Urban rail transit simulation drill intelligent assessment system
By introducing submodules of suspension, forced stop, delay and passenger flow indicators in the urban rail transit simulation drill intelligent assessment system, the problem of inadequate assessment in the existing technology is solved, and a comprehensive and accurate assessment of driving dispatchers is achieved. It has improved the scientificity and practicality of the assessment system.
Patent Information
- Application Number
- CN202410491242.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-23
- Publication Date
- 2024-11-15
AI Technical Summary
The existing urban rail transit assessment system focuses on the correctness assessment of dispatching operation steps, and fails to scientifically and reasonably assess driving dispatchers, especially in terms of suspension of operations, forced stops, delays and passenger flow indicators.
An intelligent assessment system for urban rail transit simulation drills was designed, including submodules of suspension, forced stop, delay and passenger flow indicators. By recording and calculating the scores of these indicators, the user's assessment scores are output, and the system can scientifically and reasonably evaluate driving. The operation effect of the dispatcher.
By including important driving indicators such as suspension of operations, forced stops, delays and passenger flow, the system can more accurately evaluate the operational performance of the driving dispatcher, improve the scientificity and practicality of the assessment, and ensure passenger travel experience and safety.
Smart Images

Figure CN118966852A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of transportation technology, and in particular to an intelligent assessment system for simulation exercises of urban rail transit. Background Art
[0002] At present, the assessment method for urban rail transit train dispatchers is mainly to assess the train dispatchers with the help of simulation signal systems and evaluation systems.
[0003] As a user of the assessment system, the train dispatcher can perform simulated dispatching operations through the assessment system to complete multiple assessment tasks with a preset order. The assessment system can assess the user according to the execution steps of the dispatching operations.
[0004] However, the current assessment system focuses on evaluating users based on the execution steps of scheduling operations, and pays attention to the correctness of the execution steps of scheduling operations in assessment tasks. The assessment method is not reasonable. Therefore, it is urgent to develop an efficient assessment system to conduct scientific and reasonable assessments on users. Summary of the invention
[0005] The present invention provides an intelligent assessment system for urban rail transit simulation drills, which is used to solve the defects in the prior art that there is a lack of an efficient assessment system and it is difficult to conduct scientific and reasonable assessments on users.
[0006] The present invention provides an intelligent assessment system for urban rail transit simulation drills, comprising an index evaluation module, which includes a suspension index submodule, an forced stop index submodule, a delay index submodule and a passenger flow index submodule; the suspension index submodule is used to determine a user's suspension index score; the forced stop index submodule is used to determine the user's forced stop index score; the delay index submodule is used to determine the user's delay index score; the passenger flow index submodule is used to determine the user's passenger flow index score; the index evaluation module is used to determine and output a user assessment score of a user based on the suspension index score, the forced stop index score, the delay index score and the passenger flow index score.
[0007] According to an intelligent assessment system for urban rail transit simulation drills provided by the present invention, the suspension index submodule includes a first recording submodule and a first calculation submodule; the first recording submodule is used to obtain and record the user's suspension operation information; the suspension operation information is generated based on the user's suspension operation when performing the assessment task; the first calculation submodule is used to determine the user's suspension index score based on the suspension operation information.
[0008] According to an intelligent assessment system for urban rail transit simulation drills provided by the present invention, the forced stop index submodule includes a second recording submodule and a second calculation submodule; the second recording submodule is used to obtain and record the user's forced stop operation information; the forced stop operation information is generated based on the user's forced stop operation when performing the assessment task; the second calculation submodule is used to determine the user's forced stop index score based on the forced stop operation information.
[0009] According to an intelligent assessment system for urban rail transit simulation drills provided by the present invention, the delay index submodule includes a third recording submodule and a third calculation submodule; the third recording submodule is used to obtain and record the user's delay operation information; the delay operation information is generated based on the user's delay operation when performing the assessment task; the third calculation submodule is used to determine the user's delay index score based on the delay operation information.
[0010] According to an intelligent assessment system for urban rail transit simulation drills provided by the present invention, the passenger flow index submodule includes a fourth recording submodule and a fourth calculation submodule; the fourth recording submodule is used to obtain and record passenger flow information; the passenger flow information is determined based on the user's suspension operation, forced stop operation, and delay operation when performing the assessment task; the fourth calculation submodule is used to determine the user's passenger flow index score based on the passenger flow information.
