Foundation pit settlement monitoring method and system based on numerical analysis
By using numerical analysis methods in foundation pit settlement monitoring, multiple monitoring items and data threshold intervals are set, the problem of low efficiency and accuracy of foundation pit settlement monitoring in the existing technology is solved, and efficient data screening and accuracy of monitoring results are achieved. sex.
Patent Information
- Application Number
- CN202411040993.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-19
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing foundation pit settlement monitoring methods consume a lot of manpower, and the data acquisition cycle, accuracy, analysis and processing mechanism and management methods are not efficient enough, making it difficult to reasonably screen accurate monitoring information from massive data, affecting the efficiency of foundation pit settlement monitoring.
Using the foundation pit settlement monitoring method based on numerical analysis, multiple monitoring items are set up in the target monitoring foundation pit, data acquisition and transmission are performed based on preset data acquisition and transmission strategies, data preprocessing is performed, and data threshold intervals are divided to judge abnormalities. Data, and generate exception prompt information and data acquisition instructions, update monitoring point configuration and threshold intervals to improve monitoring efficiency and accuracy.
It has realized the reasonable screening of accurate foundation pit settlement monitoring information from massive data, improved monitoring efficiency and accuracy, and improved the intelligent analysis and abnormal monitoring capabilities of foundation pit settlement monitoring.
Smart Images

Figure CN118979504A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of foundation pit settlement monitoring, and in particular to a foundation pit settlement monitoring method and system based on numerical analysis. Background Art
[0002] With the acceleration of urbanization, the demand for transportation continues to grow. In order to solve the problems of travel and traffic congestion, major cities are competing to build and develop subway transportation. Subways are generally located in densely populated urban centers, often close to buildings, traffic arteries, tunnels and various underground pipelines, etc., with tight construction sites, complex conditions and urgent construction periods. Moreover, the subway foundation pit is the most important part of the retaining structure of subway construction and the key to the entire subway construction. It is necessary to monitor the deformation of the foundation pit support structure, the deformation of surrounding buildings (structures), the changes in groundwater levels, and other information on the impact of the foundation pit support structure itself and the surrounding environment during the foundation pit excavation construction process, so as to better guide the construction and optimize the design.
[0003] The existing means of monitoring foundation pit settlement not only consume a lot of manpower, but also the data collection cycle, accuracy, analysis and processing mechanism and management method must be based on scientific management and decision-making needs; with the requirement of full-cycle monitoring of deep foundation pits, the number of deep and large foundation pit projects is increasing, which has spawned more new generation sensing, transmission and monitoring data processing technologies for research and application in foundation pit projects; the full-cycle monitoring data of foundation pits can be obtained by using the measurement method of sensor equipment, and how to reasonably screen accurate monitoring information from the massive amount of collected data and improve the monitoring efficiency of foundation pit settlement monitoring has practical application value and significance. Summary of the invention
[0004] In order to reasonably screen accurate monitoring information from massive amounts of collected data and improve the monitoring efficiency of foundation pit settlement monitoring, the present application provides a foundation pit settlement monitoring method and system based on numerical analysis.
[0005] In the first aspect, the invention objective of the present application is achieved by adopting the following technical solutions: A foundation pit settlement monitoring method based on numerical analysis, comprising: A plurality of monitoring items are set in the target monitoring foundation pit, and the plurality of monitoring items perform data collection and data transmission operations based on a preset data collection monitoring strategy and a data transmission cycle; In the preset early warning monitoring judgment model, according to the acquired monitoring point configuration information of the monitoring project, the corresponding monitoring data and the monitoring point data identifier, the monitoring data is preprocessed and the corresponding data threshold interval is obtained, and it is judged whether the preprocessed monitoring data is within the corresponding data threshold interval; When a certain pre-processed monitoring data is not within the corresponding data threshold interval, based on the corresponding monitoring point data identifier, abnormal data prompt information and data acquisition instructions are generated to a preset monitoring user terminal; When receiving a monitoring point data modification instruction corresponding to the monitoring point data identifier from the monitoring user terminal, obtaining corresponding monitoring point configuration change information and data threshold change information; updating the corresponding monitoring point configuration information based on the monitoring point configuration change information, and updating the corresponding data threshold interval based on the data threshold change information; When a foundation pit settlement monitoring instruction is identified, a foundation pit settlement judgment result of the target monitoring foundation pit is obtained by combining monitoring data sets of a plurality of monitoring items.
[0006] By adopting the above technical scheme, multiple monitoring projects include displacement monitoring, settlement monitoring, soil pressure monitoring, etc. The data acquisition monitoring strategy is pre-set by the foundation pit settlement monitoring personnel based on relevant monitoring standards, normative instruction documents, etc., combined with the actual conditions such as the soil conditions and location of the target monitoring foundation pit. The data acquisition monitoring strategy includes monitoring execution information such as data acquisition equipment, acquisition frequency, acquisition accuracy, number of monitoring point configurations, and monitoring point configuration locations. In order to achieve the purpose of reasonably screening accurate foundation pit settlement monitoring information from massive collected data, this application pre-sets a variety of different monitoring projects based on the target monitoring foundation pit. Each monitoring project performs data acquisition and data transmission operations based on the data acquisition monitoring strategy and data transmission cycle, and performs data preprocessing on the monitoring data to filter out invalid abnormal data.
[0007] At the same time, in order to improve the monitoring efficiency of foundation pit settlement monitoring, the monitoring data of multiple monitoring projects of different types are divided into data threshold intervals to determine whether the monitoring data is abnormal. When a certain pre-processed monitoring data is not in the corresponding data threshold interval, it is characterized that the monitoring data is abnormal and meets the early warning conditions. At this time, based on the monitoring point data identifier, abnormal data prompt information and data acquisition instructions are generated to the monitoring user terminal, and the data acquisition instructions are used to receive the abnormal processing information of the monitoring user terminal and the processing information of the monitoring data; when the monitoring point data modification instruction is received from the monitoring user terminal, it is characterized that the monitoring point position setting needs to be adjusted or based on long-term monitoring work, the data threshold interval used to detect whether the monitoring data is abnormal may need to be adaptively adjusted. At this time, the corresponding monitoring point configuration information and data threshold interval are appropriately adjusted and modified and updated to improve the monitoring efficiency and monitoring accuracy of foundation pit settlement monitoring; when the foundation pit settlement monitoring instruction is obtained, the corresponding foundation pit settlement judgment result is obtained in combination with the monitoring data sets of each monitoring project, so that the present application provides an intelligent foundation pit settlement monitoring method based on multiple monitoring data for intelligent analysis and abnormal monitoring, which realizes the purpose of reasonably screening accurate monitoring information from massive collected data and improving the monitoring efficiency of foundation pit settlement monitoring.
[0008] In a preferred example of the present application: the monitoring project includes a horizontal displacement monitoring project, and the preset data collection monitoring strategy of the horizontal displacement monitoring project includes: According to the foundation pit plan of the target monitoring foundation pit, a plurality of horizontal displacement reference points, a plurality of working reference points and a plurality of horizontal displacement monitoring points are buried in the target monitoring foundation pit, and corresponding reference point network and monitoring point configuration information are obtained; In each data collection cycle of the horizontal displacement monitoring project, the current coordinates of each working base point are calculated using an independent coordinate system and polar coordinate method, and the current coordinates of all working base points are grouped to form a translation working base point observation network of the current data collection cycle, and the stability of each working base point is checked based on the translation working base point observation network combined with a preset stability check observation method to obtain a working base point stability judgment result; When the working base point stability judgment result of the working base point meets the preset stability condition, performing a data acquisition operation through a preset data sensing device; Based on the current construction period of the target monitoring foundation pit, the preset benchmark point network resurvey period and the preset group observation method, the monitoring point configuration information of the benchmark point network is resurveyed to obtain the benchmark point network resurvey result, and the benchmark point network and the corresponding monitoring point configuration information are updated based on the benchmark point network resurvey result.
