Soft soil roadbed settlement observation device and settlement observation control method

By using a combined device of retractable PVC pipe, ring sheet, grouting pipe and reflective plate on soft soil roadbed, the problems of easy damage, high cost and complex installation in the prior art are solved, and the soft Accurate monitoring and timely treatment of soil subgrade settlement are suitable for soft soil subgrades and protect the pavement structure.

CN118997097APending Publication Date: 2024-11-22CHINA FIRST METALLURGICAL GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411011282.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing soft soil subgrade settlement monitoring device is prone to damage, has high cost and is complex to install, so it cannot accurately control the sinking position and handle it in time, and is not suitable for soft soil subgrade.

Method used

Using a combination device for the scalable PVC pipe, ring sheet, grouting pipe and reflective plate patch. By pre-embedding the scalable PVC pipe and grouting pipe, the ring sheet and reflective plate patch are combined to achieve accurate observation and injection. slurry to ensure that the device sinks with the roadbed and is repaired in time.

Benefits of technology

It realizes accurate monitoring and timely treatment of soft soil roadbed settlement, reduces the complexity of device damage and installation, is suitable for soft soil roadbed, improves monitoring accuracy and cost control, and protects the pavement structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997097A_ABST
    Figure CN118997097A_ABST
Patent Text Reader

Abstract

The invention discloses a soft soil roadbed settlement observation device, which comprises a telescopic PVC pipe, which is formed by vertically assembling a plurality of pipe sections with gradually increased diameters from bottom to top, and is buried from the bottom of a roadbed to the top of a road surface; the circular ring sheets are disc-shaped and are mounted on the outer sides of the middle parts of the sections of the telescopic PVC pipes, and a plurality of buckles are arranged on the inner sides of the circular ring sheets; the grouting pipe is in a long and thin pipe shape and is installed on the periphery of the telescopic PVC pipe in parallel; the reflective sticker small plates are made of small reflective materials and are mounted on the inner walls of the tops of the sections of the telescopic PVC pipes; the problem that repairing cannot be conducted in time after sinking is found is solved. The effect of the stress surface of the telescopic PVC pipe is increased, so that the telescopic PVC pipe can better sink along with the sinking of the foundation, and the effect of timely and accurately grouting the settlement position after the settlement of the observation pipe is found is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of road construction, and in particular relates to a soft soil roadbed settlement observation device and a settlement observation control method. Background Art

[0002] Soft soil roadbed is a special type of roadbed, mainly referring to the roadbed structure located in ponds or flooded areas. The soil is loose and has poor compressibility. The roadbed soil is loose, has high water content, poor compressibility, and is prone to settlement.

[0003] There are some common shortcomings in the soft soil roadbed road settlement monitoring devices in the prior art. First, although some devices can be used for settlement observation, they are easily damaged in actual applications, such as being shoveled away by snowplows or crushed by heavy vehicles, resulting in the inability to continuously and effectively monitor. Secondly, although some devices have automatic monitoring and alarm functions and can promptly remind operators to carry out maintenance, they are expensive and the assembly process is complicated, which is not conducive to widespread application. Although some other devices can measure settlement values, they need to destroy the road surface for installation, which not only affects the normal use of the road, but may also cause damage to the road surface structure. In general, the various existing roadbed settlement observation devices cannot accurately control the specific location of the settlement, nor can they deal with the settlement parts in a timely manner, and are not suitable for soft soil roadbeds. There is still room for improvement in monitoring accuracy, cost control, installation convenience and protection of the road surface. Summary of the invention

[0004] The present invention aims to solve the problem that the prior art is difficult to accurately control the specific position of the settlement of soft soil roadbed, cannot promptly process the settlement part, and is not suitable for soft soil roadbed.

[0005] The present invention adopts the following scheme: a soft soil roadbed settlement observation device, comprising: a retractable PVC pipe, which is vertically assembled from multiple pipe sections with gradually increasing diameters from bottom to top, buried from the bottom of the roadbed to the top of the road surface, and is used to sink with the settlement of the roadbed;

[0006] The sleeve is cylindrical and installed outside the retractable PVC pipe of the pavement layer to separate the retractable PVC pipe from the water-stabilized asphalt of the pavement layer;

[0007] The circular ring piece is in the shape of a disk and is installed on the outer side of the middle part of each section of the retractable PVC pipe to increase the force-bearing area of ​​the retractable PVC pipe;

[0008] The grouting pipe is a slender tube installed in parallel around the retractable PVC pipe and is used for precise grouting after the subsidence of the roadbed is found;

[0009] The reflective sticker is a small reflective material installed on the top inner wall of each section of retractable PVC pipe to reflect light for easy measurement.

