Parallel maintenance method for two columns of electrical panels of nuclear power unit
By refining the functional requirements of the nuclear power unit into the requirements of continuous power supply and intermittent power supply, and choosing cross-power or external power supply methods, the parallel maintenance of the two columns of the nuclear power unit is achieved, solving the problem of extending the overhaul period by column serial maintenance and prolonging the overhaul period. , improves the flexibility and efficiency of overhaul.
Patent Information
- Application Number
- CN202411031926.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-07-30
AI Technical Summary
The traditional serial maintenance method occupies the critical path of overhaul in the three-row electrical disk architecture of the nuclear power unit, extending the overhaul period and reducing the flexibility of overhaul.
By classifying the functional requirements of each module of the nuclear power unit as main system functions that need to meet the continuous power supply or auxiliary system functions that are intermittent power supply, and refine them to the specific equipment corresponding to the power supply of each column of electrical disk, selecting cross-power or external power supply power supply methods , realize parallel maintenance of two columns of electrical disks.
The overhaul period has been shortened, the flexible configuration of overhaul is improved, and the overhaul period time has been further optimized through the pre-check cycle strategy.
Smart Images

Figure CN118969340A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of nuclear power operation, and in particular to a method for parallel maintenance of two rows of electrical panels of a nuclear power unit. Background Art
[0002] The electrical panel of a nuclear power unit needs to be maintained in full unloading mode. The previous generation of nuclear power units generally adopts a cross-power supply scheme for serial maintenance by column because they use two columns of safety systems, that is, two columns of electrical panels. Serial maintenance by column can adopt an inter-column cross-power supply overhaul power supply configuration scheme, which has good applicability. However, with the development of nuclear power technology, the new generation of nuclear power technology is equipped with three independent and redundant safety systems and their corresponding three columns of electrical panels. For this three-column electrical panel architecture, if the traditional serial maintenance by column is still adopted, it will usually occupy the critical path of the overhaul, extend the overhaul period, and reduce the flexibility of the overhaul.
[0003] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present invention and does not constitute any limitation to the present invention. Summary of the invention
[0004] In view of the shortcomings of the prior art mentioned above, the present invention provides a method for parallel maintenance of two rows of electrical panels in a nuclear power unit. The method classifies the functional requirements of each module of the nuclear power unit into the main system function of continuous power supply or the auxiliary system function of intermittent power supply, and refines the functional requirements to the specific equipment of each row of electrical panels, and selects other electrical panels for cross-power supply or external power supply to meet the power supply needs of the nuclear power unit during the parallel maintenance of the electrical panels, so as to solve the problem of traditional serial maintenance by row, occupying the key path of overhaul, extending the overhaul period, and reducing the flexibility of overhaul.
[0005] The present invention provides a method for parallel maintenance of two rows of electrical panels of a nuclear power unit, wherein the nuclear power unit comprises a first row of electrical panels, a second row of electrical panels and a third row of electrical panels, and the method for parallel maintenance of two rows of electrical panels of the nuclear power unit comprises the following steps:
[0006] S100, determining whether the nuclear power unit meets the functional requirements for parallel maintenance of two rows of electrical panels;
[0007] S200, if not, sort out the nuclear power units to meet the functional requirements of parallel maintenance of two rows of electrical panels;
[0008] S300, if the conditions are met, adding a repowering distribution panel as the power source for the first column electrical panel, the second column electrical panel and the third column electrical panel;
[0009] S400: Perform parallel maintenance on any two of the first column electrical panel, the second column electrical panel, and the third column electrical panel based on the first maintenance cycle or the second maintenance cycle.
[0010] In one embodiment of the present invention, step S100 includes: obtaining the main system function requirements and auxiliary system function requirements of the nuclear power unit under full unloading conditions; the main system function requirements continue to supply power during the execution of parallel maintenance, and the auxiliary system function requirements intermittently supply power during the execution of parallel maintenance.
