Ground wire management and control system and method in whole process of switching operation
By designing the ground wire control system during the reverse shutdown operation, and using automatic identification and verification technology, the problem of label identification errors and insufficient locking in the ground wire management is solved, and the safety and operation process control in the substation are improved.
Patent Information
- Application Number
- CN202411085042.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the shutdown operation in the substation, the existing ground wire management has label identification errors, lack of locking measures for storage and use, and the correlation between the shutdown operation and the ground wire control system, resulting in greater safety risks.
A grounding wire control system for the entire process of backward operation is designed, including grounding wire control box, extension block, plug hole, extension plate, moving block and magnet, and automatically control by reading the keywords in the backward operation ticket. Borrowing and returning ground wires ensures that the operator's qualifications are verified and the corresponding operations are performed on the equipment.
It effectively reduces the risk of misoperation and missing items in ground wire management, improves the safety and control of reverse switch operations, ensures the correct use and return of ground wires, and reduces safety hazards.
Smart Images

Figure CN119009758A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of switching operation, and in particular to a system and method for controlling a grounding wire during the entire switching operation process. Background Art
[0002] During the operation and maintenance of power equipment in the substation, equipment with grounding switches can directly close the grounding switches, while other maintenance equipment needs to be equipped with grounding wires. As an important device to ensure personal safety, grounding wires connect the maintenance equipment to the earth during the maintenance of substation equipment, and conduct the large current that may be sent from the incoming power side to the earth, thus ensuring the life safety of maintenance workers. At present, during the switching operation, the addition of grounding wires only relies on operators to complete the steps of wire extraction, registration, hanging, removal, registration, and return. The process is cumbersome and has the risk of missing items. It is not well controlled and associated with the switching operation ticket, and there are major safety hazards.
[0003] In summary, the existing grounding wire management in substations mainly has the following problems: 1. The existing grounding wires are only identified by pasted labels, which are easy to fall off and misidentified; 2. The existing grounding wires are generally only stored in tool boxes without any locking measures, or are locked but have no effective access and return closed-loop control measures; 3. The existing switching operation control system is not linked to the grounding wire control system. Summary of the invention
[0004] The object of the present invention is to provide a system and method for controlling grounding wires during the entire switching operation process, so as to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above object, the present invention provides the following technical solution: a grounding wire control system for the entire switching operation process, comprising:
[0006] A grounding wire control box, the surface of which is provided with an extension block, and the surface of which is provided with a plug-in hole;
[0007] An extension plate, wherein a groove is provided on the surface of the extension plate, a slide groove is provided on the inner wall of the groove, a moving block is inserted in the slide groove, a vertical rod is provided on the surface of the moving block, a second adsorption plate and a first adsorption plate are provided on the surface of the vertical rod, and an arc groove is provided on the surface of the moving block; and
[0008] The plug-in board is arranged on the surface of the extension board.
[0009] Preferably, a plug-in board is plugged into the surface of the extension plate, the plug-in board can move inside the extension plate, a spring is connected to the end of the plug-in board, the spring is located inside the extension plate, the spring has a thrust on the plug-in board, so that the plug-in board extends out of the extension plate.
[0010] Preferably, the moving block can move in the slide groove, and a spring is provided in the slide groove, one end of the spring is connected to the surface of the moving block, and the other end is connected to the inner wall of the slide groove, and the spring has a pulling force on the moving block, so that the moving block is close to the end of the slide groove.
[0011] Preferably, the moving blocks are provided with two groups, the vertical rod is located between the two groups of moving blocks, and the vertical rod can rotate in the moving blocks, a first tooth is fixed on the surface of the vertical rod, an arc-shaped groove is provided on the surface of the moving block, a second tooth is provided on the inner wall of the arc-shaped groove, the first tooth can engage with the second tooth, and the vertical rod can move in the arc-shaped groove.
