Method for detecting and maintaining bridge pile foundation

By placing standard specimens and curing specimens subcages around the bridge pile foundation, the maintenance conditions under the same conditions are simulated, and their anti-shrink performance in seawater is detected, which solves the problem of difficulty in evaluating pile foundation maintenance quality in the prior art. , realizes accurate evaluation of the status of pile foundation materials and guarantees construction quality.

CN118961474APending Publication Date: 2024-11-15SHANGHAI ROAD & BRIDGE (GRP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411037869.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing technology lacks effective methods to detect the maintenance construction quality of bridge pile foundations, and cannot truly understand the maintenance status of pile foundations under the same conditions, making it difficult to decide whether further maintenance measures are needed.

Method used

Use multiple subcages to place standard specimens and maintenance specimens at the same time to simulate the maintenance construction of pile foundations, take out the specimens from water according to the set time interval for testing, and judge the maintenance of pile foundations by comparing the status of standard specimens and maintenance specimens. The material's anti-shock performance in seawater environment determines whether it meets the construction requirements.

Benefits of technology

Through this method, we can promptly and conveniently understand the true status of the pile foundation maintenance materials in the actual seawater environment, and judge whether further maintenance or other measures are needed to ensure the quality of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118961474A_ABST
    Figure CN118961474A_ABST
Patent Text Reader

Abstract

The invention discloses a method for detecting and maintaining a bridge pile foundation, which is used for detecting the quality of maintenance construction of the pile foundation and comprises the following steps: manufacturing a main bin cage; test pieces are manufactured in the sub-cages, a standard test piece is manufactured in at least one sub-cage according to a set standard mold, and a maintenance test piece which simulates maintenance construction of the pile foundation and is made of the same maintenance material is manufactured in at least one sub-cage; a plurality of sub-cages are placed in a main bin cage, and the main bin cage is placed on the periphery of a pile foundation, under the water surface, of the bridge; according to a set time interval, different sub-cages are taken out underwater; and the standard test piece and / or the maintenance test piece in the sub-cage are / is taken out and detected according to set detection requirements, and the maintenance construction quality of the pile foundation is obtained. According to the method for detecting and maintaining the bridge pile foundation, the real maintenance condition of the pile foundation under the same maintenance condition is simulated, and the real maintenance state of the maintenance material of the pile foundation in the actual seawater environment can be known timely and conveniently to judge whether the construction requirement is met or not.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a method for detecting and maintaining bridge pile foundations. Background Art

[0002] In recent years, the pile foundation scouring problem of bridges in waters has become increasingly serious, and the construction of underwater pile foundation anti-scouring protection is also imminent. The conventional reinforcement method is to use riprap filling. However, this method is not only costly, but also causes secondary damage to the bridge pile foundation. The uneven surface of the gravel will also cause secondary scouring, and the protection effect is not good. For this reason, the construction workers used a high-flow solidified soil with a curing agent to fill the underwater pile foundation scouring pit (filling the scouring pit of the pile foundation is the maintenance pile foundation), which can fit well with the bottom mud surface to form a whole and achieve the best protection effect.

[0003] However, when the highly fluid solidified soil is pumped to the bridge scour pit, the solidification development process of the fluidized soil in the pit cannot be displayed intuitively. The existing technology lacks effective technical means to obtain the actual maintenance conditions of the pile foundation under the same maintenance conditions during the maintenance construction, so as to understand the construction quality and decide whether further maintenance or other measures are needed. Summary of the invention

[0004] The technical problem to be solved by the present invention is to overcome the defect in the prior art that there is a lack of effective method for obtaining the maintenance construction quality of bridge pile foundations, and to provide a method for detecting and maintaining bridge pile foundations.

[0005] The present invention solves the above technical problems through the following technical solutions:

[0006] A method for detecting and maintaining a bridge pile foundation is used to detect the quality of maintenance construction on the pile foundation. The method for detecting and maintaining a bridge pile foundation comprises the following steps:

[0007] A main cage for accommodating the test piece is manufactured, wherein the main cage includes a plurality of sub-cages.

