Deep tunnel excavation dynamic disturbance aging damage and catastrophe process testing device

By using the motor as the power disturbance source in Zhensanxuan test equipment, the problems of high energy consumption, high maintenance costs and inconsistent power disturbance forms in the existing technology are solved, and energy consumption reduction, maintenance simplification and power disturbance frequency adjustment are achieved. Effect.

CN118961567APending Publication Date: 2024-11-15NORTHEASTERN UNIV CHINA
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411123226.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

When conducting long-term dynamic disturbance tests, the existing Zhensanxuan test equipment has problems such as large energy consumption, high maintenance costs, complex hydraulic system, and the method of applying power disturbances does not match the form of power disturbances generated during tunnel excavation.

Method used

The motor is used as the power disturbance source, which simplifies the long-term power disturbance structure of Zhensanxuan test equipment, reduces energy consumption and simplifies the maintenance process through the motor, and simulates the power disturbance generated in the rotary drilling state.

Benefits of technology

It achieves a significant reduction in equipment energy consumption, reduced maintenance costs, and more time-saving installation and commissioning, and no additional floor area requirements, which can accurately control the frequency of power disturbance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118961567A_ABST
    Figure CN118961567A_ABST
Patent Text Reader

Abstract

A deep-buried tunnel excavation power disturbance aging damage and catastrophe process testing device belongs to the technical field of rock mechanics tests and comprises a counter-force frame, a pressure chamber, an excavation power disturbance actuator and five main stress hydraulic actuators. The excavation power disturbance actuator comprises a disturbance motor, an axial thrust loading expansion piece and a disturbance drill rod; an excavation dynamic disturbance rock sample clamp is arranged in the pressure chamber and comprises a tunnel protolith cushion block and five rigid cushion blocks; and a vibration frequency monitoring sensor is arranged in the tunnel protolith cushion block. According to the invention, the motor is introduced into the true triaxial test equipment as a power disturbance source for the first time, the long-time dynamic disturbance structure of the true triaxial test equipment is simplified, the energy consumption of the equipment is reduced, the maintenance process is simpler, the maintenance cost is reduced, the motor installation and debugging process is time-saving and labor-saving, and no extra floor area is needed. The dynamic disturbance generated in a rotary drilling state can be simulated, and the adjustment of the dynamic disturbance frequency can be realized by accurately controlling the drilling speed and the axial thrust of the motor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of rock mechanics testing, and in particular relates to a device for testing the time-dependent damage and catastrophic process of dynamic disturbance in deep tunnel excavation. Background Art

[0002] The construction of deep tunnels plays an important role in the development of modern infrastructure, especially in mountainous areas, underground cities and mining development. However, there are many challenges in the construction of deep tunnels, one of which is rock burst, which not only affects the progress of the project, but also may endanger the safety of construction workers.

[0003] Rockbursts can be divided into immediate rockbursts and time-delay rockbursts. Regarding immediate rockbursts, much progress has been made in prevention, control, and early warning through on-site microseismic monitoring and other means. Regarding time-delay rockbursts, there are currently few good monitoring methods that can achieve good prevention, control, and early warning effects.

[0004] The stress path of deep tunnel excavation will lead to an increase in tangential stress and a decrease in radial stress, which puts the surrounding rock in an unfavorable stress state. Based on the excavation stress path, the surrounding rock is subjected to multi-source long-term dynamic disturbances, and cracks will continue to initiate and accumulate, resulting in a continuous decrease in the bearing capacity of the surrounding rock, and then a time-delay rockburst may occur. For example, when the face blasting repeatedly disturbs the surrounding rock behind, it is possible to induce a time-delay rockburst in the surrounding rock; when adjacent parallel tunnels are constructed, the blasting of the rear tunnel may induce a time-delay rockburst in the leading tunnel; during the TBM construction process, continuous vibrations, earthquakes and other dynamic disturbances may also trigger a time-delay rockburst in the tunnel surrounding rock.