[0011] According to the present invention, an urban rail transit simulation and drill intelligent assessment system also includes an operation step management module, which includes a first task sub-module and a second task sub-module; the first task sub-module is used to generate an assessment task with a preset order; the second task sub-module is used to generate an assessment task without a preset order.
[0012] The present invention provides an intelligent assessment system for urban rail transit simulation and drill, the system includes an index evaluation module, the index evaluation module includes a suspension index submodule, an forced stop index submodule, a delay index submodule and a passenger flow index submodule; the suspension index submodule is used to determine the suspension index score of the user; the forced stop index submodule is used to determine the forced stop index score of the user; the delay index submodule is used to determine the delay index score of the user; the passenger flow index submodule is used to determine the passenger flow index score of the user; the index evaluation module is used to determine and output the user assessment score of the user based on the suspension index score, the forced stop index score, the delay index score and the passenger flow index score. Since suspension, forced stop, delay and passenger flow are important driving indicators in urban rail transit operations and directly affect the travel experience and safety of passengers, the suspension index submodule, forced stop index submodule, delay index submodule and passenger flow index submodule are used to determine the user's suspension index score, forced stop index score, delay index score and passenger flow index score respectively, and the suspension, forced stop, delay, passenger flow and other driving indicators are included in the assessment scope, so that users can be assessed scientifically and reasonably, and the assessment system is efficient and practical. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0014] Figure 1 This is one of the structural schematic diagrams of the urban rail transit simulation drill intelligent assessment system provided by the present invention;
[0015] Figure 2 This is one of the flow charts of the intelligent assessment method for urban rail transit simulation drill provided by the present invention;
[0016] Figure 3 This is the second structural diagram of the urban rail transit simulation drill intelligent assessment system provided by the present invention;
[0017] Figure 4 This is the second flow chart of the intelligent assessment method for urban rail transit simulation drills provided by the present invention. DETAILED DESCRIPTION
[0018] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0019] The terms "first", "second", etc. in the present invention are used to distinguish similar objects, rather than to describe a specific order or sequence. It should be understood that the numbers used in this way can be interchanged where appropriate, so that the embodiments of the present invention can be implemented in an order other than those illustrated or described herein.
[0020] See also Figure 1 , Figure 1 It is one of the structural schematic diagrams of the urban rail transit simulation drill intelligent assessment system provided by the present invention.
[0021] In this embodiment, the urban rail transit simulation drill intelligent assessment system includes an indicator evaluation module.
[0022] The index evaluation module includes a suspension index submodule, an forced stop index submodule, a delay index submodule and a passenger flow index submodule.
[0023] The outage index submodule is used to determine the user's outage index score.
[0024] In this embodiment, the user is a traffic dispatcher to be assessed.
[0025] The urban rail transit simulation and drill intelligent assessment system can generate assessment tasks based on the preset train plan operation diagram. Users can send instructions to the urban rail transit simulation and drill intelligent assessment system to perform simulated scheduling operations through the urban rail transit simulation and drill intelligent assessment system, thereby completing the assessment tasks on the urban rail transit simulation and drill intelligent assessment system and simulating the operation of the train when the user participates in the scheduling.
[0026] Suspension of service refers to the phenomenon that trains are suspended due to changes in operation or suspension of operation.
[0027] Specifically, the suspension index submodule can be used to detect the suspension operations performed by the user during the execution of the assessment task. Executing the suspension operation can simulate the train suspension situation on the system; the suspension index submodule can obtain and record the simulated train suspension situation on the system, generate suspension operation information, and determine the user's suspension index score based on the suspension operation information.
[0028] The emergency stop index submodule is used to determine the emergency stop index score of the user.
[0029] Forced stop refers to the situation where the train stops at a non-stop point.
[0030] Specifically, the forced stop index submodule can be used to detect the forced stop operation performed by the user during the execution of the assessment task. Performing the forced stop operation can simulate the forced stop of the train on the system; the forced stop index submodule can obtain and record the forced stop of the train simulated on the system, generate the forced stop operation information, and determine the user's forced stop index score based on the forced stop operation information.
[0031] The delay index submodule is used to determine the user's delay index score.
[0032] Delay refers to the phenomenon that the actual running time of the simulated train is later than the planned time in the train schedule.
[0033] Specifically, the delay index submodule can be used to detect the user's delayed operations during the performance of the assessment task. Delay operations refer to operations that cause train delays due to improper user operations. Performing delay operations can simulate train delays on the system. The delay index submodule can obtain and record the simulated train delays on the system, generate delay operation information, and determine the user's delay index score based on the delay operation information.