[0012] Preferably, a magnet is disposed on the surface of the first adsorption plate, a magnet is disposed on the surface of the second adsorption plate, and the second adsorption plate and the first adsorption plate rotate along with the vertical rod.
[0013] Preferably, a telescopic frame is fixed at the end of the plug board, and the telescopic frame moves with the plug board. When the first adsorption plate or the second adsorption plate is adsorbed on the surface of other objects, the telescopic frame is squeezed, the plug board enters the interior of the extension plate, and the vertical rod moves in the arc groove, so that the first teeth engage with the second teeth.
[0014] Preferably, a grounding wire is plugged into the surface of the plug hole, and multiple groups of plug holes are provided, and two groups of extension blocks are provided, which are distributed at both ends of the grounding wire control box, and a screen and buttons are provided on the surface of the grounding wire control box.
[0015] A control method for a grounding wire control system used in the whole process of switching operation, comprising the following steps:
[0016] Step 1: When the substation is shut down; when the grounding wire control system reads a switching operation ticket in the pending state, it grabs keywords like "installation" and "grounding wire" in each line of text on the operation ticket one by one. If "installation" or "installation" or "installation" or "hanging" = "1" and "grounding wire" or "grounding wire" = "1" in any line of text, then the number of grounding wires to be borrowed is set to 1" and the corresponding group of grounding wires is allowed to be taken away. The number of grounding wires to be borrowed for the entire operation ticket is calculated in this way. If the grounding wire control system calculates that the number of grounding wires to be borrowed for this switching operation ticket exceeds the number of existing stored grounding wires, the grounding wire control system will feed back the information to the switching operation control device and pop up a window on the switching operation control device. When the grounding wire control system reads that the switching operation ticket is in the execution state, check For the qualifications of the operator and guardian of the operation ticket, if the grounding wire control system cannot query the corresponding operator and guardian, the personnel qualification alarm of the unit is set, the grounding wire is locked, and the grounding wire cannot be removed. When the operator executes the step of installing the grounding wire, the operator enters the current operation ticket number in the grounding wire control system, and enters the name and number of the grounding wire to be added in the switching operation control device. The grounding wire control system automatically unlocks the corresponding grounding wire, and the operator can remove the grounding wire and take it to the site for installation. When the operator has installed the grounding wire and scanned the grounding wire QR code with the switching operation control device, or manually entered the grounding wire name and number in the switching operation control device, the switching operation control device automatically checks with the grounding wire control system to confirm that the removed and installed grounding wires are the same group. Only then can the switching operation control device execute the next step of the operation ticket;
[0017] Step 2: When the substation equipment is energized; when the grounding wire control system reads a switching operation ticket that is in a pending state, grab the keywords and their name numbers in each line of text on the operation ticket one by one. If "dismantle" or "tear down" or "remove" = "1" and "grounding wire" or "ground wire" = "1" in any line of text, set the number of grounding wires to be returned to 1" and allow the corresponding group of grounding wires to be returned, record the name numbers of the grounding wires allowed to be returned, and use this method to calculate the number of grounding wires to be returned and their name numbers for the entire operation ticket. When the grounding wire control system reads that the switching operation ticket is in the execution state, check the operator and supervisor of the operation ticket. Personnel qualifications. If the grounding wire management and control system fails to query the corresponding operator and guardian, the personnel qualification alarm light of the unit is set to light up, the grounding wire storage interface is locked, and the grounding wire cannot be stored. When the operator uses the switching operation management and control equipment to scan the QR code on the grounding wire, or manually enters the grounding wire name and number in the switching operation management and control equipment, the grounding wire is removed after it is correct. When the operator returns the grounding wire, the operator enters the current operation ticket number in the grounding wire management and control system, and then enters the name and number of the grounding wire to be returned. If the name and number overlap with the grounding wire name and number recorded when the operation ticket to be executed is read before, the unit automatically unlocks the grounding wire storage interface, and the operator can put the grounding wire on to complete the return.