[0011] In one embodiment of the present invention, the main system function requirements and the auxiliary system function requirements include one or more of the spent tank related functions, material dumping operation functions, ventilation functions, three waste systems functions, fire protection functions, electrical and instrumentation system functions and operation and maintenance requirements.
[0012] In one embodiment of the present invention, step S300 includes: supplying power in parallel between the repower distribution panel and the first row of electrical panels, the second row of electrical panels and the third row of electrical panels, and supplying power in series between the first row of electrical panels, the second row of electrical panels and the third row of electrical panels.
[0013] In one embodiment of the present invention, it also includes: a branch box is used to connect the first column of electrical panels, the second column of electrical panels and the third column of electrical panels that adopt series cross-power supply, and the first column of electrical panels and the second column of electrical panels are connected in parallel with the third column of electrical panels and the re-power supply distribution panel through the branch box.
[0014] In one embodiment of the present invention, it further comprises an air cooling unit, which is located on a parallel power supply circuit of the repowering distribution board with the first row of electrical panels, the second row of electrical panels and the third row of electrical panels.
[0015] In one embodiment of the present invention, step S400 includes: in a first cycle, performing maintenance of the first column electrical panel and maintenance of the low-voltage electrical panel in the second column electrical panel in series; in a second cycle, performing maintenance of the second column electrical panel; in a third cycle, performing maintenance of the third column electrical panel and the low-voltage electrical panel in the first column electrical panel in parallel; wherein the first maintenance cycle is used to perform maintenance of the first column electrical panel, the second column electrical panel and the third column electrical panel.
[0016] In one embodiment of the present invention, it also includes: in the fourth cycle, the maintenance of the low-voltage electrical panels in the first column and the third column are performed in parallel; in the fifth cycle, the maintenance of the second column and the maintenance of the low-voltage electrical panels in the second column are performed in series; in the sixth cycle, the maintenance of the third column and the low-voltage electrical panels in the first column are performed in parallel; wherein the maintenance of the first column, the second column and the third column is performed using the second maintenance cycle.
[0017] In one embodiment of the present invention, step S400 further includes: in the first cycle, performing maintenance of the first column electrical panel and the third column electrical panel in parallel; in the second cycle, performing maintenance of the second column electrical panel; in the third cycle, performing maintenance of each low-voltage electrical panel in the first column electrical panel, the second column electrical panel and the third column electrical panel; wherein the first maintenance cycle is used to perform maintenance of the first column electrical panel, the second column electrical panel and the third column electrical panel. A seventh cycle is also included, in which the same maintenance steps as the first cycle are performed.
[0018] In one embodiment of the present invention, it further includes: in the fourth cycle, the first column electrical panel and the third column electrical panel are overhauled in parallel; in the fifth cycle, the second column electrical panel is overhauled; in the sixth cycle, the low voltage electrical panel in the first column electrical panel, the second column electrical panel and the third column electrical panel are overhauled; wherein the first column electrical panel, the second column electrical panel and the third column electrical panel are overhauled using the second overhaul cycle. It further includes a seventh cycle, in which the same overhaul steps as the first cycle are performed.
[0019] The beneficial effects of the present invention are as follows: by classifying the functional requirements of each module of the nuclear power unit into the main system functions that need to meet continuous power supply or the auxiliary system functions of intermittent power supply, and refining them to the specific equipment corresponding to the power supply of each column of electrical panels, different power supply methods are selected to achieve parallel maintenance of two columns of distribution panels, which shortens the overhaul period compared to the serial maintenance method by column, and further optimizes the overhaul period in conjunction with the pre-inspection cycle strategy, thereby achieving flexible configuration of electrical panel maintenance.