[0010] Furthermore, each section of the retractable PVC pipe is 20 to 40 cm long and buried to the bottom of the soft soil roadbed. The diameter of the pipe section at the bottom is the smallest, and the diameter of each section gradually increases upward, so that the upper pipe section can be sleeved on the outside of the lower pipe section to achieve the telescopic function.

[0011] Furthermore, a plurality of buckles are provided on the inner side of the circular ring piece, and the buckles are in the shape of elastic claws, which are used to tightly fix the circular ring piece on the outer wall of the telescopic PVC tube to ensure that the circular ring piece can move with the telescopic PVC tube; the buckles are evenly distributed along the inner circumference of the circular ring piece.

[0012] Furthermore, the distance between the central axis of the grouting pipe and the telescopic PVC pipe is 10 to 30 cm, the bottom end of the grouting pipe is flush with the bottom end of the telescopic PVC pipe, and the top end is slightly higher than the top end of the telescopic PVC pipe, which is convenient for grouting operation.

[0013] Furthermore, the inner diameter of the sleeve is larger than the maximum outer diameter of the telescopic PVC pipe, the height is equivalent to the thickness of the road surface layer, the bottom of the sleeve is flush with the top surface of the roadbed, and the top is flush with the road surface.

[0014] Furthermore, a group of the observation devices is arranged every 15 to 45 m road section, and each group of the observation devices includes a retractable PVC pipe and its matching circular ring piece, grouting pipe, sleeve and reflective sticker plate.

[0015] Furthermore, the reflective sticker plate is square with a side length of 1-4 cm, and is made of engineering plastic with high reflective performance.

[0016] Furthermore, it also includes a waterproof sealing cover for covering the top of the retractable PVC pipe and the grouting pipe during non-observation periods to prevent rainwater and debris from entering.

[0017] As another aspect of the present invention, it also relates to a settlement observation control method of a soft soil roadbed settlement observation device, comprising the following steps:

[0018] Step 1: When backfilling the bottom of the soft soil roadbed, the retractable PVC pipe and the grouting pipe are pre-buried. The retractable PVC pipe and the grouting pipe are 10-40cm apart, that is, they are rolled in a layer of 30cm according to the roadbed backfill requirements. Each section of the retractable PVC pipe is set to 20-40cm, and a circular ring is set in the middle of each section. A small reflective sticker is installed on the inner wall of the top of the retractable PVC pipe;

[0019] Step 2: As each layer of the roadbed is backfilled, the retractable PVC pipe is raised together with it until it reaches the top of the road surface and is parallel to the top of the road surface. The road surface layer is water-stabilized asphalt, that is, when the water-stabilized asphalt of the road surface layer is constructed, a sleeve is installed on the outside of the retractable PVC pipe to protect the retractable PVC pipe inside to prevent the water-stabilized asphalt of the road surface layer from fixing the retractable PVC pipe and causing the retractable PVC pipe to be unable to sink with the roadbed;

[0020] Step 3: After the installation is completed, a set of devices is formed that can accurately observe the sinking of the soft soil roadbed and accurately grout through the grouting pipe. A set is set every 15 to 45 meters to achieve point-to-point control of the surface;

[0021] Step 4: The retractable PVC pipe needs to be observed every three days. The first step is to visually observe whether the retractable PVC pipe is on the lower layer. Since the retractable PVC pipe is retractable, if the roadbed sinks, the top of the retractable PVC pipe will sink with it. The second step is to use a flashlight to illuminate the inside of the PVC pipe and a laser rangefinder to illuminate the reflective sticker on the inner wall of each section of the retractable PVC pipe to accurately observe which layer has sunk and how much it has sunk.

[0022] Step 5: If the soft soil roadbed does not settle after a period of observation, the retractable PVC pipe and grouting pipe can be restored and grouted to the top of the road surface.

[0023] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art:

[0024] (1) The soft soil roadbed settlement observation device and settlement observation control method of the present invention solves the problem of the small stress-bearing surface of the telescopic PVC pipe by installing a circular ring plate on the telescopic observation pipe to increase the stress-bearing surface of the telescopic PVC pipe, thereby achieving the effect of increasing the stress-bearing surface of the telescopic PVC pipe, so that the telescopic PVC pipe can sink better along with the sinking of the foundation.

[0025] (2) The soft soil roadbed settlement observation device and settlement observation control method of the present invention solves the problem that the circular ring piece and the telescopic observation tube cannot be tightly connected by installing a snap-fit ​​means in the circular ring piece, thereby achieving the effect that the circular ring piece and the telescopic PVC tube can be tightly connected.

