Near-electricity simulation method and system based on three-dimensional model analysis

Through the near-electrical simulation method based on three-dimensional model analysis, the traditional near-electrical sensing system's lack of dependence on operators and handling emergencies is solved, and high-precision near-electrical operation distance and collision risk assessment is achieved, and construction safety is improved and operation and maintenance security.

CN118981960APending Publication Date: 2024-11-19国网河南省电力公司建设分公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411081446.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

Traditional near-inductance systems have high dependence on operators, poor timeliness for handling emergencies, low intelligence in data processing and analysis, lack predictive and preventiveness, and cannot effectively apply historical and real-time data for trend prediction.

Method used

Using near-electric simulation method based on three-dimensional model analysis, the three-dimensional model of the substation is constructed through data acquisition and image acquisition, simulation analysis and collision evaluation are carried out, and model parameters are optimized using deep learning to achieve high-precision assessment of near-electric operation distance and collision risk. .

Benefits of technology

It improves construction safety, reduces delays caused by insufficient safety distance, enhances the safety of construction and operation and maintenance, is predictive and preventive, and avoids potential safety risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118981960A_ABST
    Figure CN118981960A_ABST
Patent Text Reader

Abstract

The invention provides an electric power engineering cost data management method and system, and the method comprises the steps: carrying out the data optimization of cost data in a cost database, obtaining optimized data, and carrying out the business abstraction and business modeling analysis based on the optimized data, performing entity definition, relationship definition and attribute definition analysis on a cost data model of the cost database according to the analysis result to obtain the analysis result; constructing a statistical rule according to different cost indexes in different cost systems, extracting a data source from cost data in the cost database, realizing business index analysis of the cost data through combined extraction, and constructing a data extraction rule according to an analysis result and the statistical rule; basic parameter indexes of cost analysis are processed based on the template data, and a general scheme library and a module database are constructed based on a processing result and historical engineering data; and performing project cost analysis on the to-be-processed data according to the to-be-processed data, the data extraction rule and the analysis result to form a cost analysis table.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of data processing technology, and in particular to a near-electrical simulation method and system based on three-dimensional model analysis. Background Art

[0002] With the rapid development of science and technology and the improvement of people's living standards, the number of power construction is gradually increasing, and solving the operation of near-electrical mechanical equipment is of utmost importance.

[0003] The traditional substation solutions for near-electrical mechanical equipment operations mainly include the following aspects: 1. Manual control: During the operation process, special personnel are arranged to conduct on-site monitoring in the process of near-electricity work, timely discover potential safety hazards, and take corresponding measures. At the same time, the operator needs to have certain professional skills and experience to ensure the safety of the operation.

[0004] 2. Sensor detection: Equip live devices in the substation with near-live sensors for real-time data monitoring and response. Safety personnel and other technical personnel observe equipment data and professionals use experience to assist in judgment to ensure the safety of near-live operations.

[0005] However, the traditional substation method for solving the problem of near-electric mechanical equipment operation has the following problems: 1. Dependence on operators: Traditional near-electric sensing systems are highly dependent on operators, requiring operators to have high professional skills and experience. Due to the dependence on operators, there may be certain unreliability in the actual operation process.

[0006] 2. Unable to handle emergencies in a timely manner: Traditional near-field sensing systems rely on a single sensor to monitor and respond to real-time data. However, when encountering emergencies, the limitations of this approach are obvious. Due to the timeliness of real-time data monitoring and response, the system may not be able to take effective response measures in a timely manner when handling emergencies.

[0007] 3. Low intelligence in data processing and analysis: Traditional near-electric sensing systems need to process a large amount of high-frequency real-time data and are unable to conduct comprehensive trend forecasting and evaluation for historical and real-time data. For substations that use such near-electric sensor equipment, effective data cannot be used in a more valuable way.

[0008] 4. Lack of predictability and prevention: Preventing risks before they occur is safer and more competitive than stopping construction after discovering them during the process. Traditional near-electric sensing systems mainly rely on real-time data monitoring and response, but lack predictability and prevention in terms of pre-emptive near-electric construction operation simulation. Summary of the invention

[0009] The embodiments of the present application provide a near-electrical simulation method and system based on three-dimensional model analysis to at least address the deficiencies in the above-mentioned related technologies.

