Method for judging, preventing and controlling sliding of free slope body applied to well mining disturbance
Through the combination of drilling exploration and monitoring equipment, the potential sliding surface position and depth of the coal mine's air-side slope body was determined, and high-tension prestressed anchor cable reinforcement was used to solve the slope instability and slope slip caused by coal mining under coal mines. The risk of accidents has improved the pertinence of disaster management and the overall safety and stability of the slope.
Patent Information
- Application Number
- CN202411156289.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-22
AI Technical Summary
The risks of overlying slope instability and landslide accidents caused by coal mining surfaces under coal mines are difficult to accurately predict and control. It is difficult to accurately determine the deformation law and position of the internal structure of rock mass and the sliding surface, resulting in poor targeted disaster management measures. .
The rock sample is obtained through drilling exploration and analysis of the thickness and mechanical parameters of the rock formation, combined with drilling monitoring equipment to monitor the deformation of the rock mass, determine the position and depth of the potential slip surface, and use high-tension prestressed anchor cable to strengthen it to prevent slip control.
It has achieved accurate grasp of the deformation laws of the internal structure of the rock mass, accurately judged the position and depth of the sliding surface, and improved the pertinence of disaster management and the overall safety and stability of the slope.
Smart Images

Figure CN118997185A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of coal mining, and in particular relates to a method for determining and preventing the sliding of an open-air slope caused by coal mining disturbance. Background Art
[0002] Resource exploitation at the coal mining face in underground coal mines is the main cause of the instability and structural damage of the overlying slope. Rock blocks may fall off the main body of the slope on the open face, and even worse, large-scale landslides may occur, threatening the safety of surrounding buildings and personnel. The deformation and destruction of rock slopes are controlled by the rock structure. Affected by the disturbance of mining, the rock structure becomes abnormal, resulting in the destruction of the integrity of the overlying rock mass. Because the rock mass engineering on the open face of the rock slope is large, the stability of the rock slope is more dependent on the geometry, distribution and combination of the structural surfaces in the slope, which directly affects the mode, location and movement trajectory of the deformation and destruction of the rock slope. In the process of rock slope destruction and instability, due to the complexity of the internal structure of the slope and the different rock materials that make up the slope, the slope has different failure modes, which are specifically manifested in different failure surface forms. When analyzing slope stability, theoretical calculation simulation is often used to determine the damage characteristics of the overhanging slope at the project site. This method can only roughly grasp the potential disaster risk. The deformation law of the internal structure of the rock mass and the location and depth of the slip surface under actual working conditions cannot be accurately known. The resulting disaster control measures are less targeted, resulting in excessive or insufficient prevention and control. Therefore, a method for determining and preventing the slip of overhanging slopes in the area affected by underground mining disturbance is proposed. Summary of the invention
[0003] The purpose of the present invention is to provide a method for determining and preventing the sliding of an aerial slope caused by well mining disturbance. By using this method, the deformation law of the internal structure of the rock mass under actual working conditions can be mastered, the position and depth of the sliding surface can be accurately obtained, and the implementation of disaster control measures can be well guided, thereby ensuring the high efficiency of the sliding control of the aerial slope and the safety and stability of the slope as a whole.
[0004] The present invention adopts the following technical solution: A method for determining and preventing slippage of an open slope due to well mining disturbance, comprising the following steps: The first step is to fully investigate the on-site engineering geological conditions, conduct drilling exploration within the slope elevation range, take core samples of the well-drilled open slope rock samples for analysis, understand the lithology and thickness of different rock layers, and analyze the internal structural characteristics of the rock mass; The second step is to obtain the thickness and mechanical parameters of different rock layers in the slope based on the analysis of core samples taken from drilling, so as to determine the location distribution of thick and hard "rigid" key rock layers and thin and soft "flexible" key rock layers in the slope, thereby guiding the determination of the starting position of the potential slip surface; The coupling force of the overburden key layer disturbed by well mining has a great influence on the stability of the open-air slope. The thick and hard rock layer is affected by well mining, and the rock layer sinks and rotates, and at the same time produces a strong horizontal squeezing effect. The hard layer will be pushed out and drive the upper rock mass to deform, prompting each weak layer to activate, resulting in slope instability and pushing the slope to deform toward the open surface. Through the implementation of this step, the determination of the starting position of the potential slip surface is guided. The starting position of the slip surface is located in the thick and hard "rigid" key rock layer.
[0005] The third step is to construct monitoring boreholes within the coverage area of the open-air slope, install deformation monitoring equipment in the boreholes, statistically analyze the internal deformation laws of rocks at different depths of the open-air slope within a time period, and determine the location and depth of the potential sliding structural surface of the open-air slope; The fourth step is to use high-tension prestressed anchor cables to reinforce the slope facing the air according to the slip position and slip depth of the potential slip surface, through the influence of the coupling effect of the previous key layers on the slip position and the determination of the slip depth through deep hole displacement monitoring of the slope facing the air, so that the potential detached rock on the slope surface is closely combined with the internal stable rock mass to achieve an overall stabilization effect and play a role in preventing and controlling secondary disasters.
