Method for forming cutting groove through blasting without cutting well and cutting groove construction structure
Through the method of forming cutting grooves without cutting well blasting, the ore body on the cutting tunnel is divided into multiple blasting areas and blasting in succession, which solves the problems of harsh environment, poor safety and high cost in the existing cutting well construction methods, and realizes the It has the effect of short construction time, high efficiency and high safety.
Patent Information
- Application Number
- CN202411373641.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-11-15
AI Technical Summary
Among the existing cutting well construction methods, the common method has a harsh construction environment, poor safety and high cost, the drilling equipment purchase cost is high and the construction preparation time is long. Although the medium-depth hole blasting method is low in cost and high efficiency, the construction accuracy is high and the blasting difficulty is high. Large, not fully promoted.
The method of forming a cutting groove by blasting without cutting wells is adopted. The ore body is divided into multiple blasting areas on the cutting tunnel, and each area is equipped with a gun hole row, and the angle between the plane and horizontal plane of the gun hole row is increased along the extension direction of the cutting tunnel. Large, continuous blasting in sequence to form cutting grooves, reducing construction time and improving efficiency.
The cutting groove construction time is short, efficient and safe, which reduces construction costs and improves safety, and avoids the risk of repeated entry into dangerous tunnels.
Smart Images

Figure CN118958982A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of mining, in particular to a method for forming a cutting groove by blasting without a cutting well and a cutting groove construction structure. Background Art
[0002] Cutting trenches and cutting shafts are very important links in mine development and mining projects, and the project volume accounts for 20%-25% of the total annual mine excavation volume.
[0003] In the related technology, a cutting well must be constructed before the cutting groove is constructed, and the cutting well and the cutting lane provide the initial blasting space. The construction methods of the cutting well include ordinary construction method, drilling method, medium-deep hole blasting method, etc. The ordinary method has a bad working environment, poor safety, high cost and low efficiency. Although the drilling method does not require operators to construct in the well, the working environment is good and safe, but the construction machinery is huge, the construction preparation time is long, and the equipment purchase cost is high.
[0004] In comparison, the cost of the medium-deep hole blasting method is 40% of the common method and 30% of the drilling method; while the efficiency is 141% of the common method and 128% of the drilling method. The medium-deep hole blasting method has many advantages such as low cost, high efficiency, safety and reliability. However, the medium-deep hole blasting method requires high construction precision and great blasting difficulty, and has not been fully promoted and applied. These three cutting well construction methods have their own advantages and disadvantages. Summary of the invention
[0005] The present invention aims to solve one of the technical problems in the related art at least to a certain extent. To this end, the present invention proposes a method for forming a cutting groove without cutting well blasting and a cutting groove construction structure.
[0006] The method for forming a cutting groove by blasting a non-cutting well of the present invention comprises the following steps: forming a drilling tunnel and a cutting tunnel in this section, wherein the extension direction of the cutting tunnel is perpendicular to the extension direction of the drilling tunnel; dividing the upper plate ore body of the cutting tunnel into a plurality of blasting areas along the extension direction of the cutting tunnel, each of the blasting areas being provided with a blast hole row, the blast hole row comprising a plurality of blast holes located in the same plane, wherein the cutting tunnel has a first end and a second end opposite to each other in its extension direction, and the angle between the plane where the blast hole rows of the plurality of blasting areas are located and the horizontal plane increases along the direction from the first end to the second end; and blasting the plurality of blasting areas sequentially and continuously along the direction from the first end to the second end to form a cutting groove.
[0007] The method for forming a cutting groove by blasting without cutting wells of the present invention has the advantages of short cutting groove construction time, high cutting groove forming efficiency and high safety.
[0008] Optionally, each of the blasting areas is provided with a plurality of rows of blast holes, and the plurality of rows of blast holes in each blasting area are arranged along the extension direction of the cutting lane, wherein angles between the planes where the plurality of rows of blast holes in the blasting area closest to the second end are located and the horizontal plane are equal to each other, and angles between the planes where the plurality of rows of blast holes in the remaining blasting areas are located and the horizontal plane increase in the direction from the first end to the second end.
