Finite element model conversion method and device of train and electronic equipment
By meshing and matching the train's finite element model and converting the static intensity finite element model into a collision simulation model, the problem of low efficiency of train simulation analysis is solved, and fast and accurate simulation analysis is achieved.
Patent Information
- Application Number
- CN202411203487.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-15
AI Technical Summary
The collision simulation model of the train is complex and the number of finite element grids is huge, resulting in a long modeling cycle and low simulation analysis efficiency.
It provides a finite element model conversion method for trains, which can obtain static intensity finite element model, re-divider grid, match static intensity and collision simulation information, update the model, generate target collision simulation model, shorten the modeling cycle, and improve simulation efficiency.
Without repeated modeling, the fast conversion of the static intensity finite element model is a collision simulation model, which shortens the modeling cycle, improves the simulation analysis efficiency of the train, and reduces time and cost.
Smart Images

Figure CN118965909A_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the technical field of vehicle simulation, and more specifically, to a finite element model conversion method, device and electronic equipment for a train. Background Art
[0002] With the development of the times, trains have become an important means of transportation for people. The increasing speed of trains has brought convenience to people's lives, but also put forward higher requirements for collision safety. Therefore, the demand for train collision simulation analysis is constantly expanding, and how to quickly and accurately complete collision simulation has become a top priority.
[0003] In the process of realizing the concept of the present disclosure, the inventors found that there are at least the following problems in the related art: the collision simulation model of the train is complex in structure and has a huge number of finite element grids, which leads to a long modeling cycle and low efficiency of train simulation analysis. Summary of the invention
[0004] In view of this, the present disclosure provides a finite element model conversion method, device and electronic equipment for a train.
[0005] One aspect of the present disclosure provides a finite element model conversion method for a train, comprising: obtaining a static strength finite element model for static strength simulation of a train; in response to the number of grids in the static strength finite element model satisfying a grid number threshold in a collision simulation of the train, re-meshing an area in the static strength finite element model that satisfies a preset collision condition to obtain an intermediate finite element model; matching static strength simulation information of each component of the train in the static strength finite element model with collision simulation information of each component of the train to obtain model conversion information of the component to be updated, the model conversion information being information that the static strength simulation information of the component to be updated does not match the collision simulation information; and updating the intermediate finite element model according to the model conversion information of the component to be updated to obtain a target collision simulation model.
[0006] According to an embodiment of the present disclosure, collision simulation information includes component material information, component welding point information and collision scene information; updating the intermediate finite element model according to the model conversion information of the component to be updated to obtain a target collision simulation model includes: the model conversion information for the component to be updated includes component material information, and the intermediate finite element model is updated with the component material information to obtain a material update simulation model; the model conversion information for the component to be updated also includes component welding point information, and the material update simulation model is updated with the component welding point information to obtain a welding point update simulation model; the collision scene of the welding point update simulation model is set according to the collision scene information in the collision simulation information to obtain a target collision simulation model.
[0007] According to an embodiment of the present disclosure, component material information includes material type and material properties corresponding to the material type; updating the material of the intermediate finite element model according to the component material information to obtain a material update simulation model includes: updating the material type of the intermediate finite element model according to the material type of the component to be updated to obtain an initial material update simulation model; updating the material properties of the initial material update simulation model according to the material properties corresponding to the material type to obtain a material update simulation model.
[0008] According to an embodiment of the present disclosure, component weld information includes weld position and the number of components connected to the weld position; performing weld updating on a material update simulation model according to the component weld information to obtain a weld update simulation model includes: regenerating weld units of the material update simulation model according to the weld position in the collision simulation information to obtain an initial weld update simulation model; updating the number of layers connected to each weld position in the initial weld update simulation model according to the number of components connected to the weld position to obtain a weld update simulation model.
[0009] According to an embodiment of the present disclosure, the collision scene information includes mechanical parameters and collision parameters between various components of the train; setting the collision scene of the weld update simulation model according to the collision scene information in the collision simulation information to obtain the target collision simulation model includes: according to the mechanical parameters between various components of the train in the collision simulation information, mechanically setting each component in the weld update simulation model to obtain a mechanical update simulation model; according to the collision parameters in the collision simulation information, setting the collision parameters of the mechanical update simulation model to obtain a target collision simulation model.
[0010] According to an embodiment of the present disclosure, the area that meets the preset collision conditions includes the middle area between multiple sleeper beam components of the train; re-meshing the area that meets the preset collision conditions in the static strength finite element model to obtain the intermediate finite element model includes: re-meshing the middle area between the multiple sleeper beam components in the static strength finite element model.
[0011] According to an embodiment of the present disclosure, re-gridding the middle area between multiple sleeper beam components in the static strength finite element model also includes: determining a sub-area with an annular structure from the middle area between the multiple sleeper beam components of the train; and reducing the longitudinal grid unit density of the sub-area with the annular structure.
[0012] According to an embodiment of the present disclosure, the area that meets the preset collision conditions also includes a rib plate component area, and the rib plate is located inside the train component and is not connected to other components; the area that meets the preset collision conditions in the static strength finite element model is re-meshed to obtain an intermediate finite element model including: reducing the grid unit density in a preset direction of the rib plate area, and the preset direction is the direction in which the rib plate is connected to the inside of the train component.
[0013] Another aspect of the present disclosure provides a finite element model conversion device for a train, comprising: an acquisition module, used to acquire a static strength finite element model for static strength simulation of the train; a meshing module, used to re-mesh the area in the static strength finite element model that meets a preset collision condition in response to the number of meshes in the static strength finite element model meeting a mesh number threshold in a collision simulation of the train, to obtain an intermediate finite element model; a matching module, used to match static strength simulation information of each component of the train in the static strength finite element model with collision simulation information of each component of the train, to obtain model conversion information of the component to be updated, the model conversion information being information that the static strength simulation information of the component to be updated does not match the collision simulation information; an updating module, used to update the component to be updated in the intermediate finite element model according to the model conversion information, to obtain a target collision simulation model.
[0014] Another aspect of the present disclosure provides an electronic device, comprising:
[0015] one or more processors;
[0016] a memory for storing one or more programs,
[0017] When the one or more programs are executed by the one or more processors, the one or more processors implement the method as described above.
[0018] Another aspect of the present disclosure provides a computer-readable storage medium storing computer-executable instructions, which are used to implement the above method when executed.
[0019] Another aspect of the present disclosure provides a computer program product, which includes computer executable instructions, and when the instructions are executed, are used to implement the method as described above.