[0010] In a first aspect, an embodiment of the present application provides a near-electrical simulation method based on three-dimensional model analysis, comprising the following steps: Step 1: collect data from the substation using data acquisition equipment, and construct a point cloud three-dimensional model of the substation based on the data acquisition results and the design data of the substation; Step 2: performing model cutting on the point cloud three-dimensional model to obtain an independent device model of each device in the substation; Step 3: collecting data of the substation based on an image acquisition device, and constructing a three-dimensional model of the substation based on the data acquisition result, and performing simulation analysis on the three-dimensional model and each of the independent device models to obtain corresponding simulation analysis results; Step 4: Collect scenario data of several near-electrical operation scenarios, and construct equipment attributes and near-electrical parameters of the substation according to the scenario data, and assign attributes and set near-electrical parameters to the simulation analysis results according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data; Step 5: Perform near-electric collision analysis on the simulation optimization data to output a corresponding near-electric collision analysis report, and implement near-electric mechanical equipment operation based on the near-electric collision analysis report.

[0011] Furthermore, the step 1 includes: Using a plurality of laser sensors to emit laser beams in a predetermined direction toward all internal devices of the substation, and receiving corresponding reflected signals to obtain three-dimensional coordinate information of each of the internal devices; The design data of the substation is acquired, and data processing and data combination are performed according to the design data and the three-dimensional coordinate information to obtain point cloud three-dimensional data of the substation.

[0012] Furthermore, the step three includes: Capturing images of the substation based on an image acquisition device to obtain detailed data of the interior and surrounding environment of the substation; An image processing algorithm is used to perform image processing on detailed data of the interior and surrounding environment of the substation, and information is extracted based on the image processing result to generate a vector network model with coordinate information.

[0013] Furthermore, the step three also includes: Performing simulation analysis on the three-dimensional model and each of the independent equipment models to simulate the posture and position of the construction equipment of the substation in actual operation; Acquire the three-dimensional position information of the high-voltage equipment of the substation in real time, and evaluate the proximity operation distance between the construction equipment and the high-voltage equipment through spatial coordinate conversion and distance calculation; The edge volumes of the construction equipment and the high-voltage equipment are determined based on the three-dimensional model and each of the independent equipment models, and the accuracy of the edge volumes is trained using a deep learning algorithm to optimize the model parameters of the three-dimensional model and each of the independent equipment models.

[0014] Furthermore, the step 4 includes: Collecting scene data of several near-electricity operation scenes, and integrating equipment parameters of various construction equipment of the substation based on the scene data; The equipment attributes and near-electrical parameters of each of the construction equipment are constructed according to the equipment parameters, and the attributes of the simulation analysis results are assigned and the near-electrical parameters are set according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data.

[0015] In a second aspect, an embodiment of the present application provides a near-electrical simulation system based on three-dimensional model analysis, including: A model building module, used to collect data from the substation using a data acquisition device, and to build a point cloud three-dimensional model of the substation according to the data acquisition results and the design data of the substation; A model cutting module, used for cutting the point cloud three-dimensional model to obtain an independent device model of each device in the substation; A simulation analysis module, used to collect data on the substation based on an image acquisition device, and to construct a three-dimensional model of the substation based on the data acquisition result, and to perform simulation analysis on the three-dimensional model and each of the independent device models to obtain corresponding simulation analysis results; A data optimization module, used to collect scenario data of several near-electrical operation scenarios, and construct equipment attributes and near-electrical parameters of the substation according to the scenario data, and perform attribute assignment and near-electrical parameter setting on the simulation analysis results according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data; The collision analysis module is used to perform near-electric collision analysis on the simulation optimization data to output a corresponding near-electric collision analysis report, and implement near-electric mechanical equipment operation based on the near-electric collision analysis report.

[0016] Furthermore, the model building module includes: An information acquisition unit, used to emit laser beams toward all internal devices of the substation along a predetermined direction through a plurality of laser sensors, and receive corresponding reflected signals to acquire three-dimensional coordinate information of each of the internal devices; The data processing unit is used to obtain the design data of the substation, and perform data processing and data combination according to the design data and the three-dimensional coordinate information to obtain the point cloud three-dimensional data of the substation.