[0009] Optionally, along the direction from the first end to the second end, the upper plate ore body of the cutting tunnel is divided into a first blasting area, a second blasting area and a third blasting area, the angle between the plane where the blast hole row in the first blasting area is located and the horizontal plane is greater than or equal to 25 degrees and less than or equal to 49 degrees, the angle between the plane where the blast hole row in the second blasting area is located and the horizontal plane is greater than or equal to 50 degrees and less than or equal to 85 degrees, and the angle between the plane where the blast hole row in the third blasting area is located and the horizontal plane is equal to 90 degrees.
[0010] Optionally, a protection area is set between two adjacent blasting areas; and / or the ratio of the length of the cutting tunnel to the length of the upper ore body of the cutting tunnel is (1-1.2):1, the ratio of the width of the cutting tunnel to the width of the upper ore body of the cutting tunnel is (1-1.2):1, and the ratio of the height of the cutting tunnel to the height of the upper ore body of the cutting tunnel is 1:(2.6-3).
[0011] Optionally, the projections of the multiple blast holes in the blast hole row along the extension direction of the cutting lane on the first vertical plane are multiple projected blast holes, and the first vertical plane is perpendicular to the extension direction of the cutting lane, wherein the multiple projected blast holes are distributed in a fan shape, and the multiple projected blast holes include a middle projected blast hole, a plurality of first side projected blast holes and a plurality of second side projected blast holes, and the plurality of first side projected blast holes and the plurality of second side projected blast holes are symmetrically arranged relative to the middle projected blast hole, and the angle between the projected blast holes and the horizontal plane is greater than or equal to 65 degrees and less than or equal to 90 degrees.
[0012] Optionally, the detonation delay time between the multiple rows of blast holes in the first blasting area is 0.5 milliseconds-2 milliseconds, and the multiple blast holes in each row of blast holes in the first blasting area are detonated simultaneously; the detonation delay time between the multiple rows of blast holes in the second blasting area is 0.5 milliseconds-2 milliseconds, and the multiple blast holes in each row of blast holes in the second blasting area are detonated simultaneously, and the detonation delay time of the blast hole row closest to the first end in the second blasting area is 460 milliseconds-560 milliseconds; the detonation delay time between the multiple rows of blast holes in the third blasting area is 0.5 milliseconds-2 milliseconds, and the multiple blast holes in each row of blast holes in the third blasting area are detonated simultaneously, and the detonation delay time of the blast hole row closest to the first end in the third blasting area is 460 milliseconds-560 milliseconds.
[0013] The cutting groove construction structure of the present invention includes: a rock drilling tunnel and a cutting tunnel, the extension direction of the cutting tunnel is perpendicular to the extension direction of the rock drilling tunnel, and the cutting tunnel has a first end and a second end opposite to each other in its extension direction; and an upper plate ore body of the cutting tunnel, the upper plate ore body of the cutting tunnel is located above the cutting tunnel, and the upper plate ore body of the cutting tunnel includes a plurality of blasting areas arranged along the extension direction of the cutting tunnel, each of the blasting areas is provided with a row of blast holes, and the row of blast holes includes a plurality of blast holes located in the same plane, wherein the angle between the plane where the rows of blast holes of the plurality of blasting areas are located and the horizontal plane increases along the direction from the first end to the second end.
[0014] The cutting groove construction structure of the present invention has the advantages of short cutting groove construction time, high cutting groove forming efficiency and high safety.
[0015] Optionally, each of the blasting areas is provided with a plurality of rows of blast holes, and the plurality of rows of blast holes in each blasting area are arranged along the extension direction of the cutting lane, wherein angles between the planes where the plurality of rows of blast holes in the blasting area closest to the second end are located and the horizontal plane are equal to each other, and angles between the planes where the plurality of rows of blast holes in the remaining blasting areas are located and the horizontal plane increase in the direction from the first end to the second end.
[0016] Optionally, the upper ore body of the cutting tunnel comprises a first blasting area, a second blasting area and a third blasting area which are arranged in sequence along the direction from the first end to the second end, the angle between the plane where the blast hole row of the first blasting area is located and the horizontal plane is greater than or equal to 25 degrees and less than or equal to 49 degrees, the angle between the plane where the blast hole row of the second blasting area is located and the horizontal plane is greater than or equal to 50 degrees and less than or equal to 85 degrees, and the angle between the plane where the blast hole row of the third blasting area is located and the horizontal plane is equal to 90 degrees; and / or a protection area is provided between two adjacent blasting areas; and / or the ratio of the length of the cutting tunnel to the length of the upper ore body of the cutting tunnel is (1-1.2):1, the ratio of the width of the cutting tunnel to the width of the upper ore body of the cutting tunnel is (1-1.2):1, and the ratio of the height of the cutting tunnel to the height of the upper ore body of the cutting tunnel is 1:(2.6-3).