[0020] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The drawings herein are incorporated into the specification and constitute a part of the specification, showing embodiments consistent with the present invention, and together with the specification, are used to explain the principles of the present invention. Obviously, the drawings described below are only some embodiments of the present invention, and for those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0022] Figure 1 It is a flow chart of the method for parallel maintenance of two rows of electrical panels of a nuclear power unit of the present invention;
[0023] Figure 2 A circuit structure diagram of two rows of electrical panels being repaired in parallel in one embodiment of the present invention;
[0024] Figure 3 A circuit structure diagram of two rows of electrical panels being repaired in parallel in another embodiment of the present invention;
[0025] Figure 4 It is a flow chart of executing a parallel maintenance strategy for two rows of electrical panels in one embodiment of the present invention;
[0026] Figure 5 It is a flow chart of executing a parallel maintenance strategy for two rows of electrical panels in another embodiment of the present invention. DETAILED DESCRIPTION
[0027] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied by other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the features in the following embodiments and embodiments can be combined with each other without conflict. It should also be understood that the terms used in the embodiments of the present invention are to describe specific specific embodiments, rather than to limit the scope of protection of the present invention.
[0028] See also Figures 1 to 5 . It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings in this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no substantial technical significance. Any structural modification, change in proportional relationship, or adjustment of size, without affecting the effects and purposes that can be achieved by the present invention, should still fall within the scope of the technical content disclosed by the present invention. At the same time, the terms such as position and quantitative relationship cited in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the present invention. Changes or adjustments in their relative relationships should also be regarded as the scope of the implementation of the present invention without substantially changing the technical content.
[0029] See also Figure 1 The present invention provides a method for parallel maintenance of two rows of electrical panels of a nuclear power unit, wherein the nuclear power unit comprises a first row of electrical panels, a second row of electrical panels and a third row of electrical panels, and the method for parallel maintenance of two rows of electrical panels of a nuclear power unit comprises the following steps:
[0030] S100, determining whether the nuclear power unit meets the functional requirements for parallel maintenance of two rows of electrical panels;
[0031] S200, if not, sort out the nuclear power units to meet the functional requirements of parallel maintenance of two rows of electrical panels;
[0032] S300, if the conditions are met, adding a repowering distribution panel as the power source for the first column electrical panel, the second column electrical panel and the third column electrical panel;
[0033] S400: Perform parallel maintenance on any two of the first column electrical panel, the second column electrical panel, and the third column electrical panel based on the first maintenance cycle or the second maintenance cycle.
[0034] Further, step S100 includes: obtaining the main system function requirements and auxiliary system function requirements of the nuclear power unit under full unloading conditions; the main system function requirements continue to supply power during the parallel maintenance process, and the auxiliary system function requirements intermittently supply power during the parallel maintenance process.
[0035] Specifically, in an embodiment of the present invention, the two power supplies of the nuclear power unit, that is, the electrical panel, need to provide corresponding re-powering capabilities to meet some functional requirements of the nuclear power unit when performing maintenance operations. For this, it is first necessary to sort out the functional requirements of each module of the nuclear power unit, sort out the unit-level safety functions and operation functions of the complete unloading condition, and the operation and maintenance party sorts out the power demand of the maintenance activities and the experience feedback of the same type of units. Then, the sorted functional requirements are refined and decomposed, and the functional requirements of each module of the nuclear power unit are classified into the main system functions and related auxiliary system functions (such as water supply, power supply, cold source, etc.) that should be implemented. These main system functions and auxiliary system functions must meet different power supply requirements of continuous power supply or intermittent power supply, and are refined to the specific equipment corresponding to each column of electrical panel power supply. In this way, the power supply requirements of the nuclear power unit during the parallel maintenance of the electrical panel are met.