[0020] According to an embodiment of the present disclosure, a static strength finite element model for static strength simulation of a train is obtained, and in response to the number of meshes in the static strength finite element model satisfying a threshold number of meshes in a collision simulation of the train, the area in the static strength finite element model that satisfies a preset collision condition is re-meshed to obtain an intermediate finite element model, thereby achieving re-meshing of the area that satisfies the preset collision condition on the established static strength finite element model to satisfy the threshold number of meshes in the collision simulation of the train.
[0021] The static strength simulation information of each train component in the static strength finite element model is matched with the collision simulation information of each train component to obtain the model conversion information of the components to be updated; then the components to be updated in the intermediate finite element model are updated according to the model conversion information to obtain the target collision simulation model, thereby quickly converting the static strength finite element model of the train into a collision simulation model. Without repeated modeling, the static strength and collision simulation analysis tasks of the train are normally realized, which shortens the modeling cycle of the collision simulation model and improves the simulation analysis efficiency of the train. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The above and other objects, features and advantages of the present disclosure will become more apparent through the following description of the embodiments of the present disclosure with reference to the accompanying drawings, in which:
[0023] Figure 1 A system architecture diagram of a finite element model conversion method for a train according to an embodiment of the present disclosure is schematically shown;
[0024] Figure 2 A flow chart of a finite element model conversion method for a train according to an embodiment of the present disclosure is schematically shown;
[0025] Figure 3A The static strength finite element model of a carriage in a train according to an embodiment of the present disclosure is schematically shown;
[0026] Figure 3B The collision simulation model of two trains in the embodiment of the present disclosure is schematically shown;
[0027] Figure 3C Schematically illustrates a collision area in a train according to an embodiment of the present disclosure;
[0028] Figure 4A A schematic diagram of welding two components in a finite element simulation model according to an embodiment of the present disclosure is schematically shown;
[0029] Figure 4B A schematic diagram of welding three components in a finite element simulation model according to an embodiment of the present disclosure is schematically shown;
[0030] Figure 5A A schematic diagram schematically shows a middle area between two bolster components in a train according to an embodiment of the present disclosure;
[0031] Figure 5B A schematic diagram of a sub-area having a complete ring structure in a train according to an embodiment of the present disclosure is schematically shown;
[0032] Figure 5C A schematic diagram of a sub-area having a semi-annular structure in a train according to an embodiment of the present disclosure is schematically shown;
[0033] Fig. 6A A schematic diagram schematically shows the direction in which the rib plate is connected to the internal part of a train component according to an embodiment of the present disclosure;
[0034] Figure 6B A schematic diagram of reducing the grid unit density in a preset direction of a rib plate area according to an embodiment of the present disclosure is schematically shown;
[0035] Figure 7 A flow chart of a finite element model conversion method for a train according to another embodiment of the present disclosure is schematically shown;
[0036] Figure 8 An interface diagram schematically shows the collision simulation parameter settings in the finite element model conversion method of a train according to an embodiment of the present disclosure;
[0037] Fig. 9 A block diagram schematically shows a finite element model conversion device for a train according to an embodiment of the present disclosure; and
[0038] Fig.10 A block diagram of an electronic device suitable for implementing a finite element model conversion method for a train according to an embodiment of the present disclosure is schematically shown. DETAILED DESCRIPTION
[0039] Hereinafter, embodiments of the present disclosure will be described with reference to the accompanying drawings. However, it should be understood that these descriptions are exemplary only and are not intended to limit the scope of the present disclosure. In the following detailed description, for ease of explanation, many specific details are set forth to provide a comprehensive understanding of the embodiments of the present disclosure. However, it is apparent that one or more embodiments may also be implemented without these specific details. In addition, in the following description, descriptions of known structures and technologies are omitted to avoid unnecessary confusion of the concepts of the present disclosure.
[0040] The terms used herein are only for describing specific embodiments and are not intended to limit the present disclosure. The terms "comprise", "include", etc. used herein indicate the existence of the features, steps, operations and / or components, but do not exclude the existence or addition of one or more other features, steps, operations or components.
[0041] All terms (including technical and scientific terms) used herein have the meanings commonly understood by those skilled in the art unless otherwise defined. It should be noted that the terms used herein should be interpreted as having a meaning consistent with the context of this specification and should not be interpreted in an idealized or overly rigid manner.
[0042] When using expressions such as "at least one of A, B, and C, etc.", they should generally be interpreted according to the meaning of the expression commonly understood by those skilled in the art (for example, "a system having at least one of A, B, and C" should include but is not limited to a system having A alone, B alone, C alone, A and B, A and C, B and C, and / or A, B, C, etc.).
[0043] In the embodiments of the present disclosure, the collection, updating, analysis, processing, use, transmission, provision, disclosure, storage, etc. of the data involved (for example, including but not limited to user personal information) are in compliance with the provisions of relevant laws and regulations, are used for legitimate purposes, and do not violate public order and good morals. In particular, necessary measures are taken for user personal information to prevent illegal access to user personal information data and maintain the security of user personal information, network security, and national security.
[0044] In the embodiments of the present disclosure, the user's authorization or consent is obtained before obtaining or collecting the user's personal information.
[0045] In order to save time and cost of train simulation projects, a common set of mesh unit models is adopted for static strength simulation and collision simulation. However, there are many differences between the static strength finite element model requirements and the collision simulation model, which makes it very difficult to directly use the static strength finite element model for collision simulation.
[0046] In view of this, an embodiment of the present disclosure provides a finite element model conversion method for a train, comprising: obtaining a static strength finite element model for static strength simulation of a train; in response to the number of grids in the static strength finite element model satisfying a grid number threshold in a collision simulation of the train, re-meshing the area in the static strength finite element model that satisfies a preset collision condition to obtain an intermediate finite element model; matching the static strength simulation information of each component of the train in the static strength finite element model with the collision simulation information of each component of the train to obtain model conversion information of the component to be updated, the model conversion information being information that the static strength simulation information of the component to be updated does not match the collision simulation information; updating the intermediate finite element model according to the model conversion information of the component to be updated to obtain a target collision simulation model.
[0047] Figure 1 The system architecture diagram of the finite element model conversion method of a train according to an embodiment of the present disclosure is schematically shown. It should be noted that: Figure 1 What is shown is merely an example of a system architecture to which the embodiments of the present disclosure can be applied, in order to help those skilled in the art understand the technical content of the present disclosure, but it does not mean that the embodiments of the present disclosure cannot be used in other devices, systems, environments or scenarios.
[0048] like Figure 1As shown, the system architecture 100 according to this embodiment may include a first terminal device 101, a second terminal device 102, a third terminal device 103, a network 104, and a server 105. The network 104 is used to provide a medium for a communication link between the first terminal device 101, the second terminal device 102, the third terminal device 103, and the server 105. The network 104 may include various connection types, such as wired and / or wireless communication links, etc.