[0017] Optionally, the projections of the multiple blast holes in the blast hole row along the extension direction of the cutting lane on the first vertical plane are multiple projected blast holes, and the first vertical plane is perpendicular to the extension direction of the cutting lane, wherein the multiple projected blast holes are distributed in a fan shape, and the multiple projected blast holes include a middle projected blast hole, a plurality of first side projected blast holes and a plurality of second side projected blast holes, and the plurality of first side projected blast holes and the plurality of second side projected blast holes are symmetrically arranged relative to the middle projected blast hole, and the angle between the projected blast holes and the horizontal plane is greater than or equal to 65 degrees and less than or equal to 90 degrees. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 is a schematic diagram of a cutting groove construction structure according to an embodiment of the present invention;
[0019] Figure 2 is a projection diagram of a blasthole row of a cutting groove construction structure according to an embodiment of the present invention;
[0020] Figure 3 yes Figure 1 A cross-sectional view along the AA direction;
[0021] Figure 4 The present invention is a flowchart of a method for forming a cutting groove by non-cutting well blasting according to an embodiment of the present invention. DETAILED DESCRIPTION
[0022] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0023] like Figure 4 As shown, the method for forming a cutting groove by blasting without cutting a well according to an embodiment of the present invention comprises the following steps:
[0024] The rock drilling tunnel and the cutting tunnel of this section are formed, and the extension direction of the cutting tunnel is perpendicular to the extension direction of the rock drilling tunnel.
[0025] Along the extension direction of the cutting tunnel, the upper plate ore body of the cutting tunnel (the ore body at the end of the mining area) is divided into multiple blasting areas. In other words, the upper plate ore body of the cutting tunnel is located above the cutting tunnel, and the extension direction (length direction) of the upper plate ore body of the cutting tunnel is consistent with the extension direction (length direction) of the cutting tunnel, and multiple blasting areas are arranged along the extension direction of the cutting tunnel. Each blasting area is provided with a blast hole row, and the blast hole row includes multiple blast holes located in the same plane, that is, the blast hole row is located in one plane. Among them, the cutting tunnel has a first end and a second end opposite to each other in its extension direction, and the angle between the plane where the blast hole rows of the multiple blasting areas are located and the horizontal plane increases along the direction from the first end of the cutting tunnel to the second end of the cutting tunnel.
[0026] Multiple blasting areas are blasted sequentially and continuously along the direction from the first end of the cutting tunnel to the second end of the cutting tunnel to form a cutting groove. "Continuously blasting multiple blasting areas" means that after all the blasting areas are completed, the ore is removed, rather than blasting one blasting area - removing the ore, and then blasting the next blasting area - removing the ore.
[0027] When blasting multiple blasting areas sequentially and continuously, the blasting area (first blasting area) closest to the first end of the cutting lane is blasted first, and the cutting lane provides compensation space for the blasting area. Then the next (second) blasting area is blasted, and the space formed after the blasting of the first blasting area and the cutting lane jointly provide compensation space. Next, the next (third) blasting area is blasted, and the space formed after the blasting of the first and second blasting areas and the cutting lane jointly provide compensation space. And so on, until the blasting of all blasting areas is completed.
[0028] According to the method for forming a cutting groove by blasting without a cutting well according to an embodiment of the present invention, a cutting tunnel is set up, and the ore body on the upper plate of the cutting tunnel is divided into multiple blasting areas along the extension direction of the cutting tunnel, so that the space formed by the cutting tunnel and the blasting area that has been blasted can be utilized to provide compensation space for the blasting of subsequent blasting areas.
[0029] Thus, multiple blasting areas can be blasted continuously to form a cutting groove at one time, so that the ore can be removed after all the blasting in multiple blasting areas is completed. Therefore, there is no need to repeatedly enter the cutting lane to perform operations such as charging-blasting-ore removal, which greatly saves the construction time of the cutting groove and greatly improves the construction efficiency of the cutting groove. In addition, the staff does not need to repeatedly enter the dangerous lane to operate (operating in the cutting lane after blasting is dangerous), which greatly improves the safety of the staff and effectively avoids safety accidents.