[0005] The on-site investigation of the project shows that once a time-delay rockburst occurs, most of them are strong rockbursts, which seriously endanger the safety of construction personnel and equipment and seriously affect the construction progress. Therefore, it is the most urgent need to realize the prevention and control and early warning of time-delay rockbursts during the construction of deep engineering projects, and it is very necessary to carry out dynamic disturbance test research under true triaxial conditions.

[0006] At present, the true triaxial testing machine is mainly divided into instantaneous dynamic disturbance test and long-term dynamic disturbance test when conducting dynamic disturbance test. Data from a large number of deep engineering field surveys show that the disturbance stress influence on the surrounding rock of deep engineering is continuous, and the surrounding rock stress often presents two typical modes of true triaxial compression and shear. This long-term dynamic disturbance will cause high-frequency fatigue opening and closing of cracks inside the rock, affect the energy storage and release inside the hard rock, change the ductility and brittleness characteristics of the rock mass, and finally cause brittle fracture with time-dependent characteristics. The occurrence of time-delay rock burst is related to this long-term, high-frequency, low-amplitude disturbance influence. Therefore, relevant research can only be carried out through long-term dynamic disturbance tests.

[0007] At present, although there are many types of true triaxial test equipment that can carry out long-term dynamic disturbance tests, the long-term dynamic disturbances of these true triaxial test equipment are all achieved by the cooperation of dynamic actuators and hydraulic oil sources. The problems existing in carrying out long-term dynamic disturbance tests have never been effectively overcome, as follows: ①. High energy consumption When the dynamic actuator is used in conjunction with the hydraulic oil source, there is a certain loss in the energy transmission process. For example, energy loss occurs due to the viscosity of the oil and pipeline friction, so the energy efficiency is relatively low. In addition, the temperature of the oil source will gradually increase as the test progresses, further affecting the performance of the hydraulic oil source. Long-term high temperature also poses certain safety hazards. Therefore, there are obvious application limitations in conducting long-term dynamic disturbance tests in conjunction with the dynamic actuator and the hydraulic oil source.

[0008] ②High maintenance cost In order to ensure the operating stability of the hydraulic system where the dynamic actuator and the hydraulic oil source are located, it is necessary not only to regularly replace the oil in the hydraulic system, but also to regularly inspect and maintain the valves, seals, etc. in the hydraulic system. Especially under long-term operation and high-load working conditions, oil replacement and inspection and maintenance will be more frequent, resulting in high maintenance costs.

[0009] ③. Complex hydraulic system Since the hydraulic system where the dynamic actuator and the hydraulic oil source are located has a large number of pipes, hydraulic pumps, cylinders, valves, seals and other components, the structure of the hydraulic system is very complicated, which not only makes the installation and debugging of the hydraulic system time-consuming and labor-intensive, but also requires additional installation space, resulting in the true triaxial test equipment requiring a larger footprint.

[0010] ④ The dynamic disturbance application method does not match the dynamic disturbance form generated during tunnel excavation When the dynamic actuator cooperates with the hydraulic oil source, the dynamic actuator can only apply dynamic disturbance in the axial direction. However, tunnel excavation also includes dynamic disturbances generated in the rotary drilling state. Therefore, the dynamic actuator cannot simulate the dynamic disturbances generated in the rotary drilling state. Summary of the invention

[0011] In view of the problems existing in the prior art, the present invention provides a device for testing the time-dependent damage and catastrophic process of dynamic disturbance in deep tunnel excavation, which abandons the traditional form of cooperation between a dynamic actuator and a hydraulic oil source, and introduces a motor as a power disturbance source into a true triaxial test device for the first time, thereby greatly simplifying the long-term power disturbance structure of the true triaxial test device. After using the motor as the power disturbance source, the energy consumption of the equipment is greatly reduced, the maintenance process is simpler and the maintenance cost is greatly reduced, the installation and debugging process of the motor is also more time-saving and labor-saving, and there is no additional floor space requirement. The device can simulate the power disturbance generated in the rotary drilling state, and can adjust the power disturbance frequency by precisely controlling the motor drilling speed and axial thrust.