[0017] Furthermore, the simulation analysis module includes: An image acquisition unit, used to acquire images of the substation based on an image acquisition device to obtain detailed data of the interior and surrounding environment of the substation; The image processing unit is used to perform image processing on detailed data of the interior and surrounding environment of the substation using an image processing algorithm, and extract information based on the image processing result to generate a vector network model with coordinate information.

[0018] Furthermore, the simulation analysis module also includes: A simulation analysis unit, used for performing simulation analysis on the three-dimensional model and each of the independent equipment models to simulate the posture and position of the construction equipment of the substation in actual operation; A distance calculation unit, used to obtain the three-dimensional position information of the high-voltage equipment of the substation in real time, and evaluate the close-electricity operation distance between the construction equipment and the high-voltage equipment through spatial coordinate conversion and distance calculation; A deep learning unit is used to determine the edge volume of the construction equipment and the high-voltage equipment based on the three-dimensional model and each of the independent equipment models, and to train the accuracy of the edge volume using a deep learning algorithm to optimize the model parameters of the three-dimensional model and each of the independent equipment models.

[0019] Furthermore, the data optimization module includes: A data acquisition unit, used to collect scene data of several near-electricity operation scenes, and integrate equipment parameters of various construction equipment of the substation based on the scene data; The data optimization unit is used to construct the equipment properties and near-electrical parameters of each of the construction equipment according to the equipment parameters, and to assign properties and set near-electrical parameters to the simulation analysis results according to the equipment properties and the near-electrical parameters to obtain corresponding simulation optimization data.

[0020] Compared with the related art, the embodiment of the present application provides a near-electrical simulation method and system based on three-dimensional model analysis, which utilizes the data collection results of the substation and the design data of the substation to construct a point cloud three-dimensional model of the substation, and cuts the unstructured point cloud three-dimensional model into a structured independent equipment model, so that the simulation analysis is efficient, intelligent and structured; the model is optimized using the data collected by the image acquisition device to improve the accuracy of the edge volume assessment, and the model parameters are adjusted through actual measurement values ​​and calculated values ​​to achieve higher-precision near-electrical operation distance and collision risk assessment, thereby improving construction safety, reducing construction delays caused by insufficient safety distance, and improving efficiency; collision analysis is performed on the simulation optimization data, and the operation of near-electrical mechanical equipment is realized according to the collision analysis report, which is predictive and preventive for near-electrical operations, avoids potential safety risks, reduces the occurrence of accidents, and improves the safety of construction and operation and maintenance.

[0021] Details of one or more embodiments of the present application are set forth in the following drawings and description to make other features, objects, and advantages of the present application more readily apparent. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings: Figure 1 It is a flow chart of the power engineering cost data management method in the first embodiment of the present invention; Figure 2 for Figure 1 Detailed flow chart of step S101; Figure 3 for Figure 1 Detailed flow chart of step S103; Figure 4 for Figure 1 Detailed flow chart of step S104; Figure 5 It is a structural block diagram of a near-electrical simulation system based on three-dimensional model analysis in the second embodiment of the present invention.

[0023] The following specific implementation manner will further illustrate the present invention in conjunction with the above-mentioned drawings. DETAILED DESCRIPTION

[0024] In order to make the purpose, technical solutions and advantages of the present application clearer, the present application is described and illustrated below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not intended to limit the present application. Based on the embodiments provided in the present application, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present application.

[0025] Obviously, the drawings described below are only some examples or embodiments of the present application. For ordinary technicians in this field, the present application can also be applied to other similar scenarios based on these drawings without creative work. In addition, it can also be understood that although the efforts made in this development process may be complicated and lengthy, for ordinary technicians in this field related to the content disclosed in this application, some changes in design, manufacturing or production based on the technical content disclosed in this application are just conventional technical means, and should not be understood as insufficient content disclosed in this application.

[0026] Reference to "embodiments" in this application means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those of ordinary skill in the art that the embodiments described in this application may be combined with other embodiments without conflict.