[0030] Therefore, the method for forming a cutting groove by blasting without cutting well according to the embodiment of the present invention has the advantages of short cutting groove construction time, high cutting groove forming efficiency, high safety, etc.
[0031] like Figure 1-Figure 3 As shown, the cutting groove construction structure 100 according to the embodiment of the present invention comprises a rock drilling tunnel 1, a cutting tunnel 2 and a cutting tunnel upper wall ore body 3. The extension direction (length direction) of the cutting tunnel 2 is perpendicular to the extension direction (length direction) of the rock drilling tunnel 1, and the cutting tunnel 2 has a first end 21 and a second end 22 opposite to each other in the extension direction thereof.
[0032] The cutting tunnel upper wall ore body 3 may be a hard (or relatively hard) and complete (or relatively complete) ore body. For example, the Proctor coefficient f (firmness coefficient or tightness coefficient) of the cutting tunnel upper wall ore body 3 is greater than or equal to 5, and the integrity coefficient (crack coefficient) of the cutting tunnel upper wall ore body 3 is greater than or equal to 0.55.
[0033] The cutting tunnel upper wall ore body 3 is located above the cutting tunnel 2. The cutting tunnel upper wall ore body 3 includes a plurality of blasting areas 31 arranged along the extension direction of the cutting tunnel 2. Each blasting area 31 is provided with a blast hole row 32. The blast hole row 32 includes a plurality of blast holes 321 located in the same plane, that is, the blast hole row 32 is located in one plane. The angle between the plane where the blast hole rows 32 of the plurality of blasting areas 31 are located and the horizontal plane increases along the direction from the first end 21 of the cutting tunnel 2 to the second end 22 of the cutting tunnel 2.
[0034] Accordingly, the cutting groove construction structure 100 according to the embodiment of the present invention has the advantages of short cutting groove construction time, high cutting groove forming efficiency, and high safety.
[0035] Optionally, the ratio of the length of the cutting tunnel to the length of the upper plate ore body 3 of the cutting tunnel is (1-1.2):1, the ratio of the width of the cutting tunnel to the width of the upper plate ore body 3 of the cutting tunnel is (1-1.2):1, and the ratio of the height of the cutting tunnel to the height of the upper plate ore body 3 of the cutting tunnel is 1:(2.6-3). This can not only provide more sufficient compensation space for the cutting tunnel, but also make the construction volume of the cutting tunnel more reasonable.
[0036] Further optionally, the ratio of the length of the cutting tunnel to the length of the upper wall ore body 3 of the cutting tunnel is (1-1.1):1, the ratio of the width of the cutting tunnel to the width of the upper wall ore body 3 of the cutting tunnel is (1-1.1):1, and the ratio of the height of the cutting tunnel to the height of the upper wall ore body 3 of the cutting tunnel is 1:(2.7-2.9). This can not only provide more sufficient compensation space for the cutting tunnel, but also make the construction volume of the cutting tunnel more reasonable.
[0037] Further optionally, the ratio of the length of the cutting tunnel to the length of the upper wall ore body 3 of the cutting tunnel is 1:1, the ratio of the width of the cutting tunnel to the width of the upper wall ore body 3 of the cutting tunnel is 1:1, and the ratio of the height of the cutting tunnel to the height of the upper wall ore body 3 of the cutting tunnel is 1:2.83. In this way, not only can the cutting tunnel provide more sufficient compensation space, but also the construction volume of the cutting tunnel can be more reasonable.
[0038] like Figure 1 As shown, each blasting area 31 is provided with a plurality of blasthole rows 32, and the plurality of blasthole rows 32 of each blasting area 31 are arranged along the extension direction of the cutting lane 2. The angles between the planes where the plurality of blasthole rows 32 of the blasting area 31 closest to the second end 22 are located and the horizontal plane are equal to each other, and the angles between the planes where the plurality of blasthole rows 32 of the remaining blasting areas 31 are located and the horizontal plane increase along the direction from the first end 21 to the second end 22. In this way, blasting clamping can be reduced, so that the cutting groove can be formed more smoothly.