[0009] By adopting the above technical scheme, in order to realize the full-cycle horizontal displacement monitoring of foundation pit settlement, the present application sets a monitoring method of horizontal displacement benchmark points, multiple working benchmark points and multiple horizontal displacement monitoring points in the target monitoring foundation pit; and in order to improve the data accuracy of the monitoring data of the horizontal displacement monitoring project, in each data collection cycle, a cyclic combined grouping observation method based on grouping of multiple adjacent working benchmark points is used, and the stability verification observation method is combined to perform stability verification on each working benchmark point, and the data collection operation of the horizontal displacement is performed when the stability judgment result of the working benchmark point meets the stability condition, which is conducive to ensuring the monitoring quality of the horizontal displacement of multiple horizontal displacement monitoring points. At the same time, due to the long time of full-cycle horizontal displacement monitoring, the benchmark point network re-measurement operation needs to be carried out based on different foundation pit construction cycles or construction nodes, such as re-measurement of the benchmark point network once a week after the foundation pit is excavated, and re-measurement of the benchmark point network once a month after the foundation pit is excavated to the bottom plate, which complies with the requirements of the "Building Deformation Measurement Code" and other specifications, and meets the high-precision observation requirements of the benchmark point network; the monitoring accuracy of the horizontal displacement monitoring project changes with the change of the foundation pit construction cycle, and the monitoring efficiency of the horizontal displacement monitoring project and the accuracy of the monitoring data are improved.
[0010] In a preferred example of the present application, when the working base point stability judgment result of the working base point meets the preset stability condition, after the data collection operation is performed by the preset data sensing device, it includes: Based on the preset positioning position of the data sensing device and the sight distance length and ranging angle of the currently observed horizontal displacement monitoring point, the sight distance mean error data and the angle measurement mean error data of the monitoring data of the currently observed horizontal position monitoring point are correspondingly obtained, and the point position mean error data is calculated based on the sight distance mean error data; Based on the mean error data of multiple points of the currently observed horizontal displacement monitoring point in the same data collection period, the mean error of the horizontal displacement value of the currently observed horizontal displacement monitoring point is calculated; and the mean error of the horizontal displacement value is compared with a preset translation monitoring accuracy threshold; If the error in the horizontal displacement value is within a preset translation monitoring accuracy threshold, the currently observed monitoring data is stored in a corresponding monitoring data set through a preset data sensing device.
[0011] By adopting the above technical scheme, the monitoring data obtained by the data sensing equipment in each data collection cycle is subjected to accuracy analysis and data error elimination; in actual application, for the horizontal displacement monitoring of the whole life cycle, an observation pier will be established at each working base point, and the monitoring personnel will use the data sensing equipment of the horizontal displacement to collect data at the observation pier, and in the horizontal displacement monitoring project, the horizontal position monitoring data mainly includes the angle measurement error and the distance measurement error, and the distance measurement is the distance between the working base point and the horizontal displacement monitoring point to be observed. In order to meet the high-precision data collection operation and improve the foundation pit settlement monitoring effect, the present application obtains the line of sight error data, the angle measurement error data and the point position error data of the monitoring data in each data collection cycle to obtain and judge whether the error of the horizontal displacement value is within the translation monitoring accuracy threshold. If the error of the horizontal displacement value is within the translation monitoring accuracy threshold, the monitoring data representing the currently collected horizontal displacement meets the high-precision requirements, and the currently observed monitoring data is stored in the corresponding monitoring data set, thereby achieving the data collection accuracy requirements for the horizontal displacement monitoring project, which is conducive to completing the foundation pit settlement monitoring operation with high standards.
[0012] In a preferred example of the present application: the monitoring project includes a support axial force monitoring project, and the preset data collection and monitoring strategy of the support axial force monitoring project includes: According to the foundation pit plan of the target monitoring foundation pit and the corresponding geological data, a plurality of support axial force monitoring points are buried in the concrete support assembly of the target monitoring foundation pit, each support axial force monitoring point is provided with a frequency sensing module for detecting the sensing frequency of the concrete support assembly and a stress sensing module for detecting the support stress of the concrete support assembly, and corresponding monitoring point configuration information of the support axial force monitoring point is obtained; In each data collection cycle of the support axial force monitoring project, the frequency sensing data of the concrete support assembly is continuously obtained through the frequency sensing module and the preset frequency collection times, and the corresponding frequency sensing mean is obtained; the frequency sensing mean is compared with the preset frequency threshold; When the frequency sensing mean is at a preset frequency threshold, the support stress of the concrete support component of the currently observed support axial force monitoring point is detected by a stress sensing module to obtain support stress data; The reinforced concrete support axial force of the concrete support component at the currently observed support axial force monitoring point is calculated based on a preset support axial force calculation method, the monitoring point configuration information, the component attribute data of the concrete support component and the corresponding support stress data.
[0013] By adopting the above technical solution, by obtaining the frequency sensing mean and combining the frequency threshold comparison method, the stability of the support axial force monitoring project and the concrete support component in each data collection cycle is judged, so as to judge the change state of the support axial force. When the frequency sensing mean is at the frequency threshold, it can be considered that the test data is stable at this time, and the support stress data of the corresponding concrete support component is obtained through the stress sensing module, thereby improving the accuracy of the monitoring results of the reinforced concrete support axial force.
[0014] In a preferred example of the present application, the frequency sensing module includes a frequency meter, and the stress sensing module includes a steel bar stress meter; when the currently observed support axial force monitoring point is in the first monitoring state; the support axial force calculation method is shown in formulas (1) and (2): Among them, N i is the axial force value calculated by a single steel bar stress gauge, K is the sensor sensitivity coefficient, and f i is the actual frequency of the sensor, f0 is the initial frequency of the sensor, A s is the cross-sectional area of the steel bar, A is the cross-sectional area of the concrete support beam, E c is the elastic modulus of concrete, E s is the elastic modulus of the steel bar, N is the axial force of the reinforced concrete support, and n is the number of steel bar stress gauges in a single reinforced concrete support.
[0015] By adopting the above technical solution, since the construction site conditions are complex during the actual construction of the target monitoring foundation pit and each support axial force monitoring point adopts different support axial force calculation methods due to different usage scenarios, when the currently observed support axial force monitoring point is in the first monitoring state, it represents the monitoring state of the support axial force monitoring point located at the supporting pile and concrete support point. The stress sensing module needs to be set on the main reinforcement of the support component. At this time, the reinforced concrete support axial force N is calculated by formula (1) and formula (2).
[0016] In a preferred example of the present application: when the currently observed support axial force monitoring point is in the second monitoring state, the support axial force calculation method is as shown in formula (3): N=((A0-AS)Eh*Pg) / Ag*Eg+AS*Pg / Ag (3) Among them, A0 is the cross-sectional area of the supporting beam, AS is the cross-sectional area of the longitudinal main reinforcement, Eh is the elastic modulus of concrete, Pg is the average pressure of the steel bar stress gauge, Ag is the cross-sectional area of the steel bar stress gauge, and Eg is the elastic modulus of the steel bar.
[0017] By adopting the above technical solution, when the currently observed support axial force monitoring point is in the second monitoring state, it indicates that the currently observed support axial force monitoring point is on the support beam surface of the transverse support. At this time, the reinforced concrete support axial force N is calculated by formula (3). Two different methods are adopted based on different installation scenarios of the stress sensing module, which is beneficial to improving the applicability of the support axial force monitoring project and improving the monitoring data accuracy of the reinforced concrete support axial force.
[0018] In a preferred example of the present application: the monitoring project includes a deformation monitoring project of a retaining structure, and the preset data collection and monitoring strategy of the deformation monitoring project of the retaining structure includes: According to the foundation pit plan of the target monitoring foundation pit, a plurality of structural deformation monitoring points are buried in the target monitoring foundation pit, deformation monitoring data are collected regularly through the plurality of structural deformation monitoring points and input into corresponding monitoring data sets; deformation monitoring mean data and deformation error data are calculated based on the monitoring data set of the enclosure structure deformation monitoring project; If the deformation error data is not greater than the preset deformation error threshold, the deformation monitoring mean data is reported to the monitoring user terminal; if the deformation error data is greater than the preset deformation error threshold, additional deformation monitoring data is collected; the added deformation monitoring data is judged and filtered using a gross error criterion; if the added deformation monitoring data is judged to be gross error data, the added deformation monitoring data is deleted from the corresponding monitoring data set; if the deformation monitoring data in the monitoring data set after deletion is less than the preset quantity threshold, the deformation monitoring data collection continues to be increased.