[0012] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a deep-buried tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device, comprising a reaction force frame, a pressure chamber, a first principal stress hydraulic actuator, a second principal stress hydraulic actuator, a third principal stress hydraulic actuator, a fourth principal stress hydraulic actuator, a fifth principal stress hydraulic actuator and an excavation dynamic disturbance actuator; the reaction force frame adopts a square-shaped structure, and the reaction force frame is vertically arranged; the pressure chamber adopts a hollow cylindrical structure, and the pressure chamber is horizontally arranged and inserted into the central hole of the reaction force frame; a pressure chamber pulling and driving cylinder is fixedly embedded in the base of the reaction force frame, and the pressure chamber is pressed by the pressure chamber. The force chamber pulling and pulling driving cylinder is distributed in parallel with the pressure chamber, the cylinder barrel of the pressure chamber pulling and pulling driving cylinder is fixedly connected to the reaction force frame base, and the cylinder rod of the pressure chamber pulling and pulling driving cylinder is fixedly connected to the pressure chamber; the first principal stress hydraulic actuator and the second principal stress hydraulic actuator are mirror-symmetrically distributed at the axial ends of the pressure chamber; the third principal stress hydraulic actuator and the fourth principal stress hydraulic actuator are mirror-symmetrically distributed at the left and right ends of the reaction force frame; the fifth principal stress hydraulic actuator is arranged at the bottom end of the reaction force frame; the excavation power disturbance actuator is arranged at the top end of the reaction force frame, and the excavation power disturbance actuator and the fifth principal stress hydraulic actuator are coaxially distributed.

[0013] The excavation power disturbance actuator includes a disturbance motor, an axial thrust loading telescopic device and a disturbance drill rod; the disturbance motor is vertically fixed on the top of the reaction frame with the motor shaft facing downward, the upper end of the axial thrust loading telescopic device is coaxially fixed to the motor shaft of the disturbance motor, and the upper end of the disturbance drill rod is coaxially fixed to the lower end of the axial thrust loading telescopic device.

[0014] The axial thrust loading telescopic device adopts an electric drive structure, a hydraulic drive structure or a pneumatic drive structure.

[0015] An excavation dynamic disturbance rock sample fixture is arranged inside the pressure chamber.

[0016] The excavation dynamic disturbance rock sample fixture includes a first rigid pad, a second rigid pad, a third rigid pad, a fourth rigid pad, a fifth rigid pad and a tunnel original rock pad; the first rigid pad, the second rigid pad, the third rigid pad and the fourth rigid pad are respectively in contact with the four lateral surfaces of the rock sample; the fifth rigid pad is in contact with the bottom surface of the rock sample; the tunnel original rock pad is in contact with the top surface of the rock sample.

[0017] The lower end of the disturbance drill rod is in contact with the top surface of the tunnel original rock pad.

[0018] A vibration frequency monitoring sensor is installed inside the original rock pad of the tunnel.