[0008] Making test pieces in the sub-cages, wherein the test pieces include standard test pieces and curing test pieces, making the standard test piece according to a set standard mold in at least one of the sub-cages, and making the curing test piece simulating the curing construction of the pile foundation and having the same curing material in at least one of the sub-cages;

[0009] Placing a plurality of sub-cages in the main cage, and placing the main cage around the pile foundation of the bridge under the water surface, and performing maintenance under the same conditions as the pile foundation under maintenance construction;

[0010] According to the set time intervals, taking out different sub-cages from underwater;

[0011] The standard test piece and / or the maintenance test piece in the sub-cage is taken out, and tested according to the set test requirements to obtain the maintenance construction quality of the pile foundation.

[0012] In this scheme, the method for inspecting and maintaining bridge pile foundations is to place multiple standard specimens and maintenance specimens in several sub-cages at the same time, and simulate the maintenance construction of the pile foundation according to the working conditions of the maintenance construction, and make maintenance specimens with the same material, so as to simulate the actual maintenance situation of the pile foundation under the same maintenance conditions ("maintenance under the same conditions" means that the maintenance specimens and the pile foundations actually undergoing maintenance construction are under the same construction conditions, and while pouring the pile foundations, the maintenance specimens are placed around the underwater pile foundations to ensure that they have the same application conditions as the pile foundations). Then, the maintenance specimens are taken out of the water at different set time intervals. By inspecting the maintenance specimens and standard specimens, the actual maintenance status of the maintenance materials of the pile foundation in the actual seawater environment can be timely and conveniently known (that is, the anti-scouring performance of the materials filling the pile foundation scouring pits under real seawater currents can be examined), so as to judge whether the construction requirements are met and decide whether further maintenance or other measures are needed. Among them, the standard specimen can be used for testing according to the set standard requirements (such as national standards), and the standard specimen can also be compared with the maintenance specimen to determine the actual maintenance condition of the pile foundation.

[0013] Preferably, the step of "making the maintenance specimen having the same maintenance material to simulate the maintenance construction of the pile foundation in at least one of the sub-cages" specifically also includes: while the pile foundation is undergoing maintenance construction, laying underwater original soil around the pile foundation at the bottom of the sub-cage, and pouring solidified soil slurry having the same material as the pile foundation under maintenance construction on top of the underwater original soil.

[0014] In this scheme, by pouring underwater original soil and solidified soil slurry at the bottom and top of the sub-cage respectively, the curing specimen accurately simulates the pile foundation under maintenance construction, has the same material and application environment, and can compare the quality of pile foundations under the same curing conditions.

[0015] Preferably, the step of "making the curing specimens simulating the curing construction of the pile foundation and having the same curing material in at least one of the sub-cages" specifically also includes: numbering the plurality of curing specimens according to different set times at preset time intervals.

[0016] In this scheme, multiple curing specimens are numbered according to different set times to facilitate identification and record changes in curing conditions over time.

[0017] Preferably, the step of "placing a plurality of the sub-cages in the main cage" further comprises: inserting a horizontally arranged partition cross bar and / or a vertically arranged partition vertical bar between two adjacent sub-cages.

[0018] In this solution, the sub-cages are separated by inserting the above-mentioned partition horizontal bars and / or partition vertical bars in different directions to ensure that the curing specimens or the standard specimens and the curing specimens do not interfere with each other when used underwater, thereby ensuring the integrity of the specimens and improving the accuracy of the detection.

[0019] Preferably, the main cage and / or the sub-cage include fixings for fixing the standard specimen and / or the maintenance specimen, and the method for inspecting and maintaining bridge pile foundations also includes: connecting one end of the fixing to the frame of the main cage and / or the sub-cage, and connecting the other end of the fixing to the standard specimen and / or the maintenance specimen.

[0020] In this solution, through the above steps, the standard specimens and the maintenance specimens are fixed to the frames of the sub-cage and / or the main cage using fixings, and will not become detached or deviate around the pile foundation when used underwater.

[0021] Preferably, the main cage and / or the sub-cage include fixings for fixing the standard specimen and / or the maintenance specimen, and the method for inspecting and maintaining a bridge pile foundation also includes: connecting the fixings to different positions of the frame of the main cage and / or the sub-cage, and covering the surfaces of the standard specimen and the maintenance specimen.