[0027] Unless otherwise defined, the technical terms or scientific terms involved in this application should be understood by people with ordinary skills in the technical field to which this application belongs. The words "one", "a", "a", "the" and the like involved in this application do not indicate a quantitative limitation and may represent the singular or plural. The terms "include", "comprise", "have" and any of their variations involved in this application are intended to cover non-exclusive inclusions; for example, a process, method, system, product or device that includes a series of steps or modules (units) is not limited to the listed steps or units, but may also include steps or units that are not listed, or may also include other steps or units inherent to these processes, methods, products or devices. The words "connect", "connected", "coupled" and the like involved in this application are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. Embodiment 1

[0028] See also Figure 1, which shows a near-electrical simulation method based on three-dimensional model analysis in a first embodiment of the present invention, the method specifically includes steps S101 to S105: S101, collecting data from the substation using a data collection device, and constructing a point cloud three-dimensional model of the substation according to the data collection results and the design data of the substation; For further information, see Figure 2 , the step S101 specifically includes steps S1011~S1012: S1011, emitting laser beams toward all internal devices of the substation along a predetermined direction by using a plurality of laser sensors, and receiving corresponding reflected signals to obtain three-dimensional coordinate information of each of the internal devices; S1012, acquiring design data of the substation, and performing data processing and data combination according to the design data and the three-dimensional coordinate information to obtain point cloud three-dimensional data of the substation.

[0029] In specific implementation, laser sensors are used to accurately obtain the spatial position and shape of the equipment inside the substation. By emitting a laser beam and receiving its reflected signal, the distance from the laser beam to the target object is measured. In the substation, multiple laser sensors can scan the equipment from different angles and positions to obtain the three-dimensional coordinate information of the equipment surface. The three-dimensional coordinate information is processed and combined to form a point cloud three-dimensional model of the substation; Specifically, according to the substation design drawings provided by the construction unit and the design unit, the internal model structure and correction details are improved and refined based on the point cloud scanning of the overall three-dimensional model to achieve the purpose of modeling and high simulation of the real scene.

[0030] S102, performing model cutting on the point cloud three-dimensional model to obtain an independent device model of each device in the substation; S103, collecting data on the substation based on an image acquisition device, and constructing a three-dimensional model of the substation based on the data acquisition result, and performing simulation analysis on the three-dimensional model and each of the independent device models to obtain corresponding simulation analysis results; For further information, see Figure 3 , the step S103 specifically includes steps S1031~S1032: S1031, performing image acquisition on the substation based on an image acquisition device to obtain detailed data of the interior and surrounding environment of the substation; S1032: Perform image processing on detailed data of the interior and surrounding environment of the substation using an image processing algorithm, and extract information based on the image processing result to generate a vector network model with coordinate information.

[0031] In the specific implementation, panoramic cameras are used to collect data on the substation, where the collected image data contains detailed information about the substation's interior and surrounding environment, including the visual appearance of the equipment, surrounding buildings, vegetation and other objects; through image processing algorithms, useful information is extracted from these images to generate a vector grid model with coordinate information. This model not only contains the visual features of the environment, but can also be superimposed with the point cloud structure to form a more complete and accurate three-dimensional model of the substation.

[0032] In some optional embodiments, the step S103 further includes steps S1131 to S1133: S1131, performing simulation analysis on the three-dimensional model and each of the independent equipment models to simulate the posture and position of the construction equipment of the substation in actual operation; S1132, acquiring the three-dimensional position information of the high-voltage equipment of the substation in real time, and evaluating the proximity operation distance between the construction equipment and the high-voltage equipment through spatial coordinate conversion and distance calculation; S1133, determining the edge volume of the construction equipment and the high-voltage equipment according to the three-dimensional model and each of the independent equipment models, and using a deep learning algorithm to train the accuracy of the edge volume to optimize the model parameters of the three-dimensional model and each of the independent equipment models.

