, green grass, and ornamental trees are arranged in sequence on the upper part of the precast concrete slab.

[0012] Furthermore, in step one, prefabricated guardrail central dividing strips are arranged on both sides of the upper part of the cushion layer, and both ends of the fixing rod are respectively connected to the prefabricated guardrail central dividing strips on both sides, and a concrete leveling layer is poured between the prefabricated guardrail central dividing strips on both sides.

[0013] Furthermore, the "B"-shaped fixing member includes a first section and a second section which are perpendicular to each other, the first section is vertically connected to the central dividing strip of the prefabricated guardrail, and the second section is horizontally connected to the connecting rod.

[0014] Furthermore, a plurality of clamping plates are arranged at intervals on the upper side of the clamping slot of the stainless steel tube bundle grid, so that a separation area is formed between two adjacent clamping plates.

[0015] Furthermore, in step four, upper pulleys and vertical poles are provided at both ends of the crossbar, wherein a lower pulley is rotatably installed at the lower portion of the vertical pole; the upper pulley and the lower pulley slide on the top of the central dividing strip of the prefabricated guardrail and the shelf groove respectively.

[0016] Furthermore, the longitudinal rod is connected between two adjacent transverse rods, and at least two longitudinal rods are arranged between the two adjacent transverse rods, and the suspension rod is connected between the two adjacent longitudinal rods, so that the suspension rod and the transverse rod are arranged horizontally.

[0017] Furthermore, a number of standardized movable hangers are placed between the central dividing strips of two adjacent prefabricated guardrails, so that the silicon core tubes can be inserted into a number of rings at the same time.

[0018] Furthermore, in step five, when placing the silicon core tubes, several silicon core tubes are clamped in sequence and placed in several separation areas, so that both sides of the silicon core tubes are limited by the clamping plates, and two adjacent silicon core tubes are separated by the clamping plates.

[0019] The invention also discloses a prefabricated guardrail central dividing zone side-buried tube bundle grid to constrain the silicon core tube, which is obtained by a construction method of a prefabricated guardrail central dividing zone side-buried tube bundle grid to constrain the silicon core tube.

[0020] The beneficial effects of the present invention are:

[0021] 1. The present invention adopts a hydraulic flat steel bending machine with a B-shaped overlap fixing structure to improve the stability of the bracket;

[0022] 2. The present invention adopts a stainless steel tube bundle grid slot-type fixing structure to solve the problem of rapid fixing and arrangement sequence of silicon core tubes;

[0023] 3. The present invention adopts a standardized mobile hanger auxiliary installation device to solve the problem of high difficulty in deployment caused by problems such as pipeline length and weight. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 This is a schematic diagram of the installation section of the central dividing strip of the prefabricated guardrail;

[0025] Figure 2 It is a schematic diagram of the side section and front elevation of the central dividing strip of the prefabricated guardrail;

[0026] Figure 3 It is a schematic diagram of the installation section of the silicon core tubes restrained by the side buried tube grid of the central dividing strip of the prefabricated guardrail;

[0027] Figure 4 This is a schematic diagram of the installation sample of the silicon core tube;

[0028] Figure 5 This is a schematic diagram of welding of "B"-shaped fixings;

[0029] Figure 6 It is a schematic diagram of the top encapsulation cross section of the silicon core tube;

[0030] Figure 7 It is a cross-sectional diagram of the auxiliary installation of a standardized mobile hanger;

[0031] Figure 8 It is a plan view of the standardized mobile hanger auxiliary installation.

[0032] In the figure: 1-roadbed, 2-cushion, 3-pavement, 4-leveling layer, 5-fixed rod, 6-prefabricated guardrail central dividing strip, 7-reserved slot, 8-shelf slot, 9-angle steel column, 10-stainless steel tube bundle grille slot, 11-connecting rod, 12-silicon core tube, 13-"B" shaped fixing parts, 14-prefabricated concrete slab, 15-foam concrete, 16-backfill soil, 17-green grass, 18-ornamental trees, 19-standardized mobile hanger, 20-sleeve, 21-upper pulley, 22-lower pulley, 23-upright pole, 24-lifting rope, 25-ring, 26-cross bar, 27-longitudinal bar, 28-hanging rod, 29-steel plate. DETAILED DESCRIPTION

[0033] The following will be combined with the accompanying drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.