[0036] It should be noted that the maintenance of the electrical panel in a nuclear power unit includes daily maintenance and overhaul: For routine maintenance work, it can be carried out without power outage. This type of work is usually for smaller equipment or system parts, and it is necessary to shut down some terminal equipment on the electrical panel for inspection, cleaning, debugging or replacement of parts. For overhaul work that involves a larger range or more complex operations, it is usually necessary to shut down the entire electrical panel of a column. There are some terminal devices in the nuclear power unit that need to be kept running continuously. Therefore, when the electrical panel of the corresponding column is shut down for overhaul, corresponding measures need to be taken to meet its power supply needs.
[0037] See also Figure 2 In one embodiment, step S300 includes: supplying power in parallel between the repower distribution panel and the first column electrical panel, the second column electrical panel and the third column electrical panel, and supplying power in series between the first column electrical panel, the second column electrical panel and the third column electrical panel.
[0038] Furthermore, it also includes an air-cooling unit, which is located on a parallel power supply circuit of the repowering distribution board with the first row of electrical panels, the second row of electrical panels and the third row of electrical panels.
[0039] Specifically, in the embodiment of the present invention, the first column electrical panel, the second column electrical panel and the third column electrical panel can correspond to the attached Figure 2The LKA, LKB and LKC shown in the figure adopt the newly added LKD, LKG and LKH for alternative power supply when the power is shut down for maintenance, that is, LKD, LKG and LKH correspond to the first row of electrical panels, the second row of electrical panels and the third row of electrical panels respectively. In the embodiment of the present invention, compared with the previously used LKA, LKB and LKC scheme, the cross power supply circuit between LKA and LKC and between LKB and LKC is cancelled, and a new repower distribution panel 1LKZ is added, and a parallel power supply mode is adopted between it and the three rows of electrical panels, and a series cross power supply is set between LKD, LKG and LKH on the parallel power supply circuit to meet the power supply requirements of each row of electrical panels. At the same time, for the air-cooled units in the nuclear power unit, the repower distribution panel 1LKZ is also used for power supply, so as to achieve the safety of the nuclear power unit in the parallel maintenance operation of the two rows of electrical panels.
[0040] Please note that, please refer to Figure 2 As shown, the blue line segments represent newly added circuits, the black line segments represent original lines and electrical panels, and the yellow line segments represent cancelled original circuits. In the embodiment of the present invention, the first column electrical panel, the second column electrical panel, and the third column electrical panel correspond to LKA, LKB, and LKC respectively, wherein the third column electrical panel LKC is arranged between the first column electrical panel LKA and the second column electrical panel LKB, that is, when performing parallel maintenance of two columns of electrical panels, the first column electrical panel and the third column electrical panel are selected for parallel maintenance or the second column electrical panel and the third column electrical panel are selected for parallel maintenance.
[0041] See also Figure 3 In one embodiment, it also includes: using a branch box to connect the first column of electrical panels, the second column of electrical panels and the third column of electrical panels that use series cross-power supply, and the first column of electrical panels and the second column of electrical panels are connected in parallel with the third column of electrical panels and the re-power supply distribution panel through the branch box.
[0042] Specifically, see Figure 2 As shown, the black line segments connecting the modules represent the original circuit structure, the red line segments represent that the DC power supply for the two sets of protection devices is taken from the power supply of the electrical panels in different columns to meet the national standard requirements, and the blue line segments represent that the repowering demand of several terminal devices such as network-related cabinets corresponding to the electrical panel power supply load is solved. In the embodiment of the present invention, the first column electrical panel, the second column electrical panel and the third column electrical panel can respectively correspond to the attached Figure 3The LAM, LAN and LLP in the diagram respectively include the electrical equipment on each row of electrical panels, such as network-related cabinets and the power supply of the corresponding row. For example, when the first row of electrical panels and the second row of electrical panels are repaired in parallel, the electrical equipment on the two rows of electrical panels LAM and LAN are connected to the power supply of the third row of electrical panels LLP through the arranged branch box for power supply. At the same time, a double-cut switch or a reserved re-power supply interface is set on the circuit between the third row of electrical panels LLP and the branch box. For example, the re-power supply distribution board 9LK* can be connected to the circuit through this, so that the power supply of the third row of electrical panels LLP can be used as different power supplies for the two sets of protection devices in the first row of electrical panels LAM and the second row of electrical panels LAN, respectively, to meet the national standard requirements.