[0039] In order to make the technical solution of the present application easier to understand, the following takes the extension direction of the cutting lane 2 as an example to further describe the technical solution of the present application. Figure 1 As shown by arrow B in FIG. The first end 21 is the right end of the cutting lane 2, and the second end 22 is the left end of the cutting lane 2. The multiple blasthole rows 32 of each blasting area 31 are arranged in the left-right direction. The angles between the plane where the multiple blasthole rows 32 of the blasting area 31 closest to the left end of the cutting lane 2 are located and the horizontal plane are equal to each other, that is, the angles between the plane where the multiple blasthole rows 32 of the blasting area 31 at the leftmost end are located and the horizontal plane are equal to each other. The angles between the plane where the multiple blasthole rows 32 of the remaining blasting areas 31 are located and the horizontal plane increase from right to left.
[0040] Here, "the multiple blasthole rows 32 of each blasting area 31 are arranged in the left-right direction" does not mean that one of the two adjacent blasthole rows 32 is located on the left (right) side of the other. "The multiple blasthole rows 32 of each blasting area 31 are arranged in the left-right direction" means that for the horizontally opposite parts of the two adjacent blasthole rows 32, one is located on the left (right) side of the other.
[0041] Optionally, a protection area 33 is provided between two adjacent blasting areas 31. This can prevent the blast holes 321 of two adjacent blasting areas 31 from crossing or perforating due to construction errors, thereby reducing the construction difficulty of the blast holes 321 and improving the construction efficiency and quality of the blast holes 321.
[0042] like Figure 1As shown, the upper wall ore body 3 of the cutting tunnel includes the first blasting area 31a, the second blasting area 31b and the third blasting area 31c, and the first blasting area 31a, the second blasting area 31b and the third blasting area 31c are arranged in sequence along the direction from the first end 21 of the cutting tunnel 2 to the second end 22 of the cutting tunnel 2. That is to say, along the direction from the first end 21 of the cutting tunnel 2 to the second end 22 of the cutting tunnel 2, the upper wall ore body 3 of the cutting tunnel is divided into the first blasting area 31a, the second blasting area 31b and the third blasting area 31c.
[0043] The angle between the plane where the blasthole row 32 of the first blasting area 31a is located and the horizontal plane is greater than or equal to 25 degrees and less than or equal to 49 degrees, the angle between the plane where the blasthole row 32 of the second blasting area 31b is located and the horizontal plane is greater than or equal to 50 degrees and less than or equal to 85 degrees, and the angle between the plane where the blasthole row 32 of the third blasting area 31c is located and the horizontal plane is equal to 90 degrees. In this way, the cutting groove construction structure 100 can be made more reasonable, thereby further shortening the cutting groove construction time and further improving the cutting groove formation efficiency.
[0044] For example, the first blasting area 31a is provided with 4-6 blasthole rows 32, and each blasthole row 32 of the first blasting area 31a includes 5-9 blastholes 321. The second blasting area 31b is provided with 8-12 blasthole rows 32, and each blasthole row 32 of the second blasting area 31b includes 5-9 blastholes 321. The third blasting area 31c is provided with 3-5 blasthole rows 32, and each blasthole row 32 of the third blasting area 31c includes 5-9 blastholes 321.
[0045] Optionally, the inter-row detonation delay time of the multiple blasthole rows 32 of the first blasting area 31a is 0.5 milliseconds to 2 milliseconds, and the multiple blastholes 321 of each blasthole row 32 of the first blasting area 31a are detonated simultaneously. Specifically, the multiple blastholes 321 of the first blasthole row 32 of the first blasting area 31a (the blasthole row 32 closest to the first end 21 of the cutting lane 2) are detonated simultaneously, and after 0.5 milliseconds to 2 milliseconds, the multiple blastholes 321 of the second blasthole row 32 of the first blasting area 31a are detonated simultaneously, and after another 0.5 milliseconds to 2 milliseconds, the multiple blastholes 321 of the third blasthole row 32 of the first blasting area 31a are detonated simultaneously. And so on, until all the multiple blasthole rows 32 of the first blasting area 31a are detonated, so that the blasting of the first blasting area 31a is completed. The cutting lane 2 provides a compensation space for the blasting of the first blasting area 31a.