[0034] Those skilled in the art should understand that, in the disclosure of the present invention, the orientation or position relationship indicated by the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. are based on the orientation or position relationship shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the above terms should not be understood as limiting the present invention.

[0035] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.

[0036] like Figure 1-8 The present invention provides a construction method for a prefabricated guardrail central dividing zone side buried tube bundle grid to constrain silicon core tubes, comprising the following steps:

[0037] Step 1: Construction of the central divider strip of the prefabricated guardrail: The components of the central divider strip of the prefabricated guardrail 6 are prefabricated in batches in the factory, and a reserved groove 7 and a shelf groove 8 are set on them; after the construction of the roadbed 1 and the cushion layer 2 is completed, the central divider strip of the prefabricated guardrail 6 is installed; the fixing rods 5 are prefabricated concrete components, which are evenly arranged and installed in the reserved grooves 7; after the fixing rods 5 are installed, the concrete leveling layer 4 is poured to form the central divider strips 6 of the prefabricated guardrails on both sides as a whole;

[0038] Among them, prefabricated guardrail central dividing strips 6 are arranged on both sides of the upper part of the cushion layer 2, and the two ends of the fixing rod 5 are respectively connected to the prefabricated guardrail central dividing strips 6 on both sides, and a concrete leveling layer 4 is poured between the prefabricated guardrail central dividing strips 6 on both sides.

[0039] Step 2: Pavement construction: After the construction of the prefabricated guardrail central dividing strip 6 is completed, the pavement 3 is constructed on the upper side of the roadbed 1;

[0040] Step 3: Construction of the silicon core tube installation support system: Angle steel column 9 is fixedly connected to the side of the prefabricated guardrail central dividing strip 6 close to the concrete leveling layer 4 by fixing bolts; both ends of the stainless steel tube bundle grille slot 10 are welded to the angle steel column 9; the top sides of several of the stainless steel tube bundle grille slots 10 are welded to the connecting rod 11; "B"-shaped fixing piece 13 is welded and fixed to the connecting rod 11; so that the angle steel column 9, the stainless steel tube bundle grille slot 10, the connecting rod 11, and the "B"-shaped fixing piece 13 form a silicon core tube 12 installation support system;

[0041] The “B”-shaped fixing member 13 includes a first section and a second section which are perpendicular to each other. The first section is vertically connected to the central dividing strip 6 of the prefabricated guardrail, and the second section is horizontally connected to the connecting rod 11 .

[0042] A plurality of clamping plates are arranged at intervals on the upper side of the stainless steel tube bundle grid clamping slot 10 so as to form a separation area between two adjacent clamping plates.

[0043] Step 4, construction of the auxiliary installation device of the standardized mobile hanger: the crossbar 26, the longitudinal bar 27, and the hanger 28 form a force-bearing frame of the standardized mobile hanger 19; the steel plate 29 is welded between the crossbar 26 and the hanger 28; the upper pulley 21 and the vertical rod 23 are arranged at both ends of the crossbar 26, wherein the lower pulley 22 is rotatably installed at the lower part of the vertical rod 23; the upper pulley 21 and the lower pulley 22 slide on the top of the central dividing strip 6 of the prefabricated guardrail and the shelf groove 8 respectively; the vertical rod 23 and the lower pulley 22 enable the standardized mobile hanger 19 to move inside the central dividing strip 6 of the two adjacent prefabricated guardrails and play a positioning role; the sleeve 20 is movably installed on the hanger 28, and the sleeve 20 is connected to the ring 25 by a lifting rope 24, wherein the length of the lifting rope 24 is determined according to the site, and the silicon core tube 12 is inserted into the ring 25 during installation, which improves the convenience of installation;

[0044] The longitudinal rod 27 is connected between two adjacent transverse rods 26 , and at least two longitudinal rods 27 are arranged between two adjacent transverse rods 26 . The suspension rod 28 is connected between two adjacent longitudinal rods 27 , so that the suspension rod 28 and the transverse rod 26 are arranged horizontally.