[0043] Furthermore, the functional requirements of the main system and the auxiliary system include one or more of the spent water pool related functions, material dumping operation functions, ventilation functions, three waste systems functions, fire protection functions, electrical and instrumentation system functions and the requirements of the operation and maintenance party.
[0044] More specifically, in an embodiment of the present invention, the spent fuel pool related functions in each module of the nuclear power unit include a spent fuel pool cooling circuit, which needs to ensure that the two columns of spent fuel pool cooling circuits powered by the two columns of electrical panels are operational. The power supplies of the first column of electrical panels and the second column of electrical panels are cross-powered to each other, or the power supplies of the third column of electrical panels and the first column of electrical panels and the second column of electrical panels are cross-powered to meet the maintenance requirements of the two columns of electrical panels. When the electrical panel bodies of each column are overhauled, in order to meet the operational requirements of the spent fuel pool cooling circuit, the overhaul items of each column of electrical panels can be moved to daily maintenance operations. Similarly, when one of the electrical panels is in the overhaul stage, the machine pump corresponding to the spent fuel pool cooling circuit can be externally powered to restore online, thereby achieving normal power supply to the spent fuel pool cooling circuit during the overhaul.
[0045] The functions related to the spent fuel pool also include that the reactor refueling index and the corresponding spent fuel tank monitored by one row of electrical panels must be in a continuously operating online state. When there is no fuel assembly in the reactor building of the nuclear power unit, in order to ensure that the cooling circuits of the spent fuel pool belonging to the two rows of electrical panels are operational, one of the rows of electrical panels must be in an operational state. The requirements are met by allowing the heat exchangers running in the two rows of electrical panels to be cross-supplied by the cooling water system of the terminal equipment on one row of electrical panels (that is, the cooling water of any row of electrical panels can be provided for the heat exchangers of any row).
[0046] The functions related to the spent pool also include the on-site cooling function of the cooling pump room corresponding to the heat exchanger. Under the condition of complete reactor unloading, it is necessary to ensure that the temperature of the heat exchanger pump room meets the requirements, and the on-site cooling function of the heat exchanger cooling pump room is allowed to be in intermittent operation, where the power supply of the cooling unit in the heat exchanger cooling pump room is the same as that of the heat exchanger pump. In this way, the electrical panels of each column powered by it can be moved to daily maintenance so that the panels will not be stopped during the overhaul, or the corresponding machine pumps can be restored online with external power supply during the overhaul stage.
[0047] Similarly, in the unloading operation function of the nuclear power unit, by defining the activity content of the fuel assembly and the corresponding nuclear safety risks, it is summarized as whether it belongs to the movement of irradiated fuel assemblies, and accordingly, the terminals required for the irradiated fuel assemblies, such as fans, heaters, and emergency exhaust valves, belong to different columns of electrical panels for staggered maintenance operations. That is to say, on the basis of the parallel maintenance of the first and third columns of electrical panels, and the second and third columns of electrical panels, when the irradiated fuel assemblies of the unloading operation function belong to the power terminals of the first and second columns of electrical panels respectively, the maintenance operations of the two columns of electrical panels are staggered, and when the irradiated fuel assemblies belong to the power terminals of the third column of electrical panels, parallel maintenance can be directly selected.
[0048] The ventilation function of nuclear power units can be divided into normal column electrical panel requirements and maintenance column electrical panel requirements according to whether there are corresponding operation requirements during daily operation. The ventilation system terminal equipment of the ventilation function includes the non-controlled area of the safety plant corresponding to the nuclear power units in the three-column electrical panel, the cooling water and nuclear island fire water pump room, the generator plant, the plant water pump room and the refrigeration system.