[0046] The detonation delay time of the blasthole row 32 of the second blasting area 31b closest to the first end 21 of the cutting lane 2 is 460 milliseconds to 560 milliseconds. In other words, after the last blasthole row 32 of the first blasting area 31a (the blasthole row 32 farthest from the first end 21 of the cutting lane 2) is detonated, after an interval of 460 milliseconds to 560 milliseconds, multiple blastholes 321 of the blasthole row 32 (the first blasthole row 32) of the second blasting area 31b closest to the first end 21 of the cutting lane 2 are detonated simultaneously.
[0047] The inter-row detonation delay time of the multiple blasthole rows 32 of the second blasting area 31b is 0.5 milliseconds to 2 milliseconds, and the multiple blastholes 321 of each blasthole row 32 of the second blasting area 31b are detonated simultaneously. Specifically, after the first blasthole row 32 of the second blasting area 31b is detonated, after an interval of 0.5 milliseconds to 2 milliseconds, the multiple blastholes 321 of the second blasthole row 32 of the second blasting area 31b are detonated simultaneously, and after another 0.5 milliseconds to 2 milliseconds, the multiple blastholes 321 of the third blasthole row 32 of the second blasting area 31b are detonated simultaneously. And so on, until all the multiple blasthole rows 32 of the second blasting area 31b are detonated, so that the blasting of the second blasting area 31b is completed. The space formed after the blasting of the first blasting area 31a and the cutting lane 2 provide compensation space for the blasting of the second blasting area 31b.
[0048] The detonation delay time of the blasthole row 32 of the third blasting area 31c closest to the first end 21 of the cutting lane 2 is 460 milliseconds to 560 milliseconds. In other words, after the last blasthole row 32 of the second blasting area 31b (the blasthole row 32 farthest from the first end 21 of the cutting lane 2) is detonated, a plurality of blastholes 321 of the blasthole row 32 (the first blasthole row 32) of the third blasting area 31c closest to the first end 21 of the cutting lane 2 are detonated simultaneously after an interval of 460 milliseconds to 560 milliseconds.
[0049] The inter-row detonation delay time of the multiple blasthole rows 32 of the third blasting area 31c is 0.5 milliseconds to 2 milliseconds, and the multiple blastholes 321 of each blasthole row 32 of the third blasting area 31c are detonated simultaneously. Specifically, after the first blasthole row 32 of the third blasting area 31c is detonated, after an interval of 0.5 milliseconds to 2 milliseconds, the multiple blastholes 321 of the second blasthole row 32 of the third blasting area 31c are detonated simultaneously, and after another 0.5 milliseconds to 2 milliseconds, the multiple blastholes 321 of the third blasthole row 32 of the third blasting area 31c are detonated simultaneously. And so on, until all the multiple blasthole rows 32 of the third blasting area 31c are detonated, so that the blasting of the third blasting area 31c is completed, and then the cutting groove is formed. The space formed after the blasting of the first blasting area 31a and the second blasting area 31b and the cutting lane 2 provide compensation space for the blasting of the third blasting area 31c.
[0050] Further optionally, the inter-row detonation delay time of the multiple blasthole rows 32 of the first blasting area 31a is 0.8 milliseconds to 1.4 milliseconds, the inter-row detonation delay time of the multiple blasthole rows 32 of the second blasting area 31b is 0.8 milliseconds to 1.4 milliseconds, and the inter-row detonation delay time of the multiple blasthole rows 32 of the third blasting area 31c is 0.8 milliseconds to 1.4 milliseconds. Further optionally, the inter-row detonation delay time of the multiple blasthole rows 32 of the first blasting area 31a is 0.95 milliseconds to 1.15 milliseconds, the inter-row detonation delay time of the multiple blasthole rows 32 of the second blasting area 31b is 0.95 milliseconds to 1.15 milliseconds, and the inter-row detonation delay time of the multiple blasthole rows 32 of the third blasting area 31c is 0.95 milliseconds to 1.15 milliseconds.
[0051] Further optionally, the detonation delay time of the blasthole row 32 of the first end 21 of the cutting lane 2 closest to the second blasting area 31b is 480 milliseconds to 530 milliseconds, and the detonation delay time of the blasthole row 32 of the first end 21 of the cutting lane 2 closest to the third blasting area 31c is 480 milliseconds to 530 milliseconds. The detonation delay time of the blasthole row 32 of the first end 21 of the cutting lane 2 closest to the second blasting area 31b is 490 milliseconds to 510 milliseconds, and the detonation delay time of the blasthole row 32 of the first end 21 of the cutting lane 2 closest to the third blasting area 31c is 490 milliseconds to 510 milliseconds.
