Prefabricated cable trench assembly auxiliary straightening device
By using a prefabricated cable trench assembly auxiliary straightening device, the skew problem during the assembly process of the prefabricated cable trench is solved by using straightening clamps and counterweights, thereby improving the stability and aesthetics of the cable trench, adapting to the straightening of cable trenches of different widths, and ensuring the smoothness and levelness of the cable trench.
Patent Information
- Application Number
- CN202411198763.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-15
AI Technical Summary
Precast cable trenches suffer from skewness and unevenness due to cumulative errors during assembly, affecting overall stability and aesthetics, making them difficult to match with cast-in-place concrete cable trenches.
A prefabricated cable trench assembly auxiliary straightening device is adopted, including straightening clamps and a counterweight device. The clamps are used to fit against the side wall of the cable trench for straightening, and the clamp spacing is adjusted by a connecting mechanism and a locking device. The counterweight device increases the mass of the previous cable trench to stabilize the straightening process.
It effectively solves the problem of skewing during the assembly of prefabricated cable trenches, improves the stability and aesthetics of the cable trenches, enhances the flexibility and adaptability of the straightening device, and ensures the smoothness and levelness of the cable trenches.
Smart Images

Figure CN118958366A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of cable trench construction, and in particular relates to a prefabricated cable trench assembly auxiliary straightening device. Background Art
[0002] In the construction of power infrastructure, prefabricated cable trenches are widely used in projects such as urban power grid transformation, new industrial zones and large-scale building complexes as an efficient and convenient solution for laying underground cables due to their advantages of standardized production, rapid installation and cost control. However, in the actual construction process, the assembly and installation quality of prefabricated cable trenches is often restricted by many factors, one of the most prominent problems being the lack of fit between the prefabricated cable trench and the foundation cushion and the difficulty in overall straightening.
[0003] During the installation of traditional prefabricated cable trenches, a cushion layer of a certain thickness must first be laid on site. This cushion layer is usually completed by artificially pouring concrete to provide a flat and solid support surface. However, due to the differences in construction technology, the complexity of the on-site environment, and the shrinkage and deformation of concrete during solidification, it is difficult for the bottom plate of the prefabricated cable trench to fit completely with the cushion layer, resulting in small or significant gaps. These gaps not only weaken the overall stability of the structure, but also make the prefabricated cable trench prone to "unsteady up and down shaking" when subjected to external forces, increasing safety hazards.
[0004] In addition, during the continuous assembly of multiple prefabricated cable trenches, the initial positioning needs to be done by mechanical traction, supplemented by a large amount of manual adjustment to ensure the alignment between adjacent cable trenches. Although this operation method can achieve a good leveling effect in a local area, as the assembly length increases, the cumulative error gradually appears, eventually leading to the problem of "front and back skewness and non-straightness" in the entire cable trench line. This non-straightness not only affects the aesthetics of the cable trench, but more importantly, it seriously restricts the possibility of the prefabricated cable trench reaching the cast-in-place level. Cast-in-place concrete cable trenches can achieve high straightness and stability due to the continuity and integrity of their construction process. If the prefabricated cable trench cannot effectively solve the cumulative error problem during the assembly process, its overall performance will be difficult to compare with that of cast-in-place cable trenches. Summary of the invention
[0005] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a prefabricated cable trench assembly auxiliary straightening device to solve the problem of "front and back skewness and non-straightness" of the cable trench caused by accumulated errors in the existing prefabricated cable trench assembly process.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is:
[0007] A prefabricated cable trench assembly auxiliary straightening device comprises two straightening clamps symmetrically arranged on the side walls of the prefabricated cable trench, the two straightening clamps are connected by a connecting mechanism, the straightening clamps comprise a top plate, each of the two sides of the top plate is provided with a clamping plate, the clamping plates on both sides are arranged in parallel, and the inner walls of the clamping plates are against the side walls of the prefabricated cable trench, the straightening mechanism moves on the side walls of the cable trench, and uses the parallel clamping plates on both sides of the top plate to straighten adjacent prefabricated cable trenches.
[0008] Furthermore, it also includes a counterweight device, which is connected to the straightening device, or is configured separately. The counterweight device is placed in the previous prefabricated cable trench in adjacent prefabricated cable trenches to increase the mass of the previous prefabricated cable trench.