[0019] Beneficial effects of the present invention: The deep-buried tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device of the present invention abandons the traditional form of cooperation between a dynamic actuator and a hydraulic oil source, and introduces a motor as a power disturbance source into the true triaxial test equipment for the first time, greatly simplifying the long-term dynamic disturbance structure of the true triaxial test equipment. After using the motor as the power disturbance source, the energy consumption of the equipment is greatly reduced, the maintenance process is simpler and the maintenance cost is greatly reduced, the installation and debugging process of the motor is also more time-saving and labor-saving, and there is no additional floor space requirement. It can simulate the power disturbance generated in the rotary drilling state, and can adjust the power disturbance frequency by precisely controlling the motor drilling speed and axial thrust. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a structural schematic diagram of a deep tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device of the present invention (the pressure chamber is in an extended state); Figure 2 It is a structural schematic diagram of a deep tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device of the present invention (the pressure chamber is in a retracted state); Figure 3 It is a structural schematic diagram of a deep-buried tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device (section view) of the present invention (the pressure chamber is in a retracted state); Figure 4 It is a schematic diagram of the structure of the rock sample fixture for excavation dynamic disturbance of the present invention; In the figure, 1 is a reaction frame, 2 is a pressure chamber, 3 is a first principal stress hydraulic actuator, 4 is a second principal stress hydraulic actuator, 5 is a third principal stress hydraulic actuator, 6 is a fourth principal stress hydraulic actuator, 7 is a fifth principal stress hydraulic actuator, 8 is an excavation power disturbance actuator, 9 is a pressure chamber pull-out drive cylinder, 10 is a disturbance motor, 11 is an axial thrust loading telescopic device, 12 is a disturbance drill rod, 13 is a first rigid pad, 14 is a second rigid pad, 15 is a third rigid pad, 16 is a fourth rigid pad, 17 is a fifth rigid pad, 18 is a tunnel original rock pad, 19 is a rock sample, and 20 is a vibration frequency monitoring sensor. DETAILED DESCRIPTION

[0021] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0022] like Figures 1 to 4 As shown, a deep-buried tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device comprises a reaction frame 1, a pressure chamber 2, a first principal stress hydraulic actuator 3, a second principal stress hydraulic actuator 4, a third principal stress hydraulic actuator 5, a fourth principal stress hydraulic actuator 6, a fifth principal stress hydraulic actuator 7 and an excavation dynamic disturbance actuator 8; the reaction frame 1 adopts a square-shaped structure, and the reaction frame 1 is vertically arranged; the pressure chamber 2 adopts a hollow cylindrical structure, and the pressure chamber 2 is horizontally arranged and inserted into the central hole of the reaction frame 1; a pressure chamber pulling and pulling drive cylinder 9 is fixedly embedded in the base of the reaction frame 1, and the pressure chamber pulling and pulling drive cylinder 9 and the pressure chamber are connected to each other. The force chambers 2 are distributed in parallel, the cylinder barrel of the pressure chamber pulling and driving cylinder 9 is fixedly connected to the base of the reaction frame 1, and the cylinder rod of the pressure chamber pulling and driving cylinder 9 is fixedly connected to the pressure chamber 2; the first principal stress hydraulic actuator 3 and the second principal stress hydraulic actuator 4 are mirror-symmetrically distributed at the axial ends of the pressure chamber 2; the third principal stress hydraulic actuator 5 and the fourth principal stress hydraulic actuator 6 are mirror-symmetrically distributed at the left and right ends of the reaction frame 1; the fifth principal stress hydraulic actuator 7 is arranged at the bottom end of the reaction frame 1; the excavation power disturbance actuator 8 is arranged at the top end of the reaction frame 1, and the excavation power disturbance actuator 8 and the fifth principal stress hydraulic actuator 7 are coaxially distributed.

[0023] The excavation power disturbance actuator 8 includes a disturbance motor 10, an axial thrust loading telescope 11 and a disturbance drill rod 12; the disturbance motor 10 is vertically fixed on the top of the reaction frame 1 with the motor shaft facing downward, the upper end of the axial thrust loading telescope 11 is coaxially fixed to the motor shaft of the disturbance motor 10, and the upper end of the disturbance drill rod 12 is coaxially fixed to the lower end of the axial thrust loading telescope 11.

[0024] The axial thrust loading retractor 11 adopts an electric drive structure, a hydraulic drive structure or a pneumatic drive structure.

[0025] An excavation dynamic disturbance rock sample fixture is arranged inside the pressure chamber 2 .