[0018] Compared with the prior art, the present invention has the following beneficial effects:
[0019] When the grounding wire control system proposed in the present invention reads that a certain switching operation ticket is in a waiting state, keywords such as "installation" and "grounding wire" in each line of text on the operation ticket are captured one by one. If "installation" or "installation" or "installation" or "hanging" = "1" and "grounding wire" or "grounding wire" = "1" in any line of text, the number of grounding wires to be borrowed is set to 1" and the corresponding group of grounding wires is allowed to be taken away. The number of grounding wires to be borrowed is calculated in this way for the entire operation ticket. When the grounding wire control system reads that the switching operation ticket is in the execution state, the check is performed. For the qualifications of the operator and guardian of the operation ticket, if the grounding wire management and control system fails to query the corresponding operator and guardian, the personnel qualification alarm light of the unit will be set to on, and the grounding wire storage interface will be locked, and the grounding wire cannot be stored. When the operator returns the grounding wire, the operator enters the current operation ticket number in the grounding wire management and control system, and then enters the name number of the grounding wire to be returned. If the name number overlaps with the grounding wire name number recorded when reading the operation ticket to be executed, the unit will automatically unlock the grounding wire storage interface, and the operator can put the grounding wire on to complete the return. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention.
[0021] Figure 2This is a structural schematic diagram of another viewing angle of the present invention.
[0022] Figure 3 It is a schematic diagram of the structure of the adsorption plate of the present invention.
[0023] Figure 4 for Figure 2 A schematic diagram of the enlarged structure in the middle.
[0024] Figure 5 for Figure 3 Enlarged schematic diagram of the structure at point B in the middle.
[0025] In the figure: ground wire control box 1, extension block 2, plug hole 3, extension plate 4, slot 5, telescopic frame 6, plug plate 7, moving block 8, vertical rod 9, first adsorption plate 10, second adsorption plate 11, slide groove 12, spring 13, first tooth 14, second tooth 15, arc groove 16. DETAILED DESCRIPTION
[0026] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] See also Figures 1 to 5 The present invention provides a technical solution: a grounding wire control system for the entire switching operation process, comprising:
[0028] An extension block 2 is provided on the surface of the grounding wire control box 1, and a plug hole 3 is provided on the surface of the grounding wire control box 1. A grounding wire is plugged into the surface of the plug hole 3, and multiple groups of plug holes 3 are provided. Two groups of extension blocks 2 are provided, which are distributed at both ends of the grounding wire control box 1. A screen and buttons are provided on the surface of the grounding wire control box 1;
[0029] The surface of the extension plate 4 is provided with a slot 5, the inner wall of the slot 5 is provided with a slide groove 12, a moving block 8 is plugged into the slide groove 12, a vertical rod 9 is provided on the surface of the moving block 8, a second adsorption plate 11 and a first adsorption plate 10 are provided on the surface of the vertical rod 9, an arc groove 16 is provided on the surface of the moving block 8, a plug-in board 7 is plugged into the surface of the extension plate 4, the plug-in board 7 can move inside the extension plate 4, a spring is connected to the end of the plug-in board 7, the spring is located inside the extension plate 4, the spring has a thrust on the plug-in board 7, so that the plug-in board 7 extends out of the extension plate 4, the moving block 8 can move in the slide groove 12, a spring 13 is provided in the slide groove 12, one end of the spring 13 is connected to the surface of the moving block 8 The spring 13 has a pulling force on the moving block 8, so that the moving block 8 is close to the end of the sliding groove 12. The moving block 8 is provided with two groups, and the vertical rod 9 is located between the two groups of moving blocks 8, and the vertical rod 9 can rotate in the moving block 8. The surface of the vertical rod 9 is fixed with a first tooth 14, and the surface of the moving block 8 is provided with an arc groove 16. The inner wall of the arc groove 16 is provided with a second tooth 15. The first tooth 14 can mesh with the second tooth 15, and the vertical rod 9 can move in the arc groove 16. The surface of the first adsorption plate 10 is provided with a magnet, and the surface of the second adsorption plate 11 is provided with a magnet. The second adsorption plate 11 and the first adsorption plate 10 rotate with the vertical rod 9;
[0030] The plug-in board 7 is arranged on the surface of the extension plate 4, and a telescopic frame 6 is fixed at the end of the plug-in board 7. The telescopic frame 6 moves with the plug-in board 7. When the first adsorption plate 10 or the second adsorption plate 11 is adsorbed on the surface of other objects, the telescopic frame 6 is squeezed, and the plug-in board 7 enters the interior of the extension plate 4. The vertical rod 9 moves in the arc groove 16, so that the first tooth 14 engages with the second tooth 15.