[0052] like Figure 2 As shown, the projections of the multiple blast holes 321 of the blast hole row 32 along the extension direction of the cutting lane 2 on the first vertical plane are multiple projection blast holes 322, and the first vertical plane is perpendicular to the extension direction of the cutting lane 2. The multiple projection blast holes 322 are distributed in a fan shape, and the multiple projection blast holes 322 include a middle projection blast hole 322a, a plurality of first side projection blast holes 322b, and a plurality of second side projection blast holes 322c. The plurality of first side projection blast holes 322b and the plurality of second side projection blast holes 322c are symmetrically arranged relative to the middle projection blast hole 322a. The angle between the projection blast hole 322 and the horizontal plane is greater than or equal to 65 degrees and less than or equal to 90 degrees. In this way, the cutting groove construction structure 100 can be made more reasonable, thereby further shortening the cutting groove construction time and further improving the cutting groove formation efficiency.
[0053] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0054] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0055] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0056] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0057] In the present invention, the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" etc. mean that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the described specific features, structures, materials or characteristics may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0058] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A method for forming a cutting groove by blasting without cutting a well, characterized in that: The following steps are involved: A drilling tunnel and a cutting tunnel are formed in this section, wherein the extending direction of the cutting tunnel is perpendicular to the extending direction of the drilling tunnel; The ore body on the upper wall of the cutting tunnel is divided into a plurality of blasting areas along the extension direction of the cutting tunnel, each of the blasting areas is provided with a blast hole row, the blast hole row includes a plurality of blast holes located in the same plane, wherein the cutting tunnel has a first end and a second end opposite to each other in the extension direction thereof, and the angle between the plane where the blast hole rows of the plurality of blasting areas are located and the horizontal plane increases along the direction from the first end to the second end; and The plurality of blasting areas are blasted sequentially and continuously along a direction from the first end to the second end to form a cutting groove.
2. The method for forming a cutting groove by blasting without cutting a well according to claim 1, characterized in that: Each of the blasting areas is provided with a plurality of rows of blast holes, and the plurality of rows of blast holes in each blasting area are arranged along the extension direction of the cutting lane, wherein angles between the planes where the plurality of rows of blast holes in the blasting area closest to the second end are located and the horizontal plane are equal to each other, and angles between the planes where the plurality of rows of blast holes in the remaining blasting areas are located and the horizontal plane increase along the direction from the first end to the second end.
3. The method for forming a cutting groove by blasting without cutting a well according to claim 1 or 2, characterized in that: Along the direction from the first end to the second end, the upper plate ore body of the cutting tunnel is divided into a first blasting area, a second blasting area and a third blasting area, the angle between the plane where the blast hole row in the first blasting area is located and the horizontal plane is greater than or equal to 25 degrees and less than or equal to 49 degrees, the angle between the plane where the blast hole row in the second blasting area is located and the horizontal plane is greater than or equal to 50 degrees and less than or equal to 85 degrees, and the angle between the plane where the blast hole row in the third blasting area is located and the horizontal plane is equal to 90 degrees.
4. The method for forming a cutting groove by blasting without cutting a well according to claim 1 or 2, characterized in that: Setting a protection area between two adjacent blasting areas; and / or The ratio of the length of the cutting tunnel to the length of the upper ore body of the cutting tunnel is (1-1.2):1, the ratio of the width of the cutting tunnel to the width of the upper ore body of the cutting tunnel is (1-1.2):1, and the ratio of the height of the cutting tunnel to the height of the upper ore body of the cutting tunnel is 1:(2.6-3).
5. The method for forming a cutting groove by blasting without cutting a well according to claim 1 or 2, characterized in that: The projections of the multiple blast holes of the blast hole row along the extension direction of the cutting lane on the first vertical plane are multiple projected blast holes, and the first vertical plane is perpendicular to the extension direction of the cutting lane, wherein the multiple projected blast holes are distributed in a fan shape, and the multiple projected blast holes include a middle projected blast hole, a plurality of first side projected blast holes and a plurality of second side projected blast holes, and the plurality of first side projected blast holes and the plurality of second side projected blast holes are symmetrically arranged relative to the middle projected blast hole, and the angle between the projected blast holes and the horizontal plane is greater than or equal to 65 degrees and less than or equal to 90 degrees.