[0019] By adopting the above technical scheme, a method for monitoring the deformation of enclosure structures with high-precision measurement is improved. From the perspective of data error analysis, a method for filtering monitoring data of enclosure structure deformation is proposed, which is beneficial to improving the monitoring accuracy of deformation monitoring data. Specifically, the enclosure structure deformation monitoring project includes systematic errors, gross errors and random errors. The sources of systematic errors are tool errors, condition errors and method errors. The sources of gross errors are the use of defective measuring instruments, the measurement sensor instruments of enclosure structure deformation are affected by external vibrations and electromagnetic interference, etc. The sources of random errors are the measurement environment, measurement devices and measurement personnel. In actual monitoring, this application adopts deformation The monitoring data obtains deformation monitoring data three times (or more than three times) continuously in a single data collection cycle, and performs real-time comparison according to the deformation mean error threshold required by the "Building Deformation Measurement Standard". If the mean error data is less than or equal to the preset mean error threshold, it meets the requirements of the "Building Deformation Measurement Standard"; if the deformation mean error data is greater than the deformation mean error threshold, additional deformation monitoring data is collected; and the gross error criterion is used to judge and filter the added deformation monitoring data, and delete invalid deformation monitoring data, so as to effectively improve the filtering accuracy of deformation monitoring data, and realize high-precision data collection and data storage for the enclosure structure deformation monitoring project.
[0020] In a preferred example of the present application, if the deformation monitoring data in the deleted monitoring data set is less than a preset quantity threshold, then after continuing to collect deformation monitoring data, the method further includes: Recalculate the deformation error data. If the recalculated deformation error data is not greater than the deformation error threshold, report the deformation monitoring mean data to the monitoring user terminal. If the recalculated deformation error data is still greater than the deformation error threshold, use a preset trend mutation monitoring method to analyze the change trend of the deformation monitoring data of the monitoring data set. If there is a change trend, increase the collection of deformation monitoring data. If there is no change trend, perform data conversion on the measurement data through the normality conversion method to obtain a change trend judgment result.
[0021] By adopting the above technical scheme, data movement analysis and data change trend analysis are performed on the deformation trend of the monitored enclosure structure, so as to obtain the change trend judgment result in time, and through repeated acquisition of data and recalculation of error data in deformation, the efficiency of identifying the change state of the monitored enclosure structure is improved.
[0022] In the second aspect, the invention objective of the present application is achieved by adopting the following technical solutions: A foundation pit settlement monitoring system based on numerical analysis is applied to the foundation pit settlement monitoring method based on numerical analysis as described above, and the system comprises: A foundation pit settlement monitoring strategy and data sensing module is used to set a plurality of monitoring items in a target monitoring foundation pit, and the plurality of monitoring items perform data collection and data transmission operations based on a preset data collection monitoring strategy and data transmission cycle; A data threshold interval judgment module is used to perform data preprocessing on the monitoring data and obtain the corresponding data threshold interval according to the acquired configuration information of several monitoring points of the monitoring project, the corresponding monitoring data and the monitoring point data identifier in a preset early warning monitoring judgment model, and judge whether the preprocessed monitoring data is within the corresponding data threshold interval; An abnormal data prompt module is used to generate abnormal data prompt information and data acquisition instructions to a preset monitoring user terminal based on the corresponding monitoring point data identifier when a certain pre-processed monitoring data is not within the corresponding data threshold interval; A monitoring point information and data threshold updating module, configured to, when receiving a monitoring point data modification instruction corresponding to a monitoring point data identifier from a monitoring user terminal, obtain corresponding monitoring point configuration change information and data threshold change information; update the corresponding monitoring point configuration information based on the monitoring point configuration change information, and update the corresponding data threshold interval based on the data threshold change information; The settlement judgment result acquisition module is used to obtain the foundation pit settlement judgment result of the target monitoring foundation pit by combining the monitoring data sets of the plurality of monitoring items when a foundation pit settlement monitoring instruction is identified.
[0023] By adopting the above-mentioned technical scheme, in order to achieve the purpose of reasonably screening accurate foundation pit settlement monitoring information from massive collected data, the present application pre-sets a variety of different monitoring projects based on the target monitoring foundation pit. Each monitoring project performs data collection and data transmission operations based on the data collection monitoring strategy and the data transmission cycle, and performs data preprocessing on the monitoring data to filter out invalid abnormal data; at the same time, in order to improve the monitoring efficiency of foundation pit settlement monitoring, the monitoring data of multiple monitoring projects of different types are divided into data threshold intervals to determine whether the monitoring data is abnormal. When a certain preprocessed monitoring data is not in the corresponding data threshold interval, it is characterized that the monitoring data is abnormal and meets the early warning conditions. At this time, based on the monitoring point data identifier, abnormal data prompt information and data acquisition instructions are generated to the monitoring user terminal, and the data acquisition instructions are used to receive the monitoring user The terminal's exception handling information and monitoring data processing information; when a monitoring point data modification instruction is received from a monitoring user terminal, it indicates that the monitoring point location setting needs to be adjusted or based on long-term monitoring work, the data threshold interval used to detect whether the monitoring data is abnormal may need to be adaptively adjusted. At this time, the corresponding monitoring point configuration information and data threshold interval are appropriately adjusted and modified and updated to improve the monitoring efficiency and monitoring accuracy of foundation pit settlement monitoring; when a foundation pit settlement monitoring instruction is obtained, the corresponding foundation pit settlement judgment result is obtained in combination with the monitoring data sets of each monitoring project. Therefore, the present application provides an intelligent foundation pit settlement monitoring method based on multiple monitoring data for intelligent analysis and abnormal monitoring, which realizes the reasonable screening of accurate monitoring information from massive collected data and improves the monitoring efficiency of foundation pit settlement monitoring.