[0049] For example, under the condition of complete unloading of the nuclear power unit reactor, ensure that the temperature of the rooms in the non-controlled area of the safety plant meets the requirements, and allow the normal ventilation function of the air-cooled unit and the cooling function of the pump room air-conditioning unit to operate intermittently. In this way, for the maintenance column power supply, for example, the heater powered by each column of the electrical panel can be adjusted from the initial LKA / B / C to LKD / G / H to meet the power supply and winter antifreeze requirements of the nuclear power unit, and increase the power supply from LKZ to LKD / G / H. Through the routine maintenance of LKD / G / H, it is ensured that the panel will not be stopped during the overhaul. Or directly by adding the re-power supply, the equipment such as the heater powered by each column of the electrical panel can be provided with a separate power supply.
[0050] Thus, in the embodiment of the present invention, the functional requirements of the main system that requires continuous power supply and the functional requirements of the auxiliary system that can be intermittently powered are divided into projects that require continuous power supply or intermittent power supply according to the specific requirements of the spent pool related functions, material dumping operation functions, ventilation functions, three waste system functions, fire protection functions, electrical instrumentation system functions and operation and maintenance party requirements corresponding to each module of the nuclear power unit, and the functional requirements of the corresponding power supply projects are moved to daily maintenance, and the two rows of electrical panels that are undergoing parallel maintenance are powered by the third row of electrical panels, and external power supplies are added to meet the power supply requirements of the corresponding functional requirements of each module of the nuclear power unit. No further details will be given here.
[0051] See also Figure 4 In one embodiment, step S400 includes: in the first cycle, performing maintenance of the first column electrical panel and maintenance of the low-voltage electrical panel in the second column electrical panel in series; in the second cycle, performing maintenance of the second column electrical panel; in the third cycle, performing maintenance of the third column electrical panel and the low-voltage electrical panel in the first column electrical panel in parallel; wherein the first maintenance cycle is used to perform maintenance of the first column electrical panel, the second column electrical panel and the third column electrical panel. It also includes: in the fourth cycle, performing maintenance of the low-voltage electrical panel in the first column electrical panel and the third column electrical panel in parallel; in the fifth cycle, performing maintenance of the second column electrical panel and maintenance of the low-voltage electrical panel in the second column electrical panel in series; in the sixth cycle, performing maintenance of the third column electrical panel and the low-voltage electrical panel in the first column electrical panel in parallel; wherein the second maintenance cycle is used to perform maintenance of the first column electrical panel, the second column electrical panel and the third column electrical panel. It also includes a seventh cycle, in which the same maintenance steps as the first cycle are performed.
[0052] Specifically, the 3C / 6C maintenance content of the electrical panel may include the cleaning, appearance, tightness and busbar insulation inspection of the distribution panel, lubrication of the drawer guide wheel; inspection and cleaning of the transformer body, insulation resistance and DC resistance measurement, tightness inspection of the incoming and outgoing line electrical connections, inspection and verification of the transformer temperature controller, and transformer adjustment characteristics inspection (LO system); cleaning and inspection of the circuit breaker, mechanical and electrical characteristics inspection, and replacement of the switch lubricating oil (grease); cleaning and inspection of the contactor, electrical characteristics inspection; cleaning and appearance inspection of the switch mechanism, and lubrication; verification of relays, transmitters, and meters; inspection of the secondary circuit of the distribution panel: cleaning of the equipment, inspection of cables, terminals and wiring; verification of the remote tripping and closing intermediate relays and the under-voltage unloading intermediate relays of each compartment; protection group test and circuit inspection; instrument and transmitter verification, etc., are not specifically limited here.