[0022] In this solution, through the above steps, the fixing parts are connected to different positions of the frame of the main cage and / or sub-cage, and covered on the surface of the standard specimens and the curing specimens, so that the standard specimens and the curing specimens are stably covered in the cavity of the sub-cage, which is conducive to improving the reliability of fixation.

[0023] Preferably, a lifting lug is provided on the outer frame of the main cage, and the method for detecting and maintaining a bridge pile foundation further comprises:

[0024] Use one end of the lifting tool to connect with the lifting lug of the main cage, slowly put the main cage into the water from the other end of the lifting tool, and place it around the pile foundation of the bridge under the water surface;

[0025] According to the set time interval, the main cage is taken out from underwater using a lifting tool.

[0026] In this solution, a lifting tool is used and the above method is adopted to facilitate the control of the water entry speed of the main cage and accurately place the main cage around the pile foundation where the maintenance construction is being carried out.

[0027] Preferably, a lifting lug is provided on the frame of the sub-cage, and the method for inspecting and maintaining bridge pile foundations also includes: before or after taking the main cage out from underwater, using one end of a lifting tool to connect with the lifting lug of the sub-cage, and taking the sub-cage out of the main cage from the other end of the lifting tool.

[0028] In this scheme, through the above method, the sub-cage can be taken out from the main cage separately before the main cage is taken out from underwater, which improves the removal efficiency and does not affect the continued maintenance and inspection of the specimens in other sub-cages; the sub-cage can also be taken out from the main cage after the main cage is taken out from underwater.

[0029] Preferably, before the step of "placing the main cage around the pile foundation of the bridge under the water surface", the step also includes: placing at least one counterweight block at the bottom of the main cage.

[0030] In this solution, a counterweight is placed at the bottom of the main cage to increase the weight of the main cage. After the main cage is placed at the target position, it is not easily washed away by water or deviated from the target position, so as to ensure accurate simulation of the maintenance conditions of the pile foundation.

[0031] Preferably, the method for inspecting and maintaining bridge pile foundations further includes: after inspecting the standard specimen and / or the maintenance specimen, replacing the standard specimen and / or the maintenance specimen in the sub-cage, and then placing the sub-cage back into the main cage and placing it around the pile foundation of the bridge under the water surface.

[0032] In this solution, through the above steps, the standard test pieces and / or the curing test pieces can be replaced according to the test results, and the curing time can be extended to further examine the curing condition of the pile foundation.

[0033] The positive progressive effect of the present invention is that the method for detecting and maintaining bridge pile foundations simultaneously places a plurality of standard test pieces and maintenance test pieces in a plurality of sub-cages, and simulates the maintenance construction of the pile foundation according to the working conditions of the maintenance construction, and manufactures maintenance test pieces with the same material, thereby simulating the actual maintenance situation of the pile foundation under the same maintenance conditions, and then taking the maintenance test pieces out of the water at different set time intervals. By detecting the maintenance test pieces and the standard test pieces, the actual maintenance status of the maintenance materials of the pile foundation in the actual seawater environment can be timely and conveniently known, so as to judge whether the construction requirements are met and decide whether further maintenance or other measures are needed. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 The present invention is a flowchart of a method for detecting and maintaining bridge pile foundations according to an embodiment of the present invention.

[0035] Figure 2 This is a schematic top view of the structure of the main cage and the sub-cage according to an embodiment of the present invention.

[0036] Figure 3 This is a schematic side view of the structure of the main cage and the sub-cage of an embodiment of the present invention (wherein the sub-cage is placed in the main cage).

[0037] Figure 4 This is a schematic side view of the structure of the main cage and the sub-cage of an embodiment of the present invention (wherein the sub-cage is being hoisted into the main cage).

[0038] Description of reference numerals:

[0039] Main cage 1

[0040] Cage 2

[0041] First cage 21

[0042] Second subcage 22

[0043] The third cage 23

[0044] Fourth cage 24

[0045] Standard specimen 3

[0046] Curing specimen 4

[0047] Underwater original soil 41

[0048] Solidified soil slurry 42

[0049] Lug 8 DETAILED DESCRIPTION

[0050] The present invention is further described below by way of examples, but the present invention is not limited to the scope of the examples.