[0033] In the specific implementation, after the above-mentioned three-dimensional model and each independent equipment model are imported into the simulation operation scene, the three-dimensional model of the construction equipment is calculated and updated in real time based on the built-in integrated three-dimensional construction equipment model to simulate the posture and position of the construction equipment in actual operation. At the same time, the three-dimensional position information of the high-voltage equipment is obtained in real time, and the near-electrical operation distance between the construction equipment and the high-voltage equipment is evaluated through spatial coordinate transformation and distance calculation. The intelligent algorithm evaluation system will judge the near-electrical operation distance according to the preset safety standards and specifications. In this embodiment, if the near-electrical operation distance is less than the safety standard requirement, a warning will be issued to record the position or posture problem of the construction equipment in this simulation.

[0034] Specifically, based on the three-dimensional models of the construction equipment and the high-voltage equipment, the critical area between them, that is, the edge volume, is determined. The edge volume is the key area where the construction equipment and the high-voltage equipment may collide or approach a safe distance. The accuracy of the edge volume is trained using a deep learning algorithm, including accurate modeling of the three-dimensional models of the construction equipment and the high-voltage equipment, and accurate calculation of the relative position relationship between them; through a large amount of training data and iterative learning, the deep learning algorithm can continuously optimize the model parameters and improve the accuracy of the edge volume assessment. During the training process, by comparing the actual measured values ​​and the calculated values, the model parameters are continuously adjusted and optimized to achieve higher accuracy. At the same time, in this embodiment, by introducing more sensor data and real-time monitoring information, the accuracy of the edge volume assessment is further improved.

[0035] S104, collecting scene data of several near-electrical operation scenes, and constructing equipment attributes and near-electrical parameters of the substation according to the scene data, and assigning attributes and setting near-electrical parameters to the simulation analysis results according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data; For further information, see Figure 4 , the step S104 specifically includes steps S1041-S1042: S1041, collecting scene data of several near-electricity operation scenes, and integrating equipment parameters of various construction equipment of the substation based on the scene data; S1042, constructing equipment attributes and near-electrical parameters of each of the construction equipment according to the equipment parameters, and assigning attributes and setting near-electrical parameters to the simulation analysis results according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data.

[0036] During the specific implementation, a large number of near-electrical operation scenes are collected on site. Based on this, the three-dimensional models of various construction machinery such as cranes, overhead cranes, aerial work vehicles, etc. are integrated, and parametric modeling such as crane boom length and rotation angle is performed to optimize the simulation analysis data, maximize the simulation, and achieve a construction operation scene with no blind spots.

[0037] S105, performing near-electric collision analysis on the simulation optimization data to output a corresponding near-electric collision analysis report, and implementing near-electric mechanical equipment operation based on the near-electric collision analysis report.

[0038] During the specific implementation, according to the actual operation needs, a three-dimensional model (based on the point cloud three-dimensional model) including construction equipment, high-voltage equipment and the surrounding environment is simulated to accurately reflect the actual operation scene in the simulation environment. At the same time, the operation process is simulated, including key parameters such as the position, volume, operation content, operating parameters, actual operation trends and predicted trends of mechanical equipment. The operation parameters are input by the operator or automatically generated according to the preset operating procedures. Based on these parameters, the distance between the equipment and the high-voltage equipment during the construction process is calculated in real time, and possible collisions are predicted. After the overall operation is completed, a detailed collision analysis report will be output. This report includes the distance, relative position and posture, touch points, and possible safety risks between the construction equipment and the high-voltage equipment. Through this report, operators can understand the potential risks in the operation process and take corresponding preventive measures.

[0039] It should be noted that in this embodiment, the data of the near-electric sensing layer equipment in the substation includes positioning sensors, near-electric sensors, etc., which obtain the positioning and distance information of construction equipment (such as cranes, aerial work vehicles, etc.) in real time. Each sensor is a data node, and they transmit the real-time collected position and posture data to the edge agent device through wireless communication technology. The edge agent device is responsible for receiving, processing and synchronizing this data, and transmitting it to the system in real time to ensure the accuracy and real-time nature of the data.