[0049] The user may use the first terminal device 101, the second terminal device 102, and the third terminal device 103 to interact with the server 105 through the network 104 to receive or send messages, etc. Various communication client applications may be installed on the first terminal device 101, the second terminal device 102, and the third terminal device 103, such as shopping applications, web browser applications, search applications, instant messaging tools, email clients, and / or social platform software, etc. (only for example).
[0050] The first terminal device 101, the second terminal device 102, and the third terminal device 103 may be various electronic devices having display screens and supporting web browsing, including but not limited to smart phones, tablet computers, laptop computers, desktop computers, and the like.
[0051] The server 105 may be a server that provides various services, such as a background management server (only as an example) that provides support for websites browsed by users using the first terminal device 101, the second terminal device 102, and the third terminal device 103. The background management server may analyze and process the received data such as user requests, and feed back the processing results (such as web pages, information, or data obtained or generated according to user requests) to the terminal device.
[0052] It should be noted that the finite element model conversion method of the train provided in the embodiment of the present disclosure can generally be executed by the server 105. Accordingly, the finite element model conversion device of the train provided in the embodiment of the present disclosure can generally be set in the server 105. The finite element model conversion method of the train provided in the embodiment of the present disclosure can also be executed by a server or server cluster that is different from the server 105 and can communicate with the first terminal device 101, the second terminal device 102, the third terminal device 103 and / or the server 105. Correspondingly, the finite element model conversion device of the train provided in the embodiment of the present disclosure can also be set in a server or server cluster that is different from the server 105 and can communicate with the first terminal device 101, the second terminal device 102, the third terminal device 103 and / or the server 105. Alternatively, the finite element model conversion method of the train provided in the embodiment of the present disclosure can also be executed by the first terminal device 101, the second terminal device 102 or the third terminal device 103, or can also be executed by other terminal devices different from the first terminal device 101, the second terminal device 102 or the third terminal device 103. Correspondingly, the finite element model conversion device of the train provided in the embodiment of the present disclosure can also be set in the first terminal device 101, the second terminal device 102 or the third terminal device 103, or in other terminal devices different from the first terminal device 101, the second terminal device 102 or the third terminal device 103.
[0053] For example, the static strength finite element model used for static strength simulation of the train may be originally stored in any one of the first terminal device 101, the second terminal device 102 or the third terminal device 103 (for example, the first terminal device 101, but not limited thereto), or stored on an external storage device and may be imported into the first terminal device 101. Then, the first terminal device 101 may locally execute the finite element model conversion method of the train provided in the embodiment of the present disclosure, or send the image to be processed to other terminal devices, servers, or server clusters, and the other terminal devices, servers, or server clusters that receive the image to be processed may execute the finite element model conversion method of the train provided in the embodiment of the present disclosure.
[0054] It should be understood that Figure 1 The number of terminal devices, networks and servers in the embodiment is only for illustration. Any number of terminal devices, networks and servers may be provided according to implementation requirements.
[0055] Figure 2 A flow chart of a finite element model conversion method for a train according to an embodiment of the present disclosure is schematically shown.
[0056] like Figure 2 As shown, the method includes operations S210 to S240.
[0057] In operation S210 , a static strength finite element model for performing static strength simulation on a train is obtained.
[0058] According to an embodiment of the present disclosure, the train may be a rail vehicle. For example, the train may be a motor vehicle.
[0059] According to an embodiment of the present disclosure, static strength simulation can predict the behavior of train structures and materials under static loads. For example, a constant pressure or stress is applied to part of the train structure to analyze the stress and strain of a static train.
[0060] The static strength finite element model can be divided into many grids (also called units) in the train components, and then the stress and strain of each grid are analyzed.
[0061] The static strength finite element model can define the support method or applied load between the components in the train, and can also set the mechanical properties of the materials of each component.
[0062] In operation S220, in response to the number of meshes of the static strength finite element model satisfying a mesh number threshold in the train collision simulation, the area in the static strength finite element model satisfying a preset collision condition is re-meshed to obtain an intermediate finite element model.
[0063] Figure 3A The static strength finite element model of a carriage in a train according to an embodiment of the present disclosure is schematically shown.
[0064] like Figure 3A As shown, the unit size of the mesh of the static strength finite element model can be about 20 mm, and the number of meshes for the entire train can be about 3 million.
[0065] Figure 3B A collision simulation model for two train scenarios according to an embodiment of the present disclosure is schematically shown.
[0066] like Figure 3B As shown, both train A and train B have multiple carriages. If train A has Figure 3A For the four carriages, excluding other simplified car bodies and bogies, the number of collision simulation grids reaches more than 12 million.
[0067] However, directly using the static strength finite element model for collision simulation analysis will result in a finite element model that is too large, which is not conducive to subsequent calculations, processing and storage. If all components of the static strength finite element model are re-meshed to obtain a collision simulation model, the project cost and time will increase significantly.
[0068] Considering that the number of grids in the static strength finite element model meets the grid number threshold in the train collision simulation, that is, the number of grids in the static strength finite element model is much larger than the grid number threshold in the collision simulation, which affects the subsequent calculation, processing and storage. Therefore, the area in the static strength finite element model that meets the preset collision conditions is re-meshed to obtain an intermediate finite element model.
[0069] According to an embodiment of the present disclosure, the area satisfying the preset collision condition may be a non-main deformation area of the train after the collision. The non-main deformation area may be determined by the collision direction.
[0070] For example, if two trains are traveling towards each other, the main deformation area may be the head of the train, and the non-deformation area may be the area behind the head of the train.
[0071] Figure 3C The diagram schematically shows a collision area in a train according to an embodiment of the present disclosure.
[0072] like Figure 3C As shown, during the train collision simulation, the main collision areas include the main deformation area and the non-main deformation area. For example, the main deformation area can be the head of the train, that is, the area before the driver's cab and the energy absorption device installation surface. The non-main deformation area can be the car area.
[0073] For example, if two trains are chasing each other, the main deformation area may be the rear of the chased train, and the non-main deformation area may be other areas except the rear of the chased train.
[0074] In operation S230, the static strength simulation information of each train component in the static strength finite element model is matched with the collision simulation information of each train component to obtain model conversion information of the component to be updated.
[0075] According to an embodiment of the present disclosure, the static strength simulation information may include connection methods of various components in the train, material information of various components, etc.
[0076] According to an embodiment of the present disclosure, the model conversion information is information that the static strength simulation information of the component to be updated does not match the collision simulation information.
[0077] For example, the component to be updated is Q, and the model conversion information of Q may be material thickness, Poisson's ratio, and connection mode with component W.
[0078] In operation S240 , the intermediate finite element model is updated according to the model conversion information of the component to be updated to obtain a target collision simulation model.