[0034] The passenger flow index submodule is used to determine the passenger flow index score of the user.
[0035] Generally, after the user completes the assessment task, the urban rail transit simulation drill intelligent assessment system can simulate the passenger flow conditions of each platform that the train passes through and generate passenger flow information for each platform.
[0036] It can be understood that passenger flow conditions are related to the user's suspension operations, forced stop operations, and delay operations when performing assessment tasks. Each dispatching operation of the user will affect the operation of the train, thereby affecting the passenger flow transportation at each platform. Therefore, passenger flow information can be determined based on the user's suspension operations, forced stop operations, and delay operations when performing assessment tasks.
[0037] Furthermore, the passenger flow index submodule may determine a passenger flow index score of the user based on the passenger flow information.
[0038] Furthermore, after determining the user's suspension index score, forced stop index score, delay index score and passenger flow index score, the index evaluation module can be used to determine and output the user's user assessment score based on the suspension index score, forced stop index score, delay index score and passenger flow index score.
[0039] The present embodiment provides an intelligent assessment system, method, device and medium for urban rail transit simulation drills. The system includes an index evaluation module, which includes a suspension index sub-module, an forced stop index sub-module, a delay index sub-module and a passenger flow index sub-module; the suspension index sub-module is used to determine the user's suspension index score; the forced stop index sub-module is used to determine the user's forced stop index score; the delay index sub-module is used to determine the user's delay index score; the passenger flow index sub-module is used to determine the user's passenger flow index score; the index evaluation module is used to determine and output the user's user assessment score based on the suspension index score, the forced stop index score, the delay index score and the passenger flow index score. Since suspension, forced stop, delay and passenger flow are important driving indicators in urban rail transit operations and directly affect the travel experience and safety of passengers, the suspension index submodule, forced stop index submodule, delay index submodule and passenger flow index submodule are used to determine the user's suspension index score, forced stop index score, delay index score and passenger flow index score respectively, and the suspension, forced stop, delay, passenger flow and other driving indicators are included in the assessment scope, so that users can be assessed scientifically and reasonably, and the assessment system is efficient and practical.
[0040] In some embodiments, the outage index submodule includes a first recording submodule and a first calculation submodule.
[0041] The first recording submodule is used to obtain and record the user's shutdown operation information; the shutdown operation information is generated based on the user's shutdown operation when performing the assessment task.
[0042] Among them, the suspension operation information includes the single train suspension deduction points and suspended train information corresponding to each train.
[0043] The first calculation submodule is used to determine the outage index score of the user based on the outage operation information.
[0044] The outage index score is a deduction item for the assessment. The calculation formula for the outage index score is as follows:
[0045]
[0046] Among them, S out represents the outage index score; K out Indicates that a single train is suspended and points are deducted; Represents the information of suspended trains; n represents the total number of trains; i represents the i-th train.
[0047] In some embodiments, the forced stop indicator submodule includes a second recording submodule and a second calculation submodule.
[0048] The second recording submodule is used to obtain and record the user's forced stop operation information; the forced stop operation information is generated based on the user's forced stop operation when performing the assessment task.
[0049] The forced stop operation information includes the total forced stop time and forced stop train information of each train.
[0050] The second calculation submodule is used to determine the user's forced stop index score based on the forced stop operation information.
[0051] The forced stop index score is a deduction item for the assessment. The calculation formula for the forced stop index score is as follows:
[0052]
[0053]
[0054] in, S represents the penalty points for the forced stop of the nth train; stop represents the suspension index score, which is the sum of the forced stop penalty points of all trains; L1 represents the first forced stop penalty point threshold; L2 represents the second forced stop penalty point threshold; t n K represents the total time of the emergency stop of the nth train; stop1 represents the forced stop deduction points corresponding to the first forced stop deduction points threshold; K stop2 Indicates the forced stop deduction points corresponding to the second forced stop deduction point threshold.
[0055] It can be understood that for each train, if the train makes an emergency stop in multiple time periods, the emergency stop time of the train will be accumulated.
[0056] In some embodiments, the delay indicator submodule includes a third recording submodule and a third calculation submodule.
[0057] The third recording submodule is used to obtain and record the user's late operation information; the late operation information is generated based on the user's late operation when performing the assessment task.
[0058] The delay operation information includes the total delay time of each train at different time points.
[0059] The third calculation submodule is used to determine the user's delay index score based on the delay operation information.