[0031] When the substation is shut down; when the grounding wire control system reads that a switching operation ticket is in a pending state, it grabs keywords like "installation" and "grounding wire" in each line of text on the operation ticket one by one. If "installation" or "installation" or "installation" or "hanging" = "1" and "grounding wire" or "ground wire" = "1" in any line of text, then the number of grounding wires to be borrowed is set to 1" and the corresponding group of grounding wires is allowed to be taken away. The number of grounding wires to be borrowed for the entire operation ticket is calculated in this way. If the grounding wire control system calculates that the number of grounding wires to be borrowed for this switching operation ticket exceeds the number of existing stored grounding wires, the grounding wire control system will feed back this information to the switching operation control device and pop up a window on the switching operation control device. When the grounding wire control system reads that the switching operation ticket is in execution, check the The qualifications of the operator and guardian in the operation ticket. If the grounding wire control system fails to find the corresponding operator and guardian, the personnel qualification alarm of the unit is set, the grounding wire is locked, and the grounding wire cannot be removed. When the operator executes the step of installing the grounding wire, the operator enters the current operation ticket number in the grounding wire control system, and enters the name and number of the grounding wire to be added in the switching operation control device. The grounding wire control system automatically unlocks the corresponding grounding wire, and the operator can remove the grounding wire and take it to the site for installation. When the operator has installed the grounding wire and scanned the grounding wire QR code with the switching operation control device, or manually entered the grounding wire name and number in the switching operation control device, the switching operation control device automatically checks with the grounding wire control system to confirm that the removed and installed grounding wires are the same group. Only then can the switching operation control device execute the next step of the operation ticket;
[0032] When the substation equipment is energized; when the grounding wire control system reads a certain switching operation ticket in the pending state, the keywords similar to "removal" and "grounding wire" and their name numbers in each line of text on the operation ticket are captured one by one. If "removal" or "removal" or "remove" = "1" and "grounding wire" or "ground wire" = "1" in any line of text, the number of grounding wires to be returned is set to 1" and the corresponding group of grounding wires is allowed to be returned, and the name numbers of the grounding wires allowed to be returned are recorded. The number of grounding wires to be returned and their name numbers are calculated in this way for the entire operation ticket. When the grounding wire control system reads that the switching operation ticket is in the execution state, the operator and guardian information of the operation ticket are checked. If the grounding wire management and control system fails to find the corresponding operator or guardian, the personnel qualification alarm light of the unit will be on, the grounding wire storage interface will be locked, and the grounding wire cannot be stored. When the operator scans the QR code on the grounding wire with the switching operation management and control device, or manually enters the grounding wire name and number in the switching operation management and control device, the grounding wire will be removed after it is correct. When the operator returns the grounding wire, the operator enters the current operation ticket number in the grounding wire management and control system, and then enters the name and number of the grounding wire to be returned. If the name and number overlap with the grounding wire name and number recorded when the operation ticket to be executed was read previously, the unit will automatically unlock the grounding wire storage interface, and the operator can put the grounding wire on to complete the return.