[0079] According to an embodiment of the present disclosure, the intermediate finite element model is updated based on the collision simulation information of each component of the train to obtain a target collision simulation model.
[0080] According to an embodiment of the present disclosure, a static strength finite element model for static strength simulation of a train is obtained, and in response to the number of meshes in the static strength finite element model satisfying a threshold number of meshes in a collision simulation of the train, the area in the static strength finite element model that satisfies a preset collision condition is re-meshed to obtain an intermediate finite element model, thereby achieving re-meshing of the area that satisfies the preset collision condition on the established static strength finite element model to satisfy the threshold number of meshes in the collision simulation of the train.
[0081] The static strength simulation information of each train component in the static strength finite element model is matched with the collision simulation information of each train component to obtain the model conversion information of the components to be updated; then the components to be updated in the intermediate finite element model are updated according to the model conversion information to obtain the target collision simulation model, thereby quickly converting the static strength finite element model of the train into a collision simulation model. Without repeated modeling, the static strength and collision simulation analysis tasks of the train are normally realized, which shortens the modeling cycle of the collision simulation model and improves the simulation analysis efficiency of the train.
[0082] According to an embodiment of the present disclosure, collision simulation information includes component material information, component welding point information and collision scene information; updating the intermediate finite element model according to the model conversion information of the component to be updated to obtain a target collision simulation model includes: the model conversion information for the component to be updated includes component material information, and the intermediate finite element model is updated with the component material information to obtain a material update simulation model; the model conversion information for the component to be updated also includes component welding point information, and the material update simulation model is updated with the component welding point information to obtain a welding point update simulation model; the collision scene of the welding point update simulation model is set according to the collision scene information in the collision simulation information to obtain a target collision simulation model.
[0083] According to an embodiment of the present disclosure, the component material information includes information related to the material mechanics of the component, such as material density, yield strength, Poisson's ratio, and the like.
[0084] According to an embodiment of the present disclosure, the component welding point information may include welding joints, the number of component welding points, etc.
[0085] According to an embodiment of the present disclosure, the collision scene information may include the collision mode, collision vehicle speed, collision direction, collision train number, etc.
[0086] For example, if the model conversion information of the component to be updated does not include component material information, the model conversion information of the component to be updated may directly include component welding point information, and the weld points of the intermediate finite element model are updated according to the component welding point information to obtain a welding point update simulation model; the collision scene of the welding point update simulation model is set according to the collision scene information in the collision simulation information to obtain a target collision simulation model.
[0087] For example, due to the different types and implementation methods of the spot welding units of the static strength finite element model and the collision simulation model, they cannot be used directly. However, due to the large number of welds, recreating the spot welding units suitable for collision simulation will consume a lot of time and energy, and lose the time cost saving effect of borrowing the static strength finite element model. Therefore, the component weld information can be directly called to update the welds of the material update simulation model or the intermediate finite element model to obtain the weld update simulation model.
[0088] According to an embodiment of the present disclosure, component material information includes material type and material properties corresponding to the material type; updating the material of the intermediate finite element model according to the component material information to obtain a material update simulation model includes: updating the material type of the intermediate finite element model according to the material type of the component to be updated to obtain an initial material update simulation model; updating the material properties of the initial material update simulation model according to the material properties corresponding to the material type to obtain a material update simulation model.
[0089] According to an embodiment of the present disclosure, the material type may be an elastic material, a plastic material, a brittle material, a composite material, a viscoelastic material, etc. For example, the elastic material may be steel, the plastic material may be plastic, the composite material may be a carbon fiber composite material, and the viscoelastic material may be rubber.
[0090] According to an embodiment of the present disclosure, the material property may be elastic modulus, Poisson's ratio, yield strength, tensile strength, density, internal friction coefficient, impact toughness, storage modulus, etc.
[0091] According to an embodiment of the present disclosure, the intermediate finite element model is updated with a material type according to the material type of the component to be updated to obtain an initial material update simulation model. Then, the material properties of the initial material update simulation model are updated according to the material properties corresponding to the material type to obtain a material update simulation model, so as to quickly and accurately update the material of the intermediate finite element model.
[0092] According to an embodiment of the present disclosure, component weld information includes weld position and the number of components connected to the weld position; performing weld updating on a material update simulation model according to the component weld information to obtain a weld update simulation model includes: regenerating weld units of the material update simulation model according to the weld position in the collision simulation information to obtain an initial weld update simulation model; updating the number of layers connected to each weld position in the initial weld update simulation model according to the number of components connected to the weld position to obtain a weld update simulation model.
[0093] According to the embodiments of the present disclosure, due to the different types and implementation methods of the spot welding units of the static strength finite element model and the collision simulation model, it is difficult to use them directly. However, due to the large number of welds, it will take a lot of time and effort to recreate the spot welding units suitable for collision simulation, which lacks the advantage of saving time cost by borrowing the static strength finite element model. Therefore, the weld unit of the material update simulation model is regenerated according to the weld position in the collision simulation information to obtain the initial weld update simulation model.
[0094] According to an embodiment of the present disclosure, the weld point unit of the material update simulation model is used to simulate the behavior of the weld joint.
[0095] According to an embodiment of the present disclosure, the number of components connected to the soldering point position is associated with the number of layers connected to each soldering point position. For example, the number of layers connected to each soldering point position is the same as the number of components connected to the soldering point position.
[0096] Figure 4A A schematic diagram of welding two components in a finite element simulation model according to an embodiment of the present disclosure is schematically shown.
[0097] like Figure 4A As shown, the number of layers connected to the welding point position is 2, the number of components connected to the welding point position is also 2, and the components connected to the welding point position are component 1 and component 2 respectively.
[0098] Figure 4B A schematic diagram of welding three components in a finite element simulation model according to an embodiment of the present disclosure is schematically shown.
[0099] like Figure 4B As shown in the figure, the number of layers connected to the welding point position is 3, the number of components connected to the welding point position is also 3, and the components connected to the welding point position are component 1, component 2, and component 3. Usually, for welding points with 3 layers or more, when the static strength finite element model is converted to the collision simulation model, the number of layers is often lost. Therefore, according to the correlation between the number of components connected to the welding point position and the number of layers connected to each welding point position, the number of layers connected to each welding point position in the initial welding point update simulation model can be directly updated.
[0100] According to the embodiments of the present disclosure, the weld point unit of the material update simulation model is regenerated according to the weld point position in the collision simulation information to obtain the initial weld point update simulation model, which greatly reduces the time of establishing the collision simulation model. Then, according to the number of components connected to the weld point position, the number of layers connected to each weld point position in the initial weld point update simulation model is updated to obtain the weld point update simulation model, so that the weld point update is more accurate.