[0040] Specifically, by deploying positioning and near-electric sensors in the substation, the location and posture information of the construction equipment is collected in real time, and real-time processing and analysis are performed. By using near-electric sensing algorithms and intelligent analysis of perception layer data, the near-electric operation digital simulation platform can intelligently identify and predict the behavior of construction equipment and determine whether it is close to the critical safety area of ​​high-voltage equipment. Once the construction equipment is detected to be close to the critical safety area, the near-electric behavior detection and early warning mechanism will be activated immediately. Early warning information is issued to construction and operation and maintenance personnel through sound and light alarms, mobile application push, central control room display screens, etc. The early warning information includes the distance, relative position and posture between the equipment and the high-voltage equipment, as well as possible safety risks.

[0041] In this embodiment, a data recognition and analysis algorithm is used to perform intelligent analysis and identification processing on the positioning and near-electric sensor data, taking into account the weights and credibility of different data sources, as well as the correlation between them, so as to improve the accuracy of the final analysis results; the results after intelligent analysis and processing are output to the near-electric operation digital simulation platform, and the targets in the monitoring area are monitored and warned in real time based on the fusion results, so as to achieve efficient and accurate safety management.

[0042] Furthermore, the near-electric simulation method based on three-dimensional model analysis in this embodiment is based on the existing integrated alarm mechanism on site, including on-site sound column sound alarm, SMS notification, email notification, etc., and selects appropriate alarm methods and alarm levels according to the severity and urgency of abnormal behavior. The near-electric behavior detection and early warning mechanism can also be integrated with other systems, such as interconnection with the substation monitoring system, operation and maintenance management system, etc., so that the early warning information can be more accurately transmitted to relevant personnel and guide them to take corresponding safety measures; the triggered alarm information is recorded and processed, and the substation video monitoring system is linked, including operations such as saving alarm videos and generating process disposal reports, and the alarm information is promptly fed back to relevant personnel for processing and response, to ensure timely disposal of safety incidents.

[0043] In summary, the power engineering cost data management method in the above-mentioned embodiment of the present invention utilizes the data collection results of the substation and the design data of the substation to construct a point cloud three-dimensional model of the substation, and cuts the unstructured point cloud three-dimensional model into a structured independent equipment model, so that the simulation analysis has high efficiency, intelligence and structured; the model is optimized using the data collected by the image acquisition device to improve the accuracy of the edge volume assessment, and the model parameters are adjusted through actual measurement values ​​and calculated values ​​to achieve higher-precision near-electrical working distance and collision risk assessment, thereby improving construction safety, reducing construction delays caused by insufficient safety distance, and improving efficiency; collision analysis is performed on the simulation optimization data, and the operation of near-electrical mechanical equipment is realized according to the collision analysis report, which is predictive and preventive for near-electrical operations, avoids potential safety risks, reduces the occurrence of accidents, and improves the safety of construction and operation and maintenance. Embodiment 2

[0044] On the other hand, the present invention also proposes a near-electric simulation system based on three-dimensional model analysis, see Figure 5 , shown is a near-electrical simulation system based on three-dimensional model analysis in a second embodiment of the present invention, comprising: A model building module 11 is used to collect data from the substation using a data acquisition device, and to build a point cloud three-dimensional model of the substation according to the data acquisition results and the design data of the substation; Furthermore, the model building module 11 includes: An information acquisition unit, used to emit laser beams toward all internal devices of the substation along a predetermined direction through a plurality of laser sensors, and receive corresponding reflected signals to acquire three-dimensional coordinate information of each of the internal devices; The data processing unit is used to obtain the design data of the substation, and perform data processing and data combination according to the design data and the three-dimensional coordinate information to obtain the point cloud three-dimensional data of the substation.

[0045] A model cutting module 12 is used to perform model cutting on the point cloud three-dimensional model to obtain an independent device model of each device in the substation; A simulation analysis module 13, configured to collect data on the substation based on an image acquisition device, construct a three-dimensional model of the substation based on the data acquisition result, and perform simulation analysis on the three-dimensional model and each of the independent device models to obtain corresponding simulation analysis results; Furthermore, the simulation analysis module 13 includes: An image acquisition unit, used to acquire images of the substation based on an image acquisition device to obtain detailed data of the interior and surrounding environment of the substation; The image processing unit is used to perform image processing on detailed data of the interior and surrounding environment of the substation using an image processing algorithm, and extract information based on the image processing result to generate a vector network model with coordinate information.