[0060] The lateness index score is a deduction item for the assessment. The calculation formula for the lateness index score is as follows:
[0061]
[0062]
[0063] in, S represents the delay penalty points recorded by the nth train at the mth critical moment; laterepresents the delay index score. If a single train is delayed at multiple key moments, the maximum value is taken; L late1 Indicates the first late deduction threshold; L late2 Indicates the second late deduction threshold; t n K represents the total delay time of the nth train at the mth critical moment; late1 represents the delay penalty points corresponding to the first delay penalty point threshold; K late2 Indicates the late deduction points corresponding to the second late deduction point threshold.
[0064] Among them, the key moments are the moments in the execution process of the assessment tasks with a preset sequence.
[0065] In some embodiments, the passenger flow index submodule includes a fourth recording submodule and a fourth calculation submodule.
[0066] The fourth recording submodule is used to obtain and record passenger flow information; the passenger flow information is determined based on the user's stop operation, forced stop operation, and delay operation when performing the assessment task.
[0067] Passenger flow information includes the average waiting time of passengers at each station and the passenger flow value of each platform.
[0068] The fourth calculation submodule is used to determine the passenger flow index score of the user based on the passenger flow information.
[0069] The passenger flow index score is a deduction item for evaluation. The calculation formula for the passenger flow index score is as follows:
[0070]
[0071]
[0072] in, represents the passenger flow penalty for the nth station; S represents the average waiting time penalty for passengers at the nth station; pass Score the passenger flow index, including the passenger flow deduction and the average passenger waiting time deduction; L pass1 Indicates the first passenger flow deduction threshold; L pass2 represents the second passenger flow deduction threshold; P n represents the passenger flow value of the nth platform; K pass1 represents the passenger flow deduction points corresponding to the first passenger flow deduction point threshold; K pass2 Indicates the passenger flow deduction points corresponding to the second passenger flow deduction point threshold.
[0073] Furthermore, after obtaining the user's suspension index score, forced stop index score, delay index score and passenger flow index score, the index evaluation module can obtain a preset total score, and based on the preset total score, suspension index score, forced stop index score, delay index score and passenger flow index score, determine and output the user's user assessment score.
[0074] Specifically, the user assessment score = preset total score - suspension index score - forced stop index score - delay index score - passenger flow index score.
[0075] The present embodiment provides an intelligent assessment system for urban rail transit simulation drills, which adds indicator evaluation to the assessment of users and enriches the assessment dimensions. This can avoid the problem that the system only focuses on the execution steps and processes of scheduling operations, thereby making the assessment results more accurate.
[0076] In some embodiments, an operation step management module is also included, and the operation step management module includes a first task sub-module and a second task sub-module.
[0077] The first task submodule is used to generate assessment tasks with a preset order.
[0078] Specifically, the first task submodule can generate an assessment task with a preset order, which can be composed of multiple scheduling operation steps and is the main task of the assessment process. The operation process in the main task is a key process and has a specific execution order. Therefore, the first task submodule is also called the main task management module.
[0079] The second task submodule is used to generate assessment tasks that do not have a preset order.
[0080] Specifically, the second task submodule can generate assessment tasks that do not have a preset order. The assessment tasks that do not have a preset order can be composed of multiple scheduling operation steps and are non-mainline tasks of the evaluation process. The operation process in the non-mainline task is a non-critical process and does not have a specific execution order. Therefore, the second task submodule is also called a non-mainline task management module.
[0081] In the existing user assessment scheme, the steps of the assessment task are highly correlated. Once a problem occurs in a step, the entire assessment task cannot be continued, which is inconsistent with the daily workflow of the traffic dispatcher. In actual work, traffic dispatchers often need to face various emergencies, requiring dispatchers to quickly adjust their work rhythm and response strategies. Therefore, the assessment tasks in the existing technology are too focused on memory ability and are not in line with practical applications.
[0082] The present embodiment provides an intelligent assessment system for urban rail transit simulation drills, which generates assessment tasks with a preset order based on the first task submodule, and generates assessment tasks without a preset order based on the second task submodule, for assessing users. By comprehensively considering the user's handling of the assessment tasks with a preset order and the assessment tasks without a preset order, a comprehensive assessment of the user is conducted, which can make the assessment results more accurate.
[0083] In some embodiments, a voice management module is also included.
[0084] The voice management module is used to execute the user's scheduling operation in response to the user's voice command.