[0101] According to an embodiment of the present disclosure, the collision scene information includes mechanical parameters and collision parameters between various components of the train; setting the collision scene of the weld update simulation model according to the collision scene information in the collision simulation information to obtain the target collision simulation model includes: according to the mechanical parameters between various components of the train in the collision simulation information, mechanically setting each component in the weld update simulation model to obtain a mechanical update simulation model; according to the collision parameters in the collision simulation information, setting the collision parameters of the mechanical update simulation model to obtain a target collision simulation model.
[0102] According to an embodiment of the present disclosure, the mechanical parameters may be contact load, component connection method, assembly requirements, etc.
[0103] According to an embodiment of the present disclosure, the collision parameters may be the collision mode, collision vehicle speed, collision direction, collision train number, etc.
[0104] According to an embodiment of the present disclosure, when converting a static strength finite element model to a collision simulation model, each carriage in the train can be converted in turn, and then the collision simulation model of each carriage in the train is obtained. The collision simulation models of each carriage are assembled to obtain a collision simulation model of the train, for example, the carriage is connected to components such as a bogie, a coupler, and an anti-climber. Then the train is marshaled, the collision parameters are set, and the collision simulation model of the train is checked. When the inspection result indicates that the information of each component in the collision simulation model of the train matches the collision simulation information, the target collision simulation model is obtained.
[0105] According to an embodiment of the present disclosure, mechanical settings are performed on components in a welding point update simulation model according to mechanical parameters between various components of a train in collision simulation information to obtain a mechanical update simulation model, so as to obtain a finite element simulation model of the entire train; then, collision parameters are set for the mechanical update simulation model according to collision parameters in the collision simulation information to obtain a target collision simulation model, so as to use the target collision simulation model for train collision analysis, thereby shortening the time for re-establishing the collision simulation model and improving the analysis efficiency of the train collision simulation.
[0106] According to an embodiment of the present disclosure, the area that meets the preset collision conditions includes the middle area between multiple sleeper beam components of the train; re-meshing the area that meets the preset collision conditions in the static strength finite element model to obtain the intermediate finite element model includes: re-meshing the middle area between the multiple sleeper beam components in the static strength finite element model.
[0107] Figure 5A A schematic diagram of an intermediate area between two bolster components in a train according to an embodiment of the present disclosure is schematically shown.
[0108] like Figure 5A As shown, the front and rear of a train are usually collision deformation areas in a collision simulation.
[0109] The outer area of the bolster in the train is the end area at the front and rear ends of the vehicle. It may collide with other vehicles or obstacles and deform during the collision. To ensure the simulation accuracy, the unit size cannot be too large, so it is not re-meshed. At the same time, the outer area of the bolster generally has a complex structure, which is troublesome and time-consuming to re-mesh, which is not conducive to the purpose of rapid model conversion.
[0110] According to an embodiment of the present disclosure, the intermediate area between the plurality of bolster components in the static strength finite element model is re-meshed, so as to achieve a rapid conversion from the static strength finite element model to the collision simulation model without affecting the collision simulation accuracy.
[0111] According to an embodiment of the present disclosure, re-gridding the middle area between multiple sleeper beam components in the static strength finite element model also includes: determining a sub-area with an annular structure from the middle area between the multiple sleeper beam components of the train; and reducing the longitudinal grid unit density of the sub-area with the annular structure.
[0112] According to the embodiments of the present disclosure, the annular structure can be a complete annular structure or a semi-annular structure. The sub-region with an annular structure is only connected to the regions in front and behind it, so simply reducing the density of the mesh units in the longitudinal direction in the annular region to reduce the number of meshes is convenient and quick to process, and will not cause the annular structure region and the connected structure to generate triangular units or other irregular units due to the change in unit density, resulting in unqualified mesh quality.
[0113] Figure 5B A schematic diagram of a sub-area having a complete ring structure in a train according to an embodiment of the present disclosure is schematically shown.
[0114] like Figure 5B As shown, exemplarily, a target sub-region between two annular structures in a sub-region with a complete annular structure is first determined, and the grid cell density in the longitudinal direction of the target region is reduced, while the grid cell density in the lateral direction of the target region remains unchanged.
[0115] Figure 5C A schematic diagram of a sub-area having a semi-annular structure in a train according to an embodiment of the present disclosure is schematically shown.
[0116] like Figure 5C As shown, exemplarily, the upper sub-region in the sub-region having the semi-annular structure is first determined, and the grid unit density in the longitudinal direction of the upper sub-region is reduced, while the grid unit density in the lateral direction of the upper sub-region remains unchanged.
[0117] It should be noted that the complete ring structure and the semi-ring structure can be considered comprehensively. Figure 5B The target sub-region between the two annular structures, the upper sub-region in the sub-region of the semi-annular structure, and the lower sub-region in the sub-region of the semi-annular structure can be simultaneously divided, making it more efficient to re-mesh the middle region between multiple pillow block components in the static strength finite element model.
[0118] According to an embodiment of the present disclosure, a sub-region with an annular structure is determined from a middle region between a plurality of sleeper beam components of a train; the longitudinal grid unit density of the sub-region with annular structure is reduced, so that the method of reducing the number of grids is more accurate and efficient.
[0119] According to an embodiment of the present disclosure, the area that meets the preset collision conditions also includes a rib plate component area, and the rib plate is located inside the train component and is not connected to other components; the area that meets the preset collision conditions in the static strength finite element model is re-meshed to obtain an intermediate finite element model including: reducing the grid unit density in a preset direction of the rib plate area, and the preset direction is the direction in which the rib plate is connected to the inside of the train component.
[0120] Fig. 6A A schematic diagram schematically shows the direction in which the rib plate is connected to the interior of a train component according to an embodiment of the present disclosure.
[0121] like Fig. 6A As shown, the red arrow indicates the direction of the connection between the rib plate and the internal components of the train.
[0122] Figure 6B A schematic diagram of reducing the grid unit density in a preset direction of a rib plate area according to an embodiment of the present disclosure is schematically shown.
[0123] like Figure 6B As shown, the mesh unit density in the preset direction of the rib plate area is reduced, so that the number of meshes in the rib plate area is reduced.
[0124] According to the embodiments of the present disclosure, most of the ribs are located inside the train components and are basically not welded to other adjacent components. Reducing the density of the grid units in the connection direction between the ribs and the inside of the components can reduce the number of grids, which is convenient and quick to operate. Since there are many ribs, reducing the number of rib grids can effectively reduce the number of grids in the train.
[0125] The train collision simulation analysis performed through the train finite element model conversion method can greatly shorten the time cycle and greatly reduce the time cost. At the same time, it can unify the modeling standards of the static strength finite element model and the collision simulation model to the maximum extent, reduce the errors caused by different modeling, and improve the simulation accuracy.