[0024] In summary, the present application includes at least one of the following beneficial technical effects: 1. In order to achieve the purpose of reasonably screening accurate foundation pit settlement monitoring information from massive amounts of collected data, the present application pre-sets a variety of different monitoring projects based on the target monitoring foundation pit. Each monitoring project performs data collection and data transmission operations based on the data collection monitoring strategy and the data transmission cycle, and performs data preprocessing on the monitoring data to filter out invalid abnormal data. At the same time, in order to improve the monitoring efficiency of foundation pit settlement monitoring, the monitoring data of multiple monitoring projects of different types are divided into data threshold intervals to determine whether the monitoring data is abnormal. When a certain preprocessed monitoring data is not in the corresponding data threshold interval, it is characterized that the monitoring data is abnormal and meets the early warning conditions. At this time, based on the monitoring point data identifier, abnormal data prompt information and data acquisition instructions are generated to the monitoring user terminal. The data acquisition instruction is used to receive abnormal data from the monitoring user terminal. Often process information and processing information of monitoring data; when receiving a monitoring point data modification instruction from a monitoring user terminal, it indicates that the monitoring point location setting needs to be adjusted or based on long-term monitoring work, the data threshold interval used to detect whether the monitoring data is abnormal may need to be adaptively adjusted. At this time, the corresponding monitoring point configuration information and data threshold interval are appropriately adjusted and modified and updated to improve the monitoring efficiency and monitoring accuracy of foundation pit settlement monitoring; when a foundation pit settlement monitoring instruction is obtained, the corresponding foundation pit settlement judgment result is obtained in combination with the monitoring data sets of each monitoring project, so that the present application provides an intelligent foundation pit settlement monitoring method based on multiple monitoring data for intelligent analysis and abnormal monitoring, which realizes the purpose of reasonably screening accurate monitoring information from massive collected data and improving the monitoring efficiency of foundation pit settlement monitoring; 2. In order to realize the full-cycle horizontal displacement monitoring of foundation pit settlement, the present application sets a monitoring method of horizontal displacement benchmark points, multiple working benchmark points and multiple horizontal displacement monitoring points in the target monitoring foundation pit; and in order to improve the data accuracy of the monitoring data of the horizontal displacement monitoring project, in each data collection cycle, a cyclic combined grouping observation method based on multiple adjacent working benchmark points is used to perform stability verification on each working benchmark point in combination with the stability verification observation method, and the data collection operation of the horizontal displacement is performed when the stability judgment result of the working benchmark point meets the stability condition, which is conducive to ensuring the monitoring quality of the horizontal displacement of multiple horizontal displacement monitoring points. At the same time, since the full-cycle horizontal displacement monitoring time is relatively long, the benchmark point network re-measurement operation needs to be carried out based on different foundation pit construction cycles or construction nodes, such as re-measurement of the benchmark point network once a week after the foundation pit is excavated, and re-measurement of the benchmark point network once a month after the foundation pit is excavated to the bottom plate, which complies with the requirements of the "Building Deformation Measurement Code" and other specifications, and meets the high-precision observation requirements of the benchmark point network; the monitoring accuracy of the horizontal displacement monitoring project changes with the change of the foundation pit construction cycle, and the monitoring efficiency of the horizontal displacement monitoring project and the accuracy of the monitoring data are improved; 3. Perform precision analysis and data error elimination on the monitoring data obtained by the data sensing equipment in each data collection cycle; in actual application, for the horizontal displacement monitoring of the entire life cycle, an observation pier will be established at each working base point, and the monitoring personnel will use the horizontal displacement data sensing equipment to collect data at the observation pier. In the horizontal displacement monitoring project, the horizontal position monitoring data mainly includes angle measurement error and distance measurement error. The distance measurement is the distance between the working base point and the horizontal displacement monitoring point to be observed. In order to meet the high-precision data collection operation and improve the foundation pit settlement monitoring effect, this application obtains the line of sight error data, angle measurement error data and point position error data of the monitoring data in each data collection cycle to obtain and judge whether the error of the horizontal displacement value is within the translation monitoring accuracy threshold. If the error of the horizontal displacement value is within the translation monitoring accuracy threshold, the monitoring data representing the currently collected horizontal displacement meets the high-precision requirements, and the currently observed monitoring data is stored in the corresponding monitoring data set, thereby achieving the data collection accuracy requirements for the horizontal displacement monitoring project, which is conducive to completing the foundation pit settlement monitoring operation with high standards. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a flow chart of a foundation pit settlement monitoring method based on numerical analysis in one embodiment of the present application; Figure 2 is a schematic diagram of a polar coordinate method in a foundation pit settlement monitoring method based on numerical analysis in an embodiment of the present application; Figure 3 It is a flow chart of a foundation pit settlement monitoring method based on numerical analysis in one embodiment of the present application; Figure 4 It is another flow chart of a foundation pit settlement monitoring method based on numerical analysis in one embodiment of the present application. DETAILED DESCRIPTION
[0026] The present application is further described in detail below in conjunction with the accompanying drawings.
[0027] In one embodiment, if Figure 1 As shown, the present application discloses a foundation pit settlement monitoring method based on numerical analysis, which specifically includes the following steps: S1: multiple monitoring projects are set up in the target monitoring pit, and the multiple monitoring projects perform data collection and data transmission operations based on preset data collection monitoring strategies and data transmission cycles.
[0028] In this embodiment, multiple monitoring projects include horizontal displacement, settlement, groundwater level, reinforced concrete support axial force, soil pressure, inclinometer, anchor stress monitoring and other monitoring projects. The different buildings (structures) of each monitoring project branch can be subdivided into different sub-monitoring projects; the data acquisition monitoring strategy is pre-set by the foundation pit settlement monitoring personnel based on relevant monitoring standards, normative instruction documents, etc., combined with the actual conditions such as the soil conditions and location of the target monitoring foundation pit. The data acquisition monitoring strategy includes monitoring execution information such as data acquisition equipment, acquisition frequency, acquisition accuracy, number of monitoring point configurations, and monitoring point configuration locations; the data transmission cycle of different monitoring projects is different based on the differences in data sensing equipment, foundation pit construction progress, positioning location and measured buildings (structures).
[0029] S2: In the preset early warning monitoring judgment model, according to the acquired configuration information of several monitoring points of the monitoring project, the corresponding monitoring data and the monitoring point data identification, the monitoring data is preprocessed and the corresponding data threshold interval is obtained, and it is judged whether the preprocessed monitoring data is within the corresponding data threshold interval.
[0030] In this embodiment, the early warning monitoring judgment model pre-stores data threshold intervals of unmonitored points of different monitoring projects. The data threshold intervals can be timely adjusted and updated according to the progress of the monitoring projects. For example, multiple data threshold intervals of the horizontal displacement of the top of the enclosure structure will be set the same in the first data collection cycle, and the data threshold intervals of one or more monitoring points can be modified according to the different monitoring point locations and the progress of the monitoring project.
[0031] Specifically, in order to achieve the purpose of reasonably screening accurate foundation pit settlement monitoring information from massive collected data, the present application pre-sets a variety of different monitoring projects based on the target monitoring foundation pit. Each monitoring project performs data collection and data transmission operations based on the data collection monitoring strategy and data transmission cycle, and performs data preprocessing on the monitoring data to filter out invalid abnormal data; at the same time, in order to improve the monitoring efficiency of foundation pit settlement monitoring, the monitoring data of multiple monitoring projects of different types are divided into data threshold intervals to determine whether the monitoring data is abnormal.
[0032] S3: When a certain pre-processed monitoring data is not within the corresponding data threshold interval, based on the corresponding monitoring point data identifier, abnormal data prompt information and data acquisition instructions are generated to the preset monitoring user terminal.
[0033] In this embodiment, when a certain preprocessed monitoring data is not within the corresponding data threshold interval, it is characterized that the monitoring data is abnormal and meets the warning conditions. At this time, based on the monitoring point data identifier, abnormal data prompt information and data acquisition instructions are generated to the monitoring user terminal. The data acquisition instructions are used to receive the abnormal processing information of the monitoring user terminal and the processing information of the monitoring data.
[0034] S4: When a monitoring point data modification instruction corresponding to the monitoring point data identifier is received from the monitoring user terminal, the corresponding monitoring point configuration change information and data threshold change information are obtained; the corresponding monitoring point configuration information is updated based on the monitoring point configuration change information, and the corresponding data threshold interval is updated based on the data threshold change information.
[0035] In this embodiment, when a monitoring point data modification instruction is received from a monitoring user terminal, it indicates that the monitoring point location setting needs to be adjusted or based on long-term monitoring work, the data threshold interval used to detect whether the monitoring data is abnormal may need to be adaptively adjusted. At this time, the corresponding monitoring point configuration information and data threshold interval are appropriately adjusted and modified to improve the monitoring efficiency and accuracy of foundation pit settlement monitoring.
[0036] S5: When a foundation pit settlement monitoring instruction is identified, a foundation pit settlement judgment result of a target monitoring foundation pit is obtained by combining monitoring data sets of multiple monitoring projects.
[0037] Specifically, when a foundation pit settlement monitoring instruction is obtained from a monitoring user terminal, the corresponding foundation pit settlement judgment result is obtained by combining the monitoring data sets of each monitoring project. Thus, the present application provides an intelligent foundation pit settlement monitoring method that performs intelligent analysis and abnormal monitoring based on multiple monitoring data, thereby achieving the purpose of reasonably screening accurate monitoring information from massive collected data and improving the monitoring efficiency of foundation pit settlement monitoring.