[0053] More specifically, the pre-inspection cycle of the electrical panel is 3C / 6C, and the maintenance arrangement of the electrical panel will be more flexible. Figure 4As shown in the figure, referring to the strategic planning after optimizing the electrical panel pre-inspection cycle to 3C / 6C in a nuclear power unit project, the parallel maintenance work of "one electrical panel + another electrical panel LV (low voltage electrical panel) * panel inverter and LV * 3701TB (power panel cabinet number of the DCS of the power supply load in the low voltage electrical panel) + possible corrective maintenance" still needs to be considered during the overhaul. In this way, the overhaul period of each round can be shortened by 1.5 days.
[0054] See also Figure 5 In one embodiment, step S400 further includes: in the first cycle, performing maintenance of the first column electrical panel and the third column electrical panel in parallel; in the second cycle, performing maintenance of the second column electrical panel; in the third cycle, performing maintenance of the low-voltage electrical panel in each of the first column electrical panel, the second column electrical panel and the third column electrical panel; wherein the first maintenance cycle is used to perform maintenance of the first column electrical panel, the second column electrical panel and the third column electrical panel. It also includes: in the fourth cycle, performing maintenance of the first column electrical panel and the third column electrical panel in parallel; in the fifth cycle, performing maintenance of the second column electrical panel; in the sixth cycle, performing maintenance of the low-voltage electrical panel in each of the first column electrical panel, the second column electrical panel and the third column electrical panel; wherein the second maintenance cycle is used to perform maintenance of the first column electrical panel, the second column electrical panel and the third column electrical panel. It also includes a seventh cycle, in which the same maintenance steps as the first cycle are performed.
[0055] Specifically, in the embodiment of the present invention, when the parallel maintenance of two rows of electrical panels is realized, the pre-inspection cycle of the electrical panels is superimposed as 3C / 6C, as shown in the attached Figure 5 As shown, the "long-long-short" maintenance strategy of "first cycle: parallel maintenance of A / C columns + second cycle: maintenance of B columns + third cycle: no maintenance of electrical panels, that is, the power supply cabinet number of the DCS of the power supply load in the low-voltage electrical panel LV*panel inverter and LV*3701TB low-voltage electrical panel) can be realized. The third and sixth cycles can plan ultra-short overhauls, and each round of overhaul will gain at least 2 days of path duration. In this way, the flexibility of electrical panel maintenance can be realized to the greatest extent. Therefore, it is necessary to promote the parallel maintenance of electrical panels and the optimization of pre-inspection cycles simultaneously.
[0056] In summary, the present invention provides a method for parallel maintenance of two rows of electrical panels in a nuclear power unit. The functional requirements of each module of the nuclear power unit are classified into the main system function of continuous power supply or the auxiliary system function of intermittent power supply, and the functional requirements are further classified into the specific equipment corresponding to the power supply of each row of electrical panels, and other electrical panels are cross-powered or externally powered. The power supply demand of the nuclear power unit is met during the parallel maintenance of the electrical panels, and the overhaul period is further optimized in conjunction with the pre-inspection cycle strategy, so as to realize the flexible configuration of the electrical panel maintenance.
[0057] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Anyone familiar with the art may modify or alter the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or alterations made by a person of ordinary skill in the art without departing from the spirit and technical concept disclosed by the present invention shall still be covered by the claims of the present invention.
Claims
1. A method for parallel maintenance of two rows of electrical panels of a nuclear power unit, wherein the nuclear power unit comprises a first row of electrical panels, a second row of electrical panels and a third row of electrical panels, characterized in that: The method for parallel maintenance of two rows of electrical panels of a nuclear power unit comprises the following steps: S100, determining whether the nuclear power unit meets the functional requirements for parallel maintenance of two rows of electrical panels; S200, if not, sorting out the functional requirements of the nuclear power unit to meet the requirements of performing parallel maintenance of two rows of electrical panels; S300: If the conditions are met, add a repowering distribution panel as the power source for the first column electrical panel, the second column electrical panel and the third column electrical panel; S400: Perform parallel maintenance on any two of the first column electrical panels, the second column electrical panels, and the third column electrical panels based on a first maintenance cycle or a second maintenance cycle.