[0126] Figure 7 A flow chart of a finite element model conversion method for a train according to another embodiment of the present disclosure is schematically shown.
[0127] like Figure 7 As shown, the method includes operations S710~S790.
[0128] In operation S710 , a static strength finite element model for performing static strength simulation on a train is obtained.
[0129] In operation S720, it is determined whether the number of meshes of the static strength finite element model meets the threshold of the number of meshes in the train collision simulation. If so, operation S730 is performed; if not, operation S760 is performed.
[0130] In operation S730, a sub-region having a ring structure is determined from within a middle region between a plurality of bolster members of a train.
[0131] In operation S740, a density of mesh cells in a longitudinal direction of the sub-region having the ring structure is reduced.
[0132] In operation S750, the density of grid cells in a preset direction of the rib plate region is reduced, where the preset direction is a direction in which the rib plate is connected to an internal part of a train component.
[0133] In operation S760, the static strength simulation information of each train component in the static strength finite element model is matched with the collision simulation information of each train component to obtain model conversion information of the component to be updated.
[0134] In operation S770, the model conversion information of the component to be updated includes component material information, and the intermediate finite element model is material updated according to the component material information to obtain a material updated simulation model.
[0135] In operation S780, the model conversion information for the component to be updated also includes component welding point information, and the welding points of the material update simulation model are updated according to the component welding point information to obtain a welding point update simulation model.
[0136] In operation S790, a collision scene of a simulation model is updated by setting a welding point according to the collision scene information in the collision simulation information to obtain a target collision simulation model.
[0137] According to an embodiment of the present disclosure, a static strength finite element simulation model and a collision simulation model of a train may be performed on the same simulation modeling tool.
[0138] For matching the static strength simulation information of each train component in the static strength finite element model with the collision simulation information of each train component, the model conversion information of the component to be updated is relatively small. For example, the model conversion information only includes the welding point position of a component. Or, after the collision simulation model is established, different collision scene information needs to be set. The simulation parameter adjustment interface can be set on the simulation modeling tool to realize the visual adjustment of the collision simulation information.
[0139] Figure 8 An interface diagram for setting collision simulation parameters in a finite element model conversion method for a train according to an embodiment of the present disclosure is schematically shown.
[0140] like Figure 8 As shown, in order to facilitate users to visualize the finite element model conversion process, an interface diagram for collision simulation parameter settings can be designed on the simulation modeling tool.
[0141] The interface is based on components, which can be carriages, bolsters, etc. In case users need to design collision simulation information in a personalized way, on the collision simulation parameter setting interface, users can update the material, welding points, collision scenarios, etc. of the static strength finite element simulation model of the component. Users can view the updated collision simulation model of the component in the component display area.
[0142] Fig. 9 A block diagram of a finite element model conversion device for a train according to an embodiment of the present disclosure is schematically shown.
[0143] like Fig. 9 As shown, the finite element model conversion device 900 of a train includes an acquisition module 910 , a meshing module 920 , a matching module 930 , and an updating module 940 .
[0144] The acquisition module 910 is used to acquire a static strength finite element model for performing static strength simulation on a train. In one embodiment, the acquisition module 910 can be used to perform the operation S210 described above, which will not be described in detail here.
[0145] The meshing module 920 is used to re-mesh the area in the static strength finite element model that meets the preset collision condition in response to the number of meshes in the static strength finite element model meeting the mesh number threshold in the train collision simulation to obtain an intermediate finite element model. In one embodiment, the meshing module 920 can be used to perform the operation S220 described above, which will not be repeated here.
[0146] The matching module 930 is used to match the static strength simulation information of each train component in the static strength finite element model with the collision simulation information of each train component to obtain model conversion information of the component to be updated, and the model conversion information is information that the static strength simulation information and the collision simulation information of the component to be updated do not match. In one embodiment, the matching module 930 can be used to perform the operation S230 described above, which will not be repeated here.
[0147] The updating module 940 is used to update the components to be updated in the intermediate finite element model according to the model conversion information to obtain the target collision simulation model. In one embodiment, the updating module 940 can be used to perform the operation S240 described above, which will not be described in detail here.
[0148] According to an embodiment of the present disclosure, the collision simulation information includes component material information, component welding point information and collision scene information; the update module 940 includes a first update submodule, a second update submodule and a setting submodule. The first update submodule is used for the model conversion information of the component to be updated including component material information, and updating the material of the intermediate finite element model according to the component material information to obtain a material update simulation model. The second update submodule is used for the model conversion information of the component to be updated also including component welding point information, and updating the welding points of the material update simulation model according to the component welding point information to obtain a welding point update simulation model. The setting submodule is used to set the collision scene of the welding point update simulation model according to the collision scene information in the collision simulation information to obtain a target collision simulation model.
[0149] According to an embodiment of the present disclosure, the component material information includes a material type and a material property corresponding to the material type. The second update submodule includes a first update unit and a second update unit. The first update unit is used to update the material type of the intermediate finite element model according to the material type of the component to be updated, and obtain an initial material update simulation model. The second update unit is used to update the material property of the initial material update simulation model according to the material property corresponding to the material type, and obtain a material update simulation model.
[0150] According to an embodiment of the present disclosure, the component weld information includes the weld position and the number of components connected to the weld position. The setting submodule includes a regeneration unit and a third update unit. The regeneration unit is used to regenerate the weld unit of the material update simulation model according to the weld position in the collision simulation information to obtain the initial weld update simulation model. The third update unit is used to update the number of layers connected to each weld position in the initial weld update simulation model according to the number of components connected to the weld position to obtain the weld update simulation model.
[0151] According to an embodiment of the present disclosure, the collision scene information includes mechanical parameters and collision parameters between various components of the train; the setting submodule includes a mechanical setting unit and a collision parameter setting unit. The mechanical setting unit is used to perform mechanical settings on various components in the welding point update simulation model according to the mechanical parameters between various components of the train in the collision simulation information, so as to obtain a mechanical update simulation model. The collision parameter setting unit is used to perform collision parameter settings on the mechanical update simulation model according to the collision parameters in the collision simulation information, so as to obtain a target collision simulation model.
[0152] According to an embodiment of the present disclosure, the area satisfying the preset collision condition includes the middle area between the plurality of bolster components of the train; the meshing module 920 includes a first meshing submodule. The first meshing submodule is used to re-mesh the middle area between the plurality of bolster components in the static strength finite element model.
[0153] According to an embodiment of the present disclosure, the first grid division submodule further includes a determination unit and a first grid division unit. The determination unit is used to determine a subregion having an annular structure from an intermediate region between a plurality of bolster components of the train. The first grid division unit is used to reduce a longitudinal grid unit density of the subregion having an annular structure.