[0038] In one embodiment, if Figure 3 As shown, in step S1, the monitoring project includes a horizontal displacement monitoring project, and the preset data acquisition monitoring strategy of the horizontal displacement monitoring project includes: S101: Based on the foundation pit plan of the target monitoring foundation pit, multiple horizontal displacement reference points, multiple working reference points and multiple horizontal displacement monitoring points are buried in the target monitoring foundation pit, and corresponding reference point network and monitoring point configuration information are obtained.
[0039] In this embodiment, in order to realize full-cycle horizontal displacement monitoring of foundation pit settlement, the present application sets a monitoring method of a horizontal displacement reference point, multiple working reference points and multiple horizontal displacement monitoring points in the target monitoring foundation pit.
[0040] Specifically, a data collection method is adopted in which an observation pier is established at a horizontal displacement reference point and a working base point, and then a horizontal displacement monitoring device is installed on the observation pier.
[0041] S102: In each data collection cycle of the horizontal displacement monitoring project, an independent coordinate system and polar coordinate method are used to calculate the current coordinates of each working base point, and all working base points are grouped based on their current coordinates to form a translation working base point observation network for the current data collection cycle. Based on the translation working base point observation network and a preset stability verification observation method, stability verification is performed on each working base point to obtain a working base point stability judgment result.
[0042] In this embodiment, the stability verification observation method is the resection method, and the stability check and correction of the working base point is observed by the resection method; when the resection method is used to check the stability of the working base point, four angle measurements are made and four distance measurements are made. The specific method is to use three known reference points A, B, and C as the backsight points, and the working base point P as the point to be determined. An instrument is placed at point P to observe the horizontal angle and distance between point P and the other three known reference points, thereby calculating the coordinates of point P.
[0043] Specifically, the same measuring station simultaneously uses the polar coordinate method to observe the angle and distance of each horizontal displacement reference point, observes six rounds, and calculates the coordinates of each horizontal displacement reference point through adjustment. When measuring, it is necessary to operate in accordance with the "Code for Measurement of Building Deformation". For example, when measuring the horizontal angle, it is necessary to measure under the horizontal angle limit requirements. For example: when using a 1-second instrument type for horizontal angle measurement, the half-measurement regression zero difference limit is 6 seconds, the 2C mutual difference limit within a round is 9 seconds, and the mutual difference limit of each round of measurement for the same direction value is 6 seconds, etc., to complete high-level data collection and data transmission operations.
[0044] For example, the polar coordinate method is used as Figure 2 As shown in the figure, using the polar coordinate principle in mathematics, a polar coordinate system is established with two known points as coordinate axes and one of the points as the pole; the distance from the observation point to the pole is measured, and the angle between the observation point and the known coordinate axis is measured to calculate the coordinates of the observation point. When determining the coordinates of the point C to be determined, first calculate the azimuth of the known points A and B: Determine the angle and the length S of the BC side, and calculate the azimuth of BC according to the azimuth calculation formula: α BA =tg -1 ((Y A -Y B ) / (X A -X B )); Calculate the coordinates of point C: X C =X B +S·cosα BC , Y C =Y B +S·sinαBC .
[0045] S103: When the working base point stability judgment result of the working base point meets the preset stability condition, a data collection operation is performed through a preset data sensing device.
[0046] In this embodiment, in order to improve the data accuracy of the monitoring data of the horizontal displacement monitoring project, in each data collection cycle, a cyclic combined grouping observation method is used based on grouping multiple adjacent working base points, and a stability verification observation method is combined to perform stability verification on each working base point, and when the stability judgment result of the working base point meets the stability condition, the data collection operation of the horizontal displacement is performed, which is beneficial to ensure the monitoring quality of the horizontal displacement of multiple horizontal displacement monitoring points.
[0047] S104: Based on the current construction period of the target monitoring foundation pit, the preset benchmark point network re-survey period and the preset group observation method, re-survey the monitoring point configuration information of the benchmark point network to obtain the benchmark point network re-survey results, and update the benchmark point network and the corresponding monitoring point configuration information based on the benchmark point network re-survey results.
[0048] Specifically, since the full-cycle horizontal displacement monitoring time is relatively long, the benchmark point network needs to be re-surveyed based on different foundation pit construction cycles or construction nodes. For example, the benchmark point network is re-surveyed once a week after the foundation pit is excavated, and once a month after the foundation pit is excavated to the bottom plate. This is in line with the requirements of the "Building Deformation Measurement Code" and other specifications, and meets the high-precision observation requirements of the benchmark point network; the monitoring accuracy of the horizontal displacement monitoring project changes with the change of the foundation pit construction cycle, thereby improving the monitoring efficiency of the horizontal displacement monitoring project and the accuracy of the monitoring data.
[0049] In one embodiment, after step S103, a foundation pit settlement monitoring method based on numerical analysis includes: S1031: Based on the preset positioning position of the data sensor device and the line-of-sight length and ranging angle of the currently observed horizontal displacement monitoring point, obtain the line-of-sight mean error data and angle measurement mean error data of the monitoring data of the currently observed horizontal position monitoring point, and calculate the point position mean error data based on the line-of-sight mean error data.
[0050] In this embodiment, the monitoring data obtained by the data sensing equipment in each data collection cycle is subjected to accuracy analysis and data error elimination. In actual application, for the horizontal displacement monitoring of the whole life cycle, an observation pier will be established at each working base point, and the monitoring personnel will use the horizontal displacement data sensing equipment to collect data at the observation pier. In the horizontal displacement monitoring project, the horizontal position monitoring data mainly includes the angular measurement error and the distance measurement error, and the distance measurement is the distance between the working base point and the horizontal displacement monitoring point to be observed.
[0051] S1032: Calculate the mean error of the horizontal displacement value of the currently observed horizontal displacement monitoring point based on the mean error data of multiple points of the currently observed horizontal displacement monitoring point in the same data collection period; and compare the mean error of the horizontal displacement value with a preset translation monitoring accuracy threshold.
[0052] S1033: If the error in the horizontal displacement value is within a preset translation monitoring accuracy threshold, the currently observed monitoring data is stored into a corresponding monitoring data set through a preset data sensing device.
[0053] In this embodiment, in order to meet the high-precision data collection operation and improve the foundation pit settlement monitoring effect, the present application obtains the line of sight error data, angle measurement error data and point error data of the monitoring data in each data collection cycle to obtain and judge whether the error of the horizontal displacement value is within the translation monitoring accuracy threshold. If the error of the horizontal displacement value is within the translation monitoring accuracy threshold, the monitoring data representing the currently collected horizontal displacement meets the high-precision requirements, and the currently observed monitoring data is stored in the corresponding monitoring data set, thereby realizing the data collection accuracy requirements for the horizontal displacement monitoring project, which is conducive to completing the foundation pit settlement monitoring operation with high standards.
[0054] Exemplarily, the accuracy analysis is as follows: When using observation piers, the sources of errors include angle measurement error and distance measurement error.
[0055] Take the sight distance length ≤ 150m, Angle measurement error: m 角 =m θ / ρ*s=1 / 206265*150*1000=0.7mm; Error in distance measurement: m s =a+b*D==1.5+2*10 -6 *150*1000=1.8mm; Point position error: The error in the horizontal displacement value of the same point observed twice: According to the formula: It can be seen that the mean error of the horizontal displacement observation values in a certain direction of the foundation pit in two observations is ±0.9mm. Using high-precision measuring instruments, such as Sokkia CX-101, for monitoring according to the above method can meet the accuracy requirement of 1mm.
[0056] From the above formula, we can know that when calculating the horizontal displacement accuracy of the foundation pit, the error caused by distance measurement can be ignored. Only the error caused by angle is considered. When arranging the benchmark (working benchmark) point, the distance from the observation pier to the farthest monitoring point should be controlled within 150m.
[0057] The accuracy analysis is as follows: Assuming the sight distance is ≤150m, according to the accuracy of the Sokkia CX-101 instrument (1″, 1.5+2ppm), we get: The error in the offset: m AT =m s / ρ*s=1 / 206265*150*1000=0.7mm Change monitoring error in the two-period observation change It can be seen that the mean error of the horizontal displacement observation values in a certain direction of the foundation pit in two observations is ±0.99mm. Using Sokkia CX-101 for monitoring according to the above method can meet the accuracy requirement of 1mm.