[0033] When the grounding wire control box (1) needs to be used, the cover plate on the surface of the telescopic frame (6) is removed, and the moving block (8) is moved out of the slide groove (12) under the pull of the spring (13). The surface of the first adsorption plate (10) is provided with a magnet, and the grounding wire control box (1) is adsorbed on a flat position. When it is necessary to adsorb on a columnar surface, the vertical rod (9) is rotated so that the magnet on the surface of the second adsorption plate (11) is adsorbed on the surface of the columnar object, and the telescopic frame (6) is squeezed, so that the plug board (7) Move to the inside of the extension plate (4), stabilize the angle of the second adsorption plate (11) or the first adsorption plate (10), and when the second adsorption plate (11) or the first adsorption plate (10) is adsorbed, the vertical rod (9) is subjected to a pulling force, so that the vertical rod (9) moves in the arc groove (16), and the first teeth (14) on the surface of the vertical rod (9) and the second teeth (15) on the surface of the arc groove (16) are meshed, so that the angle of the vertical rod (9) is fixed, and the first adsorption plate (10) and the second adsorption plate (11) are prevented from shaking.
[0034] Although the above describes the illustrative specific implementation methods of the present application so that technicians in this technical field can understand the present application, the present application is not limited to the scope of the specific implementation methods. For ordinary technicians in this technical field, as long as various changes are within the spirit and scope of the present application defined and determined by the attached claims, all application creations using the concept of the present application are protected.
Claims
1. A grounding wire control system for the entire switching operation process, characterized in that: include: A grounding wire control box (1), wherein an extension block (2) is arranged on the surface of the grounding wire control box (1), and a plug hole (3) is arranged on the surface of the grounding wire control box (1); An extension plate (4), a groove (5) is provided on the surface of the extension plate (4), a slide groove (12) is provided on the inner wall of the groove (5), a moving block (8) is inserted into the slide groove (12), a vertical rod (9) is provided on the surface of the moving block (8), a second adsorption plate (11) and a first adsorption plate (10) are provided on the surface of the vertical rod (9), and an arc groove (16) is provided on the surface of the moving block (8); and The plug-in board (7) is arranged on the surface of the extension board (4).
2. A grounding wire control system for the entire switching operation process according to claim 1, characterized in that: A plug-in board (7) is plugged into the surface of the extension plate (4), and the plug-in board (7) can move inside the extension plate (4). A spring is connected to the end of the plug-in board (7), and the spring is located inside the extension plate (4). The spring has a thrust on the plug-in board (7), so that the plug-in board (7) extends out of the extension plate (4).
3. A grounding wire control system for the entire switching operation process according to claim 2, characterized in that: The moving block (8) can move in the slide groove (12), and a spring (13) is arranged in the slide groove (12). One end of the spring (13) is connected to the surface of the moving block (8), and the other end is connected to the inner wall of the slide groove (12). The spring (13) has a pulling force on the moving block (8), so that the moving block (8) is close to the end of the slide groove (12).
4. A grounding wire control system for the entire switching operation process according to claim 3, characterized in that: The moving block (8) is provided with two groups, the vertical rod (9) is located between the two groups of moving blocks (8), and the vertical rod (9) can rotate in the moving block (8), a first tooth (14) is fixed on the surface of the vertical rod (9), an arc groove (16) is provided on the surface of the moving block (8), a second tooth (15) is provided on the inner wall of the arc groove (16), the first tooth (14) can mesh with the second tooth (15), and the vertical rod (9) can move in the arc groove (16).
5. A grounding wire control system for the entire switching operation process according to claim 4, characterized in that: The surface of the first adsorption plate (10) is provided with a magnet, the surface of the second adsorption plate (11) is provided with a magnet, and the second adsorption plate (11) and the first adsorption plate (10) rotate along with the vertical rod (9).