[0154] According to an embodiment of the present disclosure, the area that meets the preset collision condition also includes a rib plate component area, where the rib plate is located inside the component of the train and is not connected to other components. The meshing module 920 includes a second meshing submodule. The second meshing submodule is used to reduce the grid unit density of the rib plate area in a preset direction, where the preset direction is the direction in which the rib plate is connected to the inside of the component of the train.
[0155] According to the embodiments of the present invention, any one or more of the modules, submodules, units, and subunits, or at least part of the functions of any one of them can be implemented in one module. According to the embodiments of the present invention, any one or more of the modules, submodules, units, and subunits can be split into multiple modules for implementation. According to the embodiments of the present invention, any one or more of the modules, submodules, units, and subunits can be at least partially implemented as hardware circuits, such as field programmable gate arrays (FPGAs), programmable logic arrays (PLAs), systems on chips, systems on substrates, systems on packages, application specific integrated circuits (ASICs), or can be implemented by hardware or firmware in any other reasonable way of integrating or packaging circuits, or can be implemented in any one of the three implementation methods of software, hardware, and firmware, or in any appropriate combination of any of them. Alternatively, according to the embodiments of the present invention, one or more of the modules, submodules, units, and subunits can be at least partially implemented as computer program modules, and when the computer program modules are run, the corresponding functions can be performed.
[0156] For example, any multiple of the acquisition module 910, the meshing module 920, the matching module 930, and the update module 940 can be combined in one module / unit / sub-unit for implementation, or any one of the modules / units / sub-units can be split into multiple modules / units / sub-units. Alternatively, at least part of the functions of one or more of these modules / units / sub-units can be combined with at least part of the functions of other modules / units / sub-units and implemented in one module / unit / sub-unit. According to an embodiment of the present disclosure, at least one of the acquisition module 910, the meshing module 920, the matching module 930, and the update module 940 can be at least partially implemented as a hardware circuit, such as a field programmable gate array (FPGA), a programmable logic array (PLA), a system on a chip, a system on a substrate, a system on a package, an application specific integrated circuit (ASIC), or can be implemented by hardware or firmware such as any other reasonable way of integrating or packaging the circuit, or implemented in any one of the three implementation modes of software, hardware, and firmware or in any appropriate combination of any of them. Alternatively, at least one of the acquisition module 910, the meshing module 920, the matching module 930, and the updating module 940 may be at least partially implemented as a computer program module, and when the computer program module is executed, a corresponding function may be performed.
[0157] It should be noted that the finite element model conversion device part of the train in the embodiment of the present disclosure corresponds to the finite element model conversion method part of the train in the embodiment of the present disclosure. The description of the finite element model conversion device part of the train specifically refers to the finite element model conversion method part of the train, which will not be repeated here.
[0158] Fig.10 A block diagram of an electronic device suitable for implementing a finite element model conversion method for a train according to an embodiment of the present disclosure is schematically shown.
[0159] like Fig.10 As shown, the electronic device 1000 according to an embodiment of the present disclosure includes a processor 1001, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 1002 or a program loaded from a storage part 1008 to a random access memory (RAM) 1003. The processor 1001 may include, for example, a general-purpose microprocessor (such as a CPU), an instruction set processor and / or a related chipset and / or a special-purpose microprocessor (for example, an application-specific integrated circuit (ASIC)), etc. The processor 1001 may also include an onboard memory for caching purposes. The processor 1001 may include a single processing unit or multiple processing units for performing different actions of the method flow according to an embodiment of the present disclosure.
[0160] In RAM 1003, various programs and data required for the operation of electronic device 1000 are stored. Processor 1001, ROM 1002 and RAM 1003 are connected to each other via bus 1004. Processor 1001 performs various operations of the method flow according to the embodiment of the present disclosure by executing the program in ROM 1002 and / or RAM 1003. It should be noted that the program can also be stored in one or more memories other than ROM 1002 and RAM 1003. Processor 1001 can also perform various operations of the method flow according to the embodiment of the present disclosure by executing the program stored in the one or more memories.
[0161] According to an embodiment of the present disclosure, the electronic device 1000 may further include an input / output (I / O) interface 1005, which is also connected to the bus 1004. The electronic device 1000 may further include one or more of the following components connected to the input / output (I / O) interface 1005: an input portion 1006 including a keyboard, a mouse, etc.; an output portion 1007 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage portion 1008 including a hard disk, etc.; and a communication portion 1009 including a network interface card such as a LAN card, a modem, etc. The communication portion 1009 performs communication processing via a network such as the Internet. A drive 1010 is also connected to the input / output (I / O) interface 1005 as needed. A removable medium 1011, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 1010 as needed, so that a computer program read therefrom is installed into the storage portion 1008 as needed.
[0162] According to an embodiment of the present disclosure, the method flow according to an embodiment of the present disclosure can be implemented as a computer software program. For example, an embodiment of the present disclosure includes a computer program product, which includes a computer program carried on a computer-readable storage medium, and the computer program contains a program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from the network through the communication part 1009, and / or installed from the removable medium 1011. When the computer program is executed by the processor 1001, the above-mentioned functions defined in the system of the embodiment of the present disclosure are executed. According to an embodiment of the present disclosure, the system, equipment, device, module, unit, etc. described above can be implemented by a computer program module.
[0163] The present disclosure also provides a computer-readable storage medium, which may be included in the device / apparatus / system described in the above embodiments; or may exist independently without being assembled into the device / apparatus / system. The above computer-readable storage medium carries one or more programs, and when the above one or more programs are executed, the method according to the embodiment of the present disclosure is implemented.
[0164] According to an embodiment of the present disclosure, the computer-readable storage medium may be a non-volatile computer-readable storage medium. For example, it may include, but is not limited to: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In the present disclosure, a computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in combination with an instruction execution system, apparatus, or device.
[0165] For example, according to an embodiment of the present disclosure, the computer-readable storage medium may include the ROM 1002 and / or the RAM 1003 described above and / or one or more memories other than the ROM 1002 and the RAM 1003 .
[0166] An embodiment of the present disclosure also includes a computer program product, which includes a computer program, and the computer program contains a program code for executing the method provided by the embodiment of the present disclosure. When the computer program product runs on an electronic device, the program code is used to enable the electronic device to implement the finite element model conversion method of the train provided by the embodiment of the present disclosure.
[0167] When the computer program is executed by the processor 1001, the above functions defined in the system / device of the embodiment of the present disclosure are executed. According to the embodiment of the present disclosure, the system, device, module, unit, etc. described above can be implemented by a computer program module.
[0168] In one embodiment, the computer program may rely on tangible storage media such as optical storage devices, magnetic storage devices, etc. In another embodiment, the computer program may also be transmitted and distributed in the form of signals on a network medium, and downloaded and installed through the communication part 1009, and / or installed from the removable medium 1011. The program code contained in the computer program may be transmitted using any appropriate network medium, including but not limited to: wireless, wired, etc., or any suitable combination of the above.