2. The maintenance method according to claim 1, characterized in that: The S100 step includes: obtaining the main system function requirements and auxiliary system function requirements of the nuclear power unit under the full unloading condition; the main system function requirements provide continuous power supply during the parallel maintenance process, and the auxiliary system function requirements provide intermittent power supply during the parallel maintenance process.
3. The maintenance method according to claim 2, characterized in that: The functional requirements of the main system and the functional requirements of the auxiliary system include one or more of the functions related to the spent pool, the material dumping operation function, the ventilation function, the three waste systems function, the fire protection function, the electrical and instrumentation system function and the requirements of the operation and maintenance party.
4. The maintenance method according to claim 1, characterized in that: The step S300 includes: The repowering distribution panel and the first, second and third electrical panels are powered in parallel, and the first, second and third electrical panels are powered in series.
5. The maintenance method according to claim 4, characterized in that: Also includes: A branch box is used to connect the first column of electrical panels, the second column of electrical panels and the third column of electrical panels that are cross-powered in series. The first column of electrical panels and the second column of electrical panels are connected in parallel with the third column of electrical panels and the re-power distribution panel through the branch box.
6. The maintenance method according to claim 4, characterized in that: It also includes an air cooling unit, which is located on a parallel power supply circuit of the repowering distribution board with the first column of electrical panels, the second column of electrical panels and the third column of electrical panels.
7. The maintenance method according to claim 1, characterized in that: The step S400 includes: In a first cycle, the maintenance of the first column of electrical panels and the maintenance of the low-voltage electrical panels in the second column of electrical panels are performed in series; In the second cycle, performing an overhaul of the second column of electrical panels; In the third cycle, the maintenance of the low-voltage electrical panels in the third column of electrical panels and the first column of electrical panels is performed in parallel; The first column electrical panel, the second column electrical panel and the third column electrical panel are overhauled using the first overhaul cycle.
8. The maintenance method according to claim 7, characterized in that: Also includes: In the fourth cycle, the maintenance of the low-voltage electrical panels in the first column of electrical panels and the third column of electrical panels is performed in parallel; In the fifth cycle, the overhaul of the second column electrical panel and the overhaul of the low voltage electrical panel in the second column electrical panel are performed in series; In the sixth cycle, the maintenance of the low-voltage electrical panels in the third column of electrical panels and the first column of electrical panels is performed in parallel; The second maintenance cycle is used to perform maintenance on the first column electrical panel, the second column electrical panel and the third column electrical panel.
9. The maintenance method according to claim 1, characterized in that: The step S400 further includes: In a first cycle, the inspection of the first column electrical panel and the third column electrical panel are performed in parallel; In the second cycle, performing an overhaul of the second column of electrical panels; In a third cycle, performing maintenance on each low-voltage electrical panel in the first column electrical panel, the second column electrical panel, and the third column electrical panel; The first column electrical panel, the second column electrical panel and the third column electrical panel are overhauled using the first overhaul cycle.
10. The maintenance method according to claim 9, characterized in that: Also includes: In a fourth cycle, the inspection of the first column electrical panel and the third column electrical panel are performed in parallel; In the fifth cycle, the overhaul of the second column electrical panels is performed; In a sixth cycle, performing maintenance on each low-voltage electrical panel in the first column electrical panel, the second column electrical panel, and the third column electrical panel; The second maintenance cycle is used to perform maintenance on the first column electrical panel, the second column electrical panel and the third column electrical panel.
Citation Information
Patent Citations
Nuclear steam reforming control system
CN110838380A
Heat dissipating capacity estimation method and system for nuclear power electrical panel cabinet
CN112699334A
Nuclear power plant switchboard parallel maintenance method and system
CN117895357A
Emergency electric power supply equipment and application method of the same
JP2014098233A