[0026] (3) The soft soil roadbed settlement observation device and settlement observation control method of the present invention solves the problem of being unable to repair in time after the settlement is discovered by installing a grouting pipe around the retractable PVC pipe. After the settlement of the observation pipe is discovered, the settlement can be promptly and accurately grouted.

[0027] (4) The soft soil roadbed settlement observation device and settlement observation control method of the present invention can accurately observe which layer is sinking and how much it is sinking by installing reflective stickers on the inner wall of a retractable PVC tube and then directly illuminating the inside of the PVC tube with a flashlight and illuminating the small reflective stickers on the inner wall of each section of the retractable PVC tube with a laser rangefinder, thereby solving the problem of being unable to accurately observe the accurate data of the settlement, and achieving the effect of being able to more simply and accurately observe the specific level and size of the settlement. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 A road plan for a soft soil roadbed of a preferred embodiment of the invention;

[0029] Figure 2 A road profile of a soft soil roadbed of a preferred embodiment of the invention;

[0030] Figure 3 This is a schematic diagram of a preferred embodiment of the present invention installed in the middle of a retractable PVC pipe;

[0031] Figure 4 It is a structural schematic diagram of a circular ring sheet of a preferred embodiment of the invention;

[0032] Figure 5 This is a schematic diagram of a small reflective sticker sheet according to a preferred embodiment of the present invention;

[0033] Figure 6 This is a schematic diagram of the structure of a grouting pipe in a preferred embodiment of the present invention;

[0034] The reference numerals in the figure respectively represent: 1- casing; 2- circular ring piece; 3- retractable HPV tube; 4- grouting pipe; 41- main grouting pipe; 411- grouting outlet; 42- branch grouting pipe; 43- grouting guide pipe; 5- small reflective sticker; 6- buckle. DETAILED DESCRIPTION

[0035] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0036] Please refer to Figure 1-Figure 3 , the present invention relates to a soft soil roadbed settlement observation device, comprising: a retractable PVC pipe 3, which is vertically assembled from multiple pipe sections with gradually increasing diameters from bottom to top, buried from the bottom of the roadbed to the top of the road surface, and is used to sink with the settlement of the roadbed;

[0037] The sleeve 1 is cylindrical and installed outside the telescopic PVC pipe 3 of the pavement layer to separate the telescopic PVC pipe 3 from the water-stabilized asphalt of the pavement layer. The sleeve 1 is not needed in a pavement layer without water-stabilized asphalt or a pavement structure layer.

[0038] The circular ring piece 2 is in the shape of a disc and is installed on the outer side of the middle part of each section of the telescopic PVC pipe 3 to increase the force-bearing area of ​​the telescopic PVC pipe 3;

[0039] The grouting pipe 4 is a slender tube, which is installed in parallel around the retractable PVC pipe 3 and is used for accurate grouting after the roadbed sinking is found;

[0040] The small reflective sticker plate 5 is a small reflective material installed on the top inner wall of each section of the retractable PVC tube 3 to reflect light for easy measurement.

[0041] As a preferred solution, each section of the retractable PVC pipe 3 is 20 to 40 cm long and buried to the bottom of the soft soil roadbed. The diameter of the pipe section at the bottom is the smallest, and the diameter of each section gradually increases upward, so that the upper pipe section can be sleeved on the outside of the lower pipe section to achieve the telescopic function.

[0042] Please refer to Figure 4 As a preferred solution, a plurality of buckles 6 are provided on the inner side of the circular ring piece 2. The buckles 6 are in the shape of elastic claws and are used to tightly fix the circular ring piece 2 on the outer wall of the telescopic PVC tube 3 to ensure that the circular ring piece 2 can move with the telescopic PVC tube 3; the buckles are evenly distributed along the inner circumference of the circular ring piece 2.

[0043] As a preferred solution, the distance between the central axis of the grouting pipe 4 and the telescopic PVC pipe 3 is 10 to 30 cm, the bottom end of the grouting pipe 4 is flush with the bottom end of the telescopic PVC pipe 3, and the top end is slightly higher than the top end of the telescopic PVC pipe 3, which is convenient for grouting operation.

[0044] As a preferred solution, the inner diameter of the sleeve 1 is larger than the maximum outer diameter of the telescopic PVC pipe 3, the height is equivalent to the thickness of the road surface layer, the bottom of the sleeve 1 is flush with the top surface of the roadbed, and the top is flush with the road surface.