[0046] Furthermore, the simulation analysis module 13 also includes: A simulation analysis unit, used for performing simulation analysis on the three-dimensional model and each of the independent equipment models to simulate the posture and position of the construction equipment of the substation in actual operation; A distance calculation unit, used to obtain the three-dimensional position information of the high-voltage equipment of the substation in real time, and evaluate the close-electricity operation distance between the construction equipment and the high-voltage equipment through spatial coordinate conversion and distance calculation; A deep learning unit is used to determine the edge volume of the construction equipment and the high-voltage equipment based on the three-dimensional model and each of the independent equipment models, and to train the accuracy of the edge volume using a deep learning algorithm to optimize the model parameters of the three-dimensional model and each of the independent equipment models.

[0047] The data optimization module 14 is used to collect scenario data of several near-electrical operation scenarios, and construct equipment attributes and near-electrical parameters of the substation according to the scenario data, and perform attribute assignment and near-electrical parameter setting on the simulation analysis results according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data; Furthermore, the data optimization module 14 includes: A data acquisition unit, used to collect scene data of several near-electricity operation scenes, and integrate equipment parameters of various construction equipment of the substation based on the scene data; The data optimization unit is used to construct the equipment properties and near-electrical parameters of each of the construction equipment according to the equipment parameters, and to assign properties and set near-electrical parameters to the simulation analysis results according to the equipment properties and the near-electrical parameters to obtain corresponding simulation optimization data.

[0048] The collision analysis module 15 is used to perform near-electric collision analysis on the simulation optimization data to output a corresponding near-electric collision analysis report, and implement near-electric mechanical equipment operation based on the near-electric collision analysis report.

[0049] The functions or operation steps implemented when the above modules are executed are substantially the same as those in the above method embodiments, and will not be repeated here.

[0050] An embodiment of the present invention provides a near-electric simulation system based on three-dimensional model analysis, and its implementation principle and technical effects are the same as those of the aforementioned method embodiment. For the sake of brief description, for matters not mentioned in the system embodiment, reference can be made to the corresponding contents in the aforementioned method embodiment.

[0051] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0052] The above-mentioned embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent of the present application shall be subject to the attached claims.

Claims

1. A near-electric simulation method based on three-dimensional model analysis, characterized in that: The following steps are involved: Step 1: collect data from the substation using data acquisition equipment, and construct a point cloud three-dimensional model of the substation based on the data acquisition results and the design data of the substation; Step 2: performing model cutting on the point cloud three-dimensional model to obtain an independent device model of each device in the substation; Step 3: collecting data of the substation based on an image acquisition device, and constructing a three-dimensional model of the substation based on the data acquisition result, and performing simulation analysis on the three-dimensional model and each of the independent device models to obtain corresponding simulation analysis results; Step 4: Collect scenario data of several near-electrical operation scenarios, and construct equipment attributes and near-electrical parameters of the substation according to the scenario data, and assign attributes and set near-electrical parameters to the simulation analysis results according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data; Step 5: Perform near-electric collision analysis on the simulation optimization data to output a corresponding near-electric collision analysis report, and implement near-electric mechanical equipment operation based on the near-electric collision analysis report.

2. The method for managing power engineering cost data according to claim 1, characterized in that: The step one comprises: Using a plurality of laser sensors to emit laser beams in a predetermined direction toward all internal devices of the substation, and receiving corresponding reflected signals to obtain three-dimensional coordinate information of each of the internal devices; The design data of the substation is acquired, and data processing and data combination are performed according to the design data and the three-dimensional coordinate information to obtain point cloud three-dimensional data of the substation.

3. The method for managing power engineering cost data according to claim 1, characterized in that: The step three comprises: Capturing images of the substation based on an image acquisition device to obtain detailed data of the interior and surrounding environment of the substation; An image processing algorithm is used to perform image processing on detailed data of the interior and surrounding environment of the substation, and information is extracted based on the image processing result to generate a vector network model with coordinate information.