6. A grounding wire control system for the entire switching operation process according to claim 5, characterized in that: A telescopic frame (6) is fixed to the end of the plug board (7). The telescopic frame (6) moves along with the plug board (7). When the first adsorption plate (10) or the second adsorption plate (11) is adsorbed on the surface of other objects, the telescopic frame (6) is squeezed, the plug board (7) enters the interior of the extension plate (4), and the vertical rod (9) moves in the arc groove (16), so that the first teeth (14) are meshed with the second teeth (15).
7. A grounding wire control system for the entire switching operation process according to claim 6, characterized in that: A grounding wire is plugged into the surface of the plug hole (3), and the plug hole (3) is provided with multiple groups, and the extension block (2) is provided with two groups, which are distributed at both ends of the grounding wire control box (1), and the surface of the grounding wire control box (1) is provided with a screen and a button.
8. A control method used in the grounding wire control system for the whole switching operation process as claimed in any one of claims 1 to 7, characterized in that: The following steps are involved: Step 1: When the substation is shut down; when the grounding wire control system reads a switching operation ticket in the pending state, grab the keywords like "installation" and "grounding wire" in each line of text on the operation ticket one by one. If "installation" or "installation" or "installation" or "hanging" = "1" and "grounding wire" or "grounding wire" = "1" in any line of text, set the number of grounding wires to be borrowed to 1" and allow the corresponding group of grounding wires to be taken away. The number of grounding wires to be borrowed for the entire operation ticket is calculated in this way. If the grounding wire control system calculates that the number of grounding wires to be borrowed for this switching operation ticket exceeds the number of existing stored grounding wires, the grounding wire control system will feed back the information to the switching operation control device and pop up a window on the switching operation control device. When the grounding wire control system reads that the switching operation ticket is in the execution state, check For the qualifications of the operator and guardian of the operation ticket, if the grounding wire control system cannot query the corresponding operator and guardian, the personnel qualification alarm of the unit is set, the grounding wire is locked, and the grounding wire cannot be removed. When the operator executes the step of installing the grounding wire, the operator enters the current operation ticket number in the grounding wire control system, and enters the name and number of the grounding wire to be added in the switching operation control device. The grounding wire control system automatically unlocks the corresponding grounding wire, and the operator can remove the grounding wire and take it to the site for installation. When the operator has installed the grounding wire and scanned the grounding wire QR code with the switching operation control device, or manually entered the grounding wire name and number in the switching operation control device, the switching operation control device automatically checks with the grounding wire control system to confirm that the removed and installed grounding wires are the same group. Only then can the switching operation control device execute the next step of the operation ticket; Step 2: When the substation equipment is energized; when the grounding wire control system reads a switching operation ticket in the pending state, grab the keywords and their name numbers in each line of text of the operation ticket, such as "removal" and "grounding wire". If "removal" or "removal" or "remove" = "1" and "grounding wire" or "ground wire" = "1" in any line of text, set the number of grounding wires to be returned to 1" and allow the corresponding group of grounding wires to be returned, record the name numbers of the grounding wires allowed to be returned, and calculate the number of grounding wires to be returned and their name numbers in the entire operation ticket in this way. When the grounding wire control system reads that the switching operation ticket is in the execution state, check the operator and supervisor of the operation ticket. Personnel qualifications. If the grounding wire management and control system fails to query the corresponding operator and guardian, the personnel qualification alarm light of the unit is set to light up, the grounding wire storage interface is locked, and the grounding wire cannot be stored. When the operator uses the switching operation management and control equipment to scan the QR code on the grounding wire, or manually enters the grounding wire name and number in the switching operation management and control equipment, the grounding wire is removed after it is correct. When the operator returns the grounding wire, the operator enters the current operation ticket number in the grounding wire management and control system, and then enters the name and number of the grounding wire to be returned. If the name and number overlap with the grounding wire name and number recorded when the operation ticket to be executed is read before, the unit automatically unlocks the grounding wire storage interface, and the operator can put the grounding wire on to complete the return.