[0045] As a preferred solution, a group of the observation devices is set up every 15 to 45 m road section, and each group of the observation devices includes a retractable PVC pipe 3 and its matching circular ring piece 2, a grouting pipe 4, a sleeve 1 and a small reflective sticker 5.

[0046] Please refer to Figure 5 The reflective sticker plate 5 is square or rectangular with a side length of 1-4 cm, and is made of engineering plastic with high reflective performance.

[0047] Furthermore, it also includes a waterproof sealing cover for covering the top of the retractable PVC pipe 3 and the grouting pipe 4 during non-observation periods to prevent rainwater and debris from entering.

[0048] As a preferred solution, the grouting pipe 4 includes a main grouting pipe 41 and a plurality of branch grouting pipes 42 connected thereto, wherein the main grouting pipe 41 is vertically arranged along the depth direction of the roadbed, and a plurality of grouting outlets 411 are evenly arranged on its outer wall along the length direction; each of the branch grouting pipes 42 is connected to a grouting outlet 411 of the main grouting pipe 41, and extends to a specific depth layer of the roadbed; and further includes an L-shaped grouting guide pipe 43, which can slide freely in the main grouting pipe 41, and the lower end outlet of the grouting guide pipe 43 can be inserted into the grouting outlet 411, and guide the external mortar to the grouting outlet 411 corresponding to the settlement position determined according to the reflective sticker 5, and grout the settlement position through the branch grouting pipe 42 to control the settlement.

[0049] As another aspect of the present invention, it also relates to a settlement observation control method of a soft soil roadbed settlement observation device, comprising the following steps:

[0050] Step 1: When backfilling the bottom of the soft soil roadbed, the retractable PVC pipe 3 and the grouting pipe 4 are pre-buried. The retractable PVC pipe 3 and the grouting pipe 4 are 10-40 cm apart, that is, they are rolled in a layer of 30 cm according to the roadbed backfilling requirements. Each section of the retractable PVC pipe 3 is set to 20-40 cm, and a circular ring piece 2 is set in the middle of each section. A small reflective sticker 5 is installed on the top inner wall of the retractable PVC pipe 3;

[0051] Step 2: As each layer of the roadbed is backfilled, the retractable PVC pipe 3 is raised together with it until it reaches the top of the road surface and is parallel to the top of the road surface. The road surface layer is water-stabilized asphalt, that is, when the water-stabilized asphalt of the road surface layer is constructed, a sleeve is installed on the outside of the retractable PVC pipe 3 to protect the retractable PVC pipe 3 inside to prevent the water-stabilized asphalt of the road surface layer from fixing the retractable PVC pipe 3 so that the retractable PVC pipe 3 cannot sink with the roadbed;

[0052] Step 3: After the installation is completed, a set of devices is formed that can accurately observe the sinking of the soft soil roadbed and accurately grout through the grouting pipe. A set is set every 15 to 45 meters to achieve point-to-point control of the surface;

[0053] Step 4: The retractable PVC pipe 3 needs to be observed every three days. The first step is to visually observe whether the retractable PVC pipe 3 is on the lower layer. Since the retractable PVC pipe 3 is retractable, if the roadbed sinks, the top of the retractable PVC pipe 3 will sink with it. The second step is to illuminate the inside of the PVC pipe with a flashlight and cooperate with a laser rangefinder to illuminate the reflective sticker 5 on the inner wall of each section of the retractable PVC pipe 3 to observe which layer has sunk and how much it has sunk.

[0054] Step 5: If the soft soil roadbed does not settle after a period of observation, the retractable PVC pipe 3 and the grouting pipe 4 can be restored and grouted to the top of the road surface.

[0055] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A soft soil roadbed settlement observation device, characterized in that: include: The retractable PVC pipe (3) is vertically assembled from multiple pipe sections with gradually increasing diameters from bottom to top, buried from the bottom of the roadbed to the top of the road surface, and is used to sink with the settlement of the roadbed; The sleeve (1) is cylindrical and is installed outside the retractable PVC pipe (3) of the pavement layer, and is used to separate the retractable PVC pipe (3) from the water-stabilized asphalt of the pavement layer; The circular ring piece (2) is in the shape of a disk and is installed on the outer side of the middle part of each section of the telescopic PVC pipe (3) to increase the force-bearing area of ​​the telescopic PVC pipe (3); The grouting pipe (4) is a slender tube, installed in parallel around the retractable PVC pipe (3), and is used for accurate grouting after the roadbed sinking is found; The small reflective sticker plate (5) is a small reflective material installed on the top inner wall of each section of the retractable PVC pipe (3) to reflect light for easy measurement.