[0009] Furthermore, the connection mechanism includes a fixing seat fixedly mounted on the upper portion of the top plate, second studs are threadedly connected to the fixing seats on both sides, and a second hand wheel is fixedly connected to the middle of the second stud.
[0010] Furthermore, one of the straightening fixtures is fixedly connected to a shaft sleeve on both sides, and the other straightening fixture is fixedly connected to a guide rod on both sides, and the guide rod is slidably inserted in the shaft sleeve.
[0011] Furthermore, a plurality of guide rails are provided on one side of the top plate, two slide seats are symmetrically provided on the guide rails, the splint is fixedly installed on one side of the slide seat, a plurality of rib plates are connected between the splint and the slide seat, a plurality of sliders are provided on the other side of the slide seat, the sliders are slidably installed on the guide rails, a first stud is rotatably installed inside the top plate, and the threads at both ends of the first stud have opposite rotation directions, one end of the first stud is connected to a first hand wheel, and the lower part of the slide seat is threadedly connected to the first stud via a screw sleeve.
[0012] Furthermore, a locking device is provided on one side of the top plate, and the locking device includes a connecting plate fixedly installed on the side wall of the top plate, a sleeve is provided on one side of the connecting plate, and a through hole for accommodating a first stud is provided in the middle of the connecting plate and the sleeve, a first slot is provided on the side of the sleeve close to the connecting plate, a second slot is provided on the sleeve, and the second slot forms an opening on one side of the through hole, and a locking knob is threadedly connected to the sleeve, and the locking knob is connected to the opening of the sleeve.
[0013] Furthermore, a plurality of evenly arranged bull's eye bearings are provided on the inner wall of the clamping plate.
[0014] Furthermore, a plurality of brackets are provided on one side of the top plate, and a plurality of rollers are rotatably connected to one end of the brackets. During the straightening operation, the lower surface of the rollers contacts the upper end of the prefabricated cable trench.
[0015] Furthermore, both ends of the clamping plate are provided with chamfers, so that the front end opening of the straightening fixture is larger than the thickness of the prefabricated cable trench.
[0016] Furthermore, a level is provided on the upper part of the straightening fixture, and the level includes two mutually perpendicular level bubbles for calibrating the horizontality of the cable trench.
[0017] The beneficial effects of the present invention are:
[0018] 1) The present invention utilizes the clamping plate of the straightening fixture to fit the side wall of the prefabricated cable trench. When the straightening fixture moves, it straightens two adjacent prefabricated cable trenches, thereby solving the problem of "front and back skewness" of the cable trench caused by accumulated errors in the assembly process of the existing prefabricated cable trenches, and avoiding the problems of uneven straightening or over-correction that may occur in traditional manual straightening.
[0019] 2) By setting the counterweight device, the mass of the previous prefabricated cable trench is increased, the stability of the previous prefabricated cable trench is enhanced, and the reverse twisting of the previous prefabricated cable trench when the next prefabricated cable trench is straightened is avoided, thereby ensuring the straightening effect of the prefabricated cable trench.
[0020] 3) The connecting mechanism includes a fixing seat fixedly installed on the upper part of the top plate, and second studs are threadedly connected to the fixing seats on both sides. By turning the second hand wheel on the second stud, the spacing between the straightening clamps on both sides can be adjusted. This is suitable for straightening operations of prefabricated cable trenches of different widths, further improving the flexibility of the straightening device.
[0021] 4) The spacing between the clamps on both sides of the straightening fixture is adjustable, which improves the adaptability and flexibility of the straightening device. Whether facing a cable trench with a thinner thickness or a thicker cable trench, the operator only needs to simply rotate the first hand wheel to quickly and accurately adjust the spacing between the clamps to ensure that the clamps can fit tightly on both sides of the cable trench for effective straightening operations.
[0022] 5) A locking device is provided on one side of the top plate. After the spacing between the clamps on both sides is adjusted, the locking knob is tightened to reduce the opening, and the first stud is clamped with the sleeve to prevent the first stud from accidentally rotating during the straightening operation and changing the spacing between the clamps on both sides.
[0023] 6) A number of bull's eye bearings are arranged on the inner wall of the clamping plate to reduce the friction between the clamping plate and the side wall of the prefabricated cable trench. A number of rollers are arranged on one side of the top plate. During the straightening operation, the lower surface of the roller contacts the upper end of the prefabricated cable trench, which reduces the friction between the straightening device and the upper end of the prefabricated cable trench and improves the smoothness of the straightening device.