[0045] In one embodiment of the present scheme, a plurality of standardized movable hangers 19 are placed between the central dividing strips 6 of two adjacent prefabricated guardrails, so that the silicon core tubes 12 can be inserted into a plurality of collars 25 at the same time to ensure the stability of the silicon core tubes 12 when being suspended.

[0046] Step 5: Silicon core tube construction: different silicon core tubes 12 are placed in different positions of the stainless steel tube bundle grid slot 10, which solves the problem of rapid fixation and arrangement order of the silicon core tubes 12;

[0047] Specifically, when placing the silicon core tubes 12, several silicon core tubes 12 are clamped and placed in several separation areas in sequence, so that both sides of the silicon core tubes 12 are limited by the clamping plates, and two adjacent silicon core tubes 12 are separated by the clamping plates.

[0048] Step 6, silicon core tube encapsulation construction: After the silicon core tube 12 is installed, remove the standardized mobile hanger 19, and install the precast concrete slab 14 on the upper part of the shelf groove 8; foam concrete 15, backfill soil 16, green grass 17, and ornamental trees 18 are arranged on the upper part of the precast concrete slab 14 in sequence.

[0049] The present invention also discloses a prefabricated guardrail central dividing strip side-buried tube bundle grid constrained silicon core tube, comprising a roadbed 1, a cushion layer 2, a road surface 3, a leveling layer 4, a fixing rod 5, a prefabricated guardrail central dividing strip 6, a reserved groove 7, a shelf groove 8, an angle steel column 9, a stainless steel tube bundle grid slot 10, a connecting rod 11, a silicon core tube 12, a "B"-shaped fixing piece 13, a prefabricated concrete slab 14, foam concrete 15, backfill 16, green grass 17, ornamental trees 18, a standardized mobile hanger 19, a sleeve 20, an upper pulley 21, a lower pulley 22, a vertical rod 23, a lifting rope 24, a collar 25, a crossbar 26, a longitudinal rod 27, a hanging rod 28, and a steel plate 29; and also includes preparing a "B"-shaped fixing piece for lapped brackets by a hydraulic flat steel bending machine, a stainless steel tube bundle grid pipeline laying technology, a standardized mobile hanger 19 auxiliary installation device, and a silicon core tube 12 top prefabricated slab foam concrete encapsulation technology.

[0050] The standardized mobile hanger 19 includes a sleeve 20, an upper pulley 21, a lower pulley 22, a vertical rod 23, a suspension rope 24, a ring 25, a cross bar 26, a longitudinal rod 27, a suspension rod 28, and a steel plate 29.

[0051] The present invention is not limited to the above-mentioned optimal implementation mode. Anyone can derive other various forms of products under the inspiration of the present invention. However, no matter what changes are made in the shape or structure, all technical solutions that are the same or similar to those of the present application fall within the protection scope of the present invention.

Claims

1. The construction method of the side buried tube grid of the central dividing strip of the prefabricated guardrail to restrain the silicon core tube is characterized by: The following steps are involved: Step 1, construction of the central dividing strip of the prefabricated guardrail: a reserved groove (7) and a shelf groove (8) are set on the central dividing strip of the prefabricated guardrail (6); after the construction of the roadbed (1) and the cushion layer (2) is completed, the central dividing strip of the prefabricated guardrail (6) is installed; the fixing rods (5) are evenly arranged and installed in the reserved grooves (7); after the fixing rods (5) are installed, a concrete leveling layer (4) is poured to form a whole of the central dividing strips of the prefabricated guardrails (6) on both sides; Step 2: Pavement construction: After the construction of the prefabricated guardrail central dividing strip (6) is completed, the pavement (3) is constructed on the upper side of the roadbed (1); Step 3: Construction of the silicon core tube installation support system: the angle steel column (9) is connected to the side of the central dividing strip (6) of the prefabricated guardrail close to the concrete leveling layer (4); the two ends of the stainless steel tube bundle grille slot (10) are connected to the angle steel column (9); the top sides of a plurality of the stainless steel tube bundle grille slots (10) are connected to the connecting rod (11); the "B"-shaped fixing piece (13) is fixed to the connecting rod (11); so that the angle steel column (9), the stainless steel tube bundle grille slot (10), the connecting rod (11), and the "B"-shaped fixing piece (13) form the silicon core tube (12) installation support system; Step 4: Construction of the standardized mobile hanger auxiliary installation device: The cross bar (26), the longitudinal bar (27), and the suspension rod (28) form a force-bearing frame of the standardized mobile hanger (19); a steel plate (29) is arranged between the cross bar (26) and the suspension rod (28); a sleeve (20) is movably installed on the suspension rod (28), and the sleeve (20) is connected to the ring (25) by a suspension rope (24), and the silicon core tube (12) is inserted into the ring (25) during installation; Step 5: Silicon core tube construction: different silicon core tubes (12) are placed in different positions of the stainless steel tube bundle grid slot (10); Step 6: Silicon core tube encapsulation construction: After the installation of the silicon core tube (12) is completed, the standardized mobile hanger (19) is removed, and a precast concrete slab (14) is installed on the upper part of the shelf groove (8); foam concrete (15), backfill soil (16), green grass (17), and ornamental trees (18) are arranged in sequence on the upper part of the precast concrete slab (14).