[0085] Among them, the dispatching operation includes one or more of the shutdown operation, forced stop operation and delay operation.
[0086] Specifically, the voice management module is equipped with a voice matching algorithm, which can respond to the user's voice command, match the voice information carried in the voice command with a variety of scheduling operation commands and oral instruction templates in the dynamic voice library, and execute the user's scheduling operation based on the matching content, thereby enabling the user to have free conversations during the assessment process, so as to achieve flexible scheduling command.
[0087] The present invention also provides an intelligent assessment method for urban rail transit simulation drills. Figure 2 , Figure 2 This is one of the flow charts of the urban rail transit simulation drill intelligent assessment method provided by the present invention. In this embodiment, the urban rail transit simulation drill intelligent assessment method is applied to the urban rail transit simulation drill intelligent assessment system, and the method includes steps S210 to S220, and each step is as follows:
[0088] S210: Determine the user's suspension index score, forced stop index score, delay index score, and passenger flow index score.
[0089] The intelligent assessment system for urban rail transit simulation drills includes an index evaluation module, which includes a suspension index submodule, an emergency stop index submodule, a delay index submodule and a passenger flow index submodule.
[0090] Specifically, the user's suspension index score is determined based on the suspension index submodule of the urban rail transit simulation and drill intelligent assessment system; the user's forced stop index score is determined based on the forced stop index submodule; the user's delay index score is determined based on the delay index submodule; and the user's passenger flow index score is determined based on the passenger flow index submodule.
[0091] S220: Determine and output the user assessment score of the user based on the suspension index score, the forced stop index score, the delay index score and the passenger flow index score.
[0092] Specifically, through the indicator evaluation module, based on the suspension index score, forced stop index score, delay index score and passenger flow index score, the user assessment score of the user is determined and output.
[0093] The present invention also provides a specific example of an intelligent assessment system for urban rail transit simulation drills and an intelligent assessment method for urban rail transit simulation drills. Figure 3 and Figure 4 , Figure 3 This is the second structural diagram of the urban rail transit simulation drill intelligent assessment system provided by the present invention. Figure 4 This is the second flow chart of the intelligent assessment method for urban rail transit simulation drill provided by the present invention. Figure 4 Intelligent assessment method for urban rail transit simulation drill based on Figure 3 The intelligent assessment system for urban rail transit simulation drills is realized.
[0094] like Figure 3 As shown, the urban rail transit simulation drill intelligent assessment system includes an operation step management module, a voice management module and an indicator evaluation module.
[0095] Among them, the operation step management module includes a mainline task management module and a non-mainline task management module.
[0096] The index evaluation module includes a suspension index submodule, an forced stop index submodule, a delay index submodule and a passenger flow index submodule.
[0097] Specifically, the step management module is used to manage the scheduling operation steps of the assessment task during the assessment process; parse the user's input instructions, and match the user's input instructions with the scheduling operation steps through a matching algorithm to execute the user's scheduling operation and complete the assessment task.
[0098] Among them, the main task management module is used to generate assessment tasks with a preset order; the non-main task management module is used to generate assessment tasks that do not have a preset order.
[0099] Specifically, the voice management module is used to respond to the user's voice commands. Through the voice matching algorithm, the voice information carried in the voice command is matched with a variety of scheduling operation commands and oral instruction templates in the dynamic voice library, and the user's scheduling operation is executed according to the matching content, thereby enabling the user to have free conversations during the assessment process, so as to realize flexible scheduling command.
[0100] Specifically, the indicator evaluation module is used to obtain and record parameters (ie, operation information) at different time points during the user assessment process, and is used to calculate and output the user assessment score of the user.
[0101] Among them, the outage index submodule is used to determine the user's outage index score.
[0102] The emergency stop index submodule is used to determine the emergency stop index score of the user.
[0103] The delay index submodule is used to determine the user's delay index score.
[0104] The passenger flow index submodule is used to determine the passenger flow index score of the user.
[0105] Furthermore, after obtaining the user's suspension index score, forced stop index score, delay index score and passenger flow index score, the index evaluation module can obtain a preset total score, and based on the preset total score, suspension index score, forced stop index score, delay index score and passenger flow index score, determine and output the user's user assessment score.
[0106] Specifically, the user assessment score = preset total score - suspension index score - forced stop index score - delay index score - passenger flow index score.
[0107] like Figure 4 As shown, first determine whether the assessment is completed; if the assessment is not completed, the train forced stop monitoring is performed based on the forced stop index submodule.