[0058] In one embodiment, the monitoring project includes a support axial force monitoring project, and the preset data collection and monitoring strategy for the support axial force monitoring project includes: S111: Based on the foundation pit plan of the target monitoring foundation pit and the corresponding geological data, multiple support axial force monitoring points are buried in the concrete support components of the target monitoring foundation pit, and each support axial force monitoring point is provided with a frequency sensing module for detecting the sensing frequency of the concrete support component and a stress sensing module for detecting the support stress of the concrete support component, and the monitoring point configuration information of the corresponding support axial force monitoring point is obtained.
[0059] In this embodiment, by obtaining the frequency sensing mean and combining the frequency threshold comparison method, the stability of the support axial force monitoring project and the concrete support assembly in each data collection cycle is determined to facilitate the determination of the change state of the support axial force.
[0060] S112: In each data collection cycle of the support axial force monitoring project, the frequency sensing data of the concrete support assembly is continuously obtained through the frequency sensing module and the preset frequency collection times, and the corresponding frequency sensing mean is obtained; the frequency sensing mean is compared with the preset frequency threshold.
[0061] In this embodiment, the concrete support assembly includes a reinforced concrete support.
[0062] S113: When the frequency sensing mean is at a preset frequency threshold, the support stress of the concrete support component of the currently observed support axial force monitoring point is detected by a stress sensing module to obtain support stress data.
[0063] In this embodiment, the frequency sensing module includes a frequency meter, and the stress sensing module includes a steel bar stress meter; when the frequency sensing mean is at the frequency threshold, it can be considered that the test data is stable at this time, and the support stress data of the corresponding concrete support component is obtained through the stress sensing module to improve the accuracy of the monitoring results of the axial force of the reinforced concrete support.
[0064] Specifically, the frequency threshold may be set to 1 Hz. The stress sensing module may be installed in different ways based on different installation scenarios of the stress sensing module.
[0065] S114: Calculate the reinforced concrete support axial force of the concrete support component at the currently observed support axial force monitoring point based on a preset support axial force calculation method, monitoring point configuration information, component attribute data of the concrete support component and corresponding support stress data.
[0066] In one embodiment, the frequency sensing module includes a frequency meter, and the stress sensing module includes a steel bar stress meter; when the currently observed support axial force monitoring point is in the first monitoring state; the support axial force calculation method is shown in formulas (1) and (2): Among them, N i is the axial force value calculated by a single steel bar stress gauge, K is the sensor sensitivity coefficient, and f i is the actual frequency of the sensor, f0 is the initial frequency of the sensor, A s is the cross-sectional area of the steel bar, A is the cross-sectional area of the concrete support beam, E c is the elastic modulus of concrete, E s is the elastic modulus of the steel bar, N is the axial force of the reinforced concrete support, and n is the number of steel bar stress gauges in a single reinforced concrete support.
[0067] Specifically, during the actual construction of the target monitoring foundation pit, the construction site conditions are complex and each support axial force monitoring point adopts different support axial force calculation methods due to different usage scenarios. When the currently observed support axial force monitoring point is in the first monitoring state, it represents the monitoring state of the support axial force monitoring point located at the supporting pile and concrete support point. The stress sensing module needs to be installed on the main reinforcement of the support component. At this time, the reinforced concrete support axial force N is calculated by formula (1) and formula (2).
[0068] In this embodiment, the first monitoring state of the support axial force monitoring point is to adopt the first method of burying the support axial force monitoring point. The burying method includes: welding the pull rod of the rebar meter to a half-meter long steel bar of the same diameter, tightening one end of the screw mouth with the nut of the rebar meter to form a whole; the rebar meter is installed on the two corner main bars of the section of the above-mentioned burying position or the main bars in the middle of the support section, and buried symmetrically; the welded rebar meter is electric welded to the main bars of the support.
[0069] In one embodiment, when the currently observed support axial force monitoring point is in the second monitoring state, the support axial force calculation method is as shown in formula (3): N=((A0-AS)Eh*Pg) / Ag*Eg+AS*Pg / Ag (3) Among them, A0 is the cross-sectional area of the supporting beam, AS is the cross-sectional area of the longitudinal main reinforcement, Eh is the elastic modulus of concrete, Pg is the average pressure of the steel bar stress gauge, Ag is the cross-sectional area of the steel bar stress gauge, and Eg is the elastic modulus of the steel bar.
[0070] In this embodiment, when the currently observed support axial force monitoring point is in the second monitoring state, it indicates that the currently observed support axial force monitoring point is on the support beam surface of the transverse support. At this time, the reinforced concrete support axial force N is calculated by formula (3). Two different methods are used based on different installation scenarios of stress sensing modules, which is beneficial to improving the applicability of the support axial force monitoring project and improving the monitoring data accuracy of the reinforced concrete support axial force.
[0071] In this embodiment, the first monitoring state of the support axial force monitoring point is to adopt the first method of embedding the support axial force monitoring point. The embedding method includes: the selected steel bar stress gauge should be matched with the main steel bar, according to the support axial force monitoring point layout construction drawing, when installing, first cut the main bar of the installation part with a corresponding length that is the same as the length of the steel bar stress gauge, then weld the pull rod of the steel bar stress gauge to the main bar, the welding length meets the specification requirements, then tighten one end of the screw mouth with the steel bar gauge nut to form a whole, and apply a layer of paint or asphalt on the steel bar stress gauge, and finally wrap it with gauze, and the steel bar stress gauge wire is put with a small steel pipe to lead out of the support beam surface and fixed. The steel bar should be embedded on the side main bar of the support section.
[0072] In one embodiment, if Figure 4 As shown, the monitoring project includes the deformation monitoring project of the retaining structure. A foundation pit settlement monitoring method based on numerical analysis includes: The preset data acquisition monitoring strategy of the deformation monitoring project of the retaining structure includes: S121: Based on the foundation pit plan of the target monitoring foundation pit, multiple structural deformation monitoring points are buried in the target monitoring foundation pit, deformation monitoring data are collected regularly through the multiple structural deformation monitoring points and input into corresponding monitoring data sets; based on the monitoring data set of the enclosure structure deformation monitoring project, deformation monitoring mean data and deformation error data are calculated.
[0073] In this embodiment, a method for monitoring the deformation of a retaining structure with high-precision measurement is improved, and a filtering method for monitoring the deformation of a retaining structure is proposed from the perspective of data error analysis, which is beneficial to improving the monitoring accuracy of the deformation monitoring data; specifically, the deformation monitoring items of the retaining structure include systematic errors, gross errors and random errors, among which the sources of systematic errors are tool errors, condition errors and method errors, the sources of gross errors are the use of defective measuring instruments, the measurement sensor instruments of the deformation of the retaining structure are affected by external vibrations, electromagnetic interference, etc., and the sources of random errors are the measurement environment, measurement equipment and measurement personnel.
[0074] Specifically, during actual monitoring, the present application uses deformation monitoring data to continuously acquire deformation monitoring data three times (or more than three times) at a time in a single data collection cycle, and performs real-time comparison according to the deformation error threshold required by the "Building Deformation Measurement Standard".
[0075] S122: If the deformation error data is not greater than the preset deformation error threshold, the deformation monitoring mean data is reported to the monitoring user terminal; if the deformation error data is greater than the preset deformation error threshold, additional deformation monitoring data is collected.
[0076] Specifically, if the mean error data is less than or equal to the preset mean error threshold, it meets the requirements of the "Building Deformation Measurement Standard"; if the deformation mean error data is greater than the deformation mean error threshold, additional deformation monitoring data is collected; and the gross error criterion is used to judge and filter the added deformation monitoring data, and delete invalid deformation monitoring data, so as to effectively improve the filtering accuracy of deformation monitoring data, and realize high-precision data collection and data storage work for the enclosure structure deformation monitoring project.