2. The soft soil roadbed settlement observation device according to claim 1, characterized in that: Each section of the telescopic PVC pipe (3) is 20 to 40 cm long and is buried to the bottom of the soft soil roadbed. The diameter of the pipe section at the bottom is the smallest, and the diameter of each section gradually increases upward, so that the upper pipe section can be sleeved on the outside of the lower pipe section to achieve a telescopic function.

3. The soft soil roadbed settlement observation device according to claim 1, characterized in that: A plurality of buckles (6) are provided on the inner side of the circular ring piece (2), and the buckles (6) are in the shape of elastic claws and are used to tightly fix the circular ring piece (2) on the outer wall of the telescopic PVC tube (3) to ensure that the circular ring piece (2) can move together with the telescopic PVC tube (3); the buckles are evenly distributed along the inner circumference of the circular ring piece (2).

4. The soft soil roadbed settlement observation device according to claim 1, characterized in that: The distance between the central axis of the grouting pipe (4) and the telescopic PVC pipe (3) is 10 to 30 cm. The bottom end of the grouting pipe (4) is flush with the bottom end of the telescopic PVC pipe (3), and the top end is slightly higher than the top end of the telescopic PVC pipe (3), so as to facilitate the grouting operation.

5. The soft soil roadbed settlement observation device according to claim 1, characterized in that: The inner diameter of the sleeve (1) is greater than the maximum outer diameter of the telescopic PVC pipe (3), the height is equivalent to the thickness of the road surface layer, the bottom of the sleeve (1) is flush with the top surface of the roadbed, and the top is flush with the road surface.

6. The soft soil roadbed settlement observation device according to claim 1 is characterized in that: A group of the observation devices is arranged every 15-45 m road section, and each group of the observation devices comprises a retractable PVC pipe (3) and its matching circular ring piece (2), a grouting pipe (4), a sleeve (1) and a small reflective sticker board (5).

7. The soft soil roadbed settlement observation device according to claim 1 is characterized in that: The reflective sticker plate (5) is square, with a side length of 1-4 cm, and is made of engineering plastic with high reflective performance.

8. The soft soil roadbed settlement observation device according to any one of claims 1 to 7, characterized in that: It also includes a waterproof sealing cover, which is used to cover the top of the retractable PVC pipe (3) and the grouting pipe (4) during non-observation periods to prevent rainwater and debris from entering.

9. The settlement observation control method of the soft soil roadbed settlement observation device according to any one of claims 1 to 7, characterized in that: The following steps are involved: Step 1: When backfilling the bottom of the soft soil roadbed, the retractable PVC pipe (3) and the grouting pipe (4) are pre-buried. The retractable PVC pipe (3) and the grouting pipe (4) are 10-40 cm apart, that is, they are rolled in layers of 30 cm according to the roadbed backfilling requirements. Each section of the retractable PVC pipe (3) is set to 20-40 cm, and a circular ring piece (2) is set in the middle of each section. A small reflective sticker (5) is installed on the top inner wall of the retractable PVC pipe (3); Step 2: As each layer of the roadbed is backfilled, the retractable PVC pipe (3) is raised together with it until it reaches the top of the road surface and is parallel to the top of the road surface. The road surface layer is water-stabilized asphalt. That is, when the water-stabilized asphalt of the road surface layer is constructed, a sleeve is installed on the outside of the retractable PVC pipe (3) to protect the retractable PVC pipe (3) inside, so as to prevent the water-stabilized asphalt of the road surface layer from fixing the retractable PVC pipe (3) and causing the retractable PVC pipe (3) to be unable to sink with the roadbed; Step 3: After the installation is completed, a set of devices is formed that can accurately observe the sinking of the soft soil roadbed and accurately grout through the grouting pipe. A set is set every 15 to 45 meters to achieve point-to-point control of the surface; Step 4: The telescopic PVC pipe (3) needs to be observed every three days. The first step is to visually observe whether the telescopic PVC pipe (3) is on the lower layer. Since the telescopic PVC pipe (3) is telescopic, if the roadbed sinks, the top of the telescopic PVC pipe (3) will sink with it. The second step is to illuminate the inside of the PVC pipe with a flashlight and use a laser rangefinder to illuminate the reflective sticker (5) on the inner wall of each section of the telescopic PVC pipe (3) to accurately observe which layer has sunk and how much it has sunk. Step 5: If the soft soil roadbed does not settle after a period of observation, the retractable PVC pipe (3) and the grouting pipe (4) can be restored and grouted to the top of the road surface.