[0024] 7) A spirit level is set on the top of the straightening fixture. When the prefabricated cable trench produces the phenomenon of "unsteady up and down shaking", the level bubble on the spirit level will clearly indicate the specific direction and degree of inclination, and the construction personnel can take corresponding measures, such as using appropriate caulking materials to accurately fill the gaps to eliminate the unstable factors at the bottom. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Attached Figure 1 The present invention is a diagram showing the use status of a prefabricated cable trench assembly auxiliary straightening device.
[0026] Attached Figure 2 The present invention is a schematic diagram of the structure of a prefabricated cable trench assembly auxiliary straightening device.
[0027] Attached Figure 3 It is an exploded view of a straightening fixture in a prefabricated cable trench assembly auxiliary straightening device of the present invention.
[0028] Attached Figure 4 It is a schematic diagram of a locking device in a prefabricated cable trench assembly auxiliary straightening device of the present invention.
[0029] In the figure, 1. prefabricated cable trench; 2. straightening fixture; 21. top plate; 22. guide rail; 23. first stud; 24. first hand wheel; 25. slide seat; 251. slider; 26. clamping plate; 27. bull's eye bearing; 28. bracket; 29. roller; 3. locking device; 31. connecting plate; 32. sleeve; 33. first slot; 34. second slot; 35. locking knob; 36. through hole; 4. level; 5. fixing seat; 6. second stud; 7. second hand wheel; 8. bushing; 9. guide rod. DETAILED DESCRIPTION
[0030] The following will be combined with the attached Figure 1-Figure 4 , the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0032] like Figure 1 As shown, a prefabricated cable trench assembly auxiliary straightening device includes two straightening fixtures 2 symmetrically arranged on the side wall of the prefabricated cable trench 1, and the two straightening fixtures 2 are connected by a connecting mechanism, such as Figure 3 As shown, the straightening fixture 2 includes a top plate 21, and a clamping plate 26 is provided on each side of the top plate 21. The clamping plates 26 on both sides are arranged in parallel, and the inner walls of the clamping plates 26 are against the side walls of the prefabricated cable trench 1. The straightening mechanism moves on the side walls of the cable trench, and uses the parallel clamping plates 26 on both sides of the top plate 21 to straighten the adjacent prefabricated cable trenches.
[0033] Furthermore, it also includes a counterweight device (not shown in the figure), which is connected to the straightening device. As an implementation method, the counterweight device is a traction machine that pushes the straightening device to walk on the prefabricated cable trench 1, or the counterweight device is configured separately. As another implementation method, the counterweight device is an independent counterweight block, which is placed in the previous prefabricated cable trench in the adjacent prefabricated cable trenches to increase the mass of the previous prefabricated cable trench. According to Newton's second law, F=ma, it can be seen that under the same external force, the prefabricated subsequent cable trench with smaller mass will produce a greater acceleration, and it is more likely to produce obvious movement relative to the previous prefabricated cable trench with larger mass. On the contrary, during straightening, the previous prefabricated cable trench has stronger stability than the subsequent prefabricated cable trench, which avoids the reverse twisting of the previous prefabricated cable trench when the subsequent prefabricated cable trench is straightened, thereby ensuring the straightening effect of the prefabricated cable trench.
[0034] When using this device for straightening, when the straightening mechanism moves at the joint of two prefabricated cable trenches 1, if the side walls of the two adjacent prefabricated cable trenches are straight, the straightening mechanism can pass smoothly. When the two adjacent prefabricated cable trenches are "skewed front and back and not straight", the movement of the straightening mechanism is hindered. At this time, a counterweight device can be placed in the previous prefabricated cable trench, and then power is applied to the straightening mechanism, and the parallel clamps 26 on both sides are used to straighten the subsequent prefabricated cable trench, or the subsequent prefabricated cable trench is manually pushed for straightening. The straightening method using the clamps 26 effectively avoids the problems of uneven straightening or over-correction that may occur in traditional manual straightening.