6. The method for forming a cutting groove by blasting without cutting a well according to claim 3, characterized in that: The inter-row detonation delay time of the plurality of blasthole rows in the first blasting area is 0.5 milliseconds to 2 milliseconds, and the plurality of blastholes in each blasthole row in the first blasting area are detonated simultaneously; The detonation delay time between the rows of multiple blastholes in the second blasting area is 0.5 milliseconds to 2 milliseconds, the multiple blastholes in each row of blastholes in the second blasting area are detonated simultaneously, and the detonation delay time of the row of blastholes in the second blasting area closest to the first end is 460 milliseconds to 560 milliseconds; The detonation delay time between the multiple rows of blast holes in the third blasting area is 0.5 milliseconds to 2 milliseconds, the multiple blast holes in each row of blast holes in the third blasting area are detonated simultaneously, and the detonation delay time of the row of blast holes in the third blasting area closest to the first end is 460 milliseconds to 560 milliseconds.
7. A cutting groove construction structure, characterized in that: include: a rock drilling tunnel and a cutting tunnel, wherein the extending direction of the cutting tunnel is perpendicular to the extending direction of the rock drilling tunnel, and the cutting tunnel has a first end and a second end opposite to each other in the extending direction thereof; as well as The upper plate ore body of the cutting tunnel is located above the cutting tunnel, and the upper plate ore body of the cutting tunnel includes a plurality of blasting areas arranged along the extension direction of the cutting tunnel, each of the blasting areas is provided with a blast hole row, and the blast hole row includes a plurality of blast holes located in the same plane, wherein an angle between a plane where the blast hole rows of the plurality of blasting areas are located and a horizontal plane increases along the direction from the first end to the second end.
8. The cutting groove construction structure according to claim 7, characterized in that: Each of the blasting areas is provided with a plurality of rows of blast holes, and the plurality of rows of blast holes in each blasting area are arranged along the extension direction of the cutting lane, wherein angles between the planes where the plurality of rows of blast holes in the blasting area closest to the second end are located and the horizontal plane are equal to each other, and angles between the planes where the plurality of rows of blast holes in the remaining blasting areas are located and the horizontal plane increase along the direction from the first end to the second end.
9. The cutting groove construction structure according to claim 7 or 8, characterized in that: The upper plate ore body of the cutting tunnel comprises a first blasting area, a second blasting area and a third blasting area which are sequentially arranged along the direction from the first end to the second end, the angle between the plane where the blasthole row of the first blasting area is located and the horizontal plane is greater than or equal to 25 degrees and less than or equal to 49 degrees, the angle between the plane where the blasthole row of the second blasting area is located and the horizontal plane is greater than or equal to 50 degrees and less than or equal to 85 degrees, and the angle between the plane where the blasthole row of the third blasting area is located and the horizontal plane is equal to 90 degrees; and / or A protection area is provided between two adjacent blasting areas; and / or The ratio of the length of the cutting tunnel to the length of the upper ore body of the cutting tunnel is (1-1.2):1, the ratio of the width of the cutting tunnel to the width of the upper ore body of the cutting tunnel is (1-1.2):1, and the ratio of the height of the cutting tunnel to the height of the upper ore body of the cutting tunnel is 1:(2.6-3).
10. The cutting groove construction structure according to claim 7 or 8, characterized in that: The projections of the multiple blast holes of the blast hole row along the extension direction of the cutting lane on the first vertical plane are multiple projected blast holes, and the first vertical plane is perpendicular to the extension direction of the cutting lane, wherein the multiple projected blast holes are distributed in a fan shape, and the multiple projected blast holes include a middle projected blast hole, a plurality of first side projected blast holes and a plurality of second side projected blast holes, and the plurality of first side projected blast holes and the plurality of second side projected blast holes are symmetrically arranged relative to the middle projected blast hole, and the angle between the projected blast holes and the horizontal plane is greater than or equal to 65 degrees and less than or equal to 90 degrees.
Citation Information
Cited By
Drilling and blasting method for forming cutting groove at one time
CN119714004A
Cutting-well-free medium-length hole groove broaching method for inclined thick and large ore body
CN119737153A
A method for slotting in a deep hole in a non-cutting well of an inclined thick ore body
CN119737153B