[0169] According to an embodiment of the present disclosure, the program code for executing the computer program provided by the embodiment of the present disclosure can be written in any combination of one or more programming languages. Specifically, these computing programs can be implemented using high-level process and / or object-oriented programming languages, and / or assembly / machine languages. Programming languages include, but are not limited to, Java, C++, python, "C" language or similar programming languages. The program code can be executed entirely on the user computing device, partially on the user device, partially on the remote computing device, or entirely on the remote computing device or server. In the case of a remote computing device, the remote computing device can be connected to the user computing device through any type of network, including a local area network (LAN) or a wide area network (WAN), or can be connected to an external computing device (for example, using an Internet service provider to connect through the Internet).
[0170] The flowcharts and block diagrams in the accompanying drawings illustrate the possible implementation architecture, functions and operations of the systems, methods and computer program products according to various embodiments of the present disclosure. In this regard, each box in the flowchart or block diagram may represent a module, a program segment, or a part of a code, and the above-mentioned module, program segment, or a part of the code contains one or more executable instructions for implementing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box may also occur in an order different from that marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram or flowchart, and the combination of boxes in the block diagram or flowchart, can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions. It can be understood by those skilled in the art that the features recorded in the various embodiments of the present disclosure can be combined and / or combined in a variety of ways, even if such a combination or combination is not explicitly recorded in the present disclosure. In particular, without departing from the spirit and teaching of the present disclosure, the features described in the various embodiments of the present disclosure may be combined and / or combined in a variety of ways. All of these combinations and / or combinations fall within the scope of the present disclosure.
[0171] The embodiments of the present disclosure are described above. However, these embodiments are only for illustrative purposes and are not intended to limit the scope of the present disclosure. Although the embodiments are described above, this does not mean that the measures in the various embodiments cannot be used in combination to advantage. Without departing from the scope of the present disclosure, those skilled in the art may make a variety of substitutions and modifications, which should all fall within the scope of the present disclosure.
Claims
1. A finite element model conversion method for a train, comprising: Obtaining a static strength finite element model for static strength simulation of a train; In response to the number of meshes of the static strength finite element model satisfying a threshold of the number of meshes in the collision simulation of the train, re-meshing the area of the static strength finite element model that satisfies a preset collision condition to obtain an intermediate finite element model; Matching static strength simulation information of each train component in the static strength finite element model with collision simulation information of each train component to obtain model conversion information of the component to be updated, wherein the model conversion information is information that the static strength simulation information and the collision simulation information of the component to be updated do not match; The intermediate finite element model is updated according to the model conversion information of the component to be updated to obtain a target collision simulation model.
2. The method according to claim 1, wherein: The collision simulation information includes component material information, component welding point information and collision scene information; The updating of the intermediate finite element model according to the model conversion information of the component to be updated to obtain the target collision simulation model comprises: The model conversion information for the component to be updated includes the component material information, and the intermediate finite element model is material updated according to the component material information to obtain a material updated simulation model; The model conversion information for the component to be updated also includes the component welding point information, and the welding points of the material update simulation model are updated according to the component welding point information to obtain a welding point update simulation model; The collision scene of the welding point update simulation model is set according to the collision scene information in the collision simulation information to obtain the target collision simulation model.
3. The method according to claim 2, wherein: The component material information includes material type and material properties corresponding to the material type; The updating of the material of the intermediate finite element model according to the component material information to obtain the material updated simulation model comprises: Update the material type of the intermediate finite element model according to the material type of the component to be updated to obtain an initial material update simulation model; The material properties of the initial material update simulation model are updated according to the material properties corresponding to the material type to obtain a material update simulation model.
4. The method according to claim 2, wherein: The component welding point information includes the welding point position and the number of components connected to the welding point position; The updating of the welding points of the material updating simulation model according to the welding point information of the component to obtain the welding point updating simulation model comprises: Regenerate the weld point unit of the material update simulation model according to the weld point position in the collision simulation information to obtain an initial weld point update simulation model; According to the number of components connected to the soldering point position, the number of layers connected to each soldering point position in the initial soldering point update simulation model is updated to obtain a soldering point update simulation model.
5. The method according to any one of claims 2 to 4, wherein The collision scene information includes mechanical parameters and collision parameters between various components of the train; The step of setting the collision scene of the welding point update simulation model according to the collision scene information in the collision simulation information to obtain the target collision simulation model comprises: According to the mechanical parameters between the various train components in the collision simulation information, mechanical settings are performed on the various components in the welding point update simulation model to obtain a mechanical update simulation model; According to the collision parameters in the collision simulation information, collision parameters are set for the mechanical update simulation model to obtain the target collision simulation model.
6. The method according to claim 1, wherein: The area satisfying the preset collision condition includes the middle area between the plurality of bolster components of the train; The re-gridding of the area satisfying the preset collision condition in the static strength finite element model to obtain the intermediate finite element model comprises: Re-meshing the middle area between the plurality of bolster components in the static strength finite element model.
7. The method according to claim 6, wherein: The re-meshing of the middle area between the plurality of bolster components in the static strength finite element model further includes: determining a sub-region having an annular structure from a middle region between a plurality of bolster members of the train; The density of grid cells in the longitudinal direction of the sub-region having the annular structure is reduced.
8. The method according to claim 1, wherein: The area satisfying the preset collision condition also includes a rib plate component area, wherein the rib plate is located inside the component of the train and is not connected to other components; The re-gridding of the area satisfying the preset collision condition in the static strength finite element model to obtain the intermediate finite element model comprises: The grid cell density of the rib plate region in a preset direction is reduced, wherein the preset direction is the direction in which the rib plate is connected to the interior of the train component.
9. A finite element model conversion device for a train, comprising: An acquisition module, used for acquiring a static strength finite element model for performing static strength simulation on a train; A meshing module, configured to re-mesh the area of the static strength finite element model that meets a preset collision condition in response to the number of meshes of the static strength finite element model meeting a mesh number threshold in the collision simulation of the train, to obtain an intermediate finite element model; A matching module, used for matching the static strength simulation information of each train component in the static strength finite element model with the collision simulation information of each train component to obtain model conversion information of the component to be updated, wherein the model conversion information is information that the static strength simulation information and the collision simulation information of the component to be updated do not match; An updating module is used to update the to-be-updated components in the intermediate finite element model according to the model conversion information to obtain a target collision simulation model.
10. An electronic device comprising: one or more processors; a storage device for storing one or more programs, When the one or more programs are executed by the one or more processors, the one or more processors execute the method according to any one of claims 1 to 8.