[0035] like Figure 2 As shown, the connecting mechanism includes a fixing seat 5 fixedly installed on the upper part of the top plate 21, and a second stud 6 is threadedly connected to the fixing seat 5 on both sides, and a second hand wheel 7 is fixedly connected to the middle part of the second stud 6. By rotating the second hand wheel 7, the spacing between the straightening clamps 2 on both sides is adjusted, which is suitable for straightening operations of prefabricated cable trenches of different widths, and further improves the flexibility of the straightening device.
[0036] like Figure 2As shown, one of the straightening fixtures 2 is fixedly connected to axle sleeves 8 on both sides, and the other straightening fixture 2 is fixedly connected to guide rods 9 on both sides. The guide rods 9 are slidably inserted in the axle sleeves 8, thereby enhancing the stability of the straightening fixtures 2 on both sides after adjustment.
[0037] like Figure 3 As shown, a plurality of guide rails 22 are provided on one side of the top plate 21, two slide seats 25 are symmetrically provided on the guide rails 22, the splint 26 is fixedly installed on one side of the slide seat 25, and in order to ensure the strength and stability of the splint 26, a plurality of ribs are connected between the splint 26 and the slide seat 25, and a plurality of sliders 251 are provided on the other side of the slide seat 25, and the sliders 251 are slidably installed on the guide rails 22, a first stud 23 is rotatably installed inside the top plate 21, and the threads at both ends of the first stud 23 have opposite rotation directions, one end of the first stud 23 is connected to a first hand wheel 24, and the lower part of the slide seat 25 is threadedly connected to the first stud 23 through a screw sleeve.
[0038] By rotating the first hand wheel 24, the slides 25 on both sides are driven to move closer to or farther from each other on the top plate 21, so as to adjust the spacing between the two clamping plates 26 on the top plate 21, thereby improving the adaptability and flexibility of the straightening device. Whether facing a cable trench with a smaller thickness or a cable trench with a larger thickness, the operator only needs to simply rotate the first hand wheel 24 to quickly and accurately adjust the spacing between the clamping plates 26, ensuring that the clamping plates 26 can fit closely to both sides of the cable trench and perform effective straightening operations.
[0039] like Figure 3 , Figure 4 As shown, a locking device 3 is provided on one side of the top plate 21, and the locking device 3 includes a connecting plate 31 fixedly mounted on the side wall of the top plate 21, a sleeve 32 is provided on one side of the connecting plate 31, and a through hole 36 for accommodating the first stud 23 is provided in the middle of the connecting plate 31 and the sleeve 32, and a first slot 33 is provided on the side of the sleeve 32 close to the connecting plate 31, and a second slot 34 is provided on the sleeve 32, and the second slot 34 forms an opening on one side of the through hole 36, and a locking knob 35 is threadedly connected to the sleeve 32, and the locking knob 35 is connected to the opening of the sleeve 32; after the spacing between the clamps 26 on both sides is adjusted, the locking knob 35 is tightened to reduce the opening, and the first stud 23 is clamped by the sleeve 32, so as to avoid the first stud 23 from accidentally rotating during the straightening operation and changing the spacing between the clamps 26 on both sides.
[0040] like Figure 3 As shown, a plurality of evenly arranged bull's eye bearings 27 are provided on the inner wall of the clamping plate 26, which reduces the friction between the clamping plate 26 and the side wall of the prefabricated cable trench and improves the smoothness of the straightening device.
[0041] like Figure 3As shown, a plurality of brackets 28 are provided on one side of the top plate 21, and a plurality of rollers 29 are rotatably connected to one end of the bracket 28. During the straightening operation, the lower surface of the roller 29 contacts the upper end of the prefabricated cable trench, thereby reducing the friction between the straightening device and the upper end of the prefabricated cable trench, and further improving the smoothness of the straightening device.
[0042] As a further optimization of the present technical solution, both ends of the clamp 26 are provided with chamfers, so that the front end opening of the straightening clamp 2 is larger than the thickness of the prefabricated cable trench, thereby reducing the contact resistance at the joint between the front end of the straightening clamp 2 and the prefabricated cable trench 1, so that the straightening tool 2 can cross the joint more smoothly when it moves to the joint position.