[0077] S123: Use the gross error criterion to judge and filter the added deformation monitoring data. If the added deformation monitoring data is judged to be gross error data, delete the added deformation monitoring data from the corresponding monitoring data set; if the deformation monitoring data in the deleted monitoring data set is less than a preset quantity threshold, continue to increase the collection of deformation monitoring data.
[0078] Specifically, the gross error criterion is the Lomnaofski criterion.
[0079] For example, in this embodiment, since the amount of data is too small (n<9), it is necessary to use the Romanovsky criterion (t distribution test criterion) used for processing a small amount of data for verification, and the gross error is judged according to the actual error distribution range of the t distribution. The judgment steps are as follows: Step 1: Calculate the residual data of each measurement data Where i = 1, 2, ..., n. First, take 3 times the mean error data S calculated in step S1 as the standard, and the residual data v corresponding to each measurement data i Compare and find possible suspicious values of gross errors. The absolute value of the residual data of the measured data is greater than 3S and is first set as the suspicious value of gross error x. d If all are less than 3S, a value is randomly selected as the gross error suspicious value x d , the suspicious value x d Pre-culling; Step 2: Recalculate the observed mean data using the following formula and the mean error data S′; Step 3: Obtain the test coefficient according to the preset significance data. If the gross error suspicious value is greater than or equal to the test system, delete the measurement data corresponding to the gross error suspicious value and return to step 1; until the gross error suspicious values corresponding to several measurement data are all less than the test coefficient; in this step, select the significance data α as 0.05 and the test coefficient K(n,α) of the t distribution that meets the Romanovsky criterion (t distribution test criterion). If Then x d That is, it is a gross error and should be eliminated, otherwise it should be retained; after elimination, return to step S31 to find a new gross error suspicious value for judgment until all measurement data are less than K(n,α)S′.
[0080] In one embodiment, after step S123, a foundation pit settlement monitoring method based on numerical analysis also includes: S124: recalculating the deformation error data; if the recalculated deformation error data is not greater than the deformation error threshold, reporting the deformation monitoring mean data to the monitoring user terminal; if the recalculated deformation error data is still greater than the deformation error threshold, using a preset trend mutation monitoring method to analyze the change trend of the deformation monitoring data of the monitoring data set; if there is a change trend, additional deformation monitoring data is collected; if there is no change trend, performing data conversion on the measurement data through a normality transformation method to obtain a change trend judgment result.
[0081] In this embodiment, the trend mutation point detection method is the Mann-Kendall monotonic trend test. The Mann-Kendall driven test is a non-parametric statistical test method. Its advantage is that it does not require the measurement data in the observation processing data set to follow a certain distribution and is not disturbed by a few abnormal measurement values. The normality transformation method is the BOX-COX transformation. The BOX-COX transformation is used when the continuous response variable does not satisfy the normal distribution. After the measurement data that does not conform to the normal distribution is subjected to the BOX-COX transformation, the correlation between the unobservable measurement error and the prediction variable can be reduced to a certain extent.
[0082] Specifically, data movement analysis and data change trend analysis are performed on the deformation trend of the monitored enclosure structure to facilitate timely acquisition of change trend judgment results, and the efficiency of identifying the change state of the monitored enclosure structure is improved through repeated acquisition of data and recalculation of error data in deformation.
[0083] It should be understood that the serial numbers of the steps in the above embodiments do not imply a sequence of execution. The execution sequence of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0084] In one embodiment, a foundation pit settlement monitoring system based on numerical analysis is provided, and the foundation pit settlement monitoring system based on numerical analysis corresponds to the foundation pit settlement monitoring method based on numerical analysis in the above-mentioned embodiment.
[0085] A foundation pit settlement monitoring system based on numerical analysis includes a foundation pit settlement monitoring strategy and data sensing module, a data threshold interval judgment module, an abnormal data prompt module, a monitoring point information and data threshold update module, and a settlement judgment result acquisition module. The detailed description of each functional module is as follows: The foundation pit settlement monitoring strategy and data sensing module is used to set multiple monitoring items in the target monitoring foundation pit, and the multiple monitoring items perform data collection and data transmission operations based on the preset data collection monitoring strategy and data transmission cycle; The data threshold interval judgment module is used to perform data preprocessing on the monitoring data and obtain the corresponding data threshold interval according to the acquired configuration information of several monitoring points of the monitoring project, the corresponding monitoring data and the monitoring point data identifier in the preset early warning monitoring judgment model, and judge whether the preprocessed monitoring data is within the corresponding data threshold interval; The abnormal data prompt module is used to generate abnormal data prompt information and data acquisition instructions to a preset monitoring user terminal based on the corresponding monitoring point data identifier when a certain pre-processed monitoring data is not within the corresponding data threshold interval; A monitoring point information and data threshold update module, for, when receiving a monitoring point data modification instruction corresponding to a monitoring point data identifier from a monitoring user terminal, obtaining corresponding monitoring point configuration change information and data threshold change information; updating corresponding monitoring point configuration information based on the monitoring point configuration change information, and updating corresponding data threshold intervals based on the data threshold change information; The settlement judgment result acquisition module is used to obtain the foundation pit settlement judgment result of the target monitoring foundation pit by combining the monitoring data sets of multiple monitoring projects when the foundation pit settlement monitoring instruction is identified.
[0086] For the specific definition of a foundation pit settlement monitoring system based on numerical analysis, please refer to the definition of a foundation pit settlement monitoring method based on numerical analysis in the above text, which will not be repeated here; each module in the above-mentioned foundation pit settlement monitoring system based on numerical analysis can be fully or partially implemented by software, hardware and their combination; each of the above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the corresponding operations of each of the above modules.
[0087] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above.
[0088] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, it should be understood by those skilled in the art that the technical solutions described in the aforementioned embodiments may still be modified, or some of the features thereof may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A foundation pit settlement monitoring method based on numerical analysis, It is characterized in that include: A plurality of monitoring items are set in the target monitoring foundation pit, and the plurality of monitoring items perform data collection and data transmission operations based on a preset data collection monitoring strategy and a data transmission cycle; In the preset early warning monitoring judgment model, according to the acquired monitoring point configuration information of the monitoring project, the corresponding monitoring data and the monitoring point data identifier, the monitoring data is preprocessed and the corresponding data threshold interval is obtained, and it is judged whether the preprocessed monitoring data is within the corresponding data threshold interval; When a certain pre-processed monitoring data is not within the corresponding data threshold interval, based on the corresponding monitoring point data identifier, abnormal data prompt information and data acquisition instructions are generated to a preset monitoring user terminal; When receiving a monitoring point data modification instruction corresponding to the monitoring point data identifier from the monitoring user terminal, obtaining corresponding monitoring point configuration change information and data threshold change information; Based on the monitoring point configuration change information, the corresponding monitoring point configuration information is updated; based on the data threshold change information, the corresponding data threshold interval is updated; When a foundation pit settlement monitoring instruction is identified, a foundation pit settlement judgment result of the target monitoring foundation pit is obtained by combining monitoring data sets of a plurality of monitoring items.
2. A method for monitoring foundation pit settlement based on numerical analysis according to claim 1, It is characterized in that The monitoring project includes a horizontal displacement monitoring project, and the preset data acquisition monitoring strategy of the horizontal displacement monitoring project includes: According to the foundation pit plan of the target monitoring foundation pit, a plurality of horizontal displacement reference points, a plurality of working reference points and a plurality of horizontal displacement monitoring points are buried in the target monitoring foundation pit, and corresponding reference point network and monitoring point configuration information are obtained; In each data collection cycle of the horizontal displacement monitoring project, the current coordinates of each working base point are calculated using an independent coordinate system and polar coordinate method, and the current coordinates of all working base points are grouped to form a translation working base point observation network of the current data collection cycle, and the stability of each working base point is checked based on the translation working base point observation network combined with a preset stability check observation method to obtain a working base point stability judgment result; When the working base point stability judgment result of the working base point meets the preset stability condition, performing a data acquisition operation through a preset data sensing device; Based on the current construction period of the target monitoring foundation pit, the preset benchmark point network resurvey period and the preset group observation method, the monitoring point configuration information of the benchmark point network is resurveyed to obtain the benchmark point network resurvey result, and the benchmark point network and the corresponding monitoring point configuration information are updated based on the benchmark point network resurvey result.