[0051] This embodiment provides a method for detecting and maintaining bridge pile foundations, which is used to detect the quality of maintenance construction on pile foundations. Such pile foundations are pile foundations for building bridges or working platforms on rivers and seas.

[0052] like Figure 1 As shown, the method for detecting and maintaining bridge pile foundations comprises the following steps:

[0053] S1, manufacturing a main cage 1 for accommodating test pieces, wherein the main cage 1 includes a plurality of sub-cages 2;

[0054] S2, making test pieces in the sub-cage 2, wherein the test pieces include standard test pieces 3 and curing test pieces 4, making the standard test piece 3 according to a set standard mold in at least one sub-cage 2, and making a curing test piece 4 simulating the curing construction of the pile foundation and having the same curing material in at least one sub-cage 2;

[0055] S3, placing several sub-cages 2 in the main cage 1;

[0056] S4, placing the main cage 1 around the pile foundation of the bridge under the water surface, and performing maintenance under the same conditions as the pile foundation under maintenance construction;

[0057] S5, taking out different sub-cages 2 from underwater according to the set time interval;

[0058] S6. Take out the standard test piece 3 and / or the curing test piece 4 in the sub-cage, and perform inspection according to the set inspection requirements to obtain the quality of the maintenance construction of the pile foundation.

[0059] The method for inspecting and maintaining bridge pile foundations simultaneously places a plurality of standard test pieces 3 and maintenance test pieces 4 in a plurality of sub-cages 2, and simulates the maintenance construction of the pile foundation according to the working conditions of the maintenance construction, and manufactures maintenance test pieces 4 having the same material, thereby simulating the actual maintenance situation of the pile foundation under the same maintenance conditions ("maintenance under the same conditions" means that the maintenance test pieces and the pile foundation actually undergoing maintenance construction are under the same construction conditions, and the maintenance test pieces are placed around the underwater pile foundation while the pile foundation is being poured to ensure that the same application conditions as the pile foundation are met). The maintenance test pieces are then taken out of the water at different set time intervals. By inspecting the maintenance test pieces and the standard test pieces, the actual maintenance status of the maintenance materials of the pile foundation under the actual seawater environment can be timely and conveniently known (that is, the anti-scouring performance of the materials filled in the pile foundation scouring pit under the actual seawater current can be examined), so as to determine whether the construction requirements are met and decide whether further maintenance or other measures are needed. The standard specimen 3 may be used for testing according to set standard requirements (such as national standards), and the standard specimen 3 may also be compared with the maintenance specimen 4 to determine the actual maintenance condition of the pile foundation.

[0060] like Figure 2-4 As shown, the structure of a device for detecting and maintaining bridge pile foundations is shown, which is used to implement the method steps of this embodiment. The device includes a main cage 1, which includes four sub-cages to form a four-grid maintenance cage. The entire cage is made of ordinary steel and has low cost. The four sub-cages 2 are respectively the first sub-cage 21 (also called the standard test block maintenance warehouse) for accommodating the standard specimen 3, the second sub-cage 22, the third sub-cage 23, and the fourth sub-cage 24 (these three sub-cages are also called the seabed simulation maintenance warehouse) for accommodating the maintenance specimen 4. The standard specimen 3 is a standard specimen made according to the standard mold set by the national standard. The second sub-cage 22, the third sub-cage 23, and the fourth sub-cage 24 are respectively placed with a maintenance specimen 4, and are respectively maintained under the same conditions as the pile foundation under maintenance construction in the river and sea water flow at set time intervals of 7 days, 28 days, and 60 days to observe the anti-scouring performance of the material for the maintenance pile foundation under real seawater and ocean currents. In this embodiment, the material for the maintenance pile foundation is high-fluidity solidified soil.

[0061] Among them, the above-mentioned step S2 of "making a curing specimen with the same curing material and simulating the curing construction of the pile foundation in at least one sub-cage" specifically also includes: while the pile foundation is undergoing curing construction, laying underwater original soil 41 around the pile foundation at the bottom of the sub-cage 2, and pouring solidified soil slurry 42 with the same material as the pile foundation under curing construction on top of the underwater original soil 41.