4. The method for managing power engineering cost data according to claim 3, characterized in that: The step three also includes: Performing simulation analysis on the three-dimensional model and each of the independent equipment models to simulate the posture and position of the construction equipment of the substation in actual operation; Acquire the three-dimensional position information of the high-voltage equipment of the substation in real time, and evaluate the proximity operation distance between the construction equipment and the high-voltage equipment through spatial coordinate conversion and distance calculation; The edge volumes of the construction equipment and the high-voltage equipment are determined based on the three-dimensional model and each of the independent equipment models, and the accuracy of the edge volumes is trained using a deep learning algorithm to optimize the model parameters of the three-dimensional model and each of the independent equipment models.

5. The method for managing electric power engineering cost data according to claim 1, characterized in that: The fourth step comprises: Collecting scene data of several near-electricity operation scenes, and integrating equipment parameters of various construction equipment of the substation based on the scene data; The equipment attributes and near-electrical parameters of each of the construction equipment are constructed according to the equipment parameters, and the attributes of the simulation analysis results are assigned and the near-electrical parameters are set according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data.

6. A near-electric simulation system based on three-dimensional model analysis, characterized in that: include: A model building module, used to collect data from the substation using a data acquisition device, and to build a point cloud three-dimensional model of the substation according to the data acquisition results and the design data of the substation; A model cutting module, used for cutting the point cloud three-dimensional model to obtain an independent device model of each device in the substation; A simulation analysis module, used to collect data on the substation based on an image acquisition device, and to construct a three-dimensional model of the substation based on the data acquisition result, and to perform simulation analysis on the three-dimensional model and each of the independent device models to obtain corresponding simulation analysis results; A data optimization module, used to collect scenario data of several near-electrical operation scenarios, and construct equipment attributes and near-electrical parameters of the substation according to the scenario data, and perform attribute assignment and near-electrical parameter setting on the simulation analysis results according to the equipment attributes and the near-electrical parameters to obtain corresponding simulation optimization data; The collision analysis module is used to perform near-electric collision analysis on the simulation optimization data to output a corresponding near-electric collision analysis report, and implement near-electric mechanical equipment operation based on the near-electric collision analysis report.

7. The power engineering cost data management system according to claim 6, characterized in that: The model building module includes: An information acquisition unit, used to emit laser beams toward all internal devices of the substation along a predetermined direction through a plurality of laser sensors, and receive corresponding reflected signals to acquire three-dimensional coordinate information of each of the internal devices; The data processing unit is used to obtain the design data of the substation, and perform data processing and data combination according to the design data and the three-dimensional coordinate information to obtain the point cloud three-dimensional data of the substation.

8. The power engineering cost data management system according to claim 6, characterized in that: The simulation analysis module includes: An image acquisition unit, used to acquire images of the substation based on an image acquisition device to obtain detailed data of the interior and surrounding environment of the substation; The image processing unit is used to perform image processing on detailed data of the interior and surrounding environment of the substation using an image processing algorithm, and extract information based on the image processing result to generate a vector network model with coordinate information.

9. The power engineering cost data management system according to claim 8, characterized in that: The simulation analysis module also includes: A simulation analysis unit, used for performing simulation analysis on the three-dimensional model and each of the independent equipment models to simulate the posture and position of the construction equipment of the substation in actual operation; A distance calculation unit, used to obtain the three-dimensional position information of the high-voltage equipment of the substation in real time, and evaluate the close-electricity operation distance between the construction equipment and the high-voltage equipment through spatial coordinate conversion and distance calculation; A deep learning unit is used to determine the edge volume of the construction equipment and the high-voltage equipment based on the three-dimensional model and each of the independent equipment models, and to train the accuracy of the edge volume using a deep learning algorithm to optimize the model parameters of the three-dimensional model and each of the independent equipment models.

10. The power engineering cost data management system according to claim 6, characterized in that: The data optimization module includes: A data acquisition unit, used to collect scene data of several near-electricity operation scenes, and integrate equipment parameters of various construction equipment of the substation based on the scene data; The data optimization unit is used to construct the equipment properties and near-electrical parameters of each of the construction equipment according to the equipment parameters, and to assign properties and set near-electrical parameters to the simulation analysis results according to the equipment properties and the near-electrical parameters to obtain corresponding simulation optimization data.