[0026] The excavation dynamic disturbance rock sample fixture includes a first rigid pad 13, a second rigid pad 14, a third rigid pad 15, a fourth rigid pad 16, a fifth rigid pad 17 and a tunnel original rock pad 18; the first rigid pad 13, the second rigid pad 14, the third rigid pad 15 and the fourth rigid pad 16 are respectively in contact with the four lateral surfaces of the rock sample 19; the fifth rigid pad 17 is in contact with the bottom surface of the rock sample 19; the tunnel original rock pad 18 is in contact with the top surface of the rock sample 19.

[0027] The lower end of the disturbance drill rod 12 is in contact with the top surface of the tunnel original rock pad 18 .

[0028] A vibration frequency monitoring sensor 20 is installed inside the tunnel original rock pad 18 .

[0029] The following describes a one-time use process of the present invention in conjunction with the accompanying drawings: In this embodiment, the axial thrust loading retractor 11 can provide a maximum pressure of 10 MPa for the disturbance drill rod 12. When coordinated with the drilling speed of the disturbance motor 10, the disturbance frequency can reach a maximum of 500 Hz.

[0030] Before the test, the rock sample 19 is clamped into the excavation dynamic disturbance rock sample fixture, and at the same time, the displacement sensors are installed between the first rigid pad 13 and the third rigid pad 15, and between the second rigid pad 14 and the fourth rigid pad 16, and the vibration frequency monitoring sensor 20 is installed on the tunnel original rock pad 18.

[0031] The excavation dynamic disturbance rock sample fixture clamped with the rock sample 19 is sent into the pressure chamber 2, and then the cylinder rod of the pressure chamber pulling and driving cylinder 9 is controlled to retract until the pressure chamber 2 is completely retracted into the central hole of the reaction frame 1, and the pressure chamber 2 is closed.

[0032] First, the centering pre-clamping of the rock sample 19 is completed by the first principal stress hydraulic actuator 3, the second principal stress hydraulic actuator 4, the third principal stress hydraulic actuator 5, and the fourth principal stress hydraulic actuator 6. Then, the first principal stress hydraulic actuator 3 and the second principal stress hydraulic actuator 4 apply the minimum principal stress to the rock sample 19 to the target value. At the same time, the third principal stress hydraulic actuator 5 and the fourth principal stress hydraulic actuator 6 synchronously apply the minimum principal stress to the rock sample 19 to the target value. Then, the fifth principal stress hydraulic actuator 7 alone applies the minimum principal stress to the rock sample 19 to the target value.

[0033] After the rock sample 19 completes the application of the minimum principal stress in five directions, the stress loading of the rock sample 19 by the first principal stress hydraulic actuator 3, the second principal stress hydraulic actuator 4, the third principal stress hydraulic actuator 5 and the fourth principal stress hydraulic actuator 6 is increased to the intermediate principal stress target value, and then the stress loading of the rock sample 19 by the first principal stress hydraulic actuator 3 and the second principal stress hydraulic actuator 4 is continued to be increased to the maximum principal stress target value, thereby completing the true triaxial loading of the rock sample 19.

[0034] After the rock sample 19 completes the true triaxial loading, the disturbance motor 10 is started first, and the axial thrust loading expansion joint 11 and the disturbance drill rod 12 are driven to rotate synchronously by the disturbance motor 10, and then the axial thrust loading expansion joint 11 is started, so that the disturbance drill rod 12 gradually moves down and contacts the top surface of the tunnel original rock pad 18. As the thrust of the axial thrust loading expansion joint 11 is applied, the disturbance drill rod 12 begins to drill the tunnel original rock pad 18 to simulate tunnel excavation. In this process, dynamic disturbance will be generated on the tunnel original rock pad 18, and the dynamic disturbance will be directly transmitted to the rock sample 19 below. When the tunnel original rock pad 18 generates dynamic disturbance, the vibration signal will be directly obtained by the vibration frequency monitoring sensor 20. At this time, the thrust application value of the axial thrust loading expansion joint 11 and the rotation speed of the disturbance motor 10 can be dynamically adjusted according to the real-time acquired vibration frequency, so as to realize the dynamic adjustment of the vibration frequency until the long-term disturbance test is completed.