2. The construction method of the prefabricated guardrail central dividing strip side buried tube grid constraining silicon core tube according to claim 1 is characterized by: In step 1, prefabricated guardrail central dividing strips (6) are arranged on both sides of the upper part of the cushion layer (2), and the two ends of the fixing rod (5) are respectively connected to the prefabricated guardrail central dividing strips (6) on both sides, and a concrete leveling layer (4) is poured between the prefabricated guardrail central dividing strips (6) on both sides.

3. The construction method of the side-buried tube bundle grid constraining the silicon core tube in the central dividing zone of the prefabricated guardrail according to claim 1 is characterized by: The "B"-shaped fixing member (13) comprises a first section and a second section which are perpendicular to each other, wherein the first section is vertically connected to the central dividing strip (6) of the prefabricated guardrail, and the second section is horizontally connected to the connecting rod (11).

4. The construction method of the prefabricated guardrail central dividing strip side buried tube grid constraining silicon core tube according to claim 1, characterized in that: A plurality of clamping plates are arranged at intervals on the upper side of the stainless steel tube bundle grid clamping groove (10) so as to form a separation area between two adjacent clamping plates.

5. The construction method of the prefabricated guardrail central dividing strip side buried tube grid constraining silicon core tube according to claim 1, characterized in that: In step 4, upper pulleys (21) and vertical rods (23) are provided at both ends of the crossbar (26), wherein a lower pulley (22) is rotatably installed at the lower part of the vertical rod (23); the upper pulley (21) and the lower pulley (22) slide on the top of the central dividing strip (6) of the prefabricated guardrail and the shelf groove (8) respectively.

6. The construction method of the prefabricated guardrail central dividing strip side buried tube grid constraining silicon core tube according to claim 1, characterized in that: The longitudinal rod (27) is connected between two adjacent transverse rods (26), and at least two longitudinal rods (27) are arranged between the two adjacent transverse rods (26). The suspension rod (28) is connected between the two adjacent longitudinal rods (27), so that the suspension rod (28) and the transverse rod (26) are arranged horizontally.

7. The construction method of the prefabricated guardrail central dividing strip side buried tube grid constraining silicon core tube according to claim 1, characterized in that: A plurality of standardized movable hangers (19) are placed between the central dividing strips (6) of two adjacent prefabricated guardrails, so that the silicon core tubes (12) can be inserted into a plurality of sleeve rings (25) at the same time.

8. The construction method of the prefabricated guardrail central dividing strip side buried tube grid constraining silicon core tube according to claim 4, characterized in that: In step five, when placing the silicon core tubes (12), a plurality of silicon core tubes (12) are sequentially clamped and placed in a plurality of separation areas, so that both sides of the silicon core tubes (12) are limited by the clamping plates, and two adjacent silicon core tubes (12) are separated by the clamping plates.

9. A prefabricated guardrail central dividing zone side buried tube bundle grid constrained silicon core tube, characterized by: The method is obtained by the construction method of the prefabricated guardrail central dividing zone side-buried tube bundle grid constraining the silicon core tube as described in any one of claims 1-8.