[0062] The structure of the curing specimen used in the above method is as follows: Figure 4 As shown, the protective specimen 4 includes underwater original soil 41 under the same working conditions as the pile foundation under construction and solidified soil slurry 42 poured on the underwater original soil 41 and having the same material as the pile foundation under maintenance and filling construction.

[0063] By pouring underwater original soil and solidified soil slurry at the bottom and top of the sub-cage respectively, the curing specimens accurately simulate the pile foundation under maintenance construction, have the same material and application environment, and can compare the quality of pile foundations under the same curing conditions.

[0064] Among them, in the above step S2, "making a curing specimen simulating the curing construction of the pile foundation and having the same curing material in at least one sub-cage" specifically also includes: numbering multiple curing specimens according to different set times at preset time intervals.

[0065] Multiple curing specimens are numbered according to different set times to facilitate identification and record changes in curing conditions over time.

[0066] The above step S3 of "placing a plurality of sub-cages in the main cage" further includes:

[0067] A compartment horizontal bar arranged in the horizontal direction and / or a compartment vertical bar arranged in the vertical direction are inserted between two adjacent sub-cages.

[0068] By inserting compartment horizontal bars and / or compartment vertical bars in different directions, the sub-cages are separated to ensure that the curing specimens or the standard specimens and the curing specimens do not interfere with each other during underwater applications, thereby ensuring the integrity of the specimens and improving the accuracy of the test.

[0069] The main cage and / or the sub-cage include a fixing part for fixing the standard specimen and / or the maintenance specimen, and the fixing part is specifically a wire mesh. The method for detecting and maintaining a bridge pile foundation also includes: connecting the wire mesh to different positions of the frame of the main cage and / or the sub-cage, and covering the surface of the standard specimen and the maintenance specimen.

[0070] Through the above steps, the wire mesh stably covers the standard specimen and the curing specimen in the cavity of the sub-cage, which is beneficial to improving the reliability of fixation.

[0071] In other embodiments, the fixing member has various forms, such as chains or ropes, and the above-mentioned method of applying the fixing member is: one end of the fixing member is connected to the frame of the main cage and / or the sub-cage, and the other end of the fixing member is connected to the standard specimen and / or the curing specimen. When the chain or rope is used as the fixing member, the fixing member is used to fix the standard specimen and the curing specimen on the frame of the sub-cage and / or the main cage, and will not be disengaged or deviated around the pile foundation when used underwater.

[0072] like Figure 4 As shown, a lifting lug is provided on the outer frame of the main cage, and the method for inspecting and maintaining the bridge pile foundation also includes: using one end of a lifting tool to connect with the lifting lug of the main cage, slowly lowering the main cage into water from the other end of the lifting tool, and placing it around the pile foundation of the bridge under the water surface; according to the set time interval, using the lifting tool to take the main cage out from underwater.

[0073] By using the hoisting tools and the above method, it is easy to control the water entry speed of the main cage and accurately place the main cage around the pile foundation where the maintenance construction is being carried out.

[0074] Among them, the frame of the sub-cage is also provided with a lifting lug, and the method for inspecting and maintaining bridge pile foundations also includes: before or after taking the main cage out from underwater, using one end of the lifting tool to connect with the lifting lug of the sub-cage, and taking the sub-cage out of the main cage from the other end of the lifting tool.

[0075] Through the above method, the sub-cage can be taken out from the main cage before the main cage is taken out from underwater, which improves the removal efficiency and does not affect the continued maintenance and inspection of the specimens in other sub-cages; the sub-cage can also be taken out from the main cage after the main cage is taken out from underwater.

[0076] Wherein, before "placing the main cage around the pile foundation of the bridge under the water surface" in the above step S4, it also includes: placing at least one counterweight block at the bottom of the main cage.

[0077] By placing counterweights at the bottom of the main cage, the weight of the main cage is increased. After the main cage is placed at the target position, it is not easily washed away by water or deviated from the target position, so as to ensure accurate simulation of the maintenance conditions of the pile foundation.

[0078] Among them, the method for inspecting and maintaining bridge pile foundations also includes: after inspecting the standard test pieces and / or the maintenance test pieces, replacing the standard test pieces and / or the maintenance test pieces in the sub-cage, and then putting the sub-cage back into the main cage and placing it around the pile foundation of the bridge under the water surface.