3. A method for monitoring foundation pit settlement based on numerical analysis according to claim 2, It is characterized in that When the working base point stability judgment result of the working base point meets the preset stability condition, after the data acquisition operation is performed by the preset data sensing device, it includes: Based on the preset positioning position of the data sensing device and the sight distance length and ranging angle of the currently observed horizontal displacement monitoring point, the sight distance mean error data and the angle measurement mean error data of the monitoring data of the currently observed horizontal position monitoring point are correspondingly obtained, and the point position mean error data is calculated based on the sight distance mean error data; Based on the mean error data of multiple points of the currently observed horizontal displacement monitoring point in the same data collection period, the mean error of the horizontal displacement value of the currently observed horizontal displacement monitoring point is calculated; and the mean error of the horizontal displacement value is compared with a preset translation monitoring accuracy threshold; If the error in the horizontal displacement value is within a preset translation monitoring accuracy threshold, the currently observed monitoring data is stored in a corresponding monitoring data set through a preset data sensing device.
4. A method for monitoring foundation pit settlement based on numerical analysis according to claim 1, It is characterized in that The monitoring project includes a support shaft force monitoring project, and the preset data collection and monitoring strategy of the support shaft force monitoring project includes: According to the foundation pit plan of the target monitoring foundation pit and the corresponding geological data, a plurality of support axial force monitoring points are buried in the concrete support assembly of the target monitoring foundation pit, each support axial force monitoring point is provided with a frequency sensing module for detecting the sensing frequency of the concrete support assembly and a stress sensing module for detecting the support stress of the concrete support assembly, and corresponding monitoring point configuration information of the support axial force monitoring point is obtained; In each data collection cycle of the support axial force monitoring project, the frequency sensing data of the concrete support assembly is continuously obtained through the frequency sensing module and the preset frequency collection times, and the corresponding frequency sensing mean is obtained; the frequency sensing mean is compared with the preset frequency threshold; When the frequency sensing mean is at a preset frequency threshold, the support stress of the concrete support component of the currently observed support axial force monitoring point is detected by a stress sensing module to obtain support stress data; The reinforced concrete support axial force of the concrete support component at the currently observed support axial force monitoring point is calculated based on a preset support axial force calculation method, the monitoring point configuration information, the component attribute data of the concrete support component and the corresponding support stress data.
5. A method for monitoring foundation pit settlement based on numerical analysis according to claim 4, It is characterized in that The frequency sensing module includes a frequency meter, and the stress sensing module includes a steel bar stress meter; when the currently observed support axial force monitoring point is in the first monitoring state; the support axial force calculation method is shown in formulas (1) and (2): Among them, N i is the axial force value calculated by a single steel bar stress gauge, K is the sensor sensitivity coefficient, and f i is the actual frequency measured by the sensor, f 0 is the initial frequency of the sensor, A s is the cross-sectional area of the steel bar, A is the cross-sectional area of the concrete support beam, E c is the elastic modulus of concrete, E s is the elastic modulus of the steel bar, N is the axial force of the reinforced concrete support, and n is the number of steel bar stress gauges in a single reinforced concrete support.
6. A method for monitoring foundation pit settlement based on numerical analysis according to claim 5, It is characterized in that When the currently observed support axial force monitoring point is in the second monitoring state, the support axial force calculation method is as shown in formula (3): N=((A0-AS)Eh*Pg) / Ag*Eg+AS*Pg / Ag (3) Among them, A0 is the cross-sectional area of the supporting beam, AS is the cross-sectional area of the longitudinal main reinforcement, Eh is the elastic modulus of concrete, Pg is the average pressure of the steel bar stress gauge, Ag is the cross-sectional area of the steel bar stress gauge, and Eg is the elastic modulus of the steel bar.
7. A method for monitoring foundation pit settlement based on numerical analysis according to claim 6, It is characterized in that The monitoring project includes a retaining structure deformation monitoring project, and the preset data collection and monitoring strategy of the retaining structure deformation monitoring project includes: burying a plurality of structural deformation monitoring points in the target monitoring pit according to the pit plan of the target monitoring pit, collecting deformation monitoring data at regular intervals through the plurality of structural deformation monitoring points and inputting the corresponding monitoring data sets; calculating deformation monitoring mean data and deformation error data based on the monitoring data sets of the retaining structure deformation monitoring project; If the deformation error data is not greater than the preset deformation error threshold, the deformation monitoring mean data is reported to the monitoring user terminal; if the deformation error data is greater than the preset deformation error threshold, additional deformation monitoring data is collected; the added deformation monitoring data is judged and filtered using a gross error criterion; if the added deformation monitoring data is judged to be gross error data, the added deformation monitoring data is deleted from the corresponding monitoring data set; if the deformation monitoring data in the monitoring data set after deletion is less than the preset quantity threshold, the deformation monitoring data collection continues to be increased.
8. A method for monitoring foundation pit settlement based on numerical analysis according to claim 7, It is characterized in that If the amount of deformation monitoring data in the deleted monitoring data set is less than a preset quantity threshold, then the deformation monitoring data is continuously collected, and the method further includes: Recalculate the deformation error data. If the recalculated deformation error data is not greater than the deformation error threshold, report the deformation monitoring mean data to the monitoring user terminal. If the recalculated deformation error data is still greater than the deformation error threshold, use a preset trend mutation monitoring method to analyze the change trend of the deformation monitoring data of the monitoring data set. If there is a change trend, increase the collection of deformation monitoring data. If there is no change trend, perform data conversion on the measurement data through the normality conversion method to obtain a change trend judgment result.
9. A foundation pit settlement monitoring system based on numerical analysis, It is characterized in that A method for monitoring foundation pit settlement based on numerical analysis as described in any one of claims 1 to 8, the system comprising: A foundation pit settlement monitoring strategy and data sensing module is used to set a plurality of monitoring items in a target monitoring foundation pit, and the plurality of monitoring items perform data collection and data transmission operations based on a preset data collection monitoring strategy and data transmission cycle; A data threshold interval judgment module is used to perform data preprocessing on the monitoring data and obtain the corresponding data threshold interval according to the acquired configuration information of several monitoring points of the monitoring project, the corresponding monitoring data and the monitoring point data identifier in a preset early warning monitoring judgment model, and judge whether the preprocessed monitoring data is within the corresponding data threshold interval; An abnormal data prompt module is used to generate abnormal data prompt information and data acquisition instructions to a preset monitoring user terminal based on the corresponding monitoring point data identifier when a certain pre-processed monitoring data is not within the corresponding data threshold interval; A monitoring point information and data threshold updating module, configured to, when receiving a monitoring point data modification instruction corresponding to a monitoring point data identifier from a monitoring user terminal, obtain corresponding monitoring point configuration change information and data threshold change information; update the corresponding monitoring point configuration information based on the monitoring point configuration change information, and update the corresponding data threshold interval based on the data threshold change information; The settlement judgment result acquisition module is used to obtain the foundation pit settlement judgment result of the target monitoring foundation pit by combining the monitoring data sets of the plurality of monitoring items when a foundation pit settlement monitoring instruction is identified.
Citation Information
Patent Citations
Dynamic monitoring system and method for unwatering process of super-large deep foundation pit
CN113756318A
Open excavation construction monitoring method for tunnel passing through underground track and adjacent to surrounding building
CN115478567A
High-precision laser inclination angle integrated measurement method and system
CN116295266A
Cited By
Method and system for transmitting marine ecological environment automatic monitoring data
CN119583395A
Deformation monitoring data analysis system based on standard value and actual value double control
CN121561542A
A deformation monitoring data analysis system based on specification value and actual value double control
CN121561542B
Deep foundation pit construction settlement control method and device
CN121613778A