[0043] like Figure 2 As shown, a level 4 is provided on the upper part of the straightening fixture 2. The level 4 includes two mutually perpendicular level bubbles, which are used to calibrate the level of the cable trench. When the prefabricated cable trench produces the phenomenon of "unsteady shaking up and down", the level bubble on the level 4 will clearly indicate the specific tilt direction and degree, and the construction personnel can take countermeasures, such as using appropriate caulking materials to accurately fill the gap to eliminate the unstable factors at the bottom. During the filling process, the level 4 continues to serve as a precise measuring tool. By observing the changes in the level bubble, the construction personnel are guided to continuously adjust the caulking amount until the prefabricated cable trench returns to a stable state, which effectively solves the level problem during the assembly process of the prefabricated cable trench and significantly improves the stability and durability of the assembly.
[0044] The above contents are merely examples and explanations of the structure of the present invention. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the structure of the invention or exceed the scope defined by the claims, they should all fall within the protection scope of the present invention.
Claims
1. A prefabricated cable trench assembly auxiliary straightening device, comprising two straightening fixtures symmetrically arranged on the side walls of the prefabricated cable trench, the two straightening fixtures are connected by a connecting mechanism, characterized in that: The straightening fixture includes a top plate, with a clamping plate on each side of the top plate. The clamping plates on both sides are arranged in parallel, and the inner walls of the clamping plates are against the side walls of the prefabricated cable trench. The straightening mechanism moves on the side walls of the cable trench and uses the parallel clamping plates on both sides of the top plate to straighten adjacent prefabricated cable trenches.
2. A prefabricated cable trench assembly auxiliary straightening device according to claim 1, characterized in that: It also includes a counterweight device, which is connected to the straightening device, or is configured separately. The counterweight device is placed in the previous prefabricated cable trench in adjacent prefabricated cable trenches to increase the mass of the previous prefabricated cable trench.
3. The prefabricated cable trench assembly auxiliary straightening device according to claim 1 is characterized in that: The connection mechanism comprises a fixing seat fixedly mounted on the upper part of the top plate, second studs are threadedly connected to the fixing seats on both sides, and a second hand wheel is fixedly connected to the middle part of the second stud.
4. A prefabricated cable trench assembly auxiliary straightening device according to claim 3, characterized in that: One of the straightening fixtures has shaft sleeves fixedly connected on both sides, and the other straightening fixture has guide rods fixedly connected on both sides. The guide rods are slidably inserted in the shaft sleeves.
5. The prefabricated cable trench assembly auxiliary straightening device according to claim 1 is characterized in that: A plurality of guide rails are provided on one side of the top plate, two slide seats are symmetrically provided on the guide rails, the splint is fixedly installed on one side of the slide seat, a plurality of rib plates are connected between the splint and the slide seat, a plurality of sliders are provided on the other side of the slide seat, the sliders are slidably installed on the guide rails, a first stud is rotatably installed inside the top plate, and the threads at both ends of the first stud have opposite rotation directions, one end of the first stud is connected to a first hand wheel, and the lower part of the slide seat is threadedly connected to the first stud via a threaded sleeve.
6. A prefabricated cable trench assembly auxiliary straightening device according to claim 5, characterized in that: A locking device is provided on one side of the top plate, and the locking device includes a connecting plate fixedly installed on the side wall of the top plate, a sleeve is provided on one side of the connecting plate, and a through hole for accommodating a first stud is provided in the middle of the connecting plate and the sleeve, a first slot is provided on the side of the sleeve close to the connecting plate, a second slot is provided on the sleeve, and the second slot forms an opening on one side of the through hole, a locking knob is threadedly connected to the sleeve, and the locking knob is connected to the opening of the sleeve.
7. A prefabricated cable trench assembly auxiliary straightening device according to any one of claims 1 to 6, characterized in that: A plurality of evenly arranged bull's eye bearings are arranged on the inner wall of the clamping plate.
8. The prefabricated cable trench assembly auxiliary straightening device according to claim 7, characterized in that: A plurality of brackets are arranged on one side of the top plate, and a plurality of rollers are rotatably connected to one end of the brackets. During the straightening operation, the lower surface of the rollers contacts the upper end of the prefabricated cable trench.
9. The prefabricated cable trench assembly auxiliary straightening device according to claim 1, characterized in that: Both ends of the clamping plate are provided with chamfers, so that the front end opening of the straightening clamp is larger than the thickness of the prefabricated cable trench.
10. The prefabricated cable trench assembly auxiliary straightening device according to claim 1, characterized in that: A level is provided on the upper part of the straightening fixture. The level includes two mutually perpendicular level bubbles and is used to calibrate the horizontality of the cable trench.