[0006] Furthermore, the drilling exploration described in the first step determines the number of drilling holes according to the slope direction and the complexity of the engineering rock mass.
[0007] Furthermore, the drilling arrangement spacing in the first step is 50-100m, and the drilling depth is determined according to the slope elevation.
[0008] Furthermore, the coring described in the first step uses a coring drill rod to obtain core samples, and the rock samples at different depths are analyzed to accurately determine the thickness, lithology and integrity of the rock strata on the engineering slope.
[0009] Furthermore, the uniaxial compressive strength of the thick and hard "rigid" key rock layer in the second step is above 30 MPa, and the uniaxial compressive strength of the thin and soft "flexible" key rock layer is less than 30 MPa.
[0010] Furthermore, the monitoring borehole construction length in the third step is 25m, the horizontal spacing of the boreholes is 50m, and the vertical distance is 20m.
[0011] Furthermore, in the fourth step, the diameter of the anchor cable is 15 mm, and a 5-anchor cable bundle structure is used, and the anchoring section of the anchor cable is located inside the slip surface.
[0012] Furthermore, the length of the anchoring section is 10m.
[0013] The beneficial effects of the present invention are as follows: The present invention provides a method for determining and preventing sliding of an open-air slope body due to well mining disturbance. The method adopts a method for drilling and exploring the internal structure of a rock mass and analyzing the coupling forces of key layers to determine the potential sliding starting position of the open-air slope body; the method adopts a deep hole multi-point displacement monitoring device installed on the slope surface to monitor the deformation of the rock mass at different depths to determine the potential sliding depth of the open-air slope body; a large-tension prestressed anchor cable construction process is preferentially adopted, and according to the determination of the position and depth of the sliding surface in the early stage, the slope surface is reinforced in the treatment area to ensure reliable effect; through the method described in the present invention, the deformation law of the internal structure of the rock mass under actual working conditions is mastered, the position and depth of the sliding surface are accurately obtained, and the implementation of disaster control measures is well guided, thereby ensuring the high efficiency of the sliding control of the open-air slope body and the safety and stability of the slope as a whole. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a schematic diagram of the arrangement of drilling exploration for the open slope; Figure 2 It is the displacement curve of different depths of the open-air slope; Figure 3 Schematic diagram of determining slip position for key layer coupling; Figure 4 This is a schematic diagram of high tension prestressed anchor cable reinforcement; Among them: 1-ground; 2-slope facing the air; 3-drilling hole; 4-coal seam; 5-soft and thin rock layer; 6-thick and hard rock layer; 7-potential slip surface; 8-slip starting position; 9-slip surface; 10-anchor cable; 11-anchor section. DETAILED DESCRIPTION
[0015] The present invention will be further described with reference to the accompanying drawings.
[0016] A method for determining and preventing slippage of an open slope due to well mining disturbance, comprising the following steps: Step 1: Based on the on-site engineering geological conditions, conduct drilling exploration at an appropriate location on the top of the slope (such as Figure 1 As shown in the figure), the number of drilling holes is determined according to the direction of the slope and the complexity of the engineering rock mass. The spacing of the drilling holes is 50-100m, and the drilling depth is determined according to the slope elevation. During the construction of the exploration hole, the core drill rod is used to obtain core samples, and the rock samples at different depths are analyzed to accurately determine the specific conditions of the rock layer thickness, lithology and integrity of the engineering slope.
[0017] Step 2. According to the stratum occurrence information obtained from the above-mentioned core drilling analysis, determine the location distribution of thick and hard "rigid" rock layers and thin and soft "flexible" rock layers. The hardness of the rock type can refer to the classification standard of rock hardness. The uniaxial compressive strength is above 30MPa for hard rock, and less than this value for soft rock. At the same time, the degree of integrity during the core sampling process in step 1 can be comprehensively considered for classification. In addition, according to the characteristics of mining and subsidence, hard rock with a thickness of more than 5m has a significant effect on rock deformation. Thick and hard rock layers are affected by well mining disturbances. The rock layers sink and rotate, and at the same time, a strong horizontal squeezing effect is generated. The hard layer will be pushed out and drive the upper rock mass to deform, prompting the activation of each weak layer, resulting in slope instability and pushing the slope to deform toward the free surface. The implementation of this step determines the starting position of the potential slip surface, such as Figure 3 shown.