[0108] The forced stop indicator submodule can detect the forced stop operation performed by the user during the performance of the assessment task. The forced stop operation can simulate the forced stop of the train on the system.
[0109] Furthermore, the forced stop index submodule can determine whether there is a forced stop of the train during the user's performance of the assessment task; if there is a forced stop of the train, the total forced stop time and forced stop train information of each train are recorded; if there is no forced stop of the train, the next step of judgment is carried out.
[0110] The outage indicator submodule can be used to detect the outage operation performed by the user during the performance of the assessment task. The execution of the outage operation can simulate the train outage situation on the system.
[0111] Furthermore, determine whether a critical moment has been reached; if a critical moment has been reached, determine based on the suspension index submodule whether there is a train suspension during the user's performance of the assessment task; if there is a train suspension, record the single train suspension point deduction and suspended train information; if there is no train suspension, proceed to the next step of judgment.
[0112] If the critical moment has not been reached, it is determined whether the assessment is over.
[0113] The delay indicator submodule can be used to detect the user's delayed operation during the performance of the assessment task. Delay operation refers to the operation that causes train delay due to improper user operation. Performing delay operation can simulate train delay on the system.
[0114] Delay refers to the phenomenon that the actual running time of the simulated train is later than the planned time in the train schedule.
[0115] Furthermore, based on the delay index submodule, it is determined whether there is a train delay during the user's performance of the assessment task; if there is a train delay, the delay information is recorded, and the delay information includes the total delay time of each train at different time points; if there is no train delay, it is determined whether the assessment is completed.
[0116] If the assessment is completed, the passenger flow information is obtained and recorded based on the passenger flow index submodule.
[0117] Passenger flow information includes the average waiting time of passengers at each station and the passenger flow value of each platform.
[0118] Furthermore, the indicator evaluation module may determine the user assessment score of the user based on the user's outage indicator score, forced stop indicator score, delay indicator score, and passenger flow indicator score.
[0119] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.
[0120] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. An intelligent assessment system for urban rail transit simulation drills, characterized in that: It includes an index evaluation module, which includes a suspension index submodule, an emergency stop index submodule, a delay index submodule and a passenger flow index submodule; The outage index submodule is used to determine the outage index score of the user; The emergency stop index submodule is used to determine the emergency stop index score of the user; The delay index submodule is used to determine the delay index score of the user; The passenger flow index submodule is used to determine the passenger flow index score of the user; The index evaluation module is used to determine and output the user assessment score of the user based on the outage index score, the forced stop index score, the delay index score and the passenger flow index score.
2. The urban rail transit simulation exercise intelligent assessment system according to claim 1 is characterized in that: The outage index submodule includes a first recording submodule and a first calculation submodule; The first recording submodule is used to obtain and record the user's suspension operation information; the suspension operation information is generated based on the user's suspension operation when performing the assessment task; The first calculation submodule is used to determine the outage index score of the user based on the outage operation information.
3. The urban rail transit simulation exercise intelligent assessment system according to claim 1 is characterized in that: The forced stop index submodule includes a second recording submodule and a second calculation submodule; The second recording submodule is used to obtain and record the user's emergency stop operation information; The forced stop operation information is generated based on the forced stop operation of the user when performing the assessment task; The second calculation submodule is used to determine the forced stop index score of the user based on the forced stop operation information.
4. The urban rail transit simulation exercise intelligent assessment system according to claim 1 is characterized in that: The delay indicator submodule includes a third recording submodule and a third calculation submodule; The third recording submodule is used to obtain and record the late operation information of the user; the late operation information is generated based on the late operation of the user when performing the assessment task; The third calculation submodule is used to determine the delay index score of the user based on the delay operation information.
5. The urban rail transit simulation exercise intelligent assessment system according to claim 1 is characterized in that: The passenger flow index submodule includes a fourth recording submodule and a fourth calculation submodule; The fourth recording submodule is used to obtain and record passenger flow information; The passenger flow information is determined based on the stop operation, forced stop operation, and delay operation of the user when performing the assessment task; The fourth calculation submodule is used to determine the passenger flow index score of the user based on the passenger flow information.
6. The urban rail transit simulation drill intelligent assessment system according to claim 1 is characterized in that: Also included is an operation step management module, the operation step management module includes a first task submodule and a second task submodule; The first task submodule is used to generate assessment tasks with a preset order; The second task submodule is used to generate assessment tasks that do not have a preset order.