[0079] Through the above steps, the standard test pieces and / or curing test pieces can be replaced according to the test results, and the curing time can be extended to further examine the curing condition of the pile foundation.

[0080] Although the specific embodiments of the present invention are described above, it should be understood by those skilled in the art that this is only for illustration and the protection scope of the present invention is defined by the appended claims. Those skilled in the art may make various changes or modifications to these embodiments without departing from the principles and essence of the present invention, but these changes and modifications all fall within the protection scope of the present invention.

Claims

1. A method for detecting and maintaining a bridge pile foundation, used to detect the quality of maintenance construction of the pile foundation, characterized in that: The method for detecting and maintaining bridge pile foundations comprises the following steps: A main cage for accommodating the test piece is manufactured, wherein the main cage includes a plurality of sub-cages. Making test pieces in the sub-cages, wherein the test pieces include standard test pieces and curing test pieces, making the standard test piece according to a set standard mold in at least one of the sub-cages, and making the curing test piece simulating the curing construction of the pile foundation and having the same curing material in at least one of the sub-cages; Placing a plurality of sub-cages in the main cage, and placing the main cage around the pile foundation of the bridge under the water surface, and performing maintenance under the same conditions as the pile foundation under maintenance construction; According to the set time intervals, taking out different sub-cages from underwater; The standard test piece and / or the maintenance test piece in the sub-cage is taken out, and tested according to the set test requirements to obtain the maintenance construction quality of the pile foundation.

2. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: The step of "making the curing specimen simulating the curing construction of the pile foundation and having the same curing material in at least one of the sub-cages" specifically includes: While the pile foundation is being maintained, the underwater original soil around the pile foundation is laid at the bottom of the sub-cage, and solidified soil slurry with the same material as the pile foundation under maintenance construction is poured on the underwater original soil.

3. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: The step of "making the curing specimen simulating the curing construction of the pile foundation and having the same curing material in at least one of the sub-cages" specifically includes: According to the preset time intervals, the plurality of curing specimens are numbered according to different set times.

4. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: The step of "placing a plurality of sub-cages in the main cage" also includes: A compartment horizontal bar arranged in the horizontal direction and / or a compartment vertical bar arranged in the vertical direction are inserted between two adjacent sub-cages.

5. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: The main cage and / or the sub-cage include fixing parts for fixing the standard specimen and / or the maintenance specimen. The method for detecting and maintaining a bridge pile foundation also includes: One end of the fixing member is connected to the frame of the main cage and / or the sub-cage, and the other end of the fixing member is connected to the standard specimen and / or the curing specimen.

6. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: The main cage and / or the sub-cage include fixing parts for fixing the standard specimen and / or the maintenance specimen. The method for detecting and maintaining a bridge pile foundation also includes: The fixing parts are connected to different positions of the frame of the main cage and / or the sub-cage, and covered on the surfaces of the standard specimen and the curing specimen.

7. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: The outer frame of the main cage is provided with a lifting lug, and the method for detecting and maintaining a bridge pile foundation further comprises: Use one end of the lifting tool to connect with the lifting lug of the main cage, slowly put the main cage into the water from the other end of the lifting tool, and place it around the pile foundation of the bridge under the water surface; According to the set time interval, the main cage is taken out from underwater using a lifting tool.

8. The method for detecting and maintaining bridge pile foundation according to claim 7, characterized in that: The frame of the sub-cage is provided with a lifting lug, and the method for detecting and maintaining a bridge pile foundation further comprises: Before or after the main cage is taken out from underwater, one end of a lifting tool is used to connect with the lifting lug of the sub-cage, and the sub-cage is taken out from the main cage from the other end of the lifting tool.

9. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: Before the step of "placing the main cage around the pile foundation of the bridge under the water surface", the following steps are also included: At least one counterweight is arranged at the bottom of the main cage.

10. The method for detecting and maintaining bridge pile foundation according to claim 1, characterized in that: The method for detecting and maintaining bridge pile foundations also includes: After testing the standard test piece and / or the maintenance test piece, the standard test piece and / or the maintenance test piece in the sub-cage is replaced, and the sub-cage is put back into the main cage and placed around the pile foundation of the bridge under the water surface.