[0035] The solutions in the embodiments are not intended to limit the protection scope of the present invention. All equivalent implementations or changes that do not deviate from the present invention are included in the protection scope of the present invention.

Claims

1. A device for testing the time-dependent damage and catastrophic process of deep tunnel excavation dynamic disturbance, characterized in that: It includes a reaction force frame, a pressure chamber, a first principal stress hydraulic actuator, a second principal stress hydraulic actuator, a third principal stress hydraulic actuator, a fourth principal stress hydraulic actuator, a fifth principal stress hydraulic actuator and an excavation dynamic disturbance actuator; the reaction force frame adopts a square-shaped structure, and the reaction force frame is vertically arranged; the pressure chamber adopts a hollow cylindrical structure, and the pressure chamber is horizontally arranged and inserted into the central hole of the reaction force frame; a pressure chamber pulling and pulling drive cylinder is fixedly embedded in the base of the reaction force frame, and the pressure chamber pulling and pulling drive cylinder is parallel to the pressure chamber, and the pressure chamber pulling and pulling drive The cylinder barrel of the oil cylinder is fixedly connected to the base of the reaction force frame, and the cylinder rod of the pressure chamber pulling and driving oil cylinder is fixedly connected to the pressure chamber; the first principal stress hydraulic actuator and the second principal stress hydraulic actuator are mirror-symmetrically distributed at the axial ends of the pressure chamber; the third principal stress hydraulic actuator and the fourth principal stress hydraulic actuator are mirror-symmetrically distributed at the left and right ends of the reaction force frame; the fifth principal stress hydraulic actuator is arranged at the bottom end of the reaction force frame; the excavation power disturbance actuator is arranged at the top end of the reaction force frame, and the excavation power disturbance actuator and the fifth principal stress hydraulic actuator are coaxially distributed.

2. A deep tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device according to claim 1, characterized in that: The excavation power disturbance actuator includes a disturbance motor, an axial thrust loading telescopic device and a disturbance drill rod; the disturbance motor is vertically fixed on the top of the reaction frame with the motor shaft facing downward, the upper end of the axial thrust loading telescopic device is coaxially fixed to the motor shaft of the disturbance motor, and the upper end of the disturbance drill rod is coaxially fixed to the lower end of the axial thrust loading telescopic device.

3. A deep tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device according to claim 2, characterized in that: The axial thrust loading telescopic device adopts an electric drive structure, a hydraulic drive structure or a pneumatic drive structure.

4. The deep tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device according to claim 2 is characterized by: An excavation dynamic disturbance rock sample fixture is arranged inside the pressure chamber.

5. The deep tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device according to claim 4, characterized in that: The excavation dynamic disturbance rock sample fixture comprises a first rigid pad, a second rigid pad, a third rigid pad, a fourth rigid pad, a fifth rigid pad and a tunnel original rock pad; the first rigid pad, the second rigid pad, the third rigid pad and the fourth rigid pad are respectively in contact with four lateral surfaces of the rock sample; The fifth rigid pad is in abutment contact with the bottom surface of the rock sample; the tunnel original rock pad is in abutment contact with the top surface of the rock sample.

6. The device for testing the time-dependent damage and catastrophic process of deep tunnel excavation dynamic disturbance according to claim 5, characterized in that: The lower end of the disturbance drill rod is in contact with the top surface of the tunnel original rock pad.

7. The deep tunnel excavation dynamic disturbance time-dependent damage and catastrophic process testing device according to claim 5, characterized in that: A vibration frequency monitoring sensor is installed inside the original rock pad of the tunnel.

Citation Information

Cited By

  • Deep engineering dynamic disturbance hard rock true triaxial CT real-time scanning experiment device

    CN121090241A