[0018] Step 3: Construct monitoring boreholes within the coverage of the sky slope. According to the rock collapse step and fracture characteristics, determine the construction length of the boreholes to be 25m, the horizontal spacing of the boreholes to be 50m, and the vertical distance to be 20m. After the drilling is completed, install deformation monitoring equipment to statistically analyze the internal deformation law of rocks at different depths of the sky slope within the time period to determine the location and depth of the potential sliding structural surface of the sky slope. Through observation, the displacement of the rock mass within 6m of the slope is large (such as Figure 2 ), thereby determining the slip depth of the potential slip surface.
[0019] Step 4: Determine the sliding depth by the coupling effect of the key layers in the early stage and the deep hole displacement monitoring of the open slope surface. Use high tension prestressed anchor cables to reinforce the open slope. The anchor cable diameter is 15mm. A 5-cable bundle structure is used. The anchor section is located inside the sliding surface (such as Figure 4 As shown in the figure, to ensure reliable anchoring effect, the anchoring section length is 10m, so that the potential falling rocks on the slope are closely combined with the internal stable rock mass to achieve overall stability and play a role in disaster prevention and control.
Claims
1. A method for determining and preventing slippage of an open-air slope caused by well mining disturbance, characterized in that: The steps include: The first step is to fully investigate the on-site engineering geological conditions, conduct drilling exploration within the slope elevation range, take core samples of the well-drilled open slope rock samples for analysis, understand the lithology and thickness of different rock layers, and analyze the internal structural characteristics of the rock mass; The second step is to obtain the thickness and mechanical parameters of different rock layers in the slope based on the analysis of core samples taken from drilling, so as to determine the location distribution of thick and hard "rigid" key rock layers and thin and soft "flexible" key rock layers in the slope, thereby guiding the determination of the starting position of the potential slip surface; The third step is to construct monitoring boreholes within the coverage area of the open-air slope, install deformation monitoring equipment in the boreholes, statistically analyze the internal deformation laws of rocks at different depths of the open-air slope within a time period, and determine the location and depth of the potential sliding structural surface of the open-air slope; The fourth step is to use high-tension prestressed anchor cables to reinforce the slope facing the air according to the slip position and slip depth of the potential slip surface, through the influence of the coupling effect of the previous key layers on the slip position and the determination of the slip depth through deep hole displacement monitoring of the slope facing the air, so that the potential detached rock on the slope surface is closely combined with the internal stable rock mass to achieve an overall stabilization effect and play a role in preventing and controlling secondary disasters.
2. The method for determining and preventing slippage of an open-air slope in a well mining disturbance according to claim 1 is characterized in that: The drilling exploration described in the first step determines the number of drilling holes according to the slope direction and the complexity of the engineering rock mass.
3. The method for determining and preventing slippage of an open-air slope in a well mining disturbance according to claim 1 is characterized in that: The drilling arrangement spacing described in the first step is 50~100m, and the drilling depth is determined according to the slope elevation.
4. The method for determining and preventing the sliding of an open-air slope in a well mining disturbance according to claim 1 is characterized in that: The coring described in the first step uses a coring drill rod to obtain core samples, and analyzes rock samples at different depths to accurately determine the thickness, lithology and integrity of the rock strata on the engineering slope.
5. The method for determining and preventing slippage of an open-air slope in a well mining disturbance according to claim 1 is characterized in that: The method for determining the starting position of the potential slip surface described in the second step is as follows: the thick and hard rock layer is affected by underground mining, and the rock layer sinks and rotates, producing a strong horizontal squeezing effect at the same time. The thick and hard rock layer will be pushed out, and the upper rock mass will be deformed, prompting the activation of each weak layer, resulting in slope instability, and pushing the slope to deform toward the free surface, thereby guiding the starting position of the potential slip surface. The starting position of the slip surface is located in the thick and hard "rigid" key rock layer.
6. The method for determining and preventing slippage of an open-air slope in a well mining disturbance according to claim 1 is characterized in that: The uniaxial compressive strength of the thick and hard "rigid" key rock layer described in the second step is above 30 MPa, and the uniaxial compressive strength of the thin and soft "flexible" key rock layer is less than 30 MPa.
7. The method for determining and preventing slippage of an open-air slope in a well mining disturbance according to claim 1 is characterized in that: The monitoring borehole construction length described in the third step is 25m, the horizontal spacing of the boreholes is 50m, and the vertical distance is 20m.
8. The method for determining and preventing slippage of an open-air slope in a well mining disturbance according to claim 1 is characterized in that: In the fourth step, the diameter of the anchor cable is 15 mm, and a 5-anchor cable bundle structure is used. The anchoring section of the anchor cable is located inside the slip surface.
9. The method for determining and preventing the sliding of an open-air slope in a well mining disturbance according to claim 8 is characterized in that: The length of the anchoring section is 10m.